CLIENT : RELIANCE INDUSTRIES LTD.
EQUIPMENT DESIGN
PROJECT : IDC & UTILTIY BLCOK
ENGINEERS
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
TECHNICAL SPECIFICATIONS FOR DIESEL GENERATING SETS FOR BID ENQUIRY
REVISION NO. ISSUED FOR PREPD.BY/DATE CHKD. BY/DATE APPD. BY/ DATE
A REVIEW/
R0 ISSEUED
APPROVAL ET : 30/08/07 PSL : 30/08/07
ENQUIRY ET: 11/09/07 PSL : 12/09/07
FOR
R1 REVISED AS PER RIL COMMENTS ET: 18/09/07 PSL : 19/09/07
1 OF 41
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
Rev-R0 2 OF 41
I.DIESEL GENERATING SETS: SCOPE...........................................................................................................................3 II.APPROVAL FROM STATUTORY AUTHORITIES......................................................................................................4 III.EXCLUSIONS ..................................................................................................................................................................4 IV.DESIGN ..............................................................................................................................................................................4 V.
SPARES .....................................................................................................................................................................4
V.CODES & STANDARDS....................................................................................................................................................5 VI.GENERAL..........................................................................................................................................................................6 VII.OPERATING CONDITIONS.........................................................................................................................................6 VIII.TECHNICAL PARTICULARS AND DATA SHEETS...............................................................................................7 IX.PERFORMANCE REQUIREMENT..............................................................................................................................8 X.ALTERNATOR ...................................................................................................................................................................9 XI.GENERATOR CONTROL PANEL...............................................................................................................................14 XII.11KV SWITCHGEAR FOR DG OUTPUT CONTROL ...........................................................................................21 XIII.DIESEL ENGINE .......................................................................................................................................................26 XIV.INDUCTION MOTORS FOR AUXILIARY DRIVES..............................................................................................31 XV.PLC SYSTEM FOR DG.................................................................................................................................................32 XVI.TESTS............................................................................................................................................................................37 XVII.MAINTENANCE TOOL AND TACKLES...............................................................................................................39 XVIII.SPARES.......................................................................................................................................................................39 XIX.DRAWINGS AND DOCUMENTS SCHEDULE ......................................................................................................40
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
I.
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
Rev-R0 3 OF 41
DIESEL GENERATING SETS: SCOPE
This specification covers the technical requirements of design, manufacture, inspection and testing at manufacturer's works, delivery to site, supervision of erection, testing and commissioning of Four (4) nos. diesel generator sets having generation voltage of 11kV, rated output of 3750KVA (continuous), 1500 rpm comprising the following: 1.
DG set complete with all ancillary equipment, accessories, instruments and associated controls.
2.
Fuel oil system complete with 990 L. day tank, feed pump, priming pump, necessary piping, valves, filters and strainers, instruments, accessories, etc.
3.
Lubricating oil (L.O.) system complete with L.O. sump, L.O. Pump, necessary piping, valves and fittings, filters and strainers, L.O. heat exchanger, instruments, accessories etc.
4.
Compressed air assisted starting system with all accessories like compressor, compressed air bottle, necessary piping, valves etc., electrical starter for the compressor, interconnecting LV power and control cables to make the system self-sufficient. In case the Supplier’s standard design provides for battery starting, he may offer complete system related to battery starting.
5.
Air intake and exhaust system, complete with filters, silencers, ducts, pipe fittings & accessories and supporting arrangement for exhaust system. The silencer shall be “residential” type.
6.
Directly coupled A.C. machine (generator) with terminal box, rotating diode type brush-less exciter, automatic voltage regulator, alarm initiating devices and other accessories.
7.
Independent control panel with controls and instruments for each engine & alternator complete with AMF facility for starting of the engine and with necessary controls, interlocks, protections, metering and indications as per functional requirement of AMF feature. 11 KV VCB panel to be installed local to the gensets, complete with all controls shall also be included under this facility.
8.
Motors for auxiliary drives.
9.
Automatic and Manual synchronizing equipment for 4 DG sets.
10.
Anti-vibration pads for mounting of the DG set.
11.
PLC control system with SCADA function for remote operation of the DG system with facilities for event logging, trending, mimics alarm etc.
12.
LT power cables and control & signaling cables for DG installation along with the cable schedule for the same.
13.
Supply of consumables/spares for testing and commissioning of the DG sets at site.
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
II.
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
Rev-R0 4 OF 41
APPROVAL FROM STATUTORY AUTHORITIES.
The Bidder shall be responsible to obtain the approval of the Electrical Inspectorate or any other required statutory
authorities including approval from the Maharashtra Pollution Board and No Objection Certificate
from M.S.E.B. for the design, supply, installation, testing and commissioning of the equipment under his scope. Necessary official fees and charges will be reimbursed by the Purchaser on production of the receipt. All the required drawings, documents for the above purpose shall be prepared and supplied by the Supplier.
III.
EXCLUSIONS
Equipments & services excluded from scope of this specification.
All Civil works
11kV Cables
Main Bulk storage tank for diesel
Chimney and supporting structure
Cooling Tower with associated cooling water circulation pumps
However design inputs for chimney, supporting structure and cooling tower to be provided by the vendor.
IV.
DESIGN
The design and workmanship shall be in accordance with the best engineering practices, to ensure satisfactory performance and service life. The equipment offered by the Supplier shall be complete in all respects. Any materials or accessories, which may not have been specifically mentioned, but which are usual and necessary for the satisfactory and trouble free operation and maintenance of the equipment, shall be provided without any extra cost to the purchaser.
V.
SPARES
Sufficient spares for the DG Sets , shall be provided by the Bidder for maintenance of the DG Set for at least 2Years after successful commissioning , separate Quotation shall be provided for the same. Annual maintenance contract of the DG Set from the successful Bidder shall be negotiated separately. All Commissioning SPARES are tobe listed for FREE supply by the Bidder.
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
V.
