Understanding Power Quality Iiee Csc Ust

  • November 2019
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Understanding Power Quality Iiee Csc Ust as PDF for free.

More details

  • Words: 2,287
  • Pages: 23
Understanding Power Quality February 7, 2007 University of Sta. Tomas

Marvin Ryan G. Bathan Power Quality Team Power Services / MERALCO

Objectives • To understand the concept of EMC and what specifically becomes a power quality problem • To establish collaboration among involved parties in dealing with PQ problems

Objectives • To have a common understanding of power quality and its attendant terminology • To be acquainted with the typical causes and solutions to specific power quality problem

1

Power Quality Power Quality - the quality of the voltage, including its frequency and the resulting current that are measured in the Grid, Distribution System, or any User System

Quality?

Quality is a relative term Power Quality is relative to the sensitivity of a device, equipment, or system

Power Quality Problem "Any power problem manifested in voltage, current, or frequency deviation that results in failure or mis-operation of utility or end-user equipment."

2

PQ Problem Illustrated Failure

Normal

Failure

Power Quality Issues Power quality issues may be viewed from three different perspectives: 2 End-user 2 Utility 2 Equipment Manufacturer

PQ Problem Solution: A joint effort • Solution to PQ problems is not the responsibility of only one party. • The solution is a concerted effort between the power supplier, the electricity user, and equipment manufacturer.

3

MERALCO Power Quality Team Profile: PEE – 1 REE – 5 RME – 1 MBA – 1 Trainings: Attended various PQ conferences/trainings here and abroad Seminars conducted: Regular speaker in PQ seminars and lectures

PQ Services

PQ Services

4

PQ Services

PQ Services

C A S E S T U D Y

Voltage Sag Problem Voltage Unbalance Problem Transient Harmonics Interesting

5

Background • series of compressor breakdowns • 5 replacements since the installation of their 3 compressors • Refrigeration experts says that the power supply caused the breakdown • Customer requested for technical assistance in characterizing their power supply

Simplified Schematic Diagram S1 R1 S2 R2 S3 R3

64% FLA

• Compressor - 230Vac, 3-phase,Voltage 60Hz Current Compressor S S S R R R L –L L –L L –L 1 44.8 44.1 43.5 46.7 41.0 75 48.0 FLA, 450 LRA • Contactors - 240 Vac, 1

2 3

31.5 39.7

2

35.2 39.7

3

34.6 38.0

1

31.5 36.7

2

35.9 40.0

3

35.2 37.9

1

2

228.3

2

3

232.8

3

1

228.3

Voltage Protection • Programmable Voltage Monitor • ±10% over and under voltage setpoint • 5% voltage unbalance setpoint

6

Compressor 3 Inrush Current 80 Amperes. Loads running were the AHU and condenser.

180 Amperes. Represents the current drawn by the AHU, condenser, and compressor. 760 Amperes. Compressor #3 was started.

Compressor 1 Inrush Current 32 A

60 A

320 A

Compressor 1 Inrush Current

30 A 70 A

350 A

7

RMS Voltage Variation V RM S A B (V)

RMS Voltage Profile

V RM S B C (V) V RM S CA (V)

275 265 Voltage

Transformer tap change.

Overvoltage incidents.

255 245 235 225 9/16/04 7:23

9/15/04 10:23

9/14/04 13:23

9/13/04 16:23

9/12/04 19:23

9/11/04 1:33

9/11/04 22:23

9/9/04 6:33

9/10/04 3:33

9/8/04 9:33

9/7/04 12:33

9/6/04 15:33

9/5/04 19:00

9/4/04 1:00

9/4/04 22:00

9/3/04 3:00

9/2/04 6:00

9/1/04 9:00

8/31/04 12:00

8/30/04 15:00

215

Date & Tim e

RMS Voltage Variation

Monitoring Site Compressor 3 Compressor 1

Minimum 95.67% 96.42%

Average 103.79% 101.80%

Maximum 112.31% 106.61%

Count 264 141

Voltage Unbalance

Minimum

Average

Maximum

Count

Compressor 3

Monitoring Site

0.08%

0.62%

1.09%

264

Compressor 1

0.16%

0.50%

0.98%

141

8

Voltage & Current Harmonics • Maximum Voltage THD • Average Voltage THD

» »

