PART II SCHEDULE OF RATES FOR LABOUR OF MAJOR WORKS Sl No.
1
A
Description
Unit
Rates as Proposed 2006-07 Amount in RS 220 KV
110 KV
66 KV
33 KV
Detailed Surveying on Turn-Key: i) Reconnoitary Survey-cum-walk over Survey along with K.P.T.C. Ltd., Staff to determine the feasible route of the line on topo sheet. An alternate route if available should be indicated. The route of the line is to be indicated and got approved by the competent authority( Rates include the cost of Toposheet and Transportation) a) Hilly terrain b) Plain terrain
KM KM
855 810
430 405
KM KM
4130 2760
2060 1375
ii) Detailed Survey, fixing anchor points and taking levels at 20 Mtrs intervels drawing route profile on Graph paper indicating geographical features like Nalas, Rivers, Gardens, P&T Lines, Railway-crossings etc., and enroute villages. a) Hilly terrain b) Plain terrain
iii) Fixing marking stones with approved marks including painting above the ground level and Yellow Lettering and marking the direction of incoming line and out going lines are to be clearly marked on the top with red colour. Per Stone If the distance between two anchor points is more than 1 KM, one more directional stone is to be fixed. So also for the road crossing, railway crossing and nala crossing for all on both the sides.
205
iv) Burgie details for identification for all Anchor towers with existing permanent marks like poles, telephone lines, buildings, etc.,
Per Anchor Tower
185
v) Excavation for soil classification a) Excavation of soil 1.2 Mtrs. x 1.2 Mtrs. up to a depth of 3 Mtrs. or up to hard rock is reached which ever is less (Applicable for soil classification purpose for 400 KV & 220 KV lines only) b) Excavation of soil 1.2 Mtrs x 1.2 Mtrs. up to depth of 2.5 Mtrs. or up to hard rock is reached which ever is less(Applicable to 110 KV & 66 KV lines) The excavation of trial pits shall be retricted to one pit for every Km and part there off.
CMT
vi) Conducting soil resistivity tests
Rates for different soils encountered as per actual soil condition applicable for transmission line (Ref-item 3A )
355
Per Test
vii) Clearing of bushes, tree branches of trees crops and shrubs wherever encountered for detailed survey to enroute the corridor width of 3 Mtrs (including viewing for fixing anchor towers etc.,) a) Hilly terrain
Per Km
615
310
b) Plain terrain
Per Km
410
205
viii) a) Submission of reports in the form of good binding including the preparation of sketches for burgie details for each anchor points, scheduling of line details, S.R. values, soil classification reports tower schedule, abstract of towers etc., complete.
Per set
125
b) Drawing the route profile on graph sheet including geographic features like nala's, rivers, gardens, P&T lines, railway crossings etc., inclusive of all stationeries (Normal requirement is 5 Sets)
Per Km
125
Sl No.
Description
Unit
Rates as Proposed 2006-07 Amount in RS 220 KV
110 KV
66 KV
33 KV
ix) Preparation of Schedules: a) PTCC Proposal : Containing PTCC questionaire, topo sheet extracts with marking of the proposed line, S.R. Report, tower sketch, station single line diagram etc.,(30 Copies/Sets)
Per set
495
b) Railway Crossing proposal with drawing are inclusive of graph sheets and other stationery materials, labour etc., (10 Sets)
Per Crossing
495
c) Tree Schedule Containing the details like name of tree, girth size of tree, distance from central line of the Per Hectare alignment, approximate height of the tree etc., complete
d) Forest proposals : Inclusive of all works like fixing of stones at every 20 Mtrs in the centre line and both ends of the corridor, painting of each tree after chipping, writing the numbers on the tree, taking girth size of all the trees coming in the corridor at 1 Mtr height from GL, approximate height of the tree and forest clearance proposals etc., complete (10 sets) Note: This applies to forest area only B Check Survey by using their own Equipment a) Hilly terrain b) Plain Terrain 2
A Taking block levels for Sub-stations: a) Running Peripheral Theodolite traverse along periphery and coordinating and heightening of all comers/turning points, establishing permanent coordinate axis formation of grids at 50M intervals for northing and easting with reference to already established permanent co-ordinate axis levels at 50 M grid intersection for preparing plot plan of the entire area with contours. Including existing structure location.
355
Per Km
Per Km Per Km
2310
2060
1025
1375
685
Hectare
685
b) Establishing datum level and bench marks at every 100M/50M intervals both longitudinal and laterally and all comers/turning points with stone pillars of size not less than 0.2Mx2Mx1.0M buried on the ground and exposed top engraved for painting RL, and co-ordinates of that point.
Nos.
685
c) Taking level at 5M/ suitable grid interval in the substation area for plotting block levels, contour map.
Nos.
15
d) Preparation of CAD drawings, generating the contours using appropriate software and submission of 6 sets of Per Project blue prints and one tracing sheet (original) and one soft copy etc. Complete.
6850
e) Furnishing cutting and filling quantities using appropriate software for earth work calculation.
Per Project
2055
f) Super imposing GA drawings on contour maps in Coordination with KPTCL engineers and supply of 12 sets of Per Project blue print drawings etc., complete.
5480
Sl No.
Description
Unit
Rates as Proposed 2006-07 Amount in RS 220 KV
110 KV
66 KV
33 KV
B Geo Technical Investigations:
a) Making 150mm nominal diameter bore holes at various locations in soil using suitable approved method of boring including, cleaning providing Bore holes at interval and at change of strata, collections of water samples, observation such as ground water etc., Collection of undisturbed soil samples at every 2.0M/3.0 M interval and at change of strata, transporation of all the collected samples to the laboratory and back filling of bore holes on completion of the work, complete as per specification and instruction of the 6.0M below natural ground level or refusal strata.
