CIVILIZED SOLUTIONS, INC
Executive Team Members Seth Tibbitts: Principal In Charge Brandon Simms: Project Manager Ben Frison: Project Engineer Michael Schector: Project Engineer “Because everyone needs some stability in their lives”
Overview Founded in 1996 An engineering design and consulting firm 3400 N. Charles St (Latrobe Hall) Baltimore, MD 21218 410 – 516 – 1234
[email protected]
Proposal Outline Restoration
of the Historic Leigh Street Armory
Construction
Building
of the New Office
Armory Restoration Provide
bracing to maintain historic façade Replace structural masonry system with a steel moment frame load resisting system Install an open web steel joists floor system to support the concrete floor slab Restore all masonry walls as non-structural elements Replace all doors and windows Install new steel roof truss system to maintain original building aesthetics while improving structural integrity Comply with Current Code Requirements
Armory History Built
in 1895
Served
as headquarters for the First Battalion Virginia Volunteers Infantry, Richmond’s first African American regiment
Used
as a social center, housing facility, recreation hall, elementary school, junior and high school
Temporary Bracing
Load Cases Loads • Live loads: office, residential, corridor, storage • Roof Live Loads: Non-pedestrian roof • Wind Loads • Snow Loads • Seismic Loads
Foundation Live Loads
First Floor Live Loads
Second Floor Live Loads
Load Cases Loads • Live loads: office, residential, corridor, storage • Roof Live Loads: Non-pedestrian roof • Wind Loads • Snow Loads • Seismic Loads
Load Cases Loads • Live loads: office, residential, corridor, storage • Roof Live Loads: Non-pedestrian roof • Wind Loads • Snow Loads • Seismic Loads
Wind Loads
Load Cases Loads • Live loads: office, residential, corridor, storage • Roof Live Loads: Non-pedestrian roof • Wind Loads • Snow Loads • Seismic Loads
Frame Design Steel
Moment Frame
– Does not interfere with Building Function – Reduce member size and longer spans – Reduction in Construction Time Member
Placement
Member Placement
Floor Joist System: Open Web Steel Joist Long
Spans Light Weight System Lack of Large Concentrated Live Loads Thinner Concrete Floor Slab
Roof System Retained
Historic Hip and Gable roof
shape Replaced old wood Hip members with Steel
Picture of Roof System
Renovating the Armory Cleaning
the façade Managing Efflorescence (phosphoric acid) Examining Joints and Sealants Attaching lintel sections at each floor slab for additional lateral support
Current Code Requirements Structural Fire
Safety Accessibility
New Office Building Construct
a 61’x60’ 4-story office building in lot adjacent to Armory Create exterior façade to complement the Armory Provide Structural Steel Moment Frame Support System Install an open web steel joists floor system to support the concrete floor slab Comply with Code Requirements
Layout and Load Cases Layout of New Building Loads • Live loads: office and corridor • Roof Live Loads: Non-pedestrian roof • Wind Loads • Snow Loads • Seismic Loads
First Floor
Second - Fourth Floor
Roof Loads
Layout and Load Cases Layout of New Building Loads • Live loads: office and corridor • Roof Live Loads: Non-pedestrian roof • Wind Loads • Snow Loads • Seismic Loads
Wind Loads
Layout and Load Cases Layout of New Building Loads • Live loads: office and corridor • Roof Live Loads: Non-pedestrian roof • Wind Loads • Snow Loads • Seismic Loads
Frame Design Steel
Moment Frame
– Does not interfere with Building Function – Reduce member size and longer spans – Reduction in Construction Time Member
Placement
Floor Joist System: Open Web Steel Joist Long
Spans Light Weight System Lack of Large Concentrated Live Loads Thinner Concrete Floor Slab
Primary Envelope Design
Envelope: Prelim Data Richmond,
Virginia: 43 inch rainfall, 70 percent humidity Architectural Issues – Parapets – Ornate Brickwork bands – Wooden Windows – Efflorescence issues
Exterior Cavity Wall System with CMU
Image modified and extracted from www.masonrysystems.org
Why CMU over Steel Stud System?
System at each Floor
Engineering the Barriers: All in One Thermal:
Steel Lintel Issue
Water:
Warm-In-Winter side, Perm-ABarrier
Air:
Warm In Winter side
Vapor:
None.
• Temperate Climate • 8,000 degree-days
Code Requirements Structural Fire
Safety Accessibility
Project Timeline Investigation
~ 1 week Schematic Design ~ 1 week Design Development ~ 1 week Construction Document ~ 3 weeks Construction Administration ~ 23 months
Project Budget Estimated Total Project Cost : $ 5 million •
Armory Restoration ~ $ 2 million
•
New Building ~ $ 3 million
•
CS, Inc Schematic Design ~ $12,205
Conclusion Efficiency
– Our structure uses an intelligent moment frame design coupled with a smart open webbed joist floor system. Economical
– This will minimize material cost, saving money. The quick erection time shall reduce capital cost. Elegance
– Our Armory will maintain the authenticity of its historic fortress like appearance, and the New Building shall complement the aesthetic mastery of the Armory.
Thank You For Your Time Civilized Solutions, Inc “Because everyone needs some stability in their lives”
Specifications Mortar:
Low Alkali Cement (3/8”) Bed & Head Joint Expansion Joints: ¾ inch, rubber, located every 20 ft Veneer Support: Pintel Tie Rows 16” vertically, 24” spacing zinc coated Bond Beams: < #8 (US) Steel Lintels: TBD Water Barrier: > 5 perms Perm-a-Barrier
Plan View of Concrete Detailing
Roofing Detailing
Foundation for Cavity Wall
Windows