FIRST AMOUNT BLOCK LAYING & CONSTRUCTION OF THE BUILDING
1500 BLOCKS
GH¢ 1,140.00
PLAN OF THE BUILDING
GH¢
250.00
FOUNDATION
GH¢
300.00
CHIPINGS FOR CONC.
GH¢
350.00
60 BAGS OF CEMENT
GH¢
780.00
RODS FOR STARTING PILARS
GH¢
100.00
SAND
GH¢
140.00
LABOUR
GH¢
1,000.00
TOTAL
GH¢ 4,060.00
(FOR FLOOR LEVEL)
THAT IS CONPLETION OF FLOOR LEVEL
SECOND AMOUNT BLOCK LAYING AND CONSTRUCTION OF BUILDING BALANCE OF ADDITIONAL 1500 BLOCKS
GH¢
700.00
5 TRIPS OF SAND FOR BLOCK LAYING
GH¢
150.00
36 BAGS OF CEMENT
GH¢
468.00
LABOUR OF BLOCK LAYING
GH¢
150.00
WATER FOR BLOCK LAYING
GH¢
50.00
25 TRIPS OF SAND (FILLING)
GH¢
450.00
50 BAGS OF CEMENT
GH¢
650.00
5 TRIPS OF SAND FOR CONC. OF THE BUILDING GH¢
150.00
LABOUR (MASONS, LABOURERS, CARPINTERS AND WATER)
GH¢ 2,100.00
TOTAL
GH¢ 4,868.00
THAT IS AFTER FLOOR LEVEL
THIRD AMOUNT BLOCK LAYING AND CONSTRUCTION OF THE BUILDING 5 TRIPS OF SAND
GH¢ 150.00
36 BAGS OF CEMENT
GH¢ 468.00
LABOUR OF BLOCK LAYING
GH¢ 150.00
WATER FOR BLOCK LAYING
GH¢
50 BAGS OF CEMENT
GH¢ 650.00
IRON RODS FOR LINTEL
GH¢ 800.00
5 TRIPS OF SAND FOR CONC. OF BUILDING
GH¢ 150.00
CHIPINGS FOR LINTEL
GH¢ 350.00
10 PLYWOODS
GH¢
100 WAWA BOARDS
GH¢ 400.00
50.00
80.00
LABOUR (STEEL BENDERS, CARPINTERS, MASONS, LABOURS AND WATER) TOTAL
THAT IS LINTEL LEVEL
GH¢ 1,700.00 GH¢ 4,948.00
FOURTH AMOUNT COMPLETION OF BLOCK LAYING UP TO GABLE LABOUR COST (MASONS, LABOURERS, CARPINTERS, STEEL BENDERS AND WATER)
GH¢ 2,000.00
PLUMBING MATERIALS
GH¢ 1,000.00
ELECTRICAL MATERIALS
GH¢ 1,000.00
SUPERVISION COST
GH¢ 1,000.00
TOTAL
GH¢ 5,000.00
THAT IS FINISHING
FIFTH AMOUNT PROOFING OF THE BUILDING
2×6 2×4 2×3 NAILS
ALUMINIUMN ROOFING SHEETS
GH¢ 6,000.00