• Maximum Current TDD • Average Current TDD

3.88% 2.06%

» 10.72% » 1.97%

Compressor Cycling Compressor 3 Number of Starts 30-Aug-04* 6 31-Aug-04 20 1-Sep-04 20 2-Sep-04 4 3-Sep-04 1 4-Sep-04 1 5-Sep-04 0 6-Sep-04 1 7-Sep-04 2 8-Sep-04 1 9-Sep-04 3 10-Sep-04** 2 Date

The number of start and stops the compressor makes could be greater that those listed in the table!

*Started at 3:30 PM **Ended at 3:48 PM

Compressor Cycling Compressor 1 Date Number of Starts 10-Sep-04* 7 11-Sep-04 10 12-Sep-04 0 13-Sep-04 30 14-Sep-04 35 15-Sep-04 31 16-Sep-04** 18

*Started at 3:48 PM

**Ended at 1:08 PM

9

Causes of Intermittent Cycling

• • • •

Too sensitive Voltage protection Erratic operation of low pressure switch Insufficient refrigerant Closed suction service valve

Causes of Intermittent Cycling • Partially open discharge valve • Insufficient fluid flowing through the condenser • Presence of air in the system

Conclusion • Power supply characteristics conforms with the PDC recommended limits and therefore could not have caused the compressor breakdowns. • It is the intermittent cycling of the compressors that lead to its premature failure.

10

Recommendation

Coordinate closely with your supplier to address the intermittent cycling of the compressors.

General PQ Evaluation Procedure Ξ Ξ Ξ Ξ Ξ

Problem Category Identification Power Measurements & Data Collection Solution Range Identification Solution Evaluation Optimum Solution

Solution Range Identification

   

Equipment Design/Specification Customer Systems Utility Distribution System Utility Transmission System

11

Good Day! For your comments / suggestions / questions

MARVIN RYAN G. BATHAN [email protected] [email protected] 1622-3591

Voltage Unbalance Maximum deviation from the average of the three-phase voltages divided by the average of the three-phase voltages, usually expressed in percent

t

•Unbalanced distribution of single phase loads •Unstable system neutral •One-phase out power supply

Background

Customer business is lead recycling Customer complained of frequent breakdown of 3-phase motors

12

Profile of Voltage Unbalance Voltage Unbalance Trend 9

Voltage Unbalance (%)

8 7 6 5 4 3 2 1

4:45

22:45

1:45

11:45

18:45

8:45

5:45

15:45

22:45

12:45

1:45

8:45

19:45

15:45

5:45

22:45

12:45

2:45

19:45

9:45

5:45

15:45

22:45

3:11

13:11

20:11

10:11

0

Time

Solution

Redistribution of single-phase welding machines

Voltage Sag A decrease in RMS voltage between 10% to 90% of the nominal value for duration from half cycle to 1 minute

1 minute or less

Starting of electric motors Switching “on” of large loads Fault on either distribution, transmission, or generation systems

13

Voltage Sag PerkinElmer Main - 6/3/2004 14:50:13.142 V RMS AB

V RMS BC

V RMS CA

460

• • • •

RMS Voltage (V)

450 440 430

Nominal Voltage: 460V Magnitude: 88.41% Duration: 4 cycles Cause: Fault on the adjacent substation

420 410

0.000

0.025

0.050

0.075 Time (s)

0.100

0.125

EPRI/Electrotek

0.150 PQView®

Susceptibility Curve Information Technology Industry Council (ITIC) curve was developed to accurately reflect the performance of computertype equipment.

It is generally applicable to other equipment containing solid-state devices.

