152-0404

  • October 2019
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View 152-0404 as PDF for free.

More details

  • Words: 11,835
  • Pages: 27
Question Paper Management Accounting – II (152) : April 2004 1.

If a company uses a predetermined rate of absorbing factory overhead, the volume variance is the (a) (b) (c) (d) (e)

< Answer >

Under or over applied variable cost element of factory overhead Under or over applied fixed cost element of factory overhead Difference in budgeted cost and actual cost of fixed factory overhead items Difference in budgeted cost and actual cost of variable factory overhead items Difference in standard cost and actual cost of variable factory overhead items. (1 mark)

2.

A budget in which a responsibility center manager must justify each planned activity and its estimated total cost is known as (a) Conventional budget (c) Participative budget (e) Program planning and budget system.

< Answer >

(b) Master budget (d) Zero based budget (1 mark)

3.

< Answer >

Operation budgets normally cover a period of (a) One year or more (c) One year to two years

(b) One year or less (d) One year to three years (e) Two years. (1 mark)

4.

< Answer >

A fixed factory overhead volume variance will exist if (a) (b) (c) (d) (e)

Actual labor hours differ from budgeted labor hours Actual labor hours differ from standard labor hours Actual production volume differs from standard production volume The fixed factory overhead applied on the basis of standard labor hours for actual output differs from actual fixed factory overhead The fixed factory overhead applied on the basis of standard labor hours for actual output differs from the budgeted fixed factory overhead. (1 mark)

5.

AAC Ltd. planned to produce 1,000 units of its product-P during the month of February 2004.The standard specifications of one unit of product-P includes 5kg. of material at Rs.12 per kg. Actual production during the month was 1,068 units of product-P. The accountant computed a favorable materials purchase price variance of Rs.520 and unfavorable material quantity variance of Rs.280. Based on these variances, one should conclude that (a) (b) (c) (d) (e)

< Answer >

More materials were purchased than were used More materials were used than were purchased The actual cost of materials was less than the standard cost The actual usage of materials was less than the standard allowed The standard cost of material was less than the actual cost. (1 mark)

6.

< Answer >

Life cycle costing (a) (b) (c) (d) (e)

Includes only the cost of design and development of the product Includes only manufacturing costs incurred over the life of the product Includes only manufacturing cost, selling expense and distribution expense Emphasizes cost savings opportunities during the manufacturing cycle Is sometimes used as a basis for cost planning and product pricing. (1 mark)

7.

A limitation of transfer prices based on actual cost is that they (a) (b) (c) (d)

Charge inefficiencies to the department that is transferring the goods Can lead to sub optimal decisions for the company as a whole Must be adjusted by some markup Must be adjusted by ROI (return on investment)

< Answer >

(e)

Lack clarity and administrative convenience. (1 mark)

8.

Decentralized firms can delegate authority and yet retain control and monitor managers’ performance by structuring the organization into responsibility centers. Which of the following organizational segments is most like an independent business? (a) Revenue center (c) Cost center

(b) Profit center (d) Investment center

< Answer >

(e) Contribution center. (1 mark)

9.

< Answer >

Under standard cost system, labor rate variances are usually not attributable to (a) (b) (c) (d) (e)

Union contracts approved before the budgeting cycle Labor rate prediction The use of single average standard rate The assignment of different skill levels of workers than planned Approved wage revisions after the budgeting cycle. (1 mark)

10.

A budget manual, which enhances the operation of a budgeting system, is most likely to include

< Answer >

(a) Employee hiring policies (b) Documentation of accounting system (c) Company policies regarding the authorization of transaction (d) Employee training policies (e) Distribution instructions for budget schedules. (1 mark) 11.

The direct material usage budget and direct material purchase budget differ because of which of the following? (a) (b) (c) (d) (e)

< Answer >

The level of material scrap forecast occur The level of efficiency of men The level of efficiency of machines A change in the level of finished goods stock A planned change in the level of material stock. (1 mark)

12.

The question of raw material in the purchases budget of a company may be higher than the quantity of raw material in the production budget because (a) Stock levels are being reduced falling (c) The company obtains discount for bulk purchases (d) Units sold will be higher than units made

< Answer >

(b) Raw material prices are (e) High efficiency of men. (1 mark)

13.

Which of the following departments has the primary responsibility for an unfavorable material yield variance? (a) Purchasing department (c) Stores department (e) Inspection department.

< Answer >

(b) Production department (d) Engineering department (1 mark)

14.

If a company produces more than one product, the sales volume variance can be divided into which of the following additional variances? (a) (b) (c) (d) (e)

< Answer >

Sales price variance and flexible budget variance Sales mix variance and sales price variance Sales quantity variance and sales mix variance Sales mix variance and production volume variance Sales quantity variance and flexible budget variance. (1 mark)

15.

Comparing actual results with a budget based on achieved volume is possible with the use of a (a) Monthly budget (c) Flexible budget

(b) Master budget (d) Rolling budget

(e) Zero-based budget.

< Answer >

(1 mark) 16.

The information contained in a cost of goods manufactured budget most directly relates to the

< Answer >

(a) Materials used, direct labor, overhead applied, and ending work-in-process budgets (b) Materials used, direct labor, overhead applied, and work-in-process inventories budgets (c) Materials used, direct labor, overhead applied, work-in-process inventories, and finished goods inventories budgets (d) Materials used, direct labor, overhead applied and finished goods inventories budgets (e) Material purchased, direct labor, overhead incurred and budgeted finished goods inventory. (1 mark) 17.

< Answer >

The cash receipt budget includes (a) Funded depreciation (c) Extinguishments of debt (e) Amortization of preliminary expenses.

(b) Operating supplies (d) Loan proceeds (1 mark)

18.

If budgets are used to evaluate performance and to set limits on spending, the process will often result in departments adding something extra to ensure the budgets will be met. This extra is (a) Management by objectives (c) Continuous budgeting (e) Management by exception.

< Answer >

(b) Strategic planning (d) Budgetary slack (1 mark)

19.

‘The average human being has an inherent dislike for work and will avoid it if he can’- this job attitude is specifically dealt with in

< Answer >

(a) Douglas McGregor’s Theory X (b) Douglas McGregor’s Theory Y (c) The principles of human motivation as revealed by Abraham Maslow (d) Herzberg’s Two Factor Theory (e) McDonald’s Theory Z. (1 mark) 20.

The system of identification and communication that signals the manager when his attention is needed is known as (a) Management by objective (c) Management by exception (e) Responsibility accounting.

< Answer >

(b) Management information system (d) Management control (1 mark)

21.

The budget that describes the long term position, goals and objectives of an entity within its environment is the (a) Capital budget (c) Cash management budget (e) Production budget.

< Answer >

(b) Operating budget (d) Strategic budget (1 mark)

22.

Which of the following techniques would be best for evaluating the management performance of a department that is operated as a cost center? (a) Return on assets ratio (c) Flexible budgeting (e) Residual income.

< Answer >

(b) Return on investment ratio (d) Variance analysis (1 mark)

23.

A set of concepts and tools applied for getting all the employees focused on continuous improvement in the eyes of the customers is popularly known as (a) Quality control (c) Customer orientation (e) Total quality management.

(b) Cost control (d) Self management (1 mark)

< Answer >

24.

If the sales manager of a company accepts a rush order that will result in higher than normal manufacturing cost, these additional costs are charged to the sales manager because the authority to accept or decline the rush order was given to the sales manager. This type of accounting system is known as (a) Responsibility accounting (c) Historical accounting (e) Transfer price accounting.

< Answer >

(b) Functional accounting (d) Reciprocal allocation (1 mark)

25.

For monitoring the overall financial and physical performance of an organization, which of the following information is required?

< Answer >

(a) Breakdown of sales, region-wise and customer-wise (b) Return on investment (c) Production levels of various products (d) Cash structure (e) All of the above. (1 mark) 26.

< Answer >

Operating management of an organization requires the following information except (a) Capacity utilization (b) Productivity of labor and machinery (c) Technological advances and new product development (d) Overtime payments (e) Marketing and distribution costs. (1 mark)

27.

< Answer >

Which of the following statements is false? (a)

Value-chain is the linked set of value-creating activities from the basic raw material sources for suppliers to the ultimate end-use product delivered (b) Value chain requires an internal focus (c) No firm is likely to span the entire value chain (d) Each firm must be understood in the context of the overall value chain of value-creating activities (e) A firm is only a part of the larger set of activities in the value delivery system. (1 mark) 28.

