barr
STADIA UNIT ORGANISATION AND PORTFOLIO
barr DIVISIONAL STRUCTURE
barr limited
barr environmental limited
barr
barr
barr
manufacturing
construction
industrial
precast concrete
construction
Cranes and access
Steel fabrication
plant & transport
Steel erection
testing quarries road surfacing ready mixed concrete
barr technical services
barr
Unit Structure
Barclay Chalmers Managing Director
Sandy Milligan Director - BTS
Gordon Eccleston
Colin Timmons
Colin Veitch
Unit Managing Director
Unit Managing Director
Unit Managing Director
Tesco
Retail
Regional
Stadia
Schools
Paul Griffen
Aiden Teague
Robbie Clark
Bill Fraser
Angus Cormie
N of England
barr
UK STADIA PROJECTS Current and Future Projects Completed Projects
barr Barr Stadia Clients
Airdrie United FC
Leyton Orient FC
Ayr United FC
Livingston FC
Bournemouth AFC
Northampton RFC
Celtic FC
Partick Thistle FC
Cheltenham Town FC
Plymouth Argyle FC
Dumbarton FC
Portsmouth FC
Dundee FC
Raith Rovers FC
Dunfermline FC
Rangers FC
Fulham FC
Southampton FC
Gloucester RFC
St Mirren FC
Greenock Morton FC
Stranraer FC
Hartlepool United FC
Stenhousemuir FC
Hibernian FC
Warrington Wolves RLFC
Kidderminster Harriers FC
Worcester County Cricket
Kilmarnock FC
Wycombe Wanderers FC
Stadia Projects
barr
From Top St Mary’s Stadium,Southampton FC Craven Cottage, Fulham FC Celtic Park, Glasgow Hospitality Suite, Hibernian FC Worcestershire CCC Warrington Wolves RLFC Nelson Stand, Perth Racecourse Plymouth Argyle FC Fitness Room, St Mirren FC
New Stadium for Southampton Football Club
barr
Project: Friends Provident St Mary’s Stadium, Southampton Client: Southampton Football Club
Design Team: Barr Technical Services Seating Capacity: 32,000 seats
Project Description: Design and construction of a new wrap around stadium: steel framed metal/bridge clad structure with precast single tier concrete decking and seating with a translucent sloping roof. Integral concourse, club facilities, offices, hospitality boxes and suites, changing rooms and support accommodation. Pitch formation, landscaping, site works and infrastructure works for stadium access.
Contract Value: £25 million
New Stadium,Warrington
Project: New Stadium, Warrington Client: Warrington Wolves Rugby Football Club Design Team: Barr Technical Services Seating Capacity: 14,000 Project Description: The design and construction of a new Rugby League ground in Warrington. The 14,000 capacity arena was completed within a forty week programme Contract Value: £6.8M
barr
New Stand, Worcester
barr Project: New Stand, Worcester Client: Worcestershire County Cricket Club
Design Team: Barr Technical Services Seating Capacity: 1,200
Project Description: The construction of the new Basil D’Olivera Stand at Worcestershire’s County Ground. This open stand will provide space for 1,200 spectators.
Contract Value: £0.6M
Redevelopment of Craven Cottage for Fulham FC
Project: Stadium Redevelopment, Craven Cottage, Fulham Client: Harrods/ Fulham Football Club Design Team: Barr Technical Services Seating Capacity: 22,000 seats Project Description: The project involved the complete renovation of the existing Hammersmith and Putney ends of the ground. At the Putney End, this involved the erection of a new steel frame and roof to allow the installation of new seating units. The Hammersmith Stand involved the installation of strip foundations to support the new seating deck and the erection of steelwork to support the seating in the rear of the stand. A portion of the existing roof was retained and extended to cover the new seating deck. New hospitality units have also been installed. Underneath both stands replacement blockwork for enhanced toilet facilities and concourses have also been installed. New seating has also been installed in the Enclosure of the Stevenage Road stand. The remaining Riverside and Stevenage Road stands have also been extensively refurbished. Contract Value: £4.5 million
barr
The Nelson Grandstand Perth Racecourse
barr
Project: Nelson Grandstand at Perth Racecourse Client: Perth Racecourse Ltd Design Team: James Denholm Partnership (Architects) Ralph Ogg & Partners (Surveyors) Allen Gordon & Co (Structural Engineers) Hulley & Kirkwood (Services Engineers) Contract Value: £1.5 million
Project Description: The project involved the construction of a new grandstand at Perth Racecourse completed in less than four months. In addition to the terracing deck the facility includes a downstairs bookmaker’s hall and bar with an upstairs restaurant and function room offering views of the finishing line.
