Construction-materials-and-management.pdf

  • Uploaded by: bharani tharan
  • 0
  • 0
  • October 2019
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Construction-materials-and-management.pdf as PDF for free.

More details

  • Words: 810
  • Pages: 4
Construction Materials and Management Solutions for Volume : I Classroom Practice Questions Chapter- 3

Chapter- 5

Introduction to Project Management

07. Sol: a)

Ans: 13 weeks

13. Ans: (a) t  4t L  t P Sol: t E  o 6 8  4  9  13  = 9.5 6 2 2  t p  t o   13  82  2    Variance,      6   6  25 2  36

A B Activity C D E F G H 0 2 4 6

PERT

8 10 12 13 14

Time (weeks)

29. Sol: (a)

Total completion time of period = 13 weeks

Chapter- 4 Elements of Networks 12. Sol:

1

A B C

13. Sol:

1

2 D 4 3

A B C

ACE Engineering Publications

F

(b) 5

E 30. Sol: a)

3 D 2 4

5 E

Ans: 50% & 95.2%

TE = 24 month  = 3.6 T  TE Z= S  24  24 Z 0 3.6 From table probability = 50% 30  24 3. 6 Z = 1.67 From table probability = 95.2% Z

Ans: 65.76 & 58.25 weeks

TE = 60 weeks 

2 = 20.25

P (%) = 90 %  Z = 1.28

Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag |Tirupati | Kukatpally| Kolkata

:2:

Critical path:

variance  20.25

Std deviation =

1–2–5 = 1–2–4–5= 1–3–4–5= 1–3–5 =

 = 4.5

1.28 

TS  TE 4.5

TS = 65.76 weeks

10 + 7 10 + 9 + 11 9 + 8 + 11 9+5

= 17 = 30 = 28 = 14

Critical path = 1 – 2 – 4 – 5 TE = 30 days; TS = 36 days

b)

31.

Solutions for Additional Syllabus

P(%) = 35% For P(%) = 35 % From table, Z =  0.387 T  TE  0.387  s 4.5 TE = weeks = 58.25 weeks

TS  TE  To calculate  :-

Ans: 90.32%

36  30 = 1.27 ≃ 1.3 4.69 From the table Z = 1.3  probability = 90.32 %

Z=

 2 of critical path

 2 = 4 + 9 + 9 = 22  = Z=

t  4t L  t P tE = o 6

Sol:

6-9-18 10 1 9 5-8-17

2

 tp  to  =   6

  

2

4-7-10 7 4-10-22 4 11 5 2-5-8

2

9 4-7-22 4-7-16 8 3

22 = 4.69

Chapter- 6 CPM 5

27. Ans: (c) Sol: 1

TE =1

TE =4

1

3

4

4

TE =0

Activity 1-2 1-3 2-4 3-4 2-5 4-5 3-5

to tL  tP 6-9-18 5-8-17 4-7-22 4-7-16 4-7-10 4-10-22 2-5-8

ACE Engineering Publications

tE 10 9 9 8 7 11 5

2 4 4 9 4 1 9 1

6

5

1 4

TE =4

2

TE =11

2 4

5 TE =9

 Earliest start time for activity 5  6 = 9 days

Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag |Tirupati | Kukatpally| Kolkata

:3: 12. Ans: (c)

29. Ans: (c) TE =5 Sol: B

Sol: From the data given, the maximum time for

TL =8

5 TE =0 6

the project is 11 days and minimum time is

4

TE =6

A TL =0

Solutions for Additional Syllabus

TE =18

TE =12 6

C TL =6

D TL =12

6

TE =9 3

9 days.

F TL =18 7

E

For 11 days, the total direct cost is: 800 + 1200 + 500 = 2500 units.

TL =11

For 10 days, the total direct cost is: FT(AB) = LST EST EST = 0 LST = 8 5 = 3 FT(AB) = 3 FT(CE) = LST  EST = (11 3)  6 = 2 FFEF   TEj  TEi  t ij





= 18 9 7 =2

800 + 1350 + 500 = 2650 units. For 9 days, the total direct cost is: 900 + 1500 + 500 = 2900 units. The feasible range of total direct cost varies from 2500 to 2900.

Chapter- 7 CPM Cost Analysis

13. Ans: (a) Sol: From the given diagram, on the 21st & 22nd day three concurrent activities are there with a total resources of 6 + 7 + 9 = 22.

11. Ans: (a) Sol: 9th

Parallel Activities A

Total Resource Load 6

11th

A+B

6 + 4 = 10

13th

A + B+ D

6 + 4 + 7 = 17

A+B+C+D

6 + 4 + 3 + 7 = 20

Week

th

15

Minimum resource occurs when only one activity exists. In the present case it is 6 per day.  Maximum resources is 22 and minimum is 6

From the above, the maximum resource load per week is 20

ACE Engineering Publications

Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag |Tirupati | Kukatpally| Kolkata

More Documents from "bharani tharan"