< Answer >

Scrap and costs of spoiled units that cannot be salvaged are the examples of (a) Appraisal costs (c) External failure costs (e) Committed costs.

(b) Internal failure costs (d) Prevention costs (1 mark)

29.

< Answer >

Which of the following is usually the longest stage in the product life cycle? (a) Introduction phase (c) Maturity phase

(b) Growth phase (d) Saturation phase

(e) Decline Phase. (1 mark)

30.

< Answer >

Which of the following is not a disadvantage of shadow price? (a)

The use of shadow price is incompatible with the philosophy of decentralization through divisionalisation (b) To derive the shadow price, one has to obtain the dual solution to the mathematical programming model developed for solving the production planning problem of the buying division (c) Assimilating the data and application of the model becomes a highly centralized affair (d) Operating managers often do not understand and appreciate the concept of shadow price (e) Shadow price can be used only when the resources are available in plenty and are not scarce. (1 mark) 31.

Activities, their drivers and their costs may be classified as unit-level, batch level, product level, and facility level. If activity based costing information is prepared for internal purposes, the costs of which of the following levels is/are most likely to be treated as period costs? (a) Unit level (c) Product level

(b) Batch level (d) Facility level

(e) Both (a) and (c)

< Answer >

above. (1 mark) 32.

< Answer >

Target pricing (a) (b) (c) (d) (e)

Is more appropriate when applied to mature and long-established products Considers the variable costs and excludes fixed costs Is often used when costs are difficult to control Is a pricing strategy used to create competitive advantage Is well suited for complex products that require many sub-assemblies. (1 mark)

33.

< Answer >

Top-to-bottom budget is also known as (a) Participative budget (c) Zero-based budget

(b) Imposed budget (d) Manpower budget

(e) Master budget. (1 mark)

34.

< Answer >

Basic standards are known as (a) Ideal standards (b) Current standards (c) Measurement standards (d) High standards

(e) Expected standards. (1 mark)

35.

< Answer >

Which of the following is false with regard to full-cost pricing? (a) (b) (c) (d) (e)

It is prone to distortion by accounting misapplications The normal mark-up is based on total cost It is useful in case the company has full knowledge of the demand curve Sellers do not take advantage of the buyers when the latter’s demand becomes acute It ignores vital economic considerations. (1 mark)

36.

The relationship between the budgeted number of working hours and the maximum possible working hours in a budgeted period is (a) Efficiency ratio (b) Activity ratio (c) Calendar ratio (e) Capacity utilization ratio.

< Answer >

(d) Capacity usage ratio (1 mark)

37.

< Answer >

Which of the following statements is true regarding flexible budget? (a) (b) (c) (d) (e)

It accommodates changes in the interest rate It accommodates changes in the inflation rate It accommodates changes in activity levels It is used to evaluate capacity use It is a static budget that has been revised for changes in prices. (1 mark)

38.

A company is currently using the budget as a tool for planning. The management has decided to use the budgets for control purposes also. To affect this change, the financial controller must (a) (b) (c) (d) (e)

< Answer >

Develop forecasting procedures Organize a budget committee and appoint a budget director Report daily to operating management all deviations from the plan Report daily to top management all deviations from the plan Synchronize the budgeting and accounting systems within the organizational structure. (1 mark)

39.

Which of the following is/are true with regard to the period of budget? I. II.

The budget period should be long enough to cover complete production of various products For business of a seasonal nature, the budget period should cover atleast one entire seasonal cycle III. The budget period should be long enough to allow for the financing of production well in advance of actual needs.

< Answer >

(a) Only (I) above (c) Both (I) and (II) above (e) All (I), (II) and (III) above.

(b) Only (II) above (d) Both (I) and (III) above (1 mark)

40.

< Answer >

Fixed overhead cost variance is the difference between (a) (b) (c) (d) (e)

Actual fixed cost and Budgeted fixed cost Actual fixed cost and Standard fixed cost Actual fixed cost and Applied fixed cost Budgeted fixed cost and Applied fixed cost Standard fixed cost and Applied fixed cost. (1 mark)

41. Sify Ltd. produces a commodity by blending two raw materials – X and Y. The following are the details regarding the raw materials:

< Answer >

Material Standard mix Standard price per kg. X 44.4% Rs.5 Y 55.6% Rs.4 The standard process loss is 15%. During the month of March 2004, the company produced 4,000 kg. of finished product. The position of stock and purchases for the month of March 2004 is as under:

Material

Stock as on March 01, 2004 Kg.

Stock as on March 31, 2004 Kg.

Purchases during March 2004 Kg. Rs.

X 80 30 2,000 9,200 Y 100 120 2,500 9,500 The material yield variance of the company is (a) Rs.747.50 (Favorable) (b) Rs.747.50 (Adverse) (c) Rs.776.52 (Adverse) (d) Rs.776.52 (Favorable) (e) Rs.781.70 (Favorable). (3 marks) 42. Consider the following particulars pertaining to 1,000 units of a product produced during the month of March 2004: Standard price per kg. of raw material Rs.10 Standard direct labor cost Rs.5,000 Standard direct labor hours 500 Standard overheads per direct labor hour Rs.3 Total standard cost per unit Rs.20 Material usage variance Rs.860 (A) raw material consumed during the month of March 2004 is (a) 1,264 kgs kgs.

(b) 1,364 kgs

(c) 1,436 kgs

< Answer >

The actual quantity of

(d) 1,634 kgs

(e) 1,350 (2 marks)

43. Hiset Ltd. uses standard process costing method. The standard process cost card per month shows that 3 hours of direct labor is required to produce one kg. of finished product and the fixed overheads, which are recovered on direct labor hours, amount to Rs.120 per kg. of output. The budgeted output is 1,400 kgs. per month. Actual production during the month of March 2004 is 1,370 kgs. and the direct labor hours utilized during the month were 3,880. The details of opening and closing work-in progress (WIP) are as under: Opening work-in-progress – 200 kgs.: Degree of completion of labor and overheads – 60% Closing work-in-progress – 350 kgs.: Degree of completion of labor and overheads – 40% The company uses FIFO method for evaluation of stocks. The fixed overhead efficiency variance is (a) Rs.11,600 (Adverse) (b) Rs.11,600 (Favorable) (c) Rs. 4,800 (Adverse) (d) Rs. 4,800 (Favorable) (e) Rs. 9,500 (Favorable). (3 marks)

< Answer >

44. Tilak Ltd. has two divisions - A and B. The division A has the capacity to manufacture 83,000 units of a special component SC annually and it has some idle capacity currently. The budgeted residual income for the division A is Rs.6,00,000. The relevant details extracted from the budget of A are as under: Sales (to outside customers) Variable cost per unit Divisional fixed cost Capital employed = Cost of capital

< Answer >

= 65,000 units @ Rs.120 per unit = Rs.78 = Rs.15,00,000 Rs.50,00,000 = 18% per annum

Division B received an order for which it requires 18,000 units of a component similar to SC. An additional variable cost of Rs.7 per unit will be incurred to make minor modifications to SC to suit the requirements of Division B. The minimum transfer price per unit which A should quote to B to achieve its budgeted residual income is (a) Rs.152 (b) Rs.93 (c) Rs.135 (d) Rs.163 (e) Rs.100. (3 marks) 45. Sai Ltd. manufactures three products – A, B and C. The following is the information pertaining to the products for the month of March 2004: Product Units Machine hours per unit A 300 2 B 520 5 C 450 4 March 2004 are as under:

< Answer >

The overheads incurred for the month of

Particulars Rs. Factory overhead applicable to machine oriented activity 52,500 Set up costs 8,330 Costs of ordering materials 6,850 Handling materials 11,340 These overheads are being absorbed on a machine hour rate. However, investigation into the production overhead activities for the period reveals the following: Particulars Number of set-ups Number of material orders Number of times material was handled

A 7 3 8

B 6 4 10

C 4 3 9

The

approximate overhead cost per unit of product B under Activity Based Costing is (a) Rs.75.00 Rs.65.00.

(b) Rs.71.50

(c) Rs.72.80

(d) Rs.70.50

(e) (3 marks)

46. A company estimates its direct material requirements for the month of May 2004 to be Rs.3,00,000 and the direct labor to be Rs.1,80,000. It is the policy of the company to absorb overheads as under: Factory overheads Administrative overheads Selling and distribution overheads

< Answer >

50% of direct labor 20% of factory cost 20% of factory cost

It is estimated that the selling and distribution overheads will increase by 15% in the month of May 2004. The company sells goods at a profit of 20% on sales. The budgeted sales for the month of May 2004 is (a) Rs.8,15,100

(b) Rs.9,78,120

(c) Rs.10,18,875

(d) Rs.9,57,600

(e) Rs.9,97,500. (2 marks) < Answer >

47. MM Ltd. has estimated the following quarter-wise sales for its product for the year 2004-05: Quarter I Sales (units) 5,000 maintained are as under:

II 6,250

III 6,500

IV 7,000

The

stocks

to

be

Particulars Opening stock Closing stock

Finished goods (units)

Raw materials (kg.)