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
Rev-R0 5 OF 41
CODES & STANDARDS
The design, construction, manufacture, inspection, testing and performance shall comply with all the currently applicable statutes, safety codes, latest editions of relevant Indian Standards (IS), British Standards (BS), International Electro Technical Commission (IEC) publication, NEMA and VDE Standards. Some of the applicable Standards are given below: IS 1601 BS-5514 IS-1600 IS-1460 IS-4729 IS-78 IS-2516 IS-3427 IS-2705 IS-3156 IS-375 IS-5422 IS-4722 IS-1885 IS-4729 IS-4728 IS-2208 IS-1248 IS-3231 IS-5082 IS-3072 IS-6875 IS-2551 IS-2253
-
IS-6362 IS-4889 IS-4691 AIEE-60
-
IEC-34
-
Performance & testing of IC engines for general purpose Performance & testing of diesel Part 3-5 engines for general purposes Type testing of constant speed internal combustion engines for general purposes Specification for diesel fuels Measurement and evaluation of vibration of rotating electrical machines Guide for testing insulation resistance of rotating machines A.C. Circuit breakers Metal enclosed switchgear Current transformers Voltage transformers Marking and arrangement for switchgear bus bars Turbine type generators Rotating electrical machines Electro technical vocabulary Part XXXV Measurement and evaluation of rotating electrical machines Terminal markings for rotating electrical machinery HRC cartridge fuse links up to 650V Electrical indicating instruments Electrical relays for power system protection Aluminium busbars Installation and maintenance of switchgear Control Switches Danger notice plates Designations for types of construction & mounting arrangement of rotating electrical machines Designation of methods of cooling for rotating electrical Method of determination of efficiency of rotating electrical machinery Degrees of protection provided by enclosures for rotating electrical machinery Recommended specification for speed governing of internal combustion engine generator units Rotating Machines
The DG set shall also conform to the provisions of latest Indian Electricity Act, Indian Electricity Rules and Regulations of Statutory Authorities (Chief Electrical Inspector to the Government) and the norms set by the Pollution Control Board. The equipment conforming to any other national standards, which ensure equivalent quality, are acceptable. In such cases, the Bidder shall clearly indicate the standard adopted, and furnish a copy of the English translation of the standard along with the tender. Should there be any dispute on design standard; the most stringent one shall be adopted.
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
VI.
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
Rev-R0 6 OF 41
GENERAL
The diesel generating set shall
be indoor type AMF operated and shall comprise of diesel engine,
coupled to a suitable alternator, having brush-less excitation system complete with all accessories.
All equipment shall be of the class most suitable for working under the specified conditions and shall withstand the atmospheric conditions without deterioration and without affecting the performance requirements.
Material of construction for interconnecting pipes, pipe fittings, exhaust duct, bolts and nuts shall be as per relevant standards and suitable to withstand the temperature of the gas/liquid within the pipe. All externally mounted hardware can be of cast iron.
Nameplates and labels provided for engine, alternator, control panel and Switchgear, accessories, etc. shall be of stainless steel only.
VII.
OPERATING CONDITIONS
D.G. sets are intended for supplying stand-by power as the most reliable source of supply, in the event of failure of utility grid.
The electrical load for diesel generating system shall comprise HT (6.6 KV)/LT motors, lighting and other miscellaneous loads fed through suitable step-down transformers.
The starting time of the set shall be kept to a minimum which has been specified in Annexure-I.
The DG sets shall be suitable for parallel operation among themselves. Parallel operation with utility grid is not envisaged.
Momentary paralleling with grid at the time of restoration of power supply should be possible.
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
Rev-R0 7 OF 41
VIII. TECHNICAL PARTICULARS AND DATA SHEETS
Sr.
1
Description Quantity
Requirement 4 Nos.(as per delivery schedule indicated
2 3 4 5
Type of installation Rating (MVA) Rated Output voltage (KV) Site conditions Altitude
elsewhere) INDOOR 3.75 (continuous) 11 Less than 1000 M. above Mean Sea Level
Ambient Temperature Maximum Minimum Design Relative Humidity Maximum Site Environment
40o C 10o C 45o C inside DG House 95% Polluted
Bidder’s Confirmation
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
IX. 1 2
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
SHEET NO.
Rev-R0 8 OF 41
PERFORMANCE REQUIREMENT
Type of output voltage Nature of load
Sinusoidal 3 Nos. 6.6kV, 900KW chillers fed
through
11/6.6
*
KV
transformers and other LT load with maximum motor rating of 110kW fed through 11/0.433 KV
3
Time for Diesel engine to start and take up load
transformers. Maximum 15 Seconds.
4
from Grid failure Mode of operation In case of grid power failure
Synchronized Out of 4 sets, Engines of 3 pre
* *
selected “duty” DG shall start on AMF and take up the loads within stipulated time.
4.1.1
Isolated/ parallel mode With grid supply
The DG sets shall never be operated in parallel with grid supply except for momentary
4.1.2
Isolated mode
paralleling for power restoration. During initial stage of project implementation, 1 no. DG set may be required to run in isolation to cater to the initial load.
4.1.3
Parallel mode
When the complete project is implemented, the DG sets shall be
required
to
synchronize
among themselves and take up the entire load proposed to be 4.1.4
Shut down of DG sets after restoration of grid
connected to them. This shall not be automatic and
supply.
manual intervention for DG shut down and re-transfer the bus to grid supply will be required.
*
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
X. Sr.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
SHEET NO.
Rev-R0 9 OF 41
ALTERNATOR Description
Requirement
Bidder’s
1 2 3 4 5 6
Rated voltage and frequency Output rating Rated Power factor Type of enclosure Degree of protection Class of insulation / temperature rise
3 phase, 11KV, 50Hz 3750 KVA 0.8 Industrial SPDP IP23 Min. Class `F' with temp. rise
7 8
Type of cooling Generator neutral system earthing
limited to class B Air cooled Solidly earthed.
recommendation
clarify whether neutral of all DG
Confirmation
Bidder
to
*
sets can be directly earthed or through an isolator for earthing of individual DG set, one at a Neutral isolation facility
time. In case the bidder recommends
*
the earthing of neutral of one of the four DG sets only, then the bidder shall include isolator / contactor, adequately rated for each of the DG set in his scope
9 10
Minimum protections required Excitation system Type Type of exciter
of supply. Refer clause no: 11 of part 34 rotating diode type brush-less
*
excitation system fast response type designed to
*
have a low time constant to minimize
voltage
transients
Insulation Exciter system
under severe load changes. class F Shaft driven A.C. exciter with
In built protections for over-voltage and rate of
rotating rectifiers. Required
rise of voltage
SPECIFICATIONS FOR EQUIPMENT DESIGN
DIESEL GENERATING SETS
ENGINEERS
CLIENT : RELIANCE INDUSTRIES LTD.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
Sr.
Description
Requirement
10.1. 1
Field forcing capability
capable of forcing the field for
Rev-R0 10 OF 41
Bidder’s Confirmation
more than 3 sec in the event of dead fault at the terminals.
11
Contribution by DG to faults downstream in
12
MVA Initial during 1st 7 cycles corresponding to xd” Up to 0.5 sec corresponding to xd’ Continuous corresponding to xd Maximum over voltage surge that DG set can
* * * *
withstand without deterioration and subsequent damage. (Note DG sets are controlled by
13
VCBs) AUTOMATIC VOLTAGE REGULATOR Type
High speed, adjustable dead
Control CTs and VTs for AVR operation
band, Electronic type AUTO/MANUAL To be included by the bidder as
Accuracy Response time for step load (from no load to
*
required. + 0.5% from no load to full load *
full load) &recovery of voltage to within 95%-in
14
15
sec. Range of voltage adjustment Performance Figures Efficiency at 100% loads Efficiency at 75% loads Efficiency at 50% loads Temperature rise Cooling medium temperature
* * * (measured by
*
detector or thermometer), °C Temperature rise of armature winding above
*
cooling
16
*
medium
(measured
by
embedded
detectors), °C Temperature rise of field winding above cooling
*
medium temperature (resistance), °C Temperature of cooling air from the windings
*
(detector or thermocouple), °C Losses Total no-load losses
*
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
Sr.
