30th Mar 2017
Jong HK, RMF
3 Months Programme Look ahead Risk and Mitigation
Construction of Siglap Station Thomson‐East Coast Line
Contract T309
2) To identify the major risk hazards and elaborate the mitigation measures in this workshop
1) To identify the major works activities for the next three months, Apr 2017 – Jun 2017
Objectives of this workshop:
Hoarding Installation Noise Barrier installation Slab over drain works Utility Corridor Installation Road Works
Entrance C
Guide Wall & D‐Wall construction
4
Recharge Well Installation Kingpost Installation
Guide Wall & D‐Wall construction
Cooling Tower
Road Works ‐Siglap Link Drain works‐ Siglap Link Noise Panel installation Inside the Victoria School Noise Panel installation near to Laguna Park Hoarding Installation Guide Wall & D‐Wall construction
Drain Work at Keesun Avenue Noise Panel installation above Drain Noise Panel installation Siglap Linear Park Guide Wall & D‐Wall construction
Entrance B
Entrance D
Entrance A
Upcoming Works Apr 17 – Jun 17
Entrance A Drain Work at Keesun Avenue Noise Panel installation above Drain Noise Panel installation Siglap Linear Park Guide Wall & D‐Wall construction
Works at Ent. A
Noise Panel installation Siglap Linear Park
Works at Ent. A
Drain work at Keesun Ave.
Damaged to :
Excavation works
Insufficient marking on site.
Unplanned Drilling.
Hazard Cause
Permit to work system
Water pipe. Power grid cables.
Risk
Activity
•
Trial Trench
LCDW Carry out cable detection
‐
TBM briefing
Sub‐con Supervisor
Tan WC (JV UE) LCDW Tan WC (JV UE) Sub‐con Engineer Sub‐con Supervisor
‐ ‐ ‐ ‐ ‐
• • • • • Thorough study of utilities drawings Cable detections by qualified LCDW Provide clear utilities marking on site Provide A3 size drawing of utility plan Apply permit to dig and implement “checklist for working near utility” Barricade work area while trenching
Action Owner
Mitigation Measure
1) Drain Works at Keesun Ave – Risk mitigation
Soil transfer via long arm to soil truck. No stock pile on site.
1) Drain Works at Keesun Ave – Risk mitigation
Portable treatment plant commissioned to ensure silty water are properly treated prior discharge into public drain.
1) Drain Works at Keesun Ave – Risk mitigation
Sufficient manpower deployed to ensure silt are properly maintain.
Damaged to :
Excavation Works
Telecom cables. High tension cables.
Hazard
Activity
Only manual excavation is allowed for trail trench works
Failure to conduct detection test.
Hazard Cause
‐ ‐ ‐
Sub‐con Supervisor Sub‐con Supervisor Sub‐con Supervisor
Mark out detected cable clearly on site. Drill only when identified cables are exposed. Utilities marker are only allowed to shift or remove unless approved by JV UE.
• • •
Tan WC (JV UE)
‐
• Contact relevant utility agency for any presence of unidentified utility Always treat utility as `live’ if encountered Only manual digging allowed for trial trench Full time supervision during trial trench
Action Owner
Mitigation Measure
Entrance B
Works at Ent. B
Guide Wall & D‐Wall construction
Entrance B
Guide wall and D‐wall construction work at Ent. B
Works at Ent. B
D‐wall work
Activity
Crane hit surrounding structures, e.g. silo
Crane Toppling
Risk
•Load hit onto crane
•Instability of working platform
•Failure of loose material equipment/ rebar cages
Hazard Cause
2) D‐walling lifting work – Risk and Mitigation
‐
HSL LS
HSL SC
‐ • Look into min load radius when hoisting bulky items e.g. rebar cage. •Only R/S can give signal. Trade supervisor cannot involved in lifting work.
HSL R/S
HSL LS
HSL CO HSL LS
‐
‐
‐ ‐
•Signaler to communicate with crane operator
•Safety zone established
•Material shall be stacked safely and within stacking limit and load
•Low speed in lifting and lowering
JV Engineer
JV LE
‐
•Approved lifting plan, reviewed by LE and approved by PM
‐
HSL LS
‐
•Lift load by 300mm, stabilized for 3 seconds.
•Lifting points to be identified and approved
Action Owner
Mitigation Measure
D‐wall work
Activity
Crane hit surrounding structures, e.g. silo
•Banksmen to guide crawler crane movement, ensuring no tracking over drain, trench or uneven ground.
HSL R/S
HSL LS
‐ ‐
JV PM
HSL supervisor
‐
‐
HSL supervisor
‐
•Put in place the lifting permit system and display the relevant details on site.
•Instability of working platform •Ensure no overloading of crane •Failure of loose material •Signaler to communicate with crane equipment/ rebar cages operator •Lack of communication •Approved lifting plan, reviewed by LE and approved by PM •Inadequate supervision and control •Lifting operation supervised by lifting supervisor
JV Superintendent
‐
•Provide adequate hardstanding /firm working platform
crane Toppling
Action Owner
Mitigation Measure
Hazard Cause
Risk
2) D‐walling lifting work – Risk and Mitigation
Preparation of ground access with hard‐core
2) D‐walling lifting work – Risk and Mitigation
Heavy machine on steel plate
PTW –lifting system is established
2) D‐walling lifting work – Risk and Mitigation
Lifting supervisor checking the checklist of operator
Load chart display ensuring no overloading of crane.
2) D‐walling lifting work – Risk and Mitigation
Daily checklist of machinery
Low speed in lifting and lowering
Lifting points to be identified and approved
Approved lifting plan
Lift load by 300mm, hold for 3 seconds
2) D‐walling lifting work – Risk and Mitigation
Safety zone established
Material shall be stacked safely and within stacking limit and load
Approved lifting plan for all heavy lifting on site
2) D‐walling lifting work – Risk and Mitigation
Pre‐start briefing in language understood by workmen prior lifting work.
2) D‐walling lifting work – Risk and Mitigation
Provide exclusion zone and warning signs
2) D‐walling lifting work – Risk and Mitigation
To include min load radius in lift plan.
LM Machine not up to expectation will tagged “Not Safe for Use”
2) D‐walling lifting work – Risk and Mitigation
Utility Corridor Installation Road Works
Slab over drain Construction
Noise Barrier installation
Entrance C Hoarding Installation
Works at Ent. C
Fall from height
Noise barrier Erection
MEWP topple
Hit by fallen object
Risk
Activity
Over loading of MEWP
Poor footage
Failure to provide control
Failure to provide fall protection provision
Hazard Cause
3) Noise Barrier Erection – Laguna Park
Richee engineer JV Safety Dept. Richee Supervisor Richee Supervisor Richee Supervisor Richee Supervisor
‐ ‐ ‐ ‐ ‐ ‐
• • • • • • Provision of Fall Protection Plan. Establish PTW‐Height system. Provide proper access. Provide adequate work platform. Licensed MEWP operator. Familiarisation briefing prior appointment.
Action Owner
Mitigation Measure
Fall from height
Noise barrier Erection
MEWP topple
Hit by fallen object
Risk
Activity
Over loading of MEWP
Poor footage
Failure to provide control
Failure to provide fall protection provision
Hazard Cause
3) Noise Barrier Erection – Laguna Park
• • • • •
‐ ‐ ‐ ‐ ‐
Richee Supervisor MEWP Operator JV Engineer Richee Supervisor Richee Supervisor
Richee engineer JV Safety Dept. Richee Supervisor Richee Supervisor Richee Supervisor Richee Supervisor Richee Supervisor
‐ ‐ ‐ ‐ ‐ ‐ ‐
• • • • • • • Provision of Fall Protection Plan. Establish PTW‐Height system. Provide proper access. Provide adequate work platform. Licensed MEWP operator. Familiarisation briefing prior appointment. Enveloped MEWP work platform with scaffold netting to contain material. Limit max. 2 person on MEWP. Max. weight 120kg. Firm and compacted ground for MEWP access. Provide adequate exclusion zone and signage. Provide banksman to ensure no authorised entry in to work zone.
Action Owner
Mitigation Measure
Laguna Park
Public interface during Noise barrier erection – mitigation measures
3) Noise Barrier Erection – Laguna Park
Entrance C construction work in progress
Provide exclusion zone and banksman to prevent unauthorised entry.
3) Noise Barrier Erection – Laguna Park
Include min load radius in load chart
Welding work with fire screen, extinguisher and fire watchman standby.
3) Noise Barrier Erection – Laguna Park
No welding during wet weather.
Works at Ent. D
Guide Wall & D‐Wall construction
Road Works ‐Siglap Link Drain works‐ Siglap Link Noise Panel installation Inside the Victoria School Noise Panel installation near to Laguna Park Hoarding Installation
Entrance D
Noise Panel installation near to Laguna Park
Works at Ent. D
Noise Panel installation Inside the Victoria School
Guide Wall & D‐Wall construction Recharge Well Installation Kingpost Installation
Cooling Tower
Cooling Tower Works
“A’ frame topple
Recharge well work
Fingers / hand caught in rotating parts
Injury to public
Risk
Activity
Incompetent crew
Poor ground condition
Poor footage
Poor mobilization planning
Hazard Cause
4) Recharge Well work – Risk mitigation
• •
• •
• •
•
‐ ‐
‐ ‐
‐ ‐
‐
JV Lift Engineer Sub‐con lifting supervisor
Sub‐con supervisor Sub‐con supervisor
Sub‐con supervisor Sub‐con supervisor
Sub‐con Engineer
JV Superintendent JV Supervisor
‐ ‐
• • Ensure work assess is planned. Ensure adequate access for work mobilisation and public access. Only competent lifting crew is allowed to involved in mobilisation. PTW‐Lifting approved prior unloading. Provide proper exclusion zone to segregate work and public. Provide warning signs. Provide blinker lights to alert night motorist and /or pedestrian. Ensure footage is firm and level at all times. Never drag load. Lift vertically.
Action Owner
Mitigation Measure
4) Recharge Well work – Risk mitigation
Installation of kingpost
Activity
Machine to be inspected and certified by AE. Regular monthly maintenance of machineries
•
Installed sound barrier Used of silent piler Refrain from working at night and weekend/PH Additional sling tied to sheet pile and machinery as extra protection in case grabber gives way.
•
Accidental Carelessness and inexperience dislodgement of operator. kingpost during Faulty vibro hammer. driving
•
• • •
Structure failure of machinery..
‐Sub‐con supervisor
‐ JV superintendent
‐ JV Superintendent
‐ Sub‐con supervisor
‐ Sub‐con supervisor
‐ Sub‐con supervisor
‐ JV Engineer
Access to be laid with hardcore and compacted. I beam to be properly stacked and excluded.
• •
Action Owner
Mitigation Measure
Old machinery and poor maintenance causing disturbance to nearby resident.
Noise pollution
Using of poor condition machinery
Toppling of machinery resulting in damage to property.
Poor ground condition
Injury to surrounding people.
Hazard Cause
Risk
5) Installation of Kingpost ‐ Risk mitigation
Collision of machinery and site people.
Installation of kingpost
Kingpost installation
Hazard
Activity
5) Installation of Kingpost ‐ Risk mitigation
Mitigation Measures
Risk Owner
Machines /man are not allowed to be too close. Provide adequate exclusion zone.
Constraint of work ‐ Work zone to be barricaded to ‐ Sub‐con supervisor area prevent unauthorized entry ‐ Used of tag line to control swaying ‐ Sub‐con R/S of load. ‐ JV Superintendent Only allow skilled operator and experienced lifting team.
Hazard Cause
Poor ground condition
Installation of kingpost
Toppling of machinery resulting in damage to property Injury to surrounding people
Hazard Cause
Access laid with hardcore and compacted
Hazard
Activity
3) Installation of Kingpost ‐ Risk mitigation
‐ Sub con LS
‐ Sub‐con supervisor
Risk Owner
Piling PTW system inplace.
‐ Access to be laid with hard‐core and compacted. ‐ kingpost to be laid on top of hard‐core.
Mitigation Measures
Maintenance service report, AE inspection checklist and certificate
Using of poor condition Structure failure of machinery machinery
Installation of kingpost
Hazard Cause
Hazard
Activity
5) Installation of Kingpost ‐ Risk mitigation
‐ Machine to be inspected and certified by AE. ‐ Regular monthly maintenance of machinery
‐ Sub‐con supervisor
‐ Sub‐con supervisor
Mitigation Measures Action Owner
Hazard
Hazard Cause
Re‐charge well reservoir
Installation of sheet Noise pollution Old machinery and poor pile maintenance causing disturbance to nearby resident
Activity
5) Installation of Kingpost ‐ Risk mitigation
‐ JV Superintendent
Action Owner
Sound barrier set up at cooling tower during kingpost driving to shield the nearby resident.
Installed sound barrier Used of silent piler Refrain from working at night and weekend/PH
Mitigation Measures
End
100
100
T309/CNSS
T309/CNSS
ERSS for Temporary Work
008
007
T309/CDSS/100/008
T309/CDSS/100/007
Trenching
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
Instability of temporary works (trenches)
● Differential settlement between station ERSS ● Failure of loose material, equipment/ rebar cage ● Instability of working platform
Hazard
4
5 Hazard Cause
ERSS wall construction within F1 soil layer - F1 soil layer collapse - Trench stability
- Not identifying the behaviour and response of the ground and adjacent structures
Flawed design of temporary works - Inappropriate use / misinterpretation of design codes - Lack of understanding of design software and output - Incorrect information on adjacent structures - Temporary works design is incompatible with adjacent structures
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Doc no: T309-JHZH-RAR-PWD-RIS-0001
- Collapse of temporary works - Excessive movement/Collapse of adjacent structures - Injury or fatalities of public and Construction workers
- Collapse of temporary works - Collapse / damage of adjacent structures - damage of permanent works - Injury or fatality of construction workers or public
Impact
6
The Risk Register is a "live document" and it will be the responsibility of all parties involved in the design, construction and commissioning of the T309 Project and to ensure that all reasonable means and measures are put in place for the effective management of all the safety risks.to continue to identify new risks that arises.
e
Package 1
F
V
V
V
7
I
I
I
S
C
C
C
Ri
Initial Risk Category Ri
8
- Contractor to produce robust design - Appropriate design sensitivity - Specify minimum penetration of panels - Additional site investigation - Pre-qualify contractors - Emergency Response planning - Provide temporary strut with PE endorsement
- Review levels to be developed - Regular review of Instrumentation / monitoring e.g. LBs to monitor building movement, LGs for ground movement and IW or XYZ for ERSS. - Approved Permit to lift and lifting plan - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be identified, marked and approved
- Contractor to produce robust design - Approved Permit to lift and lifting plan - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be identified, marked and approved
Mitigation Measures
I
I
V
V
I
S
V
F
C
C
C
Ri
Residual Risk Category Rr
11
12
JHZH-PM - Regular review instrumentation reading - Perform probing and SI (SPT) at regular intervals - Perform Ground Improvements when necessary - Joint inspection between JHZHJV and QPS for every Dwall 1) Mild case (to read; less than 10% of total panel excavated volume) – Create an earth bund wall surrounding the affected panel, fill up the bund wall pool with bentonite to increase the bentonite head level. 2) Moderate case (to read; more than 10% of total panel excavated volume, without any visual ground/ platform depression) – Move the grabber and other unnecessary heavy equipment at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. 3) On a case by case basis for a severe case (to read; more than 10% of total panel excavated volume, with obvious visual ground/ platform depression) – Move all machinery away except excavator at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. After 24 hours of backfilling, conduct light cement grout beneath the depressed platform.
JHZH-PM
JHZH-PM
- Steel plate to ensure uniform loading of crane JHZH-PM weight and outrigger - Use of level indicator and inclinometer - Additional site investigation when necessary - Lifting zone to be barricaded before works commence 1) Mild case (to read; less than 10% of total panel excavated volume) – Create an earth bund wall surrounding the affected panel, fill up the bund wall pool with bentonite to increase the bentonite head level. 2) Moderate case (to read; more than 10% of total panel excavated volume, without any visual ground/ platform depression) – Move the grabber and other unnecessary heavy equipment at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. 3) On a case by case basis for a severe case (to read; more than 10% of total panel excavated volume, with obvious visual ground/ platform depression) – Move all machinery away except excavator at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. After 24 hours of backfilling, conduct light cement grout beneath the depressed platform.
*Action Owner
JHZH-PM
Risk Owner
- Steel plate to ensure uniform loading of crane JHZH-PM weight and outrigger - Use of level indicator and inclinometer - Additional site investigation when necessary - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts. - Lifting zone to be barricaded before works commence - Lift load by 300mm, hold for 3 seconds, all personnel 3m away Approved lifting plan, reviewed by LE and approved by PM - Lifting points to be identified and approved - Low speed in lifting and lowering - Material shall be stacked safely and within stacking limit and load - Safety zone established - Signaler to communicate with crane operator
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Summary of Residual Risk Classes A 0 B 0 C 51 D 15 66
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
Summary of Initial Risk Classes A 0 B 11 C 48 D 7 66
Apr-17
Apr-17
Apr-17
Due Date By
Revision G 13 14
7 months
7 months
7 months
Risk Exposure Period
C
C
ipe
Target Risk Rating
Open
Open
Open
Status
Date: 27/04/2017 15 16
17 Remarks
011
012
100
100
T309/CNSS
T309/CNSS
T309/CDSS/100/012
T309/CDSS/100/011
T309/CDSS/100/010
010
100
T309/CNSS
T309/CDSS/100/009
009
100
T309/CNSS
Construction of ERSS for Utility Diversion
Construction of ERSS for Drain Diversion
Construction of ERSS
Construction of ERSS
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
Instability of temporary works (Utility Diversion ERSS)
Instability of temporary works (Drain Diversion ERSS)
Excessive ground movement of adjacent structures and utilities
Instability of temporary works (ERSS failure)
Hazard
4
5 Hazard Cause
6 Impact
F
Structural damage/deflection of existing structures - Damage to utilities - Traffic accidents with associated injuries - injuries to public or construction workers associated with ramp distress - Damage to road surfaces - Wall toe movement
- Damage to utilities - Damage to road surfaces
-Higher than expected lateral deflection of ERSS wall during excavations - Unforeseen ground conditions - Inappropriate removal of struts - Over-excavation - Excavation for the utilities laying/trench
- Unforeseen higher than designed surcharge
- Damage to utilities - Damage to road surfaces
- Unforeseen higher than designed surcharge
IV
IV
III
III
III
III
IV
- Injuries to public or construction workers associated with ramp distress - Traffic accidents with associated injuries - Structure Integrity of sheet piles.
- Inappropriate removal of struts - Over-excavation - Excavation for the drain and damage ERSS - Sheet pile obstructed and not able to pile into required depth. -Poor quality weld and design of sheet pile bracing.
IV
III
III
III
IV
IV
IV
I
I
V
V
I
I
S
V
V
7
C
C
C
C
C
C
C
C
C
C
C
Ri
Initial Risk Category Ri
- Structural damage/deflection of existing structures - Damage to utilities - Injuries to public or construction workers associated with ramp distress - Damage to road surfaces - Wall toe movement
Structural damage/deflection of existing structures - damage to utilities - Traffic accidents with associated injuries - injuries to public or construction workers associated with ramp distress - damage to road surfaces - Wall toe movement
Package 1 8
- PE to ensure surcharge level to within acceptable loading
- Contractor to produce robust design - Method Statements to ensure safe working methods - Monitoring on site - Gather knowledge from people with relevant experience - Visual inspection
- PE to ensure surcharge level to within acceptable loading
- Method Statements to ensure safe working methods -Follow the PTW (e.g excavate) daily during work - Review design of sheet pile and provide COS. - Only certified and appointed welders are allowed to weld. - Method statement to ensure proper bracing is provided.
- Contractor to produce robust design - Method Statements to ensure safe working methods - Gather knowledge from people with relevant experience
- PE to ensure surcharge level to within acceptable loading
- Contractor to produce robust design - Method Statements to ensure safe working methods -Regular review instrumentation reading - Apply PTW (e.g. excavate) daily before commencement of work
- Calculate amount of bentonite level required
- Robust Contractor's ERSS system - Pre-qualify contractors
- Contractor to produce robust design - Appropriate design sensitivity
- Contractor’s Method Statements - Apply PTW (e.g. excavate) daily before commencement of work '- Emergency Response Planning including Contingency planning e.g. grouting of gaps - Additional site investigation
Mitigation Measures
V
V
III
III
III
III
V
V
III
III
III
I
I
V
IV
IV
V
V
I
I
V
V
S
F
D
D
D
D
D
C
C
C
C
C
C
Ri
Residual Risk Category Rr
11
- No stockpiling
JHZH-PM
-Provide ground improvements when necessary JHZH-PM - Requirements to record penetration into competent stratum on installation -High quality site records -Bearing capacity checks for construction equipment - Installation of additional recharge wells & pressure relief wells as contingencies.
- No stockpiling
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM - instrumentation/monitoring to monitor strut loads. - Daily physical inspection of strutting system
JHZH-PM
JHZH-PM
JHZH-PM -Statutory requirement for QP(Sup) to be responsible for supervision of temporary works. -Emergency Response planning including Contingency planning
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
-Normal/ established procedures for staging the JHZH-PM works to protect adjacent utilities -Permit to remove strut system followed to prevent inappropriate removal of struts -Emergency Response planning including Contingency Planning
- No stockpiling
12 *Action Owner
JHZH-PM
JHZH-PM
Risk Owner
- Control of excavation opening to pouring time JHZH-PM
- High quality construction records - Ensure trench stability - Emergency Response planning
- instrumentation/monitoring to monitor strut loads. - Daily physical inspection of strutting system
-Emergency Response planning including Contingency planning -Instrumentation/monitoring to monitor strut loads. - Instrumentation/ real time monitoring - Perform probing and SI (SPT) at regular intervals - Sufficient vibration monitors with appropriate trigger levels to be installed. - Provision of recharge wells. -Provide proper recharging system -Provide proper filter gravel
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
-Higher than expected lateral deflection of ERSS wall during excavations - Unforeseen ground conditions
- Unforeseen higher than designed surcharge
Higher than expected lateral deflection of ERSS wall during excavations - Unforeseen ground conditions - Inappropriate removal of struts - Over-excavation - Excavation of cut and cover tunnel
- Low bentonite level
Inadequate structural detail connection between - Collapse of temporary works strut, waler to ERSS walls / shafts / excavations - Excessive movement/Collapse of adjacent structures - Injury or fatalities of public and Construction workers - Contractor's ERSS design - Workmanship
- Groundwater drawdown
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Apr-17
Oct-17
Apr-17
Apr-17
Apr-17
Apr-17
Apr-17
Apr-17
Apr-17
Apr-17
Mar-17
Due Date By
Revision G 13 14
7 months
13 months
7 months
7 months
7 months
7 months
7 months
7 months
7 months
7 months
7 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 27/04/2017 15 16 17 Remarks
100
100
T309/CNSS
T309/CNSS
014
013
N.A
NA
4
Gaps in sheet piles
Hazard
- Instability of temporary works (kingpost for traffic decking - ERSS) -Poor ground condition Construction of ERSS -Using of poor condition machinery (Kingpost) - Noise pollution for traffic decking -Accidental dislodgement of kingpost during driving -Collision of machinery and site people.
Construction of ERSS (Drainage diversion)
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
5 Hazard Cause
- Poor design lead to undersize kingpost. - Poor workmanship. -Overloading of kingpost with other load not considered in the design. -Toppling of machinery resulting in damage to property. -Injury to surrounding people. -Structure failure of machinery.. -Old machinery and poor maintenance causing disturbance to nearby resident. - Carelessness and inexperience operator. Faulty vibro hammer.
- Supporting structure across the excavation due to lack of diversion corridor
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Collapse of temporary works - Collapse / damage of adjacent structures - damage of permanent works - Injury or fatality of construction workers or public
- Leakage through gap in the walls - Damage to services - Groundwater drawdown - Localized collapse of soil in the gap during excavation
Impact
Package 1
IV
7
III
S IV
F III
C
C
Ri
Initial Risk Category Ri
8
- Method Statements to ensure kingpost is constructed according to MS -JV engineer / QPS to supervise kinghpost construction work to esnure quality of workmanship. - Design to allow sufficient safety factor for structure interity of kingpost. -Access to be laid with hardcore and compacted. -I beam to be properly stacked and excluded. -Machine to be inspected and certified by AE. -Regular monthly maintenance of machineries - Work zone to be barricaded to prevent unauthorized entry - Used of tag line to control swaying of load. - Only allow skilled operator and experienced lifting team.
- Minimize gaps to minimum size required - Utilities diverted from excavation wherever possible - Instrumentation around gap area when necessary
Mitigation Measures
V
III
S IV
F IV
D
D
Ri
Residual Risk Category Rr
11 Risk Owner
- During construction phase, ensure RA control measure are implemented - e.g. -Segregation of man and machines -Provide designated pedestrian access for wokers. - Provide adequate warning signs. - Provide proper barricades around bore hole. -Installed sound barrier - Used of silent piler - Refrain from working at night and weekend /PH - Additional sling tied to sheet pile and machinery as extra protection in case grabber gives way. - Access to be laid with hard-core and compacted. - kingpost to be laid on top of hard-core.
JHZH-PM
JHZH-PM - Reinstall sheet piles if there are gaps during installation - Emergency Response Planning including Contingency Planning (e.g. immediate removal works upon sighting of unfavaourable ground/wall movements) 1) Mild case (to read; less than 10% of total panel excavated volume) – Create an earth bund wall surrounding the affected panel, fill up the bund wall pool with bentonite to increase the bentonite head level. 2) Moderate case (to read; more than 10% of total panel excavated volume, without any visual ground/ platform depression) – Move the grabber and other unnecessary heavy equipment at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. 3) On a case by case basis for a severe case (to read; more than 10% of total panel excavated volume, with obvious visual ground/ platform depression) – Move all machinery away except excavator at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. After 24 hours of backfilling, conduct light cement grout beneath the depressed platform.
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
12
JHZH-PM
JHZH-PM
*Action Owner
Apr-17
Apr-17
Due Date By
Revision G 13 14
7 months
7 months
Risk Exposure Period
C
C
Target Risk Rating
Open
Open
Status
Date: 27/04/2017 15 16 17 Remarks
102
102
102
102
102
102
102
Diaphragm walling T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
007
006
005
004
003
002
001
NA
NA
N.A
T309/CDSS/102/004
T309/CDSS/102/003
T309/CDSS/102/002
T309/CDSS/102/001
Barrette pile test
Welding Works with Welding inverter
Welding Works with Oxygen acetylene and Welding inverter
Diaphragm walling
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
5
-Instability of ERSS wall trenches - Low shear strength in Marine Clay - Loose fills - Possible removal of buried obstructions - Presence of thick peaty layers - High pore water pressure in Marine Clay - Close proximity of adjacent activities such as jet grout piles or casting of nearby trench -Leakage of Bentonite from D wall -Poor Bentonite mixe.
Hazard Cause
6
- Structural damage/deflection of existing structures - Damage to utilities - Traffic accidents with associated injuries - Damage to road surfaces - Collaspe of D wall
Impact
7
Kentledge collapse
- Failure of jack, jack force is not locked in - Unbalance pressure force in jack
- Testing of D-wall
- Improper maintenance of welding set - Improper connection and damaged cables - welding set not fully protected from wet surfaces - Welding in open space during wet weather condition
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury to public or construction personnel - Delays - Claims -Reputation
IV
IV
IV
I
I
I
II
IV
- Injury to public or construction personnel - Delays - Claims - Damage to permanent and temporary works
Fire sparks, fire explosion - Inappropriate welding of struts - Inappropriate welding of Traffic Deck due to Gas leaks, hose damaged, fitting damaged - Inappropriate welding of Noise Barriers - Incompetent welder deployed
Electrocution due to electrical leak
III
V
III
III
V
V
II
S
IV
F
B
B
B
C
D
D
D
C
Ri
Initial Risk Category Ri
- Water ingress - Lost toe stability - Loss of fines - Settlement of structures
- Delay of works -Inappropriate diaphragm wall design - Inappropriate use / misinterpretation of design codes
Package 1 8
- Contractor shall provide -uniform hydraulic pressure supply to all jacks to main balance force in test - Mechanical safe lock (safety valve) to lock pressure in jack during jack operation in case of pressure loss
- Test set up must get endorsement of PE
- PPE: Welding face shield, apron and gauntlet - Apply PTW (e.g. hot works) daily before commencement of work - Electrical wires to be secured above ground - Daily welding set checklist/ inspection - Certified welders - Reminder in Tool box meeting
- PPE: Welding face shield, apron and gauntlet - Proper housekeeping - Method Statements (e.g. - Close main value & flush hose line after usage) - Apply PTW (e.g. hot works) daily before commencements of works - Daily welding set checklist/ inspection - Fire extinguishers and fire blankets - Reminder in Tool box meeting '- Certified welders - Welding screen to contain sparks
- Specifying waterproofing details @ interface
- Use of adequate plant / equipment for diaphragm wall construction -Apply PTW (e.g. lifting) daily before commencements of works - Cage to be within lifting equipment capacity - Lifting points to be identified, marked and approved
- Emergency Response Planning including Contingency planning e.g. grouting of gaps - Method Statements to ensure safe working methods - Apply PTW (e.g. excavate) daily before commencement of work
- Method Statements to ensure safe working methods - Regular monitoring of critical structures - Stability calculations - Contingency planning e.g. (backfilling) in case of collapse, additional temporary struts - Trial panel - Raised guide walls - Control of bentonite properties (e.g. viscosity, sand content, PH value, density) - Visual inspection - Pre-qualify contractors -Apply PTW (e.g. excavate) daily before commencement of work - Deploy worker to monitor Bentonite level especially over week end.
Mitigation Measures
V
V
V
V
V
I
I
I
I
III
III
III
V
V
II
S
IV
F
C
C
C
C
D
D
D
C
Ri
Residual Risk Category Rr
11 Risk Owner
12
JHZH-PM
- Provide physical barrier (interlocked properly) JHZH-PM and safety signs around test sites - Emergency Response planning including Contingency planning - Proper design of kentledge system - Pre-qualify the subcontractor - Approved Method Statement
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM
JHZH-PM
-Monitoring of overall settlement and differential JHZH-PM settlement of the kentledge - Provide physical barrier (interlocked properly) and safety signs around test sites - Emergency Response planning including Contingency planning - Proper design of kentledge system - Pre-qualify the subcontractor - Approved Method Statement
-No welding work under rain weather/ wet surfaces - Monthly inspection of welding equipment - Apply Safe Work procedure - Electrical neoprene cable double insulated
- Remove flammable items (timber, canvas etc.. )from welding premises - Monthly inspection of welding equipment - Apply Safe Work Procedure - Implement PTW -Hot work
- High quality construction inspection and records - Method Statements to ensure safe working methods - Use of adequate plant/equipment for ERSS wall construction
- Adopt approved lifting plan - Ensure lifting equipment are inspected monthly - Lifting zone to be barricaded before works commence
- Proper post-cast for structure - Specifying waterproofing details @ interface
-Normal/ established procedures for staging the JHZH-PM works to protect adjacent utilities -Regular review instrumentation reading -Permit to remove strut system followed to prevent inappropriate removal of struts -No stockpiling against D-wall -Emergency Response planning including Contingency planning - Never start D-walling without having the cages ready.
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
Inadequate water tightness - Poor concrete compaction - Inadequate concrete cover and reduced durability due to honeycomb - Poor workmanship
Diaphragm wall cage too heavy to be lifted
Gaps in retaining systems Provision for services to pass through retaining -Cracking / leakage systems - Structural Damage - Waterproofing problems and associated repair
Excessive ground movement of adjacent structures and utilities
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Mar-17
Mar-17
Oct-17
Oct-17
Oct-17
Oct-17
Oct-17
Oct-17
Due Date By
Revision G 13 14
7 months
7 months
13 months
13 months
13 months
13 months
13 months
13 months
Risk Exposure Period
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 27/04/2017 15 16 17 Remarks
102
102
102
102
102
T309/CNSS
T309/CNSS
Pilling T309/CNSS
T309/CNSS
T309/CNSS
011
010
009
009
008
NA
T309/CDSS/102/004
T309/CDSS/102/001
NA
NA
Bored pile test
Piling
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
5
-Instability of ERSS wall trenches - Low shear strength in Marine Clay - Loose fills - Possible removal of buried obstructions - Presence of thick peaty layers - High pore water pressure in Marine Clay - Close proximity of adjacent activities such as jet grout piles or casting of nearby trench
Kentledge collapse
- Failure of jack, jack force is not locked in - Unbalance pressure force in jack
- Bored Pile testing
Inadequate water tightness - Poor concrete compaction - Inadequate concrete cover and reduced durability due to honeycomb - Poor workmanship
Excessive ground movement of adjacent structures and utilities
- Poor design - Poor workmanship - Poor rigging method
- Improper securing of material/ equipment/ cages - Overloading of material/ equipment/ cages - Slight tilt in crane '- Sudden movement of crane boom
Failing of loose material/ equipment/ rebar cages
In Stability of rebar cage (including cages for Lshape d-wall panel)
- Breakage of lifting chain - Breakage of lifting sling - Failure of brake motor/gear - Failure of sling/chain buckles and hooks - Overloading of carried loads over limited of design capacity - Unauthorized modification of lifting points -Inadequate rigging method.
Hazard Cause
Failure of lifting mechanism
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
7
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Water ingress - Lost toe Stability - Loss of fines - Settlement of structures
- Structural damage/deflection of existing structures - Damage to utilities - Traffic accidents with associated injuries - Damage to road surfaces
IV
IV
V
IV
IV
I
I
III
II
I
I
IV
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities - Rebar cage fall off during lifting process. - Crane damanged by swing load e.g. windscreen damaged by lifted rebar cage.
I
S
IV
F
B
B
D
C
B
B
B
Ri
Initial Risk Category Ri
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities -Crane topple -Tanish reputation
Impact
Package 1 8
- Contractor shall provide -uniform hydraulic pressure supply to all jacks to main balance force in test - Mechanical safe lock (safety valve) to lock pressure in jack during jack operation in case of pressure loss
- Test set up must get endorsement of PE
- Use of adequate plant / equipment for ERSS wall construction
- Method Statements to ensure safe working methods - Regular monitoring of critical structures - Stability calculations - Contingency planning e.g. (backfilling) in case of collapse, additional temporary struts - Trial panel - Raised guide walls - Control of bentonite properties (e.g. viscosity, sand content, PH value, density) - Visual inspection - Pre-qualify contractors - Apply PTW (e.g. piling) daily before commencement of work
- Cage design must get endorsement of PE - Regular inspection of interface with good records - Lifting points to be marked, identified and approved - Engineer to be present to confirm lifting points prior liftng rebar cage. - Ensure moin load radius is taken into consideration when preparing lift plan.
- Approved PTW (e.g lifting) daily before commencement of work - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be marked, identified and approved - Approved Lifting plan - Material shall be stacked safely and within stacking limit and load
- Apply PTW (e.g. lifting) daily before commencement of work - Monthly inspection of lifting mechanisms - Lifting Supervisor to ensure correct method of usage - Colour coding all lifting mechanisms for validity and serviceability levels - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Lifting points to be marked, identified and approved - Approved Lifting Plan -Weekly boom down inspection with mechanics
Mitigation Measures
V
V
V
IV
I
I
III
II
I
I
V
V
I
S
V
F
C
C
D
C
C
C
C
Ri
Residual Risk Category Rr
11
12
JHZH-PM
JHZH-PM
- Provide physical barrier (interlocked properly) JHZH-PM and safety signs around test sites - Emergency Response planning including Contingency planning - Proper design of kentledge system - Pre-qualify the subcontractor - Approved Method Statement
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM
Risk Owner
-Monitoring of overall settlement and differential JHZH-PM settlement of the kentledge - Provide physical barrier (interlocked properly) and safety signs around test sites Contingency planning - Emergency Response planning - Proper design of kentledge system - Pre-qualify the subcontractor - Approved Method Statement
- High quality construction inspection and records - Method Statements to ensure safe working methods
- Regular review Instrumentation reading -Permit to remove strut system followed to prevent inappropriate removal of struts - Emergency Response planning - Review SI report and cross check at site - Provide water relief wells when necessary
- Emergency Response planning including Contingency planning - Adopt 3X3 lifting principles. - Only R/S is allowed to give signal to crane operator.
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
Mar-17
Mar-17
Mar-17
Mar-17
Mar-17
Oct-17
Oct-17
Due Date By
Revision G 13 14
7 months
7 months
7 months
7 months
7 months
13 months
13 months
Risk Exposure Period
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Status
Date: 27/04/2017 15 16 17 Remarks
105
105
T309/CNSS
T309/CNSS
003
002
T309/CDSS/105/003
T309/CDSS/105/002
T309/CDSS/105/001
Adjacent Structures or Buildings T309/CNSS 105 001
NA
T309/CDSS/103/001
103
Permanent Works T309/CNSS
012
001
102
T309/CNSS
Construction work nearby to adjacent structures or buildings
Construction work nearby stake holders
Construction work nearby to school
Construction of Permanent Works
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
5
- Breakage of lifting chain - Breakage of lifting sling - Failure of brake motor/gear - Failure of sling/chain buckles and hooks - Overloading of carried loads over limited of design capacity - Unauthorized modification of lifting points
Hazard Cause
- Improper securing of material/ equipment/ cages - Overloading of material/ equipment/ cages - Slight tilt in crane '- Sudden movement of crane boom
Excessive ground and building settlement
Damage / excessive settlement to buildings/structures: - Victoria School Access Bridge - 2-storey semi-detached houses at Kee Sun Ave - St. Andrew's Autism Centre - Elliot at The East Coast - Laguna Park Electrical Substation (Block 5000F) - 2-storey semi-detached houses at Elliot Walk - Opera Estate Canal & Culverts Interface with the public.
Stop or delay school operation. Interface with the public.
- Activation criteria and minimum head are not given
- Ineffectiveness of recharge well layout given in the A/E design '- Some recharge well points will not provide effective recharging due to their locations being far from the buildings to be protected - Filter may not be compatible with the existing ground conditions - Pile test and D-wall test
-Long term settlements - Scheduling of work planning
-Unforeseen ground conditions -Excavation works causing unforeseen settlements -Groundwater drawdown
-Proximity of schools has special implications, -Victoria school is boarding school) - Scheduling of work planning
Excessive settlement - Insufficient ground information available for (Victoria School bridge and design canal structures)
Failing of loose material/ equipment/ rebar cages
Crane topple / Hoisted load - Poor crane footage hit crane - Incompetent lifting team - Poor lift plan - Congested work environment
Failure of lifting mechanism
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
7
- Damage to utilities - Damage to property
- Disruption to the site activities during installation of recharge well - Blockage of the filter gravel - Excessive water flow rate provided by the pumping system but little recharging effect
- Claims - Damage to buildings/structures - Complains from the public - Injuring the public
- Damage to buildings/structures - Delays - Claims - Closure of roads - Injuries / fatalities of construction workers and public
-Noise disruption to schools -Pick up and drop off times Damaged - Complains from the public - Injuring the public
- Serviceability issue with the bridge
IV
IV
V
V
III
IV
IV
III
III
I
I
IV
III
I
I
IV
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
I
S
IV
F
C
C
C
C
C
C
B
B
B
Ri
Initial Risk Category Ri
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
Impact
Package 1 8
-Activation criteria and minimum have been designed and indicated (Zone 1 to 3)
- Contractor's consultant has designed the recharging system, modified the configuration - Design of filter gravel has been provided
- Instrumentation / Monitoring - Reduce work inteface with public during peak hours
- Contractor’s Method Statements - instrumentation / monitoring - Real time monitoring - Specification of instrumentation and monitoring requirements by AE consultant - Strengthening and temporary propping when necessary - Additional site investigation
- Contingency planning, inspection and monitoring - Method Statements - Additional site supervision (e.g. traffic marshal) - Reduce work inteface with public during peak hours
- Provision of additional boreholes for bridge and canal design
- Approved PTW (e.g lifting) daily before commencement of work - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be marked, identified and approved - Approved Lifting plan - Material shall be stacked safely and within stacking limit and load
- Design and COS crane access - No Overloading at all times - Proper maintenance of crane - Only competent lifting team is allowed - Implemet Permit to lift - Include both Max. and Min load radius - Do not conduct lifting in congested work environment. - Provide exclusion zone and Provide warning signs. - Provide sufficient tag lines
- Apply PTW (e.g. lifting) daily before commencement of work - Monthly inspection of lifting mechanisms - Lifting Supervisor to ensure correct method of usage - Colour coding all lifting mechanisms for validity and serviceability levels - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Lifting points to be marked, identified and approved - Approved Lifting Plan
Mitigation Measures
IV
IV
V
V
III
IV
III
III
I
I
IV
III
I
I
V
V
I
S
V
F
C
C
C
C
C
C
C
C
C
Ri
Residual Risk Category Rr
11
- Provide proper recharging system - Provide proper filter gravel - Instrumentation/ Monitoring of settlement - Additional Site investigation
- Emergency Response planning - Provide proper recharging system - Provide proper filter gravel - Instrumentation/ Monitoring of settlement - Additional Site investigation - Control of bentonite pressures
- Perform ground improvements when necessary
-Emergency Response planning including Contingency planning -Instrumentation/monitoring to monitor strut loads. - Instrumentation/ real time monitoring - Sufficient vibration monitors with appropriate trigger levels to be installed. - Provision of recharge wells. -Provide proper recharging system -Provide proper filter gravel
12
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM
Risk Owner
JHZH-PM - Proper planning and traffic control - Provide soundproof wall - Close communication with the school and be cognisant of critical times in the school calendar
- Emergency Response planning - Insturmentation and monitoring of settlement - Additional Site investigation when necessary
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
May-20
Oct-17
Oct-17
Oct-17
Due Date By
Revision G 13 14
79 months
79 months
79 months
79 months
79 months
45 months
13 months
13 months
13 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 27/04/2017 15 16 17 Remarks
T309/ CNSS
105
004
N.A
Traffic Diversion around Victoria School
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
- Congested road leading to Victoria school - Construction activities in front of Victoria school - Heavy machinery stationed along Siglap Link - Heavy traffic from new egress to Marine Parade Road - Pedestrians jaywalking -Inadequate signage and poor traffic control measures -Unsafe traffic layout -Failure to carryout trial trench for UG services -Failure to barricade work area and provide banksman to guide vehicular movement on site -Failure to equip with proper PPE
Risk associated with Traffic Diversion -Unsafe traffic conditions, accident hot spot and vehicles crashing into site -Damaged to UG services -Noise and dust pollution
5 Hazard Cause
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Collision of construction and public vehicles - Delays - Claims - Injury to public or construction personnel
Impact
Package 1 7
S II
F IV
C
Ri
Initial Risk Category Ri
8
- Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan '- Guard rail or rigid barrier to be setup and interlocked properly - designated path for access by pedestrians '- Code of Practise of Traffic Control and Work Zone -Approval of temporary traffic diversion layout by TM -Traffic layout and signage to follow TCP -Submit PSR (road) for clearance -Ensure good visibility of signage --Apply permit to dig prior to start work -Conduct RA/ SWP briefing
Mitigation Measures
S II
F IV
C
Ri
Residual Risk Category Rr
11 Risk Owner
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly when necessary - Placement of cone or barrier during diversion without reduction in lane width -Desk top study of all utilities and carryout appropriate trial trench -Barricade work area and provide proper signage and warning to motorist and pedestrian. -Lane closure to avoid peak hours, applicable hours is 9:30-16:30 for daytime and 16:30-09:30 for night time closure -Flow chart indicating the flow of instruction enabling the lorry truck to enter the lane closure work area during soil removal or delivery of materials.