Per Mtr
1025
i) Bulk density and moisture content ii) Sieve analysis iii) Hydrometer Analysis iv) Liquid limit and plastic limit v) Shrinkage limits vi) Specific gravity vii) Standard proctor density test viii) Swell pressure
Each Each Each Each Each Each Each Each
410 410 410 410 480 480 480 550
ix) Free swell index x) Uncombined Compressive strength xi) Triaxial shear test
Each Each Each
550 550 550
xii) One dimensional consolidation test xiii)California bearing ratio
Each Each
550 550
Per Job
8220
b) Conducting various laboratory tests on soil samples at approved laboratory including preparation of soil samples to determinate of soil, all complete as per specification. Note: Laboratory identified shall be approved by KPTCL not below the rank of EE(Civil)
c) Submitting final report in 6 copies including all field records and laboratory test results, graphs and recommendations etc., complete as per specifications. Note: The above rates are inclusive of mobilization of Plant Equipment & Materials for , Topographical survey, block leveling and Geotechnical investigation works, and Demobilization. No extra rate is admisible for mobilization & Demobilization 3
A Excavation for station structure: 1) Corresponding rates in KPWD SR as mentioned against each classification below shall be adopted. 2) Area weightages applicable for the respective areas as per Latest KPWD SR shall be allowed to arrive at final rate.
Excavation of pits as per specifications for lattice type of station structures, Tr. Plinth, control panels, mounting structures for breakers, CT's, PT's Isolators, LA's etc., Excavation of trnches for control cables, U.G. Cables, Groundmat etc., i) Normal Soil ii) B.C. Soil iii) Partially Submerged soil iv) Fully submerged soil v) Wet black cotton soil
CMT CMT CMT CMT CMT
vi) Dry fissured/Ordinary rock
CMT
vii) Latterite soil
CMT
Rate for ordinary rock (without blasting) of Latest KPWD SR
viii) Hard rock with blasting/Hard latterite
CMT
Rate for hard rock (with blasting) of Latest KPWD SR
Note 1 : For Excavation purposes measurement shall be as per actuals.
Latest KPWD SR Rate for hard soil Latest KPWD SR Rate for hard soil Rate for hard soil of Latest KPWD SR Rate for hard soil of Latest KPWD SR Rate for hard soil of Latest KPWD SR Rate for ordinary rock (without blasting) of Latest KPWD SR
Sl No.
Description
Note 2 : For foundation purposes predominant soil shall be considered.
Unit
Rates as Proposed 2006-07 Amount in RS 220 KV
110 KV
66 KV
33 KV
Sl No.
Description
Unit
Rates as Proposed 2006-07 Amount in RS 220 KV
110 KV
66 KV
33 KV
B Excavation (For Tr. Line Tower) i) Normal Soil ii) B.C. Soil iii) Partially Submerged soil iv) Fully submerged soil
CMT CMT CMT CMT
v) Wet black cotton soil vi) Dry fissured/Ordinary rock
CMT CMT
vii) Latterite soil viii) Hard rock with blasting/Hard latterite C Back Filling :
(Rates as per item3-A + 50% extra)
CMT CMT
i) Back filling with excavated earth available near the tower and consolidation layer by layer of 150 mm depth with adequate quantity of water.
CMT
Rates as per Latest KPWD SR + 10% extra
ii) Supplying and back filling with external hard murrum soil with proper consolidation including lead and lift.
CMT
Rates as per Latest KPWD SR + 10% extra
Note: This item is applicable only when Black cotton soil, wet black cotton soil, dry fissured rock, ordinary rock, Hard rock are encountered. 4
Concreting and curing (For Both Transmission lines and station structures) 1) Corresponding rates in Latest KPWD SR as mentioned against each classification shall be adopted. 2) For the above basic rate add actual admissible lead for sand & jelly and aera weightage applicable as per Latest KPWD SR.
a) Concreting and curing as per specifications including the cost of materials, T&P materials and labour charges with all lead and lift, for lattice type station structures, Tr. Plinth, control panels, mounting structures for Breakers, CT's PT's Isolators, LA's, etc., i) 1:4:8 Concrete ii) 1:3:6 Concrete
CMT CMT
iii) 1:2:4 Concrete iv) 1:1.5:3 Concrete (M-20)
CMT CMT
b) Concreting and curing as per specifications including the cost of materials, T&P materials and labour charges with all lead and lift for Transmission line Towers.
CMT
Rate under plain concrete for foundation of Latest KPWD Rates under basement of SR. Latest KPWD SR Rate under raft foundation of Latest KPWD SR Rate under raft foundation of Latest KPWD SR For arriving at the rates for concrete items for transmission lines, add 25% weightage to the basic rates of different propotions of concrete proposed above.
Note : a) Extra rate of Rs 20 per CMT may be allowed for providing concrete in watery situations including cost of bailing out water and removing slush. b) Only machine mixing for concreting is to be used. c) Jelly to be used is 20 mm. and down size for 1:1.5:3, 1:2:4 & 1:3:6 concrete and 40mm and down size for CC 1:4:8. 5
Towers a) Sorting of tower parts made of fabricated angle iron.
MT
160
b) setting up of stubs templates and aligning dismantling and transportation of templates from one location to another location
Per Locn
c) Assembling and erection of towers including tightening of bolts and nuts including loading, unloading at store and site (Including the Wt. of stubs).
MT
1165
d) Rivetting of tower bolt ends by heating using dryAcetylene gas and hammering to destroy threads so as to make the tower members theft - proof (Bolts at nodal points only to be selected and rivetted up to hieght of bottom cross arm, as per the directions of the field engineer)
Per Bolt
6
e) Welding of bolts and nuts
Per Bolt
6
320
290
240
Sl No.
Description
Note : For tower erections requiring shutdown 25% above S.R. for item 5c to 5e only are to be adopted.
Unit
Rates as Proposed 2006-07 Amount in RS 220 KV
110 KV
66 KV
33 KV
Sl No.
6
Description
110 KV
66 KV
Per set
1140
Rmtr
21
a) Fixing Danger Board
Nos
22
b) Fixing Number Plate
Nos
22
c) Fixing Phase Plate
Set ( 3 Nos.)
66
d) Fixing Circuit plate
Nos
22
b) Supplying and fixing barbed wire as per specification
8
220 KV
33 KV
Supplying and fixing A.C. devices : a) Supplying and fixing G.I. Angle iron 45x45x5 mm (1mtr length) with cleats, bolt & nuts as per specification and fixing above 0.5 mtrs length each at inner and outer surface of the tower to facilitate running of barbed wire.
