Creating the A+ assignment: A project management approach Peter Mellalieu Development draft A: 11 Oct 2001 This document helps you plan out the time you need to produce an A+ assignment for an undergraduate university assignment, using a project management framework. Some adaptations and extensions need to be made for more advanced work, such as a research report, or a postgraduate assignment.
Allocating your time In general, you need to allocate your time in three roughly equal parts which together form ten distinct phases of work:
The start up, planning first draft and layout phases (4 phases) The investigation, research, figures and graphics phases (2 phases) The enhancement, proof reading, document integration and submission phases (4 phases)
The maximum grade you might achieve The diagram Maximum potential grade versus Percent Total work completed more precisely shows the maximum possible grade you might get if you just complete the first part, then the second part, and then all three parts described above. The grade applies to an undergraduate assignment and assumes a ‘quick and dirty’ cobble together and submission of the assignment given the work already completed – if you are lucky!
In detail: The project work breakdown structure The Project Work Breakdown Structure (Figure 1) shows the various tasks that need to be completed in each of the ten Phases of activity required to create an A+ (First Class) written assignment, such as an essay or report. The Work Tasks within each Phase are roughly sequenced from top to bottom according to a logical precedence in each Phase. In general, the Phases must be commenced starting from the left, and moving across the figure. However, some Phases can be carried out at the same time - such as the First Draft Writing Phase, and the Layout Design Phase. Note that an element of ‘Fast Tracking’ (to reduce the time between project start, and completion) is demonstrated. For example, some phases (such as the Enhancement Phase and the Document Integration Phase) can be commenced without waiting for feedback from the peer reviews of the document drafts produced in earlier phases. The peer feedback may be incorporated part way through the appropriate Phase, although in a more leisurely world, one would ideally have the peer feedback prior to starting work on a new Phase. The Network logic diagram (Figure 2) is a graphic representation showing the sequence and dependencies of the tasks. For those with access to project management software, a more detailed breakdown of the tasks
1
could be produced and adapted to the particular assignment to be undertaken. The thick line shows the critical path. If you get behind in your work on any activity that is on the critical path, then there is a danger that your assignment will finish later than initially intended – unless you work overtime! The Percent of Total Work in Each Work Phase (Figure 3) shows the percentage proportion of the total project time that we estimate should be allocated to each Phase. The basis for this estimate of time derives from discussion with several undergraduate students at Massey University in 1999, and is based around a typical assignment requiring a work effort of 30 hours spread over s month. Note how you should limit the time you spend researching and investigating to about one-third of the total work effort – and that time includes writing up the notes of your research and investigation! Secondly, note that the Enhancement phase takes the second largest chunk of time – it is this phase of work that helps you craft your report into a rationally sequenced, logical, clear and consistent production. This is where you practice the art of writing and demonstrate the soundness of your thinking. The Project Timeline shows in a graphical format an example of how you might allocate your time across the main tasks in each phase over a month. This example assumes you have 30 hours to spend on the assignment – about 7 hours per week.
Technical terms In the Project Work Breakdown Structure there are some technical terms that writers use that you will need to understand and learn how to apply. For example: topic sentences (look under ‘paragraphing’), transitions, introductory proposition, citation, reference, and peer review. Look in the index and contents of a book such as Emerson (2000) or De Luca & Annals (2000). There are some project management terms that you should also learn about: milestone, critical path, and fast tracking. See a reference on project management such as Duncan (1996), or Quinn et al (1996, Chapter 5)
Acknowledgements This diagram was inspired by a mini-lecture presented by Lisa Emerson, Director - Student Learning Centre, Massey University, to students of Enterprise Development at Massey University, and a tutorial by Peter Mellalieu to the same class on the topic of Project Management.
Further reading For further reading on the topics of assignment writing and project management, see: De Luca, Rosemary & Annals, Alison, (2000) Writing that works: A guide for students, Auckland: Pearson Education ISBN 0-582-71897-X Emerson, Lisa (2000) Writing Guidelines for Business Students (2nd Ed), Palmerston North: Dunmore Press William R. Duncan (1996), A Guide to the Project Management Body of Knowledge, Upper Darby (PAUSA): Project Management Institute (PMI). Quinn, R.E., Faerman S.R., Thompson, M.P., McGrath, M.R. (1996) Becoming a master manager: a competency framework 2nd ed. New York: John Wiley. ISBN 0-471-00744-7 © Based on material by Peter Mellalieu and Lisa Emerson, 1999. All Rights Reserved. This diagram may be used by others for non-commercial purposes provided it is represented in its entirety, including this message.