Description
16.1. 1 16.1. 2 16.1. 3
Total load losses at 50% load
SHEET NO.
Requirement
Rev-R0 11 OF 41
Bidder’s Confirmation
17
18
Total load losses at 75% load Total load losses at 100% load Short circuit current withstand and duration Asymmetrical short circuit current withstand and
*
duration for 3 sec. Symmetrical short circuit current withstand and
*
duration for 3 sec. Electrical characteristics
(calculated
on
maximum capacity) at 100% cooling for direct axis and quadrature axis Unsaturated synchronous reactance % Unsaturated transient reactance % Unsaturated sub-transient reactance % Saturated synchronous reactance % Saturated transient reactance % Saturated sub-transient reactance % Sr.
18.1. 1 18.1. 2
19
20
21
Description
* * * * * * Requirement
Bidder’s
Negative sequence reactance % Zero sequence reactance % D.C. resistance stator winding
Confirmation * * * *
rotor winding
*
Machine Time Constant Open circuit transient time constant Short circuit transient time constant Short circuit sub-transient time constant Short circuit armature time constant Unbalanced Stator Current Capability Ratio of negative sequence component of the
8% or more
*
system currents to rated current Momentary Excess current for Generator
capable of withstanding fifteen
*
* * * *
(15) sec. a current of fifty (50) percent in excess of its rated current
22
Stator Material of construction
high
quality
lamination
to
silicon
steel
achieve
high
permeability with low hysterisis
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
Sr.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
SHEET NO.
Description
Requirement
Windings
and eddy current losses. securely braced and wedged to
Rev-R0 12 OF 41
Bidder’s Confirmation
withstand
damage
from
mechanical & electrical forces imposed on the windings during full
voltage
conditions &
short for
the
circuit same
reason, they have to be heavily insulated
23
Rotor Construction
machined from a solid steel forging
Sr.
Description
Requirement
Bidder’s
Rotor winding MOC
Silver bearing copper
Joints between coils or half coils
to be brazed to be provided
*
26 27 28
Damper winding for satisfactory parallel running Insulation level Basic insulation level, KV peak Power frequency withstand, KV r.m.s. Vibration limits Noise level Painting finish
As per BS/IEC As per BS/IEC Within limits of BS/IEC Within limits of BS/IEC Epoxy. Paint Shade as per
* * * * *
29
Termination details
Confirmation
24 25
manufacturer’s standard. Cable Box suitable for 1 no. 11 KV, Al/XLPE, 3Cx300 sq. mm. cable
30
with
heat
shrink
termination – Raychem type Extra bracing for insulation
*
switching surges generated by VCB. Accessories Thermostat controlled anti-condensation space
Required. Supply voltage 240V
*
heater RTDS
AC, 50 Hz wired up to the terminal block in
*
Special precautions taken in the insulation system of the generator for protections against
31
a separate terminal box
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
Sr.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
SHEET NO.
Rev-R0 13 OF 41
Description
Requirement
Bidder’s
Rotor winding MOC
Silver bearing copper
Joints between coils or half coils
to be brazed to be provided
*
26 27 28
Damper winding for satisfactory parallel running Insulation level Basic insulation level, KV peak Power frequency withstand, KV r.m.s. Vibration limits Noise level Painting finish
As per BS/IEC As per BS/IEC Within limits of BS/IEC Within limits of BS/IEC Epoxy. Paint Shade as per
* * * * *
29
Termination details
Confirmation
24 25
manufacturer’s standard. Cable Box suitable for 1 no. 11 KV, Al/XLPE, 3Cx300 sq. mm. cable
30
with
heat
shrink
termination – Raychem type Extra bracing for insulation
*
switching surges generated by VCB. Accessories Thermostat controlled anti-condensation space
Required. Supply voltage 240V
*
heater 2 nos. bearing RTDs
AC, 50 Hz Required
*
6 nos. winding RTDS (2nos./phase)
Required
*
12-point Temperature Scanner for generator
Required
*
RTDs Earhing Earthing pads for alternator
Required
*
Two independent earth terminals on the frame,
Required
Special precautions taken in the insulation system of the generator for protections against
31
31.1. 1 31.1. 2
winding RTDs and engine & generator bearing
31.1. 3 31.1. 4
complete with nuts, spring washer, and plain washer for earthing of engine.. Vibration monitoring system including sensors
Required
*
and compatible monitoring unit to provide
32 33
alarm. Make of Alternator Protection CTs Construction Location
Cast Resin Neutral side of phase winding &
Ratio & class
neutral circuit Refer Attached S.L.D. for
*
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
Sr.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
SHEET NO.
Rev-R0 14 OF 41
Description
Requirement
Bidder’s
Rotor winding MOC
Silver bearing copper
Joints between coils or half coils
to be brazed to be provided
*
26 27 28
Damper winding for satisfactory parallel running Insulation level Basic insulation level, KV peak Power frequency withstand, KV r.m.s. Vibration limits Noise level Painting finish
As per BS/IEC As per BS/IEC Within limits of BS/IEC Within limits of BS/IEC Epoxy. Paint Shade as per
* * * * *
29
Termination details
Confirmation
24 25
manufacturer’s standard. Cable Box suitable for 1 no. 11 KV, Al/XLPE, 3Cx300 sq. mm. cable
30
Special precautions taken in the insulation
with
heat
shrink
termination – Raychem type Extra bracing for insulation
*
Required. Supply voltage 240V
*
system of the generator for protections against
31
switching surges generated by VCB. Accessories Thermostat controlled anti-condensation space heater
34
AC, 50 Hz Metering & Protections
Normal time the genset can run continuously
*
without requiring maintenance. (in hours)
XI.
GENERATOR CONTROL PANEL
Sr.
Description
Requirement
1 2 3 4 5 5.1 5.2 5.3
Execution Installation Degree of protection Sheet steel Sheet steel thickness Base frame / channel Load bearing members Internal partitions, doors etc
floor mounting Indoor IP52 CRCA
Bidder’s Confirmation
3mm 2mm 1.6mm
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
Sr.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
SHEET NO.
Description
Requirement
Type of assembly Surface treatment
Bolted 7 tank for removal of rust,
Rev-R0 15 OF 41
Bidder’s Confirmation
6 7
scale, oil,
grease & dirt by
pickling followed by phospating followed by 2 coats of zinc rich
8
Surface finish
primer Powder
9 10
Cable entry Panel accessories
paint shade RAL-7032 Bottom Thermostat controlled space
11
Protective Relays Type
Coated
Epoxy
with
heater and cubicle lamp
Supply Voltage Rated Current No. of output contacts Operation indicator Minimum protective functions required 11.1. 1 11.1. 2 11.1. 3 11.1. 4 11.1. 5 11.1. 6 11.1. 7
Numerical,
programmable
at
site 110V DC 1A As required for control scheme Required Voltage restraint IDMT Over
*
current Under frequency
*
Over frequency
*
Under voltage
*
Over voltage
*
Reverse power/ loss of prime
*
mover Restricted
*
earth
fault
instantaneous (high impedance circulating current)
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
11.1. 8 11.1. 9
SHEET NO.