7
Unit
Rates as Proposed 2006-07 Amount in RS
Fixing of Boards
Stringing of Conductor without allowing the conductor to touch the ground and without damaging the conductor. a) Paving out conductor from anchor to anchor normally spaced at 5 spans with 4 tangent towers in between, including providing stays at each anchor points and jointing of conductors, hoisting and fixing of insulator string, armour rods, vibration dampers, including the cost of T&P materials like comealong, wire ropes, pulley, rollers, suspension clamps, compression jointing machines with bits, drum stands, manila ropes, truckker and jeep etc., (Rate for 1 route KM of single conductor) i) For hilly terrian
KM
11290
5645
5130 with coyote ACSR 5130 with Rabbit ACSR on Towers 1410 with Rabbit ACSR on RCC Poles
ii) For Plain terrian
KM
8685
4030
3760 with coyote ACSR 1880 with Rabbit ACSR on Towers 1130 with Rabbit ACSR on RCC Poles
b) I) Stringing of ground conductor as above i) For hilly terrian
KM
3765
2820
2510
ii) For plain terrian
KM
2820
2255
1880
Note: Conductors normally used are i) 220KV - Drake and AAAC Moose ii) 110KV - Lynx and Drake iii) 66 KV- Coyote and Drake
Sl No.
Description
Unit
Rates as Proposed 2006-07 Amount in RS 220 KV
110 KV
66 KV
33 KV
50% more above the rates specified for normal works is admissible for shut down works of 33KV and above lines, CTs, PTs, LAs only. This is not applicable for 11KV & L.T line shut down works.
II) For shut down works 50% more than the above rates of the work (This is applicable to shut down of 33KV and above lines only. 11KV & L.T. lines shut down not included)
III) For National Highway crossing railway crossing and State highway crossing
15%
IV) River crossing exceeding more than 20% of the normal span. This is applicable to stringing the lines running parallel to a charged circuit also.
corresponding normal span stringing rate + 30 % extra
V) Rates for 33 KV Stringing are separately indicated under SR for 33 KV works.(Crossing charges should not be allowed when shut down charges are admitted)
9
I
These Rates are applicable only when total Length of the entire Line is less than 3 spans. A) Stringing of conductors in special conditions where normal 5 spans between anchor to anchor are not encountered, whereas anchors are provided at single/two/three spans with average span intervals of 267/320 Mtrs, (rate for spans of single conductor) i) For hilly terrian a) Anchoring single span upto 320 mtrs.
1 Span
6285
3135
2685 with coyote ACSR 1315 with Rabbit ACSR
b) Anchoring 2 span interval upto 640 mtrs with 1 tangent tower only
2 Spans
7835
3910
3330 with coyote ACSR 1590 with Rabbit ACSR
c) Anchoring 3 span interval up to 960 mtrs with two tangent towers only
3 Spans
9425
4710
3905 with Coyote ACSR 1880 with Rabbit ACSR
ii) For plain terrian a) Anchoring single span up to 320 Mtrs
1 Span
4835
2190
b) Anchoring 2 span interval upto 640 Mtrs with 1 tangent tower only
2 Spans
6040
2810
c) Anchoring 3 span interval upto 960 Mtrs with two tangent towers only
3 Spans
7245
3385
B) Stringing of ground conductor as above i) for hilly terrian a) Anchoring single span upto 320 mtrs
2015 with coyote ACSR 970 with Rabbit ACSR 2580 with coyote ACSR 1190 with Rabbit ACSR 2890 with Coyote ACSR 1395 with Rabbit ACSR
1 Span
2080
1560
1355
b) Anchoring 2 span interval upto 640 mtrs with 1 tangent tower only
2 Spans
2605
1960
1615
c) Anchoring 3 Span interval upto 960 mtrs with two tangent towers only
3 Spans
3135
2355
1920
Sl No.
Description
Unit
Rates as Proposed 2006-07 Amount in RS 220 KV
110 KV
66 KV
33 KV
ii) For plain terrian a) Anchoring single span upto 320 Mtrs
1 Span
1575
1260
1020
b) Anchoring 2 span interval upto 640 Mtrs with 1 tangent tower only
2 Spans
1970
1560
1240
c) Anchoring 3 span interval upto 960 Mtrs with two tangent towers only
3 Spans
2370
1890
1460
1 Span
945
470
b) Anchoring 2 span interval upto 640 Mtrs with 1 tangent tower only
2 Spans
1565
780
c) Anchoring 3 Span interval up to 960 Mtrs with two tangent towers only
3 Spans
2355
1180
1 Span
725
330
b) Anchoring 2 span interval upto 640 Mtrs with 1 tangent tower only
2 Spans
1210
560
c) Anchoring 3 Span interval upto 960 Mtrs with two tangent towers only
3 Spans
1810
845
Note: 1) Conductors normally used are i) 220KV - Drake and AAAC Moose ii) 110KV - Lynx and Drake iii) 66 KV- Coyote and Drake 2) For Shut down works 50% more above the normal rates of respective works (This is applicable to shut down of 33KV and above lines only. 11KV & LT line shut down works not included). Rates for Short span stringing in Normal length of II the line of more than 3 spans comprising of short spans A) Stringing of conductors in special conditions where normal 5 spans between anchor to anchor are not encountered, where as anchors are provided at single/two/three spans with average span intervals of 275/320 Mtrs, (rate for spans of single conductor) i) For hilly terrian a) Anchoring single span upto 320 Mtrs
ii) For Plain terrian a) Anchoring single span upto 320 Mtrs
B) Stringing of ground conductor as above i) for hilly terrian a) Anchoring Single span upto 320 Mtrs
400 with coyote ACSR 195 with Rabbit ACSR 665 with Coyote ACSR 320 with Rabbit ACSR 975 wilth Coyote ACSR 470 with Rabbit ACSR 300 with Coyote ACSR 145 with Rabbit ACSR 490 with Coyote ACSR 240 with Rabbit ACSR 725 with Coyote ACSR 365 with Rabbit ACSR
1 Span
310
235
205
b) Anchoring 2 Span interval upto 640 Mtrs with 1 tangent tower only
2 Spans
520
390
325
c) Anchoring 3 span interval upto 960 mtrs with two tangent towers only
3 Spans
785
590
480
1 Span
235
190
155
b) Anchoring 2 span interval upto 640 Mtrs with 1 tangent tower only
2 Spans
395
395
250
c) Anchoring 3 span interval upto 960 Mtrs with two tangent towers only
3 Spans
670
475
365
ii) For Plain terrian a) Anchoring single span upto 320 Mtrs
Sl No.