2
Maximum Potential Grade versus Percent Total Work Completed A+ A AB+ B G r a d e
BEnhancement, Proof Reading, Document Integration, and Submission Phases
C+ C D
Research, and Figures & Graphics Phases
E Startup, Planning, First Draft and Layout Phases
NIL
0
5
10
15
20
25
30
35
40
45 50 55 Percent of Total Work
3
60
65
70
75
80
85
90
95
100
Figure 1: Project Work Breakdown Structure for Creating an A+ Essay or Report Assignment © Peter Mellalieu 1999 Document Version: 1 Jan 1904
Startup Phase
Project Planning Phase
Phase Work 5% Total Work 5% Maximum Grade NIL Identify Assignment
Phase Work 5% Total Work 10% Maximum Grade E
Specification
assignment topic
Layout Design Phase
Research Phase
Phase Work 10% Total Work 20% Maximum Grade D
Phase Work 5% Total Work 25% Maximum Grade C
Phase Work 30% Total Work 55% Maximum Grade B-
Refine paragraphing
Incorporate feedback
supplementary
Prepare figures,
(Topic sentences,
on penultimate draft
available for
headings, sub-
reading, research,
diagrams, pictures
single ideas per
from peer review
committing to this
'Crash' write first
headings, fonts,
and/or interviews
and other graphics
paragraph, transitions
group
assignment
draft
margins, paragraphing, binding)
Identify key risks,
Create draft outline
uncertainties, deadline
and structure
contingency options
Contribution Allocate work load
Identify opportunities
tasks
target audience (reader) Identify co-requisite reading Define and
Identify other special
appendices, etc, and
introduction and
figures
integrate into
overview
appendices etc
argument Refine topic
Spell check
Write draft summary
Set up design
and conclusion
template and style guide on computer
report content and structure
assessment grade target
and arguments MILESTONE:
sentences
Layout design
Allocation Schedule Identify additional
and template
Schedule special
literature and
complete
resources, interviews,
research resources
against Assignment Specifications Circulate figures to peer group for critical
Spell check
review
Check revised draft
Backup computer files
Develop investigation Communicate plan to
and/or research
Circulate research
key stakeholders and
methodology
draft to peer group for critical review
MILESTONE:
searches for required
Revise Project
Project Plan
documents and/or
Management Plan
MILESTONE: Figures,
graphics
circulated
against Assignment Specification
check
guide/template to
Check introductory
Layout figures,
Binding
proposition and
graphics, appendices,
overview
break outs, etc into
Attach assignment
final document
cover sheet Dispatch to assessor
Prepare title page,
up’ statement
contents list, list of
Check for random
figures, index,
Make backup
(unconnected)
Check paragraphing
sentences
glossary,
(single ideas, topic
acknowledgements,
sentences, paragraph
appendixes, headers
length, transitions)
and footers
Check citations,
Check layout design
and Biography sections
references and
against Assignment
bibliography
Specifications
Circulate penultimate
Check figures,
Check layout for
draft to peer group
graphics, tables, etc
consistency
for critical review
explained
Revise Project
Check grammar
on final text from
Penultimate prepared
terms, formal terms,
learned, and recommendations for
Check page numbers Check spelling
Management Plan
Circulate final group for critical review
MILESTONE: text
Final
circulated
Backup computer files
Reflect and document key lessons learned, personal insights, and
Draft
First
recommendations for
circulated
carrying out future projects
This Project Work Breakdown Structure shows the various tasks that need to be completed in each of the ten major Phases of activity required to create an A+ (First Class) written assignment, such as an essay or report. The Work Tasks within each Phase are roughly sequenced from top to bottom according to a logical precedence in each Phase. In general, the Phases must be commenced starting from the left, and moving across the figure. However, some Phases can be carried out at the same time - such as the First Draft Writing Phase, and the Layout Design Phase. Note that an element of ‘Fast Tracking’ (to reduce the time between project start, and completion) is demonstrated. For example, some phases (such as the Enhancement Phase and the Document Integration Phase) can be commenced without waiting for feedback from the peer reviews of the document drafts produced in earlier phases. The peer feedback may be incorporated part way through the appropriate Phase, although in a more leisurely world, one would ideally have the peer feedback prior to starting work on a new Phase. The data for Phase Work shows the percentage proportion of the total project time that we estimate should be allocated to each Phase. The Total Work percentage shows the cumulative project work time including the current and all previous Phases. The Maximum Grade shows the maximum possible university grade which might reasonably be Maximum if the product of that Phase was quickly cobbled into a submitted assignment. This diagram was inspired by a mini-lecture presented by Lisa Emerson, Director - Student Learning Centre, Massey University, to students of Enterprise Development at Massey University, and a tutorial by Peter Mellalieu to the same class on the topic of Project Management. For further reading on the topics of assignment writing and project management, see: Lisa Emerson (1995) Writing Guidelines for Business Students, Palmerston North: Dunmore Press William R. Duncan (1996), A Guide to the Project Management Body of Knowledge,, Upper Darby (PA-USA): Project Management Institute (PMI). © Peter Mellalieu and Lisa Emerson, 1999. All Rights Reserved. This diagram may be used by others for non-commercial purposes provided it is represented in its entirety, including this message. This version: 1 Jan 1904
4
from assessor.
