EUROCONTROL CFMU

CFMU RELEASES DEPLOYMENT PLAN Planned for Implementation in 2008 - 2009

CFMU RELEASES DEPLOYMENT PLAN

PLANNED FOR IMPLEMENTATION In 2008/2009

Edition N°: 1.5 http://www.cfmu.eurocontrol.int

Amendment date: 01 Dec. 2008

Edition 1.5 Edited & produced by the CFMU/User Relations and Development Bureau ©2008 European Organisation for the Safety of Air Navigation (EUROCONTROL)

CFMU_Releases_DP_1.5

i

©2008 European Organisation for the Safety of Air Navigation (EUROCONTROL). All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any form or by any means, electronic, mechanical, photocopying, recording or otherwise, without the prior permission of EUROCONTROL.

Edition No. Edition Issue date File name Number of pages

Amendment date: 01 Dec. 2008

: : : :

1.5 01 December 2008 CFMU RELEASES DEPLOYMENT PLAN 10

Edition 1.5 Edited & produced by the CFMU/User Relations and Development Bureau ©2008 European Organisation for the Safety of Air Navigation (EUROCONTROL)

CFMU_Releases_DP_1.5

ii

EUROCONTROL CFMU

CFMU RELEASES DEPLOYMENT PLAN Planned for Implementation in 2008 - 2009

TABLE OF CONTENTS 1.

INTRODUCTION .......................................................................................................................5

2.

MILESTONES ...........................................................................................................................5

3.

LIST OF SERVICES..................................................................................................................5

4.

DEPLOYMENT PLAN...............................................................................................................6

4.1.

CFMU Data Distributions to AOs............................................................................................6

4.2.

CIAM .........................................................................................................................................6

4.3.

eRAD via EAD ..........................................................................................................................7

4.4.

CCAMS .....................................................................................................................................7

4.5.

Interactive NOP........................................................................................................................7

4.6.

Set-Up of the UUP Process.....................................................................................................8

4.7.

Scenario Handling (Regulations) ...........................................................................................8

4.8.

Refine Delay Allocation...........................................................................................................9

4.9.

Download Static Data..............................................................................................................9

4.10.

Web Services for AROs Briefing ............................................................................................9

4.11.

CHMI Services – Occupancy Monitoring Values – PEAK and SUSTAINED........................9

5.

RECOMMENDATION .............................................................................................................10

Amendment date: 01 Dec. 2008

Edition 1.5 Edited & produced by the CFMU/User Relations and Development Bureau ©2008 European Organisation for the Safety of Air Navigation (EUROCONTROL)

CFMU_Releases_DP_1.5

iii

INTENTIONALLY LEFT BLANK

Amendment date: 01 Dec. 2008

Edition 1.5 Edited & produced by the CFMU/User Relations and Development Bureau ©2008 European Organisation for the Safety of Air Navigation (EUROCONTROL)

CFMU_Releases_DP_1.5

iv

CFMU RELEASES DEPLOYMENT PLAN

EUROCONTROL CFMU

1.

Planned for Implementation in 2008 - 2009

INTRODUCTION The purpose of this document is to inform CFMU Users about the deployment schedule of the different services to be delivered with the CFMU releases. For each new service, the following are described: • Stakeholders, i.e. the categories of CFMU Users recipients of the new service. •

Operational deployment date, i.e. the availability date of the new service for operational use.



Documentation publication, i.e. the date of initial publication of the user documentation, and the associated location.



Training sessions, i.e. the training dates, and the related links for access.



Users’ validation, i.e. the sessions organised to assess the new service, in the framework of either an OPT (Operational Testing) session or a Pilot Phase.

A more detailed description of the functions can be found in the CFMU Releases Notes available on the CFMU Web Site: http://www.cfmu.eurocontrol.int/cfmu/public/site_preferences/display_library_list_publi c.html

2.

MILESTONES The major milestones of the CFMU Release deployments are the following: • CFMU_12.1: May 2008.

3.



CFMU_12.2:

October 2008.



CFMU_13.0:

April 2009.

LIST OF SERVICES The services to be deployed in the framework of the next CFMU Release are: • CFMU Data Distributions to AOs: ETFMS Data are distributed to Aircraft Operators during the flight’s life cycle.

Amendment date: 01 Dec. 2008



CIAM: the CHMI interface available to Airspace Managers.



eRAD via EAD: the publication of the eRAD through EAD/SDO in AIXM 4.5/XML format.



CCAMS for Operational Evaluation: the Centralised SSR Code Assignment and Management System will provide increased efficiency in the SSR code management and the ability to provide the flights with SSR codes for the entire operations.



Interactive NOP: will provide access to the Network Operations Plan via the CFMU Web Site (through a new interface: the NOP Portal).