Rev-R0 16 OF 41
IDMT earth fault – residual
*
current based Standby ground over current
*
fault
IDMT,
neutral
current
based Negative phase sequence over
11.1. 10
current,
voltage
unbalance,
inter-turn fault Loss of excitation
11.1.1 1 11.1. 12 11.1. 13
Differential over current
11.1. 14 11.1. 15
Master trip relay, hand reset,
*
lock out type Trip ckt supervision relay
*
Redundancy in BUS PT voltage (through BUS PT Relay ) for 110V AC Bus Wiring control Bus with for both sections of 11KV Switchgear Board. Field Protection Relays for the
11.1. 16
Exciter (single E/F (alarm) ,
Double E/F (trip ) NOTE:The above functions can be discrete numerical relays based or software based built into PLC. 12 Meters Type Digital, 7 segment LED Metering Required For Line Currents, Line voltages, frequency, PF, KVA, KW, kVAR (Multi-function Load Managers are preferred)
13
Control and selector switches Auto/Manual to select
Auto
Local / Remote to select Breaker Control switch
operation Local or Remote mode Trip - Neutral - Close, Spring
or
manual
return to Neutral.
14
Indicating Lamps Type Lens colours Red : C.B. “ON” Green : C.B. “OFF” White : “Trip Supply Supervision” Amber : Auto trip White : “Spring Charged” RYB : Phase Indication
Cluster LED
mode
of
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
11.1. 8 11.1. 9
SHEET NO.
Rev-R0 17 OF 41
IDMT earth fault – residual
*
current based Standby ground over current
*
fault
IDMT,
neutral
current
based Negative phase sequence over
11.1. 10
current,
voltage
unbalance,
inter-turn fault Loss of excitation
11.1.1 1 11.1. 12 11.1. 13
Differential over current
11.1. 14 11.1. 15
Master trip relay, hand reset,
*
lock out type Trip ckt supervision relay
*
Redundancy in BUS PT voltage (through BUS PT Relay ) for 110V AC Bus Wiring control Bus with for both sections of 11KV Switchgear Board. Field Protection Relays for the
11.1. 16
Exciter (single E/F (alarm) ,
Double E/F (trip ) NOTE:The above functions can be discrete numerical relays based or software based built into PLC. 12 Meters Type Digital, 7 segment LED Metering Required For Line Currents, Line voltages, frequency, PF, KVA, KW, kVAR (Multi-function Load Managers are preferred)
13 15
Control and selector switches Window type facia annunciators Voltage Equipped with
110V DC ‘Sound Cancel’, ‘Acknowledge’
Provided with
and ‘Reset’ push buttons Two lamps connected
Suitable for
parallel on each facia window Open to Alarm & Close to
Alarm –site selectable Designed for an operating sequence indicated below Alarm Condition Fault Contact Audible Visual Alarm Normal Abnormal
Open Closed
Alarm Off On
Off Flashing
in
*
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
11.1. 8 11.1. 9
SHEET NO.
Rev-R0 18 OF 41
IDMT earth fault – residual
*
current based Standby ground over current
*
fault
IDMT,
neutral
current
based Negative phase sequence over
11.1. 10
current,
voltage
unbalance,
inter-turn fault Loss of excitation
11.1.1 1 11.1. 12 11.1. 13
Differential over current
11.1. 14 11.1. 15
Master trip relay, hand reset,
*
lock out type Trip ckt supervision relay
*
Redundancy in BUS PT voltage (through BUS PT Relay ) for 110V AC Bus Wiring control Bus with for both sections of 11KV Switchgear Board. Field Protection Relays for the
11.1. 16
Exciter (single E/F (alarm) ,
Double E/F (trip ) NOTE:The above functions can be discrete numerical relays based or software based built into PLC. 12 Meters Type Digital, 7 segment LED Metering Required For Line Currents, Line voltages, frequency, PF, KVA, KW, kVAR (Multi-function Load Managers are preferred)
13
Control and selector switches Sound cancel Closed or Open Acknowledge Closed or Open Back to Normal Open Reset Open Lamp Test Open Minimum alarm/annunciation required
for
Off Flashing Off Steady on Off Steady on Off Off Off Steady on Generator electrical faults
alternator Downstream system fault Bearing temperature high Winding temperature high AVR trouble Excitation trouble
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
11.1. 8 11.1. 9
SHEET NO.
Rev-R0 19 OF 41
IDMT earth fault – residual
*
current based Standby ground over current
*
fault
IDMT,
neutral
current
based Negative phase sequence over
11.1. 10
current,
voltage
unbalance,
inter-turn fault Loss of excitation
11.1.1 1 11.1. 12 11.1. 13
Differential over current
11.1. 14 11.1. 15
Master trip relay, hand reset,
*
lock out type Trip ckt supervision relay
*
Redundancy in BUS PT voltage (through BUS PT Relay ) for 110V AC Bus Wiring control Bus with for both sections of 11KV Switchgear Board. Field Protection Relays for the
11.1. 16
Exciter (single E/F (alarm) ,
Double E/F (trip ) NOTE:The above functions can be discrete numerical relays based or software based built into PLC. 12 Meters Type Digital, 7 segment LED Metering Required For Line Currents, Line voltages, frequency, PF, KVA, KW, kVAR (Multi-function Load Managers are preferred)
13 16
Control and selector switches Minimum alarm/annunciation engine
required
for
Lube. oil pressure low & lowlow Jacket water temperature high and high-high Engine fails to start Engine/ Generator
Bearing
temperature high and high-high Engine shutdown Compressed air system trouble Engine over speed
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
SHEET NO.
Rev-R0 20 OF 41
Fuel oil tank level low and lowlow
17
18
19 19.1. 1
Push buttons Type
Spring return or stay put type as required 2 NO + 2 NC minimum
Contacts Labels & Name Plates Material Engraving
PVC or Anodised Aluminimum Black engraving on white background To suit application / importance. With self-tapping screws.
Size of the label Fixing Wiring Control wiring Type
660V
grade,
PVC
insulated
19.1. 2
Size
super-flexible copper wire 2.5 sq. mm. for CT circuit
19.1. 3
Colour
1.5 sq. mm. for control circuit Black for AC circuits and Grey
19.1. 4
Termination on equipment terminals / terminal
for DC circuit With crimped
blocks
copper lugs , preferably WAGO
19.1. 5
Ferruling
Type Required with non – detachable
20 21
Terminal Blocks Control terminal size No. of spare control terminals Synchronizing Facility Auto Synchronizing with each other Manual synchronizing facility Check synchro. facility to prevent synchronizing
type,
tinned
type printed ferrules Preferably WAGO type 2.5 sq. mm. minimum 10% minimum
wrong
Required Required Required
* * *
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
XII.