1,200 1,100

2,800 3,500

Each unit of finished output requires 2 kg. of raw materials. The production pattern in each quarter is based on 80% of the sales of the current quarter and 20% of the sales of the next quarter. The company proposes to purchase the entire annual requirement of raw material in the first three quarters as under: Quarter

Purchase of raw materials as % of total annual Price per kg. requirement in quantity Rs. I 30% 12 II 50% 13 III 20% 14 amount to be spent to purchase raw materials for the year 2004-05 is

(a) Rs.6,45,000 Rs.6,55,000.

(b) Rs.6,50,160

(c) Rs.6,32,100

(d) Rs.6,42,500

The budgeted (e) (2 marks) < Answer >

48. Consider the following particulars pertaining to Shiva Ltd. for the month of February 2004: Overheads cost variance = Rs.1,880 (Adverse) Overheads volume variance = Rs.1,050 (Adverse) Budgeted hours for February 2004 = 800 hours Budgeted overheads for February 2004 = Rs.16,000 Actual rate of overheads = Rs.19 per hour. The overhead capacity variance is (a) Rs.1,700 (Favorable) (b) Rs.1,700 (Adverse) (c) Rs.1,716 (Favorable) (d) Rs.1,716 (Adverse)

(e) NIL. (2 marks) < Answer >

49. Consider the following particulars for the month of March 2004: Budgeted fixed production overhead cost= Rs.1,10,000 Budgeted production = 5,500 units The fixed overhead cost was under absorbed by Rs.12,000 and the fixed production overhead expenditure variance was Rs.2,500 (Adverse). The number of units produced during the month of March 2004 was (a) 5,025 (b) 5,625 (c) 4,775 (d) 4,550 (e) 4,850. (2 marks) 50. Jeevan Ltd. has normal capacity of 50 machines working 8 hours per day of 25 days in a month. The budgeted fixed overheads of a month are Rs. 90,000. The standard time required to manufacture one unit of product is 5 hours. In a particular month, the company worked for 22 days of 390 machine hours per day and produced 1,700 units of the product. The actual fixed overheads incurred were Rs. 80,000.

< Answer >

The total fixed overhead variance and calendar variance are (a) Rs.10,000 (F) and Rs.10,800(A) respectively (b) Rs.3,500 (F) and Rs.10,800 (A) respectively (c) Rs.10,000 (A) and Rs.9,000 (A) respectively (d) Rs.3,500 (A) and Rs.10,800 (A) respectively (e) Rs.13,500 (A) and Rs.10,000 (F) respectively. (2 marks) 51. Consider the following particulars pertaining to products A and B of a company: Particulars A B Estimated production (units) 14,000 16,000 Total variable costs (other than direct labor) (Rs.) 5,60,000 7,20,000 Direct labor cost per hour (Rs.) 8 6 Number of labor hours per unit 4 4 Fixed costs (Rs.) 8,50,000 10,00,000 The investment in fixed capital is Rs.15,60,000 and working capital requirement amounts to Rs.5,00,000. A

< Answer >

return of 20% on investment is expected. If the contribution per direct labor hour is expected to be the same for both the products, the selling price of product A is (a) Rs.75.40 (b) Rs. 72.00 (c) Rs.147.40 (d) Rs.115.40 (e) Rs.107.40. (2 marks) < Answer >

52. The budgeted and actual sales of a concern are as under:

Product A B C

Budget Quantity (kgs.) 2,500 2,600 2,900

Actual Quantity (kgs.) 2,400 2,450 3,250

Price (Rs.) 15 18 20

(a) Rs.1,968.75 (Adverse) (c) Rs.4,958.75 (Adverse) (e) Rs.7,591.25 (Adverse).

Price (Rs.) 14.50 19.40 19.60

The sales mix variance is

(b) Rs.1,968.75 (Favorable) (d) Rs.1,021.25 (Favorable) (1 mark)

53. The estimated annual production of products P and Q are 8,000 units and 18,000 units respectively. The budgeted cost details of these products are as under: Particulars P Direct materials per unit Rs.60 Direct labor per unit (@Rs.5 per hour) Rs.35 Selling overheads per unit (60% variable) Rs. 8 other overheads are charged to the products as under: Factory overheads (50% fixed) = 80% of direct wages Administrative overheads (100% fixed) = 10% of factory cost

Q Rs.45 Rs.40 Rs.10

< Answer >

The

The fixed capital investment is Rs.15,00,000 and the working capital requirement is equivalent to 3 months stock of cost of sales of P and 4 months stock of cost of sales of Q. A return on investment of 20% is expected. The expected return on capital employed is (a) Rs.4,96,580 Rs.4,90,000.

(b) Rs.4,38,000

(c) Rs.4,61,760

(d) Rs.5,23,760

(e) (3 marks)

54. Machining Division of Coalis Ltd., which is operating at full capacity, manufactures and sells 6,000 units of component KL in a perfectly competitive market. Revenue and cost data are as follows: Particulars Variable cost per unit Fixed cost Sales value

< Answer >

Rs. 24 5,00,000 18,00,000

The Assembly Division received an order for which it requires the component KL. The minimum transfer price per unit that should be charged by Machining Division to other division of the company is (a) Rs.150

(b) Rs.200

(c) Rs.250

(d) Rs.300

(e) Rs.324. (1 mark)

55. Consider the following information pertaining to Prakash Ltd. Particulars May 2004 June 2004 July 2004 Expected sales (units) 12,000 14,000 13,000 Estimated wages and other 2,25,000 2,60,000 2,80,000 manufacturing expenses Rs.) Prakash Ltd. sells the goods at Rs.65 per unit. 50% of the sales are on cash. The debtors are estimated to be collected the next month. One unit of finished output requires 2 units of raw material and is estimated to be purchased for Rs.5 per unit. The production in a month includes half of that month’s sales and half of next month’s sales. The raw material required in a month is purchased in the same month on credit. The creditors are paid in the next month. The wages and other expenses are paid in the

< Answer >

month in which they are incurred. The cash surplus in the month of June 2004 will be (a) Rs.8,45,000 Rs.4,52,000.

(b) Rs.4,95,000

(c) Rs.5,65,000

(d) Rs.4,55,000

(e) (3 marks)

56. During the month of March 2004, 560 kg. of material was purchased at a total cost of Rs.15,904. The stocks of material increased by 15 kg. It is the company’s policy to value the stocks at standard purchase price. If the material price variance was Rs.224 (Adverse), the standard price per kg. of material is (a) Rs.28.40 Rs.29.60.

(b) Rs.28.00

(c) Rs.28.80

(d) Rs.29.20

< Answer >

(e) (1 mark)

57. If the asset turnover and profit margin of a company are 1.85 and 0.35 respectively, the return on investment is (a) 0.65

(b) 0.35

(c) 1.50

(d) 5.29

< Answer >

(e) 0.19 (1 mark)

58. Rajni Ltd. is currently operating at 80% capacity level. The production under normal capacity level is 1,50,000 units. The variable cost per unit is Rs.14 and the total fixed costs are Rs.8,00,000. If the company wants to earn a profit of Rs.4,00,000, then the price of the product per unit should be (a) Rs.37.50 Rs.36.00.

(b) Rs.38.25

(c) Rs.24.00

(d) Rs.34.50

< Answer >

(e) (1 mark)

< Answer 59. AB Ltd. manufactures a single product at the operated capacity of 40,000 units while the normal > capacity of the plant is 50,000 units per annum. The company has estimated 20% profit on sales realization and furnished the following budgeted information:

50,000 units 40,000 units (Rs.) (Rs.) Fixed overheads 2,00,000 2,00,000 Variable overheads 3,00,000 2,40,000 Semi-variable overheads 3,00,000 2,60,000 Sales realization 18,00,000 14,40,000 The company has received an order from a customer for a quantity equivalent to 10% of the normal capacity. It is noticed that prime cost per unit of product is constant If the company desires to maintain the same percentage of profit on selling price, the minimum price per unit to be quoted for new order is (a) Rs.26.63 (b) Rs.27.97 (c) Rs.25.40 (d) Rs.23.26 (e) Rs.30.59. Particulars

(3 marks) 60. KV Ltd., is planning to produce a new model of calculator. The potential demand for the next year is estimated to be 1,75,000 units. The company has the capacity to produce 7,00,000 units and could sell 1,75,000 units at a price of Rs.625 per calculator. The demand would double for every decrease of Rs.75 in the selling price. The company expects a minimum margin of 20%.