10
Description
Clearing of bushes, branches of tree & Crops for erection of tower & Stringing of line for full corridor width. a) In thin Jungle b) In thick Jungle c) Removing grass/vegitation,bushes in station yard/premises including disposal of the same.
11
Unit
Rates as Proposed 2006-07 Amount in RS 220 KV
110 KV
66 KV
Per Km Per Km
1505
Sq. Mtr
5
Grounding of towers/Equipments
2260
Material + Labour
a) Grounding of towers including cost of 40mm dia 2.5 mm thick, class 'C' G.I. Pipe of 3 Mtrs length as per specifications, with 50X6 mm GI Flats 3 Mtr long, salt charcoal, including excavation charges.
Set
2080 + 400 = 2480
b) Grounding of towers/Equipments excluding the cost of G.I. Pipe/C.I. Pipe as per specifications with 50X6 mm G.I. Flat 3 Mtr Long (to be supplied departmentally). But salt & Charcoal to be supplied by contractor. The rates include excavation charges.
Set
545 + 400 = 945
c) Grounding of equipments by providing cast iron pipe of 100mm ID 13mm thickness, 2.75 Mtrs long with 2 part clamp out of G.I.Flat 50X6mm continuously welded alround the pipe using cast iron welding electrodes as per drawing including the cost of excavation (All materials to be supplied by the contractor)
Set
6810 + 400 = 7210
Per Loc
1480 + 920 = 2400
a) Erection, assembly and alignment of Station structure as per the directions of site Engineer.
MT
1355
b) Erection, alignment & assembly of fabricated steel lattice structure, pedestal structures & Mounting structures, for G.O.S., CTs, PTs LAs etc.,
MT
1025
Per MT/Mtr
22
MT
490
Litre Litre
1 1
iii) Filtration of oil using filter set of the contractor, to bring the insulation value to I.E. Specifications.
Litre
2
iv) Filtering Oil as above but with the filter set supplied by the board.
Litre
1
L/S L/S L/S
2260 4520 7535
Note : All the leads from earthmat & equipment should be connected to earth electrode through the GI Flat 50 x 6 mm of suitable length and welded as per specifications.
12
Supplying and fixing of counter poise earthing with G.I. Stranded wire where hard rock is encountered as per specifications. (including excavation charges).
13
Station Structures
14
Erection of Transformers a) Moving the Transformer to the plinth. Maximum allowable distance is 50 Mtrs. (More than 50 Mtrs. approval of the D(T) has to be obtained) b) i) Assembly of Transformer parts like bushings, radiators, filling oil into Tr. etc., for the total wt. of the Tr. ii) Filling oil to the power Tr. Conservator and radiator (for maintenance purpose only) -
For 5 MVA to 20MVA Tr. For 50 MVA & above with vaccum
c) Wiring of Transformer marshalling box, bucholtz relay, fixing Thermometer, OLTC upto control panel and assisting in testing and commissioning by RT/MT/Firm engineers i) 5MVA to 6.3/8 MVA Tr. ii) 10MVA to 20MVA Tr. iii) Above 20 MVA Tr.
33 KV
Sl No.
15 16 17
Description
Unit
Fabrication of Transformer railing and embedding in Transformer plinth. (Rails to be supplied by the Corporation) Fixing of H.T. fuse units & wiring Wiring Testing & Commissioning of Power Transformers
Rates as Proposed 2006-07 Amount in RS 220 KV
110 KV
66 KV
L/S
450
Per Set
525
33 KV
a. Wiring: Identification of wires, Ferruling crimping and termination of wires. Wiring of Protective Devices, Cooling fans, Oil flow Pumps, OLTC, RTCC
b.Testing: 1. Ratio Test 2. SC test 3. Excitation test 4. Magnetic Balance test 5. Vector group test 6. Induced High voltage test 7. OLTC operation 8. Protective Devices operation Checks 9. Stability Checks: For Differential & REFR protection.
18
12.5/20/3 8/10 100/ 1.5 MVA MVA 5/6.3 MVA Lump Sum 150 aaa aaa for Each MVA aaa 29585 59175 49310 aaa 32875
Erection of Breakers / 11KV Kiosks with CTs on Mounting Structures a) Breaker Erection, assembly, alignment & interpole wiring of breakers with its connected equipments including movement from the point of unloading to the point of erection.
Per Set
7985
6390
4790
1568 38355
1280 29585
960 29585
640 29585
3995
3195
1595
800
Set ( 3 Nos.)
480
400
320
240
Set ( 3 Nos.)
19725
9860
9860
9860
Set ( 3 Nos.)
9860
9860
9860
9860
b) Assisting in Testing and Commissioning
set set
3195
c) Testing & Commissioning: Wiring: Identification, Ferruling crimping and termination of wires in Breaker & Wiring up to control panel/Relay panels Testing: Test for insulation level, gas leakage, Testing for travel time, Trip and close timings. Local Trip close test, Remote trip and close test, Tripping through relays, operation of interlocks etc., 19
Erection of CTs and PTs a) Erection of CTs and PTs and wiring including movement from the point of unloading to the point of erection. b) Assisting in Testing and Commissioning
Set (3 Nos.)
Testing & Commissioning c) Current transformers:
Wiring: Indentification of wires ii) Ferruling iii) Crimping of lugs iv) Connections up to marshalling box & v) Control panel Tests: i) Insulation ii) Polarity iii) Ratio iv) Excitation i)
d) Potential transformers: wires
iii) Ratio
Wiring: i) Indentification of ii) Ferruling iii) Crimping of lugs iv) Connections up to marshalling box Tests: i) Insulation ii) Polarity
Sl No.
20
21
Description
Unit
Rates as Proposed 2006-07 Amount in RS 220 KV
110 KV
66 KV
33 KV
Erection, Testing & Commissioning of NCTs a) Erection of NCTs including movement from the point of unloading to the point of erection with grounding connections
Set
1280
1015
480
235
b) Assisting in Testing and Commissioning
Set
55
55
55
30
i) Upright ii) under hung
Set Set
3995 4795
3195 3995
1600 2400
480
b) Assisting in Testing and Commissioning i) Upright ii) under hung
Set Set
400 480
320 400
160 240
50
Set
800
480
240
120
Per Stack
160
125
95
40
9860
9860
9860
Erection of Isolators a) Assembly, Errection alignment and wiring including movement from the point of unloading to the point of erection.
