Daily Staging Plan & MPC Report BMB Project 5140C

11-may-2018

PT Petrosea Tbk. No Document : PTP-CC-TPL-G-0006

2

MINE PLANNING – Digger Position 11 may 2018 Digger task : •

EX 152 -> Create Counter Weight



EX 154 -> Expose seam D & construct road LW



EX155 -> Loading mud area A21 & Cut Floor A11



EX156 -> Service est RFU night shift 11/05/2018 After RFU Expose seam D

152

Ramp RL +11 to RL 0 RL35 RL+50

RL40 RL01

RL45 RL55

Coal Priority • Seam D3 • Seam D lower • Seam B2

RL25 RL40 RL20

ULTRA/ULNA : • EX 154 Disposal : • IPD RL+20 (blok mud from west area)



RL11

OPD RL+40

General :

BMB:

PTP :

ENG

Operation

ENG

Operation 3

SITARUM

MINE PLANNING – PHOTO – PIT VIEW

EX0156

EX0154 n(2)

EX0154 (1)

4 SITARUM

MINE PLANNING – PHOTO – PIT VIEW

EX0155

5 SITARUM

MINE PLANNING – PHOTO – OPD VIEW

Compartment 5

Compartment 4

RL +40

6 SITARUM

MINE PLANNING – PHOTO – IPD VIEW

RL 0

7

SITARUM

1

ULTRA / ULNA OBSTACLE INFORMATION

EX0152 (OB Digger) Obstacle

ULTRA/ULNA NOT AVAILABLE

GRADE BOX

• Top Loading

Action

• -

• Grade box not avaliable

EX0154 (OB Digger) Obstacle

ULTRA/ULNA AVAILABLE

GRADE BOX

• -

Action

• -

• Grade box not avaliable

8 SITARUM – MINING OPERATION PROCESS

1

ULTRA / ULNA OBSTACLE INFORMATION

EX0155 (OB Digger) Obstacle

ULTRA/ULNA NOT AVAILABLE

GRADE BOX

• Top Loading

Action

• -

Grade box not available

EX0156 (OB Digger) Obstacle

ULTRA/ULNA -

• Service

GRADE BOX

• Grade box not available

Action

• -

SERVICE

9 SITARUM – MINING OPERATION PROCESS

3

Digger Productivity

Summary DS (11 may 2018) Digger

Productivity

EX0152

626

EX0154

EX0155

853

800

Bench Preparation

Geometri Loading point

Hauling Road

Dumping point

Next Plan Area Preparation

ULTRA / ULNA

-

-





-

-













-

EX0156

-





-



Note

-

Dump to bank soil IPD Used 3 HD Create Counter Weight Top Loading

-

Service

-

Dump to IPD RL +20 Used 5 HD Blast Material Finalisasi Bottom pit Bottom Loading

-

Service

Update Avg. Productivity : 13.30 WITA Legend √ : Comply X : Not Comply : Not Available

10 SITARUM – MINING OPERATION PROCESS

11

MINE PLANNING – Digger Position 11 May 2018

Digger Task : • EX0137 Service (Replace Engine) • EX0135 Expose seam C  seam D • EX0145 Expose seam F

Coal Priority : • Seam C boxcut • Seam C Middle • Seam B LW

RL35 RL50

RL30

RL25

RL45 RL55

ULTRA/ULNA : • EX0135 • EX0145

RL40 RL20

RL10

Disposal : • OPD RL+50 Project: • Layback HW • Sloping HW East RL60-50 (NS) • Construct ROM (BMB) jalan keluar

PTP : ENG

Operation

12 TABUHAN

MINE PLANNING – PHOTO – PIT VIEW

EX0145-1 EX0145-2

EX0135-2 EX0135-1

Coal Priority

OB

Plan Blast Area 11 may 18

13 TABUHAN

MINE PLANNING – PHOTO – OPD VIEW

RL+50

14 TABUHAN

1

ULTRA / ULNA OBSTACLE INFORMATION

EX0137 (OB Digger) Obstacle

ULTRA/ULNA NOT AVAILABLE

Service (Replace Engine) GRADE BOX

• -

Action

• -

• -

EX0135 (OB Digger) Obstacle

ULTRA/ULNA AVAILABLE

• -

GRADE BOX

• Grade box not available

Action

• -

15 TABUHAN – MINING OPERATION PROCESS

2

ULTRA / ULNA OBSTACLE INFORMATION

EX0145 (OB Digger) Obstacle

ULTRA/ULNA AVAILABLE

GRADE BOX

Action

• -

• Grade box available

16 TABUHAN – MINING OPERATION PROCESS

3

Digger Productivity

Summary DS (11 May2018) Digger

Productivity

EX0137

Install digging limit

Bench preparation

OB/Coal loading

OB/Coal Hauling

Install Dumping Peg

Dumping point

ULTRA / ULNA

-

-

-

-

-

-

-

-

Service (replace engine)





-

Dump to OPD RL +50 Used 4 HD Bottom loading Blast material





-

Dump to OPD RL +50 Used 4 HD Bottom loading Blast material

EX0135



EX0145







Legend √ : Comply X : Not Comply : Not Available













Note

Update Avg. Productivity : 15.30 WITA

17 TABUHAN – MINING OPERATION PROCESS

4

Mine Production Control Inspection

Summary DS (11 May 2018)

18 TABUHAN – MINING OPERATION PROCESS

To become a world-class company recognised for excellent integrated mining solution provider

19 TABUHAN – MINING OPERATION PROCESS

Related Documents

Daily Plan
October 2019 10
Daily Report
July 2020 6
Daily Report
November 2019 29
Staging Booklet
November 2019 5
Mpc-ebooklet.pdf
December 2019 16

More Documents from "Ankit Prajapati"