1
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
Execution
Indoor, metal enclosed, mounting, free-
standing,
5 6
SHEET NO.
11KV SWITCHGEAR FOR DG OUTPUT CONTROL
floor
2 3 4
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
Degree of protection Sheet steel Sheet steel thickness Base frame / channel Load bearing members Internal partitions, doors etc Type of assembly Surface treatment
dust
and
vermin-proof IP4X CRCA 3mm 2mm 1.6mm Bolted 7 tank for removal of rust, scale, oil,
grease,
dirt by pickling followed by phosphating followed by 2 coats of
7
Surface Finish
zinc rich primer Powder Coated Epoxy with paint shade RAL
8 9 10
Cable entry Version of circuit breakers – fixed or draw-out Panel accessories
7032 Bottom Drawout Space heater with MCB and thermostat + cubicle lamp
11
Bus bars Material Continuous current rating Insulation for bus bars
Electrolytic Aluminium 400A Heat shrinkable providing full insulation
*
Rev-R0 21 OF 41
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
SHEET NO.
Bus bar temperature rise while carrying
Final
temperature
of
rated current
85 C for bus bars and 0
900C for joints with an
12
12.1.1 12.1.2
Bus bar Supports Circuit breaker Type of circuit breakers No. of poles Make Rating Derated current rating at site condition Breaking capacity Short time rating Execution Mechanism Control Supply Voltage Spring charging Motor Closing and tripping coil CB mechanical indications (flags)
ambient of 400C SMC, DMC or cast resin Vacuum 3 * 630A 630A 26.24kA at 11kV = 500 MVA 26.24kA for 1 second Draw – out Motorised 240V AC 110V DC `ON’, `OFF’,
“Service”,
“Test”, “Isolated”, “Spring CB operation facility
charged” AUTO/MANUAL
Spare Auxiliary contacts
4 NO + 4 NC wired to terminal block
13
14
Requirement of surge suppressor For machines switched with VCB Type Class Meters Type Metering required for
Required Gapless, Zinc Oxide Rotating Machine class Digital, 7 segment LED Line Currents, Line voltages
15
Control and selector switches Function Auto/manual to select
Auto or manual mode of
Local / remote to select Breaker control switch
operation Local or Remote mode Trip - Neutral - Close, Spring return to Neutral.
16
Indicating lamps Type Lens colours Red : C.B. “ON” Green : C.B. “OFF”
Cluster LED
*
Rev-R0 22 OF 41
SPECIFICATIONS FOR EQUIPMENT DESIGN
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS
ENGINEERS
CLIENT : RELIANCE INDUSTRIES LTD.
SHEET NO.
Bus bar temperature rise while carrying
Final
temperature
of
rated current
85 C for bus bars and 0
900C for joints with an
12
12.1.1 12.1.2
Bus bar Supports Circuit breaker Type of circuit breakers No. of poles Make Rating Derated current rating at site condition Breaking capacity Short time rating Execution Mechanism Control Supply Voltage Spring charging Motor Closing and tripping coil CB mechanical indications (flags)
ambient of 400C SMC, DMC or cast resin Vacuum 3 * 630A 630A 26.24kA at 11kV = 500 MVA 26.24kA for 1 second Draw – out Motorised 240V AC 110V DC `ON’, `OFF’,
“Service”,
“Test”, “Isolated”, “Spring CB operation facility
charged” AUTO/MANUAL
Spare Auxiliary contacts
4 NO + 4 NC wired to terminal block
17
18
White : Amber : White : RYB : Push Buttons Type
“Trip Supply Supervision” Auto trip “Spring Charged” Phase Indication
Contacts Labels & Nameplates Material
Spring return or stay put type as required 2 NO + 2 NC minimum PVC
or
Anodised
Engraving
Aluminimum Black engraving
Size of the label
white background To suit application
Fixing
importance. With self-tapping
Use
screws. Main Panel,
on /
feeders
and individual devices
*
Rev-R0 23 OF 41
SPECIFICATIONS FOR EQUIPMENT DESIGN
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS
ENGINEERS
CLIENT : RELIANCE INDUSTRIES LTD.
SHEET NO.
Bus bar temperature rise while carrying
Final
temperature
of
rated current
85 C for bus bars and 0
900C for joints with an
12
12.1.1 12.1.2
ambient of 400C SMC, DMC or cast resin
Bus bar Supports Circuit breaker Type of circuit breakers No. of poles Make Rating Derated current rating at site condition Breaking capacity
Vacuum 3 * 630A 630A 26.24kA at 11kV = 500 MVA 26.24kA for 1 second Draw – out Motorised
Short time rating Execution Mechanism Control Supply Voltage Spring charging Motor Closing and tripping coil CB mechanical indications (flags)
240V AC 110V DC `ON’, `OFF’,
“Service”,
“Test”, “Isolated”, “Spring CB operation facility
charged” AUTO/MANUAL
Spare Auxiliary contacts
4 NO + 4 NC wired to terminal block
19 19.1.1
Wiring Control wiring Type
660V insulated
19.1.2
grade,
PVC
super-flexible
copper wire 2.5 sq. mm. for CT
Size
circuit 1.5 sq. mm. for control 19.1.3
Colour
19.1.4
Termination
19.1.5
circuit Black for AC circuits and on
equipment
terminals
/
Grey for DC circuit With crimped type,
terminal blocks
tinned
copper
lugs
Ferruling
preferably WAGO Type Required with non – detachable type printed
20
Terminal blocks Control terminal size
ferrules Preferably WAGO type 2.5 sq. mm. minimum
*
Rev-R0 24 OF 41
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
SHEET NO.
Bus bar temperature rise while carrying
Final
temperature
of
rated current
85 C for bus bars and 0
900C for joints with an
12
12.1.1 12.1.2
Bus bar Supports Circuit breaker Type of circuit breakers No. of poles Make Rating Derated current rating at site condition Breaking capacity Short time rating Execution Mechanism Control Supply Voltage Spring charging Motor Closing and tripping coil CB mechanical indications (flags)
ambient of 400C SMC, DMC or cast resin Vacuum 3 * 630A 630A 26.24kA at 11kV = 500
*
MVA 26.24kA for 1 second Draw – out Motorised 240V AC 110V DC `ON’, `OFF’,
“Service”,
“Test”, “Isolated”, “Spring
21 22
CB operation facility
charged” AUTO/MANUAL
Spare Auxiliary contacts
4 NO + 4 NC wired to
No. Of spare control terminals Testing All routine tests as per applicable standards Quality Assurance Plan
terminal block 10% minimum Required. *
Rev-R0 25 OF 41
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
SHEET NO.