Stadium Redevelopment for Leyton Orient FC
Project: Stadium Redevelopment, London Client: Leyton Orient Football Club Design Team Barr Technical Services (West Stand) Archer Boxer (Architect - Novated) Dewhurst MacFarlane (Engineer -Novated) Gordon Harris Partnership (Surveyors) Seating Capacity: West Stand - 2,500 seats South stand - 1336 seats East stand - 840 seats Total Contract Value: £7 million
barr
Project Description: Barr has just completed a new West Stand for Leyton Orient Football Club (shown above). This stand comprises substantial office accommodation and allows space for the construction of residential development in the corner areas. Barr previously constructed the South Stand (below) and renovated the existing East Stand. Contract included fitting out of concourse area for family room and community offices, along with concurrent safety improvement works to the North Terrace and East Stand with a conversion of existing terracing to seated area.
New Stands for Plymouth Argyle Football Club
Client: Plymouth Argyle FC Design Team: Barr Technical Services Project Description: Demolition of existing stands and terracings to 3 sides of the ground including removal of bankings. Design and construction of new wrap-round spectator stands within an overall masterplan for a complete spectator bowl. Includes level internal and external concourses, achieving access for wheelchairs disabled. Complete with all facilities for spectators comfort and ease of circulation. New floodlights to be roof mounted on new stand. Transformation of the existing facilities into a modern football stadium was completed within 7 months.
Seating Capacity: Phase 1 - 12,600 seats Phase 2 - 6,000 seats Contract Value Phase 1 - £4.6 million Phase 2 - £4.6 million
barr
New East & West Stands for Celtic FC
barr
Client: Celtic Football Club Ltd Design Team: Barr Technical Services in conjunction with Percy Johnson Marshall & Partners Barr Steel and HJT Consulting Engineers Seating Capacity: East Stand - 12,500 West Stand - 12,800
Project Description: Two major phases of the redevelopment of Celtic Park to achieve an all-seated stadium capacity of 60,000 spectators. Both phases were constructed within the restrictions of a fully operational football stadium, providing a total of 25,300 seats plus all the necessary toilets, refreshment areas and safety features required for a modern stadium including a new stadium control facility. Additional floors provided will potentially accommodate quality offices, hospitality/banquet facilities, leisure club and hotel. Contract Value: £12 million
Greyhound Stadium,Wallyford
barr Project: New Greyhound Stadium, Wallyford near Edinburgh Client: Howard Wallace Design Team: Barr Technical Services
Project Description: The design and construction of a new Greyhound Stadium including full hospitality and catering facilities. Contract Value £8M
Stadium Redevelopment Northampton
Project: Stadium Redevelopment, Northampton Client: Northampton Rugby Football Club Design Team: Barr Technical Services Seating Capacity: 12,000 (including 1,600 standing) Project Description: Design and construction of three new stands and control tower incorporating hospitality and related spectator facilities. Barr have recently completed a major extension of the ground to create 1,600 new seats. Contract Value: £8.5M
barr
New Grandstand Halton Stadium, Widnes
Project: Construction of a new Grandstand at Halton Stadium Client: Halton Borough Council Design Team: Barr Technical Services Seating Capacity: 1,500 seats Project Description: This project involved the construction of a new grandstand at the Halton Stadium in Widnes. The stand was designed to complement the existing facilities at the ground and was completed within the twenty week programme. The Halton Stadium is the home venue for Widnes Vikings Rugby League club. Contract Value: £1.5 million
barr
Stadium Redevelopment Bournemouth
barr
Project: New stands for AFC Bournemouth Client: AFC Bournemouth
Design Team: Barr Technical Services Seating Capacity: 10,000 seats
Project Description: Design and construction of a three new stands and relocation of existing pitch, in a phased development
Contract Value: £5.2 million
Rangers Training Centre and Youth Academy, Glasgow
barr
Project: Training Academy, Auchenhowie, Milngavie Client: Rangers Football Club plc
Design Team: Gareth Hutchison (Architect) Woolgar Hunter (Engineer)
Project Description: Construction of a Training Centre and Youth Academy involved the provision of new all weather and grass football pitches, indoor training and leisure complex, hydrotherapy pool and associated road works, drainage and site work infrastructure.
