POWER SHORTAGE & DISEMPOWERIN G SOLUTIONS Wilson M. Fortaleza Freedom From Debt Coalition June 23, 2009, Davao City
A FORUM ON THE DCWD-HEDCOR ISSUE BATTLE OVER THE PANIGAN-TAMUGAN RIVERS OF DAVAO CITY
FDC frameworks On Power The power industry, due to its inherent nature, should be placed at the realm of public domain and its products and services remain as public goods. The principle strongly pursues the progressive role of the State – that it cannot and should not consign the industry entirely to private hands and let the market determine what is good for the public. FDC is also for a power shift – from dirty to clean and renewable power
FDC frameworks On Water Upholding the people’s right to water Water, the same with power, are public goods that should remain in public domain
Power Situation As of Dec. 2007 Installed generating capacity is 15,937 MW Dependable capacity is 13,205 MW Source: DOE
Power Situation PEAK DEMAND
Source: PDP-DOE
Power Situation ENERGY CONSUMPTION
Source: PDP-DOE
Power Situation GRID CONSUMPTION
Source: PDP-DOE
Power Sales
7,890 GWh
Source: DOE Power Development Plan,
Demand forecast Grid
2 006
2 007
2 008
2009
2010
Luzon
6,72 6,98 7,25 7,552 7,878 8 1 2
Visayas
1,15 1,21 1,28 1,364 1,448 4 4 9
Mindanao 1,29 1,36 1,44 1,525 1,620 3 3 0 PHILIPPI NES
9,17 9,55 9,98 10,44 10,94 5 8 1 1 6
Source: Transmission Development Plan,
Demand forecast (Mindanao)
Source: DOE Power Development Plan,
How is demand projected?
Historically, government’s demand projection is poor (Top to bottom approach). Poor planning is also a factor. DOE makes use of an aggregation of the demand projection from the Distribution Development Plans(DDPs) from distribution utilities plus projections from directlyconnected non-utilities. TransCo’s forecast is based on econometric modeling with Gross Domestic Product (GDP) as main explanatory variable.
Supply-Demand forecast
Source: DOE Power Development Plan,
Supply-Demand forecast Demand projection is always on the “High Demand Case” Both cases show a radical decline in the demand forecast for Luzon, owing to the very low projection of the Meralco, which demand covers around 70% of the aggregate demand in the Luzon grid. Source: Transmission Development Plan, 2007
Supply-Demand forecast
Source: DOE Power Development Plan,
Supply-Demand forecast
Source: DOE Power Development Plan,
Supply-Demand forecast
Source: DOE Power Development Plan,
Dependable Capacity in Mindanao
Source: DOE Power Development Plan,
“Teetering” into recession
SOURCE: NSCB MAY 2009
Sharp Fall GDP AND GNP (in million PhP)
SOURCE: NSCB MAY 2009
All industry performance GDP by industry origin (in million PhP)
SOURCE: NSCB MAY 2009
The cost of wrong projections Consumers are made to pay the full cost of installed capacities whether they are consumed or not, or even those that were not generated at all. We also pay for all the risks The case of the IPP contracts which we were made to pay through the PPA.
The Mindanao Grid
Source: Transmission Development Plan,
The Mindanao Grid In TransCos CAPEX Program approved by the ERC, the program is mainly driven by load growth . Of the estimated P56.23-B, 82% or P46-B are for projects necessary to meet load growth within the planning horizon. (40% for Luzon, 28% for Visayas, and 32% for Mindanao. For the projects for implementation, however, Capex driven by load growth is not as high as the ongoing projects as it accounts for only 58%. Source: Transmission Development Plan, 2007 In Mindanao, all of the projects
for
“Dropped” inter-connection project
Source: Transmission Development Plan, 2007
TransCo’s ongoing projects in the Mindanao Grid Abaga-Kirahon 230 kV Transmission Line to provide additional transmission corridor to the 676.4 MW Agus Hydro Complex which accounts for 70% of total dependable capacity for the Mindanao Grid. The Agus 2-Kibawe and AbagaTogoloan 138 kV lines serve as Agus’ link to the grid. The bombing of Agus 2-Kibawe line resulted in huge power swing to the other corridor. The Abaga-Togoloan line will not be able to carry 70% of the 90% load as a result of the Agus 2Kibawe outage. The project is expected to be completed June Source: Transmission Development Plan, 2008 and would serve as initial step in
Power planning/Plant Sitting Choosing as site for a new power plant is an important part of electric system planning. There are plants that are site-specific such as hydro, geothermal, wind among others. Social-acceptability must also be considered.
War over water "The wars of the next century will be about Ismail Serageldin, water."
Vice president of the World Bank
Water for ALL Power can be produced from many sources Although the globe is made up mainly of water, potable water is not a finite resources.
Global consumption of water is doubling Available every 20 years, more freshwater amounts to less than one-half than twice the rate of of 1 percent of all the human population growth. water on earth. The
Making a choice Why make us choose between a dark and waterless future when the answer is obviously clear:
Nobody desires such kind of world!
Is there a win-win solution? “Kung ayaw may dahilan, Kung gusto maraming paraan”
A proposal for a MultiStakeholders Development Planning Process Panay Case (Separate Presentation) Naga Case (Participatory Planning)
Thank You!
End of presentation