Rev-R0 26 OF 41
XIII. DIESEL ENGINE Sr.
1 2
Description Make Engine capacity (KW)
Requirement Compatible
with
Bidder’s Confirmation * *
alternator of 3750KVA
3
Type of fuel for engine
4 5 6
Engine Speed Short time overload capacity of engine Cooling Cooling water requirement Inlet water temperature Outlet water temperature Quality of cooling water Cooling water system monitoring instrumentation
0.8 PF commercial High speed diesel (HSD) 1500 RPM Water Cooled Mcu/Hr 32 Deg C 37 Deg C maximum Raw / DM/ treated Flow meters, inlet & outlet
water
* * * * * * * *
temp.
indicator Maximum duration the DG can run at rated load
7 8 9
without cooling water No of cylinders Time interval between successive starts Fuel oil system Day tank Capacity Accessory
* * * 990 liters Filling, draining
and
vent
with
connection
valves
and
switches
for
level low
oil
level & high oil level alarm
and
automatic
operation scheme for
Sr.
Type of filter
day-tank filling. Duplex
Description Pre-Combustion Chamber
Requirement Designed so
as
achieve
knock-
safe
Bidder’s Confirmation
free performance with smokeless exhaust
to
SPECIFICATIONS FOR EQUIPMENT DESIGN
DIESEL GENERATING SETS
ENGINEERS
Sr.
10
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
CLIENT : RELIANCE INDUSTRIES LTD.
Description Type of engine
SHEET NO.
Requirement multi-cylinder, enclosed, duty,
Rev-R0 27 OF 41
Bidder’s Confirmation totally
continuous direct
fuel
injection,
turbo-
charged,
compression
ignition, inter-cooled oil engine Specific fuel consumption under site conditions 10.1.1 10.1.2 10.1.3
11
Full Load 3/4 Full Load 1/2 Full Load Pressure fed type
Lubricating Oil System Lube. Oil required at rated Load Type of filter in lube oil system to take load due
* *
Duplex type
to clogging of Lube filter Arrangement to bypass the oil cooler during starting
until
oil
temperature
rises
Required
above
minimum. Bypass valve to prevent engine being starved of
Required
oil in case filter is choked Accessories such as
Required
pressure
gauges,
temperature indicators, pressure relief valves,
12 13
Sr.
bypass valves, pressure switches Engine shaft driven lube oil pump Electrical motor driven lube oil pump Lube Oil Coolers Engine starting system Type of starting
1 1 working+ 1 standby As Required Compressed air starting
Description No. of starts to be permitted by compressed air
Requirement Minimum 3 consecutive
system Compressed air system
starting attempts 1 no. compressor having
adequate
capacity to be installed local
to
engine.
the
diesel
Individual
compressor individual DG.
for
Bidder’s Confirmation
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
Sr.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
Description Completeness of compressed air system
SHEET NO.
Requirement Storage adequate
receiver to
Rev-R0 28 OF 41
Bidder’s Confirmation *
hold
compressed air for 3 successive starts of the engine,
necessary
interconnecting piping, pressure
gauges,
pressure switches for automatic cycling of the compressor, starter, Starting solenoid valves with manual bypass
14 14.1.1 14.1.2
valve for local starting ( UPS / DC Supply ) Governing system Make Type Load sharing features Adjustable droop Steady state speed regulation Steady state governing speed plus or minus % of
LV
electric power
&
control cabling. Required
* Electronic type Required Required
* * * *
rated speed Momentary over speed after full load rejection %
*
of rated speed Sr.
Description Momentary under speed of rated
Requirement
Bidder’s Confirmation *
speed after
sudden increase of 25% rated load Prescribed speed band ± rated speed Safety
over - speed trip device to
automatically
shut
off fuel in case the speed
exceeds
the
prescribed limit.
15
Exhaust system Engine exhaust system, complete with exhaust
Required
gas driven turbo charger, residential silencer, ducting, bends , silicate lagging, supporting accessories etc G.I. cladding for Exhaust pipes within enclosure
22 gauge with thermal insulation
* *
SPECIFICATIONS FOR EQUIPMENT DESIGN
DIESEL GENERATING SETS
ENGINEERS
Sr.
16
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
CLIENT : RELIANCE INDUSTRIES LTD.
Description Local Indicator Panel Flexibly mounted local indicator panel with speed
SHEET NO.
Requirement
Rev-R0 29 OF 41
Bidder’s Confirmation
Required
indicator and gauges for lubricating oil pressure
17
before and after filter Bearings
Self-aligning
Type No. Life Lubrication Type of lubricant Lubricating interval Well with a suitable thermometer in the oil drain
journal
bearings Self lubricated type * * * * * Required
and a suitable sight flow opening to observe bearing oil flow. They shall also be provided with Pt-100
Sr.
type
RTDs
for
monitoring
their
temperature. Maximum generator shaft voltage
100 mV
Description In case, shaft voltage exceeds 100mV
Requirement Non-driving
end
bearing
and
Bidder’s Confirmation
housing
lead-in & lead out pipes to be fully insulated (Non
18
conductive
Separate terminal box for space heater and
insulation) Required
R.T.D./Thermistors Forced Lubrication System
In
case
forced
lubrication is required, bidder shall provide 1 W+ 1 SB forced lube oil
19
Engine exercising facility to be built into engine and generator control panel “Service” (Duty)- Engine shall remain as “Ready-
pumps,
electrical
motor driven. Normal service, Auto, Manual
to-start” and shall start automatically when called upon (AMF) Automatic exercising
Engine should be able to start and run at a
*
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
Sr.
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
Description
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
Requirement preset time (e.g. once
Bidder’s Confirmation
a week) and shall run for preset time (e.g. 30min) this shall be programmable at site Manual Exercising
without load Operator shall be in a position to start and run the engine as desired
20 21
Overall dimensions of fully assembled DG unit Without acoustic enclosure Weight schedule
Rev-R0 30 OF 41
*
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
Sr.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
Description Overall weight of complete system for foundation
SHEET NO.
Requirement
Rev-R0 31 OF 41
Bidder’s Confirmation *
design Heaviest single unit to be handled during normal
*
maintenance KGs
XIV. INDUCTION MOTORS FOR AUXILIARY DRIVES Sr.
1 2
Description Rated Voltage Type of installation
Requirement 415V ±10%, 50 Hz, ±5% Industrial, 3 phase,
3
Degree of protection
squirrel cage IP54 for indoor and IP 55
4 5
Reference standard Surface treatment
for outdoor IS 325. painted with
6
Winding treatment
works type epoxy paint windings shall be treated
chemical
for chemically corrosive atmosphere.
Overhang
shall be applied with gel
7
Minimum Motor rating
coat epoxy paint. 15% higher than
the
driven equipment input
8 9
Insulation class Minimum starting voltage
power requirement Class B or better 80% of rated voltage
Bidder’s Confirmation
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
XV.
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
Rev-R0 32 OF 41
PLC SYSTEM FOR DG
A PLC (Programmable Logic Controller) system shall be provided for centralized control of 4nos. 3750 KVA DG sets. Only the functional requirement expected from the system are specified here. The Bidder has to make his own estimate about hardware requirement.
