Preliminary Schedule Cowell Smokestack Demolition and Site Restoration Client: Cowell Homeowner"s Association Contractor: Evans Brothers, Inc. Date: 4/7/2009 Latest Revision 6/1/09
1-Jun Week 1 Item 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
8-Jun 15-Jun 22-Jun 29-Jun 2 3 4 5
Description Notice to Proceed X Contract/Submittals/Permits XXXXX On Site Mobilization/Temp Const XXXXX XXXXX Clear Site XXXXX Mobilize Crane XX Demolish Cornice X Demolish Stack with Crane XX XXXXX XXXXX Demobilize Crane Demolish Stack with Excavator Load out Rubble Chip Wall at Base/Salvage Brick Clen Up/Clear Site/Rough Grade Concrete Paving/Wall Repair Landscaping/Irrigation/Planting Landscape Maintenance 90 days
7-Jul 6
13-Jul 7
20-Jul 8
27-Jul 9
3-Aug 10-Aug 17-Aug 24-Aug 31-Aug 10 11 12 13 14
8-Sep 9/14-12/14 15 16-28
XX XXXX XXX XXXXX XXXXX XXX XXXXX XXXXX XXXXX XXXXX XXXXX XXXXX XXXX XXXXXXX
File: 9.04 Const. Schedule
6-01-09