Preparation of the UUP Process: CFMU systems will be able to accept Route and Airspace Status modifications after the publication of the CRAM. Edition 1.5 Edited & produced by the CFMU/User Relations and Development Bureau ©2008 European Organisation for the Safety of Air Navigation (EUROCONTROL)

CFMU_Releases_DP_1.5

5

EUROCONTROL CFMU •



• • •

4.

CFMU RELEASES DEPLOYMENT PLAN Planned for Implementation in 2008 - 2009

Scenario Handling (Regulations): the change will ease the migration of Regulation definitions between the different ATFCM Phases, in particular between Pre-Tactical and Tactical Phases. Delay Allocation Refinement: the capture of the Traffic Flow for ATFCM measures will be dissociated from the identification of the cause of the congestion (hence from the delay attribution). Download of Static Data: the definition of points and airports will be directly downloaded from the EAD database to the CFMU ENV system. Preparation for the AROs Briefing: a first set of Web Services will be developed to prepare the access to the ARO Briefing functions via the NOP Access Layer. CHMI Services - Occupancy Monitoring Values: PEAK and SUSTAINED Occupancy Monitoring Values will be introduced in the Occupancy count graph display.

DEPLOYMENT PLAN The new services will be deployed according to the following plan:

4.1.

4.2.

CFMU Data Distributions to AOs •

Stakeholders: Aircraft Operators and Computerised Flight Plan Services Providers.



Operational deployment date: deployed with the CFMU 12.1 release (May 2008) for a pilot phase, expected to be completed by January 2009. OCG will decide in 2009 about the operational deployment of the service.



Documentation publication: Interface Control Documents available on request. CFMU Flight Progress Messages Document published in CFMU Library.



Training sessions: N/A.



Users’ validation: Initial validation with a limited number of AOs and CFSPs has started in May and is expected to be completed in December 2008.

CIAM •

Stakeholders: Airspace Managers. ─ ─ ─



Operational evaluation: between May and June 2008. Shadow operation: from mid October 2008. Operational deployment: when all AMCs are ready for transfer into operation (Expected in January 2009). Documentation publication: ─ ─



Amendment date: 01 Dec. 2008

General presentation: CFMU Releases Notes. Detailed presentation: CIAM User Reference Guide available to AMCs on Extranet (OneSkyTeam). Training sessions: From May 2008 until June 2008 for AMCs participating to the Operational validations. For the other AMCs training will be performed using virtual classroom as from mid October 2008. Edition 1.5 Edited & produced by the CFMU/User Relations and Development Bureau ©2008 European Organisation for the Safety of Air Navigation (EUROCONTROL)

CFMU_Releases_DP_1.5

6

CFMU RELEASES DEPLOYMENT PLAN

EUROCONTROL CFMU

4.3.

4.4.

4.5.

Planned for Implementation in 2008 - 2009

eRAD via EAD •

Stakeholders: Computerised Flight Plan Service Providers.



Operational deployment date: following successful deployment of the CFMU 12.1 Release (May 2008) and subsequent pilot phase.



Documentation publication:



─ General presentation: CFMU Releases Notes. ─ Detailed presentation: EAD Users Guide. Training sessions: included in EAD training.



Users’ validation: Pilot phase ongoing, to be finalised end of December 2008.



Fully operational: in January 2009.

CCAMS •

Stakeholders: Air Navigation Service Providers.



Operational deployment date: not available yet. Functionalities will only be available in Operational Evaluation/Test Systems.



Documentation publication: Users Guide (Postponed).



Training sessions: (Postponed).



Users’ validation: Initial validation with a limited number of States from Central Europe is expected end 2009 at the earliest.

Interactive NOP •

Stakeholders: Air Navigation Service Providers, Airports and Aircraft Operators.



Operational deployment date: following successful deployment of the CFMU 12.2 Release (October 2008) and subsequent pilot phase.



Main steps of the pilot and operational deployment phases NB: These dates are tentative as each step will be subject to a ‘GO/NOGO decision’ depending on the successful achievement of the previous step.



Amendment date: 01 Dec. 2008

Pilot Phase: 7 November to 5 December. Actions: ─ User Acceptance Testing, at EUROCONTROL, with users’ taskforce: 7 November. ─

Demos at CFMU User Forum, at EUROCONTROL: 17/18 November.



‘NOP Online Days’: NOP Portal pilot platform accessible on-line to token users who volunteer to participate to the pilot, for awareness and feed-back between 24th November and 5th December.



Registration opens on the day of the CFMU12.2 announcement.