Note: 1) Assisting in testing and commissioning for item no. 17 to 19 means contractors should provide labourers for testing and commissioning by RT/MT/Firm engineers. 2) Testing & Commissioning in item 17 & 20 means the testing will be carried out by the firms themself using their own testing equipments & staff in presence of the MRT staff who will witness the tests. 22
Erection of Lightning Arrestors Erection of Lightning arrestors and wiring including movement from the point of unloading to the point of erection
23 24 25
Fixing of Solid Core insulator Test & Commissioning: Capacitor Bank with reactors Control Cables and U.G. Cables a) Formation of Cable Duct i) Burnt brick/size stone/RCC Cable duct including form box, back filling the sides, removing the excess escavated soil, duct covering with RCC slabs.
Each
Cmt
ii) Supplying 300 mm dia 1.5" to 2" thick RCC Hume pipes including loading unloading, and transportation charges and laying at required level and gradient as per the direction of field engineer
As per Latest KPWD SR applicable to respective area
As per Latest KPWD SR applicable to respective area
b) Providing, laying and jointing PVC pipes conforming to IS 4085-1960, & 7634-1975, and approved makes with necessary specials such as collars, bends, Elbows, Tee, nipples, plugs with cuts and threads using jointing ring with solutions, wherever necessary as per the directions of the field engineer including all lead and lift. 25 mm dia (outer) 2mm to 2.5mm thick 32 mm dia (outer) 2mm to 2.5mm thick 63 mm dia (outer) 2mm to 2.5mm thick 75 mm dia (outer) 2mm to 2.5mm thick 90 mm dia (outer) 2mm to 2.5mm thick 110 mm dia (outer) 2mm to 2.5mm thick 140 mm dia (outer) 2mm to 2.5mm thick 160 mm dia (outer) 2mm to 2.5mm thick c) Supplying & Laying cable trays including welding fixing of supports
Mtr Mtr Mtr Mtr Mtr Mtr Mtr Mtr
As per Latest KPWD SR applicable to respective area
Material + Labour
i) Cable tray of 600mm width (Suitable for cable ducts of A, B & C type)
Rmtr
ii) Cable tray of 300mm width (Suitable for cable duct of D type)
Rmtr
205+ 100 = 305 Material + Labour 150 + 75 = 225
Sl No.
Description
d) Laying of control cables from equipments to control panels. e) Laying of 11 KV cables in existing trench/G.I. Pipe/Stoneware pipe/RCC Hume pipe using wooden / aluminium rollers as directed by KPTCL staff. i) Cables of Sizes 3Cx95 to 3Cx150 sqmm ii) Cables of sizes 3Cx185 to 3Cx240sqmm iii) Cables of sizes 3Cx300 to 3Cx400 sqmm iv) Cables of sizes 1Cx630 to 1Cx1000 sqmm
26
f) Fixing of pot heads for HT cable only i) Epoxy type ii) Heat Shrinkable/Cold Shrinkable/Pushon Control Panels
Unit
Rates as Proposed 2006-07 Amount in RS 220 KV
110 KV
66 KV
Rmtr
5
Rmtr Rmtr
25 25
Rmtr Rmtr
25 25
Nos Nos
1110 1445
a) Erection of control panel, auxilary panel, carrier cabinet etc., alignment and fixing properly to foundation base including movement from the point of unloading to the point of erection.
Per Panel
b) Wiring & assisting in testing and commissioning of panel.
Per Panel
2000
2000
1600
33 KV
1600
2500
c) Test & Commissioning: i) C& R Panels Wiring & Testing: Wiring: Identification, Ferruling, Crimping, termination of wires in C&R panels. Testing: Testing for insulation level Testing of relays, control operations for closing tripping etc., interlock. Alarm Annunciation & Indication Checks.
27
Each
39175
29585
29585
ii) Sychronising Trolley/Panel: Wiring, Testing, Calibration of meters & Testing for operation
Each
9860
iii) Bus Bar Protection Panel wiring & testing Wiring: Identification of wires, Ferruling, Crimping & termination of wires in Bus Bar protection Panel Testing: 1.Testing of relays. 2. Stability test.
Each
Rs. 9860 up to 3 Bays & Rs. 4930 for each additional bay
Per panel Per Panel
960 800
Per Panel Per Panel
320 320
Per set
49310
ii) For single 11KV panel indoor type iii) For additional 11KV panel (indoor type) iv) For single 11KV panel outdoor type/Kiosk
Each Each Each
9860 4930 9860
v) For each additional 11KV panel out door type/Kiosk
Each
7535
11 KV Switchgear a) Erection, alignment and fixing to the foundation, indoor/outdoor 11KV switchgear Panel/unit including movement from the point of unloading to the point of erection. i) 11KV Indoor/out door switchgear ii) 11KV Kiosk b) Wiring & assisting in testing & Commissioning i) 11 KV indoor/ outdoor switchgear ii) 11KV Kiosk c) Testing & Commissioning: Wiring: Identification of wires, Ferruling Crimping & Termination of wires for annunciation, etc., Testing of Relays, CTs, PTs, & Breaker for operation. i) For indoor/outdoor panel comprising of 2I+8F+1BC+1AP3
Note:Assisting in testing & Commissioning for item 22,24& 23 means contractors should provide labourers for wiring & Commissioning by RT/MT/Firm Engineers.
29585
Sl No.
28
Description
Busbar Formation
Main bus/cross bus (all the three phases in a segment) of using Falcon/Drake/Lynx/Coyote-single/double conductors with fixing of insulator spacers, levelling of string conductors to the required height above the equipment, including providing jumps to interconnect different segments of the main bus.(Spacers to be used only for Double Conductor)
29
220 KV
110 KV
66 KV
Per Bay
i) Falcon single conductor 4795/ii) Falcon double conductor 7190/iii) Single drake conductor 3835/iv) Double drake conductor 5755/v) Single Lynx conductor 3190/vi) Single Coyote conductor 3190/-
a) Laying of M.S. Flats, welding, applying ACB paint to welded portion and covering with sodium bentonite clay
Rmtr
16
b) (i) Supplying and laying of 50X6mm MS flat, welding and applying ACB paint to welded portion and covering with sodium bentonite clay, as per the drawing/standard specifications and consolidation.