< Answer >

At full capacity level, the target cost per unit will be (a) Rs.475

(b) Rs.440

(c) Rs.380

(d) Rs.500

(e) Rs.400. (1 mark)

61. Vinak Ltd. services washing machines and clothes dryers. It charges customers for the spare materials with markup on variable cost. The company has five employees, each earning Rs. 6,000 per year and spending 1,000 hours per year on service calls. It sells parts that cost Rs. 45,000 annually. The company has other costs of Rs. 25,000 a year, which is allocated two-thirds to labor and the remainder to material. The amount of markup on labor cost, if the target profit of the company is Rs.20,000 per annum, is (a) Rs.18,000 Rs.27,000.

(b) Rs.12,000

(c) Rs.30,000

(d) Rs.48,000

(e) (2 marks)

< Answer >

< Answer >

62. Consider the following data of a company during the month of March 2004: i. Budgeted hours ii. Standard hours for actual production iii. Maximum possible hours in the budget period iv. Actual hours The activity ratio of the company during the month of March 2004 is (a) 111%

(b) 120%

(c) 95%

4,000 4,440 4,800 3,800

(d) 117%

(e) 126%. (1 mark)

63. Sanjay is a divisional manager for C-Top Ltd. He has been assigned the task of creating a production budget for his division, which produces the company’s most popular stuffed animal. Budgeted sales for this toy for the next year have been set at 5,00,000 units, desired ending finished goods inventory at 1,50,000 units, and Sanjay desires 60,000 equivalent units in ending work-in-process inventory. The opening finished goods inventory for the next year is 80,000 units, with 50,000 equivalent units in beginning work-in-process inventory. How many equivalent units should Vijay plan for his division to produce? (a) 5,50,000 5,80,000.

(b) 5,75,000

(c) 7,25,000

(d) 5,00,000

< Answer >

(e) (2 marks)

64. Adarsh Ltd. is preparing its cash budget for the next period. Sales are expected to be Rs. 1,00,000 in April 2004, Rs. 2,00,000 in May 2004, Rs.3,00,000 in June 2004 and Rs.1,00,000 in July 2004. Half of all sales are cash sales, and the other half are on credit. Experience indicates that 70% of the credit sales will be collected in the month following the sale, 20% the month after that, and 10% in the third month after the sale. The budgeted collection for the month of July 2004 is (a) Rs.1,30,000 Rs.2,00,000.

(b) Rs.1,80,000

(c) Rs.2,60,000

(d) Rs.3,60,000

< Answer >

(e) (2 marks) < Answer >

65. The following data pertaining to Tishan Ltd. which is operating at 70% of the capacity: Particulars Variable overheads: Indirect labor Indirect material Semi-variable overheads:

At 70% capacity (Rs.) 21,000 10,500 10,500

1 3

Power ( fixed, balance variable) Repairs and maintenance (60 % fixed, 40 % variable) Fixed overheads: Depreciation Insurance Others Total Estimated direct labor hours – 1,15,500 hrs.

1,400 9,000 4,000 3,000 59,400

The overhead recovery rate per direct labor hour at 80% is (a) 0.555

(b) 0.492

(c) 0.536

(d) 0.465

(e) 0.634. (2 marks)

66. A timber merchant purchased 2,000 cft. of timber logs on January 01, 2004 at the rate of Rs.160 per cft and stored them in his timber yard for three months for seasoning. In the timber yard the following items of expenses were incurred during the period of seasoning:

(i) (ii) (iii) (iv)

(i) (ii) (iii) (iv)

Rent –Rs.14,200 per quarter Salaries of 6 guards at the rate of Rs.300 per month Incidental expenditure for maintenance, power, lighting, etc. Rs.900 per month Annual share of administration overheads Rs.16,000.

70% of the floor area of the godown and other connected operations were incurred for stocking the

< Answer >

seasoned timber. Loss in volume of the logs due to seasoning should be taken at 8%. If the timber merchant desires a profit of 20% on cost, the selling price of the seasoned timber per cft as on March 31, 2004 is (a) Rs.225.85

(b) Rs.183.92

(c) Rs.203.05

(d) Rs.229.90

(e) Rs.220.70. (2 marks)

67. Chandana Ltd. is attempting to compute costs for its three products A, B and C for pricing purposes. The company has annual fixed manufacturing costs of Rs. 4,73,625. The variable costs per unit of the company’s products are as follows: Product

Variable costs of manufacture (Rs.)

A B C

10.50 12.90 11.80

< Answer >

The company expects to produce and sell 45,000 units of A, 90,000 units of B, and 75,500 units of C annually. Company’s policy is to add a markup of 20 percent to each product’s total manufacturing costs to compute the tentative selling price. The selling prices of products A, B and C, if fixed costs are allocated on the basis of number of units produced, are (a) Rs. 15.30, Rs. 18.18 and Rs. 16.86 respectively (b) Rs. 18.18, Rs. 15.30 and Rs. 16.86 respectively (c) Rs. 15.30, Rs. 18.18 and Rs. 19.25 respectively (d) Rs. 12.53, Rs. 18.18 and Rs. 16.86 respectively (e) Rs. 15.30, Rs. 18.18 and Rs. 17.85 respectively. (2 marks) < Answer >

68. The data relating to Bhanu Ltd. for the month of March 2004 are as follows: Output (units) Wages paid for 18,000 hours Material purchased 5,000 kg

9,500 Rs. 49,500 Rs. 45,000

Variances : Particulars Labor rate Labor efficiency Labor idle time Material price Material usage (a) Rs.9.43 Rs.19.89.

Rs. 3,000 (A) 5,000 (F) 675 (A) 2,200 (F) 1,440 (F) The standard prime cost per unit is (b) Rs.12.00

(c) Rs.9.95

(d) Rs.10.47

(e) (2 marks)

69. ABC Ltd. has the following cost components for 75,000 units of product X for the month of March 2004: Raw materials Direct labor Manufacturing overheads Selling and administrative overheads

= =

= Rs.7,50,000 = Rs.6,07,500 Rs.2,50,000 (40% fixed) Rs.3,75,000 (70 % fixed)

The total costs to produce and sell 90,000 units in the month of April 2004 are (a) Rs.24,60,000 (c) Rs.23,86,760 Rs.23,06,500.

(b) Rs.24,56,760 (d) Rs.22,91,000

(e) (2 marks)

70. Satish Ltd. is currently working at 50% capacity and produces 10,000 units. At 50% working, the product cost is Rs. 180 per unit and it is sold at Rs. 200 per unit. At 60% working, raw material cost increases by 2% and selling price falls by 2%.

< Answer >

The unit cost of Rs. 180 is made up as follows: Particulars Rs. Material 100 Labor 30 Factory overhead 30 (40 % fixed) Administration overhead 20 (50 % fixed) The total profit at 60% level of capacity is (a) Rs.2,20,000 (d) Rs.2,25,000

(b) Rs.2,12,000 (e) Rs. 1,95,000.

(c) Rs.2,32,000 (2 marks)

END OF QUESTION PAPER

Suggested Answers Management Accounting – II (152) : April 2004 Section A 1.

Answer : (b) Reason : The volume variance is the under applied or over applied of fixed factory overhead. It is the difference between the budgeted fixed factory overhead and applied (standard) fixed factory overhead. The volume variance is not applicable in case of variable factory overhead. Other options (a), (c), (d) and (e) are not correct.

< TOP >

2.

Answer : (d) Reason : A budget in which a responsibility center manager must justify each planned activity and its estimated total cost is called Zero based budget. Other options are not correct.

< TOP >

3.

Answer : (b) Reason : Operation budgets normally cover a period of one year or less. Other options are not correct.

< TOP >

4.

Answer : (e) Reason : A fixed factory overhead volume variance is the difference between the budgeted fixed factory overhead and the overhead applied based on a predetermined rate and standard direct labor hours allowed for the actual output. Option (a) is incorrect. Option (b) is incorrect because the difference between actual direct labor hours and standard direct labor hours allowed is the basis of the variable overhead efficiency variance. Option (c) is incorrect because it is not the difference between actual production and standard production. Option (d) is incorrect because the difference between fixed factory overhead applied on the absis of standard allowed direct labor hours and for actual output the budgeted fixed factory overhead defines the total fixed overhead variances.

