COMPLETED AIRPORT PROJECTS August 15, 2007

Location Clearfield-Lawrence Township Airport

Owner

Bradford Regional Airport DuBois-Jefferson County Airport

Clearfield-Lawrence Township Joint Airport Authority Bradford Regional Airport Authority Bradford Regional Airport Authority DuBois-Jefferson County Airport Authority

Connellsville Airport

Fayette County Airport Authority

DuBois-Jefferson County Airport

DuBois-Jefferson County Airport Authority

Bradford Regional Airport

Project Description Replace VASI Runway 12-30 with PAPI Rehabilitate Runway 14-32 Lighting Runway 32 Safety Area Improvements New Access Road and Parking Lot Relocate Runway 14 & Runway 32 Thresholds Expand Snow Removal Equipment Building

Contract Amount $67,730.00 $166,719.00 $30,300.00 $105,000.00 $59,120.00 $17,225.00