Rmtr
175
ii) Same as above but without sodium bentonite clay
Rmtr
86
Per Point
160
d) Carrying out the work as detailed in item-c above, but all the materials supplied by the contractor
Rmtr
145
e) Providing 25mm dia M.S.rod 1.05 Mtr. Long earthmat spikes including heating, bending top 50mm over lap flattening and making spike edge at one end driving into the earth below the ground level and welding the rod with ground mat flat.
Each
125
f) Supplying & Providing 450 mm dia 450 mm height 1.5" to 2" thick hume pipe collar (non pressure type) for earth pits including all lead and lifts etc.,
Each
415
Rmtr Rmtr Kgs
330 260 7
Per joint
275
Providing Deep Bore earthing "Sinking bore of 150mm clear dia using fast rig including fixing of 40mm dia MS rod, including jointing the pipes as per KPTCL standard and providing sodium bentonite treatment in the annular space, including transportation of rig and other supporting vehicles etc., complete, as per the directions of engineer in charge, including cost of MS rod & sodium bentonite". a) Drilling 150mm dia bore b) 40 mm dia MS rod c) Bentonite Clay d) Cost of GI flat for joining two rods by welding to obtain continuous length
33 KV
Main/Cross bus with spacers(Spacers to be utilised only for Double Conductor ) using
Groundmat
c) Grounding of equipment with 50x6mm G.I. Flat and connecting Equipment to the earthmat/ground pit. Each point of earthing with all formation works like bending, twisting, drilling of holes and connecting by welding (inclusive of all T&P and consumables) to the earthmat/ ground pit/ point of earth connection.
30
Unit
Rates as Proposed 2006-07 Amount in RS
Sl No.
31
Description
Unit
Rates as Proposed 2006-07 Amount in RS 220 KV
110 KV
66 KV
33 KV
Spreading of Jelly Supplying and spreading 100mm thick with 20/25mm jelly with all lead and lifts. i) 20/25 mm Jelly Note : Only 20/25mm jelly shall be used.
32
Cmtr.
985
Per set
As per Latest KPWD electrical SR applicable to respective areas.
b) Supplying and fixing of Sodium Vapour lamp fittings of 250 watts.
Per fitting
As per Latest KPWD electrical SR applicable to respective areas.
c) Supplying and laying of 1.1KV, 6 Sqmm PVC cable or any other specified size, testing and commissioning of yard lights.
Rmtr
As per Latest KPWD electrical SR applicable to respective areas.
Station Yard Lightning a) Supplying and erection of fabricated supporting structures including foundation.
d) Erection of RCC poles with stringing of O.H. conductor/Laying of cable for yard lights. 33
34
Rates for different items as per ESCOM SR to be applied.
Painting of structures
Material + Labour
a) Supplying and painting of two coats of good quality Red Oxide primer after cleaning and scrapping the surface.
Sqmtr
15 + 20 = 35
b) As above with 2 coats of good quality Aluminium paint after2 coats of good quality Red Oxide primer.
Sqmtr
35 + 30 = 65
c) Supplying and painting two coats of aluminium paint after cleaning and scraping the surface wilthout applying Red Oxide primer
Sqmtr
15 + 17 = 32
d) As per (b) but with synthetic enamel paint
Sqmtr
35 + 35 = 70
e) Supplying and painting two coats of Synthetic enamel paint after cleaning and scraping the surface without aplying red oxide primer.
Sqmtr
22 + 15 = 37
Set Set Set
10385 3995 1595
Set Set Set
640 640 640
Battery Set and charger a) Installing, assembling, filling of acid, wiring, assisting, test-charging and discharging Battery set. i) 220 Volts ii) 110 Volts iii) 48/24 Volts b) Erection of Battery Charger and wiring i) 220 Volts ii) 110 Volts iii) 48/24 Volts c) Testing & Commissioning of Battery Charger: Wiring: Identification, Ferruling, Crimping & connecting i) AC Supply cable upto 2 sources ii) Load cables, connection at charger end upto 10 load points. Testing: i) AC supply voltage phase Sequence. ii) Testing of Output DC Voltages in Boost/ Float/ Trickle/ Variations as per the order/ requirement. iii) Testing for repel factor. Commissioning: i) Fixing of Boost Voltage level ii) Fixing of Float Voltage level iii) Fixing of Trickle Voltage level iv) Testing of alarm, indication and load ckts, Auto/Manual change overs etc. v) Full load test in Boost & Trickle modes. a) 220 V DC:
35
b) 110V DC: Fencing : Colony and Station yard Boundary fencing including erection of supports a) Security fencing using 8G chainlink/50mm Mesh b) Barbed wire fencing
Per set Per set
30135 19725
19725
19725
As per Latest KPWD SR applicable to respective areas
Sl No.
36
37
Description
110 KV
66 KV
33 KV
a) Erection of mounting structures for coupling capacitors
Set
2500
2500
2500
2500
b) Erection of Coupling capacitors/wave traps/LMU. c) Wiring , testing and commissioning
Set Set
5000 500
3995 430
1905 430
940 280
Cmt
As per Latest KPWD SR applicable to respective areas
Per Shift
112
Yard Levelling
Watch and Ward Emoluments for watch and ward including pay and DA for 8 hours duty
39
220 KV
PLCC Equipments
Yard Levelling and filling up of soil and consolidation. 38
Unit
Rates as Proposed 2006-07 Amount in RS
Transportation a) Transportation of Transformer, CT's, PT's, Breakers, C&R Panels, 11KV Switchgears and EHT LA's only. 1. Using 10 MT Lorry Rs.35/- per KM, subject to a Min. of Rs. 8220/-
i) 1 to 50 KMs ii) 51 to 100 KMs iii) 101 to 150 KMs iv) Beyond 150 KMs 2. Using 10 MT Truck & Trailor
Min + Rs. 27/- per KM Min + Rs. 20/- per KM Min + Rs. 13/- per KM Rs.35/- per KM, subject to a Min. of Rs. 16437/-
i) 1 to 50 KMs ii) 51 to 100 KMs iii) 101 to 150 KMs iv) Beyond 150 KMs 3. Using 11 to 20 MT Truck & Trailor.
Min + Rs. 27/- per KM Min + Rs. 20/- per KM Min + Rs. 13/- per KM Rs. 275/- per KM, subject to a Min. of Rs. 20546/-
i) 1 to 50 KMs ii) 51 to 100 KMs iii) 101 to 150 KMs iv) Beyond 150 KMs 4. Using 21 MT to 40 MT Truck & Trailor.