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
12
JHZH-PM
*Action Owner
Mar-23
Due Date By
Revision G 13 14
79 months
Risk Exposure Period
C
Target Risk Rating
Open
Status
Date: 27/04/2017 15 16 17
Further improvemen ts will be discuss in PSR roadworks
Remarks
005
Future developments or Addition & Alteration works 112 001 T309/CNSS T309/CDSS/112/001
110
T309/CDSS/110/005
N.A
T309/CNSS
109
Existing Conditions T309/CNSS
004
T309/CDSS/106/003
T309/CDSS/110/004
106
T309/CNSS
003
T309/CDSS/106/002
Interface with Adjacent Contracts T309/CNSS 110 004
106
T309/CNSS
002
T309/CDSS/106/001
T309/CDSS/109/006
106
T309/CNSS
001
006
106
Existing Utilities T309/CNSS
Future developments or Addition & Alteration works
Excavation
Excavation
Excavation for Utility Diversion Works
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
Clashes between railway structures and future underground infrastructure works and/or future above ground developments
Interfacing with adjacent contracts
Incompatible Interfacing with adjacent contracts
Seawall obstruction
Limited Work Areas
Damage to utilities
Damage to utilities and disruption to services
Damage to submarine cable
Hazard
4
5 Hazard Cause
- Injury or fatalities of public and construction workers Unplanned excavation -Insufficient marking on site -Failure to conduct detection test
- Damage to the equipment used - Deep foundation and diaphragm wall are not constructed properly
- Unforeseen higher than designed surcharge
- Damage to utilities - Damage to road surfaces - Damage to property
-Proposals for future underground infrastructure - Incompatible construction techniques and developments in direct conflict with alignment and stations - Delay of works - Unaware of future infrastructure and developments proposals
Effect of T310 TBM tunnels on D-Walls subway - Excessive ground movement near Entrance C - Movement to adjacent structures
Unappropriate or non-workable connection - Excessive ground movement design at interface of bored tunnels and station - Movement to adjacent structures end walls - Groundwater drawdown - Waterproofing problem and associated repairs
Abandon seawall
- Work areas too restricted or efficient workings - Schedule delays - Work areas require significant temporary - Unsafe environment for construction works for their establishment personnel traffic congestion
-Diversion and support of utilities across excavation: - Water pipe - Power Grid cables - SP Telecom cables - Starhub cables
6 Impact
Disturbance to public
-Non coordinated inter-contract utility diversion, - Delay - Remote disruption -Unforeseen obstructions - Missing information from utilities agencies - Insufficient trial trenches
Insufficient information about cable location
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Package 1
F
V
V
V
V
IV
II
II
I
I
IV
III
I
V
III
III
I
S
III
V
7
C
C
C
C
D
C
C
C
C
Ri
Initial Risk Category Ri
8
- PE to ensure surcharge level to within acceptable loading
- Contractor to review Development Interface Report in detail - Coordination meetings between interfacing designers - Coordination between all parties (Client, Contractor, designers)
- Coordination meetings between interfacing contractors and designers to be managed by Contractors - Construction Interface report by Contractor - Coordination between all parties (Client, Contractor, Designers)
- Coordination meetings between interfacing contractors - Construction Interface report by Contractor - Coordination between all parties (Client, Contractor, Designers) - Specifying waterproofing details @ interface
- Additional trial trench and site investigation
- Buidling temporary decking for efficient road/land use - Detailed SHE procedure to enforce safety
- Ongoing co-ordination with relevant utility companies - Contractor's Method Statement - Approved NCE - Pre-qualify Contractors - Apply PTW daily before commencement of work -Thorough study of utilities drawings -Cable detections by qualified LCDW -Provide clear utilities marking on site -Provide A3 size drawing of utility plan -Apply permit to dig -Barricade work area while trenching -Contact relevant utility agency for any presence of unidentified utility -Always treat utility as `live’ if encountered -Only manual digging allowed for trial trench -Full time supervision during trial trench -No mechanical excavation within 3 meters from live utilities. - Only manual excavation allowed for trial trench digging. - Brief utilities plan in language understood by the workmen.
- Method Statements - Additional site investigation - Approved NCE
- To divert submarine cable away from the station box
Mitigation Measures
V
V
V
V
IV
II
II
I
I
IV
III
I
V
IV
III
I
S
IV
V
F
C
C
C
C
D
C
C
C
C
Ri
Residual Risk Category Rr
11
12
- No stockpiling
- Close coordination with related parties
- Instrumentation and monitoring - Close coordination
- Emergency Response planning e.g. grouting - Methods Statement - Close coordination
- Cross check at site - Laise with related authority about the information of seawall
- Efficient site utilization plan for each different working stage - Hire a professional road safety review learn and checking when necessary
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
-Utility cable detection and trial trench should be JHZH-PM carried out to identify the alignment -Diversion out of the structure footprint -Emergency Response planning including Contingency planning -Close communication with utilities agencies -Cable detection -Properly mark the location of utilities and briefing site staffs, workers and sub-contractors -If unclear with the finding of services after reaching the 2m limit, conduct further detection to determine the presence of any services below. -Dimensions and depth of Trial Trenches recorded by Project Survey Team for As Build information Photo records of trial trench including any utility discovered are recorded
JHZH-PM
JHZH-PM
-Design protective measures and temporary support scheme for utilities across excavation -Close communication with inter-contract and utilities agencies -Identify clear markers for utilities locations lines and brief staffs, workers and subcontractors -Cable detection -Emergency Response planning including Contingency planning
JHZH-PM
*Action Owner
JHZH-PM
Risk Owner
- Divert submarine cable away from the station JHZH-PM box and identify the clearly marker
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
May-20
May-20
May-20
May-20
Jan-17
Oct-17
Oct-17
Oct-17
Oct-17
Due Date By
Revision G 13 14
45 months
45 months
45 months
45 months
5 months
13 months
13 months
13 months
13 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 27/04/2017 15 16 17 Remarks
001
002
Ground Improvements T309/CNSS 118
118
121
T309/CNSS
Fire and Explosions T309/CNSS
001
009
Construction Methodology T309/CNSS 117
T309/CDSS/121/001
T309/CDSS/118/002
T309/CDSS/118/001
T309/CDSS/117/009
Construction works involving flammable or explosive materials
Construction works for ERSS or permanent walls
Jet grouting
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
5
Inappropriate jet grouting methods
-Overloading of lifting equipment -Failure to observe safe work procedures -- Instability of working platform. - Failure of loose material equipment/ rebar cages - Lack of communication - Inadequate supervision and control - Unplanned and poor control of crane movement - Substandard lift plan
Hazard Cause
Fire or explosion during construction
-Encounter flammable materials - Breakage of buried services - Ignition of methane from peat layers - Contaminant gas - War relics/unexploded ordnances - Heavy vehicles carrying flammable materials may be driven into the construction site
Excessive deflection of Insufficient ground improvement / treatment ERSS or permanent walls works
Ground improvement failure
●Crane collapse or failure ●Toppling of crane ●Crane hit surrounding structures, eg silo ●Hoisted material hit crane
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Injury or fatality of public or construction workers - Damage to existing structures and services
- Flooding of excavation - Collapse of temporary works and adjacent structures - Injury of public or construction personnel - Disruption of essential services - Delays - Claims
- Collapse of ground - Injury or fatality of construction workers and public - Waterproofing problems and associated repair - Damage to buildings - Delay of works - Movements of adjacent structures
-Injury to site staff -Delay to construction -Damage to property
Impact
Package 1
IV
F
V
V
V
7
I
II
II
II
S
C
C
C
C
Ri
Initial Risk Category Ri
8
- Provision of appropriate plant - additional site investigation and geophysics when necessary - Gather knowledge from people with relevant experience - Apply PTW (e.g hot works) daily before commencement of work - Safety Datasheet and Warning signs and Emergency contacts on display - Reporting to Safety and Security Department
- Contractor to produce robust Design - Method Statements to ensure safe working methods - Robust ERSS Design - instrumentation / monitoring e.g. LBs to monitor building movement, LGs for ground movement and IW or XYZ for ERSS.
- Contractor to produce robust design - Jet grouting trials - Specifying waterproofing details @ interface - Instrumentation / Monitoring e.g. LBs to monitor building movement, LGs for ground movement and IW or XYZ for ERSS. - Additional site investigation and geophysics
- Provide support plates for firm support - Apply PTW (e.g. lifting) daily before commencement of work - Full extension of outrigger prior to lifting - Approved Lifting Permit - No workers shall be allowed to stand below suspended loads - Lifting Supervisor to ensure correct method of usage - Approved lifting plan (e.g. full extension of outrigger, approved and proper use of slings) - Lifting points to be marked, identified and approved -Safety zone established -Tag line with coloured flag to be installed along hoarding to warn operator from crossing the line when turning during lifting -Tag line with coloured flag to be installed at the top of bentonite tank to warn crane operator and signal man to guide operator during crane movement. -Bentonite tanks near to Dwall will only be erected after the completion of Dwall. -To include min load radius in lift plan.
Mitigation Measures
V
V
V
V
F
I
II
II
II
S
C
C
C
C
Ri
Residual Risk Category Rr
11 Risk Owner
- Proper and independent flammable materials storage and management - Emergency Response Planning including Contingency planning e.g. quick evacuation route - Permit to carry hazardous material
- Provide efficient geometric design and the road level to mitigate flooding - Witness the instrumentation reading - Regular review and analyse instrumentation reading - Emergency Response planning include Contingency planning, inspection and monitoring
JHZH-PM
JHZH-PM
- High quality construction records and material JHZH-PM testing - Methods statement - Pre-qualify contractors - Regular review instrumentation reading of inclinometers and ground settlement markers in trial test and feedback main works - Emergency Response Planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts.
JHZH-PM - Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Reminder in tool box meeting - Lifting zone to be barricaded before works commence -Provide adequate hardstanding /firm working platform -Put in place the lifting permit system and display the relevant details on site. -Ensure no overloading of crane -Signaler to communicate with crane operator -Lift load by 300mm, hold for 3 seconds, all personnel 3m away -Approved lifting plan, reviewed by LE and approved by PM -Lifting operation supervised by lifting supervisor -Banksmen to guide crawler crane movement, ensuring no tracking over drain, trench or uneven ground. -Lifting points to be identified and approved -Low speed in lifting and lowering -Material shall be stacked safely and within stacking limit and load -Authorization of all machineries movement from point to point -Establish a permit to move system for heavy machineries -A lockout /tagout system during maintenance and breakdown period of mchineries -Maincon to control all machineries movement on site with daily discussion during coordination meeting -Setting up a security management plan that involved site security to be aware of the delivery of materials and ensuring no material delivery during lunch time and peak hour
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
12
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
Mar-23
Jan-18
Jul-17
May-20
Due Date By
Revision G 13 14
79 months
16 months
10 months
45 months
Risk Exposure Period
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Status
Date: 27/04/2017 15 16 17 Remarks
122
999
999
999
999
999
999
999
Flooding T309/CNSS
Other Hazards T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
007
006
005
004
003
002
001
002
N.A
T309/CDSS/999/006
T309/CDSS/999/005
T309/CDSS/999/004
T309/CDSS/999/003
T309/CDSS/999/002
T309/CDSS/999/001
T309/CDSS/122/001
4
5 Hazard Cause
Cleaning
Setting up of Noise Barrier
Traffic Diversion
6
Damage to construction works
-Occurrence of a natural disaster during construction - Flooding - Heavy rainfall causing significant ground water table rise
- Construction activities require frequent transport movements - Works at site with long working hours for 7 days a week
Use of high ultra water jet
Noise Barrier and foundation
-Pipe leakage and burst -Loose connection -Lose control of hose
-Construction works in close proximity to the public and existing housing -Excessive noise due to construction
Movement of heavy -Spoil removed to designated location remote vehicles causing disruption from site to traffic movement
F
- Injury to public or construction personnel
- Injury to public or construction personnel - Disruption of essential services - Negative PR - Delays - Claims
- Delay and accidents, - ECM issues, - Mosquito breeding, - Security problems
IV
II
III
III
III
V
IV
IV
I
V
- Flooding of excavation - Collapse of temporary works and adjacent structures - Injury or fatality of public or construction personnel - Disruption of essential services - Delays - Claims
II
III
I
S
II
IV
IV
V
7
C
D
C
D
C
C
C
C
C
Ri
Initial Risk Category Ri
IV
-Environmental pollution
Package 1 8
- Assign two trained hydro jetting operators. - Rotate shift every alternate hours - Provide safety warning signage to keep other works clear from work area - Provide safety access to washing bay
- Method Statements - additional site investigation - Provision of Noise barrier - Monitoring of Noise - Noise control plan - Engage community regularly and gather feedback
- Method Statements -Additional traffic management
- Method Statements - additional site supervision - ECM Plan
- Robust ERSS design including flood barriers when necessary - Temporary groundwater controls and pumps within excavation - Specifying water proofing details @ interface
- Design and approved traffic diversions - Minimise traffic around construction sites - Use of barrier and/or gate guards for exit/ entrances to site
- Design and approved traffic diversions - Clear and good signages - Minimise traffic around construction sites
- Contingency planning, e.g. additional noise barriers, inspection and monitoring - Method Statements to ensure safe working methods - Installation of noise barriers - Noise level monitoring - Engaging community for feedback '- Noise, dust control plan
- Method Statements - Additional site investigation -Confirmation with LTA on any specific flood protection measures required during construction
Mitigation Measures
V
V
IV
II
III
III
IV
I
V
IV
II
II
III
I
S
V
V
V
V
F
C
D
C
D
C
C
C
D
C
Ri
Residual Risk Category Rr
11 Risk Owner
JHZH-PM
12
JHZH-PM
JHZH-PM
- Assign safety supervisor when possible at work place to ensure operation is safe - Barricade work area to prevent unauthorized access and display warning signage.
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly -Designated haul routes -Contingency planning, inspection and monitoring - Placement of cone or barrier during diversion without reduction in lane width - Minimize loud noise activity during evening and weekends - Monitor noise meters at designated intervals - Contingency planning, inspection and monitoring
JHZH-PM
JHZH-PM - Install additional EC measures (e.g. silt fences, nets) when necessary '- Regular inspection of site by ECO at affected zones - Contingency planning, inspection and monitoring
- Close communication with related authority - Emergency Response planning including Contingency planning e.g. quick evacuation route - Provide efficient geometric design and the road level to mitigate flooding
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM - To provide traffic marshals to direct traffic when necessary - Clearly defined zones for accessible pathways and restricted areas - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Guard rail or rigid barrier to be setup and interlocked properly - Code of Practise of Traffic Control and Work Zone - Placement of cone or barrier during diversion without reduction in lane width
JHZH-PM - To provide traffic marshals to direct traffic when necessary - Clearly defined zones for accessible pathways and restricted areas - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Guard rail or rigid barrier to be setup and interlocked properly - Code of Practise of Traffic Control and Work Zone - Placement of cone or barrier during diversion without reduction in lane width
- Vibration control plan - Vibration monitoring
JHZH-PM - Provide efficient geometric design and the road level to mitigate flooding -Awareness of climatic conditions -Regular monitor of water level in Opera estate Canal -Emergency Response planning including Contingency planning
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
- Complaint from nearby occupants - Complaint from LTA - Working time may be reduced with delay to programme
-Traffic congestion due to minimum diversions, - Injury to public or construction personnel drivers seeking alternative routes - Damage to temporary or permanent works
Road vehicles entering construction site / excavations
-Traffic congestion - Unauthorized entry of personnel to site
-Construction works in close proximity to the public -Excessive noise due to construction -Excessive noise due to bored and barette pile testing
- Injury to public or construction personnel - Disruption of essential services - Negative PR - Delays - Claims
-Interrupted construction, -Delays, -Environmental pollution
Impact
Noise, dust and vibration
Flooding from the Opera -Damage the canal or foundation during Estate Canal at Siglap Link construction, -Extreme flooding event; -Tidal fluctuation -Structural problem of the canal
Hazard
Discharge into Canal from -Heavy rain construction - Insufficient control on site -Surface run off, construction materials Construction Works (bentonite, concrete, grout, near Drains and Canal maintenance/cleaning facilities)
Construction Works near Drains and Canal
Traffic Diversion
Construction Works near Residental area
Construction works near Opera East Canal
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Mar-23
Mar-20
Mar-23
Mar-20
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Due Date By
Revision G 13 14
79 months
45 months
79 months
45 months
79 months
79 months
79 months
79 months
79 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 27/04/2017 15 16 17 Remarks
999
999
999
999
999
999
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
Site set up T309/CNSS
013
012
011
010
009
008
NA
N.A
N.A
N.A
N.A
N.A
Setting up of Noise Barriers
Recahrge well work
Lifting with Excavator (Pick and Carry)
Traffic Diversion
Traffic Diversion
Removal of sludge
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
MEWP topple
Hit by fallen object
Fall from height
Noise Barrier structural failure
Water pipe. Power grid cables. Telecom cables. High tension cables.
6
- Collapse of temporary works - Excessive movement / Collapse of adjacent structures - Injury or fatalities of public and construction workers
-Damage of machinery -Injury of worker -Damage of materials
-Damage of machinery -Injury of worker -Damage of materials
- Traffic jams hindering construction vehicles - Bottlenecks hindering traffic speed - Crossed traffic and pedestrian circulation paths - injury to public and/or construction work
- Traffic jams hindering construction vehicles - Bottlenecks hindering traffic speed - Crossed traffic and pedestrian circulation paths - injury to public and/or construction work
'- Injury to public or construction personnel - Contaminate soil, groundwater and surface water
Impact
-Failure to provide fall protection provision - Failure to provide control - Poor footage - Over loading of MEWP
-Damage to own and public properties (Claims) - Injury or fatalities of public and construction workers
- Collapse of temporary works - Incorrect information on adjacent structures - Not identifying the behaviour and response of - Damage to own and public properties (Claims) - Injury or fatalities of public and construction the ground and adjacent structures workers
-Flawed design of temporary works - Inappropriate use / misinterpretation of design codes - Lack of understanding of design software and output - Temporary works design is incompatible with adjacent structures
-Unplanned Drilling. - Insufficient marking on site. - Failure to conduct detection test.
-Uneven ground - Unauthorised lifting - Improper rigging -Overloading -Inexperience operator
-“A’ frame topple - Injury to public - Fingers / hand caught in rotating parts
- Change to road condition due to delivering material to site
- Change to road condition due to construction work, poor line of sight - Changed traffic condition causes confusion to road users - Improper/ unclear signages - Improper/ unclear separation of pedestrians paths and work site ingress/ egress points - Pedestrians jaywalking
-Pipe leakage and burst -Loose connection
-Uneven ground - Unauthorised lifting - Improper rigging -Overloading -Inexperience operator
-Damaged to :
5 Hazard Cause
-Toppling of excavator - Falling of load/ material
Risk associated with Traffic Diversion
Risk associated with Traffic Diversion
Sludge spill
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Package 1 7
II
II
IV
IV
II
II
II
II
II
IV
IV
IV
IV
IV
II
II
IV
S
F IV
C
C
C
B
B
B
C
C
C
Ri
Initial Risk Category Ri
8
- Provision of Fall Protection Plan. - Establish PTW-Height system. - Provide proper access. - Provide adequate work platform. - Licensed MEWP operator. - Familiarisation briefing prior appointment.
- Perform further structural or geotechnical investigations e.g. coring, trial trenching - Apply PTW (e.g. welding) daily before commencement of work - Certified welder
- Sensitivity of design input parameters - Pre-qualify contractor - Apply PTW (e.g. welding) daily before commencement of work - Certified welder
-Thorough study of utilities drawings. - Cable detections by qualified LCDW - Provide clear utilities marking on site - Provide A3 size drawing of utility plan - Apply permit to dig and implement “checklist for working near utility” - Barricade work area while trenching
- Ensure work assess is planned. - Ensure adequate access for work mobilisation and public access. - Only competent lifting crew is allowed to involved in mobilisation. - PTW-Lifting approved prior unloading. - Provide proper exclusion zone to segregate work and public. - Provide warning signs.
●The excavator designed for pick and carry operations must have load chart stating clearly the limitattions for picks and carry operation ●Tag line shall be used during operation ● Ensure the route of travel is firm and level ●Lifting supervisor to ensure the load is firmly secured and tied ●Benchman to guide excavator during the pick and carry operation
- Design stages of traffic diversion to allow construction to be carried out section by section - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Safety barrier to be setup at designated storage zones - Proper signages display at prominent locations - Code of Practise of Traffic Control and Work Zone - designated path for access by pedestrians - Control unauthorized entry of personnel into loading/unloading zone during material delivery
- Design stages of traffic diversion to allow construction to be carried out section by section - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Guard rail or rigid barrier to be setup and interlocked properly Proper signages display at prominent locations - Code of Practise of Traffic Control and Work Zone
- Competent staff - Provide safety warning signage to keep other works clear from work area - Provide safety access to treatment plant - Permit for handling of sludge - Provide emergency contact no.
Mitigation Measures
II
II
V
V
II
II
II
II
II
V
V
V
V
V
II
II
V
V
S
F
C
C
C
C
C
C
C
C
C
Ri
Residual Risk Category Rr
11
JHZH-PM
Risk Owner
JHZH-PM
12
JHZH-PM
JHZH-PM
- Strengthening of noise barrier when necessary JHZH-PM - Additional site investigations and localized ground improvement when necessary - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts. - Approved Method Statement
-Enveloped MEWP work platform with scaffold JHZH-PM netting to contain material. Limit max. 2 person on MEWP. Max. weight 120kg. Firm and compacted ground for MEWP access. Provide adequate exclusion zone and signage. Provide banksman to ensure no authorised entry in to work zone.
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM - Engage experienced and competent consultant to perform the design - Engage experienced and competent contractor - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts. - Approved Method Statement
-Contact relevant utility agency for any presence JHZH-PM of unidentified utility Always treat utility as `live’ if encountered Only manual digging allowed for trial trench Full time supervision during trial trench
- Provide blinker lights to alert night motorist and /or pedestrian. - Ensure footage is firm and level at all times. - Never drag load. Lift vertically.
-AE to examine the lifting capacity of excavator JHZH-PM and issued the certification for the lifting. -Pick and carry operation is guided in SS536 : 2008
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly - Placement of cone or barrier during diversion without reduction in lane width
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly - designated path for access by pedestrians - Placement of cone or barrier during diversion without reduction in lane width
- Contain and handle spillage (e.g. excavate spill site and treat with dry sand, temporary diking) immediately - Contact additional emergency services when necessary
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
Mar-23
Mar-23
Mar-23
May-23
May-23
Mar-23
Mar-23
Mar-23
May-20
Due Date By
Revision G 13 14
79 months
79 months
79 months
79 months
79 months
79 months
79 months
79 months
45 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 27/04/2017 15 16 17 Remarks
T309/CNSS
999
014
NA
4
Hazard
5
6
Old machinery and poor maintenance causing disturbance to nearby resident
Installation of sheet piles Noise pollution (foundation support for sound barrier)
Installation of sheet piles Accidental dislodgement of -Carelessness and inexperience operator. (foundation support for sheet pile during driving - Faulty vibro hammer sound barrier)
Structure failure of machinery
Installation of sheet Using of poor condition piles (foundation support for machinery sound barrier)
-Serious injury to worker and property. -Stop work causing delay
-Disturbance to neighbouring resident -Hearing injury to workers
-Low productivity Job delay and behind schedule -Cost implication
-Serious injury to worker and property. -Stop work causing delay
-Toppling of machinery resulting in damage to property. -Injury to surrounding people.
Installation of sheet piles Poor ground condition (foundation support for sound barrier)
-Damage to underground services -Disruption to stakeholders -Penalty charges by authority -Stop work order by authority -Delay to work schedule
Impact
-Serious injury to worker and property. -Stop work causing delay -Damage to machineries
Location of utilities not reflected in utility drawing
Hazard Cause
Installation of sheet Collision of machinery and piles Constraint of work area (foundation support for site people. sound barrier)
Installation of sheet piles Damage to utilities (foundation support for sound barrier)
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Package 1
-
IV
IV
IV
IV
IV
IV
7
F
I
II
II
I
I
II
S
B
C
C
B
B
C
Ri
Initial Risk Category Ri
8
I
-Additional sling tied to sheetpile and machinery as extra protection in case grabber gives way V -Ensure sheetpile is clamped tightly between the grabber jaws before hoisting up vertically for installation
II
I
I
II
II
V
V
V
F
S
C
C
C
C
C
C
Ri
Residual Risk Category Rr
-Installed sound barrier. -Used of silent piler. V -Refrain from working at night and weekend/PH
-Machine to be inspected and certified by AE. -Regular monthly maintenance of machineries
-Access to be laid with hardcore and compacted. -Steelplate to be laid on top of hardcore. -Movement of machinery must be guided by benchemen
-Work zone to be barricaded to prevent unauthorized entry -Used of tag line to control swaying of load - Employed skilled operator and experienced lifting team
-Carry out cable detection and trial trench along the path of sheet piles. V -Apply permit to dig prior to work start.
Mitigation Measures
Daily pre operation check on grabber by operator before start of work
Regular maintenance regime in place
LOTO system applied during maintenance period
-Ground preparation completed with the issuance of COS from PE -Ensure no overloading of machinery (Load kept at 75% of SWL
Apply for permit to move for machinery movement from point to point
Cable detection by LEW
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
11
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
Risk Owner
12
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Due Date By
Revision G 13 14
79 months
79 months
79 months
79 months
79 months
79 months
Risk Exposure Period
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Status
Date: 27/04/2017 15 16 17 Remarks
999
999
999
999
T309/CNSS
Vector Management T309/CNSS
T309/CNSS
Mobilization T309/CNSS
018
017
016
015
NA
NA
NA
NA
Traffic Diversion
Workers working on site
Setting up of Hoarding
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
5 Hazard Cause
Risk associated with Traffic Diversion -Unsafe traffic conditions, accident hot spot and vehicles crashing into site -Damaged to UG services -Noise and dust pollution
Transmission of Dengue and Zika
Mosquito bites on construction/ public personnel
6
- Collapse of temporary works - Excessive movement / Collapse of adjacent structures - Injury or fatalities of public and construction workers
Impact
- Transfer (delivery and lifting) material, plant and manpower -Inadequate signage and poor traffic control measures -Unsafe traffic layout -Failure to carryout trial trench for UG services -Failure to barricade work area and provide banksman to guide vehicular movement on site -Failure to equip with proper PPE
- Mosquito breeding - Mosquito bites
- Mosquito breeding - Mosquito bites
- Traffic jam - Injury to public or construction personnel - Claims - Delays
- Injury or fatality of public or construction personnel - Claims - Delays
- Injury to public or construction personnel - Claims - Delays
- Collapse of temporary works - Incorrect information on adjacent structures - Not identifying the behaviour and response of - Damage to own and public properties (Claims) the ground and adjacent structures
Hoarding structural failure -Flawed design of temporary works - Inappropriate use / misinterpretation of design codes - Lack of understanding of design software and output - Temporary works design is incompatible with adjacent structures
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Package 1 7
IV
IV
IV
IV
IV
F
II
I
I
II
II
S
C
B
B
C
C
Ri
Initial Risk Category Ri
8
- Code of Practise of Traffic Control and Work Zone - Use of barrier and/or gate guards for exit/entrances to site -Approval of temporary traffic diversion layout by TM -Traffic layout and signage to follow TCP -Submit PSR (road) for clearance -Ensure good visibility of signage --Apply permit to dig prior to start work -Conduct RA/ SWP briefing -Desk top study of all utilities and carryout appropriate trial trench -Barricade work area and provide proper signage and warning to motorist and pedestrian. -Lane closure to avoid peak hours, applicable hours is 9:30-16:30 for daytime and 16:30-09:30 for night time closure
- Pest control '- Emergency Response planning - Vector control management - Additional supervision - Oiling in stagnant water and other respective areas - Provision of insect repellents to site staff
- Pest control - Emergency Response planning - Vector control Management - Additional supervision - Oiling in stagnant water and other respective areas - Provision of insect repellents to site staff
- Perform further structural or geotechnical investigations e.g. coring, trial trenching
- Sensitivity of design input parameters - Engage experienced and competent consultant to do the design - Engage experienced and competent contractor - Pre-qualify contractor
Mitigation Measures
IV
V
V
V
V
F
II
I
I
II
II
S
C
C
C
C
C
Ri
Residual Risk Category Rr
11 Risk Owner
JHZH-PM
JHZH-PM
JHZH-PM - Properly traffic control and signages with qualified traffic marshal - Clearly defined zones for accessible pathways and restricted areas - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Emergency Response planning including Contingency planning, inspection and monitoring - Lifting zone to be barricaded before works commence - Placement of cone or barrier during diversion without reduction in lane width -Flow chart indicating the flow of instruction enabling the lorry truck to enter the lane closure work area during soil removal or delivery of materials.
- Regular inspection of site to identify and eliminate breeding sites - Misting
- Regular inspection of site to identify and eliminate breeding sites - Misting
JHZH-PM - Strengthening of hoarding when necessary - Additional site investigations and localized ground improvement when necessary - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts.
JHZH-PM - Engage experienced and competent consultant to perform the design - Engage experienced and competent contractor - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts.
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
12
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Due Date By
Revision G 13 14
79 months
79 months
79 months
79 months
79 months
Risk Exposure Period
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Status
Date: 27/04/2017 15 16 17 Remarks
999
T309/CNSS
020
019
N.A
NA
Lifting with crane
Lifting with crane
4
5
- Breakage of lifting chain - Breakage of lifting sling - Failure of brake motor/gear - Failure of sling/chain buckles and hooks - Overloading of carried loads over limited of design capacity - Unauthorized modification of lifting points
Hazard Cause
- Improper securing of material/ equipment - Overloading of material/ equipment - Slight tilt in crane '- Sudden movement of crane boom
Sharp edge material being - Site personnel cut by sharp material during lifted/ lowered/ handled handling
Failing of loose material/ equipment
Crane topple / Hoisted load - Poor crane footage hit crane - Incompetent lifting team - Poor lift plan - Congested work environment
Failure of lifting mechanism
Hazard
Note * - Action Owner will be reassigned from PM to Engineer-in-Charge when respective Engineer-in Charge is established
999
T309/CNSS
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
7
- Injury and fatality to construction personnel - Delays - Claims
I
II
IV
IV
I
IV
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
I
S
IV
F
C
B
B
B
Ri
Initial Risk Category Ri
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
Impact
Package 1 8
- Store all sharp material into material cages when possible - Pack/ organize sharp material - Use of PPE (e.g appropriate safety gloves, long sleeves, helmet and safety boots and glasses)
- Approved PTW (e.g lifting) daily before commencement of work - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be marked, identified and approved - Approved Lifting plan - Material shall be stacked safely and within stacking limit and load
- Design and COS crane access - No Overloading at all times - Proper mainyenance of crane - Only competent lifting team is allowed - Implemet Permit to lift - Include both Max. and Min load radius - Do not conduct lifting in congested work environment. - Provide exclusion zone and Provide warning signs. - Provide sufficient tag lines
- Apply PTW (e.g. lifting) daily before commencement of work - Monthly inspection of lifting mechanisms - Lifting Supervisor to ensure correct method of usage - Colour coding all lifting mechanisms for validity and serviceability levels - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Lifting points to be identified and approved - Approved Lifting Plan
Mitigation Measures
I
II
IV
I
V
V
I
S
V
F
C
C
C
C
Ri
Residual Risk Category Rr
11
12
JHZH-PM
- '- Identify sharp material and dipose (e.g. nails, JHZH-PM broken glasses) - Wrap sharp edges when possible
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM
Risk Owner
JHZH-PM
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
Oct-17
Mar-23
Oct-17
Mar-23
Due Date By
Revision G 13 14
13 months
79 months
13 months
79 months
Risk Exposure Period
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Status
Date: 27/04/2017 15 16 17 Remarks
Minutes Title: 3 months look ahead Risk Register Workshop No 11 Date: 13 Apr 2017 Time: 10.30am-12.30pm Held at: LTA level 2 meeting room
Chaired by: Jong/ Peter Minuted by: Jong Distribution date: 27 Apr 17
Attendees list See attached
Apologies list
Page 1 of 3
Minutes ITEM
MATTERS DISCUSSED
1.0
Introduction
ACTION
The complete flow of the process will be demonstrated via a short slide presentation
Info
Jong introduced the three months' activities from Apr-Jun 17 at the five working zones.
2.0
2.1
Slide presentation on activities at Entrance A
LTA commented to note on the sealing between Canal and Diverted Drain and any debris resulted from excavation to be cleared from the drain.
2.2
Jong/ Peter
JHZH
JHZH LTA commented to look into tree removal when grabbing D-wall at Entrance A
3.0
Slide presentation on activities at Cooling Tower
Jong/ Peter
3.1
JHZH commented that CCTV will be installed to view trucks loading soil in and out of site and possibly to monitor unsafe acts when Working at Height
INFO
4.0
Slide presentation on activities at Entrance D
Jong/ Peter
4.1
LTA commented to manage the public movement within Entrance D and regularly update the school on changes in construction sequence and the implementation of safety measures
5.0
Any Other Matters:
5.1
LTA commented to inform Nparks on 17th Apr the start of Traffic Diversion Stage 1C.
5.2
5.3
LTA commented that 3 months look ahead shall focus only on major risk. The presentation is too long. LTA commented that concrete pump supplier should inspect and use the correct type/length of pipe when pumping concrete.
Page 2 of 3
JHZH
INFO JHZH
Minutes ITEM
MATTERS DISCUSSED
6.0
Next Meeting
ACTION
The next meeting will be scheduled on 27 Apr 17 @ 10am
Page 3 of 3
All / Info
18th May 2017
Jong/ Peter Nugent/ Tommy
3 Months Programme Look ahead Risk and Mitigation
Construction of Siglap Station Thomson‐East Coast Line
Contract T309
2) To identify the major risk hazards and elaborate the mitigation measures in this workshop
1) To identify the major works activities for the three months, May 2017 – Jul 2017
Objectives of this workshop:
Hoarding Installation Noise Barrier installation Box culvert drain works Utility Corridor Installation Road Works
Entrance C
Guide Wall & D‐Wall construction (L‐shape‐Dwall lifting)
3
Recharge Well Installation
Guide Wall & D‐Wall construction
Cooling Tower
Road Works ‐Siglap Link Drain works‐ Siglap Link Noise Panel installation Inside the Victoria School Noise Panel installation near to Laguna Park Hoarding Installation Guide Wall & D‐Wall construction
Drain connection to canal work at Keesun Avenue Noise Panel installation above Drain Noise Panel installation Siglap Linear Park Guide Wall & D‐Wall construction
Entrance B
Entrance D
Entrance A
Upcoming Works May 17 – Jul 17
Works at Ent. B
Entrance B
D‐Wall construction (L‐shape panel)
Entrance B
Side View
Ground
“L” shaped D‐wall panel
Plan View
6.5m
1) “L” shaped D‐wall panel installation – Risk mitigation
5
Normal D‐wall panel
Hazard Cause
• •
•
•
Loose • material on D‐ • wall panel •
6
Designed and COS crane access. Approved Permit to Lift. Approved lift plan. Valid and adequate lift gears for taking weight of D‐wall panel. Provide adequate tag lines. Identify proper hooking point for turning D‐ wall. Only one LS to control tandem lift. Standing supervision by LE. Ensure lifting activities not carried out in congested work area. Ensure no loose material on D wall panel prior lifting. Provide exclusion zone and warning sign to prevent unauthorised entry. Tandem lift to be carried out during day shift. No obstruction of LS/CO view at all times.
Mitigation Measure
Unplanned lift • • • Workers hit by Over loading • fallen objects due to poor from D –wall coordination • between LS •
Risk
Tandem lift Crane collapse work
Activity
1) “L” shaped D‐wall panel installation – Risk mitigation
‐ ‐
‐
‐
JV Superintendent – Peter HSL LS Ahmed Sufi
HSL LS Ahmed Sufi
HSL LS Ahmed Sufi
JV Lift Engineer Killi JV Lift Engineer killi JV Superintendent – Peter
HSL LS Ahmed Sufi JV Engineer Desi
‐ ‐ ‐ ‐ ‐
LV lift Engineer Killi JV Project Manager ‐ Frank JV Project Manager ‐ Frank HSL LS Ahmed Sufi
‐ ‐ ‐ ‐
Action Owner
Hand finger injuries / Amputation
Stitching D‐wall
Workers fall into d‐wall trench
Risk
Activity
‐
‐ ‐
7
Designed stopper for resting D wall cage All personnel to cleared at least 3 meters away during lowering of stitched D‐wall. Do not start stitching rebar cage until rebar cage is fully rested on stopper. Always keep hand away from line of fire. Provide proper barricades and warning sign around D—wall trench.
Mitigation Measure
‐ D‐wall stiches ‐ tear due to poor coordinated lift
Uncontrolled movement / poor coordinated lift.
Hazard Cause
1) “L” shaped D‐wall panel installation – Risk mitigation
‐ ‐
‐
‐ ‐
HSL Supervisor – Sohel HSL Supervisor‐ Sohel
HSL Supervisor – Sohel
JV Engineer – Desi HSL Supervisor Sohel
Action Owner
Entrance A Drain Work connection to existing cannel at Keesun Avenue Noise Panel installation above Drain Noise Panel installation Siglap Linear Park Guide Wall & D‐Wall construction
Works at Ent. A
Drain work at Keesun Ave.
2) “Diverted drain connection to existing cannel – Risk mitigation
2) “Diverted drain connection to existing cannel – Risk mitigation
Risk
Connection New diverted to existing drain flooded drain
Activity
Back flow from existing drain due to high tides
Hazard Cause
•
•
•
Richee / Technocrete Supervisor‐ Babu/Sayeed Richee Supervisor‐ Babu
‐
JV Engineer – Jessica ‐
‐
JV Engineer – Jessica Richee/ Technocrete Supervisor‐ Babu/Sayeed
‐ ‐
• • Work to be carryout on low tide period. Provide sandbags to block water from entering work area. No personnel to enter drain when water start back flowing. No workers allowed inside drain when water is more than or equal to 10cm deep. Markers to be clearly mark out inside drain.
Action Owner
Mitigation Measure
2) “Diverted drain connection to existing canal – Risk mitigation
Wall cut not secured
Workers crush by collapse wall
Hazard Cause
Back flow from existing drain due to high tides
Risk
Connection Flooding of to existing diverted drain drain
Activity
•
• •
•
•
• •
JV Engineer – Jessica
Technocrete Supervisor‐ Sayeed Technocrete Supervisor‐ Sayeed
Richee / Technocrete Supervisor‐ Babu/ Sayeed
JV Engineer – Jessica
JV Engineer – Jessica Richee / Technocrete Supervisor‐ Babu/ Sayeed
Action Owner
Work to be carryout on low tide period. ‐ Provide sandbags to block water from entering ‐ work area. ‐ No personnel to enter drain when water ‐ Wall must be properly secured before cutting take place. ‐ MS must be strictly followed. ‐ Never place man near wall especially when cutting come to the last bit. ‐ Standing supervision by JV Engineer and ‐ subbies supervisor. ‐
Mitigation Measure
2) “Diverted drain connection to existing cannel – Risk mitigation
Guide wall and D‐wall construction work at Ent. B
Works at Ent. B
D‐wall work
Activity
Crane hit surrounding structures, e.g. silo
Crane Toppling
Risk
•Load hit onto crane
•Instability of working platform
•Failure of loose material equipment/ rebar cages
Hazard Cause
2) D‐walling lifting work – Risk and Mitigation
‐
•Material shall be stacked safely and within stacking limit and load
‐
‐
• Look into min load radius when hoisting bulky items e.g. rebar cage. •Only R/S can give signal. Trade supervisor cannot involved in lifting work.
HSL R/S Ganesan
‐
•Signaler to communicate with crane operator
HSL LS Ahmed Sufi
HSL SC‐ Omar
HSL LS Ahmed Sufi
HSL Supervisor‐ Sohel HSL LS Ahmed Sufi ‐
•Safety zone established
‐
•Low speed in lifting and lowering
JV Engineer Desi
JV LE Killi
‐
•Approved lifting plan, reviewed by LE and approved by PM
‐
HSL LS Ahmed Sufi
‐
•Lift load by 300mm, stabilized for 3 seconds.
•Lifting points to be identified and approved
Action Owner
Mitigation Measure
D‐wall work
Activity
Crane hit surrounding structures, e.g. silo
crane Toppling
Risk
HSL supervisor‐ Sohel
‐
•Put in place the lifting permit system and display the relevant details on site.
•Inadequate supervision and control
•Lack of communication
•Banksmen to guide crawler crane movement, ensuring no tracking over drain, trench or uneven ground.
•Lifting operation supervised by lifting supervisor
•Approved lifting plan, reviewed by LE and approved by PM
HSL LS Ahmed Sufi HSL R/S Ganesan
‐
JV PM‐ Frank
‐
‐
HSL supervisor‐ Sohel
JV Superintendent
‐
•Provide adequate hardstanding /firm working platform
‐
Action Owner
Mitigation Measure
•Instability of working platform •Ensure no overloading of crane •Signaler to communicate with crane •Failure of loose material operator equipment/ rebar cages
Hazard Cause
2) D‐walling lifting work – Risk and Mitigation
Preparation of ground access with hard‐core
2) D‐walling lifting work – Risk and Mitigation
Heavy machine on steel plate
PTW –lifting system is established
2) D‐walling lifting work – Risk and Mitigation
Lifting supervisor checking the checklist of operator
Load chart display ensuring no overloading of crane.
2) D‐walling lifting work – Risk and Mitigation
Daily checklist of machinery
Low speed in lifting and lowering
Lifting points to be identified and approved
Approved lifting plan
Lift load by 300mm, hold for 3 seconds
2) D‐walling lifting work – Risk and Mitigation
Safety zone established
Material shall be stacked safely and within stacking limit and load
Approved lifting plan for all heavy lifting on site
2) D‐walling lifting work – Risk and Mitigation
Pre‐start briefing in language understood by workmen prior lifting work.
2) D‐walling lifting work – Risk and Mitigation
Provide exclusion zone and warning signs
2) D‐walling lifting work – Risk and Mitigation
To include min load radius in lift plan.
LM Machine not up to expectation will tagged “Not Safe for Use”
2) D‐walling lifting work – Risk and Mitigation
End
Minutes Title: Risk Register Workshop No. 14 Date: 18 May 2017 Time: 11.00am-12.00pm Held at: LTA level 2 meeting room
Chaired by: Tommy Lee/ Peter Nugent/ Minuted by: Tommy Lee Distribution date: 22 May 17
Attendees list See attached
Apologies list
Page 1 of 3
Minutes ITEM
MATTERS DISCUSSED
1.0
Introduction
ACTION
Risk Workshop will be on 3 months look ahead presentation with TD1 canal works connection at Entrance A and lifting of L-shape D-wall panel held on 18 May 2017 was submitted. This is the no. 14 workshop held.
Info
The complete flow of the process will be demonstrated via a short slide presentation The project superintendent will provide the necessary information required to mitigate risks on TD1 canal works and L-shape D-wall lifting works. 2.0
Slide presentation on 3 months look ahead activities 2.1
2.2
2.3
2.4
T309P informed JHZH that space between two cranes shall be considered carefully within the site utilization. T309P informed that pictorial safe working procedure can be a more effective way to educate the workers.
JHZH informed that the lifting of the L-shape panel methodology is under discussion and will be finalize in the method statement. T309P informed that the large cage is propped up in other project and for JHZH's consideration. T309P asked on the risk involving traffic diversion within Laguna Park and hot works which can be topics for the workshop.
2.5
Peter JHZH
INFO
JHZH
JHZH
JHZH T309P informed to include in the risk register, if not already included: 1. burning of plant equipment 2. loading/ unloading of material
2.6
LYL T309P informed QPS to include an I&M risk register which can be discussed in the next workshop.
Any Other Matters: 3.0
The next workshop shall cover traffic diversion within Laguna Park or hot works in general.
Page 2 of 3
INFO
Minutes ITEM
MATTERS DISCUSSED
ACTION
Next Workshop 4.0 The next weekly workshop will be scheduled on 25 May 17 @ 10am.
Page 3 of 3
All / Info
100
100
T309/CNSS
T309/CNSS
ERSS for Temporary Work
008
007
T309/CDSS/100/008
T309/CDSS/100/007
Trenching
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
Instability of temporary works (trenches)
● Differential settlement between station ERSS ● Failure of loose material, equipment/ rebar cage ● Instability of working platform
Hazard
4
5 Hazard Cause
ERSS wall construction within F1 soil layer - F1 soil layer collapse - Trench stability
- Not identifying the behaviour and response of the ground and adjacent structures
Flawed design of temporary works - Inappropriate use / misinterpretation of design codes - Lack of understanding of design software and output - Incorrect information on adjacent structures - Temporary works design is incompatible with adjacent structures
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Doc no: T309-JHZH-RAR-PWD-RIS-0001
- Collapse of temporary works - Excessive movement/Collapse of adjacent structures - Injury or fatalities of public and Construction workers
- Collapse of temporary works - Collapse / damage of adjacent structures - damage of permanent works - Injury or fatality of construction workers or public
Impact
6
The Risk Register is a "live document" and it will be the responsibility of all parties involved in the design, construction and commissioning of the T309 Project and to ensure that all reasonable means and measures are put in place for the effective management of all the safety risks.to continue to identify new risks that arises.
e
Package 1
F
V
V
V
7
I
I
I
S
C
C
C
Ri
Initial Risk Category Ri
8
- Contractor to produce robust design - Appropriate design sensitivity - Specify minimum penetration of panels - Additional site investigation - Pre-qualify contractors - Emergency Response planning - Provide temporary strut with PE endorsement
- Review levels to be developed - Regular review of Instrumentation / monitoring e.g. LBs to monitor building movement, LGs for ground movement and IW or XYZ for ERSS. - Approved Permit to lift and lifting plan - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be identified, marked and approved
- Contractor to produce robust design - Approved Permit to lift and lifting plan - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be identified, marked and approved
Mitigation Measures
I
I
V
V
I
S
V
F
C
C
C
Ri
Residual Risk Category Rr
11
12
JHZH-PM - Regular review instrumentation reading - Perform probing and SI (SPT) at regular intervals - Perform Ground Improvements when necessary - Joint inspection between JHZHJV and QPS for every Dwall 1) Mild case (to read; less than 10% of total panel excavated volume) – Create an earth bund wall surrounding the affected panel, fill up the bund wall pool with bentonite to increase the bentonite head level. 2) Moderate case (to read; more than 10% of total panel excavated volume, without any visual ground/ platform depression) – Move the grabber and other unnecessary heavy equipment at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. 3) On a case by case basis for a severe case (to read; more than 10% of total panel excavated volume, with obvious visual ground/ platform depression) – Move all machinery away except excavator at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. After 24 hours of backfilling, conduct light cement grout beneath the depressed platform.