Voltage Sag Problem • Mall somewhere in the north • 3 transformers, 1.5MVA each, 34.5kV / 230V • Mall tenants are complaining of power “fluctuations” that causes equipment shutdown • Mall pumps and fans shutdown on power “fluctuations”

14

Monitoring Results Parameter

Minimum

Average

Maximum

Limits

Comment

105.83%

±10%

Within Recommended Limits

2.50%

5%

Within Recommended Limits

13.59%

5%

Outside Recommended Limits

1.85%

2.5%

Within Recommended Limits

Vab – 102.37% RMS Voltage

99.83%

Vbc – 103.32% Vca – 101.15%

Voltage Harmonic Distortion Current Total Demand Distortion

Vab – 1.16% 0.31%

Vbc – 1.20% Vca – 1.18% Vab – 3.63%

0.66%

Vbc – 4.37% Vca – 3.94%

Voltage Unbalance

0.38%

1.02%

Voltage Sags Date

Time

Magnitude

Duration

Coincident Data

Effect on Customer

7/26/05

18:36

38.75%

9 cyc

7/26/05

18:40

36.67%

8 cyc

7/26/05

18:41

34.79%

9 cyc

7/26/05

18:42

36.12%

7 cyc

Equipment Failure

Shutdown

7/30/05

13:27

87.67%

2 cyc

Transient

7/31/05

12:51

82.86%

3 cyc

NPC 230kV

7/31/05

12:51

88.77%

2 cyc

line trip

8/1/05

18:33

88.32%

4 cyc

Lightning

8/2/05

16:46

71.39%

5 cyc

Transient

8/6/05

16:48

88.02%

13 cyc

Transient

8/11/05

10:23

70.11%

4 cyc

8/15/05

11:00

81.87%

1 cyc

No data

8/17/05

14:10

69.09%

5 cyc

Transient

8/17/05

14:10

89.41%

1 cyc

Transient

No data

Shutdown Shutdown

Findings / Recommendation • Voltage regulation, unbalance, and voltage harmonics are within prescribed limits • Adjust the -5% under-voltage relay setting to -10% and include 1 sec delay • Holding coils could be installed to increase voltage sag ride-through • Reduce ITDD levels to within limit

15

Customer Facility • High rise residential building • 2 - 53 story buildings with 396 semifurnished units • each unit is equipped with two refrigerators and two freezers (personal-size)

Supplier Investigation “Cause of motor-compressor failure is due to low voltage”

Monitoring Equipment

16

Monitoring Results

Phase AB, BC and CA RMS Voltage Chart

245

244

242

240

240

238

236

Volt

235

234

230

232

230

225

228

226

15:35:00

9:35:00

7:35:00

13:35:00

11:35:00

5:35:00

3:35:00

1:35:00

23:35:00

21:35:00

19:35:00

17:35:00

9:35:00

15:35:00

13:35:00

7:35:00

11:35:00

5:35:00

3:35:00

1:35:00

23:35:00

21:35:00

19:35:00

17:35:00

9:35:00

15:35:00

13:35:00

7:35:00

11:35:00

5:35:00

3:35:00

1:35:00

23:35:00

21:35:00

19:35:00

17:35:00

224 15:35:00

220

Time

4 days monitoring

Monitoring Results Nominal Voltage: 230V

VAB Maximum

238.4

Minimum

227.0 (-1.3%)

VBC

VCA 242.7 239.9 (+5.52%) 229.6

231.1

Most Probable Cause • Voltage sags and short duration interruptions can contribute to the degradation and eventually failure of the motors. • If the motor-compressors were running prior to an interruption, large inrush current will be imposed on the motor winding as it tries to restart when power is restored. • Results to over-heating and additional motor stress

17

Recommendations • Installation of time delay switch. This will provide ample time for pressure equalization in the compressor and thus lower the motor load. • Installation of a thermal protector on the motor-compressor. This will prevent burning of the motor winding due to overloading / overheating.

What is the best solution? Increasing Cost

Utility Solution

Over-all Protection Inside Plant

3

4

Control Protection

2

Equipment Specification

1 Controls Motors Other Loads

Think about it….