orphans’
document to peer
MILESTONE:
Receive feedback
MILESTONE: Celebrate
definitions)
review
Management Plan
date
Resolve ‘widows and
Revise Project
peer group for critical
assessor by due
future projects
(straightforward text
Assignment
Revise lessons
Check words
text
MILESTONE: A+
peer review group Check spelling
MILESTONE:
computer backups
delivered to
Incorporate feedback
Research-based
hardcopy and
Celebrate completion
Spell check
Revise Project and
Final visual and spell
summary and ‘wrap
MILESTONE: circulated
group
Printout Final version
Backup computer files
Check first draft
from peer review
figures from peer
group
Backup computer files Spell check
Incorporate feedback
on layout design and
final text
Management Plan
confirm interviews
Incorporate feedback
Check conclusion,
Complete Reference
against Assignment Specification
group meetings
Check sequence
Backup computer files
MILESTONE::
established
supporting evidence
Phase Work 5% Total Work 100% Maximum Grade A+
from peer review
Circulate first draft to
Determine
Targets
Introduce quotations,
Check layout design
Phase Work 10% Total Work 95% Maximum Grade A
Apply style
Incorporate feedback
sentences
citations, and other Backup computer files
aids?) Brainstorm ideas for
graphics, tables,
and explanations to
requirements (group project?, multi-media
Prepare introductions structure
Draft key topic
circulated
argument Explain figures,
Initiate requests and
concepts and terms
Requirements
figures etc
group
Submission and Closing Phase
Check logic and
Refine logic and
peer review team
understand key
from peer review
Document Integration Phase
review group
thought)
‘break out’ sections,
Type up draft
Identify or specify
Prepare labelling for
figures, graphics,
Identify milestones Develop Gantt Work
Incorporate feedback
Write draft
Identify critical path
Work Load Hours
to new lines of
for using illustrations,
hours to phases and
Identify assessment
Recommended Total
Phase Work 5% Total Work 85% Maximum Grade A-
Complete
Assessment
Identify
Phase Work 15% Total Work 80% Maximum Grade B+
(page design, titles,
clashes, priorities, and
criteria
Final ProofReading Phase
Design layout style
Identify Percent
Identify Due Date
Phase Work 10% Total Work 65% Maximum Grade B
Enhancement Phase
reading
Identify length and format
Figures and Graphics Phase
Complete co-requisite Estimate work hours
Identify and/or select
First Draft Writing Phase
Update Project Management Template (for future projects) Backup computer files MILESTONE: document circulated
Final
success
Figure 2: Network Logic Diagram for Creating and A+ Essay or Report Assignment
First Draft Writing 10 %
Startup Phase 5%
Research 30 %
Enhancement 15 %
Proof Reading 5%
Document Integration 10 %
Project Planning 5%
Layout Design 5%
Figures & Graphics 10 %
This diagram shows the logical dependencies which exist for this project. For example, the Enhancement Phase depends on outputs from both the Research and Figures & Graphics Phases. Work flows from left to right across the diagram. Figures show percentage of total expected work load for the complete project. Thick line indicates Critical Path © Peter Mellalieu, 1 Jan 1904
5
Submission and Closing 5% %
Figure 3: Percent of Total Work in Each Work Phase Submission
Startup Planning
Integration
Startup 5% Planning 5% First Draft
First Draft
10%
Layout 5%
Proof Reading
Research 30% Layout
Figures 10% Enhancement 15% ProofReading 5%
Enhancement
Integration 10% Submission 5%
Research
Figures
First Draft
6
Project Time Line for Creating an A+ Written Assignment
(Relaxed Version) Task Name
% of Total Project Work
STARTUP, PLANNING, FIRST DRAFT Startup
5
Requirements & Targets established Project Planning
5
Project Plan Circulated First Draft Writing
10
First Draft Circulated
Planned Start Duration in Hours
Planned Finish
Actual Start
Actual Finish
% Done Jul 2000 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1/07/2000
0
1/07/2000
1/07/2000
1.5
2/07/2000
2/07/2000
0
2/07/2000
2/07/2000
1.5
4/07/2000
4/07/2000
0
4/07/2000
4/07/2000
3
7/07/2000
7/07/2000
0
7/07/2000
5
10
20
RESEARCH, FIGURES, GRAPHICS Research
30
Research-based text circulated Layout and Design
5
Design Template completed Figures and Graphics
10
Figures and Graphics circulated
7/07/2000
9
16/07/2000
16/07/2000
0
16/07/2000
16/07/2000
1.5
17/07/2000
17/07/2000
0
17/07/2000
17/07/2000
3
20/07/2000
20/07/2000
0
20/07/2000
20/07/2000
4.5
25/07/2000
25/07/2000
0
25/07/2000
25/07/2000
1.5
26/07/2000
26/07/2000
0
26/07/2000
26/07/2000
3
29/07/2000
29/07/2000
0
29/07/2000
29/07/2000
0.75
30/07/2000
30/07/2000
0
30/07/2000
30/07/2000
0.75
31/07/2000
31/07/2000
0
31/07/2000
50
55
65
ENHANCEMENT, INTEGRATION, SUBMISSION & CLOSURE Enhancement
15
Penultimate text circulated Final Proof Reading
5
Final Text and Figures circulated Document Integration
10
Final Document circulated Submission
2.5
Assignment delivered Closure Project Closed
2.5
80
85
95
This chart shows the scheduling of actual hours spent on a Writing project. Assumptions: 30 hours available for the assignment, a work load capacity of 7 hours/per week, and no ‘fast tracking’.
97.5
100
7