JHZH-PM
JHZH-PM
- Steel plate to ensure uniform loading of crane JHZH-PM weight and outrigger - Use of level indicator and inclinometer - Additional site investigation when necessary - Lifting zone to be barricaded before works commence 1) Mild case (to read; less than 10% of total panel excavated volume) – Create an earth bund wall surrounding the affected panel, fill up the bund wall pool with bentonite to increase the bentonite head level. 2) Moderate case (to read; more than 10% of total panel excavated volume, without any visual ground/ platform depression) – Move the grabber and other unnecessary heavy equipment at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. 3) On a case by case basis for a severe case (to read; more than 10% of total panel excavated volume, with obvious visual ground/ platform depression) – Move all machinery away except excavator at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. After 24 hours of backfilling, conduct light cement grout beneath the depressed platform.
*Action Owner
JHZH-PM
Risk Owner
- Steel plate to ensure uniform loading of crane JHZH-PM weight and outrigger - Use of level indicator and inclinometer - Additional site investigation when necessary - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts. - Lifting zone to be barricaded before works commence - Lift load by 300mm, hold for 3 seconds, all personnel 3m away Approved lifting plan, reviewed by LE and approved by PM - Lifting points to be identified and approved - Low speed in lifting and lowering - Material shall be stacked safely and within stacking limit and load - Safety zone established - Signaler to communicate with crane operator
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Summary of Residual Risk Classes A 0 B 0 C 74 D 15 89
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
Summary of Initial Risk Classes A 0 B 22 C 60 D 7 89
Apr-17
Apr-17
Apr-17
Due Date By
Revision I 13 14
7 months
7 months
7 months
Risk Exposure Period
C
C
ipe
Target Risk Rating
Open
Open
Open
Status
Date: 23/05/2017 15 16
17 Remarks
010
100
100
100
T309/CNSS
T309/CNSS
T309/CNSS
012
011
009
100
T309/CNSS
T309/CDSS/100/012
T309/CDSS/100/011
T309/CDSS/100/010
T309/CDSS/100/009
Construction of ERSS for Utility Diversion
Construction of ERSS for Drain Diversion
Construction of ERSS
Construction of ERSS
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
Instability of temporary works (Utility Diversion ERSS)
Instability of temporary works (Drain Diversion ERSS)
Excessive ground movement of adjacent structures and utilities
Instability of temporary works (ERSS failure)
Hazard
4
5 Hazard Cause
6 Impact
F
Structural damage/deflection of existing structures - Damage to utilities - Traffic accidents with associated injuries - injuries to public or construction workers associated with ramp distress - Damage to road surfaces - Wall toe movement
- Damage to utilities - Damage to road surfaces
-Higher than expected lateral deflection of ERSS wall during excavations - Unforeseen ground conditions - Inappropriate removal of struts - Over-excavation - Excavation for the utilities laying/trench
- Unforeseen higher than designed surcharge
- Damage to utilities - Damage to road surfaces
- Unforeseen higher than designed surcharge
IV
IV
III
III
III
III
IV
- Injuries to public or construction workers associated with ramp distress - Traffic accidents with associated injuries - Structure Integrity of sheet piles.
- Inappropriate removal of struts - Over-excavation - Excavation for the drain and damage ERSS - Sheet pile obstructed and not able to pile into required depth. -Poor quality weld and design of sheet pile bracing.
IV
III
III
III
IV
IV
IV
I
I
V
V
I
I
S
V
V
7
C
C
C
C
C
C
C
C
C
C
C
Ri
Initial Risk Category Ri
- Structural damage/deflection of existing structures - Damage to utilities - Injuries to public or construction workers associated with ramp distress - Damage to road surfaces - Wall toe movement
Structural damage/deflection of existing structures - damage to utilities - Traffic accidents with associated injuries - injuries to public or construction workers associated with ramp distress - damage to road surfaces - Wall toe movement
Package 1 8
- PE to ensure surcharge level to within acceptable loading
- Contractor to produce robust design - Method Statements to ensure safe working methods - Monitoring on site - Gather knowledge from people with relevant experience - Visual inspection
- PE to ensure surcharge level to within acceptable loading
- Method Statements to ensure safe working methods -Follow the PTW (e.g excavate) daily during work - Review design of sheet pile and provide COS. - Only certified and appointed welders are allowed to weld. - Method statement to ensure proper bracing is provided.
- Contractor to produce robust design - Method Statements to ensure safe working methods - Gather knowledge from people with relevant experience
- PE to ensure surcharge level to within acceptable loading
- Contractor to produce robust design - Method Statements to ensure safe working methods -Regular review instrumentation reading - Apply PTW (e.g. excavate) daily before commencement of work
- Calculate amount of bentonite level required
- Robust Contractor's ERSS system - Pre-qualify contractors
- Contractor to produce robust design - Appropriate design sensitivity
- Contractor’s Method Statements - Apply PTW (e.g. excavate) daily before commencement of work '- Emergency Response Planning including Contingency planning e.g. grouting of gaps - Additional site investigation
Mitigation Measures
V
V
III
III
III
III
V
V
III
III
III
I
I
V
IV
IV
V
V
I
I
V
V
S
F
D
D
D
D
D
C
C
C
C
C
C
Ri
Residual Risk Category Rr
11
- No stockpiling
JHZH-PM
-Provide ground improvements when necessary JHZH-PM - Requirements to record penetration into competent stratum on installation -High quality site records -Bearing capacity checks for construction equipment - Installation of additional recharge wells & pressure relief wells as contingencies.
- No stockpiling
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM - instrumentation/monitoring to monitor strut loads. - Daily physical inspection of strutting system
JHZH-PM
JHZH-PM
JHZH-PM -Statutory requirement for QP(Sup) to be responsible for supervision of temporary works. -Emergency Response planning including Contingency planning
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
-Normal/ established procedures for staging the JHZH-PM works to protect adjacent utilities -Permit to remove strut system followed to prevent inappropriate removal of struts -Emergency Response planning including Contingency Planning
- No stockpiling
12 *Action Owner
JHZH-PM
JHZH-PM
Risk Owner
- Control of excavation opening to pouring time JHZH-PM
- High quality construction records - Ensure trench stability - Emergency Response planning
- instrumentation/monitoring to monitor strut loads. - Daily physical inspection of strutting system
-Emergency Response planning including Contingency planning -Instrumentation/monitoring to monitor strut loads. - Instrumentation/ real time monitoring - Perform probing and SI (SPT) at regular intervals - Sufficient vibration monitors with appropriate trigger levels to be installed. - Provision of recharge wells. -Provide proper recharging system -Provide proper filter gravel
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
-Higher than expected lateral deflection of ERSS wall during excavations - Unforeseen ground conditions
- Unforeseen higher than designed surcharge
Higher than expected lateral deflection of ERSS wall during excavations - Unforeseen ground conditions - Inappropriate removal of struts - Over-excavation - Excavation of cut and cover tunnel
- Low bentonite level
Inadequate structural detail connection between - Collapse of temporary works strut, waler to ERSS walls / shafts / excavations - Excessive movement/Collapse of adjacent structures - Injury or fatalities of public and Construction workers - Contractor's ERSS design - Workmanship
- Groundwater drawdown
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Apr-17
Oct-17
Apr-17
Apr-17
Apr-17
Apr-17
Apr-17
Apr-17
Apr-17
Apr-17
Mar-17
Due Date By
Revision I 13 14
7 months
13 months
7 months
7 months
7 months
7 months
7 months
7 months
7 months
7 months
7 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 23/05/2017 15 16 17 Remarks
100
100
T309/CNSS
T309/CNSS
014
013
NA
N.A
4
Gaps in sheet piles
Hazard
- Instability of temporary works (kingpost for traffic decking - ERSS) -Poor ground condition -Using of poor condition machinery - Noise pollution -Accidental dislodgement of kingpost during driving Construction of ERSS -Collision of machinery and (Kingpost) site people. for traffic decking
Construction of ERSS (Drainage diversion)
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
5 Hazard Cause
- Poor design lead to undersize kingpost. - Poor workmanship. -Overloading of kingpost with other load not considered in the design. -Toppling of machinery resulting in damage to property. -Injury to surrounding people. -Structure failure of machinery.. -Old machinery and poor maintenance causing disturbance to nearby resident. - Carelessness and inexperience operator. Faulty vibro hammer.
- Supporting structure across the excavation due to lack of diversion corridor
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Collapse of temporary works - Collapse / damage of adjacent structures - damage of permanent works - Injury or fatality of construction workers or public
- Leakage through gap in the walls - Damage to services - Groundwater drawdown - Localized collapse of soil in the gap during excavation
Impact
Package 1 7
IV
III
S IV
F III
C
C
Ri
Initial Risk Category Ri
8
- Method Statements to ensure kingpost is constructed according to MS -JV engineer / QPS to supervise kinghpost construction work to esnure quality of workmanship. - Design to allow sufficient safety factor for structure interity of kingpost. -Access to be laid with hardcore and compacted. -I beam to be properly stacked and excluded. -Machine to be inspected and certified by AE. -Regular monthly maintenance of machineries - Work zone to be barricaded to prevent unauthorized entry - Used of tag line to control swaying of load. - Only allow skilled operator and experienced lifting team.
- Minimize gaps to minimum size required - Utilities diverted from excavation wherever possible - Instrumentation around gap area when necessary
Mitigation Measures
V
III
S IV
F IV
D
D
Ri
Residual Risk Category Rr
11 Risk Owner
- During construction phase, ensure RA control JHZH-PM measure are implemented - e.g. -Segregation of man and machines -Provide designated pedestrian access for wokers. - Provide adequate warning signs. - Provide proper barricades around bore hole. -Installed sound barrier - Used of silent piler - Refrain from working at night and weekend /PH - Additional sling tied to sheet pile and machinery as extra protection in case grabber gives way. - Access to be laid with hard-core and compacted. - kingpost to be laid on top of hard-core.
JHZH-PM - Reinstall sheet piles if there are gaps during installation - Emergency Response Planning including Contingency Planning (e.g. immediate removal works upon sighting of unfavaourable ground/wall movements) 1) Mild case (to read; less than 10% of total panel excavated volume) – Create an earth bund wall surrounding the affected panel, fill up the bund wall pool with bentonite to increase the bentonite head level. 2) Moderate case (to read; more than 10% of total panel excavated volume, without any visual ground/ platform depression) – Move the grabber and other unnecessary heavy equipment at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. 3) On a case by case basis for a severe case (to read; more than 10% of total panel excavated volume, with obvious visual ground/ platform depression) – Move all machinery away except excavator at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. After 24 hours of backfilling, conduct light cement grout beneath the depressed platform.
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
12
JHZH-PM
JHZH-PM
*Action Owner
Apr-17
Apr-17
Due Date By
Revision I 13 14
7 months
7 months
Risk Exposure Period
C
C
Target Risk Rating
Open
Open
Status
Date: 23/05/2017 15 16 17 Remarks
102
102
102
102
102
102
102
Diaphragm walling T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
007
006
005
004
003
002
001
NA
NA
N.A
T309/CDSS/102/004
T309/CDSS/102/003
T309/CDSS/102/002
T309/CDSS/102/001
Barrette pile test
Welding Works with Welding inverter
Welding Works with Oxygen acetylene and Welding inverter
Diaphragm walling
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
5
-Instability of ERSS wall trenches - Low shear strength in Marine Clay - Loose fills - Possible removal of buried obstructions - Presence of thick peaty layers - High pore water pressure in Marine Clay - Close proximity of adjacent activities such as jet grout piles or casting of nearby trench -Leakage of Bentonite from D wall -Poor Bentonite mixe.
Hazard Cause
6
- Structural damage/deflection of existing structures - Damage to utilities - Traffic accidents with associated injuries - Damage to road surfaces - Collapse of D wall
Impact
Kentledge collapse
- Failure of jack, jack force is not locked in - Unbalance pressure force in jack
- Testing of D-wall
- Improper maintenance of welding set - Improper connection and damaged cables - welding set not fully protected from wet surfaces - Welding in open space during wet weather condition
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury to public or construction personnel - Delays - Claims -Reputation
IV
IV
IV
I
I
I
II
IV
- Injury to public or construction personnel - Delays - Claims - Damage to permanent and temporary works
Fire sparks, fire explosion - Inappropriate welding of struts - Inappropriate welding of Traffic Deck due to Gas leaks, hose damaged, fitting damaged - Inappropriate welding of Noise Barriers - Incompetent welder deployed
Electrocution due to electrical leak
III
III
III
V
V
II
S
IV
F
V
#NAME?
7
B
B
B
C
D
D
D
C
Ri
Initial Risk Category Ri
- Water ingress - Lost toe stability - Loss of fines - Settlement of structures
-Inappropriate diaphragm wall design - Inappropriate use / misinterpretation of design codes
Package 1 8
- Contractor shall provide -uniform hydraulic pressure supply to all jacks to main balance force in test - Mechanical safe lock (safety valve) to lock pressure in jack during jack operation in case of pressure loss
- Test set up must get endorsement of PE
- PPE: Welding face shield, apron and gauntlet - Apply PTW (e.g. hot works) daily before commencement of work - Electrical wires to be secured above ground - Daily welding set checklist/ inspection - Certified welders - Reminder in Tool box meeting
- PPE: Welding face shield, apron and gauntlet - Proper housekeeping - Method Statements (e.g. - Close main value & flush hose line after usage) - Apply PTW (e.g. hot works) daily before commencements of works - Daily welding set checklist/ inspection - Fire extinguishers and fire blankets - Reminder in Tool box meeting '- Certified welders - Welding screen to contain sparks
- Specifying waterproofing details @ interface
- Use of adequate plant / equipment for diaphragm wall construction -Apply PTW (e.g. lifting) daily before commencements of works - Cage to be within lifting equipment capacity - Lifting points to be identified, marked and approved - Use of tandem lifting and explain in Safe Work Procedure - Close supervision by lifting engineer and signalman
- Emergency Response Planning including Contingency planning e.g. grouting of gaps - Method Statements to ensure safe working methods - Apply PTW (e.g. excavate) daily before commencement of work
- Method Statements to ensure safe working methods - Regular monitoring of critical structures - Stability calculations - Contingency planning e.g. (backfilling) in case of collapse, additional temporary struts - Trial panel - Raised guide walls - Control of bentonite properties (e.g. viscosity, sand content, PH value, density) - Visual inspection - Pre-qualify contractors -Apply PTW (e.g. excavate) daily before commencement of work - Deploy worker to monitor Bentonite level especially over week end.
Mitigation Measures
V
V
V
V
V
I
I
I
I
III
III
III
V
V
II
S
IV
F
C
C
C
C
D
D
D
C
Ri
Residual Risk Category Rr
11 Risk Owner
12
JHZH-PM
- Provide physical barrier (interlocked properly) JHZH-PM and safety signs around test sites - Emergency Response planning including Contingency planning - Proper design of kentledge system - Pre-qualify the subcontractor - Approved Method Statement
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM
JHZH-PM
-Monitoring of overall settlement and differential JHZH-PM settlement of the kentledge - Provide physical barrier (interlocked properly) and safety signs around test sites - Emergency Response planning including Contingency planning - Proper design of kentledge system - Pre-qualify the subcontractor - Approved Method Statement
-No welding work under rain weather/ wet surfaces - Monthly inspection of welding equipment - Apply Safe Work procedure - Electrical neoprene cable double insulated
- Remove flammable items (timber, canvas etc.. )from welding premises - Monthly inspection of welding equipment - Apply Safe Work Procedure - Implement PTW -Hot work
- High quality construction inspection and records - Method Statements to ensure safe working methods - Use of adequate plant/equipment for ERSS wall construction
- Adopt approved lifting plan - Ensure lifting equipment are inspected monthly - Lifting zone to be barricaded before works commence
- Proper post-cast for structure - Specifying waterproofing details @ interface
-Normal/ established procedures for staging the JHZH-PM works to protect adjacent utilities -Regular review instrumentation reading -Permit to remove strut system followed to prevent inappropriate removal of struts -No stockpiling against D-wall -Emergency Response planning including Contingency planning - Never start D-walling without having the cages ready.
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
Inadequate water tightness - Poor concrete compaction - Inadequate concrete cover and reduced durability due to honeycomb - Poor workmanship
Diaphragm wall cage too heavy to be lifted - Irregular D-wall cage to be lifted
Gaps in retaining systems Provision for services to pass through retaining -Cracking / leakage systems - Structural Damage - Waterproofing problems and associated repair
Excessive ground movement of adjacent structures and utilities
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Mar-17
Mar-17
Oct-17
Oct-17
Oct-17
Oct-17
Oct-17
Oct-17
Due Date By
Revision I 13 14
7 months
7 months
13 months
13 months
13 months
13 months
13 months
13 months
Risk Exposure Period
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 23/05/2017 15 16 17 Remarks
102
102
102
102
102
T309/CNSS
T309/CNSS
Pilling T309/CNSS
T309/CNSS
T309/CNSS
011
010
009
009
008
NA
T309/CDSS/102/004
T309/CDSS/102/001
NA
NA
Bored pile test
Piling
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
5
-Instability of ERSS wall trenches - Low shear strength in Marine Clay - Loose fills - Possible removal of buried obstructions - Presence of thick peaty layers - High pore water pressure in Marine Clay - Close proximity of adjacent activities such as jet grout piles or casting of nearby trench
Kentledge collapse
- Failure of jack, jack force is not locked in - Unbalance pressure force in jack
- Bored Pile testing
Inadequate water tightness - Poor concrete compaction - Inadequate concrete cover and reduced durability due to honeycomb - Poor workmanship
Excessive ground movement of adjacent structures and utilities
- Poor design - Poor workmanship - Poor rigging method
- Improper securing of material/ equipment/ cages - Overloading of material/ equipment/ cages - Slight tilt in crane '- Sudden movement of crane boom
Failing of loose material/ equipment/ rebar cages
In Stability of rebar cage (including cages for Lshape d-wall panel)
- Breakage of lifting chain - Breakage of lifting sling - Failure of brake motor/gear - Failure of sling/chain buckles and hooks - Overloading of carried loads over limited of design capacity - Unauthorized modification of lifting points -Inadequate rigging method.
Hazard Cause
Failure of lifting mechanism
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
7
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Water ingress - Lost toe Stability - Loss of fines - Settlement of structures
- Structural damage/deflection of existing structures - Damage to utilities - Traffic accidents with associated injuries - Damage to road surfaces
IV
IV
V
IV
IV
I
I
III
II
I
I
IV
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities - Rebar cage fall off during lifting process. - Crane damanged by swing load e.g. windscreen damaged by lifted rebar cage.
I
S
IV
F
B
B
D
C
B
B
B
Ri
Initial Risk Category Ri
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities -Crane topple -Tanish reputation
Impact
Package 1 8
- Contractor shall provide -uniform hydraulic pressure supply to all jacks to main balance force in test - Mechanical safe lock (safety valve) to lock pressure in jack during jack operation in case of pressure loss
- Test set up must get endorsement of PE
- Use of adequate plant / equipment for ERSS wall construction
- Method Statements to ensure safe working methods - Regular monitoring of critical structures - Stability calculations - Contingency planning e.g. (backfilling) in case of collapse, additional temporary struts - Trial panel - Raised guide walls - Control of bentonite properties (e.g. viscosity, sand content, PH value, density) - Visual inspection - Pre-qualify contractors - Apply PTW (e.g. piling) daily before commencement of work
- Cage design must get endorsement of PE - Regular inspection of interface with good records - Lifting points to be marked, identified and approved - Engineer to be present to confirm lifting points prior liftng rebar cage. - Ensure moin load radius is taken into consideration when preparing lift plan.
- Approved PTW (e.g lifting) daily before commencement of work - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be marked, identified and approved - Approved Lifting plan - Material shall be stacked safely and within stacking limit and load
- Apply PTW (e.g. lifting) daily before commencement of work - Monthly inspection of lifting mechanisms - Lifting Supervisor to ensure correct method of usage - Colour coding all lifting mechanisms for validity and serviceability levels - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Lifting points to be marked, identified and approved - Approved Lifting Plan -Weekly boom down inspection with mechanics
Mitigation Measures
V
V
V
IV
I
I
III
II
I
I
V
V
I
S
V
F
C
C
D
C
C
C
C
Ri
Residual Risk Category Rr
11
12
JHZH-PM
JHZH-PM
- Provide physical barrier (interlocked properly) JHZH-PM and safety signs around test sites - Emergency Response planning including Contingency planning - Proper design of kentledge system - Pre-qualify the subcontractor - Approved Method Statement
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM
Risk Owner
-Monitoring of overall settlement and differential JHZH-PM settlement of the kentledge - Provide physical barrier (interlocked properly) and safety signs around test sites Contingency planning - Emergency Response planning - Proper design of kentledge system - Pre-qualify the subcontractor - Approved Method Statement
- High quality construction inspection and records - Method Statements to ensure safe working methods
- Regular review Instrumentation reading -Permit to remove strut system followed to prevent inappropriate removal of struts - Emergency Response planning - Review SI report and cross check at site - Provide water relief wells when necessary
- Emergency Response planning including Contingency planning - Adopt 3X3 lifting principles. - Only R/S is allowed to give signal to crane operator.
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
Mar-17
Mar-17
Mar-17
Mar-17
Mar-17
Oct-17
Oct-17
Due Date By
Revision I 13 14
7 months
7 months
7 months
7 months
7 months
13 months
13 months
Risk Exposure Period
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Status
Date: 23/05/2017 15 16 17 Remarks
105
T309/CNSS
003
T309/CDSS/105/003
T309/CDSS/105/002
105
T309/CNSS
002
T309/CDSS/105/001
Adjacent Structures or Buildings T309/CNSS 105 001
NA
T309/CDSS/103/001
103
Permanent Works T309/CNSS
012
001
102
T309/CNSS
Construction work nearby to adjacent structures or buildings
Construction work nearby stake holders
Construction work nearby to school
Construction of Permanent Works
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
5
- Breakage of lifting chain - Breakage of lifting sling - Failure of brake motor/gear - Failure of sling/chain buckles and hooks - Overloading of carried loads over limited of design capacity - Unauthorized modification of lifting points
Hazard Cause
- Improper securing of material/ equipment/ cages - Overloading of material/ equipment/ cages - Slight tilt in crane '- Sudden movement of crane boom
Excessive ground and building settlement
Damage / excessive settlement to buildings/structures: - Victoria School Access Bridge - 2-storey semi-detached houses at Kee Sun Ave - St. Andrew's Autism Centre - Elliot at The East Coast - Laguna Park Electrical Substation (Block 5000F) - 2-storey semi-detached houses at Elliot Walk - Opera Estate Canal & Culverts Interface with the public.
Stop or delay school operation. Interface with the public.
- Activation criteria and minimum head are not given
- Ineffectiveness of recharge well layout given in the A/E design '- Some recharge well points will not provide effective recharging due to their locations being far from the buildings to be protected - Filter may not be compatible with the existing ground conditions - Pile test and D-wall test
-Long term settlements - Scheduling of work planning
-Unforeseen ground conditions -Excavation works causing unforeseen settlements -Groundwater drawdown
-Proximity of schools has special implications, -Victoria school is boarding school) - Scheduling of work planning
Excessive settlement - Insufficient ground information available for (Victoria School bridge and design canal structures)
Failing of loose material/ equipment/ rebar cages
Crane topple / Hoisted load - Poor crane footage hit crane - Incompetent lifting team - Poor lift plan - Congested work environment
Failure of lifting mechanism
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
7
- Damage to utilities - Damage to property
- Disruption to the site activities during installation of recharge well - Blockage of the filter gravel - Excessive water flow rate provided by the pumping system but little recharging effect
- Claims - Damage to buildings/structures - Complains from the public - Injuring the public
- Damage to buildings/structures - Delays - Claims - Closure of roads - Injuries / fatalities of construction workers and public
-Noise disruption to schools -Pick up and drop off times Damaged - Complains from the public - Injuring the public
- Serviceability issue with the bridge
IV
IV
V
V
III
IV
IV
III
III
I
I
IV
III
I
I
IV
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
I
S
IV
F
C
C
C
C
C
C
B
B
B
Ri
Initial Risk Category Ri
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
Impact
Package 1 8
-Activation criteria and minimum have been designed and indicated (Zone 1 to 3)
- Contractor's consultant has designed the recharging system, modified the configuration - Design of filter gravel has been provided
- Instrumentation / Monitoring - Reduce work inteface with public during peak hours
- Contractor’s Method Statements - instrumentation / monitoring - Real time monitoring - Specification of instrumentation and monitoring requirements by AE consultant - Strengthening and temporary propping when necessary - Additional site investigation
- Contingency planning, inspection and monitoring - Method Statements - Additional site supervision (e.g. traffic marshal) - Reduce work inteface with public during peak hours
- Provision of additional boreholes for bridge and canal design
- Approved PTW (e.g lifting) daily before commencement of work - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be marked, identified and approved - Approved Lifting plan - Material shall be stacked safely and within stacking limit and load
- Design and COS crane access - No Overloading at all times - Proper maintenance of crane - Only competent lifting team is allowed - Implemet Permit to lift - Include both Max. and Min load radius - Do not conduct lifting in congested work environment. - Provide exclusion zone and Provide warning signs. - Provide sufficient tag lines
- Apply PTW (e.g. lifting) daily before commencement of work - Monthly inspection of lifting mechanisms - Lifting Supervisor to ensure correct method of usage - Colour coding all lifting mechanisms for validity and serviceability levels - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Lifting points to be marked, identified and approved - Approved Lifting Plan
Mitigation Measures
IV
IV
V
V
III
IV
III
III
I
I
IV
III
I
I
V
V
I
S
V
F
C
C
C
C
C
C
C
C
C
Ri
Residual Risk Category Rr
11
- Provide proper recharging system - Provide proper filter gravel - Instrumentation/ Monitoring of settlement - Additional Site investigation
- Emergency Response planning - Provide proper recharging system - Provide proper filter gravel - Instrumentation/ Monitoring of settlement - Additional Site investigation - Control of bentonite pressures
- Perform ground improvements when necessary
-Emergency Response planning including Contingency planning -Instrumentation/monitoring to monitor strut loads. - Instrumentation/ real time monitoring - Sufficient vibration monitors with appropriate trigger levels to be installed. - Provision of recharge wells. -Provide proper recharging system -Provide proper filter gravel
12
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM
Risk Owner
JHZH-PM - Proper planning and traffic control - Provide soundproof wall - Close communication with the school and be cognisant of critical times in the school calendar
- Emergency Response planning - Insturmentation and monitoring of settlement - Additional Site investigation when necessary
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
May-20
Oct-17
Oct-17
Oct-17
Due Date By
Revision I 13 14
79 months
79 months
79 months
79 months
79 months
45 months
13 months
13 months
13 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 23/05/2017 15 16 17 Remarks
105
105
T309/ CNSS
T309/CNSS
005
004
N.A
NA
Road diversion work (Laguna park)
Traffic Diversion around Victoria School
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
- Congested road leading to Victoria school - Construction activities in front of Victoria school - Heavy machinery stationed along Siglap Link - Heavy traffic from new egress to Marine Parade Road - Pedestrians jaywalking -Inadequate signage and poor traffic control measures -Unsafe traffic layout -Failure to carryout trial trench for UG services -Failure to barricade work area and provide banksman to guide vehicular movement on site -Failure to equip with proper PPE
- Congested road leading to Laguna Park - Construction activities in front of Laguna Park - Heavy machinery stationed in Laguna Park - Heavy traffic from new egress to Marine Parade Road - Pedestrians jaywalking -Inadequate signage and poor traffic control measures -Unsafe traffic layout -Failure to carryout trial trench for UG services -Failure to barricade work area and provide banksman to guide vehicular movement on site -Failure to equip with proper PPE
Risk associated with Traffic Diversion -Unsafe traffic conditions, accident hot spot and vehicles crashing into site -Damaged to UG services -Noise and dust pollution
Risk associated with Traffic Diversion -Unsafe traffic conditions, accident hot spot and vehicles crashing into site -Damaged to UG services -Noise and dust pollution
5 Hazard Cause
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Collision of construction and public vehicles - Delays - Claims - Injury to public or construction personnel
- Collision of construction and public vehicles - Delays - Claims - Injury to public or construction personnel
Impact
Package 1 7
II
II
IV
S
F IV
C
C
Ri
Initial Risk Category Ri
8
- Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan '- Guard rail or rigid barrier to be setup and interlocked properly - designated path for access by pedestrians '- Code of Practise of Traffic Control and Work Zone -Approval of temporary traffic diversion layout by TM -Traffic layout and signage to follow TCP -Submit PSR (road) for clearance -Ensure good visibility of signage --Apply permit to dig prior to start work -Conduct RA/ SWP briefing
- Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan '- Guard rail or rigid barrier to be setup and interlocked properly - designated path for access by pedestrians '- Code of Practise of Traffic Control and Work Zone -Approval of temporary traffic diversion layout by TM -Traffic layout and signage to follow TCP -Submit PSR (road) for clearance -Ensure good visibility of signage --Apply permit to dig prior to start work -Conduct RA/ SWP briefing
Mitigation Measures
II
II
IV
S
F IV
C
C
Ri
Residual Risk Category Rr
11 Risk Owner
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly when necessary - Placement of cone or barrier during diversion without reduction in lane width -Desk top study of all utilities and carryout appropriate trial trench -Barricade work area and provide proper signage and warning to motorist and pedestrian. -Lane closure to avoid peak hours, applicable hours is 9:30-16:30 for daytime and 16:30-09:30 for night time closure -Flow chart indicating the flow of instruction enabling the lorry truck to enter the lane closure work area during soil removal or delivery of materials.
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly when necessary - Placement of cone or barrier during diversion without reduction in lane width -Desk top study of all utilities and carryout appropriate trial trench -Barricade work area and provide proper signage and warning to motorist and pedestrian. -Lane closure to avoid peak hours, applicable hours is 9:30-16:30 for daytime and 16:30-09:30 for night time closure -Flow chart indicating the flow of instruction enabling the lorry truck to enter the lane closure work area during soil removal or delivery of materials.
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
12
JHZH-PM
JHZH-PM
*Action Owner
Jul-17
Mar-23
Due Date By
Revision I 13 14
17 months
79 months
Risk Exposure Period
C
C
Target Risk Rating
Open
Open
Status
Date: 23/05/2017 15 16 17 Remarks
005
Future developments or Addition & Alteration works T309/CNSS 112 001 T309/CDSS/112/001
110
T309/CDSS/110/005
N.A
T309/CNSS
109
Existing Conditions T309/CNSS
004
T309/CDSS/106/003
T309/CDSS/110/004
106
T309/CNSS
003
T309/CDSS/106/002
Interface with Adjacent Contracts T309/CNSS 110 004
106
T309/CNSS
002
T309/CDSS/106/001
T309/CDSS/109/006
106
T309/CNSS
001
006
106
Existing Utilities T309/CNSS
Future developments or Addition & Alteration works
Excavation
Excavation
Excavation for Utility Diversion Works
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
Clashes between railway structures and future underground infrastructure works and/or future above ground developments
Interfacing with adjacent contracts
Incompatible Interfacing with adjacent contracts
Seawall obstruction
Limited Work Areas
Damage to utilities
Damage to utilities and disruption to services
Damage to submarine cable
Hazard
4
5 Hazard Cause
- Injury or fatalities of public and construction workers Unplanned excavation -Insufficient marking on site -Failure to conduct detection test
- Damage to the equipment used - Deep foundation and diaphragm wall are not constructed properly
- Unforeseen higher than designed surcharge
- Damage to utilities - Damage to road surfaces - Damage to property
-Proposals for future underground infrastructure - Incompatible construction techniques and developments in direct conflict with alignment and stations - Delay of works - Unaware of future infrastructure and developments proposals
Effect of T310 TBM tunnels on D-Walls subway - Excessive ground movement near Entrance C - Movement to adjacent structures
Unappropriate or non-workable connection - Excessive ground movement design at interface of bored tunnels and station - Movement to adjacent structures end walls - Groundwater drawdown - Waterproofing problem and associated repairs
Abandon seawall
- Work areas too restricted or efficient workings - Schedule delays - Work areas require significant temporary - Unsafe environment for construction works for their establishment personnel traffic congestion
-Diversion and support of utilities across excavation: - Water pipe - Power Grid cables - SP Telecom cables - Starhub cables
6 Impact
Disturbance to public
-Non coordinated inter-contract utility diversion, - Delay - Remote disruption -Unforeseen obstructions - Missing information from utilities agencies - Insufficient trial trenches
Insufficient information about cable location
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Package 1
F
V
V
V
V
IV
II
II
I
I
IV
III
I
V
III
III
I
S
III
V
7
C
C
C
C
D
C
C
C
C
Ri
Initial Risk Category Ri
8
- PE to ensure surcharge level to within acceptable loading
- Contractor to review Development Interface Report in detail - Coordination meetings between interfacing designers - Coordination between all parties (Client, Contractor, designers)
- Coordination meetings between interfacing contractors and designers to be managed by Contractors - Construction Interface report by Contractor - Coordination between all parties (Client, Contractor, Designers)
- Coordination meetings between interfacing contractors - Construction Interface report by Contractor - Coordination between all parties (Client, Contractor, Designers) - Specifying waterproofing details @ interface
- Additional trial trench and site investigation
- Buidling temporary decking for efficient road/land use - Detailed SHE procedure to enforce safety
- Ongoing co-ordination with relevant utility companies - Contractor's Method Statement - Approved NCE - Pre-qualify Contractors - Apply PTW daily before commencement of work -Thorough study of utilities drawings -Cable detections by qualified LCDW -Provide clear utilities marking on site -Provide A3 size drawing of utility plan -Apply permit to dig -Barricade work area while trenching -Contact relevant utility agency for any presence of unidentified utility -Always treat utility as `live’ if encountered -Only manual digging allowed for trial trench -Full time supervision during trial trench -No mechanical excavation within 3 meters from live utilities. - Only manual excavation allowed for trial trench digging. - Brief utilities plan in language understood by the workmen.
- Method Statements - Additional site investigation - Approved NCE
- To divert submarine cable away from the station box
Mitigation Measures
V
V
V
V
IV
II
II
I
I
IV
III
I
V
IV
III
I
S
IV
V
F
C
C
C
C
D
C
C
C
C
Ri
Residual Risk Category Rr
11
12
- No stockpiling
- Close coordination with related parties
- Instrumentation and monitoring - Close coordination
- Emergency Response planning e.g. grouting - Methods Statement - Close coordination
- Cross check at site - Laise with related authority about the information of seawall
- Efficient site utilization plan for each different working stage - Hire a professional road safety review learn and checking when necessary
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
-Utility cable detection and trial trench should be JHZH-PM carried out to identify the alignment -Diversion out of the structure footprint -Emergency Response planning including Contingency planning -Close communication with utilities agencies -Cable detection -Properly mark the location of utilities and briefing site staffs, workers and sub-contractors -If unclear with the finding of services after reaching the 2m limit, conduct further detection to determine the presence of any services below. -Dimensions and depth of Trial Trenches recorded by Project Survey Team for As Build information Photo records of trial trench including any utility discovered are recorded
JHZH-PM
JHZH-PM
-Design protective measures and temporary support scheme for utilities across excavation -Close communication with inter-contract and utilities agencies -Identify clear markers for utilities locations lines and brief staffs, workers and subcontractors -Cable detection -Emergency Response planning including Contingency planning
JHZH-PM
*Action Owner
JHZH-PM
Risk Owner
- Divert submarine cable away from the station JHZH-PM box and identify the clearly marker
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
May-20
May-20
May-20
May-20
Jan-17
Oct-17
Oct-17
Oct-17
Oct-17
Due Date By
Revision I 13 14
45 months
45 months
45 months
45 months
5 months
13 months
13 months
13 months
13 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 23/05/2017 15 16 17 Remarks
001
002
Ground Improvements T309/CNSS 118
118
121
T309/CNSS
Fire and Explosions T309/CNSS
001
009
Construction Methodology T309/CNSS 117
T309/CDSS/121/001
T309/CDSS/118/002
T309/CDSS/118/001
T309/CDSS/117/009
Construction works involving flammable or explosive materials
Construction works for ERSS or permanent walls
Jet grouting
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
5
Inappropriate jet grouting methods
-Overloading of lifting equipment -Failure to observe safe work procedures -- Instability of working platform. - Failure of loose material equipment/ rebar cages - Lack of communication - Inadequate supervision and control - Unplanned and poor control of crane movement - Substandard lift plan
Hazard Cause
Fire or explosion during construction
-Encounter flammable materials - Breakage of buried services - Ignition of methane from peat layers - Contaminant gas - War relics/unexploded ordnances - Heavy vehicles carrying flammable materials may be driven into the construction site
Excessive deflection of Insufficient ground improvement / treatment ERSS or permanent walls works
Ground improvement failure
●Crane collapse or failure ●Toppling of crane ●Crane hit surrounding structures, eg silo ●Hoisted material hit crane
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Injury or fatality of public or construction workers - Damage to existing structures and services
- Flooding of excavation - Collapse of temporary works and adjacent structures - Injury of public or construction personnel - Disruption of essential services - Delays - Claims
- Collapse of ground - Injury or fatality of construction workers and public - Waterproofing problems and associated repair - Damage to buildings - Delay of works - Movements of adjacent structures
-Injury to site staff -Delay to construction -Damage to property
Impact
Package 1
IV
F
V
V
V
7
I
II
II
II
S
C
C
C
C
Ri
Initial Risk Category Ri
8
- Provision of appropriate plant - additional site investigation and geophysics when necessary - Gather knowledge from people with relevant experience - Apply PTW (e.g hot works) daily before commencement of work - Safety Datasheet and Warning signs and Emergency contacts on display - Reporting to Safety and Security Department
- Contractor to produce robust Design - Method Statements to ensure safe working methods - Robust ERSS Design - instrumentation / monitoring e.g. LBs to monitor building movement, LGs for ground movement and IW or XYZ for ERSS.
- Contractor to produce robust design - Jet grouting trials - Specifying waterproofing details @ interface - Instrumentation / Monitoring e.g. LBs to monitor building movement, LGs for ground movement and IW or XYZ for ERSS. - Additional site investigation and geophysics
- Provide support plates for firm support - Apply PTW (e.g. lifting) daily before commencement of work - Full extension of outrigger prior to lifting - Approved Lifting Permit - No workers shall be allowed to stand below suspended loads - Lifting Supervisor to ensure correct method of usage - Approved lifting plan (e.g. full extension of outrigger, approved and proper use of slings) - Lifting points to be marked, identified and approved -Safety zone established -Tag line with coloured flag to be installed along hoarding to warn operator from crossing the line when turning during lifting -Tag line with coloured flag to be installed at the top of bentonite tank to warn crane operator and signal man to guide operator during crane movement. -Bentonite tanks near to Dwall will only be erected after the completion of Dwall. -To include min load radius in lift plan.
Mitigation Measures
V
V
V
V
F
I
II
II
II
S
C
C
C
C
Ri
Residual Risk Category Rr
11 Risk Owner
- Proper and independent flammable materials storage and management - Emergency Response Planning including Contingency planning e.g. quick evacuation route - Permit to carry hazardous material
- Provide efficient geometric design and the road level to mitigate flooding - Witness the instrumentation reading - Regular review and analyse instrumentation reading - Emergency Response planning include Contingency planning, inspection and monitoring
JHZH-PM
JHZH-PM
- High quality construction records and material JHZH-PM testing - Methods statement - Pre-qualify contractors - Regular review instrumentation reading of inclinometers and ground settlement markers in trial test and feedback main works - Emergency Response Planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts.
JHZH-PM - Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Reminder in tool box meeting - Lifting zone to be barricaded before works commence -Provide adequate hardstanding /firm working platform -Put in place the lifting permit system and display the relevant details on site. -Ensure no overloading of crane -Signaler to communicate with crane operator -Lift load by 300mm, hold for 3 seconds, all personnel 3m away -Approved lifting plan, reviewed by LE and approved by PM -Lifting operation supervised by lifting supervisor -Banksmen to guide crawler crane movement, ensuring no tracking over drain, trench or uneven ground. -Lifting points to be identified and approved -Low speed in lifting and lowering -Material shall be stacked safely and within stacking limit and load -Authorization of all machineries movement from point to point -Establish a permit to move system for heavy machineries -A lockout /tagout system during maintenance and breakdown period of mchineries -Maincon to control all machineries movement on site with daily discussion during coordination meeting -Setting up a security management plan that involved site security to be aware of the delivery of materials and ensuring no material delivery during lunch time and peak hour
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
12
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
Mar-23
Jan-18
Jul-17
May-20
Due Date By
Revision I 13 14
79 months
16 months
10 months
45 months
Risk Exposure Period
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Status
Date: 23/05/2017 15 16 17 Remarks
122
999
999
999
999
999
999
999
Flooding T309/CNSS
Other Hazards T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
007
006
005
004
003
002
001
002
N.A
T309/CDSS/999/006
T309/CDSS/999/005
T309/CDSS/999/004
T309/CDSS/999/003
T309/CDSS/999/002
T309/CDSS/999/001
T309/CDSS/122/001
4
5 Hazard Cause
Cleaning
Setting up of Noise Barrier
Traffic Diversion
6
Damage to construction works
-Occurrence of a natural disaster during construction - Flooding - Heavy rainfall causing significant ground water table rise
- Construction activities require frequent transport movements - Works at site with long working hours for 7 days a week
Use of high ultra water jet
Noise Barrier and foundation
-Pipe leakage and burst -Loose connection -Lose control of hose
-Construction works in close proximity to the public and existing housing -Excessive noise due to construction
Movement of heavy -Spoil removed to designated location remote vehicles causing disruption from site to traffic movement
F
- Injury to public or construction personnel
- Injury to public or construction personnel - Disruption of essential services - Negative PR - Delays - Claims
- Delay and accidents, - ECM issues, - Mosquito breeding, - Security problems
IV
II
III
III
III
V
IV
IV
I
V
- Flooding of excavation - Collapse of temporary works and adjacent structures - Injury or fatality of public or construction personnel - Disruption of essential services - Delays - Claims
II
III
I
S
II
IV
IV
V
7
C
D
C
D
C
C
C
C
C
Ri
Initial Risk Category Ri
IV
-Environmental pollution
Package 1 8
- Assign two trained hydro jetting operators. - Rotate shift every alternate hours - Provide safety warning signage to keep other works clear from work area - Provide safety access to washing bay
- Method Statements - additional site investigation - Provision of Noise barrier - Monitoring of Noise - Noise control plan - Engage community regularly and gather feedback
- Method Statements -Additional traffic management
- Method Statements - additional site supervision - ECM Plan
- Robust ERSS design including flood barriers when necessary - Temporary groundwater controls and pumps within excavation - Specifying water proofing details @ interface
- Design and approved traffic diversions - Minimise traffic around construction sites - Use of barrier and/or gate guards for exit/ entrances to site
- Design and approved traffic diversions - Clear and good signages - Minimise traffic around construction sites
- Contingency planning, e.g. additional noise barriers, inspection and monitoring - Method Statements to ensure safe working methods - Installation of noise barriers - Noise level monitoring - Engaging community for feedback '- Noise, dust control plan
- Method Statements - Additional site investigation -Confirmation with LTA on any specific flood protection measures required during construction
Mitigation Measures
V
V
IV
II
III
III
IV
I
V
IV
II
II
III
I
S
V
V
V
V
F
C
D
C
D
C
C
C
D
C
Ri
Residual Risk Category Rr
11 Risk Owner
JHZH-PM
12
JHZH-PM
JHZH-PM
- Assign safety supervisor when possible at work place to ensure operation is safe - Barricade work area to prevent unauthorized access and display warning signage.
