Delay Notice Letter No (1) 28/Mar/12

Subject: Additional Cost and Time notice for Local Authorities Permission Dear Employer, Reference to the subject mentioned above and client Letter Ref.1 dated 3/25/2012 We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above. Following are the impacted activities due to Employer instruction:

The additional scope of work: Activity ID

Letter 1 - 1

Activity Name

Authorities Permissions

The Impacted Existing Activity: Activity ID

SUBz100020

Activity Name

Excavation Activity

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice Letter No (2) 24/Mar/12

Subject: Additional Cost and Time notice for Site Handing Over Dear Employer, Reference to the subject mentioned above and client Letter Ref.2 dated 3/20/2012 We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above. Following are the impacted activities due to Employer instruction:

The additional scope of work: Activity ID

Letter 2 - 1

Activity Name

Site Delivery Delay

The Impacted Existing Activity: Activity ID

SUBZ100010

Activity Name

Mobilization

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice Letter No (3) 18/Apr/12

Subject: Additional Cost and Time notice for Pumps Submittal Dear Employer, Reference to the subject mentioned above and client Letter Ref.2 dated 4/15/2012 We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above. Following are the impacted activities due to Employer instruction:

The additional scope of work: Activity ID

MAR-20-1

Activity Name

New Pumps Submittal

The Impacted Existing Activity: Activity ID

0801MW0011

Activity Name

INSTALLATION OF WATER & FIRE PUMPS

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice Letter No (4) 15/May/12

Subject: Additional Cost and Time notice for Lighting Fixture Type 2*26 w Dear Employer, Reference to the subject mentioned above and client Letter Ref.3 dated 5/12/2012 We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above. Following are the impacted activities due to Employer instruction:

The additional scope of work: Activity ID

MAR 4-1

Activity Name

Delay of MAR response

The Impacted Existing Activity: Activity ID

A2250

Activity Name

LIGHTING FIXTURES& SWITCHS Procurement

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice Letter No (5) 3/Jan/13

Subject: Additional Cost and Time notice for Item no.1 ( Utilities will be available on 1 July 2013 ). Dear Employer, Reference to the subject mentioned above and client Letter Ref.1 dated 2/1/2013 We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above. Following are the impacted activities due to Employer instruction:

The additional scope of work: Activity ID

MOM-13-1

Activity Name

Delay of Utilities availability

The Impacted Existing Activity: Activity ID

A2450

Activity Name

Elevators TESTING AND COMMISSIONING

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice Letter No (6) 9/3/20162

Subject: Additional Cost and Time notice for Supplying Safe door Dear Employer, Reference to the subject mentioned above and client Letter Ref.2 dated 9/1/2012 We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above. Following are the impacted activities due to Employer instruction:

The additional scope of work: Activity ID

MOM 9-1

Activity Name

Safe Door Supplying Delay

The Impacted Existing Activity: Activity ID

Arch1070

Activity Name

Wall Preparation for Painting

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice Letter No (7) 1/Apr/12

Subject: Additional Cost and Time notice for Under Ground Water Level Dear Employer, Reference to the subject mentioned above and client Letter Ref.1 dated 3/29/2012 We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above. Following are the impacted activities due to Employer instruction:

The additional scope of work: Activity ID

RFI No.3-1

Activity Name

Response from Consultant

The Impacted Existing Activity: Activity ID

SUBZ100030

Activity Name

COMPACTING WORKS UNDER THE P.C LAYER

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice Letter No (8) 4/Feb/13

Subject: Additional Cost and Time notice for Clash between Lighting Unit and Diffuser Dear Employer, Reference to the subject mentioned above and client Letter Ref.3 dated 2/1/2013 We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above. Following are the impacted activities due to Employer instruction:

The additional scope of work: Activity ID

RFI-6- 1

Activity Name

Remove Fixed Lighting Fixture

The Impacted Existing Activity: Activity ID

0801EL0005

Activity Name

LIGHTING FIXTURES& SWITCHS & OUTLETS

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice Letter No (9) 10/May/12

Subject: Additional Cost and Time notice for Doors and Windows Shop Drawing Dear Employer, Reference to the subject mentioned above and client Letter Ref.3 dated 5/7/2012 We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above. Following are the impacted activities due to Employer instruction:

The additional scope of work: Activity ID

SDF 2-1

Activity Name

New Door Submittal

The Impacted Existing Activity: Activity ID

ARCH1150

Activity Name

WOODEN DOORS INSTALLING

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice Letter No (10) 5/Jun/12

Subject: Additional Cost and Time notice for Change Marble Fixation Dear Employer, Reference to the subject mentioned above and client Letter Ref.1 dated 6/2/2012 We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above. Following are the impacted activities due to Employer instruction:

The additional scope of work: Activity ID

SWI1_1

Activity Name

Demolish all fixed marble

The Impacted Existing Activity: Activity ID

Arch1110

Activity Name

MARBLE WORKS VIP SEC. WALL'S CLADDING &FLOORING

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice Letter No (11) 19/Mar/13

Subject: Additional Cost and Time notice for Change Painting Color Code Dear Employer, Reference to the subject mentioned above and client Letter Ref.3 dated 3/15/2013 We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above. Following are the impacted activities due to Employer instruction:

The additional scope of work: Activity ID

SWI 2_1

Activity Name

Submit new material for approved

The Impacted Existing Activity: Activity ID

A2290

Activity Name

Painting Site delivery date

The additional cost and / or time impact analysis will be submitted in due course.