Value: £8.75 million
Stadium Redevelopment for Hibernian Football Club
barr
Client: Hibernian Football Club Limited Design Team: Barr Technical Services in conjunction with Percy Johnson Marshall & Partners
Project Description: In 1995 Barr provided Hibernian Football Club with two new double-tiered stands complete with luxury hospitality facilities and office accommodation. This was followed by a contract to level the famous Easter Road sloping pitch during the close season of 2000 and, in 2001, by the new two-tier west stand, a six month project including hospitality suites, press suites, boardroom, players’ accommodation, gymnasium, treatment room and various refreshment bars.
Seating Capacity: North Stand South Stand West Stand Contract Value: £12.5M
3,700 3,700 6,500
Strathclyde Homes Stadium Dumbarton
Client: Dumbarton FC Design Team: Barr Technical Services Seating Capacity: 2,100 seats Project Description: The design and construction of a new stadium for Dumbarton FC including office accommodation, changing areas and catering facilities. Contract Value: £2.5 million Photos courtesy of www.scottishgroundguide.co.uk
barr
New Stand, Kidderminster
barr Client: Kidderminster Harriers Football Club Limited Design Team: Barr Technical Services
Project Description: The design and construction of a new 2,100 capacity east stand at the Aggborough Stadium.
Contract Value: £1.2M
Two New Stands for Dundee Football Club
barr Project: Stadium Redevelopment, Dens Park, Dundee Client: Dundee Football Club
Design Team: Barr Technical Services and Barr Steel Seating Capacity: 6,000
Project Description: Two new 3,000 seat stands, complete with toilets and refreshment kiosks, plus stadium control room were constructed in 84 Days. The works involved the removal of existing terracings and construction of retaining walls prior to construction of the new stands to suit future regrading of the playing surface. External concourses were created to improve crowd control and circulation within an extremely restrictive site. Contract Value: £2.5 million
Reconstruction of Kilmarnock Football Club
barr Project: Stadium Redevelopment, Rugby Park, Kilmarnock Client: Kilmarnock Football Club
Design Team: Barr Technical Services Seating Capacity: 18,000 seats
Contract Value: £3.6 million
Project Description: The comprehensive redevelopment of Rugby Park has provided an 18,000 all-seater stadium incorporating the construction of three new stands, reseating and recladding of the main stand and erection of new turnstiles, boundary walling, segregation fencing and floodlighting. The new stands include toilets, refreshment kiosks, disabled facilities and new facilities for police, ambulance and stewarding. The distinctive trussed columns and roof trusses were by Barr Steel, with precast concrete steps by Solway Precast. The redevelopment was carried out within one football season
Stadium Redevelopment Portsmouth
barr Project: Stadium Redevelopment, Fratton Park, Portsmouth Client: Portsmouth FC Design Team: Barr Technical Services Capacity: 36,000 Contract Value: £23M
Project Description: Barr is preferred bidder for the redevelopment of Fratton Park. Phase One involves the addition of a new stand followed by a ninety degree rotation of the pitch during the close season. This will be followed by the extension of the current east and west stands during the following season. The new stadium is just part of an overall £90M scheme at Portsmouth which includes housing, leisure and retail development. This scheme will all be planned, designed, programmed and organised within the Barr Group.
New Stand for Livingston Football Club
barr Client: Livingston Football Club Design Team: Percy Johnston Marshall & Partners (Architects - Novated) Barr Steel (Structural Design)
Project Description: All-seater stand with hospitality facilities. Construction was steel frame with precast seating units. The outer skin of the building was prefinished blockwork to match existing, with cladding to upper areas of the stand and a projecting roof to cover all seated areas. The facilities include a hospitality area to seat 200 people, with hardwood dance floor, fitted bar and dedicated kitchen. An office and changing areas for the existing 5-a-side outdoor soccer facilities are provided, together with public toilets. Work on the project was completed within the contract duration of 20 working weeks.
Contract Value: £0.784 million Seating Capacity: 1,962 seats
New Stand for Cheltenham Town FC
Client: Cheltenham Town Football Club Design Team: Barr Technical Services Clarke Nicholls & Marcel (Engineer) Seating Capacity: 2,000 seats Contract Value: £1.1 million Project Description: Phase 1 of a 10 year stadium redevelopment plan. The Wyman Road Stand (shown at the bottom of the aerial picture) seats 2,000 spectators and provides excellent viewing and comfort to both home and away support.