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly -Designated haul routes -Contingency planning, inspection and monitoring - Placement of cone or barrier during diversion without reduction in lane width - Minimize loud noise activity during evening and weekends - Monitor noise meters at designated intervals - Contingency planning, inspection and monitoring
JHZH-PM
JHZH-PM - Install additional EC measures (e.g. silt fences, nets) when necessary '- Regular inspection of site by ECO at affected zones - Contingency planning, inspection and monitoring
- Close communication with related authority - Emergency Response planning including Contingency planning e.g. quick evacuation route - Provide efficient geometric design and the road level to mitigate flooding
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM - To provide traffic marshals to direct traffic when necessary - Clearly defined zones for accessible pathways and restricted areas - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Guard rail or rigid barrier to be setup and interlocked properly - Code of Practise of Traffic Control and Work Zone - Placement of cone or barrier during diversion without reduction in lane width
JHZH-PM - To provide traffic marshals to direct traffic when necessary - Clearly defined zones for accessible pathways and restricted areas - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Guard rail or rigid barrier to be setup and interlocked properly - Code of Practise of Traffic Control and Work Zone - Placement of cone or barrier during diversion without reduction in lane width
- Vibration control plan - Vibration monitoring
JHZH-PM - Provide efficient geometric design and the road level to mitigate flooding -Awareness of climatic conditions -Regular monitor of water level in Opera estate Canal -Emergency Response planning including Contingency planning
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
- Complaint from nearby occupants - Complaint from LTA - Working time may be reduced with delay to programme
-Traffic congestion due to minimum diversions, - Injury to public or construction personnel drivers seeking alternative routes - Damage to temporary or permanent works
Road vehicles entering construction site / excavations
-Traffic congestion - Unauthorized entry of personnel to site
-Construction works in close proximity to the public -Excessive noise due to construction -Excessive noise due to bored and barette pile testing
- Injury to public or construction personnel - Disruption of essential services - Negative PR - Delays - Claims
-Interrupted construction, -Delays, -Environmental pollution
Impact
Noise, dust and vibration
Flooding from the Opera -Damage the canal or foundation during Estate Canal at Siglap Link construction, -Extreme flooding event; -Tidal fluctuation -Structural problem of the canal
Hazard
Discharge into Canal from -Heavy rain construction - Insufficient control on site -Surface run off, construction materials Construction Works (bentonite, concrete, grout, near Drains and Canal maintenance/cleaning facilities)
Construction Works near Drains and Canal
Traffic Diversion
Construction Works near Residental area
Construction works near Opera East Canal
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Mar-23
Mar-20
Mar-23
Mar-20
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Due Date By
Revision I 13 14
79 months
45 months
79 months
45 months
79 months
79 months
79 months
79 months
79 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 23/05/2017 15 16 17 Remarks
999
999
999
999
999
999
999
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
Site set up T309/CNSS
013
21
012
011
010
009
008
NA
N,A
N.A
N.A
N.A
N.A
N.A
Setting up of Noise Barriers
Drain Works
Recahrge well work
Lifting with Excavator (Pick and Carry)
Traffic Diversion
Traffic Diversion
Removal of sludge
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
5
Noise Barrier structural failure
Flooding hazard in confined space
6
- Collapse of temporary works - Excessive movement / Collapse of adjacent structures - Injury or fatalities of public and construction workers
- Flooding of drain - Collapse of temporary works and adjacent structures - Injury of public or construction personnel - Disruption of essential services - Delays - Claims
-Damage of machinery -Injury of worker -Damage of materials
-Damage of machinery -Injury of worker -Damage of materials
- Traffic jams hindering construction vehicles - Bottlenecks hindering traffic speed - Crossed traffic and pedestrian circulation paths - injury to public and/or construction work
- Traffic jams hindering construction vehicles - Bottlenecks hindering traffic speed - Crossed traffic and pedestrian circulation paths - injury to public and/or construction work
'- Injury to public or construction personnel - Contaminate soil, groundwater and surface water
Impact
- Collapse of temporary works - Incorrect information on adjacent structures - Not identifying the behaviour and response of - Damage to own and public properties (Claims) - Injury or fatalities of public and construction the ground and adjacent structures workers
-Flawed design of temporary works - Inappropriate use / misinterpretation of design codes - Lack of understanding of design software and output - Temporary works design is incompatible with adjacent structures
Obstructed access out of drain
-Unplanned Drilling. - Insufficient marking on site. - Failure to conduct detection test.
-Damaged to :
Water pipe. Power grid cables. Telecom cables. High tension cables.
-Uneven ground - Unauthorised lifting - Improper rigging -Overloading -Inexperience operator
-Uneven ground - Unauthorised lifting - Improper rigging -Overloading -Inexperience operator
- Change to road condition due to delivering material to site
- Change to road condition due to construction work, poor line of sight - Changed traffic condition causes confusion to road users - Improper/ unclear signages - Improper/ unclear separation of pedestrians paths and work site ingress/ egress points - Pedestrians jaywalking
-Pipe leakage and burst -Loose connection
Hazard Cause
-“A’ frame topple - Injury to public - Fingers / hand caught in rotating parts
-Toppling of excavator - Falling of load/ material
Risk associated with Traffic Diversion
Risk associated with Traffic Diversion
Sludge spill
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Package 1 7
II
II
IV
II
II
II
II
II
IV
V
IV
IV
IV
IV
II
II
IV
S
F IV
C
C
C
B
B
B
C
C
C
Ri
Initial Risk Category Ri
8
- Perform further structural or geotechnical investigations e.g. coring, trial trenching - Apply PTW (e.g. welding) daily before commencement of work - Certified welder
- Sensitivity of design input parameters - Pre-qualify contractor - Apply PTW (e.g. welding) daily before commencement of work - Certified welder
- Contractor to produce robust Design - Method Statements to ensure safe working methods - Robust ERSS Design
-Thorough study of utilities drawings. - Cable detections by qualified LCDW - Provide clear utilities marking on site - Provide A3 size drawing of utility plan - Apply permit to dig and implement “checklist for working near utility” - Barricade work area while trenching
- Ensure work assess is planned. - Ensure adequate access for work mobilisation and public access. - Only competent lifting crew is allowed to involved in mobilisation. - PTW-Lifting approved prior unloading. - Provide proper exclusion zone to segregate work and public. - Provide warning signs.
●The excavator designed for pick and carry operations must have load chart stating clearly the limitattions for picks and carry operation ●Tag line shall be used during operation ● Ensure the route of travel is firm and level ●Lifting supervisor to ensure the load is firmly secured and tied ●Benchman to guide excavator during the pick and carry operation
- Design stages of traffic diversion to allow construction to be carried out section by section - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Safety barrier to be setup at designated storage zones - Proper signages display at prominent locations - Code of Practise of Traffic Control and Work Zone - designated path for access by pedestrians - Control unauthorized entry of personnel into loading/unloading zone during material delivery
- Design stages of traffic diversion to allow construction to be carried out section by section - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Guard rail or rigid barrier to be setup and interlocked properly Proper signages display at prominent locations - Code of Practise of Traffic Control and Work Zone
- Competent staff - Provide safety warning signage to keep other works clear from work area - Provide safety access to treatment plant - Permit for handling of sludge - Provide emergency contact no.
Mitigation Measures
II
II
V
II
II
II
II
II
V
V
V
V
V
V
II
II
V
V
S
F
C
C
C
C
C
C
C
C
C
Ri
Residual Risk Category Rr
11
JHZH-PM
Risk Owner
JHZH-PM
JHZH-PM
- Strengthening of noise barrier when necessary JHZH-PM - Additional site investigations and localized ground improvement when necessary - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts. - Approved Method Statement
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
12 *Action Owner
JHZH-PM - Engage experienced and competent consultant to perform the design - Engage experienced and competent contractor - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts. - Approved Method Statement
- Provide efficient geometric design and the road level to mitigate flooding - Emergency Response planning include Contingency planning, inspection and monitoring - Ensure workers are familiar with confined space ingress/egress in case of flooding and collapse of temporary works
-Contact relevant utility agency for any presence JHZH-PM of unidentified utility Always treat utility as `live’ if encountered Only manual digging allowed for trial trench Full time supervision during trial trench
- Provide blinker lights to alert night motorist and /or pedestrian. - Ensure footage is firm and level at all times. - Never drag load. Lift vertically.
-AE to examine the lifting capacity of excavator JHZH-PM and issued the certification for the lifting. -Pick and carry operation is guided in SS536 : 2008
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly - Placement of cone or barrier during diversion without reduction in lane width
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly - designated path for access by pedestrians - Placement of cone or barrier during diversion without reduction in lane width
- Contain and handle spillage (e.g. excavate spill site and treat with dry sand, temporary diking) immediately - Contact additional emergency services when necessary
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
Mar-23
Mar-23
Jun-17
May-23
May-23
Mar-23
Mar-23
Mar-23
May-20
Due Date By
Revision I 13 14
79 months
79 months
11 months
79 months
79 months
79 months
79 months
79 months
45 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 23/05/2017 15 16 17 Remarks
T309/CNSS
999
014
NA
4
MEWP topple
Hit by fallen object
Fall from height
Hazard
5
6
Old machinery and poor maintenance causing disturbance to nearby resident
Installation of sheet piles Noise pollution (foundation support for sound barrier)
Installation of sheet piles Accidental dislodgement of -Carelessness and inexperience operator. (foundation support for sheet pile during driving - Faulty vibro hammer sound barrier)
Structure failure of machinery
Installation of sheet Using of poor condition piles (foundation support for machinery sound barrier)
-Serious injury to worker and property. -Stop work causing delay
-Disturbance to neighbouring resident -Hearing injury to workers
-Low productivity Job delay and behind schedule -Cost implication
-Serious injury to worker and property. -Stop work causing delay
-Toppling of machinery resulting in damage to property. -Injury to surrounding people.
Installation of sheet piles Poor ground condition (foundation support for sound barrier)
-Damage to underground services -Disruption to stakeholders -Penalty charges by authority -Stop work order by authority -Delay to work schedule
Risk Register Package 1
-
IV
IV
IV
IV
IV
IV
7
F
I
II
II
I
I
II
II
S
B
C
C
B
B
C
C
Ri
Initial Risk Category Ri
8
I
-Additional sling tied to sheetpile and machinery as extra protection in case grabber gives way V -Ensure sheetpile is clamped tightly between the grabber jaws before hoisting up vertically for installation
II
I
I
II
II
II
V
V
V
V
F
S
C
C
C
C
C
C
C
Ri
Residual Risk Category Rr
-Installed sound barrier. -Used of silent piler. V -Refrain from working at night and weekend/PH
-Machine to be inspected and certified by AE. -Regular monthly maintenance of machineries
-Access to be laid with hardcore and compacted. -Steelplate to be laid on top of hardcore. -Movement of machinery must be guided by benchemen
-Work zone to be barricaded to prevent unauthorized entry -Used of tag line to control swaying of load - Employed skilled operator and experienced lifting team
-Carry out cable detection and trial trench along the path of sheet piles. V -Apply permit to dig prior to work start.
- Provision of Fall Protection Plan. - Establish PTW-Height system. - Provide proper access. - Provide adequate work platform. - Licensed MEWP operator. - Familiarisation briefing prior appointment.
Mitigation Measures
11 Risk Owner
Daily pre operation check on grabber by operator before start of work
Regular maintenance regime in place
LOTO system applied during maintenance period
-Ground preparation completed with the issuance of COS from PE -Ensure no overloading of machinery (Load kept at 75% of SWL
Apply for permit to move for machinery movement from point to point
Cable detection by LEW
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
-Enveloped MEWP work platform with scaffold JHZH-PM netting to contain material. Limit max. 2 person on MEWP. Max. weight 120kg. Firm and compacted ground for MEWP access. Provide adequate exclusion zone and signage. Provide banksman to ensure no authorised entry in to work zone.
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
-Damage to own and public properties (Claims) IV - Injury or fatalities of public and construction workers
Impact
-Serious injury to worker and property. -Stop work causing delay -Damage to machineries
Location of utilities not reflected in utility drawing
-Failure to provide fall protection provision - Failure to provide control - Poor footage - Over loading of MEWP
Hazard Cause
Installation of sheet Collision of machinery and piles Constraint of work area (foundation support for site people. sound barrier)
Installation of sheet piles Damage to utilities (foundation support for sound barrier)
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 12
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
44986
Due Date By
Revision I 13 14
79 months
79 months
79 months
79 months
79 months
79 months
79 months
Risk Exposure Period
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Status
Date: 23/05/2017 15 16 17 Remarks
999
999
999
999
T309/CNSS
Vector Management T309/CNSS
T309/CNSS
Mobilization T309/CNSS
018
017
016
015
NA
NA
NA
NA
Traffic Diversion
Workers working on site
Setting up of Hoarding
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
5 Hazard Cause
Risk associated with Traffic Diversion -Unsafe traffic conditions, accident hot spot and vehicles crashing into site -Damaged to UG services -Noise and dust pollution
Transmission of Dengue and Zika
Mosquito bites on construction/ public personnel
6
- Collapse of temporary works - Excessive movement / Collapse of adjacent structures - Injury or fatalities of public and construction workers
Impact
- Transfer (delivery and lifting) material, plant and manpower -Inadequate signage and poor traffic control measures -Unsafe traffic layout -Failure to carryout trial trench for UG services -Failure to barricade work area and provide banksman to guide vehicular movement on site -Failure to equip with proper PPE
- Mosquito breeding - Mosquito bites
- Mosquito breeding - Mosquito bites
- Traffic jam - Injury to public or construction personnel - Claims - Delays
- Injury or fatality of public or construction personnel - Claims - Delays
- Injury to public or construction personnel - Claims - Delays
- Collapse of temporary works - Incorrect information on adjacent structures - Not identifying the behaviour and response of - Damage to own and public properties (Claims) the ground and adjacent structures
Hoarding structural failure -Flawed design of temporary works - Inappropriate use / misinterpretation of design codes - Lack of understanding of design software and output - Temporary works design is incompatible with adjacent structures
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Package 1 7
IV
IV
IV
IV
IV
F
II
I
I
II
II
S
C
B
B
C
C
Ri
Initial Risk Category Ri
8
- Code of Practise of Traffic Control and Work Zone - Use of barrier and/or gate guards for exit/entrances to site -Approval of temporary traffic diversion layout by TM -Traffic layout and signage to follow TCP -Submit PSR (road) for clearance -Ensure good visibility of signage --Apply permit to dig prior to start work -Conduct RA/ SWP briefing -Desk top study of all utilities and carryout appropriate trial trench -Barricade work area and provide proper signage and warning to motorist and pedestrian. -Lane closure to avoid peak hours, applicable hours is 9:30-16:30 for daytime and 16:30-09:30 for night time closure
- Pest control '- Emergency Response planning - Vector control management - Additional supervision - Oiling in stagnant water and other respective areas - Provision of insect repellents to site staff
- Pest control - Emergency Response planning - Vector control Management - Additional supervision - Oiling in stagnant water and other respective areas - Provision of insect repellents to site staff
- Perform further structural or geotechnical investigations e.g. coring, trial trenching
- Sensitivity of design input parameters - Engage experienced and competent consultant to do the design - Engage experienced and competent contractor - Pre-qualify contractor
Mitigation Measures
IV
V
V
V
V
F
II
I
I
II
II
S
C
C
C
C
C
Ri
Residual Risk Category Rr
11 Risk Owner
JHZH-PM
JHZH-PM
JHZH-PM - Properly traffic control and signages with qualified traffic marshal - Clearly defined zones for accessible pathways and restricted areas - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Emergency Response planning including Contingency planning, inspection and monitoring - Lifting zone to be barricaded before works commence - Placement of cone or barrier during diversion without reduction in lane width -Flow chart indicating the flow of instruction enabling the lorry truck to enter the lane closure work area during soil removal or delivery of materials.
- Regular inspection of site to identify and eliminate breeding sites - Misting
- Regular inspection of site to identify and eliminate breeding sites - Misting
JHZH-PM - Strengthening of hoarding when necessary - Additional site investigations and localized ground improvement when necessary - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts.
JHZH-PM - Engage experienced and competent consultant to perform the design - Engage experienced and competent contractor - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts.
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
12
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Due Date By
Revision I 13 14
79 months
79 months
79 months
79 months
79 months
Risk Exposure Period
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Status
Date: 23/05/2017 15 16 17 Remarks
999
T309/CNSS
020
019
N.A
NA
Lifting with crane
Lifting with crane
4
5
- Breakage of lifting chain - Breakage of lifting sling - Failure of brake motor/gear - Failure of sling/chain buckles and hooks - Overloading of carried loads over limited of design capacity - Unauthorized modification of lifting points
Hazard Cause
- Improper securing of material/ equipment - Overloading of material/ equipment - Slight tilt in crane '- Sudden movement of crane boom
Sharp edge material being - Site personnel cut by sharp material during lifted/ lowered/ handled handling
Failing of loose material/ equipment
Crane topple / Hoisted load - Poor crane footage hit crane - Incompetent lifting team - Poor lift plan - Congested work environment
Failure of lifting mechanism
Hazard
Note * - Action Owner will be reassigned from PM to Engineer-in-Charge when respective Engineer-in Charge is established
999
T309/CNSS
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running Code number
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
7
- Injury and fatality to construction personnel - Delays - Claims
I
II
IV
IV
I
IV
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
I
S
IV
F
C
B
B
B
Ri
Initial Risk Category Ri
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
Impact
Package 1 8
- Store all sharp material into material cages when possible - Pack/ organize sharp material - Use of PPE (e.g appropriate safety gloves, long sleeves, helmet and safety boots and glasses)
- Approved PTW (e.g lifting) daily before commencement of work - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be marked, identified and approved - Approved Lifting plan - Material shall be stacked safely and within stacking limit and load
- Design and COS crane access - No Overloading at all times - Proper mainyenance of crane - Only competent lifting team is allowed - Implemet Permit to lift - Include both Max. and Min load radius - Do not conduct lifting in congested work environment. - Provide exclusion zone and Provide warning signs. - Provide sufficient tag lines
- Apply PTW (e.g. lifting) daily before commencement of work - Monthly inspection of lifting mechanisms - Lifting Supervisor to ensure correct method of usage - Colour coding all lifting mechanisms for validity and serviceability levels - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Lifting points to be identified and approved - Approved Lifting Plan
Mitigation Measures
I
II
IV
I
V
V
I
S
V
F
C
C
C
C
Ri
Residual Risk Category Rr
11
12
JHZH-PM
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- '- Identify sharp material and dipose (e.g. nails, JHZH-PM broken glasses) - Wrap sharp edges when possible
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM
Risk Owner
JHZH-PM
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting - Guidance by traffic controller - Familization course for operator
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
Future Actions
PREPARED BY LEE/ HUA KWAN JONG 9 10
Diaphragm wall, bored piles, ground improvement and enabling works TOMMY
Risk Register
Oct-17
Mar-23
Oct-17
Mar-23
Due Date By
Revision I 13 14
13 months
79 months
13 months
79 months
Risk Exposure Period
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Status
Date: 23/05/2017 15 16 17 Remarks
18th May 2017
3 Months Programme Look ahead Risk and Mitigation
Construction of Siglap Station Thomson‐East Coast Line
Contract T309
2) To identify the major risk hazards and elaborate the mitigation measures in this workshop
1) To identify the major works activities for the next three months, Jun 2017 – Aug 2017
Objectives of this workshop:
Noise Barrier installation Slab over drain works Utility Corridor Installation Road Works Traffic diversion 1C Sheet pile installation
Entrance C
Guide Wall & D‐Wall construction Test bore pile
3
Recharge Well Installation
Guide Wall & D‐Wall construction
Cooling Tower / Main Station
Guide Wall & D‐Wall construction Noise Panel installation near to Laguna Park
Demolition and back filling of old drain Guide Wall Mobilisation of D‐wall rig D‐Wall construction
Entrance B
Entrance D
Entrance A
Upcoming Works Jun 17 – Aug 17
Traffic diversion 1C
Sheet Piling work
Slab over drain Construction
Noise Barrier installation
Entrance C Hoarding Installation
Works at Ent. C
Traffic Diversion
Activity
Poor planning
Hazard Cause
Noise
Complaints from stakeholder
Traffic jam / congestion
Lack of coordination
Workers hit by Lack of traffic communication
Motorist confusion
Public confusion
Risk
Risk mitigation
Traffic diversion – 1C
Apply for lane closure Close lane in accordance with COP Traffic control Put up sufficient advance warning signage
• •
parties on personnel on process of diversion.
Briefing session to be conducted with all relevant
parties
Organise “work session” to brief all relevant
LTA
Coordinate closely with relevant authority e.g.
•
•
•
•
Sufficient and clear notification signage to
• motorist – e.g. VMS
Clear and advance notification to all stake holders
•
Mitigation Measure
Hari (ES Engineer) Jay Cel (JV Site Engineer)
•
Jay Cel (JV Site Engineer)
Jay Cel (JV Site Engineer)
Jay Cel (JV Site Engineer)
•
•
•
•
Jay Cel (JV Site Engineer)
Jay Cel (JV Site Engineer)
• •
Erin (JV SPRO)
•
Action Owner
Traffic Diversion
Activity
Noise
Complaints from stakeholder
Traffic jam / congestion
Lack of coordination •
•
Inform NEA about late traffic diversion work
•
Workers hit by Lack of communication traffic
Carry out traffic diversion off peak hours.
•
Poor planning
Motorist confusion
batons
Traffic controllers to equipped with light
Ensure workers put on reflective vest.
– Potential noise issue
start
Brief TCP to all relevant person prior work
Mitigation Measure •
Hazard Cause
Public confusion
Hazard
Risk mitigation
Traffic diversion – 1C
•
Hari (ES Engineer)
Mike (JV Safety)
Arron (JV ECO)
• •
Jay Cel (JV Site Engineer)
Jay Cel (JV Site Engineer)
•
•
Action Owner
Notification via eRMS with the help of LTA project team
Mitigation measures: Communication ‐ Authority
Traffic diversion – 1C
Notification to relevant authority
LTA communication with Main contractors
Mitigation measures: Communication – LTA / Main Contractors /Sub contractors
Traffic diversion – 1C
Contractors communication
Main contractors to stake holders
Mitigation measure: Communication – Stakeholders/residents
Traffic diversion – 1C
Briefing to stakeholders
Presentation to Laguna Park Residents
Mitigation measure: Communication – Laguna Park resident
Traffic diversion – 1C
Information will change accordingly
Mitigation measure: Communication – Motorist
Traffic diversion – 1C
Alert motorist using traffic marshaller
Mitigation measure: TCP ‐ Traffic Closure
Traffic diversion – 1C
Deployment of APO at strategic location for traffic controls
Mitigation measure: Traffic Closures ‐ Auxiliary Police Officers
Traffic diversion – 1C
Guide Wall & D‐Wall construction Recharge Well Installation
Cooling Tower
Cooling Tower Works
“A’ frame topple
Recharge well work
Fingers / hand caught in rotating parts
Injury to public
Risk
Activity
Incompetent crew
Poor ground condition
Poor footage
Poor mobilization planning
Hazard Cause
4) Recharge Well work – Risk mitigation
• •
• •
• •
•
‐ ‐
‐ ‐
‐ ‐
‐
JV Lift Engineer Sub‐con lifting supervisor
Sub‐con supervisor Sub‐con supervisor
Sub‐con supervisor Sub‐con supervisor
Sub‐con Engineer
JV Superintendent JV Supervisor
‐ ‐
• • Ensure work assess is planned. Ensure adequate access for work mobilisation and public access. Only competent lifting crew is allowed to involved in mobilisation. PTW‐Lifting approved prior unloading. Provide proper exclusion zone to segregate work and public. Provide warning signs. Provide blinker lights to alert night motorist and /or pedestrian. Ensure footage is firm and level at all times. Never drag load. Lift vertically.
Action Owner
Mitigation Measure
4) Recharge Well work – Risk mitigation
End
12th July 2017
3 Months Programme Look ahead Risk and Mitigation
Construction of Siglap Station Thomson‐East Coast Line
Contract T309
2) To identify the major risk hazards and elaborate the mitigation measures in this workshop
1) To identify the major works activities for the next three months, Jul 2017 – Sep 2017
Objectives of this workshop:
Guide Wall & D‐Wall construction
Entrance C
Guide Wall & D‐Wall construction
3
Cooling Tower D‐Wall construction Recharge Well Installation Excavation
Noise Panel installation near to Laguna Park Hoarding Shifting Installation Guide Wall & D‐Wall construction
Guide Wall & D‐Wall construction
Entrance B
Entrance D
Entrance A
Upcoming Works Jul 17 – Sep 17
Guide Wall & D‐Wall construction
Entrance A
Works at Ent. A
D‐ walling work
1) Guide wall / D‐ wall excavation
Works at Ent. A
Guide wall in progress
Damaged to :
Excavation works
Insufficient marking on site.
Unplanned Drilling.
Hazard Cause
Permit to work system
Water pipe. Power grid cables.
Risk
Activity
•
Trial Trench
LCDW Carry out cable detection
‐
Soheal
TBM briefing
Tan WC (JV UE) LCDW Tan WC (JV UE) Thiha Soheal
‐ ‐ ‐ ‐ ‐
• • • • • Thorough study of utilities drawings Cable detections by qualified LCDW Provide clear utilities marking on site Provide A3 size drawing of utility plan Apply permit to dig and implement “checklist for working near utility” Barricade work area while trenching
Action Owner
Mitigation Measure
1) Guide wall / D‐ wall excavation – Risk mitigation
Works at Ent. A
Damaged to :
Excavation Works
Telecom cables. High tension cables.
Hazard
Activity
•
•
•
• • • • ‐ ‐ ‐ ‐ ‐
‐ ‐ ‐ ‐
Tan WC Soheal Soheal Soheal Jeremia / Peter
Soheal Soheal Soheal Jeremia (HSL) / Peter (JV)
Tan WC (JV UE)
‐
• Contact relevant utility agency for any presence of unidentified utility Always treat utility as `live’ if encountered Only manual digging allowed for trial trench Full time supervision during trial trench ‐No mechanical digging within 3m from identified utilities. ‐Brief utility plan in language understood by the workmen. ‐Provide watch man to watchout for utilities during excavation ‐Senior staff to be involved in site inspection prior to PTW approval.
Action Owner
Mitigation Measure
Mark out detected cable clearly on site. Drill only when identified cables are exposed. Utilities marker are only allowed to shift or remove unless approved by JV UE.
Only manual excavation is allowed for trial trench works
Failure to conduct detection test.
Hazard Cause
1) Guide wall / D‐ wall excavation – Risk mitigation
Works at Ent. A
D‐wall work (Lifting Work)
Activity
Crane hit surrounding structures, e.g. silo
Crane Toppling
Risk
•Load hit onto crane
•Instability of working platform
•Failure of loose material equipment/ rebar cages
Hazard Cause
1) Guide wall / D‐ wall excavation – Risk mitigation
Works at Ent. A
‐
Sufi
Omar
‐ • Look into min load radius when hoisting bulky items e.g. rebar cage. •Only R/S can give signal. Trade supervisor cannot involved in lifting work.
Junaet
Sufi
Bok Soon Sufi
‐
‐
‐ ‐
•Signaler to communicate with crane operator
•Safety zone established
•Material shall be stacked safely and within stacking limit and load
•Low speed in lifting and lowering
Gajan
Killi
‐
•Approved lifting plan, reviewed by LE and approved by PM
‐
Sufi
‐
•Lift load by 300mm, stabilized for 3 seconds.
•Lifting points to be identified and approved
Action Owner
Mitigation Measure
Side View
Ground
“L” shaped D‐wall panel
Plan View
6.5m
9
1) Guide wall / D‐ wall excavation – Risk mitigation (“L” Shaped panel
Works at Ent. A
Normal D‐wall panel
Risk
Tandem lift Crane collapse work (“L” shape panel) Workers hit by fallen objects from D –wall
Activity
• •
•
•
Loose • material on D‐ • wall panel •
10
Designed and COS crane access. Approved Permit to Lift. Approved lift plan. Valid and adequate lift gears for taking weight of D‐wall panel. Provide adequate tag lines. Identify proper hooking point for turning D‐ wall. Only one LS to control tandem lift. Standing supervision by LE. Ensure lifting activities not carried out in congested work area. Ensure no loose material on D wall panel prior lifting. Provide exclusion zone and warning sign to prevent unauthorised entry. Tandem lift to be carried out during day shift. No obstruction of LS/CO view at all times.
Mitigation Measure
Unplanned lift • • • Over loading • due to poor coordination • between LS •
Hazard Cause
1) Guide wall / D‐ wall excavation – Risk mitigation
Works at Ent. A
‐ ‐
‐
‐
JV Superintendent – Peter HSL LS
HSL LS Ahmed Sufi
HSL LS Ahmed Sufi
JV Lift Engineer Killi JV Lift Engineer killi JV Superintendent – Peter
HSL LS Ahmed Sufi JV Engineer Desi
‐ ‐ ‐ ‐ ‐
LV lift Engineer Killi JV Project Manager ‐ Frank JV Project Manager ‐ Frank HSL LS Ahmed Sufi
‐ ‐ ‐ ‐
Action Owner
Hand finger injuries / Amputation
Stitching D‐wall (“L” shape panel)
Workers fall into d‐wall trench
Risk
Activity
‐
‐ ‐
11
Designed stopper for resting D wall cage All personnel to cleared at least 3 meters away during lowering of stitched D‐wall. Do not start stitching rebar cage until rebar cage is fully rested on stopper. Always keep hand away from line of fire. Provide proper barricades and warning sign around D—wall trench.
Mitigation Measure
‐ D‐wall stiches ‐ tear due to poor coordinated lift
Uncontrolled movement / poor coordinated lift.
Hazard Cause
1) Guide wall / D‐ wall excavation – Risk mitigation
Works at Ent. A
‐ ‐
‐
‐ ‐
HSL Supervisor – Soheal HSL Supervisor‐ Soheal
HSL Supervisor – Soheal
JV Engineer – Desi HSL Supervisor Soheal
Action Owner
D‐wall work (Grabbing Work)
Activity
Utility damage
Grabber hit surrounding structures, e.g. silo
•Instability of working platform
Grabber Toppling
•Inadequate supervision and control
•Lack of communication
•Failure of loose material equipment/ rebar cages
Hazard Cause
Risk
1) Guide wall / D‐ wall excavation – Risk mitigation
Works at Ent. A
•Banksmen to guide crawler crane movement, ensuring no tracking over drain, trench or uneven ground.
•Lifting operation supervised by lifting supervisor
•Approved lifting plan, reviewed by LE and approved by PM
•Signaler to communicate with crane operator
‐
‐
‐
Junaet
Sufi
Frank
Soheal
Soheal
‐
•Put in place the excavation permit system and display the relevant details on site.
‐
Peter
‐
•Provide adequate hardstanding /firm working platform
•Ensure no overloading of grabber
Action Owner
Mitigation Measure
Provide barricade around grabbing work
1) Guide wall / D‐ wall excavation – Risk mitigation
Works at Ent. A
Heavy machine on steel plate
PTW –lifting system is established
Approved Lift Plan
1) Guide wall / D‐ wall excavation – Risk mitigation
Works at Ent. A
Lifting supervisor checking the checklist of operator
Low speed in lifting and lowering
Lifting points to be identified and approved
Approved lifting plan
Lift load by 300mm, hold for 3 seconds
Provide Valid Fire extinguisher
1) Guide wall / D‐ wall excavation – Risk mitigation
Works at Ent. A
Safety zone established
Material shall be stacked safely and within stacking limit and load
Heavy machines mobilization process guided by TC, supervised by engineer, supervisors and safety personnel
1) Guide wall / D‐ wall excavation – Risk mitigation
Works at Ent. A
Approved lifting plan for all lifting on site
Pre‐start briefing in language understood by workmen prior lifting work.
1) Guide wall / D‐ wall excavation – Risk mitigation
Works at Ent. A
LM Machine not up to expectation will tagged “Not Safe for Use”
1) Guide wall / D‐ wall excavation – Risk mitigation
Works at Ent. A
Weekly boom down inspection with mechanics
Guide Wall & D‐Wall construction
Entrance B
Works at Ent. B
Guide wall and D‐wall construction work at Ent. B
Works at Ent. B
Guide Wall & D‐Wall construction
Entrance C
Works at Ent. C
Noise Panel installation near to Laguna Park
Guide Wall & D‐Wall construction
Hoarding Shifting Installation
Entrance D
Works at Ent. D
Works at Ent. D
D‐ walling at Entrance D
Guide Wall & D‐Wall construction Recharge Well Installation Excavation Work
Cooling Tower
Cooling Tower Works
Cooling Tower Works
Area of excavation
Excavation work
Activity
Fall into Excavation
Excavation Collapse
Risk
•
Incompetent crew
Poor ground condition
•
• •
• •
‐
‐ ‐
‐ ‐
‐ ‐
‐
Gajan
Killi Sufi
Soheal Soheal
Soheal Soheal
Thiha
Peter Thomas
‐ ‐
• • Ensure work assess is planned. Ensure adequate access for work mobilisation and public access. Only competent excavation crew is allowed to involved. PTW‐Excavation approved prior activity. Provide proper exclusion zone to segregate man and machines. Provide warning signs. Provide blinker lights to excavator and proper lighting particularly for night work. Ensure footage is firm and level at all times. Provide proper design and COS for shoring or sloping. No stock pipe of spoil at site. To cover with canvas in case of
Action Owner
Mitigation Measure
• Poor Shoring / • Sloping
Poor Planning
Hazard Cause
3) Excavation work (Cooling Tower) – Risk mitigation
Recharge well work
Activity
Fingers / hand caught in rotating parts
Injury to public
“A’ frame topple
Risk
Incompetent crew
Poor ground condition
Poor footage
Poor mobilization planning
Hazard Cause
3) Recharge Well work – Risk mitigation
• •
• •
• •
•
‐ ‐
‐ ‐
‐ ‐
‐
Killi Sufi
Soheal Soheal
Soheal Soheal
Thiha
Peter Thomas
‐ ‐
• • Ensure work assess is planned. Ensure adequate access for work mobilisation and public access. Only competent lifting crew is allowed to involved in mobilisation. PTW‐Lifting approved prior unloading. Provide proper exclusion zone to segregate work and public. Provide warning signs. Provide blinker lights to alert night motorist and /or pedestrian. Ensure footage is firm and level at all times. Never drag load. Lift vertically.
Action Owner
Mitigation Measure
• Noise ‐ Noise monitoring of activities throughout operations
• Vibration ‐ 24/7 monitoring of vibration/ground movements
• Dust ‐ Spraying of water as a dust suppression activity ‐ Use of erosion control blankets
Examples
Other Mitigation Measures
End
Minutes Title: Monthly Risk Register Workshop No 6 Date:12 Jul 2017 Time: 2.00pm--3.30pm Held at: T306 Meeting Room
Chaired by: Jong Hua Kwan/ Tommy Lee Minuted by: Tommy Lee Distribution date: 17 Jul 17
Attendees list See attached
Apologies list
Page 1 of 3
Minutes ITEM
MATTERS DISCUSSED
1.0
Introduction
ACTION
Risk Workshop will be on Guide Wall/ D-wall excavation, L-shape panel lifting, excavation works was submitted.
Info
The complete flow of the process will be demonstrated via a short slide presentation The project superintendent will provide the necessary information required to mitigate risks on the above.
2.0
Slide presentation on 3 monthly look ahead - Jul - Sep 17
Peter/ Jong
2.1
DD asked in relation to the incident where the LV cable was hit, if trial trench was carried out. JHZH replied that for all future trial trench, JHZH will co-sign on the trial digging and excavation permit.
Note
2.2
DD informed to include positive identification of utilities under utilities risk in risk register.
JHZH
2.3
2.4
T309P informed to include ramp specification for loading/unloading of heavy machinery. JHZH will amend the Safety Plan to include this information.
DD highlighted the importance of using several languages in the workforce and commended JHZH on the good practise.
JHZH
Note
2.5
T309P asked about the sequence of the two crane lifting of the L-shape D-wall panel. T309P had shared the experience of the tandem lift for T308 with JHZH. DD suggested to have a working session on this discussion.
JHZH
2.6
DD commended on the good practise of steel plate placement within site. However, maintenance of the steel plate level and checking out the compactness of the ground are important. On regular basis, JHZH will top up the ground with mill waste.
JHZH
2.7
JHZH
DD/T309P informed JHZH to maintain the risk register and treat it as a live document and constantly update it. 2.8
T309P informed that the action owner shall be specific personnel to be included in the risk register.
2.9
JHZH
JHZH
Page 2 of 3
Minutes ITEM
MATTERS DISCUSSED
ACTION
2.10
T309P informed that to include sub-con mechanic and supplier mechanic in performing equipment functionality when the need arises.
JHZH
2.11
T309P asked to highlight the closed and new risks for the next monthly risk meeting.
JHZH
DD asked for programme risk to be included separately. T309P asked for instrumentation and monitoring risk to be included in subsequent risk register.
3.0
Any Other Matters: The next workshop topic will be proposed accordingly.
4.0
INFO
Next Workshop The next monthly workshop will be discussed with T309P for a proposed date
Page 3 of 3
All / Info
T309/CNSS
T309/CNSS
100
100
ERSS for Temporary Work
008
007
T309/CDSS/100/008
T309/CDSS/100/007
Trenching
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
Instability of temporary works (trenches)
● Differential settlement between station ERSS ● Failure of loose material, equipment/ rebar cage ● Instability of working platform
Hazard
4
5 Hazard Cause
ERSS wall construction within F1 soil layer - F1 soil layer collapse - Trench stability
- Not identifying the behaviour and response of the ground and adjacent structures
Flawed design of temporary works - Inappropriate use / misinterpretation of design codes - Lack of understanding of design software and output - Incorrect information on adjacent structures - Temporary works design is incompatible with adjacent structures
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Doc no: T309-JHZH-RAR-PWD-RIS-0001
6
- Collapse of temporary works - Excessive movement/Collapse of adjacent structures - Injury or fatalities of public and Construction workers
- Collapse of temporary works - Collapse / damage of adjacent structures - damage of permanent works - Injury or fatality of construction workers or public
Impact
Risk Classes A 0 B 23 C 59 D 7 89
Package 1
V
V
V
F
7
I
I
I
S
C
C
C
Ri
Initial Risk Category Ri
8
- Contractor to produce robust design - Appropriate design sensitivity - Specify minimum penetration of panels - Additional site investigation - Pre-qualify contractors - Emergency Response planning - Provide temporary strut with PE endorsement
- Review levels to be developed - Regular review of Instrumentation / monitoring e.g. LBs to monitor building movement, LGs for ground movement and IW or XYZ for ERSS. - Approved Permit to lift and lifting plan - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be identified, marked and approved
- Contractor to produce robust design - Approved Permit to lift and lifting plan - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be identified, marked and approved
Mitigation Measures
I
I
V
V
I
S
V
F
C
C
C
Ri
Residual Risk Category Rr
11
12
JHZH-PM - Regular review instrumentation reading - Perform probing and SI (SPT) at regular intervals - Perform Ground Improvements when necessary - Joint inspection between JHZHJV and QPS for every Dwall 1) Mild case (to read; less than 10% of total panel excavated volume) – Create an earth bund wall surrounding the affected panel, fill up the bund wall pool with bentonite to increase the bentonite head level. 2) Moderate case (to read; more than 10% of total panel excavated volume, without any visual ground/ platform depression) – Move the grabber and other unnecessary heavy equipment at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. 3) On a case by case basis for a severe case (to read; more than 10% of total panel excavated volume, with obvious visual ground/ platform depression) – Move all machinery away except excavator at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. After 24 hours of backfilling, conduct light cement grout beneath the depressed platform.
JHZH-PM
JHZH-PM
- Steel plate to ensure uniform loading of crane JHZH-PM weight and outrigger - Use of level indicator and inclinometer - Additional site investigation when necessary - Lifting zone to be barricaded before works commence 1) Mild case (to read; less than 10% of total panel excavated volume) – Create an earth bund wall surrounding the affected panel, fill up the bund wall pool with bentonite to increase the bentonite head level. 2) Moderate case (to read; more than 10% of total panel excavated volume, without any visual ground/ platform depression) – Move the grabber and other unnecessary heavy equipment at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. 3) On a case by case basis for a severe case (to read; more than 10% of total panel excavated volume, with obvious visual ground/ platform depression) – Move all machinery away except excavator at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. After 24 hours of backfilling, conduct light cement grout beneath the depressed platform.
*Action Owner
JHZH-PM
Risk Owner
- Steel plate to ensure uniform loading of crane JHZH-PM weight and outrigger - Use of level indicator and inclinometer - Additional site investigation when necessary - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts. - Lifting zone to be barricaded before works commence - Lift load by 300mm, hold for 3 seconds, all personnel 3m away Approved lifting plan, reviewed by LE and approved by PM - Lifting points to be identified and approved - Low speed in lifting and lowering - Material shall be stacked safely and within stacking limit and load - Safety zone established - Signaler to communicate with crane operator
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
Summary of Residual Risk Classes A 0 B 0 C 74 D 15 89
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
The Risk Register is a "live document" and it will be the responsibility of all parties involved in the design, construction and commissioning of the T309 Initial Project and to ensure that all reasonable means and measures are put in place for the effective management of all the safety risks.to continue to identify new risks that arises.
e
Apr-17
Apr-17
Apr-17
Due Date By
Revision J 13 14
7 months
7 months
7 months
Risk Exposure Period
C
C
C
Target Risk Rating
Open
Open
Open
Status
Date: 11/08/2017 15 16
17 Remarks
011
012
100
100
T309/CNSS
T309/CNSS
T309/CDSS/100/012
T309/CDSS/100/011
T309/CDSS/100/010
010
100
T309/CNSS
T309/CDSS/100/009
009
100
T309/CNSS
Construction of ERSS for Utility Diversion
Construction of ERSS for Drain Diversion
Construction of ERSS
Construction of ERSS
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
Instability of temporary works (Utility Diversion ERSS)
Instability of temporary works (Drain Diversion ERSS)
Excessive ground movement of adjacent structures and utilities
Instability of temporary works (ERSS failure)
Hazard
4
5 Hazard Cause
6 Impact
Structural damage/deflection of existing structures - Damage to utilities - Traffic accidents with associated injuries - injuries to public or construction workers associated with ramp distress - Damage to road surfaces - Wall toe movement
- Damage to utilities - Damage to road surfaces
-Higher than expected lateral deflection of ERSS wall during excavations - Unforeseen ground conditions - Inappropriate removal of struts - Over-excavation - Excavation for the utilities laying/trench
- Unforeseen higher than designed surcharge
- Damage to utilities - Damage to road surfaces
- Unforeseen higher than designed surcharge
IV
IV
III
III
III
III
IV
- Injuries to public or construction workers associated with ramp distress - Traffic accidents with associated injuries - Structure Integrity of sheet piles.
- Inappropriate removal of struts - Over-excavation - Excavation for the drain and damage ERSS - Sheet pile obstructed and not able to pile into required depth. -Poor quality weld and design of sheet pile bracing.
IV
III
III
III
IV
IV
IV
I
I
V
V
I
I
S
V
V
F
7
C
C
C
C
C
C
C
C
C
C
C
Ri
Initial Risk Category Ri
- Structural damage/deflection of existing structures - Damage to utilities - Injuries to public or construction workers associated with ramp distress - Damage to road surfaces - Wall toe movement
Structural damage/deflection of existing structures - damage to utilities - Traffic accidents with associated injuries - injuries to public or construction workers associated with ramp distress - damage to road surfaces - Wall toe movement
Package 1
- PE to ensure surcharge level to within acceptable loading
- Contractor to produce robust design - Method Statements to ensure safe working methods - Monitoring on site - Gather knowledge from people with relevant experience - Visual inspection
- PE to ensure surcharge level to within acceptable loading
- Method Statements to ensure safe working methods -Follow the PTW (e.g excavate) daily during work - Review design of sheet pile and provide COS. - Only certified and appointed welders are allowed to weld. - Method statement to ensure proper bracing is provided.
- Contractor to produce robust design - Method Statements to ensure safe working methods - Gather knowledge from people with relevant experience
- PE to ensure surcharge level to within acceptable loading
- Contractor to produce robust design - Method Statements to ensure safe working methods -Regular review instrumentation reading - Apply PTW (e.g. excavate) daily before commencement of work
- Calculate amount of bentonite level required
- Robust Contractor's ERSS system - Pre-qualify contractors
- Contractor to produce robust design - Appropriate design sensitivity
- Contractor’s Method Statements - Apply PTW (e.g. excavate) daily before commencement of work '- Emergency Response Planning including Contingency planning e.g. grouting of gaps - Additional site investigation
Mitigation Measures
8
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
-Higher than expected lateral deflection of ERSS wall during excavations - Unforeseen ground conditions
- Unforeseen higher than designed surcharge
Higher than expected lateral deflection of ERSS wall during excavations - Unforeseen ground conditions - Inappropriate removal of struts - Over-excavation - Excavation of cut and cover tunnel
- Low bentonite level
Inadequate structural detail connection between - Collapse of temporary works strut, waler to ERSS walls / shafts / excavations - Excessive movement/Collapse of adjacent structures - Injury or fatalities of public and Construction workers - Contractor's ERSS design - Workmanship
- Groundwater drawdown
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
V
V
III
III
III
III
V
V
III
III
III
I
I
V
IV
IV
V
V
I
I
V
V
S
F
D
D
D
D
D
C
C
C
C
C
C
Ri
Residual Risk Category Rr
11
- No stockpiling
JHZH-PM
-Provide ground improvements when necessary JHZH-PM - Requirements to record penetration into competent stratum on installation -High quality site records -Bearing capacity checks for construction equipment - Installation of additional recharge wells & pressure relief wells as contingencies.