< TOP >

5.

Answer : (c) Reason : The materials price variance may be isolated at the time of purchase or at the time of transfer to production. It equals the actual quantity of materials purchased or transferred times the difference between the actual and standard unit prices. Hence, a favorable materials price variance means that materials were purchased at a price less than the standard price. Therefore, option (e) is not correct. Option (c) is correct. Option (a) and (b) are incorrect because no variance relates quantity purchased to quantity used. Option (d) is incorrect because the unfavorable quantity variance indicates the more materials were used than allowed by the standard. The material quantity variance equals the standard unit price times the difference between the actual quantity used and the standard quantity used and the standard quantity allowed for the actual output.

< TOP >

6.

Answer : (e) Reason : Life cycle costing estimates a product’s revenue and expenses over its expected life cycle. This approach is especially useful when revenues and related costs do not occur in the same period. It emphasizes the need to price products to cover all costs, not just those for production. Hence, costs are determined for all value chain categories: upstream ( R & D, design), manufacturing and downstream (marketing, distribution and customer service). The result is to highlight upstream and downstream costs in the cost planning process that often receive insufficient attention.

< TOP >

7.

Answer : (b) Reason : The optimal transfer price of a selling division should be set at a point that will have the most desirable economic effect on the firm as a whole while at the same time continuing to motivate the management of every division to perform efficiently. Setting the transfer price based on actual costs rather than standard costs would give the selling division little incentive to control costs. Option (a) is incorrect because inefficiencies are charged to the buying department. Options (c) and (d) are not correct, because by definition, cost based transfer prices are not adjusted by mark-up or ROI. Option (e) is incorrect because cost-based transfer price which provides the advantages of clarity and administrative convenience.

< TOP >

8.

Answer : (d) Reason : An investment center is the organizational type most like an independent business because it is

< TOP >

responsible for its own revenues, cost incurred and capital invested. The other types of centers do not incorporate all three elements. Option (a) is incorrect because a revenue center is responsible only for revenue generation, not for costs or capital investment. Option (b) is incorrect because a profit center is responsible for revenues and costs but not for invested capital. Option (c) is incorrect because a cost center is evaluated only on the basis of costs incurred. It is not responsible for revenues and invested capital. Option (e) is not correct because it is responsible for revenues and variable costs but not invested capital. 9.

Answer : (a) Reason : The labor price (rate) variance is the difference between the actual rate paid and standard rate times the actual hours. The difference may be attributable to a change in labor rates since the establishment of the standards, using a single average standard rate despite different rates earned among different employees, assigning higher-paid workers to job estimated to require lower-paid workers (or vice versa), or paying hourly rates but basing standards on piece work rates (or vice versa). The difference should not be caused by a union contract approved before the budgeting cycle because such rates would have been incorporated into the standards. Other options given in (b), (c), (d) and (e) are the causes for labor rate variance.

< TOP >

10.

Answer : (e) Reason : A budget manual describes how a budget is to be prepared. Items usually included in a budget manual are a planning calendar and distribution instructions for all budget schedules. Distribution instructions are important because once a schedule is prepared, other departments within the organization will use the schedule to prepare their own budget. Without distribution instructions, someone who needs a particular schedule may be overlooked. Therefore option (e) is correct.

< TOP >

11.

Answer : (e) Reason : The direct material usage budget and direct material purchases budget differ because of a change in the level of material stock. If stock is required to maintain in the production, material purchase should be more than the material usage. Therefore, (e) is correct.

< TOP >

12.

Answer : (c) Reason : If the company obtains discount for bulk purchases, the company can purchase more quantity of materials than requirements for cost saving. The high purchase of materials is not useful if the company wants to reduce the stock level. The low price of materials and high sales volume are not the reasons for high purchase of materials.

< TOP >

13.

Answer : (b) Reason : When actual production is less than the standard production it is an unfavorable material yield variance. This is the responsibility of the production department. This is not the responsibility of the purchasing, stores, engineering and inspection department. Therefore (b) is true.

< TOP >

14.

Answer : (c) Reason : The sales volume variance can be divided into the sales quantity variance and the sales mix variance. The sales quantity variance is the change in contribution margin caused by the difference between actual and budgeted volume, assuming that budgeted sales mix, unit variable costs, and unit sales prices are constant. Thus, it equals the sales volume variance when the sales mix variance is zero. In a multiproduct company, the sales mix variance is a variance caused by a sales mix that differs from that budgeted. For example, even when the sales quantity is exactly as budgeted, an unfavorable sales mix variance can be caused by greater sales of a low-contribution product at the expense of lower sales of a high-contribution product.

< TOP >

15.

Answer : (c) Reason : A flexible budget is essentially a series of several budgets prepared for many levels of sales of production. At the end of the period, management can compare actual costs or performance with the appropriate budgeted level in the flexible budget. New columns can quickly be made by interpolation or extrapolation, if necessary. A flexible budget is designed to allow adjustment of the budget to the actual level of activity before comparing the budgeted activity with actual results.

< TOP >

16.

Answer : (b) Reason : Cost of goods manufactured is equivalent to manufacturing costs incurred during the period, plus beginning work-in-process, minus ending work-in-process. A cost of goods manufactured budget is therefore based on materials, direct labor, factory overhead, and work-in-process.

< TOP >

17.

Answer : (d) Reason : A cash budget may be prepared monthly or even weekly to facilitate cash planning and control. The purpose is to anticipate cash needs while minimizing the amount of idle cash. The cash receipts section of the budget includes all sources of cash. One such source is the proceeds of loans.

< TOP >

18.

Answer : (d) Reason : Budgetary slack is the term referring to the underestimation of probable performance in a budget. With slack in a budget, a manager can achieve the budget more easily. Slack must be avoided if a budget is to have its desired effects. Other options are not correct.

< TOP >

19.

Answer : (a) Reason : McGregor’s Theory X is based on the conception that ‘The average human being has an inherent dislike of work and will avoid it if he can’. Because of this human characteristic of dislike for work most people must be coerced, controlled, and directed towards the achievement of goal. Option (b) is incorrect as this theory is based on principles of human motivation as revealed by Abraham Maslow. Option (c) is incorrect as it is set forth hierarchy of human needs. Option (d) and (e) are not correct.

< TOP >

20.

Answer : (c) Reason : The system of identification and communication that signals the manager when his attention is needed is known as management by exception. The system remains silent when attention of the manager is not required. The manager can devote attention only to those areas which require managerial action.

< TOP >

21.

Answer : (d) Reason : Strategic budget is a form of long range planning based on identifying and specifying organizational goals and objectives. The strength and weaknesses of the organization are evaluated and risk levels are assessed. The influences of environmental factors are forecasted to derive the best strategy for reaching the organization’s objectives. Other options are not correct.

< TOP >

22.

Answer : (d) Reason : A cost center is a responsibility center that is responsible for costs only. Of the alternatives given, variance analysis is the only one that can be used in a cost center. Variance analysis involves comparing actual costs with predicted or standard costs. Other options are not true.

< TOP >

23.

Answer : (e) Reason : Total quality management is often termed as a set of concepts and tools for getting all employees focused on continuous improvement in the eyes of the customer. It is neither quality control (a) nor cost control (b). Customer orientation is one of the core concepts of total quality management. TQM aims at eliciting greater employee commitment through shared decision making and introduce various forms of self management (d). This is one of the elements in TQM.

< TOP >

24.

Answer : (a) Reason : Responsibility accounting holds managers responsible only for factors under their control. For this purpose, operations are organized into responsibility centers. Costs are classified as controllable and non-controllable, which implies that some revenues and costs can be changed through effective management. If a manager has authority to incur costs, a responsibility accounting system will charge them to the manager’s responsibility center. So, this type of accounting is known as Responsibility accounting.

< TOP >

25.

Answer : (e) Reason : For monitoring the overall financial and physical performance of the organization, information relating to breakdown of sales, region-wise and customer-wise, return on investment, production levels of various products, cash structure is required to the corporate management. Therefore, option (e) is correct.

< TOP >

26.

Answer : (c) Reason : The information pertaining to technological advances and new product development is required to corporate management of the organization. Other information like capacity utilization, productivity of labor and machinery, overtime payments and marketing and distribution costs is required to operating management of the organization.

< TOP >

27.

