PAYMENT PLAN & SCHEDULE AT THE TIME OF BOOKING
25 % OF ABOVE COST
AT THE TIME OF INITITION & AGREEMENT
10 % OF ABOVE COST
AT THE COMPLETION OF PLINTH LEVEL
8 % OF ABOVE COST
AT THE COMPLETION OF GROUND FLOOR SLAB
8 % OF ABOVE COST
AT THE COMPLETION OF 1ST FLOOR SLAB
8 % OF ABOVE COST
AT THE COMPLETION OF 2ND FLOOR SLAB
8 % OF ABOVE COST
AT THE COMPLETION OF 3RD FLOOR SLAB
8 % OF ABOVE COST
AT THE COMPLETION OF 4TH FLOOR SLAB
8 % OF ABOVE COST
AT THE COMPLETION OF ELEVATION Treatment
8 % OF ABOVE COST
AT THE COMPLETION OF BRICKWORK
3% OF ABOVE COST
AT THE COMPLETION OF PLASTERING WORK
3 % OF ABOVE COST
AT THE COMPLETION OF FINISHING & POSSESSION
3 % OF ABOVE COST
PAYMENT PLAN & SCHEDULE AT THE TIME OF BOOKING
25 % OF ABOVE COST
AT THE TIME OF INITITION & AGREEMENT
10 % OF ABOVE COST
AT THE COMPLETION OF PLINTH LEVEL
7 % OF ABOVE COST
AT THE COMPLETION OF GROUND FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 1ST FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 2ND FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 3RD FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 4RT FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 5 TH FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF ELEVATION TREATMENT
7 % OF ABOVE COST
AT THE COMPLETION OF BRICKWORK
3% OF ABOVE COST
AT THE COMPLETION OF PLASTERING WORK
3 % OF ABOVE COST
AT THE COMPLETION OF FINISHING & POSSESSION
3 % OF ABOVE COST
INFRATECH REALESTATE PVT LTD
PAYMENT PLAN & SCHEDULE AT THE TIME OF BOOKING
25 % OF ABOVE COST
AT THE TIME OF INITITION & AGREEMENT
10 % OF ABOVE COST
AT THE COMPLETION OF PLINTH LEVEL
7 % OF ABOVE COST
AT THE COMPLETION OF GROUND FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 1ST FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 2ND FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 3RD FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 4RT FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 5 TH FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF ELEVATION TREATMENT
7 % OF ABOVE COST
AT THE COMPLETION OF BRICKWORK
3% OF ABOVE COST
AT THE COMPLETION OF PLASTERING WORK
3 % OF ABOVE COST
AT THE COMPLETION OF FINISHING & POSSESSION
3 % OF ABOVE COST
INFRATECH REALESTATE PVT LTD
PAYMENT PLAN & SCHEDULE AT THE TIME OF BOOKING
25 % OF ABOVE COST
AT THE TIME OF INITITION & AGREEMENT
10 % OF ABOVE COST
AT THE COMPLETION OF PLINTH LEVEL
8 % OF ABOVE COST
AT THE COMPLETION OF GROUND FLOOR SLAB
8 % OF ABOVE COST
AT THE COMPLETION OF 1ST FLOOR SLAB
8 % OF ABOVE COST
AT THE COMPLETION OF 2ND FLOOR SLAB
8 % OF ABOVE COST
AT THE COMPLETION OF 3RD FLOOR SLAB
8 % OF ABOVE COST
AT THE COMPLETION OF 4TH FLOOR SLAB
8 % OF ABOVE COST
AT THE COMPLETION OF ELEVATION Treatment
8 % OF ABOVE COST
AT THE COMPLETION OF BRICKWORK
3% OF ABOVE COST
AT THE COMPLETION OF PLASTERING WORK
3 % OF ABOVE COST
AT THE COMPLETION OF FINISHING & POSSESSION
3 % OF ABOVE COST
PAYMENT PLAN & SCHEDULE AT THE TIME OF BOOKING
25 % OF ABOVE COST
AT THE TIME OF INITITION & AGREEMENT
10 % OF ABOVE COST
AT THE COMPLETION OF PLINTH LEVEL
7 % OF ABOVE COST
AT THE COMPLETION OF GROUND FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 1ST FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 2ND FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 3RD FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 4RT FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 5 TH FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF ELEVATION TREATMENT
7 % OF ABOVE COST
AT THE COMPLETION OF BRICKWORK
3% OF ABOVE COST
AT THE COMPLETION OF PLASTERING WORK
3 % OF ABOVE COST
AT THE COMPLETION OF FINISHING & POSSESSION
3 % OF ABOVE COST
PAYMENT PLAN & SCHEDULE AT THE TIME OF BOOKING
25 % OF ABOVE COST
AT THE TIME OF INITITION & AGREEMENT
10 % OF ABOVE COST
AT THE COMPLETION OF PLINTH LEVEL
7 % OF ABOVE COST
AT THE COMPLETION OF GROUND FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 1ST FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 2ND FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 3RD FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 4RT FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 5 TH FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF ELEVATION TREATMENT
7 % OF ABOVE COST
AT THE COMPLETION OF BRICKWORK
3% OF ABOVE COST
AT THE COMPLETION OF PLASTERING WORK
3 % OF ABOVE COST
AT THE COMPLETION OF FINISHING & POSSESSION
3 % OF ABOVE COST
PAYMENT PLAN & SCHEDULE AT THE TIME OF BOOKING
25 % OF ABOVE COST
AT THE TIME OF INITITION & AGREEMENT
10 % OF ABOVE COST
AT THE COMPLETION OF PLINTH LEVEL
7 % OF ABOVE COST
AT THE COMPLETION OF GROUND FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 1ST FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 2ND FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 3RD FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 4RT FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 5 TH FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 6TH FLOOR
7 % OF ABOVE COST
AT THE COMPLETION OF BRICKWORK
3% OF ABOVE COST
AT THE COMPLETION OF PLASTERING WORK
3 % OF ABOVE COST
AT THE COMPLETION OF FINISHING & POSSESSION
3 % OF ABOVE COST
INFRATECH REALESTATE PVT LTD
PAYMENT PLAN & SCHEDULE AT THE TIME OF BOOKING
25 % OF ABOVE COST
AT THE TIME OF INITITION & AGREEMENT
10 % OF ABOVE COST
AT THE COMPLETION OF PLINTH LEVEL
7 % OF ABOVE COST
AT THE COMPLETION OF GROUND FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 1ST FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 2ND FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 3RD FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 4RT FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 5 TH FLOOR SLAB
7 % OF ABOVE COST
AT THE COMPLETION OF 6TH FLOOR
7 % OF ABOVE COST
AT THE COMPLETION OF BRICKWORK
3% OF ABOVE COST
AT THE COMPLETION OF PLASTERING WORK
3 % OF ABOVE COST
AT THE COMPLETION OF FINISHING & POSSESSION
3 % OF ABOVE COST