ITEM PEMBAYARAN NO. JENIS PEKERJAAN

: 1.8 (2) : Pemasangan & Pemeliharaan Jembatan Sementara

% TERHADAP TOTAL BIAYA PROYEK = ???

No.

URAIAN

%

SATUAN

I.

Data & Asumsi

1 2 3 4 5 6

Jembatan sementara jenis Bailley Jembatan sementara konstruksi kayu Sewa jembatan Bailley sudah termasuk angkut, pasang dan bongkar Detour diperlukan length (m) = 300 Total Masa Pelaksanaan Proyek Masa Pemeliharaan Jembatan Efektif

II.

Bahan & Perlengkapan

1 2 3 4 5 6

Biaya jembatan Bailley Biaya jembatan kayu Agg.Kls.B Detour tebal (cm) = 10 Agg.Kls.A Detour tebal (cm) = 10 Prime Coat Detour Sewa tanah

III.

Pekerja Untuk Pemeliharaan

1 2 3

Pekerja Tukang ( Batu/Cat/Las) Pemimpin Regu (Mandor)

9 3 1

VOL.

HARGA SATUAN (Rp.)

JUMLAH HARGA (Rp.)

M2 M2

250 150

M2 Hari Hari

1,200 360 180

M2 M2 M3 M3 Liter M2

250 150 120 120 1,200 1,300

115,000 100,000 317,000 120,000 125,000 500

28,750,000 15,000,000 38,040,000 14,400,000 150,000,000 650,000

Org/hari Org/hari Org/hari

1,620 540 180

11,429 14,286 17,143

18,514,286 7,714,286 3,085,714

Total Biaya Pemeliharaan & Perlindungan Lalu Lintas

276,154,286

Catatan : Jumlah yang tercantum pada masing-masing item di atas sudah termasuk over-head dan laba serta seluruh pajak dan bea (kecuali PPn), dan pengeluaran lainnya.

Related Documents

Jembatan
April 2020 26
Jembatan
December 2019 37
Jembatan Wheatstone
April 2020 21
Tugas Jembatan
October 2019 32

More Documents from "Dsc Septer"

Bulog Ereke.docx
April 2020 13
Agnes.docx
December 2019 14
Add Kontrak.xls
December 2019 20
Foto Pagar.pdf
April 2020 9