Answer : (b)

(b)

Reason : Value chain requires an external focus unlike conventional management accounting. Hence (b) is false. Value-chain is the linked set of value-creating activities from the basic raw material sources for suppliers to the ultimate end-use product delivered into the final customer’s hands. No firm is likely to span the entire value chain. Typically, a firm is only a part of the larger set of activities in the value delivery system. Each firm must be understood in the context of the overall value chain of value-creating activities. 28.

Answer : (b) Reason : Scrap and costs of spoiled units that cannot be salvaged are examples of internal failure costs. These are the costs associated with materials and products that fail to meet quality standards and result in manufacturing losses. These defects are identified before the goods are shipped to customers. Hence the answer is (b). Appraisal costs are incurred to ensure that materials, products and services meet quality standards. They begin with the inspection of raw materials and parts from vendors. External failure costs are the costs incurred when inferior-quality products or services are sold to customers. Prevention costs are the costs incurred to reduce the number of defective units produced or the incidence of poor-quality service. Committed cost is fixed costs which results from the decision of the management in the prior period and is not subject to the management control in the present on a short-run basis.

< TOP >

29.

Answer : (c) Reason : The maturity phase begins after sales cease to rise exponentially. The causes of the declining percentage growth rate is the market saturation. Sales growth continues but at a diminishing rate because of the diminishing number of potential customers. This is usually the longest stage in the life cycle and most existing products are in this stage.

< TOP >

30.

Answer : (e) Reason : Only a constrained resource has shadow price. Where resources are not fully utilized, shadow price is zero. The shadow price can be used only when the resources are scarce. Hence the answer is (e). The use of shadow prices is incompatible with the philosophy of decentralization through divisionalisation. To derive at the shadow prices one has to obtain the dual solution to the mathematical programming model developed for solving the production planning problem of the buying division. A great deal of data like the market data for the buying division, cost data for the selling and buying divisions and capcacity data for both the divisions are required. Hence assimilating the data and application of the model becomes a highly centralized affair. Operating managers do not understand and appreciate the concept of shadow price.

< TOP >

31.

Answer : (d) Reason : A difficulty in applying ABC is that, whereas the unit level, batch level and product level costs of activities pertain to specific products or services, facility level costs do not. Thus facility level costs are not accurately assignable to products. The theoretically sound solution is to treat them as period costs. Nevertheless, Organizations that apply ABC ordinarily assign them to products to obtain a full absorption costs suitable for external reporting. However, for internal purposes, facility level costs should be treated as period costs to avoid distorting decisions about cost efficiency, pricing and profitability.

< TOP >

32.

Answer : (d) Reason : Target pricing and costing may result in a competitive advantage because it is customeroriented approach that focuses on what products can be sold at what prices. Hence (d) is the answer. It is also advantageous because it emphasizes control over costs prior to their being locked in during the early links in the value chain. The company sets a target price for a potential product reflecting what it believes consumer will pay and competitors will do. After subtracting the desired profit margin, the long-run target cost is known. If current costs are too high to allow an acceptable profit, cost-cutting measures are implemented or the product is abandoned. The assumption is that target price is the constraint. Option (a) is incorrect because target pricing is used on products that have not yet been developed. Option (b) is incorrect because target pricing includes all costs. Option (c) is incorrect because target pricing can be used in any situation but is most likely to succeed when costs can be well controlled. Option (e) is not correct because it is difficult to use with complex products that require many subassemblies such as automobiles. This is because tracking costs becomes too complicated and tedious, and cost analysis must be performed at so many levels.

< TOP >

33.

Answer : (b) Reason : Top-to-bottom budget is also known as imposed budget. In this type of budget, the budgeted quantities are obtained from the top level managers and then communicated downward to lower level managers. Lower level managers do not participate in this type of budget. Hence

< TOP >

the answer is (b). In participative budget, estimations of lower level managers are coordinated and communicated upward to the top-level managers. Zero-based budgeting is a method of budget review and evaluation that requires all projects and programs to justify all resources. Manpower budget will take an overall view of the organizations needs for manpower for all areas of activity for a period of years. Master budget is a budget which is prepared from and summarizes the functional budgets. 34.

Answer : (c) Reason : Basic standards are known as measurement standards. These are established at a particular time and remain unchanged over a period of time. These standards are not revised frequently, but if they are revised, it is only due to changes in specification of materials and technology. They may also be revised if there are substantial price changes.

< TOP >

35.

Answer : (c) Reason : Full-cost pricing is useful in case the company lacks knowledge of demand curve. Hence (c) is false. It is prone to distortion by accounting misapplications such as undue reliance upon historical cost, an unjustifiable inclusion of manufacturing overhead based on predetermined rates, and an ignorance of the effect of volume on unit costs and profits. In full-cost pricing, the price is determined by adding a mark-up on full cost. Cost plus pricing is fairer to both buyers and sellers. Sellers do not take advantage of buyers when the latter’s demand becomes acute. It ignores vital economic considerations of demand and competition.

< TOP >

36.

Answer : (d) Reason : The relationship between the budgeted number of working hours and the maximum possible working hours in a budgeted period is capacity usage ratio. Hence the answer is (d). The standard hours equivalent to the work produced expressed as a percentage of the actual hours spent in producing that work is efficiency ratio. The activity ratio is the number of standard hours equivalent to the work produced expressed as a percentage of the budgeted standard hours. Calendar ratio is the relationship between the number of working days in a period and the number of working days in the relative budget period. Capacity utilization ratio is the relationship between the actual hours in a budget period and the budgeted working hours in a given period.

< TOP >

37.

Answer : (c) Reason : The correct answer is (c). A flexible budget is essentially a series of several budgets prepared for various levels of operating activity. A flexible budget facilitates comparison of actual results with budget figures. (a) and (b) are not correct because accounting for interest and inflation is the same in static budgets. (d) is not correct because the purpose of the flexible budgets is to provide plans for different levels of activity. (e) is not correct because a flexible budget is actually a series of static budgets for different operating activities.

< TOP >

38.

Answer : (e) Reason : A budget is a means of control because it sets standard guidelines with which actual performance can be compared. The feedback provided by comparison of actual and budgeted performance reveals whether a manager has used company assts efficiently. If a budget is to be used for control purposes, however, the accounting system must be designed to produce information required for at the control process. Further, the budgeting and accounting system must be related the organizational structure. So that variances twill be assigned to the proper individuals. Option (a) is incorrect because the company should already be using forecasting procedures if the budget is being used as planning tool. Option (b) is not correct because a budget director and committee are needed even if a budget is to be used only for planning. Option (c) and (d) are incorrect because daily reporting is usually not necessary.

< TOP >

39.

Answer : (e) Reason : The budget period should be long enough to cover complete production of various products. For business of a seasonal nature, the budget period should cover atleast one entire seasonal cycle. The budget period should be long enough to allow for the financing of production well in advance of actual needs as it should provide adequate time to arrange the funds for production and other purposes. Thus the answer is (e).

< TOP >

40.

Answer : (c) Reason : Fixed overhead cost variance = Actual fixed overhead cost ~ Applied fixed overhead cost. Other options mentioned in (a), (b), (d) and (e) are not correct.

< TOP >

41. Answer : (e) Reason : Actual material consumption: Particulars Stock as on March 01, 2004 Kg Add: Purchases during the month of March 2004 Kg Less: Stock as on March 31, 2004 Kg Material consumed during the month of March 2004 Kg Total material consumption = 2,050 + 2,480 = 4,530kg. Standard cost: Quantity (kg.)

Price (Rs.)

Amount (Rs.)

X

2,000

5

10,000

Y

2,500

4

10,000

X 80

Y 100

2,000

2,500

2,080 30

2,600 120

2,050

2,480

4,500 Loss:

675

Output

3825

20,000

Standard yield =

Standard output 85 kg. ×Actual input = × 4,530kg.= 3,850.5kg. Standard input 100 kg.

Material yield variance = Standard rate of output (Actual yield – Standard yield) =

Rs.20,000 × (3,850.5 kg. - 4000 kg.) 3825

= Rs.781.70 (F)

42. Answer : (c) Reason : Particulars

Rs.

