As per Hindrance Register Sl. No.
Nature of Hindrance
1 The work is held up due to non-availability of Structural Drawing 2 The work could not be started due to non availability of cement 3 The work is hindered due to non availability of required dia of steel in CPWD Store 4 The work is likely held up due to want of cement 5 The work is totally held up as the flood came at site. 6 The work is hindered due to non availability of required dia of steel. 7 The work is partially hampered due to Lok Sabha Election. 8 The work stopped due to assasination of contractor R. N. Sharma. 9 The work hindered and slow down due to earth approach road in raining season. The heavy loaded vehicles such as truck could not reach at site from N.H.
Period for Date of Extension of which is likely Overlapping occurance of time applied by to last (date of period if any. hindrance the contractor removal)
Net period for which extension is recommended
06.01.03
12.08.03
219 days
Nil
(Allowed 95% of 219 days) 208 days
06.02.03
15.05.03
Nil
99 days
Nil
06.02.03
08.07.03
153 days
153 days
Nil
20.07.03
08.08.03
Nil
20 days
Nil
03.08.03
10.09.03
30 days
9 days
30 days
20.12.03
10.03.04
81 days
Nil
(Allowed 97% of 81 days) 79 days
08.04.04
27.04.04
20 days
Nil
(Allowed 90% of 20 days) 18 days
14.05.04
30.09.04
140 days
Nil
140 days
04.06.04
19.08.04
Nil
77 days
Nil
Remarks
10 The work hindered and slow down due to scarcity of materials due to strike of Indian Transport. 11 The work hindered and slow down due to Bihar Election period. 12 The work is held up due to non-availability of required dia of steel. 13 The work is suffered slow down due to non availability of taking decision of Balcony Railing, Stair Railing, RCC Jali & Cup Board details. 14 The progress of work is slow down due to non decision of colour scheme of internal & exterior surface. 15 The work hindered due to non availability of required dia of steel 16 The work suffered / stopped due to Holi festival. 17 The work suffered due to heavy rain & stagnant of water in the campus. 18 The work suffered due to Durga Puja festival 19 The work suffered / hindered due to Bihar Election 20 The work hindered due ot Holi festival.
21.08.04
27.08.04
Nil
7 days
Nil
15.02.05
22.02.05
8 days
Nil
(Allowed 80% of 8 days) 6 days
15.02.05
22.03.05
28 days
8 days
(Allowed 96% of 28 days) 27 days
23.02.05
05.04.05
14 days
28 days
(Allowed 90% of 14 days) 13 days
23.02.05
30.11.05
240 days
43 days
(Allowed 58% of 240 days) 132 days
04.03.05
20.09.06
294 days
272 days
(Allowed 63% of 294 days) 187 days
22.03.05
30.03.05
Nil
9 days
Nil
18.07.05
05.08.05
Nil
19 days
Nil
09.10.05
16.10.05
Nil
8 days
Nil
15.10.05
24.11.05
Nil
40 days
Nil
13.03.06
19.03.06
Nil
6 days
Nil
Total days of hindrance - 840 days Add extra time for extra work - 172 days
Grand Total - 1012 days
Add extra time required for extra work done Gross work done amount Tendered Amount Extra work done Rs. 17,52,610/=
5581568.00 4038196.00 1543372.00
Then 12/4038196 x 1543372 x 1.25 = 5.73 months = 172 days