As per Hindrance Register Sl. No.

Nature of Hindrance

1 The work is held up due to non-availability of Structural Drawing 2 The work could not be started due to non availability of cement 3 The work is hindered due to non availability of required dia of steel in CPWD Store 4 The work is likely held up due to want of cement 5 The work is totally held up as the flood came at site. 6 The work is hindered due to non availability of required dia of steel. 7 The work is partially hampered due to Lok Sabha Election. 8 The work stopped due to assasination of contractor R. N. Sharma. 9 The work hindered and slow down due to earth approach road in raining season. The heavy loaded vehicles such as truck could not reach at site from N.H.

Period for Date of Extension of which is likely Overlapping occurance of time applied by to last (date of period if any. hindrance the contractor removal)

Net period for which extension is recommended

06.01.03

12.08.03

219 days

Nil

(Allowed 95% of 219 days) 208 days

06.02.03

15.05.03

Nil

99 days

Nil

06.02.03

08.07.03

153 days

153 days

Nil

20.07.03

08.08.03

Nil

20 days

Nil

03.08.03

10.09.03

30 days

9 days

30 days

20.12.03

10.03.04

81 days

Nil

(Allowed 97% of 81 days) 79 days

08.04.04

27.04.04

20 days

Nil

(Allowed 90% of 20 days) 18 days

14.05.04

30.09.04

140 days

Nil

140 days

04.06.04

19.08.04

Nil

77 days

Nil

Remarks

10 The work hindered and slow down due to scarcity of materials due to strike of Indian Transport. 11 The work hindered and slow down due to Bihar Election period. 12 The work is held up due to non-availability of required dia of steel. 13 The work is suffered slow down due to non availability of taking decision of Balcony Railing, Stair Railing, RCC Jali & Cup Board details. 14 The progress of work is slow down due to non decision of colour scheme of internal & exterior surface. 15 The work hindered due to non availability of required dia of steel 16 The work suffered / stopped due to Holi festival. 17 The work suffered due to heavy rain & stagnant of water in the campus. 18 The work suffered due to Durga Puja festival 19 The work suffered / hindered due to Bihar Election 20 The work hindered due ot Holi festival.

21.08.04

27.08.04

Nil

7 days

Nil

15.02.05

22.02.05

8 days

Nil

(Allowed 80% of 8 days) 6 days

15.02.05

22.03.05

28 days

8 days

(Allowed 96% of 28 days) 27 days

23.02.05

05.04.05

14 days

28 days

(Allowed 90% of 14 days) 13 days

23.02.05

30.11.05

240 days

43 days

(Allowed 58% of 240 days) 132 days

04.03.05

20.09.06

294 days

272 days

(Allowed 63% of 294 days) 187 days

22.03.05

30.03.05

Nil

9 days

Nil

18.07.05

05.08.05

Nil

19 days

Nil

09.10.05

16.10.05

Nil

8 days

Nil

15.10.05

24.11.05

Nil

40 days

Nil

13.03.06

19.03.06

Nil

6 days

Nil

Total days of hindrance - 840 days Add extra time for extra work - 172 days

Grand Total - 1012 days

Add extra time required for extra work done Gross work done amount Tendered Amount Extra work done Rs. 17,52,610/=

5581568.00 4038196.00 1543372.00

Then 12/4038196 x 1543372 x 1.25 = 5.73 months = 172 days

Related Documents

Register
December 2019 41
Register
May 2020 29
Register
October 2019 57
Register
November 2019 50
Register
May 2020 35
Register
June 2020 26

More Documents from ""