Total standard cost (1,000 units @ Rs.20)

20,000

Less: Standard direct labor cost

5,000

Standard overhead cost (500hours @ Rs.3)

1,500

Standard cost of raw material

13,500

standard quantity of raw material required Standard cost of raw material used Rs.13,500 = Standard rate per kg. of raw material Rs.10

= = 1,350 kg. Material usage variance = Standard rate (standard quantity – actual quantity) i.e. Rs.860(A) = Rs.10 x (1,350kg. – actual quantity) Actual quantity = 43. Answer : (b) Reason :

< TOP >

(Rs.10 × 1,350 kg.) + 860 =1,436 kg. 10

Total

Particulars

Units

Degree of completion

Completed stock: From opening work-in-progress Current production (1370-200) Closing work-in-progress Total

200 1,170 350

40 % 100 % 40 %

Overheads 80 1,170 140 1,390

Budgeted rate per unit = Rs.120 No. of direct labor hours per unit = 3 Budgeted rate per hour = Rs.40 Standard hours for actual production = 1,390x 3 = 4,170hours Fixed overhead efficiency variance = (Standard hours for actual production – Actual hours) x budgeted rate per hour = ( 4,170hours – 3,880hours ) x Rs.40 = Rs.11,600(F) 44. Answer : (e) Reason : Fixed costs (in Rs.)

15,00,000

Return on capital employed (Rs.50,00,000 x 18%) (in Rs.)

9,00,000

Residual income desired (in Rs.)

6,00,000

Total desired contribution (in Rs.) 30,00,000 Contribution per unit from outside sales = Rs.120 – Rs.78 = Rs.42 per unit Total contribution from outside sales = Rs.42 per unit x 65,000 units = Rs.27,30,000 Minimum contribution to be earned from supply to division B = Rs.30,00,000– Rs.27,30,000= Rs. 2,70,000 Contribution per unit on additional 18,000 units

Rs. 2,70,000 18,000 units

= =

Variable cost for minor modification Minimum transfer price per unit to be quoted

=

Rs.15 per unit = Rs.7 per unit Rs.78 + Rs.15 + Rs.7 =

Rs.100 45. Answer : (b) Reason : Total machine hours = (300 2) + (520 5) + (450 4) = 5,000 hours Machine overhead charges = Rs.52,500 / 5,000 hours = Rs.10.50 per hour Set-up costs = Rs8,330/ 17 (i.e. total number of set-ups) = Rs.490 per set-up Material ordering cost = Rs.6,850/10 operations = Rs.685per operation Material handling cost = Rs.11,340/ 27 operations = Rs.420 per operation ×

×

×

Overhead cost for product B: Particulars Machine overhead charges 5 Rs.10.50 Set-up costs 6 Rs.490 / 520 Material ordering cost 4 Rs.685 / 520 Material handling cost 10 Rs.420 / 520 Total overhead cost Hence the total overhead cost is Rs.71.50 per unit of B. ×

×

×

×

46. Answer : (c) Reason :

Rs. 52.50 5.65 5.27 8.08 71.50

Rs.

< TOP >

Direct material Direct labor Factory overheads (50% of direct labor) Factory cost Administrative overheads (20% of factory cost) Selling and distribution expenses (20% of factory cost + 15%)= (5,70,000 × 20% × 115%)

3,00,000 1,80,000 90,000 5,70,000 1,14,000 1,31,100 8,15,100 2,03,775 10,18,875

Profit 20% on sales (i.e. 25% on cost) Sales

< TOP >

47. Answer : (a) Reason : units 24,750 1,100 25,850 1,200 24,650

Sales (total of all quarters) Add: Closing stock Less: opening stock Total production for next year

kg 49,300 3,500 52,800 2,800 50,000

Raw material required for production (24,650units ×2) Add: Closing stock Less: opening stock Raw material to be purchased Quarter I II III

% of rawmaterial 30% 50% 20%

Rawmaterial (kg.) 15,000 25,000 10,000

Price per kg. (Rs.) 12 13 14

Amount (Rs.) 1,80,000 3,25,000 1,40,000 6,45,000

Total amount of rawmaterial to be purchased is Rs.6,45,000 48. Answer : (c) Reason : Overhead expenditure variance = Overhead cost variance ~ Overhead volume variance = Rs.1,880(A) ~ Rs.1,050 (A) = Rs.830(A) Actual overheads incurred = budgeted overheads ~ overheads expenditure variance = Rs.16,000~ Rs.830(A) = Rs.16,830

< TOP >

Actual overheads incurred Rs.16,830 = =885.8 hours Actual rate of recovery Rs.19

Actual hours = Overheads capacity variance = Standard rate × (Actual hours – budgeted hours) = Rs.16,000 800

× (885.8 hours – 800 hours) = Rs.1,716 (F). < TOP >

49. Answer : (a) fixed overhead cost Rs.1,10,000 = =Rs.20 per unit Production (Units) 5,500 units

Reason : Fixed overhead recovery rate = Particulars Rs. Budgeted fixed overhead 1,10,000 Add: Fixed overhead expenditure variance 2,500 Actual fixed overhead 1,12,500 Absorbed overhead = Actual fixed overhead – under-absorbed overhead = Rs.1,12,500 – 12,000= Rs.1,00,500 Actual production =

Overhead absorbed Rs.1,00,500 = Fixed overhead rate Rs.20

50. Answer : (d) Reason : Standard/ Budgeted data

= 5,025 units < TOP >

Budgeted fixed overheads (Rs.) Budgeted output units Budgeted hours Budgeted days Standard labor hours per unit Standard hours worked per day Standard rate per unit (Rs.) Standard rate per hour (Rs.) Standard fixed overhead rate per day (Rs.)

90,000 2,000 10,000 25 5 400 45 9 3,600

Actual fixed overheads (Rs.) Actual output units Actual hours Actual days

80,000 1,700 8,580 22

Actual data

The total overhead variance = (Fixed overhead recovered on actual output – Actual fixed overhead incurred) = (1,700 units x Rs.45 – Rs.80,000)= Rs.3,500 (A) Calendar variance = Standard fixed overhead rate per day (Actual days – Budgeted days) = Rs.3,600 (22 days- 25 days) = Rs.10,800 (A)

< TOP >

51. Answer : (c) Reason : Particulars Fixed cost (Rs.8,50,000 + Rs.10,00,000) Add: expected return (Rs.15,60,000 + Rs.5,00,000) ×20% Contribution Total labor hours: Product A: (4× 14,000 units) Product B: (4× 16,000 units) Total labor hours Contribution per labor hour = Calculation of selling price:

Rs.22,62,000 1,20,000 hours

Rs. 40.00 32.00 75.40 147.40

52. Answer : (d) Reason : Total quantity of actual sales = 2,400+2,450+3,250 = 8,100kgs. Sales Mix variance = Standard rate × (Actual quantity- Revised Standard quantity) A 15 × B 18 × C 20 × Total

  8,100  × 2, 500  2, 400 −   8, 000     8,100  × 2, 600  2, 450 −   8, 000     8,100  × 2, 900  3, 250 −   8, 000  

1,20,000

= Rs.18.85 per labor hour.

Particulars Variable cost other than labor (Rs.5,60,000 / 14,000 units) Direct labor (Rs.8×4 hours) Contribution (Rs.18.85 ×4) Selling price

53. Answer : (d) Reason :

fixed

< TOP >

1,968.75 (A) = 3,285.00 (A) = 6,275.00 (F) = 1,021.25 (F) < TOP >

P

Particulars Direct material Direct labor Factory overheads Total factory cost Administrative overheads Selling overheads Total cost per unit

Total cost (Rs.) 60.00 35.00 28.00 123.00 12.30 8.00 143.30

Q Variable cost (Rs.) 60.00 35.00 14.00 109.00

Total cost (Rs.) 45.00 40.00 32.00 117.00 11.70 10.00 138.70

4.80 113.80

Variable cost (Rs.) 45.00 40.00 16.00 101.00 6.00 107.00

P – 143 .30 × 8,000 = Rs.11,46,400 Q – 138.70 × 18,000 = Rs.24,96,600 Particulars Fixed capital Working capital

Rs. 15,00,000 ×

P – 11,46,400 ×

3 12

2,86,600 = 8,32,200

4 12

Q – 24,96,600 Total Capital employed Expected ROI 20% Expected Return = 26,18,800 × 20% = Rs.5,23,760

26,18,800

54. Answer : (d) Reason : Minimum transfer price, if the division is in a full capacity and product is in a perfectly competitive market, is the sale price of Rs.300, i.e. Rs.18,00,000 ÷ 6,000 units = Rs.300 per unit.