- No stockpiling
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM - instrumentation/monitoring to monitor strut loads. - Daily physical inspection of strutting system
JHZH-PM
JHZH-PM
JHZH-PM -Statutory requirement for QP(Sup) to be responsible for supervision of temporary works. -Emergency Response planning including Contingency planning
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
-Normal/ established procedures for staging the JHZH-PM works to protect adjacent utilities -Permit to remove strut system followed to prevent inappropriate removal of struts -Emergency Response planning including Contingency Planning
- No stockpiling
12 *Action Owner
JHZH-PM
JHZH-PM
Risk Owner
- Control of excavation opening to pouring time JHZH-PM
- High quality construction records - Ensure trench stability - Emergency Response planning
- instrumentation/monitoring to monitor strut loads. - Daily physical inspection of strutting system
-Emergency Response planning including Contingency planning -Instrumentation/monitoring to monitor strut loads. - Instrumentation/ real time monitoring - Perform probing and SI (SPT) at regular intervals - Sufficient vibration monitors with appropriate trigger levels to be installed. - Provision of recharge wells. -Provide proper recharging system -Provide proper filter gravel
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
Apr-17
Oct-17
Apr-17
Apr-17
Apr-17
Apr-17
Apr-17
Apr-17
Apr-17
Apr-17
Mar-17
Due Date By
Revision J 13 14
7 months
13 months
7 months
7 months
7 months
7 months
7 months
7 months
7 months
7 months
7 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 11/08/2017 15 16 17 Remarks
T309/CNSS
T309/CNSS
100
100
014
013
N.A
NA
Construction of ERSS (Kingpost) for traffic decking
Construction of ERSS (Drainage diversion)
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
- Instability of temporary works (kingpost for traffic decking - ERSS) -Poor ground condition -Using of poor condition machinery - Noise pollution -Accidental dislodgement of kingpost during driving -Collision of machinery and site people.
Gaps in sheet piles
Hazard
4
5 Hazard Cause
- Poor design lead to undersize kingpost. - Poor workmanship. -Overloading of kingpost with other load not considered in the design. -Toppling of machinery resulting in damage to property. -Injury to surrounding people. -Structure failure of machinery.. -Old machinery and poor maintenance causing disturbance to nearby resident. - Carelessness and inexperience operator. Faulty vibro hammer.
- Supporting structure across the excavation due to lack of diversion corridor
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Collapse of temporary works - Collapse / damage of adjacent structures - damage of permanent works - Injury or fatality of construction workers or public
- Leakage through gap in the walls - Damage to services - Groundwater drawdown - Localized collapse of soil in the gap during excavation
Impact
Package 1
IV
III
S IV
F III
C
C
Ri
Initial Risk Category Ri
7
- Method Statements to ensure kingpost is constructed according to MS -JV engineer / QPS to supervise kinghpost construction work to esnure quality of workmanship. - Design to allow sufficient safety factor for structure interity of kingpost. -Access to be laid with hardcore and compacted. -I beam to be properly stacked and excluded. -Machine to be inspected and certified by AE. -Regular monthly maintenance of machineries - Work zone to be barricaded to prevent unauthorized entry - Used of tag line to control swaying of load. - Only allow skilled operator and experienced lifting team.
- Minimize gaps to minimum size required - Utilities diverted from excavation wherever possible - Instrumentation around gap area when necessary
Mitigation Measures
8
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
V
III
S IV
F IV
D
D
Ri
Residual Risk Category Rr
11 Risk Owner
- During construction phase, ensure RA control measure are implemented - e.g. -Segregation of man and machines -Provide designated pedestrian access for wokers. - Provide adequate warning signs. - Provide proper barricades around bore hole. -Installed sound barrier - Used of silent piler - Refrain from working at night and weekend /PH - Additional sling tied to sheet pile and machinery as extra protection in case grabber gives way. - Access to be laid with hard-core and compacted. - kingpost to be laid on top of hard-core.
JHZH-PM
JHZH-PM - Reinstall sheet piles if there are gaps during installation - Emergency Response Planning including Contingency Planning (e.g. immediate removal works upon sighting of unfavaourable ground/wall movements) 1) Mild case (to read; less than 10% of total panel excavated volume) – Create an earth bund wall surrounding the affected panel, fill up the bund wall pool with bentonite to increase the bentonite head level. 2) Moderate case (to read; more than 10% of total panel excavated volume, without any visual ground/ platform depression) – Move the grabber and other unnecessary heavy equipment at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. 3) On a case by case basis for a severe case (to read; more than 10% of total panel excavated volume, with obvious visual ground/ platform depression) – Move all machinery away except excavator at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. After 24 hours of backfilling, conduct light cement grout beneath the depressed platform.
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10 12
JHZH-PM
JHZH-PM
*Action Owner
Apr-17
Apr-17
Due Date By
Revision J 13 14
7 months
7 months
Risk Exposure Period
C
C
Target Risk Rating
Open
Open
Status
Date: 11/08/2017 15 16 17 Remarks
102
102
102
102
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
102
102
T309/CNSS
T309/CNSS
102
Diaphragm walling T309/CNSS
007
006
005
004
003
002
001
NA
NA
N.A
T309/CDSS/102/004
T309/CDSS/102/003
T309/CDSS/102/002
T309/CDSS/102/001
Barrette pile test
Welding Works with Welding inverter
Welding Works with Oxygen acetylene and Welding inverter
Diaphragm walling
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
5
-Instability of ERSS wall trenches - Low shear strength in Marine Clay - Loose fills - Possible removal of buried obstructions - Presence of thick peaty layers - High pore water pressure in Marine Clay - Close proximity of adjacent activities such as jet grout piles or casting of nearby trench -Leakage of Bentonite from D wall -Poor Bentonite mixe.
Hazard Cause
6
- Structural damage/deflection of existing structures - Damage to utilities - Traffic accidents with associated injuries - Damage to road surfaces - Collaspe of D wall
Impact
Kentledge collapse
- Failure of jack, jack force is not locked in - Unbalance pressure force in jack
- Testing of D-wall
- Improper maintenance of welding set - Improper connection and damaged cables - welding set not fully protected from wet surfaces - Welding in open space during wet weather condition
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury to public or construction personnel - Delays - Claims -Reputation
IV
IV
IV
I
I
I
II
IV
- Injury to public or construction personnel - Delays - Claims - Damage to permanent and temporary works
Fire sparks, fire explosion - Inappropriate welding of struts - Inappropriate welding of Traffic Deck due to Gas leaks, hose damaged, fitting damaged - Inappropriate welding of Noise Barriers - Incompetent welder deployed
Electrocution due to electrical leak
III
V
III
III
V
V
II
S
IV
F
7
B
B
B
C
D
D
D
C
Ri
Initial Risk Category Ri
- Water ingress - Lost toe stability - Loss of fines - Settlement of structures
- Delay of works -Inappropriate diaphragm wall design - Inappropriate use / misinterpretation of design codes
Package 1
- Contractor shall provide -uniform hydraulic pressure supply to all jacks to main balance force in test - Mechanical safe lock (safety valve) to lock pressure in jack during jack operation in case of pressure loss
- Test set up must get endorsement of PE
- PPE: Welding face shield, apron and gauntlet - Apply PTW (e.g. hot works) daily before commencement of work - Electrical wires to be secured above ground - Daily welding set checklist/ inspection - Certified welders - Reminder in Tool box meeting
- PPE: Welding face shield, apron and gauntlet - Proper housekeeping - Method Statements (e.g. - Close main value & flush hose line after usage) - Apply PTW (e.g. hot works) daily before commencements of works - Daily welding set checklist/ inspection - Fire extinguishers and fire blankets - Reminder in Tool box meeting '- Certified welders - Welding screen to contain sparks
- Specifying waterproofing details @ interface
- Use of adequate plant / equipment for diaphragm wall construction -Apply PTW (e.g. lifting) daily before commencements of works - Cage to be within lifting equipment capacity - Lifting points to be identified, marked and approved
- Emergency Response Planning including Contingency planning e.g. grouting of gaps - Method Statements to ensure safe working methods - Apply PTW (e.g. excavate) daily before commencement of work
- Method Statements to ensure safe working methods - Regular monitoring of critical structures - Stability calculations - Contingency planning e.g. (backfilling) in case of collapse, additional temporary struts - Trial panel - Raised guide walls - Control of bentonite properties (e.g. viscosity, sand content, PH value, density) - Visual inspection - Pre-qualify contractors -Apply PTW (e.g. excavate) daily before commencement of work - Deploy worker to monitor Bentonite level especially over week end.
Mitigation Measures
8
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
Inadequate water tightness - Poor concrete compaction - Inadequate concrete cover and reduced durability due to honeycomb - Poor workmanship
Diaphragm wall cage too heavy to be lifted
Gaps in retaining systems Provision for services to pass through retaining -Cracking / leakage systems - Structural Damage - Waterproofing problems and associated repair
Excessive ground movement of adjacent structures and utilities
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
V
V
V
V
V
I
I
I
I
III
III
III
V
V
II
S
IV
F
C
C
C
C
D
D
D
C
Ri
Residual Risk Category Rr
11 Risk Owner
12
JHZH-PM
- Provide physical barrier (interlocked properly) JHZH-PM and safety signs around test sites - Emergency Response planning including Contingency planning - Proper design of kentledge system - Pre-qualify the subcontractor - Approved Method Statement
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM
JHZH-PM
-Monitoring of overall settlement and differential JHZH-PM settlement of the kentledge - Provide physical barrier (interlocked properly) and safety signs around test sites - Emergency Response planning including Contingency planning - Proper design of kentledge system - Pre-qualify the subcontractor - Approved Method Statement
-No welding work under rain weather/ wet surfaces - Monthly inspection of welding equipment - Apply Safe Work procedure - Electrical neoprene cable double insulated
- Remove flammable items (timber, canvas etc.. )from welding premises - Monthly inspection of welding equipment - Apply Safe Work Procedure - Implement PTW -Hot work
- High quality construction inspection and records - Method Statements to ensure safe working methods - Use of adequate plant/equipment for ERSS wall construction
- Adopt approved lifting plan - Ensure lifting equipment are inspected monthly - Lifting zone to be barricaded before works commence
- Proper post-cast for structure - Specifying waterproofing details @ interface
-Normal/ established procedures for staging the JHZH-PM works to protect adjacent utilities -Regular review instrumentation reading -Permit to remove strut system followed to prevent inappropriate removal of struts -No stockpiling against D-wall -Emergency Response planning including Contingency planning - Never start D-walling without having the cages ready.
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
Mar-17
Mar-17
Oct-17
Oct-17
Oct-17
Oct-17
Oct-17
Oct-17
Due Date By
Revision J 13 14
7 months
7 months
13 months
13 months
13 months
13 months
13 months
13 months
Risk Exposure Period
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 11/08/2017 15 16 17 Remarks
102
T309/CNSS
102
102
Pilling T309/CNSS
T309/CNSS
102
102
T309/CNSS
T309/CNSS
011
010
009
009
008
NA
T309/CDSS/102/004
T309/CDSS/102/001
NA
NA
Bored pile test
Piling
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
5
-Instability of ERSS wall trenches - Low shear strength in Marine Clay - Loose fills - Possible removal of buried obstructions - Presence of thick peaty layers - High pore water pressure in Marine Clay - Close proximity of adjacent activities such as jet grout piles or casting of nearby trench
Kentledge collapse
- Failure of jack, jack force is not locked in - Unbalance pressure force in jack
- Bored Pile testing
Inadequate water tightness - Poor concrete compaction - Inadequate concrete cover and reduced durability due to honeycomb - Poor workmanship
Excessive ground movement of adjacent structures and utilities
- Poor design - Poor workmanship - Poor rigging method
- Improper securing of material/ equipment/ cages - Overloading of material/ equipment/ cages - Slight tilt in crane '- Sudden movement of crane boom
Failing of loose material/ equipment/ rebar cages
In Stability of rebar cage (including cages for Lshape d-wall panel)
- Breakage of lifting chain - Breakage of lifting sling - Failure of brake motor/gear - Failure of sling/chain buckles and hooks - Overloading of carried loads over limited of design capacity - Unauthorized modification of lifting points -Inadequate rigging method.
Hazard Cause
Failure of lifting mechanism
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Water ingress - Lost toe Stability - Loss of fines - Settlement of structures
- Structural damage/deflection of existing structures - Damage to utilities - Traffic accidents with associated injuries - Damage to road surfaces
IV
IV
V
IV
IV
I
I
III
II
I
I
IV
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities - Rebar cage fall off during lifting process. - Crane damanged by swing load e.g. windscreen damaged by lifted rebar cage.
I
S
IV
F
7
B
B
D
C
B
B
B
Ri
Initial Risk Category Ri
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities -Crane topple -Tanish reputation
Impact
Package 1
- Contractor shall provide -uniform hydraulic pressure supply to all jacks to main balance force in test - Mechanical safe lock (safety valve) to lock pressure in jack during jack operation in case of pressure loss
- Test set up must get endorsement of PE
- Use of adequate plant / equipment for ERSS wall construction
- Method Statements to ensure safe working methods - Regular monitoring of critical structures - Stability calculations - Contingency planning e.g. (backfilling) in case of collapse, additional temporary struts - Trial panel - Raised guide walls - Control of bentonite properties (e.g. viscosity, sand content, PH value, density) - Visual inspection - Pre-qualify contractors - Apply PTW (e.g. piling) daily before commencement of work
- Cage design must get endorsement of PE - Regular inspection of interface with good records - Lifting points to be marked, identified and approved - Engineer to be present to confirm lifting points prior liftng rebar cage. - Ensure moin load radius is taken into consideration when preparing lift plan.
- Approved PTW (e.g lifting) daily before commencement of work - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be marked, identified and approved - Approved Lifting plan - Material shall be stacked safely and within stacking limit and load
- Apply PTW (e.g. lifting) daily before commencement of work - Monthly inspection of lifting mechanisms - Lifting Supervisor to ensure correct method of usage - Colour coding all lifting mechanisms for validity and serviceability levels - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Lifting points to be marked, identified and approved - Approved Lifting Plan -Weekly boom down inspection with mechanics
Mitigation Measures
8
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
V
V
V
IV
I
I
III
II
I
I
V
V
I
S
V
F
C
C
D
C
C
C
C
Ri
Residual Risk Category Rr
11
12
JHZH-PM
JHZH-PM
- Provide physical barrier (interlocked properly) JHZH-PM and safety signs around test sites - Emergency Response planning including Contingency planning - Proper design of kentledge system - Pre-qualify the subcontractor - Approved Method Statement
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM
Risk Owner
-Monitoring of overall settlement and differential JHZH-PM settlement of the kentledge - Provide physical barrier (interlocked properly) and safety signs around test sites Contingency planning - Emergency Response planning - Proper design of kentledge system - Pre-qualify the subcontractor - Approved Method Statement
- High quality construction inspection and records - Method Statements to ensure safe working methods
- Regular review Instrumentation reading -Permit to remove strut system followed to prevent inappropriate removal of struts - Emergency Response planning - Review SI report and cross check at site - Provide water relief wells when necessary
- Emergency Response planning including Contingency planning - Adopt 3X3 lifting principles. - Only R/S is allowed to give signal to crane operator.
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
Mar-17
Mar-17
Mar-17
Mar-17
Mar-17
Oct-17
Oct-17
Due Date By
Revision J 13 14
7 months
7 months
7 months
7 months
7 months
13 months
13 months
Risk Exposure Period
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Status
Date: 11/08/2017 15 16 17 Remarks
105
105
T309/CNSS
T309/CNSS
003
002
T309/CDSS/105/003
T309/CDSS/105/002
T309/CDSS/105/001
Adjacent Structures or Buildings T309/CNSS 105 001
NA
T309/CDSS/103/001
103
Permanent Works T309/CNSS
012
001
102
T309/CNSS
Construction work nearby to adjacent structures or buildings
Construction work nearby stake holders
Construction work nearby to school
Construction of Permanent Works
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
5
- Breakage of lifting chain - Breakage of lifting sling - Failure of brake motor/gear - Failure of sling/chain buckles and hooks - Overloading of carried loads over limited of design capacity - Unauthorized modification of lifting points
Hazard Cause
- Improper securing of material/ equipment/ cages - Overloading of material/ equipment/ cages - Slight tilt in crane '- Sudden movement of crane boom
Excessive ground and building settlement
Damage / excessive settlement to buildings/structures: - Victoria School Access Bridge - 2-storey semi-detached houses at Kee Sun Ave - St. Andrew's Autism Centre - Elliot at The East Coast - Laguna Park Electrical Substation (Block 5000F) - 2-storey semi-detached houses at Elliot Walk - Opera Estate Canal & Culverts Interface with the public.
Stop or delay school operation. Interface with the public.
- Activation criteria and minimum head are not given
- Ineffectiveness of recharge well layout given in the A/E design '- Some recharge well points will not provide effective recharging due to their locations being far from the buildings to be protected - Filter may not be compatible with the existing ground conditions - Pile test and D-wall test
-Long term settlements - Scheduling of work planning
-Unforeseen ground conditions -Excavation works causing unforeseen settlements -Groundwater drawdown
-Proximity of schools has special implications, -Victoria school is boarding school) - Scheduling of work planning
Excessive settlement - Insufficient ground information available for (Victoria School bridge and design canal structures)
Failing of loose material/ equipment/ rebar cages
Crane topple / Hoisted load - Poor crane footage hit crane - Incompetent lifting team - Poor lift plan - Congested work environment
Failure of lifting mechanism
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Damage to utilities - Damage to property
- Disruption to the site activities during installation of recharge well - Blockage of the filter gravel - Excessive water flow rate provided by the pumping system but little recharging effect
- Claims - Damage to buildings/structures - Complains from the public - Injuring the public
- Damage to buildings/structures - Delays - Claims - Closure of roads - Injuries / fatalities of construction workers and public
-Noise disruption to schools -Pick up and drop off times Damaged - Complains from the public - Injuring the public
- Serviceability issue with the bridge
IV
IV
V
V
III
IV
IV
III
III
I
I
IV
III
I
I
IV
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
I
S
IV
F
7
C
C
C
C
C
C
B
B
B
Ri
Initial Risk Category Ri
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
Impact
Package 1
-Activation criteria and minimum have been designed and indicated (Zone 1 to 3)
- Contractor's consultant has designed the recharging system, modified the configuration - Design of filter gravel has been provided
- Instrumentation / Monitoring - Reduce work inteface with public during peak hours
- Contractor’s Method Statements - instrumentation / monitoring - Real time monitoring - Specification of instrumentation and monitoring requirements by AE consultant - Strengthening and temporary propping when necessary - Additional site investigation
- Contingency planning, inspection and monitoring - Method Statements - Additional site supervision (e.g. traffic marshal) - Reduce work inteface with public during peak hours
- Provision of additional boreholes for bridge and canal design
- Approved PTW (e.g lifting) daily before commencement of work - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be marked, identified and approved - Approved Lifting plan - Material shall be stacked safely and within stacking limit and load
- Design and COS crane access - No Overloading at all times - Proper maintenance of crane - Only competent lifting team is allowed - Implemet Permit to lift - Include both Max. and Min load radius - Do not conduct lifting in congested work environment. - Provide exclusion zone and Provide warning signs. - Provide sufficient tag lines
- Apply PTW (e.g. lifting) daily before commencement of work - Monthly inspection of lifting mechanisms - Lifting Supervisor to ensure correct method of usage - Colour coding all lifting mechanisms for validity and serviceability levels - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Lifting points to be marked, identified and approved - Approved Lifting Plan
Mitigation Measures
8
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
IV
IV
V
V
III
IV
III
III
I
I
IV
III
I
I
V
V
I
S
V
F
C
C
C
C
C
C
C
C
C
Ri
Residual Risk Category Rr
11
- Provide proper recharging system - Provide proper filter gravel - Instrumentation/ Monitoring of settlement - Additional Site investigation
- Emergency Response planning - Provide proper recharging system - Provide proper filter gravel - Instrumentation/ Monitoring of settlement - Additional Site investigation - Control of bentonite pressures
- Perform ground improvements when necessary
-Emergency Response planning including Contingency planning -Instrumentation/monitoring to monitor strut loads. - Instrumentation/ real time monitoring - Sufficient vibration monitors with appropriate trigger levels to be installed. - Provision of recharge wells. -Provide proper recharging system -Provide proper filter gravel
12
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM
Risk Owner
JHZH-PM - Proper planning and traffic control - Provide soundproof wall - Close communication with the school and be cognisant of critical times in the school calendar
- Emergency Response planning - Insturmentation and monitoring of settlement - Additional Site investigation when necessary
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
May-20
Oct-17
Oct-17
Oct-17
Due Date By
Revision J 13 14
79 months
79 months
79 months
79 months
79 months
45 months
13 months
13 months
13 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 11/08/2017 15 16 17 Remarks
105
105
T309/ CNSS
T309 / CNSS
005
004
NA
N.A
Traffic Diversion for Option 1C (Laguna Park)
Traffic Diversion around Victoria School
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
5
'- Lack of communication between LTA, main contractors, and sub contractors.
Motorist confusion
Noise
Complaints from stakeholder
Traffic jam / congestion
'- Lack of coordination between JHZHJV and subbies operation team
- Poor planning
-Public confusion
Workers hit by traffic
- Congested road leading to Victoria school - Construction activities in front of Victoria school - Heavy machinery stationed along Siglap Link - Heavy traffic from new egress to Marine Parade Road - Pedestrians jaywalking -Inadequate signage and poor traffic control measures -Unsafe traffic layout -Failure to carryout trial trench for UG services -Failure to barricade work area and provide banksman to guide vehicular movement on site -Failure to equip with proper PPE
Hazard Cause
Risk associated with Traffic Diversion -Unsafe traffic conditions, accident hot spot and vehicles crashing into site -Damaged to UG services -Noise and dust pollution
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Collision of construction and public vehicles - Fatality - Delays - Claims - Injury to public or construction personnel - Tarbish reputation
- Collision of construction and public vehicles - Delays - Claims - Injury to public or construction personnel
Impact
Package 1
II
II
IV
S
F IV
C
C
Ri
Initial Risk Category Ri
7
-Clear and advance notification to all stake holders - Sufficient and clear notification signage to motorist – e.g. VMS - Coordinate closely with relevant authority e.g. LTA - Organise “work session” to brief all relevant parties - Briefing session to be conducted with all relevant parties on personnel on process of diversion. - Apply for lane closure - Close lane in accordance with COP Traffic control - Put up sufficient advance warning signage - Brief TCP to all relevant person prior work start - Carry out traffic diversion off peak hours. - Inform NEA about late traffic diversion work Potential noise issue - Ensure workers put on reflective vest. - Traffic controllers to equipped with light batons
- Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan '- Guard rail or rigid barrier to be setup and interlocked properly - designated path for access by pedestrians '- Code of Practise of Traffic Control and Work Zone -Approval of temporary traffic diversion layout by TM -Traffic layout and signage to follow TCP -Submit PSR (road) for clearance -Ensure good visibility of signage --Apply permit to dig prior to start work -Conduct RA/ SWP briefing
Mitigation Measures
8
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
II
II
V
S
F IV
C
C
Ri
Residual Risk Category Rr
11 Risk Owner
- Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan '- Guard rail or rigid barrier to be setup and interlocked properly - designated path for access by pedestrians '- Code of Practise of Traffic Control and Work Zone -Approval of temporary traffic diversion layout by TM -Traffic layout and signage to follow TCP -Submit PSR (road) for clearance -Ensure good visibility of signage --Apply permit to dig prior to start work -Conduct RA/ SWP briefing
JHZH-PM
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly when necessary - Placement of cone or barrier during diversion without reduction in lane width -Desk top study of all utilities and carryout appropriate trial trench -Barricade work area and provide proper signage and warning to motorist and pedestrian. -Lane closure to avoid peak hours, applicable hours is 9:30-16:30 for daytime and 16:30-09:30 for night time closure -Flow chart indicating the flow of instruction enabling the lorry truck to enter the lane closure work area during soil removal or delivery of materials.
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10 12
JHZH-PM
JHZH-PM
*Action Owner
Jun-23
Mar-23
Due Date By
Revision J 13 14
79 months
79 months
Risk Exposure Period
C
C
Target Risk Rating
Open
Open
Status
Date: 11/08/2017 15 16 17
To be discuss further in briefing session later.
Further improvemen ts will be discuss in PSR roadworks
Remarks
005
Future developments or Addition & Alteration works 112 001 T309/CNSS T309/CDSS/112/001
110
T309/CDSS/110/005
N.A
T309/CNSS
109
Existing Conditions T309/CNSS
004
T309/CDSS/106/003
T309/CDSS/110/004
106
T309/CNSS
003
T309/CDSS/106/002
Interface with Adjacent Contracts T309/CNSS 110 004
106
T309/CNSS
002
T309/CDSS/106/001
T309/CDSS/109/006
106
T309/CNSS
001
006
106
Existing Utilities T309/CNSS
Future developments or Addition & Alteration works
Excavation
Excavation
Excavation for Utility Diversion Works
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
Clashes between railway structures and future underground infrastructure works and/or future above ground developments
Interfacing with adjacent contracts
Incompatible Interfacing with adjacent contracts
Seawall obstruction
Limited Work Areas
Damage to utilities
Damage to utilities and disruption to services
Damage to submarine cable
Hazard
4
5 Hazard Cause
- Injury or fatalities of public and construction workers Unplanned excavation -Insufficient marking on site -Failure to conduct detection test
- Damage to the equipment used - Deep foundation and diaphragm wall are not constructed properly
- Unforeseen higher than designed surcharge
- Damage to utilities - Damage to road surfaces - Damage to property
-Proposals for future underground infrastructure - Incompatible construction techniques and developments in direct conflict with alignment and stations - Delay of works - Unaware of future infrastructure and developments proposals
Effect of T310 TBM tunnels on D-Walls subway - Excessive ground movement near Entrance C - Movement to adjacent structures
Unappropriate or non-workable connection - Excessive ground movement design at interface of bored tunnels and station - Movement to adjacent structures end walls - Groundwater drawdown - Waterproofing problem and associated repairs
Abandon seawall
- Work areas too restricted or efficient workings - Schedule delays - Work areas require significant temporary - Unsafe environment for construction personnel works for their establishment traffic congestion
-Diversion and support of utilities across excavation: - Water pipe - Power Grid cables - SP Telecom cables - Starhub cables
6 Impact
Disturbance to public
-Non coordinated inter-contract utility diversion, - Delay - Remote disruption -Unforeseen obstructions - Missing information from utilities agencies - Insufficient trial trenches
Insufficient information about cable location
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Package 1
V
V
V
V
IV
II
II
I
I
IV
III
I
V
III
III
I
S
III
V
F
C
C
C
C
D
C
C
C
C
Ri
Initial Risk Category Ri
7
- PE to ensure surcharge level to within acceptable loading
- Contractor to review Development Interface Report in detail - Coordination meetings between interfacing designers - Coordination between all parties (Client, Contractor, designers)
- Coordination meetings between interfacing contractors and designers to be managed by Contractors - Construction Interface report by Contractor - Coordination between all parties (Client, Contractor, Designers)
- Coordination meetings between interfacing contractors - Construction Interface report by Contractor - Coordination between all parties (Client, Contractor, Designers) - Specifying waterproofing details @ interface
- Additional trial trench and site investigation
- Buidling temporary decking for efficient road/land use - Detailed SHE procedure to enforce safety
- Ongoing co-ordination with relevant utility companies - Contractor's Method Statement - Approved NCE - Pre-qualify Contractors - Apply PTW daily before commencement of work -Thorough study of utilities drawings -Cable detections by qualified LCDW -Provide clear utilities marking on site -Provide A3 size drawing of utility plan -Apply permit to dig -Barricade work area while trenching -Contact relevant utility agency for any presence of unidentified utility -Always treat utility as `live’ if encountered -Only manual digging allowed for trial trench -Full time supervision during trial trench -No mechanical excavation within 3 meters from live utilities. - Only manual excavation allowed for trial trench digging. - Brief utilities plan in language understood by the workmen.
- Method Statements - Additional site investigation - Approved NCE
- To divert submarine cable away from the station box
Mitigation Measures
8
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
V
V
V
V
IV
II
II
I
I
IV
III
I
V
IV
III
I
S
IV
V
F
C
C
C
C
D
C
C
C
C
Ri
Residual Risk Category Rr
11
12
- No stockpiling
- Close coordination with related parties
- Instrumentation and monitoring - Close coordination
- Emergency Response planning e.g. grouting - Methods Statement - Close coordination
- Cross check at site - Laise with related authority about the information of seawall
- Efficient site utilization plan for each different working stage - Hire a professional road safety review learn and checking when necessary
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
-Utility cable detection and trial trench should be JHZH-PM carried out to identify the alignment -Diversion out of the structure footprint -Emergency Response planning including Contingency planning -Close communication with utilities agencies -Cable detection -Properly mark the location of utilities and briefing site staffs, workers and sub-contractors -If unclear with the finding of services after reaching the 2m limit, conduct further detection to determine the presence of any services below. -Dimensions and depth of Trial Trenches recorded by Project Survey Team for As Build information Photo records of trial trench including any utility discovered are recorded
JHZH-PM
JHZH-PM
-Design protective measures and temporary support scheme for utilities across excavation -Close communication with inter-contract and utilities agencies -Identify clear markers for utilities locations lines and brief staffs, workers and subcontractors -Cable detection -Emergency Response planning including Contingency planning
JHZH-PM
*Action Owner
JHZH-PM
Risk Owner
- Divert submarine cable away from the station JHZH-PM box and identify the clearly marker
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
May-20
May-20
May-20
May-20
Jan-17
Oct-17
Oct-17
Oct-17
Oct-17
Due Date By
Revision J 13 14
45 months
45 months
45 months
45 months
5 months
13 months
13 months
13 months
13 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 11/08/2017 15 16 17 Remarks
Construction Methodology T309/CNSS 117
009
T309/CDSS/117/009
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
●Crane collapse or failure ●Toppling of crane ●Crane hit surrounding structures, eg silo ●Hoisted material hit crane
Hazard
4
5 Hazard Cause
-Overloading of lifting equipment -Failure to observe safe work procedures -- Instability of working platform. - Failure of loose material equipment/ rebar cages - Lack of communication - Inadequate supervision and control - Unplanned and poor control of crane movement - Substandard lift plan
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
-Injury to site staff -Delay to construction -Damage to property
Impact
Package 1
IV
F II
S C
Ri
Initial Risk Category Ri
7
- Provide support plates for firm support - Apply PTW (e.g. lifting) daily before commencement of work - Full extension of outrigger prior to lifting - Approved Lifting Permit - No workers shall be allowed to stand below suspended loads - Lifting Supervisor to ensure correct method of usage - Approved lifting plan (e.g. full extension of outrigger, approved and proper use of slings) - Lifting points to be marked, identified and approved -Safety zone established -Tag line with coloured flag to be installed along hoarding to warn operator from crossing the line when turning during lifting -Tag line with coloured flag to be installed at the top of bentonite tank to warn crane operator and signal man to guide operator during crane movement. -Bentonite tanks near to Dwall will only be erected after the completion of Dwall. -To include min load radius in lift plan.
Mitigation Measures
8
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
V
F II
S C
Ri
Residual Risk Category Rr
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Reminder in tool box meeting - Lifting zone to be barricaded before works commence -Provide adequate hardstanding /firm working platform -Put in place the lifting permit system and display the relevant details on site. -Ensure no overloading of crane -Signaler to communicate with crane operator -Lift load by 300mm, hold for 3 seconds, all personnel 3m away -Approved lifting plan, reviewed by LE and approved by PM -Lifting operation supervised by lifting supervisor -Banksmen to guide crawler crane movement, ensuring no tracking over drain, trench or uneven ground. -Lifting points to be identified and approved -Low speed in lifting and lowering -Material shall be stacked safely and within stacking limit and load -Authorization of all machineries movement from point to point -Establish a permit to move system for heavy machineries -A lockout /tagout system during maintenance and breakdown period of mchineries -Maincon to control all machineries movement on site with daily discussion during coordination meeting -Setting up a security management plan that involved site security to be aware of the delivery of materials and ensuring no material delivery during lunch time and peak hour
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10 11
JHZH-PM
Risk Owner
12
JHZH-PM
*Action Owner
May-20
Due Date By
Revision J 13 14
45 months
Risk Exposure Period
C
Target Risk Rating
Open
Status
Date: 11/08/2017 15 16 17 Remarks
121
Fire and Explosions T309/CNSS
001
002
118
T309/CNSS
9
001
118
Ground Improvements T309/CNSS 118
T309/CNSS
T309/CDSS/121/001
T309/CDSS/118/002
T309/CDSS/118/001
T309/CDSS/117/010
Construction works involving flammable or explosive materials
Construction works for ERSS or permanent walls
Jet grouting
"L" shape D- wall cage installation - Tandam Lift
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
5
Inappropriate jet grouting methods
-Overloading of lifting equipment -Failure to observe safe work procedures -- Instability of working platform. - Failure of loose material equipment/ rebar cages - Lack of communication - Inadequate supervision and control - Unplanned and poor control of crane movement - Substandard lift plan
Hazard Cause
Fire or explosion during construction
-Encounter flammable materials - Breakage of buried services - Ignition of methane from peat layers - Contaminant gas - War relics/unexploded ordnances - Heavy vehicles carrying flammable materials may be driven into the construction site
Excessive deflection of Insufficient ground improvement / treatment ERSS or permanent walls works
Ground improvement failure
●Collision of cranes ●Crane collapse or failure ●Toppling of crane ●Crane hit surrounding structures, eg silo ●Hoisted material hit crane ●D wall stich snap ●Hoisted material hit crane
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Injury or fatality of public or construction workers - Damage to existing structures and services
- Flooding of excavation - Collapse of temporary works and adjacent structures - Injury of public or construction personnel - Disruption of essential services - Delays - Claims
- Collapse of ground - Injury or fatality of construction workers and public - Waterproofing problems and associated repair - Damage to buildings - Delay of works - Movements of adjacent structures
-Injury to site staff -Delay to construction -Damage to property
Impact
Package 1
F
V
V
V
IV
I
II
II
II
S
C
C
C
C
Ri
Initial Risk Category Ri
7
- Provision of appropriate plant - additional site investigation and geophysics when necessary - Gather knowledge from people with relevant experience - Apply PTW (e.g hot works) daily before commencement of work - Safety Datasheet and Warning signs and Emergency contacts on display - Reporting to Safety and Security Department
- Contractor to produce robust Design - Method Statements to ensure safe working methods - Robust ERSS Design - instrumentation / monitoring e.g. LBs to monitor building movement, LGs for ground movement and IW or XYZ for ERSS.
- Contractor to produce robust design - Jet grouting trials - Specifying waterproofing details @ interface - Instrumentation / Monitoring e.g. LBs to monitor building movement, LGs for ground movement and IW or XYZ for ERSS. - Additional site investigation and geophysics
- Provide support plates for firm support - Apply PTW (e.g. lifting) daily before commencement of work - Full extension of outrigger prior to lifting - Approved Lifting Permit - No workers shall be allowed to stand below suspended loads - Lifting Supervisor to ensure correct method of usage - Approved lifting plan (e.g. full extension of outrigger, approved and proper use of slings) - Lifting points to be marked, identified and approved -Safety zone established -Tag line with coloured flag to be installed along hoarding to warn operator from crossing the line when turning during lifting -Tag line with coloured flag to be installed at the top of bentonite tank to warn crane operator and signal man to guide operator during crane movement. -Bentonite tanks near to Dwall will only be erected after the completion of Dwall. -To include min load radius in lift plan.
Mitigation Measures
8
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
V
V
V
V
F
I
II
C
C
C
C
II
II
Ri
S
Residual Risk Category Rr
11
JHZH-PM
Risk Owner
- Proper and independent flammable materials storage and management - Emergency Response Planning including Contingency planning e.g. quick evacuation route - Permit to carry hazardous material
- Provide efficient geometric design and the road level to mitigate flooding - Witness the instrumentation reading - Regular review and analyse instrumentation reading - Emergency Response planning include Contingency planning, inspection and monitoring
JHZH-PM
JHZH-PM
- High quality construction records and material JHZH-PM testing - Methods statement - Pre-qualify contractors - Regular review instrumentation reading of inclinometers and ground settlement markers in trial test and feedback main works - Emergency Response Planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts.
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Reminder in tool box meeting - Lifting zone to be barricaded before works commence -Provide adequate hardstanding /firm working platform -Put in place the lifting permit system and display the relevant details on site. -Ensure no overloading of crane -Signaler to communicate with crane operator -Lift load by 300mm, hold for 3 seconds, all personnel 3m away -Approved lifting plan, reviewed by LE and approved by PM -Lifting operation supervised by lifting supervisor -Banksmen to guide crawler crane movement, ensuring no tracking over drain, trench or uneven ground. -Lifting points to be identified and approved -Low speed in lifting and lowering -Material shall be stacked safely and within stacking limit and load -Authorization of all machineries movement from point to point -Establish a permit to move system for heavy machineries -A lockout /tagout system during maintenance and breakdown period of mchineries -Maincon to control all machineries movement on site with daily discussion during coordination meeting -Setting up a security management plan that involved site security to be aware of the delivery of materials and ensuring no material delivery during lunch time and peak hour
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10 12
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
Mar-23
Jan-18
Jul-17
May-20
Due Date By
Revision J 13 14
79 months
16 months
10 months
45 months
Risk Exposure Period
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Status
Date: 11/08/2017 15 16 17 Remarks
122
994
994
Flooding T309/CNSS
Site set up T309/CNSS
T309/CNSS
002
001
002
NA
NA
T309/CDSS/122/001
4
5 Hazard Cause
MEWP topple
Hit by fallen object
Fall from height
Noise Barrier structural failure
6
- Collapse of temporary works - Excessive movement / Collapse of adjacent structures - Injury or fatalities of public and construction workers
-Interrupted construction, -Delays, -Environmental pollution
Impact
-Damage to own and public properties (Claims) - Injury or fatalities of public and construction workers
Old machinery and poor maintenance causing disturbance to nearby resident
Installation of sheet piles Noise pollution (foundation support for sound barrier)
Installation of sheet piles Accidental dislodgement of -Carelessness and inexperience operator. (foundation support for sheet pile during driving - Faulty vibro hammer sound barrier)
Structure failure of machinery
Installation of sheet Using of poor condition piles (foundation support for machinery sound barrier)
-Serious injury to worker and property. -Stop work causing delay
-Disturbance to neighbouring resident -Hearing injury to workers
-Low productivity Job delay and behind schedule -Cost implication
-Serious injury to worker and property. -Stop work causing delay
Installation of sheet piles Poor ground condition (foundation support for sound barrier)
-Toppling of machinery resulting in damage to property. -Injury to surrounding people.
-Serious injury to worker and property. -Stop work causing delay -Damage to machineries
Installation of sheet Collision of machinery and piles Constraint of work area (foundation support for site people. sound barrier)
-Damage to underground services -Disruption to stakeholders Location of utilities not reflected in utility drawing -Penalty charges by authority -Stop work order by authority -Delay to work schedule
-Failure to provide fall protection provision - Failure to provide control - Poor footage - Over loading of MEWP
-
- Collapse of temporary works - Incorrect information on adjacent structures - Not identifying the behaviour and response of - Damage to own and public properties (Claims) - Injury or fatalities of public and construction the ground and adjacent structures workers
-Flawed design of temporary works - Inappropriate use / misinterpretation of design codes - Lack of understanding of design software and output - Temporary works design is incompatible with adjacent structures
Flooding from the Opera -Damage the canal or foundation during Estate Canal at Siglap Link construction, -Extreme flooding event; -Tidal fluctuation -Structural problem of the canal
Hazard
Installation of sheet piles Damage to utilities (foundation support for sound barrier)
Setting up of Noise Barriers
Construction works near Opera East Canal
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Package 1
IV
IV
IV
IV
IV
IV
I
II
II
I
I
II
II
II
IV
IV
II
I
S
IV
V
F
B
C
C
B
B
C
C
C
C
C
Ri
Initial Risk Category Ri
7
V
V
-Additional sling tied to sheetpile and machinery as extra protection in case grabber gives way -Ensure sheetpile is clamped tightly between the grabber jaws before hoisting up vertically for installation
V
V
V
V
I
II
II
I
I
II
II
II
V
V
II
I
S
V
V
F
C
C
C
C
C
C
C
C
C
C
Ri
Residual Risk Category Rr
11 Risk Owner
12
Daily pre operation check on grabber by operator before start of work
Regular maintenance regime in place
LOTO system applied during maintenance period
-Ground preparation completed with the issuance of COS from PE -Ensure no overloading of machinery (Load kept at 75% of SWL
Apply for permit to move for machinery movement from point to point
Cable detection by LEW
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
- Strengthening of noise barrier when necessary JHZH-PM - Additional site investigations and localized ground improvement when necessary - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts. - Approved Method Statement
-Enveloped MEWP work platform with scaffold JHZH-PM netting to contain material. Limit max. 2 person on MEWP. Max. weight 120kg. Firm and compacted ground for MEWP access. Provide adequate exclusion zone and signage. Provide banksman to ensure no authorised entry in to work zone.
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM - Engage experienced and competent consultant to perform the design - Engage experienced and competent contractor - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts. - Approved Method Statement
JHZH-PM - Provide efficient geometric design and the road level to mitigate flooding -Awareness of climatic conditions -Regular monitor of water level in Opera estate Canal -Emergency Response planning including Contingency planning
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
-Installed sound barrier. -Used of silent piler. -Refrain from working at night and weekend/PH
-Machine to be inspected and certified by AE. -Regular monthly maintenance of machineries
-Access to be laid with hardcore and compacted. -Steelplate to be laid on top of hardcore. -Movement of machinery must be guided by benchemen
-Work zone to be barricaded to prevent unauthorized entry -Used of tag line to control swaying of load - Employed skilled operator and experienced lifting team
-Carry out cable detection and trial trench along the path of sheet piles. -Apply permit to dig prior to work start.
- Provision of Fall Protection Plan. - Establish PTW-Height system. - Provide proper access. - Provide adequate work platform. - Licensed MEWP operator. - Familiarisation briefing prior appointment.
- Perform further structural or geotechnical investigations e.g. coring, trial trenching - Apply PTW (e.g. welding) daily before commencement of work - Certified welder
- Sensitivity of design input parameters - Pre-qualify contractor - Apply PTW (e.g. welding) daily before commencement of work - Certified welder
- Method Statements - Additional site investigation -Confirmation with LTA on any specific flood protection measures required during construction
Mitigation Measures
8
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Due Date By
Revision J 13 14
79 months
79 months
79 months
79 months
79 months
79 months
79 months
79 months
79 months
79 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 11/08/2017 15 16 17 Remarks
994
996
996
997
T309/CNSS
Vector Management T309/CNSS
T309/CNSS
Mobilization T309/CNSS
001
002
001
003
NA
NA
NA
NA
Traffic Diversion
Workers working on site
Setting up of Hoarding
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
5 Hazard Cause
Risk associated with Traffic Diversion -Unsafe traffic conditions, accident hot spot and vehicles crashing into site -Damaged to UG services -Noise and dust pollution
Transmission of Dengue and Zika
Mosquito bites on construction/ public personnel
6
- Collapse of temporary works - Excessive movement / Collapse of adjacent structures - Injury or fatalities of public and construction workers
Impact
- Transfer (delivery and lifting) material, plant and manpower -Inadequate signage and poor traffic control measures -Unsafe traffic layout -Failure to carryout trial trench for UG services -Failure to barricade work area and provide banksman to guide vehicular movement on site -Failure to equip with proper PPE
- Mosquito breeding - Mosquito bites
- Mosquito breeding - Mosquito bites
- Traffic jam - Injury to public or construction personnel - Claims - Delays
- Injury or fatality of public or construction personnel - Claims - Delays
- Injury to public or construction personnel - Claims - Delays
- Collapse of temporary works - Incorrect information on adjacent structures - Not identifying the behaviour and response of - Damage to own and public properties (Claims) the ground and adjacent structures
Hoarding structural failure -Flawed design of temporary works - Inappropriate use / misinterpretation of design codes - Lack of understanding of design software and output - Temporary works design is incompatible with adjacent structures
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Package 1
F
IV
IV
IV
IV
IV
II
I
I
II
II
S
C
B
B
C
C
Ri
Initial Risk Category Ri
7
- Code of Practise of Traffic Control and Work Zone - Use of barrier and/or gate guards for exit/entrances to site -Approval of temporary traffic diversion layout by TM -Traffic layout and signage to follow TCP -Submit PSR (road) for clearance -Ensure good visibility of signage --Apply permit to dig prior to start work -Conduct RA/ SWP briefing -Desk top study of all utilities and carryout appropriate trial trench -Barricade work area and provide proper signage and warning to motorist and pedestrian. -Lane closure to avoid peak hours, applicable hours is 9:30-16:30 for daytime and 16:30-09:30 for night time closure
- Pest control '- Emergency Response planning - Vector control management - Additional supervision - Oiling in stagnant water and other respective areas - Provision of insect repellents to site staff
- Pest control - Emergency Response planning - Vector control Management - Additional supervision - Oiling in stagnant water and other respective areas - Provision of insect repellents to site staff
- Perform further structural or geotechnical investigations e.g. coring, trial trenching
- Sensitivity of design input parameters - Engage experienced and competent consultant to do the design - Engage experienced and competent contractor - Pre-qualify contractor
Mitigation Measures
8
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
IV
V
V
V
V
F
II
I
I
II
II
S
C
C
C
C
C
Ri
Residual Risk Category Rr
11 Risk Owner
JHZH-PM
JHZH-PM
JHZH-PM - Properly traffic control and signages with qualified traffic marshal - Clearly defined zones for accessible pathways and restricted areas - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Emergency Response planning including Contingency planning, inspection and monitoring - Lifting zone to be barricaded before works commence - Placement of cone or barrier during diversion without reduction in lane width -Flow chart indicating the flow of instruction enabling the lorry truck to enter the lane closure work area during soil removal or delivery of materials.