Min + Rs. 240/- per KM Min + Rs. 130/- per KM Min + Rs. 116/- per KM Rs. 308/-per KM, subject to a Min. of Rs. 24656/Min + Rs. 192/- per KM Min + Rs. 165/- per KM Min + Rs. 137/- per KM
i) 1 to 50 KMs ii) 51 to 100 KMs iii) 101 to 150 KMs iv) Beyond 150 KMs 5. Using 41 MT to 80 MT Truck & Trailor.
Rs. 308/-per KM, subject to a Min. of Rs. 27395/-
i) 1 to 50 KMs ii) 51 to 100 KMs iii) 101 to 150 KMs iv) Beyond 150 KMs 6. Using 81 MT to 120 MT Truck & Trailor.
Min + Rs. 192/- per KM Min + Rs. 165/- per KM Min + Rs. 137/- per KM Rs. 336/- per KM, subject to a Min. of Rs. 29568/-
i) 1 to 50 KMs
Rs. 336/- per KM, subject to a Min. of Rs. 29568/Min + Rs. 168/- per KM Min + Rs.146/- per KM
ii) 51 to 100 KMs iii) 101 to 150 KMs iv) Beyond 150 KMs Mobilisation charges of IDLE Transportation applicable for places where heavy duty trucks are not available, is admissible in addition to (a) as far as possible full load shall be transported. b) Transportation of other materials
Per KM
15
25% of the above
Sl.
c) Transportation by Head Load wherever there is no accessability for transportation by vehicle for transmission line works only. Rates as Proposed 2006-07 Steel,
Total Distance
Rough, size, cut Earth, Gravel, Latterite Stones, Sand, Lime & other Concrete Blocks Str.Mat. Rate per Rate per Cmt in Cmt in Rs. Cement, RS Per Ton in Rs.
1 Up to 50 Mtrs initial lead No
2
Beyond 50 Mtrs and upto 100 Mtrs
3
RCC Pole 300 Kg WL Rate per pole in Rs.
included in the item Rate
9
12
15
182
Beyond 100 Mtrs and upto 150 Mtrs
15
19
23
262
4
Beyond 150 Mtrs and upto 200 Mtrs
20
26
32
290
5
Beyond 200 Mtrs and upto 250 Mtrs
25
32
39
334
6
Beyond 250 Mtrs and upto 300 Mtrs
32
39
49
334
Page 17 of 23
Rate as Proposed 2006-07 No.
Discription
d) Using light vehicle including fuel, oil, lubricants and crew subject to a minimum of 100 Kms per day in case of break down/ subject to prior approval of CEE(MW). 40
41
220 KV
110 KV
66 KV
33 KV
Per Day
Prevailing Board approved Rates
a) Loading of Power Trs, CT's. PT's Breakers, C&R Panels, 11KV Switchgears, wavetrap, coupling capacitors, HT UG Cables, Insulators, ACSR Conductor, Ground Conductors, etc.,
MT
845
b) Unloading of power Transformers, CT's PT's Breakers, C&R Panels, 11 KV Switchgears, Wavetrap, coupling capacitors, HT UG Cables, Insulators, ACSR conductor, Ground conductors, etc.,
MT
845
c) Loading of other materials like structural steel, building materials etc.,
MT
150
d) Unloading of other materials like structural steel, building materials etc.,
MT
150
Cmt
As per latest KPWD, SR rates
No.
320
Set
575
Loading and Unloading
Benching, Revetment and Pitching Providing granite rough stone 30 to 50 cms thick dry packing of revetments and pitching side slopes of quadrant including providing the walls, jelly packing, 0.15 cms thick and wedging etc., Complete including cost of conveyance of all materials.
42
Unit
Labour for 66/33KV lines using 9/9.5 Mtrs Long RCC Poles a) Erection of 9/9.5 Mtrs RCC Poles 300 Kg working load, in the excavated pit as per the approved drawing specification (excluding the cost of excavation, backfilling and concreting) Note: The rates of excavation, Backfilling and concreting are to be adopted as noted in SL nos 3 and 4 respectively.
b) Erection of DP structure excluding cost of erection of RCC poles. Including fixing of braces insulators etc., as per the approved drawings and specifications (excluding the cost of excavation, backfilling and concreting). Note: The rates of excavation, Backfilling and concreting are to be adopted as noted in SL nos 3 and 4 respectively.
Rate as Proposed 2006-07 No.
Discription
Unit
220 KV
110 KV
66 KV
33 KV
c) Fixing of V-Shape cross arms, single top supports and insulators.
Set
65
40
d) Fixing of spiral earth electrodes e) Road/P&T Guarding
Set Set
50 430
50 400
KM KM
1160 830
1120 830
Nos.
96
96
RM tr
25
25
f) Stringing Rabbit conductor, fixing disc insulator to cross arms etc., i) For hilly terrain ii) For plain terrain g) Fixing of guy sets in the excavated pits using 7/9 or 7/10 SWG guy wire/turn buckle, guy rod break insulators, as per the approved drawings and specifications (excluding the cost of excavation, backfilling and concreting) Note : The rates of excavation, backfilling and concreting are to be adopted as noted in SL nos 2,3 and 4. h) supplying and fixing of AC devices as per specification 43
Dismantling Same rate as that of erection of Power Transformer
i) Dismantling of Power Transformer ii Dismantling charges for conctrete with steel reinforcement
Cmt
340
iii) Dismantling of concrete only
Cmt
165
iv) Dismantling charges in all other cases
75% of erection charges in general
Rate as Proposed 2006-07 No.
44
Discription
Unit
220 KV
110 KV
66 KV
Special Locality Allowance Following places are eligible for extra locality allowance against each items on labour charges a) Dakshina Kannada district Bantwal, Mangalore, Sulya, Puttur, Belthangady taluks.
35%
b) Udupi : Udupi, Kundapur, Karkala Tqs
35%
c) Uttara Kannada District : Karwar, Supa, Haliyal, Sirsi, Mundagodu, Yellapur, Bhatkal, Siddapur, Honnavar, Kumta Ankola Tqs.
35%
d) Kodagu District : Madikeri, Virajpet, Somarwarpet, Tqs.
35%
e) Chikkamagalur District : Kadur, Chikkamagalur, Koppal, Tarikere, Mudigere, Narasimharajapura, Sringeri Tqs.