< TOP >

55. Answer : (d)

< TOP >

Reason : Particulars Expected sales (units) Production (units) Raw material required for production (units) Amount to be paid for raw material (in Rs.) Payment to creditors (in Rs.) Particulars Expected sales (units) Sales (in Rs.) Cash sales (in Rs.) Collection from debtors (in Rs.) Particulars Cash sales Collection from debtors Less: Payment to creditors Other expenses Cash surplus

May 2004 12,000 7,80,000 3,90,000

May 2004 12,000 6,000+7,000 = 13,000 26,000 1,30,000

June 2004 14,000 7,000+6,500 = 13,500 27,000 1,35,000 1,30,000

June 2004 14,000 9,10,000 4,55,000 3,90,000

July 2004 13,000 8,45,000 4,22,500 4,55,000

Rs. June 2003 4,55,000 3,90,000 1,30,000 2,60,000 4,55,000 < TOP >

56. Answer : (b) Reason : Particulars Actual cost Less: Adverse material price variance Actual purchases at standard price

Rs. 15,904 224 15,680

Standard price =

Rs.15,680 560 kg.

= Rs.28 < TOP >

57. Answer : (a) Reason : Return on investment =Asset turnover × Profit margin = 1.85×0.35 = 0.65 58. Answer : (c) Reason : Total fixed cost = Expected profit = Variable cost at 80% level (80% x 1,50,000 units x Rs.14) = Total price = Per unit price at 80% level

< TOP >

Rs. 8,00,000 Rs. 4,00,000 Rs.16,80,000 Rs.28,80,000 Rs28,80,000 1,20,000 units

=

= Rs.24 < TOP >

59. Answer : (a) Reason : Computation of prime cost Rs. Sales (40,000 units) Less: Profit margin – 20% Cost of sales – (80% of Rs.14,4,000) Less: Variable overheads – Semi-variable overheads – Fixed overheads – Prime cost Semi-variable overheads: Change in cos t Change in units

Variable cost =

= =

At 40,000 units Fixed cost =

14,40,000 2,88,000 11,52,000 Rs.2,40,000 Rs.2,60,000 Rs.2,00,000

7,00,000 4,52,000

Rs.3,00,000-Rs.2,60,000 50,000 units-40,000 units Rs.40, 000 10, 000 units

= Rs.4per unit

Total cost – Variable cost

=

Rs.2,60,000 – 40,000 units × Rs.4

=

45,000 units × Rs.4 + Rs.1,00,000 = Rs.2,80,000

= Rs.1,00,000

At 45,000 units Total cost

Computation of differential cost of production of 5,000 additional units (i.e. 10% of normal capacity): Element of cost Prime cost – (Working Note 1) Variable overhead Semi variable overhead (Working Note 2) Fixed overhead

40,000 units (Rs.) 4,52,000 2,40,000 2,60,000 2,00,000 11,52,000

45,000 units (Rs.) 5,08,500 2,70,000 2,80,000 2,00,000 12,58,500

Rs.1, 06, 500 5, 000

Cost per unit of new order = Profit margin 25% (20% on sale = 25% on cost) Minimum selling price per unit 60. Answer : (c) Reason : Target cost = Selling price at capacity – 20% profit margin

= =

Differential cost for 5000 units (Rs.) 56,500 30,000 20,000 – 1,06,500 Rs.21.30 Rs. 5.33 =

Rs.26.63 < TOP >

Price (Rs.) 625 550 475

Demand (Units) 1,75,000 3,50,000 7,00,000

Target cost

=

Rs.475 –

20% × Rs.475 = Rs.475 – Rs.95 = Rs.380 < TOP >

61. Answer : (a) Reason : Total labor cost 5 x Rs. 6,000 = Rs. 30,000 Cost of parts = Rs. 45,000 Total variable cost Rs.75,000 Transfer profit = Rs. 20,000 Fixed cost = Rs. 25,000 = Rs. 45,000 Mark up %

=

Rs. 45,000 ÷ Rs. 75,000 = 60%

Mark up on labor cost

=

60% of Rs. 30,000 = Rs. 18,000 < TOP >

62. Answer : (a) Reason : Activity ratio

= =

S tan dard hours for actual producation Budgeted hours 4,440 hours 4,000 hours

× 100

× 100 = 111%

63. Answer : (e) Reason : Using production related budgets, units to produce equals budgeted sales + desired ending finished goods inventory + desired equivalent units in ending work-in-process inventory – beginning finished goods inventory – equivalent units in beginning work-in-process inventory. Therefore, in this case, units to produce is equal to 5,00,000 + 1,50,000 + 60,000 – 80,000– 50,000 = 5,80,000.

< TOP >

64. Answer : (b) Reason : Collections from July 2004 cash sales will be half of total sales, or Rs. 50,000. From April Rs. 50,000 of credit sales, collections should be 10% or Rs.5,000. From May Rs. 1,00,000 of credit sales, collections should be 20% or Rs.20,000. From June Rs. 1,50,000 of credit sales, collections will be 70% or Rs. 1,05,000. Thus, total collections will amount to Rs. 1,80,000.

< TOP >

65. Answer : (b) Reason : Flexible budget for overhead.

< TOP >

Particulars 1.

2.

At 80% capacity level (Rs.)

Variable overhead: (a) indirect labor (b) indirect material Variable portion of semi-variable overhead: (a) power (b) repairs and maintenance

24,000 12,000 8,000 640

Total variable (A) 3. Fixed portion of semi-variable overheads: (a) power (b) Repairs and maintenance 4. Fixed overhead: (a) Depreciation (b) Insurance (c) Others Total Fixed (B) 5. Total overheads (A+B) 6. Estimated direct labor hrs. 7. Overhead recovery rate per direct labor hour (5÷6)

44,640 3,500 840 9,000 4,000 3,000 20,340 64,980 1,32,000 0.492

66. Answer : (e) Reason : Statement showing the determination of selling price of seasoned timber as on March 31, 2004: Particulars

Qantity (cft)

Cost of timber logs at the rate of Rs.160 per cft. Seasoning expenses for 3 months: Rent (Rs. 14,200 x 70%) Salaries of 6 guards (Rs. 300 x 6 x 3 x 70%) Incidental expenses (Rs. 900 x 3 x 70%) Administration overheads (Rs. 16,000 x ¼ x 70%)

2,000

Total

2,000

Amount (Rs.) 3,20,000 9,940 3,780 1,890 2,800

Less: Normal loss at the rate of 8%

3,38,410

160

Total(net) Profit margin (20% of cost)

1,840

Total selling price

3,38,410 67,682 4,06,092

Selling price per cft (Rs. 4,06,092 ÷ 1,840)

220.70 < TOP >

67. Answer : (a) Reason : Particulars Total fixed costs (Rs.) Number of units Fixed cost per unit (Rs.) Variable cost per unit Total unit cost (Rs.) Markup – 20% Selling price (Rs.)

< TOP >

A

B

C

45,000 2.25 10.50 12.75 2.55 15.30

90,000 2.25 12.90 15.15 3.03 18.18

75,500 2.25 11.80 14.05 2.81 16.86

Total 4,73,625 2,10,500

68. Answer : (d) Reason : Actual cost Standard material cost = Actual material cost + Favorable material price variance + Favorable material usage variance Standard wages = Actual wages paid + favorable labor efficiency variance – adverse labor rate variance – adverse labor idle time variance

< TOP >

Particulars Standard material cost (45,000 + 2,200 + 1,440) Standard wages (49,500+5,000 – 3,000 – 675)

Rs. Total

Rs. Per unit

48,640 50,825

5.12 5.35

Total

10.47 < TOP >

69. Answer : (e) Reason : Variable cost : Raw materials = Rs. 10.00

Rs.7,50,000 ÷ 75,000 units

=

Direct labor Rs. 8.10

Rs.6,07,500 ÷ 75,000 units

=

=

Manufacturing overheads = 60% of Rs.2,50,000 ÷ 75,000 units Rs. 2.00 Selling and administrative overheads = 30% of 3,75,000 ÷ 75,000 units = 1.50 Rs. 21.60 Fixed cost = = Cost of 90,000 units =

= Rs.

= 40% of Rs.2,50,000 + 70% of Rs.3,75,000 Rs.1,00,000+ Rs.2,62,500 Rs.3,62,500 = 90,000x Rs. 21.60 + Rs. 3,62,500 Rs. 19,44,000 + Rs. 3,62,500 = Rs. 23,06,500. < TOP >

70. Answer : (b) Reason : Statement showing profit at different capacity level Capacity levels 50 %(Rs.)

60%(Rs.)

10,000

12,000

Selling price per unit

200

196

Material

100

102

Labor

30

30

Factory overhead

18

18

Administration overhead

10

10

158

160

42

36

Total contribution

4,20,000

4,32,000

Less : Fixed cost

2,20,000

2,20,000

Profit

2,00,000

2,12,000

Units

Total marginal cost per unit Contribution per unit

Incremental profit

12,000 < TOP OF THE DOCUMENT >