- Regular inspection of site to identify and eliminate breeding sites - Misting
- Regular inspection of site to identify and eliminate breeding sites - Misting
JHZH-PM - Strengthening of hoarding when necessary - Additional site investigations and localized ground improvement when necessary - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts.
JHZH-PM - Engage experienced and competent consultant to perform the design - Engage experienced and competent contractor - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts.
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10 12
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Due Date By
Revision J 13 14
79 months
79 months
79 months
79 months
79 months
Risk Exposure Period
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Status
Date: 11/08/2017 15 16 17 Remarks
997
999
Other Hazards T309/CNSS
997
T309/CNSS
T309/CNSS
001
3
002
T309/CDSS/999/001
N.A
NA
Construction Works near Residental area
Lifting with crane
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
5
- Breakage of lifting chain - Breakage of lifting sling - Failure of brake motor/gear - Failure of sling/chain buckles and hooks - Overloading of carried loads over limited of design capacity - Unauthorized modification of lifting points
Hazard Cause
Noise, dust and vibration
-Construction works in close proximity to the public -Excessive noise due to construction -Excessive noise due to bored and barette pile testing
Sharp edge material being - Site personnel cut by sharp material during lifted/ lowered/ handled handling
- Improper securing of material/ equipment Failing of loose material/ equipment including heavy - Overloading of material/ equipment - Slight tilt in crane mchineries / equipment '- Sudden movement of crane boom - Early release of jack base / hydraulic jack out riggers
Crane topple / Hoisted load - Poor crane footage hit crane - Incompetent lifting team - Poor lift plan - Congested work environment
Failure of lifting mechanism
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Injury to public or construction personnel - Disruption of essential services - Negative PR - Delays - Claims
- Injury and fatality to construction personnel - Delays - Claims
III
II
IV
IV
I
IV
I
IV
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
I
S
IV
F
7
C
C
B
B
B
Ri
Initial Risk Category Ri
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
Impact
Package 1
- Contingency planning, e.g. additional noise barriers, inspection and monitoring - Method Statements to ensure safe working methods - Installation of noise barriers - Noise level monitoring - Engaging community for feedback '- Noise, dust control plan
- Store all sharp material into material cages when possible - Pack/ organize sharp material - Use of PPE (e.g appropriate safety gloves, long sleeves, helmet and safety boots and glasses)
- Approved PTW (e.g lifting) daily before commencement of work - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be marked, identified and approved - Approved Lifting plan - Material shall be stacked safely and within stacking limit and load - Always secure materilas/heavy machineries on lorry bed before release out riggers / hydraulic jack. - Do not stay in libne of fire at all times.
- Design and COS crane access - No Overloading at all times - Proper mainyenance of crane - Only competent lifting team is allowed - Implemet Permit to lift - Include both Max. and Min load radius - Do not conduct lifting in congested work environment. - Provide exclusion zone and Provide warning signs. - Provide sufficient tag lines
- Apply PTW (e.g. lifting) daily before commencement of work - Monthly inspection of lifting mechanisms - Lifting Supervisor to ensure correct method of usage - Colour coding all lifting mechanisms for validity and serviceability levels - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Lifting points to be identified and approved - Approved Lifting Plan
Mitigation Measures
8
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
III
II
IV
V
I
I
V
V
I
S
V
F
D
C
C
C
C
Ri
Residual Risk Category Rr
11
12
- Vibration control plan - Vibration monitoring
JHZH-PM
JHZH-PM
JHZH-PM
- '- Identify sharp material and dipose (e.g. nails, JHZH-PM broken glasses) - Wrap sharp edges when possible
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM
Risk Owner
JHZH-PM
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
Mar-23
Oct-17
Mar-23
Oct-17
Mar-23
Due Date By
Revision J 13 14
79 months
13 months
79 months
13 months
79 months
Risk Exposure Period
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Status
Date: 11/08/2017 15 16 17 Remarks
999
999
999
999
999
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
006
005
004
003
002
T309/CDSS/999/006
T309/CDSS/999/005
T309/CDSS/999/004
T309/CDSS/999/003
T309/CDSS/999/002
4
Damage to construction works
-Traffic congestion - Unauthorized entry of personnel to site
Road vehicles entering construction site / excavations
Hazard
5
Setting up of Noise Barrier
Traffic Diversion
-Occurrence of a natural disaster during construction - Flooding - Heavy rainfall causing significant ground water table rise
- Construction activities require frequent transport movements - Works at site with long working hours for 7 days a week
-Construction works in close proximity to the public and existing housing -Excessive noise due to construction
-Spoil removed to designated location remote Movement of heavy vehicles causing disruption from site to traffic movement
Noise Barrier and foundation
6 Impact
- Injury to public or construction personnel - Disruption of essential services - Negative PR - Delays - Claims
- Delay and accidents, - ECM issues, - Mosquito breeding, - Security problems
III
III
III
V
IV
IV
I
V
- Flooding of excavation - Collapse of temporary works and adjacent structures - Injury or fatality of public or construction personnel - Disruption of essential services - Delays - Claims
II
S
II
IV
F
7
D
C
D
C
C
C
Ri
Initial Risk Category Ri
IV
-Environmental pollution
Package 1
- Method Statements - additional site investigation - Provision of Noise barrier - Monitoring of Noise - Noise control plan - Engage community regularly and gather feedback
- Method Statements -Additional traffic management
- Method Statements - additional site supervision - ECM Plan
- Robust ERSS design including flood barriers when necessary - Temporary groundwater controls and pumps within excavation - Specifying water proofing details @ interface
- Design and approved traffic diversions - Minimise traffic around construction sites - Use of barrier and/or gate guards for exit/ entrances to site
- Design and approved traffic diversions - Clear and good signages - Minimise traffic around construction sites
Mitigation Measures
8
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
- Complaint from nearby occupants - Complaint from LTA - Working time may be reduced with delay to programme
-Traffic congestion due to minimum diversions, - Injury to public or construction personnel drivers seeking alternative routes - Damage to temporary or permanent works
Hazard Cause
Discharge into Canal from -Heavy rain construction - Insufficient control on site -Surface run off, construction materials Construction Works (bentonite, concrete, grout, near Drains and Canal maintenance/cleaning facilities)
Construction Works near Drains and Canal
Traffic Diversion
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
V
IV
III
III
IV
I
V
IV
II
II
S
V
V
F
D
C
D
C
C
C
Ri
Residual Risk Category Rr
11 Risk Owner
12
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly -Designated haul routes -Contingency planning, inspection and monitoring - Placement of cone or barrier during diversion without reduction in lane width - Minimize loud noise activity during evening and weekends - Monitor noise meters at designated intervals - Contingency planning, inspection and monitoring
JHZH-PM
JHZH-PM - Install additional EC measures (e.g. silt fences, nets) when necessary '- Regular inspection of site by ECO at affected zones - Contingency planning, inspection and monitoring
- Close communication with related authority - Emergency Response planning including Contingency planning e.g. quick evacuation route - Provide efficient geometric design and the road level to mitigate flooding
JHZH-PM
JHZH-PM
*Action Owner
JHZH-PM - To provide traffic marshals to direct traffic when necessary - Clearly defined zones for accessible pathways and restricted areas - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Guard rail or rigid barrier to be setup and interlocked properly - Code of Practise of Traffic Control and Work Zone - Placement of cone or barrier during diversion without reduction in lane width
JHZH-PM - To provide traffic marshals to direct traffic when necessary - Clearly defined zones for accessible pathways and restricted areas - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Guard rail or rigid barrier to be setup and interlocked properly - Code of Practise of Traffic Control and Work Zone - Placement of cone or barrier during diversion without reduction in lane width
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
Mar-20
Mar-23
Mar-20
Mar-23
Mar-23
Mar-23
Due Date By
Revision J 13 14
45 months
79 months
45 months
79 months
79 months
79 months
Risk Exposure Period
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Status
Date: 11/08/2017 15 16 17 Remarks
999
999
999
999
999
999
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
013
012
011
010
009
008
007
N.A
N.A
N.A
N.A
N.A
N.A
N.A
Operation of machineries / equipment
Recahrge well work
Lifting with Excavator (Pick and Carry)
Traffic Diversion
Traffic Diversion
Removal of sludge
Cleaning
4
5
-Pipe leakage and burst -Loose connection
-Pipe leakage and burst -Loose connection -Lose control of hose
Hazard Cause
- Engine catch fire - Hydraulic oil leakage - Unvoluntary movement of machines boom / arm. - Load bearing componant give way.
Water pipe. Power grid cables. Telecom cables. High tension cables.
6
-Damage of machinery -Injury of worker -Damage of materials
-Damage of machinery -Injury of worker -Damage of materials
- Traffic jams hindering construction vehicles - Bottlenecks hindering traffic speed - Crossed traffic and pedestrian circulation paths - injury to public and/or construction work
- Traffic jams hindering construction vehicles - Bottlenecks hindering traffic speed - Crossed traffic and pedestrian circulation paths - injury to public and/or construction work
'- Injury to public or construction personnel - Contaminate soil, groundwater and surface water
- Injury to public or construction personnel
Impact
- Overloading or over running of machineries / -Damage of machinery -Injury of worker equipment result in over heating. -Damage of materials - Hydraulic leak - Poor maintenance reguime - Misue of machineries or equipment
-Unplanned Drilling. - Insufficient marking on site. - Failure to conduct detection test.
-Uneven ground - Unauthorised lifting - Improper rigging -Overloading -Inexperience operator
-“A’ frame topple - Injury to public - Fingers / hand caught in rotating parts
-Damaged to :
-Uneven ground - Unauthorised lifting - Improper rigging -Overloading -Inexperience operator
-Toppling of excavator - Falling of load/ material
Risk associated with Traffic - Change to road condition due to delivering Diversion material to site
Risk associated with Traffic - Change to road condition due to construction Diversion work, poor line of sight - Changed traffic condition causes confusion to road users - Improper/ unclear signages - Improper/ unclear separation of pedestrians paths and work site ingress/ egress points - Pedestrians jaywalking
Sludge spill
Use of high ultra water jet
Hazard
Note * - Action Owner will be reassigned from PM to Engineer-in-Charge when respective Engineer-in Charge is established
999
T309/CNSS
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Package 1
F
IV
IV
IV
IV
IV
IV
IV
II
II
II
II
II
II
II
S
B
B
B
B
C
C
C
Ri
Initial Risk Category Ri
7
- Ensure maintenance regisme is carried out properly. - Always equip machineries / equipment with valid fire extinguisher - Never misuse machineries / equipment. Use it as what it is intended for.
-Thorough study of utilities drawings. - Cable detections by qualified LCDW - Provide clear utilities marking on site - Provide A3 size drawing of utility plan - Apply permit to dig and implement “checklist for working near utility” - Barricade work area while trenching
- Ensure work assess is planned. - Ensure adequate access for work mobilisation and public access. - Only competent lifting crew is allowed to involved in mobilisation. - PTW-Lifting approved prior unloading. - Provide proper exclusion zone to segregate work and public. - Provide warning signs.
●The excavator designed for pick and carry operations must have load chart stating clearly the limitattions for picks and carry operation ●Tag line shall be used during operation ● Ensure the route of travel is firm and level ●Lifting supervisor to ensure the load is firmly secured and tied ●Benchman to guide excavator during the pick and carry operation
- Design stages of traffic diversion to allow construction to be carried out section by section - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Safety barrier to be setup at designated storage zones - Proper signages display at prominent locations - Code of Practise of Traffic Control and Work Zone - designated path for access by pedestrians - Control unauthorized entry of personnel into loading/unloading zone during material delivery
- Design stages of traffic diversion to allow construction to be carried out section by section - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Guard rail or rigid barrier to be setup and interlocked properly Proper signages display at prominent locations - Code of Practise of Traffic Control and Work Zone
- Competent staff - Provide safety warning signage to keep other works clear from work area - Provide safety access to treatment plant - Permit for handling of sludge - Provide emergency contact no.
- Assign two trained hydro jetting operators. - Rotate shift every alternate hours - Provide safety warning signage to keep other works clear from work area - Provide safety access to washing bay
Mitigation Measures
8
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
V
V
V
V
V
II
II
II
II
II
II
II
V
V
S
F
C
C
C
C
C
C
C
Ri
Residual Risk Category Rr
11
JHZH-PM
JHZH-PM
Risk Owner
JHZH-PM
JHZH-PM - Ensure fire extingisher is checked on a monthly basis - Monitor mechnais attendance for maintenance closely -
-Contact relevant utility agency for any presence JHZH-PM of unidentified utility Always treat utility as `live’ if encountered Only manual digging allowed for trial trench Full time supervision during trial trench
- Provide blinker lights to alert night motorist and /or pedestrian. - Ensure footage is firm and level at all times. - Never drag load. Lift vertically.
-AE to examine the lifting capacity of excavator JHZH-PM and issued the certification for the lifting. -Pick and carry operation is guided in SS536 : 2008
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly - Placement of cone or barrier during diversion without reduction in lane width
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly - designated path for access by pedestrians - Placement of cone or barrier during diversion without reduction in lane width
- Contain and handle spillage (e.g. excavate spill site and treat with dry sand, temporary diking) immediately - Contact additional emergency services when necessary
- Assign safety supervisor when possible at work place to ensure operation is safe - Barricade work area to prevent unauthorized access and display warning signage.
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10 12
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
*Action Owner
May-23
May-23
May-23
Mar-23
Mar-23
Mar-23
May-20
Mar-23
Due Date By
Revision J 13 14
79 months
79 months
79 months
79 months
79 months
79 months
45 months
79 months
Risk Exposure Period
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 11/08/2017 15 16 17 Remarks
17th Aug 2017
3 Months Programme Look ahead Risk and Mitigation
Construction of Siglap Station Thomson‐East Coast Line
Contract T309
2) To identify the major risk hazards and elaborate the mitigation measures in this workshop
1) To identify the major works activities for the next three months, Aug 2017 – Oct 2017
Objectives of this workshop:
Guide Wall & D‐Wall construction
Entrance C
Guide Wall & D‐Wall construction
3
Cooling Tower D‐Wall construction Recharge Well Installation Excavation RC Work
Noise Panel installation near to Laguna Park Hoarding Shifting Installation Guide Wall & D‐Wall construction
Guide Wall & D‐Wall construction Mob/demob of machineries
Entrance B
Entrance D
Entrance A
Upcoming Works Aug 17 – Oct 17
Mob / demob heavy machineries
Entrance A
1. ENT.A Mob / demobilisation Risk and measures
Mob / demo heavy machineries
Activity
Workers hit by topple machineries
Machines topple
Hazard
Poor supervision
Poor planning
Hazard Cause
Ensure proper footage for heavy machineries park/access Never mob/demob during wet weather condition
‐ ‐
Only relevant staff are allowed to be involved in mob/demob Risk assessment must be approved prior activity Never mob/demob at congested work area Always ensure height limit is <4.5m Operator deployed must be appointed and licensed (if applicable) Machines must be approved by LTA prior mobilisation New machines to comply with LTA “Approval Procedure for new machine”.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Provide exclusion zone and banksman
Angle of ramp within machine manufacturer recommendation
‐
‐
Ramp of trailer must be equal or wider than machine crawler belt.
‐
trailers are used for mob / demob
JV LE (Killi) Sub con supervisor
‐ ‐
JV LE (Killi) JV super. (Peter) JV super. (Peter) Sub con supervisor Sub con supervisor JV LE (Killi) JV LE (Killi)
‐ ‐ ‐ ‐ ‐ ‐ ‐
Sub con supervisor
JV LE (Killi)
‐
‐
JV LE (Killi)
‐
JV LE (Killi)
‐
‐
Obtained machineries technical information to ensure fit for purpose
Action Owner
Mitigation Measure
1. ENT.A Mob / demobilisation Risk and measures
New machines – Seek LTA approval by submission of relevant document and requirement prior mobilisation.
1. ENT.A Mob / demobilisation Risk and measures
Never mob/demob at congested work area
Avoid mob/demob on night shift
Mob/demob on clear and dry weather condition
Ground preparation to ensure stable footage for mobilisation
1. ENT.A Mob / demobilisation Risk and measures
• Turning radius of trailers etc
• Length and height of trailers
• Capacity of trailers
trailers <4.5m.
• Total height of loaded machines on
• Weight of machine
• Width of machine
• Width of machine track
FOS)
• Max angle of machines travel (giving
Obtain technical information of machineries such as;
1. ENT.A Mob / demobilisation Risk and measures
conditions etc.
• Machineries in good working
submitted and accepted.
• All required documentation
• Approval of machines by LTA / JV
accordance with design
• Area to park and steel plate layout
machineries (giving FOS)
• Ground bearing for heavy
Obtain other information such as;
Provide exclusion zone for mob‐demob activity
Conduct pre‐check prior mob/demob of machines
Alcohol check on operator involved in mob/demob prior operation
1. ENT.A Mob / demobilisation Risk and measures
Traffic controllers to guide mob/demob in/out site assisted by LE and relevant staff
Traffic control in place to ensure smooth transition into worksite
Only relevant personnel are allowed to get involved in mob/demob operation
1. ENT.A Mob / demobilisation Risk and measures
Conduct briefing to relevant personnel involved in mob/demob activity
Guide Wall & D‐Wall construction Recharge Well Installation Excavation Work
Cooling Tower
Cooling Tower Works
Cooling Tower Works
Area of excavation
Excavation work
Activity
Fall into Excavation
Excavation Collapse
Risk
•
Incompetent crew
Poor ground condition
•
• •
• •
‐
KKL Supervisor
Gajan (JV Engineer) KKL Supervisor
KKL Supervisor KKL Supervisor KKL Supervisor
‐ ‐ ‐ ‐ ‐
KKL Supervisor KKL Supervisor
‐ ‐
Peter (JV Superintendent) Thomas (Senior Supervisor)
‐ ‐
• • Ensure work assess is planned. Ensure adequate access for work mobilisation and public access. Only competent excavation crew is allowed to involved. PTW‐Excavation approved prior activity. Provide proper exclusion zone to segregate man and machines. Provide warning signs. Provide blinker lights to excavator and proper lighting particularly for night work. Ensure footage is firm and level at all times. Provide proper design and COS for shoring or sloping. No stock pipe of spoil at site. To cover with canvas in case of
Action Owner
Mitigation Measure
• Poor Shoring / • Sloping
Poor Planning
Hazard Cause
2. Excavation work (Cooling Tower) – Risk mitigation
Risk
Instability of ERSS/ temporary Works
Activity
Excavation work
Ensure correct grade, dimensions of steel materials used in strutting system as per details construction drawings. Good control on the welding quality – UT for butt weld & MPT for fillet weld
•
•
Poor workmanship
Only competent welders are allowed to weld
•
Sensitivity of design input parameters / robust design to minimise movement
Sufficient review of instruments monitoring results by Instrument Engineer and QPS
•
•
Independent Instrumentation Monitoring Specialist
•
‐
‐
‐
‐
‐
‐
Ensure construction sequence is in accordance ‐ with design
Jay Cel (JV Project Engineer)
Jay Cel (JV Project Engineer)
Jay Cel (JV Project Engineer)
Jay Cel (JV Project Engineer)
Desi (Senior Engineer)
Desi (Senior Engineer)
Peter (JV Superintendent)
Action Owner
•
Mitigation Measure
Insufficient control of the works
Design implementati on incorrect Insufficient monitoring
Hazard Cause
2. Excavation work (Cooling Tower) – Risk mitigation
Excavation work
Activity
Excessive wall deflection and ground movement
Ground instability during excavation
Risk
Insufficient control of the works
Design implementati on incorrect Insufficient monitoring
Hazard Cause
•
•
•
•
•
‐
‐
‐
‐
‐
Olive (JV Senior engineer)
Jay Cel (JV Project engineer)
Peter (JV Superintendent)
Olive (JV Senior engineer)
Olive (JV Senior engineer)
Olive (JV Senior engineer)
‐
• Recharge well to be installed before excavation commences Monitor alert level and suspension level of instruments Ensure all instrumentation are in place before excavation commencement Excavation sequence in accordance with design Independent monitoring of ERSS including struts loads, and joint review of instrumentation results by Instrumentation Engineer & QP(S). Monitor inclinometer (daily) and strut load readings (real‐time)
Action Owner
Mitigation Measure
2. Excavation work (Cooling Tower) – Risk mitigation
2. Excavation work (Cooling Tower) – Risk mitigation
16
2. Excavation work (Cooling Tower) – Risk mitigation
17
Locations of strain gauge / Load Cell
Risk
Noise – result in complains
Activity
Excavation work
Noise work activities
Hazard Cause
•
• • • •
‐
‐ ‐ ‐ ‐
Peter (JV Superintendent)
Peter (JV Superintendent) Manoj (JV ECO) Peter (JV Superintendent) Erin (JV SPRO)
Killi (JV Lifting Eningeer)
‐
• Equipment and machinery with noise insulating material Setting up of noise barrier around work site Monitoring of site noise level Adhere to designated work hours Keeping stakeholders informed on activities and planning activities (e.g. school exam period) Avoid noisy work after normal working hours.
Action Owner
Mitigation Measure
2. Excavation work (Cooling Tower) – Risk mitigation
Zone 1
Noise Barrier
Zone 2
Zone 3
Zone 4
Traffic Diversion TD1C
2. Excavation work (Cooling Tower) – Risk mitigation
Zone5
Zone6
19
Recharge well work
Activity
Fingers / hand caught in rotating parts
Injury to public
“A’ frame topple
Risk
Incompetent crew
Poor ground condition
Poor footage
Poor mobilization planning
Hazard Cause
3) Recharge Well work – Risk mitigation
• •
• •
• •
•
‐ ‐
‐ ‐
‐ ‐
‐
Killi (JV LE) Killi (JV LE)
Thomas (Senior Supervisor) Thomas (Senior Supervisor)
Killi (JV LE) Thomas (Senior Supervisor)
Desi (JV Senior Engineer)
Peter (JV Superintendent) Thomas (Senior Supervisor)
‐ ‐
• • Ensure work assess is planned. Ensure adequate access for work mobilisation and public access. Only competent lifting crew is allowed to involved in mobilisation. PTW‐Lifting approved prior unloading. Provide proper exclusion zone to segregate work and public. Provide warning signs. Provide blinker lights to alert night motorist and /or pedestrian. Ensure footage is firm and level at all times. Never drag load. Lift vertically.
Action Owner
Mitigation Measure
Risk
Fall from Height
Activity
RC works
4. RC Work– Risk mitigation
Working at edge Temporary Construction Openings Penetration covers not secured
Hazard Cause
• •
‐ ‐
Milan (JV Project engineer) Milan (JV Project engineer)
Peter (JV Superintendent) Peter (JV Superintendent) Peter (JV Superintendent) Peter (JV Superintendent) Peter (JV Superintendent) Peter (JV Superintendent)
‐ ‐ ‐ ‐ ‐ ‐
• • • • • • Ensure edges are barricaded when possible Use of safety harness Construction openings to be secured Penetration covers to be cast with wire mesh Proper access/ ladders/ platforms as provided Placing of signages to warn fall from height locations Retaining Wall to be cast (Roof Slab level) Guard Rail to be installed (Concourse level and below)
Action Owner
Mitigation Measure
TYPICAL EXAMPLE OF CONSTRUCTION OPENINGS AND REQUIREMENT FOR EDGE PROTECTION
Guard rail
Retaining wall
4. RC Work– Risk mitigation
22
Asphyxiation – Confined space
RC works
Trip and fall
Risk
Activity
Poor illumination
Lack of oxygen
Hazard Cause
4. RC Work– Risk mitigation
Peter (JV Superintendent) Peter (JV Superintendent)
‐ ‐
•
Thomas (Senior Supervisor) Peter (JV Superintendent) Peter (JV Superintendent) Peter (JV Superintendent) Peter (JV Superintendent) Peter (JV Superintendent)
‐ ‐ ‐ ‐ ‐ ‐
• • • • • • • Adhere to confined spaces specification Control of personnel entering Implement Confined Space permit systems Provide sufficient ventilation Conduct gas check every 4 hours Continuous air monitoring Appointment of qualified confined space supervisor. Installation of lighting
Action Owner
Mitigation Measure
Risk
Structural failure Concrete Design
Activity
RC works
• • • •
•
• •
Peter (JV Superintendent) Peter (JV Superintendent) Milan (JV Project engineer) Peter (JV Superintendent)
Peter (JV Superintendent)
‐
Milan (JV Project engineer)
Peter (JV Superintendent) Peter (JV Superintendent)
‐ ‐ ‐ ‐
‐ ‐ ‐ ‐
Peter (JV Superintendent)
‐
• Formwork removal shall be approved by formwork safety supervisor. Removal inspection checklist to be endorsed Ensure concrete strength is achieved prior to removal Temporary props are to be secured and not removed unless approved by engineer Ground shall be compacted Cast lean concrete Formwork design shall be endorsed by PE Supervision by engineer to ensure installation is as per shop drawings and according to method statement and RA assessment Emergency response planning including Contingency planning
Action Owner
Mitigation Measure
Design/ installation not being certified by PE Installation not as per PE • shop drawings
Ground foundation unstable
Early formwork removal
Hazard Cause
4. RC Work– Risk mitigation
Wall System Formwork
4. RC Work– Risk mitigation
25
Temporary Propping as part of Design (Stairshaft landing, bottom up construction) Scaffold System
End
Minutes Title: Monthly Risk Register Workshop No 6 Date:17 Aug 2017 Time: 2.00pm--3.30pm Held at: T309 LTA Level 2 Meeting Room
Chaired by: Jong Hua Kwan/ Tommy Lee Minuted by: Tommy Lee Distribution date: 5 Sep 17
Attendees list See attached
Apologies list
Page 1 of 3
Minutes ITEM
MATTERS DISCUSSED
1.0
Introduction
ACTION
Risk Workshop will be on 3 months look ahead activities. The complete flow of the process will be demonstrated via a short slide presentation
Info
The project superintendent will provide the necessary information required to mitigate risks on the above.
2.0 2.1
2.2
2.3
Slide presentation on 3 monthly look ahead - Aug - Oct Peter/ Jong 17 T309P informed that the incident relating to T309 project on hitting the LV cable was a case study between LTA/SPPG.
Drawings showing Site Services and Utilities should be split into three drawings: Respectively, Utilities (agencies), Site Services- Electrical, Site Services- Water. These drawings shall be distributed to all parties and place it on site.
T309P informed JHZH on the following items:
Note
JHZH
JHZH
a) Package 1 and 2 risks shall be combined as 1 risk register. b) To present/include the programme risks for the next meeting. c) Action owner shall be specific personnel to be included in the risk register. d) T309/CNSS/997/002- Page 23, T309/CNSS/102/012- Page 9, to add in machinery mobilization and demobilization issues into the risk register. e) T309/CNSS/117/013- Page 17, to add material falling from Slab into risk register. f) T309/CNSS/100/008- Page 4, to address the risk/mitigation measures as per findings and lessons learnt from collapse of trench for EB 26 panel. g) T309/CNSS/999/008- Page 26, to address the risk/mitigation measures as per findings and lessons learnt from bentonite spillage incident happened on 17 Aug 17.
3.0
Any Other Matters: The next workshop topic will be based on activities for the next 3 months look ahead.
Page 2 of 3
INFO
Minutes ITEM
MATTERS DISCUSSED
4.0
Next Workshop
ACTION
The next monthly workshop will be discussed with T309P for a proposed date
Page 3 of 3
All / Info
T309/CNSS
T309/CNSS
100
100
ERSS for Temporary Work
008
007
T309/CDSS/100/008
T309/CDSS/100/007
Trenching
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
Instability of temporary works (trenches)
● Differential settlement between station ERSS ● Failure of loose material, equipment/ rebar cage ● Instability of working platform
Hazard
4
5 Hazard Cause
ERSS wall construction within F1 soil layer - F1 soil layer collapse - Trench stability
- Not identifying the behaviour and response of the ground and adjacent structures
Flawed design of temporary works - Inappropriate use / misinterpretation of design codes - Lack of understanding of design software and output - Incorrect information on adjacent structures - Temporary works design is incompatible with adjacent structures
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Doc no: T309-JHZH-RAR-PWD-RIS-0001
6
- Collapse of temporary works - Excessive movement/Collapse of adjacent structures - Injury or fatalities of public and Construction workers
- Collapse of temporary works - Collapse / damage of adjacent structures - damage of permanent works - Injury or fatality of construction workers or public
Impact
Risk Classes A 0 B 23 C 63 D 7 93
Package 1
V
V
V
F
7
C
C
C
Ri
8 Mitigation Measures
- Contractor to produce robust design - Appropriate design sensitivity - Specify minimum penetration of panels - Additional site investigation - Pre-qualify contractors - Emergency Response planning - Provide temporary strut with PE endorsement
- Review levels to be developed - Regular review of Instrumentation / monitoring e.g. LBs to monitor building movement, LGs for ground movement and IW or XYZ for ERSS. - Approved Permit to lift and lifting plan - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be identified, marked and approved
- Contractor to produce robust design - Approved Permit to lift and lifting plan - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be identified, marked and approved
Page 1 of 17
I
I
I
S
Initial Risk Category Ri
I
I
V
V
I
S
V
F
C
C
C
Ri
Residual Risk Category Rr
11
12
JHZH-PM - Regular review instrumentation reading - Perform probing and SI (SPT) at regular intervals - Perform Ground Improvements when necessary - Joint inspection between JHZHJV and QPS for every Dwall 1) Mild case (to read; less than 10% of total panel excavated volume) – Create an earth bund wall surrounding the affected panel, fill up the bund wall pool with bentonite to increase the bentonite head level. 2) Moderate case (to read; more than 10% of total panel excavated volume, without any visual ground/ platform depression) – Move the grabber and other unnecessary heavy equipment at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. 3) On a case by case basis for a severe case (to read; more than 10% of total panel excavated volume, with obvious visual ground/ platform depression) – Move all machinery away except excavator at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. After 24 hours of backfilling, conduct light cement grout beneath the depressed platform.
JHZH-SBM
JHZH-LE/SO
- Steel plate to ensure uniform loading of crane JHZH-PM weight and outrigger - Use of level indicator and inclinometer - Additional site investigation when necessary - Lifting zone to be barricaded before works commence 1) Mild case (to read; less than 10% of total panel excavated volume) – Create an earth bund wall surrounding the affected panel, fill up the bund wall pool with bentonite to increase the bentonite head level. 2) Moderate case (to read; more than 10% of total panel excavated volume, without any visual ground/ platform depression) – Move the grabber and other unnecessary heavy equipment at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. 3) On a case by case basis for a severe case (to read; more than 10% of total panel excavated volume, with obvious visual ground/ platform depression) – Move all machinery away except excavator at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. After 24 hours of backfilling, conduct light cement grout beneath the depressed platform.
*Action Owner
JHZH-LE/SO
Risk Owner
- Steel plate to ensure uniform loading of crane JHZH-PM weight and outrigger - Use of level indicator and inclinometer - Additional site investigation when necessary - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts. - Lifting zone to be barricaded before works commence - Lift load by 300mm, hold for 3 seconds, all personnel 3m away Approved lifting plan, reviewed by LE and approved by PM - Lifting points to be identified and approved - Low speed in lifting and lowering - Material shall be stacked safely and within stacking limit and load - Safety zone established - Signaler to communicate with crane operator
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
Summary of Residual Risk Classes A 0 B 0 C 78 D 15 93
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
The Risk Register is a "live document" and it will be the responsibility of all parties involved in the design, construction and commissioning of the T309 Initial Project and to ensure that all reasonable means and measures are put in place for the effective management of all the safety risks.to continue to identify new risks that arises.
e
Apr-17
Apr-17
Apr-17
Due Date By
Revision K 13 14
7 months
7 months
7 months
Risk Exposure Period
C
C
C
Target Risk Rating
Open
Open
Open
Status
Date: 16/08/2017 15 16
17 Remarks
011
012
100
100
T309/CNSS
T309/CNSS
T309/CDSS/100/012
T309/CDSS/100/011
T309/CDSS/100/010
010
100
T309/CNSS
T309/CDSS/100/009
009
100
T309/CNSS
Construction of ERSS for Utility Diversion
Construction of ERSS for Drain Diversion
Construction of ERSS
Construction of ERSS
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
Instability of temporary works (Utility Diversion ERSS)
Instability of temporary works (Drain Diversion ERSS)
Excessive ground movement of adjacent structures and utilities
Instability of temporary works (ERSS failure)
Hazard
4
5 Hazard Cause
6 Impact
Structural damage/deflection of existing structures - Damage to utilities - Traffic accidents with associated injuries - injuries to public or construction workers associated with ramp distress - Damage to road surfaces - Wall toe movement
- Damage to utilities - Damage to road surfaces
-Higher than expected lateral deflection of ERSS wall during excavations - Unforeseen ground conditions - Inappropriate removal of struts - Over-excavation - Excavation for the utilities laying/trench
- Unforeseen higher than designed surcharge
- Damage to utilities - Damage to road surfaces
- Unforeseen higher than designed surcharge
IV
IV
C
C
C
C
C
C
C
C
C
C
C
Ri
8 Mitigation Measures
- PE to ensure surcharge level to within acceptable loading
- Contractor to produce robust design - Method Statements to ensure safe working methods - Monitoring on site - Gather knowledge from people with relevant experience - Visual inspection
- PE to ensure surcharge level to within acceptable loading
- Method Statements to ensure safe working methods -Follow the PTW (e.g excavate) daily during work - Review design of sheet pile and provide COS. - Only certified and appointed welders are allowed to weld. - Method statement to ensure proper bracing is provided.
- Contractor to produce robust design - Method Statements to ensure safe working methods - Gather knowledge from people with relevant experience
- PE to ensure surcharge level to within acceptable loading
- Contractor to produce robust design - Method Statements to ensure safe working methods -Regular review instrumentation reading - Apply PTW (e.g. excavate) daily before commencement of work
- Calculate amount of bentonite level required
- Robust Contractor's ERSS system - Pre-qualify contractors
- Contractor to produce robust design - Appropriate design sensitivity
- Contractor’s Method Statements - Apply PTW (e.g. excavate) daily before commencement of work '- Emergency Response Planning including Contingency planning e.g. grouting of gaps - Additional site investigation
Page 2 of 17
III
III
III
III
IV
- Injuries to public or construction workers associated with ramp distress - Traffic accidents with associated injuries - Structure Integrity of sheet piles.
- Inappropriate removal of struts - Over-excavation - Excavation for the drain and damage ERSS - Sheet pile obstructed and not able to pile into required depth. -Poor quality weld and design of sheet pile bracing.
IV
III
III
III
IV
IV
IV
I
I
V
V
I
I
S
V
V
F
7 Initial Risk Category Ri
- Structural damage/deflection of existing structures - Damage to utilities - Injuries to public or construction workers associated with ramp distress - Damage to road surfaces - Wall toe movement
Structural damage/deflection of existing structures - damage to utilities - Traffic accidents with associated injuries - injuries to public or construction workers associated with ramp distress - damage to road surfaces - Wall toe movement
Package 1 Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
-Higher than expected lateral deflection of ERSS wall during excavations - Unforeseen ground conditions
- Unforeseen higher than designed surcharge
Higher than expected lateral deflection of ERSS wall during excavations - Unforeseen ground conditions - Inappropriate removal of struts - Over-excavation - Excavation of cut and cover tunnel
- Low bentonite level
Inadequate structural detail connection between - Collapse of temporary works strut, waler to ERSS walls / shafts / excavations - Excessive movement/Collapse of adjacent structures - Injury or fatalities of public and Construction workers - Contractor's ERSS design - Workmanship
- Groundwater drawdown
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
V
V
III
III
III
III
V
V
III
III
III
I
I
V
IV
IV
V
V
I
I
V
V
S
F
D
D
D
D
D
C
C
C
C
C
C
Ri
Residual Risk Category Rr
11
- No stockpiling
JHZH-PM
-Provide ground improvements when necessary JHZH-PM - Requirements to record penetration into competent stratum on installation -High quality site records -Bearing capacity checks for construction equipment - Installation of additional recharge wells & pressure relief wells as contingencies.
- No stockpiling
JHZH-PM
JHZH-SBM
JHZH-SBM
JHZH-CWM
JHZH-CWM
JHZH-PM - instrumentation/monitoring to monitor strut loads. - Daily physical inspection of strutting system
JHZH-CWM
JHZH-SBM
JHZH-PM -Statutory requirement for QP(Sup) to be responsible for supervision of temporary works. -Emergency Response planning including Contingency planning
JHZH-PM
JHZH-SBM
JHZH-SBM
JHZH-CM
JHZH-PM
JHZH-SBM
JHZH-CM
-Normal/ established procedures for staging the JHZH-PM works to protect adjacent utilities -Permit to remove strut system followed to prevent inappropriate removal of struts -Emergency Response planning including Contingency Planning
- No stockpiling
12 *Action Owner
JHZH-PM
JHZH-PM
Risk Owner
- Control of excavation opening to pouring time JHZH-PM
- High quality construction records - Ensure trench stability - Emergency Response planning
- instrumentation/monitoring to monitor strut loads. - Daily physical inspection of strutting system
-Emergency Response planning including Contingency planning -Instrumentation/monitoring to monitor strut loads. - Instrumentation/ real time monitoring - Perform probing and SI (SPT) at regular intervals - Sufficient vibration monitors with appropriate trigger levels to be installed. - Provision of recharge wells. -Provide proper recharging system -Provide proper filter gravel
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
Apr-17
Oct-17
Apr-17
Apr-17
Apr-17
Apr-17
Apr-17
Apr-17
Apr-17
Apr-17
Mar-17
Due Date By
Revision K 13 14
7 months
13 months
7 months
7 months
7 months
7 months
7 months
7 months
7 months
7 months
7 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 16/08/2017 15 16 17 Remarks
T309/CNSS
T309/CNSS
100
100
014
013
N.A
NA
Construction of ERSS (Kingpost) for traffic decking
Construction of ERSS (Drainage diversion)
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
- Instability of temporary works (kingpost for traffic decking - ERSS) -Poor ground condition -Using of poor condition machinery - Noise pollution -Accidental dislodgement of kingpost during driving -Collision of machinery and site people.
Gaps in sheet piles
Hazard
4
5 Hazard Cause
- Poor design lead to undersize kingpost. - Poor workmanship. -Overloading of kingpost with other load not considered in the design. -Toppling of machinery resulting in damage to property. -Injury to surrounding people. -Structure failure of machinery.. -Old machinery and poor maintenance causing disturbance to nearby resident. - Carelessness and inexperience operator. Faulty vibro hammer.
- Supporting structure across the excavation due to lack of diversion corridor
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Collapse of temporary works - Collapse / damage of adjacent structures - damage of permanent works - Injury or fatality of construction workers or public
- Leakage through gap in the walls - Damage to services - Groundwater drawdown - Localized collapse of soil in the gap during excavation
Impact
Package 1
IV
C
C
Ri
8 Mitigation Measures
- Method Statements to ensure kingpost is constructed according to MS -JV engineer / QPS to supervise kinghpost construction work to esnure quality of workmanship. - Design to allow sufficient safety factor for structure interity of kingpost. -Access to be laid with hardcore and compacted. -I beam to be properly stacked and excluded. -Machine to be inspected and certified by AE. -Regular monthly maintenance of machineries - Work zone to be barricaded to prevent unauthorized entry - Used of tag line to control swaying of load. - Only allow skilled operator and experienced lifting team.
- Minimize gaps to minimum size required - Utilities diverted from excavation wherever possible - Instrumentation around gap area when necessary
Page 3 of 17
III
S IV
F III
Initial Risk Category Ri
7
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
V
III
S IV
F IV
D
D
Ri
Residual Risk Category Rr
11 Risk Owner
- During construction phase, ensure RA control measure are implemented - e.g. -Segregation of man and machines -Provide designated pedestrian access for wokers. - Provide adequate warning signs. - Provide proper barricades around bore hole. -Installed sound barrier - Used of silent piler - Refrain from working at night and weekend /PH - Additional sling tied to sheet pile and machinery as extra protection in case grabber gives way. - Access to be laid with hard-core and compacted. - kingpost to be laid on top of hard-core.
JHZH-PM
JHZH-PM - Reinstall sheet piles if there are gaps during installation - Emergency Response Planning including Contingency Planning (e.g. immediate removal works upon sighting of unfavaourable ground/wall movements) 1) Mild case (to read; less than 10% of total panel excavated volume) – Create an earth bund wall surrounding the affected panel, fill up the bund wall pool with bentonite to increase the bentonite head level. 2) Moderate case (to read; more than 10% of total panel excavated volume, without any visual ground/ platform depression) – Move the grabber and other unnecessary heavy equipment at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. 3) On a case by case basis for a severe case (to read; more than 10% of total panel excavated volume, with obvious visual ground/ platform depression) – Move all machinery away except excavator at least 20m away from the affected panel, and backfill the panel with LSS to the ground level by tremie method. After 24 hours of backfilling, conduct light cement grout beneath the depressed platform.
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10 12
JHZH-PM
JHZH-SBM
*Action Owner
Apr-17
Apr-17
Due Date By
Revision K 13 14
7 months
7 months
Risk Exposure Period
C
C
Target Risk Rating
Closed
Open
Status
Date: 16/08/2017 15 16 17 Remarks
102
102
102
102
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
102
102
T309/CNSS
T309/CNSS
102
Diaphragm walling T309/CNSS
007
006
005
004
003
002
001
NA
NA
N.A
T309/CDSS/102/004
T309/CDSS/102/003
T309/CDSS/102/002
T309/CDSS/102/001
Barrette pile test
Welding Works with Welding inverter
Welding Works with Oxygen acetylene and Welding inverter
Diaphragm walling
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
5
-Instability of ERSS wall trenches - Low shear strength in Marine Clay - Loose fills - Possible removal of buried obstructions - Presence of thick peaty layers - High pore water pressure in Marine Clay - Close proximity of adjacent activities such as jet grout piles or casting of nearby trench -Leakage of Bentonite from D wall -Poor Bentonite mixe.
Hazard Cause
6
- Structural damage/deflection of existing structures - Damage to utilities - Traffic accidents with associated injuries - Damage to road surfaces - Collaspe of D wall
Impact
Kentledge collapse
- Failure of jack, jack force is not locked in - Unbalance pressure force in jack
- Testing of D-wall
- Improper maintenance of welding set - Improper connection and damaged cables - welding set not fully protected from wet surfaces - Welding in open space during wet weather condition
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury to public or construction personnel - Delays - Claims -Reputation
IV
IV
IV
B
B
B
C
D
D
D
C
Ri
8 Mitigation Measures
- Contractor shall provide -uniform hydraulic pressure supply to all jacks to main balance force in test - Mechanical safe lock (safety valve) to lock pressure in jack during jack operation in case of pressure loss
- Test set up must get endorsement of PE
- PPE: Welding face shield, apron and gauntlet - Apply PTW (e.g. hot works) daily before commencement of work - Electrical wires to be secured above ground - Daily welding set checklist/ inspection - Certified welders - Reminder in Tool box meeting
- PPE: Welding face shield, apron and gauntlet - Proper housekeeping - Method Statements (e.g. - Close main value & flush hose line after usage) - Apply PTW (e.g. hot works) daily before commencements of works - Daily welding set checklist/ inspection - Fire extinguishers and fire blankets - Reminder in Tool box meeting '- Certified welders - Welding screen to contain sparks
- Specifying waterproofing details @ interface
- Use of adequate plant / equipment for diaphragm wall construction -Apply PTW (e.g. lifting) daily before commencements of works - Cage to be within lifting equipment capacity - Lifting points to be identified, marked and approved
- Emergency Response Planning including Contingency planning e.g. grouting of gaps - Method Statements to ensure safe working methods - Apply PTW (e.g. excavate) daily before commencement of work
- Method Statements to ensure safe working methods - Regular monitoring of critical structures - Stability calculations - Contingency planning e.g. (backfilling) in case of collapse, additional temporary struts - Trial panel - Raised guide walls - Control of bentonite properties (e.g. viscosity, sand content, PH value, density) - Visual inspection - Pre-qualify contractors -Apply PTW (e.g. excavate) daily before commencement of work - Deploy worker to monitor Bentonite level especially over week end.