barr
New North Stand, Firhill Stadium
barr Project: New North Stand, Firhill Stadium, Glasgow
Client: Partick Thistle Football Club Design Team: Barr Technical Services
Project Description: Two phase construction of a new North Stand at Firhill. First phase completed in time for the start of Partick’s Premier League campaign and the stand was extended the following close season
Seating Capacity: 2,000 Contract Value: £0.8M Photography courtesy of Garthland Print (0141) 445 5360
Two New Stands for Dunfermline Athletic FC
barr
Client:
Dunfermline Athletic Football Club Limited
Design Team:
Barr Technical Services and Barr Steel in conjunction with GCA Architects Limited
Seating Capacity:
6,000
Contract Value:
£3.5 million
Project Description:
Construction of two new 3,000 spectator stands and the refurbishment of an existing standing enclosure with installation of seating. Restricted access to the site and the proximity of adjacent commercial premises and houses presented particular project constraints. During the removal of the terraces the existing fill material was monitored and, as a consequence, gas impermeable membranes and venting system were introduced. The stands were detailed in the context of an ambitious strategy for the overall development of the stadium and features have been incorporated to facilitate future extensions.
New Stands for St. Mirren Football Club
barr Client: St. Mirren Football Club Client’s Agents: GCA Architects
Design Team: Barr Technical Services Seating Capacity: East Stand - 2,000 seats West Stand - 3,000 seats Contract Value: £2.5 million
Project Description: The new West Stand provides indoor leisure facilities - cafe, two five-a-side football halls, aerobics hall, general purpose sports halls and associated changing facilities, sauna, solaria and steam room. It also incorporates toilets, refreshment kiosks, a police control room and disabled facilities. The structural steel frame with externally expressed columns and cantilevered roof trusses is by Barr Steel. All precast concrete work associated with floors, stairs and steppings are by Solway Precast. The existing East Stand concrete terracings were reprofiled to create a new seating deck complete with new roof canopy. Ancillary toilets and refreshment kiosks including specialised facilities for wheelchair disabled were also provided.
New Stand for Stranraer Football Club
Client: Stranraer Football Club Design Team: Barr Technical Services Seating Capacity: 1,500 seats Contract Value: £0.5 million Photos courtesy of www.scottishgroundguide.co.uk
barr
Project Description: Demolition of existing stand and construction of new 1,500-seater stand to part of the south touchline, capable of future modular extension. The stand accommodates new club facilities, including changing rooms, offices, boardroom and hospitality suite in addition to toilet and catering facilities for the spectators. Car parking and concoursing to the rear has improved facilities and access for disabled spectators and the emergency services.
barr
New Stadium for Airdrie Football Club
Project: New Broomfield Stadium, Airdrie Client: Airdrie Football & Athletic Co Limited Design Team: Barr Technical Services & Barr Steel Seating Capacity: 10,000
Project Description Design and Construction of a new 10,000seat stadium for Airdrie FC. Four spectator stands with refreshment serveries and toilets; pitch formation, floodlighting, car parking and vehicular accesses, plus associated road junctions. Enabling works also involved ground consolidation, piling and services diversions, in addition to amendment and upgrading of adjacent public football facilities. The main stand provides players’ facilities, gymnasium, crèche, restaurant/ lounges, hospitality suites and viewing boxes, directors’ accommodation and facilities for emergency services. Contract Value: £5.3 million
New Stands for Raith Rovers Football Club
barr
Client: Raith Rovers Football Club Design Team: Barr Technical Services Barr Steel Seating Capacity: 7,500 seats
Project Description: Stark’s Park presented particular problems imposed by the constraints of topography, tight site boundaries and restricted access. The project involved the removal of standing terracings to the north, south and west sides of the ground and the construction of new stands at each end, plus a new stand to part of the west side to extend seated accommodation. The layout of spectator concourses and circulation around the ground was developed to improve access and crowd control. All stands provide toilet and refreshment facilities and are fitted with the safety features necessary for a modern football stadium. A new floodlighting system was installed to provide 1200 lux at the playing surface. Contract Value: £2.46 million
New Stand for Stenhousemuir FC
barr Client: Stenhousemuir Football Club Design Team: Barr Technical Services
Project Description: All-seater stand with hospitality facilities. Construction was steel frame with precast seating units. The outer skin of the building was pre-finished blockwork to match existing, with cladding to upper areas of the stand and a projecting roof to cover all seated areas. The facilities include a hospitality area.
Seating Capacity: 1000 seats Contract Value £0.8 million
barr
Stand Extension, High Wycombe
Project: Stand Extension, Adams Park, High Wycombe Client: Wycombe Wanderers FC Design Team: Barr Technical Services Seating Capacity: 1,000 additional seats Contract Value £0.4M
Project Description: The design and construction of a stand extension at Wycombe’s Adams Park. The project involved an additional deck being fitted to the rear of an existing stand with the erection of a new roof (project shown under construction). The completed stand brings the total capacity for the East Stand up to 2,000.