Edition 1.5 Edited & produced by the CFMU/User Relations and Development Bureau ©2008 European Organisation for the Safety of Air Navigation (EUROCONTROL)

CFMU_Releases_DP_1.5

7

EUROCONTROL CFMU •

• •

4.6.

4.7.

Amendment date: 01 Dec. 2008

CFMU Operations training and implementation of procedures.

Deployment 2 Phases: 21 January to 5 February. Actions: ─ Extension of the access to the NOP Portal operational platform to all token users: live trials, on-line assistance to users. ─



Planned for Implementation in 2008 - 2009

Deployment 1 Phase: 8 December to 21 January. Actions: ─ NOP Portal operational platform accessible on-line to pre-registered token users (same group as for the Pilot Phase) for user testing and feed-back. ─



CFMU RELEASES DEPLOYMENT PLAN

Finalisation of the CFMU operations training and procedures.

Full Operations: 5 February. After monitoring of the readiness of the operational procedures. CIA Phase-out: 1Q 2009 (date to be confirmed). After monitoring of the CIA users’ migration. Documentation publication: ─

Web based training on main functions: 28 October 2008.



Other user documentations: to be delivered at deployment 2.



Training sessions: planning published on the CFMU Public Web Site.



Users’ validation: see paragraph above ‘Main steps of the pilot and operational deployment phases’.

Set-Up of the UUP Process •

Stakeholders: Airspace Managers.



Operational deployment date: following successful deployment of the CFMU 13 release (April 2009) and subsequent pilot phase.



Documentation publication: under preparation.



Training sessions: under preparation.



Users’ validation: to be defined.

Scenario Handling (Regulations) •

Stakeholders: Flow Management Positions.



Operational deployment date: following successful deployment of the CFMU 13 release (April 2009).



Documentation publication: under preparation.



Training sessions: under preparation.



Users’ validation: to be defined.

Edition 1.5 Edited & produced by the CFMU/User Relations and Development Bureau ©2008 European Organisation for the Safety of Air Navigation (EUROCONTROL)

CFMU_Releases_DP_1.5

8

CFMU RELEASES DEPLOYMENT PLAN

EUROCONTROL CFMU

4.8.

4.9.

4.10.

4.11.

Amendment date: 01 Dec. 2008

Planned for Implementation in 2008 - 2009

Refine Delay Allocation •

Stakeholders: Flow Management Positions.



Operational deployment date: following successful deployment of the CFMU 13 release (April 2009).



Documentation publication: under preparation.



Training sessions: under preparation.



Users’ validation: to be defined.

Download Static Data •

Stakeholders: Air Navigation Service Providers.



Operational deployment date: following successful deployment of the CFMU 13 release (April 2009).



Documentation publication: under preparation.



Training sessions: under preparation.



Users’ validation: to be defined.

Web Services for AROs Briefing •

Stakeholders: ATS Reporting Offices.



Operational deployment date: following successful deployment of the CFMU 13 release (April 2009).



Documentation publication: under preparation.



Training sessions: under preparation.



Users’ validation: to be defined.

CHMI Services – Occupancy Monitoring Values – PEAK and SUSTAINED •

Stakeholders: Flow Management Positions.



Operational deployment date: Due to time and cost constraints, the implementation will be spread over two releases (CFMU13 and 14). Limitations in CFMU13 will prevent a full deployment but should be enough to validate and mature the requirements and Operational procedures. ─

In CFMU13 the full User Interface will be implemented, but the storage of the data will be limited to the local CHMI Preferences.



In CFMU14, the OTMV input by FMPs will be properly managed and stored in the ADR and archived.



A pilot phase will be organised with volunteering FMPs and organised by CFMU OPSD.



Documentation publication: under preparation.



Training sessions: under preparation. Edition 1.5 Edited & produced by the CFMU/User Relations and Development Bureau ©2008 European Organisation for the Safety of Air Navigation (EUROCONTROL)

CFMU_Releases_DP_1.5

9

EUROCONTROL CFMU •

5.

CFMU RELEASES DEPLOYMENT PLAN Planned for Implementation in 2008 - 2009

Users’ validation: to be defined.

RECOMMENDATION The CFMU Users are invited to: • Participate to the training proposed according to their needs.

Amendment date: 01 Dec. 2008



Participate to the Pilot phases proposed when concerned.



Adapt their procedures and systems to take benefit of the new services relevant to their operations.

Edition 1.5 Edited & produced by the CFMU/User Relations and Development Bureau ©2008 European Organisation for the Safety of Air Navigation (EUROCONTROL)

CFMU_Releases_DP_1.5

10

Related Documents

Deployment
November 2019 89
Deployment
June 2020 60
Deployment
November 2019 77
Press Releases
May 2020 16
Plan 5
November 2019 6

More Documents from ""