Page 4 of 17
I
I
I
II
IV
- Injury to public or construction personnel - Delays - Claims - Damage to permanent and temporary works
Fire sparks, fire explosion - Inappropriate welding of struts - Inappropriate welding of Traffic Deck due to Gas leaks, hose damaged, fitting damaged - Inappropriate welding of Noise Barriers - Incompetent welder deployed
Electrocution due to electrical leak
III
V
III
III
V
V
II
S
IV
F
7 Initial Risk Category Ri
- Water ingress - Lost toe stability - Loss of fines - Settlement of structures
- Delay of works -Inappropriate diaphragm wall design - Inappropriate use / misinterpretation of design codes
Package 1 Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
Inadequate water tightness - Poor concrete compaction - Inadequate concrete cover and reduced durability due to honeycomb - Poor workmanship
Diaphragm wall cage too heavy to be lifted
Gaps in retaining systems Provision for services to pass through retaining -Cracking / leakage systems - Structural Damage - Waterproofing problems and associated repair
Excessive ground movement of adjacent structures and utilities
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
III
V
V
V
V
V
I
I
I
I
III
III
V
V
II
S
IV
F
C
C
C
C
D
D
D
C
Ri
Residual Risk Category Rr
11 Risk Owner
12
JHZH-SBM
JHZH-PM
JHZH-PM
- Provide physical barrier (interlocked properly) JHZH-PM and safety signs around test sites - Emergency Response planning including Contingency planning - Proper design of kentledge system - Pre-qualify the subcontractor - Approved Method Statement
JHZH-SBM
JHZH-SBM
JHZH-SO
JHZH-SO
JHZH-SBM
JHZH-PM
JHZH-PM
JHZH-SBM
JHZH-SBM
*Action Owner
JHZH-PM
-Monitoring of overall settlement and differential JHZH-PM settlement of the kentledge - Provide physical barrier (interlocked properly) and safety signs around test sites - Emergency Response planning including Contingency planning - Proper design of kentledge system - Pre-qualify the subcontractor - Approved Method Statement
-No welding work under rain weather/ wet surfaces - Monthly inspection of welding equipment - Apply Safe Work procedure - Electrical neoprene cable double insulated
- Remove flammable items (timber, canvas etc.. )from welding premises - Monthly inspection of welding equipment - Apply Safe Work Procedure - Implement PTW -Hot work
- High quality construction inspection and records - Method Statements to ensure safe working methods - Use of adequate plant/equipment for ERSS wall construction
- Adopt approved lifting plan - Ensure lifting equipment are inspected monthly - Lifting zone to be barricaded before works commence
- Proper post-cast for structure - Specifying waterproofing details @ interface
-Normal/ established procedures for staging the JHZH-PM works to protect adjacent utilities -Regular review instrumentation reading -Permit to remove strut system followed to prevent inappropriate removal of struts -No stockpiling against D-wall -Emergency Response planning including Contingency planning - Never start D-walling without having the cages ready.
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
Mar-17
Mar-17
Oct-17
Oct-17
Oct-17
Oct-17
Oct-17
Oct-17
Due Date By
Revision K 13 14
7 months
7 months
13 months
13 months
13 months
13 months
13 months
13 months
Risk Exposure Period
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 16/08/2017 15 16 17 Remarks
102
102
102
102
T309/CNSS
Pilling T309/CNSS
T309/CNSS
102
T309/CNSS
T309/CNSS
010
009
010
009
008
T309/CDSS/102/004
T309/CDSS/102/001
NA
NA
NA
Piling
D Wall & Excavation
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
5
- Injury and/or fatalities to public and construction personnel
- Wrong instruments specified
C
- Set up the correct trigger value by QP(D).
- Exchange instrumentation design with neighbour contractors to cover whole stretch and interface boundary with T308 & T310.
Instrumentation snd Monitoring Plan for T309
-Instability of ERSS wall trenches - Low shear strength in Marine Clay - Loose fills - Possible removal of buried obstructions - Presence of thick peaty layers - High pore water pressure in Marine Clay - Close proximity of adjacent activities such as jet grout piles or casting of nearby trench
- Design is not checked or back analyzed
- Anomalities or unexpected behaviour is not investigated
- Records of monitoring are falsified
- Site staff do not understand the results of monitoring
- Water ingress - Lost toe Stability - Loss of fines - Settlement of structures
V
D
- Use of adequate plant / equipment for ERSS wall construction
Page 5 of 17
III
- Method Statements to ensure safe working methods - Regular monitoring of critical structures - Stability calculations - Contingency planning e.g. (backfilling) in case of collapse, additional temporary struts - Trial panel - Raised guide walls - Control of bentonite properties (e.g. viscosity, sand content, PH value, density) - Visual inspection - Pre-qualify contractors - Apply PTW (e.g. piling) daily before commencement of work
- Regularly check the machine condition.
- Contractor to ensure site activity planning takes into account the results of the monitoring where necessary.
- QP(S)/QP(D) and Contractor to review monitoring results daily and QP(S)/QP(D) to promptly issue any necessary instruction regards progress of the works.
II
C
- Cage design must get endorsement of PE - Regular inspection of interface with good records - Lifting points to be marked, identified and approved - Engineer to be present to confirm lifting points prior liftng rebar cage. - Ensure moin load radius is taken into consideration when preparing lift plan.
- Damage of instrument
IV
II
B
- Approved PTW (e.g lifting) daily before commencement of work - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be marked, identified and approved - Approved Lifting plan - Material shall be stacked safely and within stacking limit and load
- Apply PTW (e.g. lifting) daily before commencement of work - Monthly inspection of lifting mechanisms - Lifting Supervisor to ensure correct method of usage - Colour coding all lifting mechanisms for validity and serviceability levels - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Lifting points to be marked, identified and approved - Approved Lifting Plan -Weekly boom down inspection with mechanics
- To ensure that Instrumentation and Monitoring Plan is implemented by the Instrumentation Contractor.
- Inadequare review of monitoring
- Structural damage/deflection of existing structures - Damage to utilities - Traffic accidents with associated injuries - Damage to road surfaces
IV
I
B
B
Ri
8 Mitigation Measures
- Frequency of readings is insufficient
- Ground heave / settlement or additional stresses on other structures
- Collapse of adjacent structures
- Insufficient coverage of instruments
- Instruments are faulty or not correctly calibrated
- Collapse of temporary works
IV
I
IV
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
S I
F
7 Initial Risk Category Ri IV
Insufficient monitoring during construction
Package 1 Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities -Crane topple -Tanish reputation
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities - Rebar cage fall off during lifting process. - Crane damanged by swing load e.g. windscreen damaged by lifted rebar cage.
Inadequate water tightness - Poor concrete compaction - Inadequate concrete cover and reduced durability due to honeycomb - Poor workmanship
Excessive ground movement of adjacent structures and utilities
Instability or failure of D Walls due to insufficient monitoring during construction
6 Impact
- Poor design - Poor workmanship - Poor rigging method
- Improper securing of material/ equipment/ cages - Overloading of material/ equipment/ cages - Slight tilt in crane '- Sudden movement of crane boom
Failing of loose material/ equipment/ rebar cages
Instability of rebar cage (including cages for Lshape d-wall panel)
- Breakage of lifting chain - Breakage of lifting sling - Failure of brake motor/gear - Failure of sling/chain buckles and hooks - Overloading of carried loads over limited of design capacity - Unauthorized modification of lifting points -Inadequate rigging method.
Hazard Cause
Failure of lifting mechanism
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
V
IV
V
III
II
II
I
I
V
V
I
S
V
F
D
C
C
C
C
C
Ri
Residual Risk Category Rr
- High quality construction inspection and records - Method Statements to ensure safe working methods
- Regular review Instrumentation reading -Permit to remove strut system followed to prevent inappropriate removal of struts - Emergency Response planning - Review SI report and cross check at site - Provide water relief wells when necessary
- Monitoring value is reviewed by QP(S)/QP(D) as required.
- Set up trigger, alert value
- Instrumentation Plan
- Emergency Response planning including Contingency planning - Adopt 3X3 lifting principles. - Only R/S is allowed to give signal to crane operator.
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10 11
12
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-SBM
JHZH-SBM
JHZH-SBM
JHZH-LE/SO
JHZH-LE/SO
JHZH-PM
JHZH-PM
JHZH-LE/SO
*Action Owner
JHZH-PM
Risk Owner
Mar-17
Mar-17
Mar-23
Mar-17
Oct-17
Oct-17
Due Date By
Revision K 13 14
7 months
7 months
79 months
7 months
13 months
13 months
Risk Exposure Period
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Status
Date: 16/08/2017 15 16 17 Remarks
T309/CNSS
102
011
NA
Bored pile test
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
Kentledge collapse
Hazard
4
5 Hazard Cause
- Failure of jack, jack force is not locked in - Unbalance pressure force in jack
- Bored Pile testing
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
Impact
Package 1
F
IV
IV
B
B
Ri
8 Mitigation Measures
- Contractor shall provide -uniform hydraulic pressure supply to all jacks to main balance force in test - Mechanical safe lock (safety valve) to lock pressure in jack during jack operation in case of pressure loss
- Test set up must get endorsement of PE
Page 6 of 17
I
I
S
Initial Risk Category Ri
7
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
V
V
F
I
I
S
C
C
Ri
Residual Risk Category Rr
11 Risk Owner
- Provide physical barrier (interlocked properly) JHZH-PM and safety signs around test sites - Emergency Response planning including Contingency planning - Proper design of kentledge system - Pre-qualify the subcontractor - Approved Method Statement
-Monitoring of overall settlement and differential JHZH-PM settlement of the kentledge - Provide physical barrier (interlocked properly) and safety signs around test sites Contingency planning - Emergency Response planning - Proper design of kentledge system - Pre-qualify the subcontractor - Approved Method Statement
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10 12
JHZH-SBM
JHZH-SBM
*Action Owner
Mar-17
Mar-17
Due Date By
Revision K 13 14
7 months
7 months
Risk Exposure Period
C
C
Target Risk Rating
Open
Open
Status
Date: 16/08/2017 15 16 17 Remarks
105
105
T309/CNSS
T309/CNSS
003
002
T309/CDSS/105/003
T309/CDSS/105/002
T309/CDSS/105/001
Adjacent Structures or Buildings T309/CNSS 105 001
NA
T309/CDSS/103/001
103
Permanent Works T309/CNSS
012
001
102
T309/CNSS
Construction work nearby to adjacent structures or buildings
Construction work nearby stake holders
Construction work nearby to school
Construction of Permanent Works
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
5
- Breakage of lifting chain - Breakage of lifting sling - Failure of brake motor/gear - Failure of sling/chain buckles and hooks - Overloading of carried loads over limited of design capacity - Unauthorized modification of lifting points
Hazard Cause
- Improper securing of material/ equipment/ cages - Overloading of material/ equipment/ cages - Slight tilt in crane '- Sudden movement of crane boom
Excessive ground and building settlement
Damage / excessive settlement to buildings/structures: - Victoria School Access Bridge - 2-storey semi-detached houses at Kee Sun Ave - St. Andrew's Autism Centre - Elliot at The East Coast - Laguna Park Electrical Substation (Block 5000F) - 2-storey semi-detached houses at Elliot Walk - Opera Estate Canal & Culverts Interface with the public.
Stop or delay school operation. Interface with the public.
- Activation criteria and minimum head are not given
- Ineffectiveness of recharge well layout given in the A/E design '- Some recharge well points will not provide effective recharging due to their locations being far from the buildings to be protected - Filter may not be compatible with the existing ground conditions - Pile test and D-wall test
-Long term settlements - Scheduling of work planning
-Unforeseen ground conditions -Excavation works causing unforeseen settlements -Groundwater drawdown
-Proximity of schools has special implications, -Victoria school is boarding school) - Scheduling of work planning
Excessive settlement - Insufficient ground information available for (Victoria School bridge and design canal structures)
Failing of loose material/ equipment/ rebar cages
Crane topple / Hoisted load - Poor crane footage hit crane - Incompetent lifting team - Poor lift plan - Congested work environment
Failure of lifting mechanism
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Damage to utilities - Damage to property
- Disruption to the site activities during installation of recharge well - Blockage of the filter gravel - Excessive water flow rate provided by the pumping system but little recharging effect
- Claims - Damage to buildings/structures - Complains from the public - Injuring the public
- Damage to buildings/structures - Delays - Claims - Closure of roads - Injuries / fatalities of construction workers and public
-Noise disruption to schools -Pick up and drop off times Damaged - Complains from the public - Injuring the public
- Serviceability issue with the bridge
IV
IV
V
V
III
IV
IV
C
C
C
C
C
C
B
B
B
Ri
8 Mitigation Measures
-Activation criteria and minimum have been designed and indicated (Zone 1 to 3)
- Contractor's consultant has designed the recharging system, modified the configuration - Design of filter gravel has been provided
- Instrumentation / Monitoring - Reduce work inteface with public during peak hours
- Contractor’s Method Statements - instrumentation / monitoring - Real time monitoring - Specification of instrumentation and monitoring requirements by AE consultant - Strengthening and temporary propping when necessary - Additional site investigation
- Contingency planning, inspection and monitoring - Method Statements - Additional site supervision (e.g. traffic marshal) - Reduce work inteface with public during peak hours
- Provision of additional boreholes for bridge and canal design
- Approved PTW (e.g lifting) daily before commencement of work - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be marked, identified and approved - Approved Lifting plan - Material shall be stacked safely and within stacking limit and load
- Design and COS crane access - No Overloading at all times - Proper maintenance of crane - Only competent lifting team is allowed - Implemet Permit to lift - Include both Max. and Min load radius - Do not conduct lifting in congested work environment. - Provide exclusion zone and Provide warning signs. - Provide sufficient tag lines
- Apply PTW (e.g. lifting) daily before commencement of work - Monthly inspection of lifting mechanisms - Lifting Supervisor to ensure correct method of usage - Colour coding all lifting mechanisms for validity and serviceability levels - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Lifting points to be marked, identified and approved - Approved Lifting Plan
Page 7 of 17
III
III
I
I
IV
III
I
I
IV
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
I
S
IV
F
7 Initial Risk Category Ri
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
Impact
Package 1 Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
IV
IV
V
V
III
IV
III
III
I
I
IV
III
I
I
V
V
I
S
V
F
C
C
C
C
C
C
C
C
C
Ri
Residual Risk Category Rr
11
- Provide proper recharging system - Provide proper filter gravel - Instrumentation/ Monitoring of settlement - Additional Site investigation
- Emergency Response planning - Provide proper recharging system - Provide proper filter gravel - Instrumentation/ Monitoring of settlement - Additional Site investigation - Control of bentonite pressures
- Perform ground improvements when necessary
-Emergency Response planning including Contingency planning -Instrumentation/monitoring to monitor strut loads. - Instrumentation/ real time monitoring - Sufficient vibration monitors with appropriate trigger levels to be installed. - Provision of recharge wells. -Provide proper recharging system -Provide proper filter gravel
12
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-SBM
JHZH-SBM
JHZH-SBM
JHZH-SBM
JHZH-SBM
JHZH-SBM
JHZH-LE/SO
JHZH-LE/SO
JHZH-PM
JHZH-PM
JHZH-LE/SO
*Action Owner
JHZH-PM
Risk Owner
JHZH-PM - Proper planning and traffic control - Provide soundproof wall - Close communication with the school and be cognisant of critical times in the school calendar
- Emergency Response planning - Insturmentation and monitoring of settlement - Additional Site investigation when necessary
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
May-20
Oct-17
Oct-17
Oct-17
Due Date By
Revision K 13 14
79 months
79 months
79 months
79 months
79 months
45 months
13 months
13 months
13 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 16/08/2017 15 16 17 Remarks
105
105
T309/ CNSS
T309 / CNSS
005
004
NA
N.A
Traffic Diversion for Option 1C (Laguna Park)
Traffic Diversion around Victoria School
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
5
'- Lack of communication between LTA, main contractors, and sub contractors.
Motorist confusion
Noise
Complaints from stakeholder
Traffic jam / congestion
'- Lack of coordination between JHZHJV and subbies operation team
- Poor planning
-Public confusion
Workers hit by traffic
- Congested road leading to Victoria school - Construction activities in front of Victoria school - Heavy machinery stationed along Siglap Link - Heavy traffic from new egress to Marine Parade Road - Pedestrians jaywalking -Inadequate signage and poor traffic control measures -Unsafe traffic layout -Failure to carryout trial trench for UG services -Failure to barricade work area and provide banksman to guide vehicular movement on site -Failure to equip with proper PPE
Hazard Cause
Risk associated with Traffic Diversion -Unsafe traffic conditions, accident hot spot and vehicles crashing into site -Damaged to UG services -Noise and dust pollution
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Collision of construction and public vehicles - Fatality - Delays - Claims - Injury to public or construction personnel - Tarbish reputation
- Collision of construction and public vehicles - Delays - Claims - Injury to public or construction personnel
Impact
Package 1
C
C
Ri
8 Mitigation Measures
-Clear and advance notification to all stake holders - Sufficient and clear notification signage to motorist – e.g. VMS - Coordinate closely with relevant authority e.g. LTA - Organise “work session” to brief all relevant parties - Briefing session to be conducted with all relevant parties on personnel on process of diversion. - Apply for lane closure - Close lane in accordance with COP Traffic control - Put up sufficient advance warning signage - Brief TCP to all relevant person prior work start - Carry out traffic diversion off peak hours. - Inform NEA about late traffic diversion work Potential noise issue - Ensure workers put on reflective vest. - Traffic controllers to equipped with light batons
- Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan '- Guard rail or rigid barrier to be setup and interlocked properly - designated path for access by pedestrians '- Code of Practise of Traffic Control and Work Zone -Approval of temporary traffic diversion layout by TM -Traffic layout and signage to follow TCP -Submit PSR (road) for clearance -Ensure good visibility of signage --Apply permit to dig prior to start work -Conduct RA/ SWP briefing
Page 8 of 17
II
II
IV
S
F IV
Initial Risk Category Ri
7
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
II
II
V
S
F IV
C
C
Ri
Residual Risk Category Rr
11 Risk Owner
- Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan '- Guard rail or rigid barrier to be setup and interlocked properly - designated path for access by pedestrians '- Code of Practise of Traffic Control and Work Zone -Approval of temporary traffic diversion layout by TM -Traffic layout and signage to follow TCP -Submit PSR (road) for clearance -Ensure good visibility of signage --Apply permit to dig prior to start work -Conduct RA/ SWP briefing
JHZH-PM
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly when necessary - Placement of cone or barrier during diversion without reduction in lane width -Desk top study of all utilities and carryout appropriate trial trench -Barricade work area and provide proper signage and warning to motorist and pedestrian. -Lane closure to avoid peak hours, applicable hours is 9:30-16:30 for daytime and 16:30-09:30 for night time closure -Flow chart indicating the flow of instruction enabling the lorry truck to enter the lane closure work area during soil removal or delivery of materials.
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10 12
JHZH-PM
JHZH-SBM
*Action Owner
Jul-17
Mar-23
Due Date By
Revision K 13 14
10 months
79 months
Risk Exposure Period
C
C
Target Risk Rating
Closed
Open
Status
Date: 16/08/2017 15 16 17
Further improvemen ts will be discuss in PSR roadworks
Remarks
106
106
106
106
106
106
106
109
Existing Utilities T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
Existing Conditions T309/CNSS
006
006
005
004
004
003
002
001
T309/CDSS/109/006
N.A
N.A
N.A
N.A
T309/CDSS/106/003
T309/CDSS/106/002
T309/CDSS/106/001
Excavation
Excavation for Utility Diversion Works
Excavation for Utility Diversion Works
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
Seawall obstruction
Damage to HV cable
Damage to LV cable
Damage to Water pipe
Limited Work Areas
Damage to utilities
Damage to utilities and disruption to services
Damage to submarine cable
Hazard
4
5 Hazard Cause
- Injury or fatalities of public and construction workers Unplanned excavation -Insufficient marking on site -Failure to conduct detection test
Abandon seawall
Accidental damage - Excavator hitting protection pipe
Accidental damage - Excavator hitting protection pipe
Accidental damage - Excavator hitting protection pipe
- Damage to the equipment used - Deep foundation and diaphragm wall are not constructed properly
- Voltage drop
- Property damage -
- Disruption to water supply - Low pressure water supply
- Work areas too restricted or efficient workings - Schedule delays - Work areas require significant temporary - Unsafe environment for construction personnel works for their establishment traffic congestion
-Diversion and support of utilities across excavation: - Water pipe - Power Grid cables - SP Telecom cables - Starhub cables
6 Impact
Disturbance to public
-Non coordinated inter-contract utility diversion, - Delay - Remote disruption -Unforeseen obstructions - Missing information from utilities agencies - Insufficient trial trenches
Insufficient information about cable location
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Package 1
IV
III
III
III
D
C
C
C
C
C
C
C
Ri
8 Mitigation Measures
- Additional trial trench and site investigation
- Bracket to be fabricated and installed according to design and use of correct material - Use of heavy duty flexible hose to protect cable - Additional cables to create slag and prevent tension '- Ensure team is at work zone within 1hour of issues - clear demarcation of work zone - Apply Utilities service damage plan and utilities preventation plan - Positive identification of utiltiies
- Bracket to be fabricated and installed according to design and use of correct material - Use of heavy duty flexible hose to protect cable - Additional cables to create slag and prevent tension '- Ensure team is at work zone within 1hour of issues - clear demarcation of work zone - Apply Utilities service damage plan and utilities preventation plan - Serve affect resident notice during water diversion works - Positive identification of utiltiies
- Bracket to be fabricated and installed according to design and use of correct material - Ensure team is at work zone within 1hour of issues - clear demarcation of work zone - Apply Utilities service damage plan and utilities preventation plan - Supply of water bag/ water tank during water disruption by PUB '- PUB Technician to supervise valve closing operation - Elbow joints to be haunched - Positive identification of utiltiies
- Buidling temporary decking for efficient road/land use - Detailed SHE procedure to enforce safety
- Ongoing co-ordination with relevant utility companies - Contractor's Method Statement - Approved NCE - Pre-qualify Contractors - Apply PTW daily before commencement of work -Thorough study of utilities drawings -Cable detections by qualified LCDW -Provide clear utilities marking on site -Provide A3 size drawing of utility plan -Apply permit to dig -Barricade work area while trenching -Contact relevant utility agency for any presence of unidentified utility -Always treat utility as `live’ if encountered -Only manual digging allowed for trial trench -Full time supervision during trial trench -No mechanical excavation within 3 meters from live utilities. - Only manual excavation allowed for trial trench digging. - Brief utilities plan in language understood by the workmen.
- Method Statements - Additional site investigation - Approved NCE
- To divert submarine cable away from the station box
Page 9 of 17
IV
III
III
III
III
I
V
III
III
I
S
III
V
F
Initial Risk Category Ri
7
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
III
IV
IV
IV
III
III
IV
IV
III
I
V
IV
III
I
S
IV
V
F
D
C
C
C
C
C
C
C
Ri
Residual Risk Category Rr
11
12
- Cross check at site - Laise with related authority about the information of seawall
-Close communication with utilities agencies -Identify clear markers for utilities locations lines and brief staffs, workers and subcontractors -Emergency Response planning including Contingency planning
-Close communication with utilities agencies -Identify clear markers for utilities locations lines and brief staffs, workers and subcontractors -Emergency Response planning including Contingency planning
-Close communication with utilities agencies -Identify clear markers for utilities locations lines and brief staffs, workers and subcontractors -Emergency Response planning including Contingency planning
- Efficient site utilization plan for each different working stage - Hire a professional road safety review learn and checking when necessary
JHZH-UE
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-UE
JHZH-UE
JHZH-PM
JHZH-PM
JHZH-UE
JHZH-UE
-Utility cable detection and trial trench should be JHZH-PM carried out to identify the alignment -Diversion out of the structure footprint -Emergency Response planning including Contingency planning -Close communication with utilities agencies -Cable detection -Properly mark the location of utilities and briefing site staffs, workers and sub-contractors -If unclear with the finding of services after reaching the 2m limit, conduct further detection to determine the presence of any services below. -Dimensions and depth of Trial Trenches recorded by Project Survey Team for As Build information Photo records of trial trench including any utility discovered are recorded
JHZH-PM
JHZH-UE
-Design protective measures and temporary support scheme for utilities across excavation -Close communication with inter-contract and utilities agencies -Identify clear markers for utilities locations lines and brief staffs, workers and subcontractors -Cable detection -Emergency Response planning including Contingency planning
JHZH-PM
*Action Owner
JHZH-UE
Risk Owner
- Divert submarine cable away from the station JHZH-PM box and identify the clearly marker
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
Jan-17
Dec-18
Dec-18
Dec-18
Oct-17
Oct-17
Oct-17
Oct-17
Due Date By
Revision K 13 14
5 months
27 months
27 months
27 months
13 months
13 months
13 months
13 months
Risk Exposure Period
C
C
C
C
C
C
C
C
Target Risk Rating
Closed
Open
Open
Open
Open
Open
Open
Open
Status
Date: 16/08/2017 15 16 17 Remarks
T309/CDSS/110/005
Future developments or Addition & Alteration works 112 001 T309/CNSS T309/CDSS/112/001
005
T309/CNSS
110
T309/CDSS/110/004
Interface with Adjacent Contracts T309/CNSS 110 004
Future developments or Addition & Alteration works
Excavation
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
Clashes between railway structures and future underground infrastructure works and/or future above ground developments
Interfacing with adjacent contracts
Incompatible Interfacing with adjacent contracts
Hazard
4
5 Hazard Cause
6 Impact
- Unforeseen higher than designed surcharge
- Damage to utilities - Damage to road surfaces - Damage to property
-Proposals for future underground infrastructure - Incompatible construction techniques and developments in direct conflict with alignment and stations - Delay of works - Unaware of future infrastructure and developments proposals
Effect of T310 TBM tunnels on D-Walls subway - Excessive ground movement near Entrance C - Movement to adjacent structures
- Excessive ground movement Unappropriate or non-workable connection design at interface of bored tunnels and station - Movement to adjacent structures - Groundwater drawdown end walls - Waterproofing problem and associated repairs
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Package 1
V
V
V
V
F
C
C
C
C
Ri
8 Mitigation Measures
- PE to ensure surcharge level to within acceptable loading
- Contractor to review Development Interface Report in detail - Coordination meetings between interfacing designers - Coordination between all parties (Client, Contractor, designers)
- Coordination meetings between interfacing contractors and designers to be managed by Contractors - Construction Interface report by Contractor - Coordination between all parties (Client, Contractor, Designers)
- Coordination meetings between interfacing contractors - Construction Interface report by Contractor - Coordination between all parties (Client, Contractor, Designers) - Specifying waterproofing details @ interface
Page 10 of 17
II
II
I
I
S
Initial Risk Category Ri
7
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
V
V
V
V
F
II
II
I
I
S
C
C
C
C
Ri
Residual Risk Category Rr
- No stockpiling
- Close coordination with related parties
- Instrumentation and monitoring - Close coordination
- Emergency Response planning e.g. grouting - Methods Statement - Close coordination
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10 11
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
Risk Owner
12
JHZH-PM
JHZH-PM
JHZH-CM
JHZH-CM
*Action Owner
May-20
May-20
May-20
May-20
Due Date By
Revision K 13 14
45 months
45 months
45 months
45 months
Risk Exposure Period
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Status
Date: 16/08/2017 15 16 17 Remarks
118
Ground Improvements T309/CNSS 118
T309/CNSS
Construction Methodology T309/CNSS 117
001
9
009
T309/CDSS/118/001
T309/CDSS/117/010
T309/CDSS/117/009
Jet grouting
"L" shape D- wall cage installation - Tandam Lift
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
Ground improvement failure
●Collision of cranes ●Crane collapse or failure ●Toppling of crane ●Crane hit surrounding structures, eg silo ●Hoisted material hit crane ●D wall stich snap ●Hoisted material hit crane
●Crane collapse or failure ●Toppling of crane ●Crane hit surrounding structures, eg silo ●Hoisted material hit crane
Hazard
4
5 Hazard Cause
Inappropriate jet grouting methods
-Overloading of lifting equipment -Failure to observe safe work procedures -- Instability of working platform. - Failure of loose material equipment/ rebar cages - Lack of communication - Inadequate supervision and control - Unplanned and poor control of crane movement - Substandard lift plan
-Overloading of lifting equipment -Failure to observe safe work procedures -- Instability of working platform. - Failure of loose material equipment/ rebar cages - Lack of communication - Inadequate supervision and control - Unplanned and poor control of crane movement - Substandard lift plan
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Collapse of ground - Injury or fatality of construction workers and public - Waterproofing problems and associated repair - Damage to buildings - Delay of works - Movements of adjacent structures
-Injury to site staff -Delay to construction -Damage to property
-Injury to site staff -Delay to construction -Damage to property
Impact
Package 1
V
IV
IV
F
C
C
C
Ri
8 Mitigation Measures
- Contractor to produce robust design - Jet grouting trials - Specifying waterproofing details @ interface - Instrumentation / Monitoring e.g. LBs to monitor building movement, LGs for ground movement and IW or XYZ for ERSS. - Additional site investigation and geophysics
- Provide support plates for firm support - Apply PTW (e.g. lifting) daily before commencement of work - Full extension of outrigger prior to lifting - Approved Lifting Permit - No workers shall be allowed to stand below suspended loads - Lifting Supervisor to ensure correct method of usage - Approved lifting plan (e.g. full extension of outrigger, approved and proper use of slings) - Lifting points to be marked, identified and approved -Safety zone established -Tag line with coloured flag to be installed along hoarding to warn operator from crossing the line when turning during lifting -Tag line with coloured flag to be installed at the top of bentonite tank to warn crane operator and signal man to guide operator during crane movement. -Bentonite tanks near to Dwall will only be erected after the completion of Dwall. -To include min load radius in lift plan.
- Provide support plates for firm support - Apply PTW (e.g. lifting) daily before commencement of work - Full extension of outrigger prior to lifting - Approved Lifting Permit - No workers shall be allowed to stand below suspended loads - Lifting Supervisor to ensure correct method of usage - Approved lifting plan (e.g. full extension of outrigger, approved and proper use of slings) - Lifting points to be marked, identified and approved -Safety zone established -Tag line with coloured flag to be installed along hoarding to warn operator from crossing the line when turning during lifting -Tag line with coloured flag to be installed at the top of bentonite tank to warn crane operator and signal man to guide operator during crane movement. -Bentonite tanks near to Dwall will only be erected after the completion of Dwall. -To include min load radius in lift plan.
Page 11 of 17
II
II
II
S
Initial Risk Category Ri
7
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
V
V
V
F
II
II
II
S
C
C
C
Ri
Residual Risk Category Rr
11
JHZH-PM
JHZH-PM
Risk Owner
- High quality construction records and material JHZH-PM testing - Methods statement - Pre-qualify contractors - Regular review instrumentation reading of inclinometers and ground settlement markers in trial test and feedback main works - Emergency Response Planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts.
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Reminder in tool box meeting - Lifting zone to be barricaded before works commence -Provide adequate hardstanding /firm working platform -Put in place the lifting permit system and display the relevant details on site. -Ensure no overloading of crane -Signaler to communicate with crane operator -Lift load by 300mm, hold for 3 seconds, all personnel 3m away -Approved lifting plan, reviewed by LE and approved by PM -Lifting operation supervised by lifting supervisor -Banksmen to guide crawler crane movement, ensuring no tracking over drain, trench or uneven ground. -Lifting points to be identified and approved -Low speed in lifting and lowering -Material shall be stacked safely and within stacking limit and load -Authorization of all machineries movement from point to point -Establish a permit to move system for heavy machineries -A lockout /tagout system during maintenance and breakdown period of mchineries -Maincon to control all machineries movement on site with daily discussion during coordination meeting -Setting up a security management plan that involved site security to be aware of the delivery of materials and ensuring no material delivery during lunch time and peak hour
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Reminder in tool box meeting - Lifting zone to be barricaded before works commence -Provide adequate hardstanding /firm working platform -Put in place the lifting permit system and display the relevant details on site. -Ensure no overloading of crane -Signaler to communicate with crane operator -Lift load by 300mm, hold for 3 seconds, all personnel 3m away -Approved lifting plan, reviewed by LE and approved by PM -Lifting operation supervised by lifting supervisor -Banksmen to guide crawler crane movement, ensuring no tracking over drain, trench or uneven ground. -Lifting points to be identified and approved -Low speed in lifting and lowering -Material shall be stacked safely and within stacking limit and load -Authorization of all machineries movement from point to point -Establish a permit to move system for heavy machineries -A lockout /tagout system during maintenance and breakdown period of mchineries -Maincon to control all machineries movement on site with daily discussion during coordination meeting -Setting up a security management plan that involved site security to be aware of the delivery of materials and ensuring no material delivery during lunch time and peak hour
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10 12
JHZH-SBM
JHZH-LE
JHZH-LE/SO
*Action Owner
Jul-17
May-20
May-20
Due Date By
Revision K 13 14
10 months
45 months
45 months
Risk Exposure Period
C
C
C
Target Risk Rating
Open
Open
Open
Status
Date: 16/08/2017 15 16 17 Remarks
118
121
T309/CNSS
Fire and Explosions T309/CNSS
001
002
T309/CDSS/121/001
T309/CDSS/118/002
Construction works involving flammable or explosive materials
Construction works for ERSS or permanent walls
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
5 Hazard Cause
Fire or explosion during construction
-Encounter flammable materials - Breakage of buried services - Ignition of methane from peat layers - Contaminant gas - War relics/unexploded ordnances - Heavy vehicles carrying flammable materials may be driven into the construction site
Excessive deflection of Insufficient ground improvement / treatment ERSS or permanent walls works
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Injury or fatality of public or construction workers - Damage to existing structures and services
- Flooding of excavation - Collapse of temporary works and adjacent structures - Injury of public or construction personnel - Disruption of essential services - Delays - Claims
Impact
Package 1
C
C
Ri
8 Mitigation Measures
- Provision of appropriate plant - additional site investigation and geophysics when necessary - Gather knowledge from people with relevant experience - Apply PTW (e.g hot works) daily before commencement of work - Safety Datasheet and Warning signs and Emergency contacts on display - Reporting to Safety and Security Department
- Contractor to produce robust Design - Method Statements to ensure safe working methods - Robust ERSS Design - instrumentation / monitoring e.g. LBs to monitor building movement, LGs for ground movement and IW or XYZ for ERSS.
Page 12 of 17
I
II
V
V
S
F
Initial Risk Category Ri
7
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
I
II
V
V
S
F
C
C
Ri
Residual Risk Category Rr
- Proper and independent flammable materials storage and management - Emergency Response Planning including Contingency planning e.g. quick evacuation route - Permit to carry hazardous material
- Provide efficient geometric design and the road level to mitigate flooding - Witness the instrumentation reading - Regular review and analyse instrumentation reading - Emergency Response planning include Contingency planning, inspection and monitoring
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10 11
JHZH-PM
JHZH-PM
Risk Owner
12
JHZH-SO
JHZH-SBM
*Action Owner
Mar-23
Jan-18
Due Date By
Revision K 13 14
79 months
16 months
Risk Exposure Period
C
C
Target Risk Rating
Open
Open
Status
Date: 16/08/2017 15 16 17 Remarks
122
994
994
Flooding T309/CNSS
Site set up T309/CNSS
T309/CNSS
002
001
002
NA
NA
T309/CDSS/122/001
4
5 Hazard Cause
MEWP topple
Hit by fallen object
Fall from height
Noise Barrier structural failure
6
- Collapse of temporary works - Excessive movement / Collapse of adjacent structures - Injury or fatalities of public and construction workers
-Interrupted construction, -Delays, -Environmental pollution
Impact
-Damage to own and public properties (Claims) - Injury or fatalities of public and construction workers
Old machinery and poor maintenance causing disturbance to nearby resident
Installation of sheet piles Noise pollution (foundation support for sound barrier)
Installation of sheet piles Accidental dislodgement of -Carelessness and inexperience operator. (foundation support for sheet pile during driving - Faulty vibro hammer sound barrier)
Structure failure of machinery
Installation of sheet piles Using of poor condition (foundation support for machinery sound barrier)
-Serious injury to worker and property. -Stop work causing delay
-Disturbance to neighbouring resident -Hearing injury to workers
-Low productivity Job delay and behind schedule -Cost implication
-Serious injury to worker and property. -Stop work causing delay
Installation of sheet piles Poor ground condition (foundation support for sound barrier)
-Toppling of machinery resulting in damage to property. -Injury to surrounding people.
-Serious injury to worker and property. -Stop work causing delay -Damage to machineries
Installation of sheet Collision of machinery and piles Constraint of work area (foundation support for site people. sound barrier)
-Damage to underground services -Disruption to stakeholders Location of utilities not reflected in utility drawing -Penalty charges by authority -Stop work order by authority -Delay to work schedule
-Failure to provide fall protection provision - Failure to provide control - Poor footage - Over loading of MEWP
-
- Collapse of temporary works - Incorrect information on adjacent structures - Not identifying the behaviour and response of - Damage to own and public properties (Claims) - Injury or fatalities of public and construction the ground and adjacent structures workers
-Flawed design of temporary works - Inappropriate use / misinterpretation of design codes - Lack of understanding of design software and output - Temporary works design is incompatible with adjacent structures
Flooding from the Opera -Damage the canal or foundation during Estate Canal at Siglap Link construction, -Extreme flooding event; -Tidal fluctuation -Structural problem of the canal
Hazard
Installation of sheet piles Damage to utilities (foundation support for sound barrier)
Setting up of Noise Barriers
Construction works near Opera East Canal
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Package 1
IV
IV
IV
IV
IV
IV
B
C
C
B
B
C
C
C
C
C
Ri
8 Mitigation Measures
V
V
-Additional sling tied to sheetpile and machinery as extra protection in case grabber gives way -Ensure sheetpile is clamped tightly between the grabber jaws before hoisting up vertically for installation
V
V
V
V
I
II
II
I
I
II
II
II
V
V
II
I
S
V
V
F
C
C
C
C
C
C
C
C
C
C
Ri
Residual Risk Category Rr
11 Risk Owner
12
Daily pre operation check on grabber by operator before start of work
Regular maintenance regime in place
LOTO system applied during maintenance period
-Ground preparation completed with the issuance of COS from PE -Ensure no overloading of machinery (Load kept at 75% of SWL
Apply for permit to move for machinery movement from point to point
Cable detection by LEW
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-PM
JHZH-SBM
JHZH-SBM
JHZH-SBM
JHZH-SBM
JHZH-SBM
JHZH-SBM
JHZH-SBM
JHZH-SBM
- Strengthening of noise barrier when necessary JHZH-PM - Additional site investigations and localized ground improvement when necessary - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts. - Approved Method Statement
-Enveloped MEWP work platform with scaffold JHZH-PM netting to contain material. Limit max. 2 person on MEWP. Max. weight 120kg. Firm and compacted ground for MEWP access. Provide adequate exclusion zone and signage. Provide banksman to ensure no authorised entry in to work zone.
JHZH-SBM
JHZH-SBM/ ECO
*Action Owner
JHZH-PM - Engage experienced and competent consultant to perform the design - Engage experienced and competent contractor - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts. - Approved Method Statement
JHZH-PM - Provide efficient geometric design and the road level to mitigate flooding -Awareness of climatic conditions -Regular monitor of water level in Opera estate Canal -Emergency Response planning including Contingency planning
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
-Installed sound barrier. -Used of silent piler. -Refrain from working at night and weekend/PH
-Machine to be inspected and certified by AE. -Regular monthly maintenance of machineries
-Access to be laid with hardcore and compacted. -Steelplate to be laid on top of hardcore. -Movement of machinery must be guided by benchemen
-Work zone to be barricaded to prevent unauthorized entry -Used of tag line to control swaying of load - Employed skilled operator and experienced lifting team
-Carry out cable detection and trial trench along the path of sheet piles. -Apply permit to dig prior to work start.
- Provision of Fall Protection Plan. - Establish PTW-Height system. - Provide proper access. - Provide adequate work platform. - Licensed MEWP operator. - Familiarisation briefing prior appointment.
- Perform further structural or geotechnical investigations e.g. coring, trial trenching - Apply PTW (e.g. welding) daily before commencement of work - Certified welder
- Sensitivity of design input parameters - Pre-qualify contractor - Apply PTW (e.g. welding) daily before commencement of work - Certified welder
- Method Statements - Additional site investigation -Confirmation with LTA on any specific flood protection measures required during construction
Page 13 of 17
I
II
II
I
I
II
II
II
IV
IV
II
I
S
IV
V
F
Initial Risk Category Ri
7
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Due Date By
Revision K 13 14
79 months
79 months
79 months
79 months
79 months
79 months
79 months
79 months
79 months
79 months
Risk Exposure Period
C
C
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 16/08/2017 15 16 17 Remarks
994
996
996
997
T309/CNSS
Vector Management T309/CNSS
T309/CNSS
Mobilization T309/CNSS
001
002
001
003
NA
NA
NA
NA
Traffic Diversion
Workers working on site
Setting up of Hoarding
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
5 Hazard Cause
Risk associated with Traffic Diversion -Unsafe traffic conditions, accident hot spot and vehicles crashing into site -Damaged to UG services -Noise and dust pollution
Transmission of Dengue and Zika
Mosquito bites on construction/ public personnel
6
- Collapse of temporary works - Excessive movement / Collapse of adjacent structures - Injury or fatalities of public and construction workers
Impact
- Transfer (delivery and lifting) material, plant and manpower -Inadequate signage and poor traffic control measures -Unsafe traffic layout -Failure to carryout trial trench for UG services -Failure to barricade work area and provide banksman to guide vehicular movement on site -Failure to equip with proper PPE
- Mosquito breeding - Mosquito bites
- Mosquito breeding - Mosquito bites
- Traffic jam - Injury to public or construction personnel - Claims - Delays
- Injury or fatality of public or construction personnel - Claims - Delays
- Injury to public or construction personnel - Claims - Delays
- Collapse of temporary works - Incorrect information on adjacent structures - Not identifying the behaviour and response of - Damage to own and public properties (Claims) the ground and adjacent structures
Hoarding structural failure -Flawed design of temporary works - Inappropriate use / misinterpretation of design codes - Lack of understanding of design software and output - Temporary works design is incompatible with adjacent structures
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Package 1
F
IV
IV
IV
IV
IV
C
B
B
C
C
Ri
8 Mitigation Measures
- Code of Practise of Traffic Control and Work Zone - Use of barrier and/or gate guards for exit/entrances to site -Approval of temporary traffic diversion layout by TM -Traffic layout and signage to follow TCP -Submit PSR (road) for clearance -Ensure good visibility of signage --Apply permit to dig prior to start work -Conduct RA/ SWP briefing -Desk top study of all utilities and carryout appropriate trial trench -Barricade work area and provide proper signage and warning to motorist and pedestrian. -Lane closure to avoid peak hours, applicable hours is 9:30-16:30 for daytime and 16:30-09:30 for night time closure
- Pest control '- Emergency Response planning - Vector control management - Additional supervision - Oiling in stagnant water and other respective areas - Provision of insect repellents to site staff
- Pest control - Emergency Response planning - Vector control Management - Additional supervision - Oiling in stagnant water and other respective areas - Provision of insect repellents to site staff
- Perform further structural or geotechnical investigations e.g. coring, trial trenching
- Sensitivity of design input parameters - Engage experienced and competent consultant to do the design - Engage experienced and competent contractor - Pre-qualify contractor
Page 14 of 17
II
I
I
II
II
S
Initial Risk Category Ri
7
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
IV
V
V
V
V
F
II
I
I
II
II
S
C
C
C
C
C
Ri
Residual Risk Category Rr
11 Risk Owner
JHZH-PM
JHZH-PM
JHZH-PM - Properly traffic control and signages with qualified traffic marshal - Clearly defined zones for accessible pathways and restricted areas - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Emergency Response planning including Contingency planning, inspection and monitoring - Lifting zone to be barricaded before works commence - Placement of cone or barrier during diversion without reduction in lane width -Flow chart indicating the flow of instruction enabling the lorry truck to enter the lane closure work area during soil removal or delivery of materials.
- Regular inspection of site to identify and eliminate breeding sites - Misting
- Regular inspection of site to identify and eliminate breeding sites - Misting
JHZH-PM - Strengthening of hoarding when necessary - Additional site investigations and localized ground improvement when necessary - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts.
JHZH-PM - Engage experienced and competent consultant to perform the design - Engage experienced and competent contractor - Emergency Response planning including Contingency planning e.g. stop all excavation, ensure safe escape route for workers, additional temporary struts.
