FLOOR FINISHES
CEMENT AND SAND PAVING (Hand Mixed) Cement = RM16.00/ bag (50kg) Sand = RM38.00/ 1 tonne = RM38.00 X 1.44 = RM54.72/ meter cube Material Cost Cement mortar (1:3) 1 meter cube cement = 28 bag x RM16.00 3 meter cube sand = 3 meter cube x RM54.72 Add 1/3 for wastage and shrinkage Cost for 4 meter cube Cost for 1 meter cube Mortar Cost General worker = 2hour x RM60.00/8 Mortar cost 25mm thk/ meter sq. = (RM15.00+204.05) X 25 1000 Labour Cost General worker = 0.30 x RM60.00/8 Skilled worker = 0.30 x RM113.33/8 Add 10% profit & O.H
= RM448.00 = RM164.16 RM612.16 = RM204.05 = RM816.21 = RM204.05
= RM15.00 = RM5.48
= RM2.25 = RM 4.25 RM11.98 = RM1.20 RM13.18/m2
CEMENT AND SAND SCREED (to receive ceramic tiles(1:3)) Mortar Cost/ meter cube Mortar Cost 20mm thk/ meter sq. = RM204.05 x 20 1000 Labour cost Skilled worker = 0.25 x RM113.33/8 General worker = 0.25 x RM60.00/8 Add 10 % profit and O.H
= RM204.05 = RM 4.08 = RM 3.54 = RM 1.88 RM 9.50 = RM 0.95 RM10.45/m2
CEMENT AND SAND SKIRTING (1:3) Mortar cost / m3 Mortar cost 25mm thk/m2 = RM204.05 x 25 1000 25mm thk x 100mm high = RM5.10 X 100 1000 Labour cost Skilled worker = 0.38 (hour) x RM113.33/8 General worker = 0.38 (hour) x RM60.00/8 Add 10% profit and O.H
= RM204.05 = RM5.10 = RM0.51 = RM5.38 = RM2.85 RM8.74 =RM0.87 RM9.61/m2
Porcelain Tiles (0.3m x 0.3m) – HGN30773 RM3.67/piece Material cost Tile = 12 piece x RM3.67 5% wastage Cement concentrated 1m3 cement = 28 bags x RM16.00 5% wastage
= RM44.04 = RM2.20 RM46.24 =RM448.00 =RM22.40 =RM470.40
Labour cost Mixer: General worker = 2hour x RM60.00/8
=RM15.00
Cost cement concentrated/m3 0.02 m3 concentrated cement = RM470.40 x 0.02 m3
=RM9.41
Fix tile to floor: General worker = 0.75 hour x RM60.00/8 Skill worker = 0.75 hour x RM113.33/8 Add 10% profit and O.H
=RM5.63 =RM10.62 RM86.90 = RM8.69 RM95.59/m2
Porcelain Tiles (0.6m x 0.6m) – H60019 RM16.06/piece Material cost Tile = 3 piece x RM16.06 5% wastage Cement concentrated 1m3 cement = 28 bags x RM16.00 5% wastage
= RM48.18 = RM2.41 RM50.59 =RM448.00 =RM22.40 =RM470.40
Labour cost Mixer: General worker = 2hour x RM60.00/8
=RM15.00
Cost cement concentrated/m3 0.02 m3 concentrated cement = RM470.40 x 0.02 m3
=RM9.41
Fix tile to floor: General worker = 0.75 hour x RM60.00/8 Skill worker = 0.75 hour x RM113.33/8 Add 10% profit and O.H
=RM5.63 =RM10.62 RM91.25 = RM9.13 RM100.38/m2
Porcelain Tiles (0.6m x 0.6m) – H60014 RM17.67/piece Material cost Tile = 3 piece x RM17.67 5% wastage Cement concentrated 1m3 cement = 28 bags x RM16.00 5% wastage
= RM53.01 = RM2.65 RM55.66 =RM448.00 =RM22.40 =RM470.40
Labour cost Mixer: General worker = 2hour x RM60.00/8
=RM15.00
Cost cement concentrated/m3 0.02 m3 concentrated cement = RM470.40 x 0.02 m3
=RM9.41
Fix tile to floor: General worker = 0.75 hour x RM60.00/8 Skill worker = 0.75 hour x RM113.33/8 Add 10% profit and O.H
=RM5.63 =RM10.62 RM96.32 = RM9.63 RM105.95/m2
Homogeneous Tiles (0.3m x 0.3m) – H30230 RM3.71/piece Material cost Tile = 12 piece x RM3.71 5% wastage Cement concentrated 1m3 cement = 28 bags x RM16.00 5% wastage
= RM44.52 = RM2.23 RM46.75 =RM448.00 =RM22.40 =RM470.40
Labour cost Mixer: General worker = 2hour x RM60.00/8
=RM15.00
Cost cement concentrated/m3 0.02 m3 concentrated cement = RM470.40 x 0.02 m3
=RM9.41
Fix tile to floor: General worker = 0.75 hour x RM60.00/8 Skill worker = 0.75 hour x RM113.33/8 Add 10% profit and O.H
=RM5.63 =RM10.62 RM87.41 = RM8.74 RM96.15/m2
Porcelain Tiles (0.3m x 0.3m) – HIT30140 RM2.28/piece Material cost Tile = 12 piece x RM2.28 5% wastage Cement concentrated 1m3 cement = 28 bags x RM16.00 5% wastage
= RM27.36 = RM1.37 RM28.73 =RM448.00 =RM22.40 =RM470.40
Labour cost Mixer: General worker = 2hour x RM60.00/8
=RM15.00
Cost cement concentrated/m3 0.02 m3 concentrated cement = RM470.40 x 0.02 m3
=RM9.41
Fix tile to floor: General worker = 0.75 hour x RM60.00/8 Skill worker = 0.75 hour x RM113.33/8 Add 10% profit and O.H
=RM5.63 =RM10.62 RM69.39 = RM6.94 RM76.33/m2
TIMBER AND WOODWORKS Timber board cost (100mm x 25mm) = RM4.50/m Nail cost: RM4.50/kg Nail required for 1m2 of timber flooring = 0.55kg Labour output for 1m2 of timber flooring = 0.65 hour Tongue of board = 12mm Material Cost Timber (including overlapping) = 11.36m x RM4.50 Add 10% for wastage Nail = 0.55kg x RM4.50 Labour cost Carpenter = RM60.00/ 8 x 0.65 hour Add 10% profit and O.H Rate
= RM51.12 = RM5.11 = RM2.48 = RM58.71 = RM4.88 = RM6.36 RM69.95/m2