9.1
SCOPE: Supply of hardware to support the software and for operator interface.
Develop software based on the functional requirements stipulated in this specification.
Loading of the software into PLC system at the Bidder’s Works and testing by simulation.
Deliver the equipment at site.
Supervision of installation, testing and on load commissioning of the system.
Training of the Owner’s operating personnel for 5 working days for operating, maintenance troubleshooting, editing / modifications to the software etc.
9.2
Supply of essential spares. PERFORMANCE REQUIREMENTS OF THE PLC SYSTEM –
The following performance activities are expected from the PLC:
Starting and stopping of 04 nos. DG sets along with their auxiliaries in a sequenced manner.
The DG sets are to run in synchronism with each other.
The PLC shall allow selection of any three out of four DG duty sets as “Service” sets and fourth as “standby”.
Automatic Mains Failure starting of 3 nos. duty DG sets. In case one of the DG set fails to start or trip during operation, the standby DG set shall be brought into operation automatically.
ON – OFF control of DG sets VCBs.
Generation of static and dynamic mimic for each DG set along with important parameters of generator and engine.
Fault report generation indicating type of fault and date & time of occurrence of the fault. The system shall be capable of loading the faults in its memory for 48 hours.
Generation print-outs periodically or on-demand as desired by the operator in a format to be approved by the Purchaser.
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
Rev-R0 33 OF 41
Basic System The basic system shall comprise the following:
Central Processing Unit.
Adequate Memory for storing and running of the software.
Interfacing device viz.
Key board
Mouse
17” flat screen Colour Monitor
Laser Printer for taking hard copy output.
Programming unit (as described below)
Adequate number of digital I / O racks.
Adequate number of Analogue / Analogue or Analogue / digital converters.
Sheet steel cabinet to house the CPU, I / O racks and converters etc.
Interconnecting cabling between various devices of the system
Self – diagnostics.
Back – up storage of the software.
Any other hardware / software that is required to make the system complete and fully operational. The Bidder shall clearly spell out all such features is his Bid for better understanding / evaluation of his Bid.
System hardware requirement CPU The Bidder shall select the CPU with appropriate speed so that the software can be run with reasonable speed and the data can be updated reasonably fast. The Bidder shall furnish technical particulars of the CPU offered. MEMORY Memory offered shall be adequate: To store the entire software with at least 100% spare memory for future alternations additions / losses in corrupt memory segments. (ROM / Hard Disk) To run the entire software with at least 100% spare memory for the same purpose as above (RAM). The Bidder shall furnish technical particulars of the Memory offered. INTERFACING DEVICE The keyboard, Mouse and 17” flat screen colour monitor shall be standard commercially available device available in the market, to the extent possible. PRINTER This shall be standard commercially available laser type. Programming Unit This has been described in more details in the following paragraph under “Software”
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
Rev-R0 34 OF 41
Digital I / O racks
Digital input cards are required to accept inputs such as VCB auxiliary contacts, temperature switch, pressure switch contacts etc. These shall be potential – free. The interrogating voltage shall preferably be low voltage DC (such as 12 or 24 V. DC) which has to be generated by the Bidder. Digital output cards, complete with heavy duty auxiliary interposing relays if required, shall be suitable for onerous switching duty such as operation of VCB closing and tripping coil at 110 V. DC.
Analogue / Analogue or Analogue / Digital converters –
Analogue input signals such as DG set current and voltages shall be the inputs to the PLC system. Currents shall be 0-1 A and voltages 0-110V corresponding to 0-11 kV, 50 Hz AC signals. The converters shall convert them for use in PLC software.
Construction
The sheet steel cabinet shall be floor mounting, free – standing, CRCA sheet cabinet made out of 2 mm thick sheet. The sheet shall under go 7 – tank chemical pre-treatment which shall be followed by epoxy based powder coating in shade RAL 7032 or the one approved by the Purchaser. The cubicle shall provide degree of protection not less than IP 52. Neoprene gasketting shall be provided at the doors and all metal-to-metal contacts. Louvres, if required, shall be covered by fine wire mesh. The cable entry shall be from bottom. Panel earthing and system earthing shall be provided as detailed under “Earthing“ below. If glass is used in the panel door for viewing of the PLC system, the same shall be heat resistant toughened type. The cubicle, in general, shall be aesthetically built and compatible with the system & its installation Interconnecting Cabling – All interconnecting cabling between the CPU, Digital I / O Racks, Analogue input racks, keyboard, mouse, VDU, printer, programming unit etc. shall be included by the Bidder in his scope of supply. Field cabling for digital inputs / outputs, analogue inputs etc. shall also be provided by the bidder. Self Diagnostic The PLC system shall be complete with hardware and software for providing self-diagnostic feature for the system. Failure of power supplies, components, PCBs shall be indicated by RED LEDs. The LEDs shall be tagged to indicate the type of failure that has taken place. The Bidder shall furnish an operations and Maintenance Manual highlighting the steps that are to be taken by the operator in the event of occurrence of such an event.
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
Rev-R0 35 OF 41
Back – up storage of the software In the event of the software getting non-operative / corrupt due to some reason the operator should be capable of re-loading the same into the PLC system. The Bidder shall, therefore, included in his scope suitable back-up system such as a CD (with a drive) Completeness of the System If the Bidder feels that based on his experience certain additional hardware / software is required to be included by him to make the system fully operation, he shall offer the same, highlighting the particulars. Software The sequencing logic shall be either ladder diagram based or execution statement based. It is preferable that the operator is in a position to edit the logic or add the ladders / execution statement from his PC with the help of keyboard or mouse. Power supply The Purchaser shall make available power at 240V, Single phase, 50 Hz or 415 V, 3 ph., 4 wire, 50 Hz, depending on the KVA requirement of the PLC system. The industrial (plant power distribution) power supply is prone to frequent failures, is subject to over voltages / under voltages and is likely to be contaminated by spurious noise signals, spike etc. The Bidder shall clearly state in his Bid whether the above mentioned power supply is acceptable to his system, in which case he has to elaborate the arrangements made by him in his PLC input power supply system. If the Bidder requires conditioned and UPS power supply for his system, He shall include adequately rated UPS system operating on the abovementioned Industrial type power supply, with adequately rated (AH capacity) sealed Maintenance – Free batteries. Other power supplies such as 12 / 24 V DC or as required, for the electronics system of the PLC, in any case will have to be derived by the Bidder himself. Necessary power packs and other hardware required for this purpose will have to be included by the bidder in his scope. Earthing The Bidder shall clearly spell out the requirement of earthing, both panel frame earthing and signal earthing in his bid. He shall highlight the requirement of “Clean Earth” if required. He shall also furnish specifications i.e. size and shielded / unshielded cable for interconnection between PLC system and earth pits. Training The Bidder shall include in his scope training of Purchaser’s operating staff for a period of 5 working days. The training shall cover a minimum of
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
Rev-R0 36 OF 41
Familiarization of configuration of the PLC system.
