Construction Materials and Management Solutions for Volume : I Classroom Practice Questions Chapter- 3
Chapter- 5
Introduction to Project Management
07. Sol: a)
Ans: 13 weeks
13. Ans: (a) t 4t L t P Sol: t E o 6 8 4 9 13 = 9.5 6 2 2 t p t o 13 82 2 Variance, 6 6 25 2 36
A B Activity C D E F G H 0 2 4 6
PERT
8 10 12 13 14
Time (weeks)
29. Sol: (a)
Total completion time of period = 13 weeks
Chapter- 4 Elements of Networks 12. Sol:
1
A B C
13. Sol:
1
2 D 4 3
A B C
ACE Engineering Publications
F
(b) 5
E 30. Sol: a)
3 D 2 4
5 E
Ans: 50% & 95.2%
TE = 24 month = 3.6 T TE Z= S 24 24 Z 0 3.6 From table probability = 50% 30 24 3. 6 Z = 1.67 From table probability = 95.2% Z
Ans: 65.76 & 58.25 weeks
TE = 60 weeks
2 = 20.25
P (%) = 90 % Z = 1.28
Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag |Tirupati | Kukatpally| Kolkata
:2:
Critical path:
variance 20.25
Std deviation =
1–2–5 = 1–2–4–5= 1–3–4–5= 1–3–5 =
= 4.5
1.28
TS TE 4.5
TS = 65.76 weeks
10 + 7 10 + 9 + 11 9 + 8 + 11 9+5
= 17 = 30 = 28 = 14
Critical path = 1 – 2 – 4 – 5 TE = 30 days; TS = 36 days
b)
31.
Solutions for Additional Syllabus
P(%) = 35% For P(%) = 35 % From table, Z = 0.387 T TE 0.387 s 4.5 TE = weeks = 58.25 weeks
TS TE To calculate :-
Ans: 90.32%
36 30 = 1.27 ≃ 1.3 4.69 From the table Z = 1.3 probability = 90.32 %
Z=
2 of critical path
2 = 4 + 9 + 9 = 22 = Z=
t 4t L t P tE = o 6
Sol:
6-9-18 10 1 9 5-8-17
2
tp to = 6
2
4-7-10 7 4-10-22 4 11 5 2-5-8
2
9 4-7-22 4-7-16 8 3
22 = 4.69
Chapter- 6 CPM 5
27. Ans: (c) Sol: 1
TE =1
TE =4
1
3
4
4
TE =0
Activity 1-2 1-3 2-4 3-4 2-5 4-5 3-5
to tL tP 6-9-18 5-8-17 4-7-22 4-7-16 4-7-10 4-10-22 2-5-8
ACE Engineering Publications
tE 10 9 9 8 7 11 5
2 4 4 9 4 1 9 1
6
5
1 4
TE =4
2
TE =11
2 4
5 TE =9
Earliest start time for activity 5 6 = 9 days
Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag |Tirupati | Kukatpally| Kolkata
:3: 12. Ans: (c)
29. Ans: (c) TE =5 Sol: B
Sol: From the data given, the maximum time for
TL =8
5 TE =0 6
the project is 11 days and minimum time is
4
TE =6
A TL =0
Solutions for Additional Syllabus
TE =18
TE =12 6
C TL =6
D TL =12
6
TE =9 3
9 days.
F TL =18 7
E
For 11 days, the total direct cost is: 800 + 1200 + 500 = 2500 units.
TL =11
For 10 days, the total direct cost is: FT(AB) = LST EST EST = 0 LST = 8 5 = 3 FT(AB) = 3 FT(CE) = LST EST = (11 3) 6 = 2 FFEF TEj TEi t ij
= 18 9 7 =2
800 + 1350 + 500 = 2650 units. For 9 days, the total direct cost is: 900 + 1500 + 500 = 2900 units. The feasible range of total direct cost varies from 2500 to 2900.
Chapter- 7 CPM Cost Analysis
13. Ans: (a) Sol: From the given diagram, on the 21st & 22nd day three concurrent activities are there with a total resources of 6 + 7 + 9 = 22.
11. Ans: (a) Sol: 9th
Parallel Activities A
Total Resource Load 6
11th
A+B
6 + 4 = 10
13th
A + B+ D
6 + 4 + 7 = 17
A+B+C+D
6 + 4 + 3 + 7 = 20
Week
th
15
Minimum resource occurs when only one activity exists. In the present case it is 6 per day. Maximum resources is 22 and minimum is 6
From the above, the maximum resource load per week is 20
ACE Engineering Publications
Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag |Tirupati | Kukatpally| Kolkata