UNIVERSITY OF MALAYA
Rawang-Ipoh Double Tracking Project
Introduction Single Track Double Track
Double Electrified Track
Case study Rawang to Ipoh Electrification & Double-tracking Project Keretapi Tanah Melayu Berhad (KTMB) ►main rail operator in Peninsular Malaysia. ► ►Headquarters located in Kuala Lumpur ►consists of two main lines (West Coast line & East Coast line) and several branch lines.
Encik Suhaimi Ahmad
Overview 1700km
Route Length= Track Gauge=
1000mm
Electrified
Double Tracking
-
:Route length
150 km Seremban 105km Klang 45 km
:Rawang:Sentul-Port
Intercity services 22 Intercity and Regional services
nationwide Popular route KL – Singapore Construction of Electrified Double Track between Rawang Ipoh to link Kuala Lumpur-Ipoh Travel time between KL – Ipoh will be reduced to 2 hours 15 minutes
Commuter services services daily expansion: Tanjung Malim Service Rawang - Ipoh
>Approximate 247 Commuter trains >Future :Rawang by 2008 :Rapid Train between by 2008 :Sentul - Batu
objective to upgrade existing rail infrastructure for the increase in track capacity for commuter, intercity and freight trains.
to extend the existing commuter service from Seremban - Rawang sector to Seremban - Tg. Malim sector with an average number of service of 100 trips a day.
introduction of a rapid intercity service, between Ipoh – Sentral KL for 16 services a day and ultimately 32 services a day.
Partially completed Electrification System sub station for Rawang – Ipoh Project
Project brief & contract Integrated project System - Signaling, communication electrification, supply item
Infrastructure - station, track work, bridges, culvert, civil work
-This project use existing single track route >modify & upgrade – add 1 track beside – become doubletrack & electrification system
Project brief & contract (cont’d) Commencement Date:17 July 2000 Completion Date: 31 December 2007 Cost: original contract show 2.6 billion infrastructure work + 1.6 billion system work : UEM Construction Sdn Bhd take over – extra 766 million Total sum: 4.966 billion
Project brief & contract (cont’d) Infrastructure works originally awarded to DRB-Hicom Berhad in
2000 (35months contract )– due to delay & contractual disputes – government appointed UEM Construction Sdn Bhd from 1 June 2005 (19months contract ) System main contractor: Mitsui of Japan Sub-contractor : ♥ System : 1) Siemens-balfour Beatty Consortium ► Siemens Transportation Turnkey Systems Sdn Bhd (signalling) ► Balfour Beatty Rail Sdn Bhd (electrification) ► Siemens Malaysia Sdn Bhd (communication) ♥ Infrastructure: ► Emrail Sdn Bhd for track works ► IJM Corporation Berhad for the construction of stations ► UEM Construction Sdn Bhd for the construction of bridges ► Perspec Prime (Malaysia) Sdn Bhd for civil works
Organization Chart
General design concept Design concept:Modern Railway Concept Objective: Major components service Life 50 years Type: Flat-bottom rail Upgrade existing single track to electrified double track system – change wooden sleeper to precast concrete sleeper Design speed of track is 160km/hr, achieve full speed –2 mainline of platform (at the mainline) – straightway
General design concept (cont’d)
Have 14 stations Early day: have interlocking >> no interlocking, train need to wait station manager permission Nowadays: before train come to signal, automatic switch and detected by track circuit >> electric bond
Construction techniques overview
Machinery more than manual Using precast material Jointing – welded Concrete Sleeper- rail to fasten
Flat-bottom rail type
Project
layout
Construction Stages of Electrified Double Track Project – Civil & Track - 10 stages
STAGE 1 LEGEND CONDITION BEFORE WORK CARRIED OUT IN THIS STAGE WORK CARRIED OUT IN THE PREVIOUS STAGE
STAGE 2
STAGE 3
STAGE 5
STAGE 4
STAGE 6
STAGE 7
STAGE 9
STAGE 8
STAGE 10
TAKE OVER OF FORMATION (Part formation for one track)
BOTTOM BALLASTING
SLEEPER SLEEPER
TOP BALLAST
BOTTOM BALLAST FORMATION
Bottom ballasting by ballast box
Bottom ballast by paver
Compaction of bottom ballast
Laying of sleepers
Laying of depot welded 144M Rail Panels
LWR Train
LWR Laying
Threading of rails by wide wheel tractor
Fresh Flash Butt Weld
Insitu Flush Butt Welding
Top Ballasting prior to Tamping
Unloading of ballast hoppers at site
Loading of hopper tain in ballast depot
Track Tamping: Lifting, lining & levelling
Tamping tynes close up Compaction of top ballast by dynamic track stabiliser
Ballast regulation
Destressing and at welding
Destressing-pulling of rail by tensor
At Welding
Cut & Slew for operation
Track auditing
Completed track
Track QA/QC
During Construction
Material Testing
Finished Track
ITP of Processes & Track
Static Measurements Dynamic Measurements
THANK YOU