Familiarization and working of the software including the procedure for loading of the software from back-up storage system, editing of / modifications to the preloaded software.
Actual operation of the DG system including the VCBs from the PLC.
Fault diagnostics and trouble-shooting
Repair of the faulty PCB / replacement by spare PCBs etc.
10 BIDDER’S EXPERIENCE The Bidder shall furnish a reference list to establish his credentials by way of submitting a list of at least 5 nos. industrial type projects executed in last 3 years of similar ratings.
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
Rev-R0 37 OF 41
XVI. TESTS
Tests shall be carried out during and after completion of manufacture of different component parts and the assembly, as applicable, in accordance with the requirement of relevant codes and standards. Bidder shall indicate other tests, which are required to be carried out at site after installation.
Tests shall be performed in presence of Purchaser's representative if so desired by Purchaser, at Supplier's works on completed assembly of the DG set. The Bidder shall give at least two (2) weeks advance notice for inspection.
Following tests shall be carried out on the engine-generator completed assembly at manufacturer's works: a) b) 25.1
Power run of auxiliary equipment. Functional checks and adjustments of speed governor and control devices.
The generator shall be subjected to following tests (for which only Test Certificates are required):
a)
High voltage tests on stator and rotor windings.
b)
Insulation resistance of stator and rotor windings.
c)
Temperature rise test
d)
Open circuit and short circuit tests.
e)
Stator phase sequence check.
f)
Overload capability test.
g)
Measurement of air gap.
h)
Stator winding resistance measurement
25.2
Excitation System
The excitation system shall be subjected to the following tests at manufacturer's works (for which only Test Certificates are required): a)
High voltage tests on windings.
b)
Insulation resistance of windings.
c)
Temperature rise test.
d)
Measurement of resistance of stator and rotor windings.
e)
Open circuit magnetization test.
f) Functional check and operation of relays, protection, metering and signalling schemes. 25.3
Voltage regulator
The voltage regulator shall be subjected to the following tests at manufacturer's works (for which only Test Certificates are required): a)
Sensitivity test.
b)
Response time test.
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
25.4
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
Rev-R0 38 OF 41
Control Panels
The control panels shall be subjected to the following tests at manufacturer's works, which shall be witnessed by the Purchaser/ his representative.
25.5
a)
Continuity Checks
b)
High voltage withstand test as per relevant standard.
c)
Insulation resistance test.
d)
Functional and operation test. D.G. set and the auxiliaries
D.G. set and the auxiliaries shall be assembled at the manufacturer's works and the following tests shall be performed, which shall be witnessed by the Purchaser/ his representative. a)
One (1) hour running at full load.
b)
One (1) hour running at 3/4 load.
c)
One (1) hour running at 110% full load.
d)
Engine starting time.
e)
Fuel consumption test.
Before each test, the engine shall be brought to a steady state under the conditions of the test. 25.6
Tests at Site
The tests shall be performed after proper installation of the diesel generating unit at site to prove the proper operation of interlock circuits and the capability of the engine to start and pick-up load in the specified time, under supervision of the purchaser's representative responsible for supervision of testing and commissioning. Guarantee tests to prove guaranteed performance of the D.G. set shall also be carried out at site after proper installation. 25.7 a. b.
Test Certificates Test certificates shall be submitted in six (6) copies. The test certificates shall be furnished to the purchaser for prior approval before despatch of any
equipment from works and the approval in writing from purchaser shall be essential to effect dispatch of the equipment. c.
The test reports shall indicate complete identification of the data, including serial number of each
equipment.
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002 SHEET NO.
Rev-R0 39 OF 41
XVII. MAINTENANCE TOOL AND TACKLES
The Bidder shall furnish to the purchaser a complete and unused set of all special tools and tackles, which are necessary or convenient for erection, testing and commissioning, maintenance and overhauling of any of the equipment provided under this specification.
The tools shall be shipped in separate containers clearly marked with the name of equipment for which they are intended.
The Bidder shall submit a list of tools proposed to be furnished under the scope of supply with his proposal.
XVIII. SPARES Adequate quantity of spares for DG sets, shall be provided by the bidder for maintenance of the Dg sets at least for 2 years after successful commissioning. The bidder shall submit a list of recommended spare parts, with suggested quantities and catalogue numbers, for ten(10) years smooth and trouble free operation.
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
SHEET NO.
Rev-R0 40 OF 41
XIX. DRAWINGS AND DOCUMENTS SCHEDULE
A.
FOR GENERATOR CONTROL & BREAKER PANEL
Documents shall comprise but not limited to the following:
Required after Purchase Order Engineering Data
Require
For
No. of
As
d
approva
weeks
built
With
l Qty
No. of weeks
Qty
Bid-Qty 1 2 3
Outline dimension drawing Cross sections with part description Foundation drawings with static & dynamic
4 5 6
loading data Completed Data Sheets Bill of Materials for scope of Supply Performance Data /Curves:/Discharge
7
curves Installation / Operation / Maintenance
8 9 10 11 12
Manual Priced Spare List for 10 years service Terminal point schedule / drawing Control Schematic Diagram Description of Control Sequences Type test certificate for short circuit
13
withstand for panel Type test certificate for short circuit
14 15
breaking current of circuit breaker At the time of inspection Test Certificates for bought out items (Breaker, CT, PT, Meter, Relay)
2
4
2
6
6
2
4
2
6
6
2 2 2
4
2
6
6
3
With dispatch
6 6
6 6
6 6
At the time of
2 4 4
2 2
2 2
inspection
SPECIFICATIONS FOR EQUIPMENT DESIGN ENGINEERS
B.
DOCUMENT NUMBER MH-IDMHMUMB001-E-SP-002
DIESEL GENERATING SETS CLIENT : RELIANCE INDUSTRIES LTD.
SHEET NO.
Rev-R0 41 OF 41
DRAWING AND DOCUMENTS SCHEDULE FOR DG SYSTEM
Documents shall comprise but not limited to the following:
Required after Purchase Order Engineering Data
1
General arrangement drawing showing all major dimensions, including required and crane
Reqd
For
No.of
As
No.of weeks
With
approval
weeks
built
Bid
Qty
2
4
2
6
6
2
4
2
6
6
Qty
clearances
requirement for
assembly & dis- mantling, nett & shipping 2
weights of all items of equipment. Recommended layout showing
room
dimensions, ventilation requirement
civil
foundations, loading data, trench,
wall
3
opening, etc. Schematic P & I diagrams for lube oil, fuel
2
4
2
6
6
4
oil, jacket cooling, etc. Schematic diagrams for control
2
4
2
6
6
2
4
2
6
6
panel,
synchronising panel, voltage regulator, 5
governor Literature, write ups, description of DG set excitation system,
voltage regulator,
6 7
governor & other auxiliaries Voltage dip calculations Test reports
-
4 -
2 -
6 6
6 Before
8 9
Generator characteristic curves Bill of material
yes 2
3 4
2 2
6 6
despatch 6 6