25%
f) Shimoga District : i) Hosangar, Thirthahally, Sagar, Sorab, Shikarpur Tqs ii) Shimoga, Bhadravathi, Honnali Tqs g) Davangere District : Chennagiri Tq only h) Dharwad District i) Kalgatagi ii) Dharwad Tq i) Haveri District : i) Hangal, Herekerur ii) Bydagi, Shigaon, Savanur Tqs., j) Belgaum District i) Khanapura Tq
25% 15% 15% 25% 15% 25% 15% 25%
ii) Hukkeri, Belgaum, Bylahongal, Soundatti Taluk's only.
15%
k) Mysore District : Heggadadevanakote, Hunsur Tqs
25%
l) Chamarajanagar District : Gundlupet, Chamarajanagar, Kollegal Tqs
25%
m) Hassan District : Sakaleshpur, Hassan, Arakalagud, Belur, Alur, Taluks only.
25%
Note: 1) In case of civil works where KPWD SR rates are adopted, the locality allowance as applicable in KPWD SR shall be followed. 2) For all other works the locality allowance as indicated above shall be followed.
33 KV
Rates as Proposed 2006-07 Amount in RS Sl No.
45
Description
Unit
220 KV
110 KV
66 KV
1
Surveying of cable route excavation trial holes as per field requirements, preparation of cable route profile, drawings for cable laying, final route alignment, marking lines and grades, preparation of final cable route, drawings after laying and energising for preparing bill of materials.
Kms.
25,000
25,000
2
Excavation of earth for laying of single core EHT UG Cable Cables to a depth of 1.5 mtr including removing & refixing the Kerb & pavement stone slabs , removing and refixing masonry of other services with patch work. Depositing of the Earth on back with a lead 50 mtrs. including storing, structing, providing caution boards, danger lighting. in the following strata of soils. a) In ordinary soil
Cmt.
400
400
b) Black Cotton Soil c) Laterite Soil b) In Dry fissured rock. c) In hard rock with chistling and wedging
Cmt. Cmt. Cmt. Cmt.
500 600 1,000 1,500
500 600 1000 1500
Cmt.
500
500
b) Cutting as flat surface
Cmt.
600
600
c) Cutting cement concrete surface
Cmt.
1,000
1000
3
Cutting the roads surface cable trench & disposing of the excavation, as directed including barricading providing danger lighting boards etc., in the following classifications of road surfaces a) Cutting Macadan road surface
4
Laying EHT single core, . XLPE copper cable in trefoil, tapping, fixing pipes for drain and gate crossing as per drawings & specifications in trench pipes, ducts by pulling, drawing etc., including transport, handling of cable drums, paving out cables using standard cable installation equipments. NOTE: The quoted rate per km shall include laying one circuit per km each circuits consisting of 3 Nos. Single core cables including transport of cable drums material, equipments to site and retaining unused items to stores.
KM/Ckts. 12,00,000
4,00,000
5
Handling and spreading riddled/sleved sand in the cable trench, forming cushion & cover around cable.
Cmt.
800
800
6
Handling and covering the cables in the trench with RCC protection covers (Slabs)
Nos.
300
300
33 KV
Rates as Proposed 2006-07 Amount in RS Sl No.
Description
Unit
220 KV
110 KV
66 KV
7
Back filling the cable trench, with selected available ridded earth from the trench excavation & consolidating with ramming in successive layers of 15 Cmts. Thickness watering wherever necessary,achieve 95 % protective density forming a crown for subsidence, including supply and laying in the trench PVC warming tape.
Cmt.
400
400
8
Disposing the surplus earth, debris, debris of excavation, after back filling including handling and transporting with max. lead of 12 to 15 Kms.
Cmt.
700
700
9
Handling and making normal straight joints for EHV power cables with all consumables at site etc., complete.
Nos.
1,00,000
20,000
10
Handling and making of cables end termination for EHV single core XLPE copper cable.
Nos.
1,25,000
20,000
11
Erection of supporting structure for EHV cable end terminations fixing cable with termination using suitable clamps fixtures connecting earth lead etc., complete.
Nos.
10,000
5,000
12
Erection of special cable terminating structure for EHV Cable
Nos.
13
Erection of single phase earth link boxes on to the cable mounting structure connecting earth leads with all lugs, fixtures, clamps bolts, and nuts complete.
Nos.
15,000
15,000
Nos.
1,000
1,000
Mtrs.
2,000
2,000
14 15
Handling and fixing of cable joints/route marking blocks on cable route. Thermal Backfill, design, source , procure and provide suitable thermal backfill + NTR value 120 degree.
1,25,000
33 KV
Rates as Proposed 2006-07 Amount in RS Sl No.
Description
Unit
220 KV
110 KV
66 KV
16
FOUNDATION: Engineering supply of all labours, materials and construction of RCC footings of any depth, pedestals including the cost of Excavation, concreteing, cement reinforcement steel for all the works, grouting under pinning etc., for EHV cable end terminations structure.
Nos.
50,000
17
JOINT BAYS: Designing and providing RCC joint bay to accommodate jointing of 3 Nos. of single core XLPE, UG cable. The construction shall be side walls of 15 Cms. thick with necessary reinforcement as per design and directions including providing RCC floor slab on PCC, 1:4:8, 100 mm thick, as per the design and directions including excavation, backfilling with sieved sand, the RCC shall be plastered in CM 1:4 12 mm thick. The RCC protections slab/cover shall be provided as per design.
Nos.
2,00,000
1,25,000
18
CABLE DUCTS: Including road crossings design of cable, crossing arrangement at strom water drain. The arrangment shall accommodate crossing of 3 Nos. of EHV. XLPE UG cable. The design supply and erection includes, RCC masonary, abutment, wall foundation and construction of cable duct, complete with all supplies and works.
Rmtr.
15,000
15,000
19
STORM WATER DRAINS: Design and providing crossing arrangment at strom water drain supply pipe line. The arrangement shall accommodate crossing of 3 Nos. of single core EHV XLPE UG cable .
Rmtr.
9000
9,000
20
CONCRETE: Providing and laying granite jelly cement 1:2:4 using 20mm and down size granite jelly and clean sieved sand including machine mixing, laying taping, curing and smooth finixhing for exposed faces and with necessary centering and form works etc., complete.
Cmt.
6,000
6,000
33 KV