18

End of Presentation Good day!

Background An electrical service contractor offered Company X installation of additional capacitor banks to improve pf and avail of the pf discount

Background • Several days after the installation of the new capacitor banks, the existing old capacitor bank failed. • The electrical service contractor sought the help of MERLACO PQ Team to determine the feasibility of installing a 1800 kVar capacitor at the high voltage feeder in place of the existing capacitor banks.

19

Single Line Diagram

Requirements for evaluation

• Magnitude of harmonic currents • Equivalent circuit model

Current TDD Measured using Dranetz-BMI 7100 PQ Node Ch ann el IT D D A IT D D B IT D D C

A v e ra g e 1 7 .8 5 % 1 7 .1 7 % 1 8 .0 8 %

M a x im u m 2 5 .2 1 % 2 3 .8 7 % 2 4 .2 0 %

20

Harmonic Current Statistical Summary of Current TDD and Harmonics

CP05 Average CP95

25.00%

% of Base Current

20.00%

15.00%

10.00%

5.00%

25

23

21

19

17

15

13

9

11

7

5

3

TDD

0.00%

TDD and Individual Harm onics PQView ®

Equivalent Circuit • Equivalent circuit for nth harmonic frequency

• Equivalent circuit for fundamental frequency

Variable Definitions • XT0 - tx impedance at fund. freq. ω 0, 0.0649 pu • XS0 - source impedance at fund. freq. ω 0, 0.021189 pu • XC0 - capacitor impedance at fund. Freq. ω 0, 1.94 pu • VCh - hth harmonic component of voltage across the capacitor • Vh - hth harmonic component of the voltage at transformer secondary • Ich - hth harmonic component of the current through the capacitor • Ih

- hth harmonic current generated by the load

21

Resonant Frequency • Determine hr

I Ch

Let,

     − h2 X S0   X    C0   = Ih  1 − h 2  X S 0    X    C0   

1 − hr 2

X S0 =0 X C0

Which results to

hr =

XC0 X S0

=

1.94 = 9.57 .021189

Effect of Resonance Determine the effect of resonance to the capacitor current and voltage, and the load voltage

I Ch

2    −h   hr2  = I 2  h  1 −  h     h2     r 

  h    hr  VCh = jX S I h  2   1 −  h     h2     r 

   h      hr  Vh = jI h  hX T 0 + X S  2    h   1−      h2       r   

Effect of Resonance Equations for equivalent circuit for fundamental frequency

VCh =

− XC0 X S 0 − XC0

I Ch =

1. 0 X S0 − X C0

Vh =

− XC0 X S 0 − X C0

22

Harmonic Current & Voltage Magnitude h 1 3 5 7 9 11 13 15 17 19 21 23 25

Ih -1.00000* 0.02760 0.20403 0.05450 0.01023 0.03950 0.01907 0.01060 0.04940 0.03610 0.01393 0.01300 0.00753

Ic -0.51011* -0.00301 -0.07664 -0.06275 -0.07852 0.16233 0.04161 0.01787 0.07231 0.04837 0.01758 0.01572 0.00883

Vc Vh -0.95038* -0.92472* 0.17814 0.00732 2.72252 0.09594 1.59227 0.04215 1.54958 0.02290 -2.62120 -0.00043 -0.56850 0.00988 -0.21164 0.00801 -0.75549 0.04625 -0.45215 0.03958 -0.14873 0.01737 -0.12141 0.01808 -0.06271 0.01154

Effective voltage across the capacitor will reach as high as 460% of nominal voltage!

Recommendation Installation of the capacitor at the high voltage feeder should be complemented with preventive measure/s to prevent harmonic resonance. This could be through: –



installation of reactors at the capacitor for harmonic de-tuning or filtering of the harmonics at the harmonic generating load.

23

Related Documents

Understanding Power
October 2019 34
Power Quality
June 2020 12
Csc
May 2020 19
Csc
October 2019 31
Csc
November 2019 34