STANDARD OPERATING PROCEDURES Boiler Heating Batching Control Trainer (Model : SE 107) Start Up Procedures 1.
Ensure that all valves are set according to level control initial valve positions ( Non Self Regulating) outlined below:OPEN
CLOSE
HV 231 HV 236 HV 237 HV 238
HV 232 HV 235 HV 239 HV 241
LEAVE ALONE HV 233 HV 234
HV 240 2. 3. 4. 5.
Fill up sump tank T 601. Switch on the panel. Set the Control Mode switch to “ LEVEL” to engage the level control loop. Switch on pump P 601.
Shut down procedures. 1. 2. 3.
Switch off all pumps. Open fully valve HV 620 to allow the water return into sump tank T 601. Switch off control panel power supply.