Field Instruction #3_003 Stantec Consulting Ltd. 600 - 4808 Ross Street Red Deer AB T4N 1X5 Tel: (403) 341-3320 Fax: (403) 342-0969
Job No.:
113928100
Total Pages:
1
Client:
SRDRWC
Date:
Nov 25, 2009
Project:
Contract 3
File:
113928100
Contractor:
Boulder Contracting Ltd
Attention:
Jon Rowley
Reference:
Directional Drill from STA 303+480 to STA 303+800.
THIS FIELD INSTRUCTION AUTHORIZES YOU TO PROCEED WITH THE WORK DESCRIBED.
IF AS A RESULT OF THIS FIELD
INSTRUCTION, AN ADJUSTMENT TO THE CONTRACT PRICE AND/OR CONTRACT SCHEDULE IS REQUIRED, A REQUEST FOR AN ADJUSTMENT IS TO BE SUBMITTED TO THE ENGINEER’S PROJECT MANAGER WITHIN
10
DAYS OF THE DATE OF THIS FIELD
INSTRUCTION.
1.0
To avoid overhead powerlines and buried power lines, directionally drill from STA 303+480 to STA 303+800.
ISSUED BY DON MUNRO, STANTEC CONSULTING LTD.
RECEIVED BY CONTRACTOR (OR REPRESENTATIVE)
c. CLIENT (John Van Doesburg, Project Manager, SRDRWC) Stantec (Tim Ainscough, Project Manger; Stephan Weninger, Project Engineer, Don Munro, Construction Manager) CONTRACTOR (Jon Rowley, Boulder Contracting Ltd.)
ar /opt/pdfcoke/conversion/tmp/scratch2/25515403.doc