DETAILS OF NIT NO.-46/2009-10/ EE/ PHEDN/ RATLAM DATED 23/09/2009

NAME OF WORK : DESIGN, CONSTRUCTION AND TESTING OF R.C.C. ANICUT OF 225M LENGTH AND 6.00M HEIGHT CROSS RIVER KSHIPRA NEAR VILLAGE GURADIYA OF ALOTE BLOCK IN RATLAM DISTRICT (M.P.) TENDER NO: 114 N.I.T. NO: 46/2009-10/EE/PHEDN/RATLAMDATED23/09/2009 N.I.T. DATE: 30-09-2009 TENDER CATEGORY: PHED ,WORK - LUMP SUM, BASIN / PROJECT: INDORE ZONE CIRCLE / DIVISION: RATLAM DIVISION OFFICER: RAJENDRA KUMAR HIRODIYA DESIGNATION: EXECUTIVE ENGINEER CLASS OF CONTRACTOR: A-4 S-4 & ABOVE IN ANY GOVERNMENT DEPARTMENT. NO. OF CALL: THIRD CALL

DETAILS OF TENDER:-

Work Details – Contractor (WHO QUOTED LOWEST RATE IN THE BID ONLINE )

Company: k g developers Bid No: 2538

BASE RATE:

IN FIGURES -

6,80,00,000.00

IN WORDS - RUPEES SIX CARORES EIGHTY LAKHS ONLY

1. Details of Previously called tender :- This is the third call of the work Lowest Rate

A. In year 2004-05 ( 1 call)

3,20,00,000.00(aprox)

B. In year 2007-08 (2nd Call)

9,90,00,000.00

C. In year 2008-09 (3rd Call)

6,80,00,000.00

st

2. Publication of tender: - Tender is invited by online e-procurement system of M.P. Govt.

3. PAC worked on SOR:- S.O.R. E-in-C, M.P. Water Resources department w.e.f. 1.7.2007

4. Current SOR:-Now the revised WRD Unified SOR w.e.f 1/02/2009 with up-to-date amendments is effective with this kind of work in department.

5. Cost of work:- A.- As PAC in invited tender (on SOR of 2007)

355.00

lakhs b. –As revised Estimate prepared by the department

570.00

lakhs (On SOR of 2009)

6

Bid quoted by bidder: - M/S K G Developers

680.00

lakhs. Examination of bid:1) Department is not considering Some logical points in their design and preparation of estimate like A. Top width of anicut was considered as 2.0 mtrs but it is not sufficient for providing grooves for operational arrangement of curry shutter (i.e. min. 1.8 mtrs) as well as walk way slab too on top of anicut (i.e. min. 1.2 mtrs) so it will minimum 3.0 mtrs at top. B. Provision of paneled pitching is also include in the tender but not considered in preparation of estimate. C. Some miscellaneous provisions like cutting of bank in slop of 1:2, jungle clearance, surveying, geological investigation, preparation of design and drawing.

D. There is no provision of escalation covered in NIT and time allowed for completion is Fifteen months excluding rainy season which is having risk of rate increment in market as common trend. E. The measure qty of concrete goes in to the foundation of anicut and the department consider depth of foundation as 1.5 mtrs below average river bad level. In our opinion which is not sufficient and not correlate the recommendation of geological investigation. 2) After taking above consideration in estimate it goes to the amount of Rs. 639.00 lakhs (Approximately) 3) There are number of risk involves in turn key projects so it is understood about higher cost in compression of item rate or percentage rate tender. 4) There is no chance to come lower bids in future.

DETAILS OF SIMILAR TYPE OF WORK EXECUTED BY DEPARTMENT:S. No . 1 2

Name of work

Name of division

Length in mtr

Height in mtr

Year of senction

RCC Anicut across river Gambhir , Unhel, ujjain RCC Anicut across river Avna ,

Ujjain

100.00

6.5

2005

Senctioned amount in lakhs 265.00 lakhs

Mandsa ur

92.7

4.5

2006-07

148.00 lakhs

3 4

Narayangarh, Mandsaur RCC Anicut across river Chamla, Badnagar, ujjain RCC Anicut across river , Behadwa, Alirajpur

Ujjain

64

7

2005

250.00 lakhs

Jhabua

180

5.0

2001

448.00 lakhs (aprox)

Length in mtr

Height in mtr

Year of tender

amount in lakhs

225.00

6.0

2009

680.00 lakhs

Scope of This Work:S. No .

Name of work

1

RCC Anicut across river Kshipra , Alote, Ratlam

Name of divisio n Ratla m

From above details it may be concluded that the said rate are reasonable and justified.