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10 12
JHZH-SBM
JHZH-SBM/ECO
JHZH-SBM/ECO
JHZH-PM
JHZH-PM
*Action Owner
Mar-23
Mar-23
Mar-23
Mar-23
Mar-23
Due Date By
Revision K 13 14
79 months
79 months
79 months
79 months
79 months
Risk Exposure Period
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Closed
Closed
Status
Date: 16/08/2017 15 16 17 Remarks
T309/CNSS
T309/CNSS
997
997
3
002
N.A
NA
Lifting with crane
Lifting with crane
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
5
- Breakage of lifting chain - Breakage of lifting sling - Failure of brake motor/gear - Failure of sling/chain buckles and hooks - Overloading of carried loads over limited of design capacity - Unauthorized modification of lifting points
Hazard Cause
Sharp edge material being - Site personnel cut by sharp material during lifted/ lowered/ handled handling
- Improper securing of material/ equipment Failing of loose material/ equipment including heavy - Overloading of material/ equipment - Slight tilt in crane mchineries / equipment '- Sudden movement of crane boom - Early release of jack base / hydraulic jack out riggers
Crane topple / Hoisted load - Poor crane footage hit crane - Incompetent lifting team - Poor lift plan - Congested work environment
Failure of lifting mechanism
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title: 6
- Injury and fatality to construction personnel - Delays - Claims
II
IV
C
B
B
B
Ri
8 Mitigation Measures
- Store all sharp material into material cages when possible - Pack/ organize sharp material - Use of PPE (e.g appropriate safety gloves, long sleeves, helmet and safety boots and glasses)
- Approved PTW (e.g lifting) daily before commencement of work - Lifting Supervisor to ensure correct method of usage - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Avoid loading and unloading near edge of properties or access walkways - Low speed in lifting and lowering of material '- Signaller to communicate with crane operator during lifting and lowering operation - Lifting points to be marked, identified and approved - Approved Lifting plan - Material shall be stacked safely and within stacking limit and load - Always secure materilas/heavy machineries on lorry bed before release out riggers / hydraulic jack. - Do not stay in libne of fire at all times.
- Design and COS crane access - No Overloading at all times - Proper mainyenance of crane - Only competent lifting team is allowed - Implemet Permit to lift - Include both Max. and Min load radius - Do not conduct lifting in congested work environment. - Provide exclusion zone and Provide warning signs. - Provide sufficient tag lines
- Apply PTW (e.g. lifting) daily before commencement of work - Monthly inspection of lifting mechanisms - Lifting Supervisor to ensure correct method of usage - Colour coding all lifting mechanisms for validity and serviceability levels - Safety zone to establish and marked - Clear signages place to warn entry of unauthorized personnel - Lifting points to be identified and approved - Approved Lifting Plan
Page 15 of 17
I
IV
I
IV
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
I
S
IV
F
7 Initial Risk Category Ri
- Injury and fatality to public or construction personnel - Delays - Claims - Damage adjacent structures and utilities
Impact
Package 1 Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
I
II
IV
I
V
V
I
S
V
F
C
C
C
C
Ri
Residual Risk Category Rr
11
12
JHZH-LE/SO
- '- Identify sharp material and dipose (e.g. nails, JHZH-PM broken glasses) - Wrap sharp edges when possible
JHZH-LE/SO
JHZH-PM
JHZH-LE/SO
JHZH-LE/SO
*Action Owner
JHZH-PM
Risk Owner
JHZH-PM
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
- Adopt three 3s as a guide - Lifting load by 300mm - Hold for 3 seconds - All personnel 3m away from lifting operation - Lifting zone to be barricaded before works commence - Reminder in toolbox meeting
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
Oct-17
Mar-23
Oct-17
Mar-23
Due Date By
Revision K 13 14
13 months
79 months
13 months
79 months
Risk Exposure Period
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Status
Date: 16/08/2017 15 16 17 Remarks
999
999
999
999
999
999
Other Hazards T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
006
005
004
003
002
001
T309/CDSS/999/006
T309/CDSS/999/005
T309/CDSS/999/004
T309/CDSS/999/003
T309/CDSS/999/002
T309/CDSS/999/001
4
Damage to construction works
-Traffic congestion - Unauthorized entry of personnel to site
Road vehicles entering construction site / excavations
Noise, dust and vibration
Hazard
5
Setting up of Noise Barrier
Traffic Diversion
-Occurrence of a natural disaster during construction - Flooding - Heavy rainfall causing significant ground water table rise
- Construction activities require frequent transport movements - Works at site with long working hours for 7 days a week
-Construction works in close proximity to the public and existing housing -Excessive noise due to construction
-Spoil removed to designated location remote Movement of heavy vehicles causing disruption from site to traffic movement
Noise Barrier and foundation
6
- Injury to public or construction personnel - Disruption of essential services - Negative PR - Delays - Claims
Impact
- Injury to public or construction personnel - Disruption of essential services - Negative PR - Delays - Claims
- Delay and accidents, - ECM issues, - Mosquito breeding, - Security problems
D
C
D
C
C
C
C
Ri
8 Mitigation Measures
- Method Statements - additional site investigation - Provision of Noise barrier - Monitoring of Noise - Noise control plan - Engage community regularly and gather feedback
- Method Statements -Additional traffic management
- Method Statements - additional site supervision - ECM Plan
- Robust ERSS design including flood barriers when necessary - Temporary groundwater controls and pumps within excavation - Specifying water proofing details @ interface
- Design and approved traffic diversions - Minimise traffic around construction sites - Use of barrier and/or gate guards for exit/ entrances to site
- Design and approved traffic diversions - Clear and good signages - Minimise traffic around construction sites
- Contingency planning, e.g. additional noise barriers, inspection and monitoring - Method Statements to ensure safe working methods - Installation of noise barriers - Noise level monitoring - Engaging community for feedback '- Noise, dust control plan
Page 16 of 17
III
III
III
V
IV
IV
I
V
- Flooding of excavation - Collapse of temporary works and adjacent structures - Injury or fatality of public or construction personnel - Disruption of essential services - Delays - Claims
II
III
S
II
IV
IV
F
7 Initial Risk Category Ri
IV
-Environmental pollution
Package 1 Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
- Complaint from nearby occupants - Complaint from LTA - Working time may be reduced with delay to programme
-Traffic congestion due to minimum diversions, - Injury to public or construction personnel drivers seeking alternative routes - Damage to temporary or permanent works
-Construction works in close proximity to the public -Excessive noise due to construction -Excessive noise due to bored and barette pile testing
Hazard Cause
Discharge into Canal from -Heavy rain construction - Insufficient control on site -Surface run off, construction materials Construction Works (bentonite, concrete, grout, near Drains and Canal maintenance/cleaning facilities)
Construction Works near Drains and Canal
Traffic Diversion
Construction Works near Residental area
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
V
IV
III
III
IV
I
V
IV
II
II
III
S
V
V
V
F
D
C
D
C
C
C
D
Ri
Residual Risk Category Rr
11
JHZH-PM
Risk Owner
12
JHZHSBM/CWM
JHZH-PM
JHZH-PM
JHZH-SBM
JHZH-SBM
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly -Designated haul routes -Contingency planning, inspection and monitoring - Placement of cone or barrier during diversion without reduction in lane width - Minimize loud noise activity during evening and weekends - Monitor noise meters at designated intervals - Contingency planning, inspection and monitoring
JHZHSBM/CWM
JHZH-PM - Install additional EC measures (e.g. silt fences, nets) when necessary '- Regular inspection of site by ECO at affected zones - Contingency planning, inspection and monitoring
- Close communication with related authority - Emergency Response planning including Contingency planning e.g. quick evacuation route - Provide efficient geometric design and the road level to mitigate flooding
JHZH-SBM
JHZH-SBM
JHZH-SBM
*Action Owner
JHZH-PM - To provide traffic marshals to direct traffic when necessary - Clearly defined zones for accessible pathways and restricted areas - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Guard rail or rigid barrier to be setup and interlocked properly - Code of Practise of Traffic Control and Work Zone - Placement of cone or barrier during diversion without reduction in lane width
JHZH-PM - To provide traffic marshals to direct traffic when necessary - Clearly defined zones for accessible pathways and restricted areas - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Guard rail or rigid barrier to be setup and interlocked properly - Code of Practise of Traffic Control and Work Zone - Placement of cone or barrier during diversion without reduction in lane width
- Vibration control plan - Vibration monitoring
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10
Mar-20
Mar-23
Mar-20
Mar-23
Mar-23
Mar-23
Mar-23
Due Date By
Revision K 13 14
45 months
79 months
45 months
79 months
79 months
79 months
79 months
Risk Exposure Period
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Status
Date: 16/08/2017 15 16 17 Remarks
999
999
999
999
999
999
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
T309/CNSS
PM- Project Manager CM- Coordination Manager SBM- Station Box Manager CWM- Canal Works Manager LE- Lifting Engineer UE- Utility Engineer SO- Safety Officer ECO - Environment Control Officer
999
T309/CNSS
013
012
011
010
009
008
007
N.A
N.A
N.A
N.A
N.A
N.A
N.A
Operation of machineries / equipment
Recahrge well work
Lifting with Excavator (Pick and Carry)
Traffic Diversion
Traffic Diversion
Removal of sludge
Cleaning
3
Work Activity
2
Previous Hazard ID
1
Hazard ID Hazard No. Hazard Running number Code
5
-Pipe leakage and burst -Loose connection
-Pipe leakage and burst -Loose connection -Lose control of hose
Hazard Cause
- Engine catch fire - Hydraulic oil leakage - Unvoluntary movement of machines boom / arm. - Load bearing componant give way.
Water pipe. Power grid cables. Telecom cables. High tension cables.
6
-Damage of machinery -Injury of worker -Damage of materials
-Damage of machinery -Injury of worker -Damage of materials
- Traffic jams hindering construction vehicles - Bottlenecks hindering traffic speed - Crossed traffic and pedestrian circulation paths - injury to public and/or construction work
- Traffic jams hindering construction vehicles - Bottlenecks hindering traffic speed - Crossed traffic and pedestrian circulation paths - injury to public and/or construction work
'- Injury to public or construction personnel - Contaminate soil, groundwater and surface water
- Injury to public or construction personnel
Impact
- Overloading or over running of machineries / -Damage of machinery -Injury of worker equipment result in over heating. -Damage of materials - Hydraulic leak - Poor maintenance reguime - Misue of machineries or equipment
-Unplanned Drilling. - Insufficient marking on site. - Failure to conduct detection test.
-Uneven ground - Unauthorised lifting - Improper rigging -Overloading -Inexperience operator
-“A’ frame topple - Injury to public - Fingers / hand caught in rotating parts
-Damaged to :
-Uneven ground - Unauthorised lifting - Improper rigging -Overloading -Inexperience operator
-Toppling of excavator - Falling of load/ material
Risk associated with Traffic - Change to road condition due to delivering Diversion material to site
Risk associated with Traffic - Change to road condition due to construction Diversion work, poor line of sight - Changed traffic condition causes confusion to road users - Improper/ unclear signages - Improper/ unclear separation of pedestrians paths and work site ingress/ egress points - Pedestrians jaywalking
Sludge spill
Use of high ultra water jet
Hazard
4
CONTRACT T309 CONSTRUCTION OF SIGLAP STATION FOR THOMSON-EAST COAST LINE
Project Title:
Package 1
F
IV
IV
IV
IV
IV
IV
IV
B
B
B
B
C
C
C
Ri
8 Mitigation Measures
- Ensure maintenance regime is carried out properly. - Always equip machineries / equipment with valid fire extinguisher - Never misuse machineries / equipment. Use it as what it is intended for.
-Thorough study of utilities drawings. - Cable detections by qualified LCDW - Provide clear utilities marking on site - Provide A3 size drawing of utility plan - Apply permit to dig and implement “checklist for working near utility” - Barricade work area while trenching
- Ensure work assess is planned. - Ensure adequate access for work mobilisation and public access. - Only competent lifting crew is allowed to involved in mobilisation. - PTW-Lifting approved prior unloading. - Provide proper exclusion zone to segregate work and public. - Provide warning signs.
●The excavator designed for pick and carry operations must have load chart stating clearly the limitattions for picks and carry operation ●Tag line shall be used during operation ● Ensure the route of travel is firm and level ●Lifting supervisor to ensure the load is firmly secured and tied ●Benchman to guide excavator during the pick and carry operation
- Design stages of traffic diversion to allow construction to be carried out section by section - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Safety barrier to be setup at designated storage zones - Proper signages display at prominent locations - Code of Practise of Traffic Control and Work Zone - designated path for access by pedestrians - Control unauthorized entry of personnel into loading/unloading zone during material delivery
- Design stages of traffic diversion to allow construction to be carried out section by section - Traffic elements (e.g speed bumps/ road markings/ warning signs) indicated on plan - Guard rail or rigid barrier to be setup and interlocked properly Proper signages display at prominent locations - Code of Practise of Traffic Control and Work Zone
- Competent staff - Provide safety warning signage to keep other works clear from work area - Provide safety access to treatment plant - Permit for handling of sludge - Provide emergency contact no.
- Assign two trained hydro jetting operators. - Rotate shift every alternate hours - Provide safety warning signage to keep other works clear from work area - Provide safety access to washing bay
Page 17 of 17
II
II
II
II
II
II
II
S
Initial Risk Category Ri
7
Diaphragm wall, bored piles, ground improvement and enabling works
Risk Register
V
V
V
V
V
II
II
II
II
II
II
II
V
V
S
F
C
C
C
C
C
C
C
Ri
Residual Risk Category Rr
11
JHZH-PM
JHZH-PM
Risk Owner
JHZH-PM
JHZH-PM - Ensure fire extingisher is checked on a monthly basis - Monitor mechnais attendance for maintenance closely -
-Contact relevant utility agency for any presence JHZH-PM of unidentified utility Always treat utility as `live’ if encountered Only manual digging allowed for trial trench Full time supervision during trial trench
- Provide blinker lights to alert night motorist and /or pedestrian. - Ensure footage is firm and level at all times. - Never drag load. Lift vertically.
-AE to examine the lifting capacity of excavator JHZH-PM and issued the certification for the lifting. -Pick and carry operation is guided in SS536 : 2008
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly - Placement of cone or barrier during diversion without reduction in lane width
JHZH-PM - To provide traffic marshals to direct traffic when necessary - To study provision of temporary traffic lights to faciltate passing of construction and public vehicles smoothly - designated path for access by pedestrians - Placement of cone or barrier during diversion without reduction in lane width
- Contain and handle spillage (e.g. excavate spill site and treat with dry sand, temporary diking) immediately - Contact additional emergency services when necessary
- Assign safety supervisor when possible at work place to ensure operation is safe - Barricade work area to prevent unauthorized access and display warning signage.
Future Actions
PREPARED BY TOMMY LEE/ HUA KWAN JONG 9 10 12
JHZH-LE/SO
JHZH-SBM
JHZH-SBM
JHZH-LE/SO
JHZH-SBM
JHZH-SBM
JHZH-SO
JHZH-SO
*Action Owner
May-23
May-23
May-23
Mar-23
Mar-23
Mar-23
May-20
Mar-23
Due Date By
Revision K 13 14
79 months
79 months
79 months
79 months
79 months
79 months
45 months
79 months
Risk Exposure Period
C
C
C
C
C
C
C
C
Target Risk Rating
Open
Open
Open
Open
Open
Open
Open
Open
Status
Date: 16/08/2017 15 16 17 Remarks
particularly to workers on site
2) To cascade the risk and mitigation measures to all parties concerned,
that may arise.
1) To identify the on going major works activities and potential risk hazards
Objectives of this workshop:
a) b) c) d) e) f)
Guide wall and Dwall Sheetpile installation Noise barrier erection Bored pile load test Soil Investigation Tree cutting
1)The on going major works activities are:
Mitigation Measures: 1) Provide proper barricade/ railing 2) Install proper ladder with handrail 3) Standby water pump during raining season 4) Conduct daily toolbox meeting and ensure proper PPE with gloves to prevent hand injury due to sharp object 5) Protruding nails to be removed during demoulding of formwork. 6) End treatment to all exposed rebar 7) Step ladder to have handrail on both sides
Construction of Guide Wall Hazard : 1) Fall into excavated pit 2) Flooding of pit during heavy downpour 3) Cut by sharp object, example rebar and protruding nails
Hazard: 1) Collapse of machine 2) Fallen into pit 3) Lowering of rebar cage 4) Connection and lowering of tremie pipes 5) Casting of dwall
Construction of Dwall
Mitigation: 1) Machinery must sit on hard ground with steel plates 2) Work area to be barricaded 3) Slow rotation of crane during hoisting of rebar cages 4) Provide tagline while hoisting of rebar cages to avoid violent swinging 5) Ensure U‐clips are securely tightened before lowering of cages 6) Worker at platform while lifting of tremie pipes must wear full hardness and secure to prevent falling from height 7) Banksman to guide concrete truck when reversing during casting 8) Incorporate the SWP and put in place a lifting plan 9) All workers to be trained in Work at height 10) Application of permit to move for heavy machineries movement 11) Approved Certificate of Supervision
Hazard
Damage to utilities
Activity
Installation of sheet piles
b) Sheetpiling – Risk and Mitigation
Location of utilities not reflected in utility drawing.
Hazard Cause
Carry out cable detection and trial trench along the path of sheet piles. Apply permit to dig prior to work start.
Mitigation Measures
Collision of machinery and site people.
Installation of sheet piles
Constraint of work area Negligence of operator Uneven ground Absence of lifting plan Failure to guide machineries movement
Hazard Cause
Ensuring the alignment and verticality of the pile.
Hazard
Activity
1) Sheetpiling – Risk and Mitigation
‐Work zone to be barricaded to prevent unauthorized entry ‐Used of tag line to control swaying of load. ‐Employed skilled operator and experienced lifting team. ‐Provision of lifting plan . ‐Full compaction and void filled with quarry dust or mill waste. ‐daily reminder during toolbox meeting
Mitigation Measures
Poor ground condition
Installation of sheet piles
Access laid with hardcore and compacted
Hazard
Activity Toppling of machinery resulting in damage to property Injury to surrounding people
Hazard Cause
Machine sitting on sheet pile
Access to be laid with hard core and compacted. Steel plates to be laid on top of hard core. ‐Full compaction and void filled with quarry dust or mill waste. ‐daily reminder during toolbox meeting
Mitigation Measures
Using of poor condition machinery
Installation of sheet piles
Maintenance service report, AE inspection checklist and certificate
Hazard
Activity Structure failure of machinery
Hazard Cause
Machine to be inspected and certified by AE. Regular monthly maintenance of machinery
Mitigation Measures
Accidental dislodge of sheet pile during driving
Installation of sheet piles
Additional sling tied to sheet pile and machine
Hazard
Activity
Sub‐con approval system to select skill operator Additional sling tied to sheet pile and machine as extra protection in case if grabber gives way.
Mitigation Measures
Sling will only be removed after sheet pile is fully driven into the ground.
Negligent operator. Faulty vibro head
Hazard Cause
Hazard: 1) Fall from height 2) Faulty machine 3) Poor PPE
c) Noise Barrier Installation
Mitigation: 1) Only 2 person allowed in cabin of boomlift and not exceeding SWL 2) Full harness and restrained to cabin 3) Workers trained in WAH procedure 4) Supervisor to check the condition of harness worn by workers 5) Daily check on machinery before start work 6) Protective shield to be worn during drilling and cutting of metal. 7) Proper area set up solely for welding, drilling and cutting of metal
Bored pile test
Activity
Failure of kentledge system
Hazard
•Testing area to be laid with hard core and fully compacted with 10 ton roller
• Inadequate design • Poor ground condition • No proper lifting plan • Improper loading of kentledge • Inadequate monitoring of kentledge system
•Approved Method Statement
•Ensure loading of kentledge system is carried out in accordance with the design
•PE’s design of kentledge system
•Provide physical barrier and safety signs around test site
•Monitoring of overall settlement and differential settlement of the kentledge
•Proper lifting plan to be submitted with approval from PM and review by Lifting Engineer.
•Contractor HSL to produce COS to confirm suitability of ground preparation and kentledge set prior to pile test.
•Plate load test is to be carried out on test ground to determine the bearing capacity of compacted ground
Mitigation Measures
Hazard Cause
d) Bored pile test – Risk and Mitigation
Bored pile test
Activity
Failure of kentledge system
Hazard •
d) Bored pile test – Risk and Mitigation
Improper loading of kentledge
Hazard Cause • •
self‐ retractable lifeline to a concrete block
Use of man‐cage to hoist rigger to top of kentledge set. Rigger to secure self‐retractable lifeline to a concrete block at all times
Mitigation Measures
Bored pile test
Activity
Failure of kentledge system
Hazard •
Hazard Cause
Mitigation Measures
Surveyor monitoring settlement daily
• Monitoring of overall settlement and differential settlement of the kentledge
6 settlement points located at platform to monitor any differential settlement.
Unequal and large settlement
d) Bored pile test – Risk and Mitigation
Barrette pile test
Activity
Failure of kentledge system
Hazard • • Inadequate design Improper loading of kentledge
Hazard Cause
d) Bored pile/Barrette pile test – Risk and Mitigation
•Approved Method Statement
•Ensure loading of kentledge system is carried out in accordance with the design
•PE’s design of kentledge system
Mitigation Measures
Bored pile test
Activity
Failure of lifting mechanism
Hazard
•Adopt approved lifting plan
•Overloading of carried loads over limited design capacity
Yellow for November
•Unauthorized modification of lifting points
•Lifting points to be identified and approved
•Failure of brake motor/gear
Mitigation Measures •Colour coding all lifting mechanisms for validity and serviceability levels
Hazard Cause
•Breakage of lifting chain/ sling
d) Bored pile test – Risk and Mitigation
Mitigation : 1) Qualified operator identified with photo displayed 2) Application of permit to dig 3) Daily check on machine
Hazard: 1) Inexperience operator 2) Faulty machine
e) Soil Investigation
Hazard: 1) Fall from height 2) Eye and Ear injury 3) Hit by falling branches
f) Tree cutting
Mitigation: 1) Full harness and secured with additional strap to branch 2) Full PPE with goggle and ear plug 3) Barricade work area 4) Experience worker employed 5) Cutting from top down and in layer 6) Banksman to ensure no unauthorised entry
THANK YOU
Minutes Title: Risk Register Workshop Date: 1 Dec 2016 Time: 11am Held at: LTA level 2 meeting room
Chaired by: James Minuted by: Distribution date:
Attendees list See attached
Apologies list
Page 1 of 3
Minutes ITEM
MATTERS DISCUSSED
1.0
Introduction
ACTION
JHZH RMF reported the first Risk Register Workshop and there will be weekly workshop every Thursday, after the weekly progress meeting. Info LTA commented that all site engineers, safety, CM and PM should participate in this weekly workshop discussion. The objective of the workshop is to identify the on-going major works activities and potential risk hazards that may arise and to cascade the risk and mitigation measures to all parties concerned, particularly to workers on site. LTA encourage all present to come forward with any new risk that they encountered on site so that it can be discussed and recorded in the register. All mitigation measures shall also be discussed and recorded.
2.0
Slide presentation RMF presented a slide presentation on the risk hazards when working on:
James
Guide wall and D-wall Sheet pile installation Noise barrier erection Bored pile load test Soil Investigation Tree cutting 2.1
On guide wall/ D-wall construction, LTA(Vima) commented: i) proper storage of formwork ii) protruding nails should not be allowed to be freely thrown on the ground after form work removal. iii) end treatment must be carried out to any exposed rebar to prevent cut by sharp end of the rebar. Iv) construction of d-wall to have in placed a) COS b) SWP c) lifting plan d) permit to move
Page 2 of 3
JHZH
Minutes ITEM
MATTERS DISCUSSED
ACTION
On sheet pile installation, LTA commented: 2.3
i) the flow of full process of trial trenching prior to sheet piling work should be presented
JHZH
ii) there should be a sub-con approval system to select skill and experience operator On Noise Barrier installation, LTA commented: 2.4
JHZH
i) boom lift should not exceed the SWL ii) proper work area should be set up for welding work On Bored pile test, LTA commented: i) the settlement monitoring should be recorded and submitted for review daily
2.5
ii) the colour coated on the lifting gear faded with time, therefore it should be painted regularly
3.0
Any Other Matters: LTA commented the workshop to be kept in one hour duration and for subsequent session, individual engineer will be task to speak on the risk and mitigation findings in their respective zone.
4.0
JHZH
INFO
Next Meeting The next meeting will be scheduled on 8 Dec 2016 @ 11am
NEXT MEETING Date: Time: Location:
Page 3 of 3
All / Info
underground services.
3) All site personnel should be fully informed and clear with the work process concerning
carrying out trench excavation on site.
2) A flow chart to demonstrate the necessary steps to be taken to avoid any mishap while
measures to be adopted.
1) To identify the potential risk hazards concerning underground utilities and the mitigation
Objectives of this workshop:
Damaged to : -Unplanned excavation -Water pipe -Insufficient -Power grid marking on cables site -Telecom -Failure to cables conduct -High tension detection cables test
Locating of Utility services
Hazard Cause
Hazard
Activity
-If unclear with the finding of services after reaching the 2m limit, conduct further detection to determine the presence of any services below.
-Thorough study of utilities drawings -Cable detections by qualified LCDW -Provide clear utilities marking on site -Provide A3 size drawing of utility plan -Apply permit to dig -Barricade work area while trenching -Contact relevant utility agency for any presence of unidentified utility -Always treat utility as `live’ if encountered -Only manual digging allowed for trial trench -Full time supervision during trial trench
Mitigation Measure
Locating of Utility services prior to sheet piling work in Victoria School
JHZH’s UE
All Excavating contractor JHZH’s site engineer or supervisor
JHZH’s engineer, UE/Sub –con Requested by JHZH’s UE JHZH JHZH Excavating Contractor JHZH/sub con UE
Action Owner
Cable detection by LCDW
Production of utility drawing after completion of cable detection
Apply permit to dig
Commence trial trench up to a depth 1.5m
Contact relevant utility agency for any presence of unidentified utility
If unclear with the finding of services after reaching the 2m limit, conduct further detection to determine the presence of any services below.
Backfilled all trial trench once data/photos taken
1
2
3
4
5
6
7
Activity
Flow chart of utility work at Victoria School
JHZH site engineer Approval/Excavating contractor
LCDW/ Request by JHZH UE
JHZH UE
Excavating Contractor/Full time supervision by JHZH’s site engineer
Excavating Contractor
LCDW/ Requested by JHZH UE
Requested by JHZH’s UE
Action Owner
Permit to dig raised by who ever in charge
Indication of nature of work and duration
Completed by RMF together with the attendance of the team after briefing
Briefing will be carried out for: -working in new location -change of location(zone) -change of person in charge
To be completed by QPS
Commencement of cable detection work
Trial trench locations
Updated utility plan
Flow of underground utility work
Mitigation of In-Ground Utilities Prior to Sheet Piling Activities At Victoria School
Mitigation of In-Ground Utilities Prior to Sheet Piling Activities Description Step 1: Establish Site Boundary Obtain Design Alignment of sheet piles and commence desktop study of site environment
Responsibility Main Contractor (JHZH) 1. Utility Engineer 2. Area Site Engineer and/or Supervisor
Step 2: Information Retrieval to ascertain InGround Utilities a) Obtain a preliminary understanding of inground utilities present within and around site boundaries from sources such as Owner’s Construction Drawings, LCDW Reports (NCCDW), Utility Agency drawings, etc. b) Commission a LCDW survey to update Site Utilities Plan if information is lacking within the immediate site boundary
Main Contractor (JHZH) 1. Utility Engineer 2. Area Site Engineer and/or Supervisor 3. Licensed Cable Detection Worker (LCDW)
Plan showing alignment of sheet piles
Site utility Plan from LCDW report
Example of property owner’s construction drawing
Updated LCDW report to supplement previous reports
1
Excavating Contractor to commission cable detection in their immediate area of work.
Step 3: Commence on site investigation to identify signs of in ground utilities that may be present. These photos show the presence of the following in-ground utilities: a) PUB Water Inspection Chamber b) SingTel Manhole Pits c) SP Gas Valve Pit Site survey commenced
In this instance, SP Gas Valve Pit was noted to be inconsistent with Utility Agency drawings. A query was lodge with Singapore Power Gas to obtain more information. Note: A decision was later made to revise pile group locations to avoid the gas utilities.
Main Contractor (JHZH) 1. Utility Engineer 2. Area Site Engineer and/or Supervisor Excavating Contractor to familiarise themselves with existing utilities and their routing with Main Contractor.
Indicative signs of in ground utilities are noted
Mark in-ground utilities identified from site survey and desktop studies
Mark alignment of sheet piles
2
Step 4: On Site Review and Markings a) Mark out locations of sheet piling alignment and pile groups b) Also mark out locations of in-ground utilities identified from the above steps. Possible lines of utility conduits, cables and pipes were plotted on site with information obtained from desktop studies as well as on-site review
Main Contractor (JHZH) 1. Area Site Engineer and/or Supervisor 2. LCDW
Step 5: Establish if there are any Trial Trenches are required Locations of trial trenches were selected base on the following: a) Proximity of in-ground utilities to alignment of sheet piles (trench locations were selected to coincide on top of location of pile groups) b) Any indication of in-ground utilities on-site that are inconsistent when compared with desktop studies required investigation by trial trenching Note: All trial trenches were dug by hand, excavator shown in photo was utilised to clear above ground site vegetation. Any incomplete trial trench was protected with a steel plate as a safety measure. Factory wide Notice to Commence Excavation (NCE) was previously submitted.
Photos showing Site Preparation ahead of sheet piling activity
Site peg for pile group
3
Main Contractor (JHZH) 1. Utility Engineer 2. Area Site Engineer and/or Supervisor Main Contractor hired labour undertaking trial trenching were under full time supervision by JHZH Site Engineer
Step 6: Digging of Trial Trenches by Hand, with full time supervision by JHZH. Step 7: Recording of trial trench findings via: a) Photo and daily diary records b) Survey point by Project Survey Team for As Build Drawing
Findings from Trial Trench recorded
Step 8: Where there is discovery of In-Ground Utilities not previously ascertained or identified: a) Further scanning was conducted by LCDW to focus on a smaller area adjacent to trial trench b) Further trial trenching conducted to investigate route of discovered utility
Further scanning in a smaller area adjacent discovered utility
Scanning also undertaken inside trial trench
4
Lesson learnt: Utility Agency Plans and the limitations of cable detection are liable to errors, an experience team of Utility Engineers and LCDW is required to mitigate risks and ensure due diligence undertaken to avoid of clashing between sheet pile and undiscovered in-ground utility.
Main Contractor (JHZH) 1. RMF and QPS reviewed and give approval for trial trenching to commence 2. Area Site Engineer and/or Supervisor 3. Survey Team Main Contractor (JHZH) 1. Area Site Engineer and/or Supervisor 2. LCDW at the request of Utility Engineer
Step 9: Continuous updating of sheet pile grouping to avoid discovered in-ground utilities
Revised Sheet Pile Alignment after reiterations to avoid utilities
Permit to Dig
Sheet Piling Contractor submits the Step 10: Permit to Dig submitted and reviewed by request to dig Main Contractor Utility Engineer, Risk permit Management Facilitator, QPS and LTA. This is a construction hold point prior to commencing Main sheet piling. Contractor (JHZH) 1. Area Site Engineer and/or Supervisor 2. Design Engineer confirms the revision of sheet pile locations 3. RMF and QPS review and approved for sheet piling to commence Sheet Piling Contractor is responsible to maintain awareness and familiarise with in-ground utilities throughout the entire process
Step 11: Commence sheet piling activity only after hold point is released by review and approval of Permit to Dig.
5
Sheet Piling Contractor lay steel plates to mitigate the influence and impact of track vehicles over any nearby utilities
Minutes Title: Risk Register Workshop No 2 Date: 8 Dec 2016 Time: 11am Held at: LTA level 2 meeting room
Chaired by: James Minuted by: Distribution date:
Attendees list See attached
Apologies list
Page 1 of 3
Minutes ITEM
MATTERS DISCUSSED
1.0
Introduction
ACTION
JHZH RMF reported the first Risk Register Workshop MOM held on 1 Dec 2016 was submitted. Info As suggested by LTA to keep the session within one hour and to highlight one individual risk in each workshop, the risk and hazard of utility services at Victoria school was selected for discussion in this workshop The complete flow of the process will be demonstrated via a short slide presentation The utility engineer, Leonard will provide the necessary information required to carry out the detection of services in a safe manner.
2.0
Slide presentation on flow of work on utility services at Victoria School
James/ Leonard
Attached slides with amended comments added in RED
2.1
LTA commented JHZH should enhanced the traffic control with traffic marshal at Victoria School as there are students staying in the boarding house and may not be familiar with the access route due to the site work activities.
JHZH
2.2
LTA commented the current safety measures taken by T309 are much more stringent than the QPS enhance control measures for Permit to Dig by T305.
Info
New Permit to Dig(T305)
Old Permit to Dig(T305)
T309 standard of control for Permit to Dig
Produce a updated combined utility plan every month
Nil
Factory Wide Combined Utility Plan completed at onset of Project Work Area Specific Utility Plan reviewed in advance from commencement of any tasks at risk to in-ground utilities On site investigations to supplement desktop study of Utilities Plan and steps taken to ensure risks are well communicated to site supervision
Provide dimension of trial trench
Nil
Dimensions and depth of Trial Trenches recorded by Project Survey Team for As Build information Photo records of trial trench including any utility discovered are recorded
Page 2 of 3
Minutes ITEM
3.0
MATTERS DISCUSSED
ACTION
Indicate nearest utility distance on the drawing
Nil
Area Specific Utilities Plan is continuously updated with visits by Licensed Cable Detection Worker (LCDW) while the work activity is ongoing, LCDW will be activated to attend site when suspected utilities are encountered All utilities detected are marked on site with type and route of utility indicated on site
Risk assessment to be conducted when utility within 2m distance
Nil
Standard trial trenching undertaken to 2m for visual verification of suspected utility Risk assessment is undertaken continuously by Utility Engineer/ Site Engineer/ Supervisor/ QPS on site Full time supervision is undertaken while trial trenching
Not use excavator for digging the trial trench below 700mm
Nil
Mechanical trial trenching not permitted. Manual trial trenching to 2000mm
Any Other Matters: As the demolition of brick wall and tree clearing are commencing in Entrance A for drain diversion, it will be appropriate to highlight the risk hazards and mitigations in the next workshop.
4.0
INFO
Next Meeting The next meeting will be scheduled on 15 Dec 2016 @ 11am
Page 3 of 3
All / Info
Entrance A / Kee Sun Ave
Controlled Demolition
demolition work and the associated hazards and risks.
3) All site personnel should be fully informed and clear with the work process concerning
carrying demolition work on site.
2) A flow chart to demonstrate the necessary steps to be taken to avoid any mishap while
1) To identify the potential risk hazards concerning demolition work at Entrance A
Objectives of this workshop:
Hazard
-Eye and hand injury -Noise and dust pollution
Activity
Demolition of brick wall
-Flying debris -Failure to equip with proper PPE -Failure to barricade work area
Hazard Cause
Mitigation Measure
Action Owner
- Conduct RA/ SWP briefing Site - Pre-plant check of machinery engineer/technocrete - Barricade work area and protection set-up to prevent debris falling into drain. - Cutter rail track to be securely mounted on brick wall before cutting. - Operator to ensure that no one is near the cutting zone and the remote control cutter is activated. - Only experienced operator assigned to operate the remote control cutter can do the cutting of wall. - Similarly only qualified person can operate the remote control crusher and breaker. - Spray water during cutting, crushing and hacking to prevent dust pollution - Wear protective goggles and ear plug
Demolition of existing brick walls at Entrance A
RA/SWP Briefing
Checking of plant and machinery before starting of demolition work
Prevent debris from falling into drain during demolition.
Protection Set Up
- Operator to ensure that no one is near the cutting zone and the remote control cutter is activated. - Only experienced operator assigned to operate the remote control cutter can do the cutting of wall.
- Cutter rail track to be securely mounted on brick wall before cutting.
Cutting to Terminate Wall
Cutter rail track to be securely mounted on brick wall before cutting
Mounting of Track
Grab Machine Operated Remotely
- Similarly only qualified person can operate the remote control crusher and breaker. - Spray water during cutting, crushing and hacking to prevent dust pollution
Grab Machine Operated Remotely
- Similarly only qualified person can operate the remote control crusher and breaker. - Spray water during cutting, crushing and hacking to prevent dust pollution
- Similarly only qualified person can operate the remote control crusher and breaker. - Spray water during cutting, crushing and hacking to prevent dust pollution
Hacking Machine Operated Remotely
Bobcat Clearing Debris to Dump Container
Avoid discharging the hard core debris from height to prevent dust and loud noise when debris hit bin
Safety Barriers Demarcating Dumping Zone
THANK YOU
Minutes Title: Risk Register Workshop No 3 Date: 16 Dec 2016 Time: 11am Held at: LTA level 2 meeting room
Chaired by: James Minuted by: Distribution date:
Attendees list See attached
Apologies list
Page 1 of 2
Minutes ITEM
MATTERS DISCUSSED
1.0
Introduction
ACTION
JHZH RMF reported the 3rd Risk Register Workshop MOM held on 16 Dec 2016 was submitted on 17 Dec 2016
Info
The risk and hazard of demolition at Entrance A was selected for discussion in this workshop The complete flow of the process was presented via a short slide presentation The site engineer, Alfred provided the necessary information required to carry out the demolition of brick-wall in a safe manner.
2.0
Slide presentation on the demolition of brick-wall at Entrance A.
James/ Alfred
Attached slides with amended comments added in RED 2.1
LTA commented the following:
JHZH
1) Since the location is fixed, the Action Owner on the risk register should bear the name of actual person in charge. (slide 3) 2) Railing should be provided at edge of drain to prevent workers falling into drain during demolition. (slide 11) 3) Experienced operator controlling the remote control should be changed the appointed operator instead. (slide 3) 4) Bracing of undisturbed wall to provide stability during demolition (slide 7) 2.2
LTA would like to have the risk hazard on guide wall construction as a topic for discussion in the next workshop.
3.0
Any Other Matters: NIL
4.0
Next Meeting
INFO
The next meeting will be scheduled on 22 Dec 2016 @ 11am
Page 2 of 2
All / Info
Sheet Piling.
2) All site personnel should be fully informed and clear with the work process concerning
mitigation measures to be adopted.
1) To identify the potential risk hazards concerning Sheet Piling at Entrance A and the
Objectives of this workshop (no.5):
Existing Hoarding
Extension of Noise Barriers (12m) w SheetPiling
Two rows of sheet piles
Sheet Pile depth: 9m
Ingress/ Egress
Hazard
Hazard Cause
‐Submit lifting plan and machinery record prior to start of operation ‐Provision of signalman and traffic controller to guide machinery movement ‐Full compaction and void filled with quarry dust or mill waste.
Absence of lifting plan
Failure to guide machineries movement
Uneven ground
‐Establish good communication at all times between operator and signalman ‐Used of tag line to control swaying of load. ‐Provision of steel plate for machinery
‐Ensure work zone is organized with good housekeeping ‐Proper barricade and demarcation of work zone to prevent unauthorized entry
Mitigation Measure
Negligence of operator
Installation Collision of Constraint of of sheet machinery and work zone piles site people.
Activity
SheetPiling Risks and Mitigation Measures
Walter Lai
Walter Lai/ Killi
Walter Lai
Walter Lai
Walter Lai/ Jessica Ng
Walter Lai/ Jessica Ng
Action Owner
Ingress/ egress area to be covered with steel plate
SheetPiling Risks and Mitigation Measures
Machine access to be covered with steel plate
Accidental dislodge of sheet pile during driving
Installatio n of sheet piles
Negligent operator Faulty vibro head
Hazard Cause
Walter Lai
Walter Lai
Action Owner
Sling will only be removed after sheet pile is fully driven into the ground.
Employ skilled operator and perform daily checks prior to start of operation Additional sling tied to sheet pile and machine as extra protection in case if grabber gives way.
Mitigation Measure
Additional sling tied to sheet pile and machine
Hazard
Activity
Ensuring the alignment and verticality of the pile.
SheetPiling Risks and Mitigation Measures
Damaged to : ‐Unplanned excavation ‐Water pipe ‐Insufficient ‐Power grid marking on site cables ‐Failure to ‐Telecom conduct cables ‐High tension detection test cables
Locating of Utility services
Hazard Cause
Hazard
Activity
‐If unclear with the finding of services after reaching the 2m limit, conduct further detection to determine the presence of any services below.
Leonard Kok/ Tan WC/ Walter Lai Tan Hock Huat/ Tan WC Leonard Kok/ Tan WC Leonard Kok/ Tan WC Walter Lai Walter Lai Leonard Kok/ Tan WC
‐Thorough study of utilities drawings ‐Cable detections by qualified LCDW ‐Provide clear utilities marking on site ‐Provide A3 size drawing of utility plan ‐Apply permit to dig ‐Barricade work area while trenching ‐Contact relevant utility agency for any presence of unidentified utility ‐Always treat utility as `live’ if encountered ‐Only manual digging allowed for trial trench ‐Full time supervision during trial trench
Leonard Kok/ Tan WC
All Walter Lai Jessica Ng/ Thomas Ng
Action Owner
Mitigation Measure
SheetPiling Risks and Mitigation Measures
Hazard Eileen Walter Lai
12m/6m noise barrier to be set up Good insulation on equipment, temporary sound barrier (when necessary) Regular monitoring of noise level during sheet piling activity
Insufficient Noise insulation and noise monitoring
Surface run‐ offs entering drain Silt fence intact
Guna
Walter Lai/ Guna Guna/ Lina
Mr. Lau
Action Owner
Mitigation Measure
Hazard Cause
Existing drain to be cleared regularly Installatio Flooding or Heavy rain (Flash flood) Portable ECM to be in place n of sheet clogging of pile existing drain
Installatio Noise level is n of sheet above pile acceptable level
Activity
SheetPiling Risks and Mitigation Measures
Hazard
Hazard Cause
Installatio Gaps in sheet Poor n of sheet piles workmanshi piles p
Activity Minimize gaps by interlocking sheetpile
Mitigation Measure
SheetPiling Hazards and Mitigation Measures
Walter Lai/ Jessica Ng
Action Owner
Hazard
Hazard Cause
Installatio Using of poor Structure n of sheet condition failure of piles machinery machinery
Activity
Maintenance service report, AE inspection checklist and certificate
Action Owner
Machine to be inspected and certified by AE. Walter Lai Regular monthly maintenance of machinery
Mitigation Measure
SheetPiling Risks and Mitigation Measures
Hazard
Hazard Cause
Mitigation Measure
Installatio Failure of n of sheet lifting pile mechanism
Brake motor failed Failure of sling and chain
Monthly inspection of lifting mechanism Colour coding all lifting mechanisms Safety zone to be established Lift load for 3 sec, 300mm and personnel 3 m away
Installatio Welding‐ Fire Combustible Clear of combustible material n of sheet damage material pile Inappropriat Provide PPE‐ Welding face shield, apron, gauntlet e welding Daily welding set checklist/inspection rod Provision of fire blanket and fire extinguisher
Activity
SheetPiling Risks and Mitigation Measures
Walter Lai/ Killi Walter Lai Walter Lai/ Crawford Walter Lai
Walter Lai Crawford Ang
Walter Lai
Walter Lai/ Jessica Ng
Action Owner
Hazard: 1) Fall from height 2) Faulty machine 3) Poor PPE
c) Noise Barrier Installation
Mitigation: 1) Only 2 person allowed in cabin of boomlift and not exceeding SWL 2) Full harness and restrained to cabin 3) Workers trained in WAH procedure 4) Supervisor to check the condition of harness worn by workers 5) Daily check on machinery before start work 6) Protective shield to be worn during drilling and cutting of metal. 7) Proper area set up solely for welding, drilling and cutting of metal
THANK YOU
Minutes Title: Risk Register Workshop No 5 Date: 2 Feb 2017 Time: 11am-12pm Held at: LTA level 2 meeting room
Chaired by: Tommy Lee Minuted by: Tommy Lee Distribution date: 8 Feb 17
Attendees list See attached
Apologies list
Page 1 of 3
Minutes ITEM
MATTERS DISCUSSED
1.0
Introduction
ACTION
Mr, Jong, JHZH Safety Manager and RMF joined in for the Risk Workshop no.5 which covers Sheet Piling at Entrance A.
Info
2.0
Slide presentation on sheet piling at Entrance A
Tommy
2.1
LTA noted to establish utilities with Entrance A and siglap park connector area, to ensure that all utilities are identified.
JHZH
2.2
It was noted that Lighting is adequate and will be placed at the hoarding and other designated location. 2.3
2.4
2.5 2.6
2.7
2.8
It was discussed that the sheet pile clearance area is approx. 3.5m and sufficient clearance is required for the vibro machine rotation shall be considered. The schedule for sheet piling and drainage excavation, including the sequence of work shall be made known to LTA and QPS.
Info JHZH
JHZH
Surveys shall be conducted to houses along Kee Sun Ave to access any potential issues during sheet piling.
JHZH
Peter highlighted that one main risk is to secure the 2 trees from toppling within the excavation area. Sheetpile may be driven on its side to secure the trees in position.
JHZH
Ingress for delivery of sheet pile is being delivered from Kee Sun Ave as originally planned with the use of lorry crane. Egress will be towards Marine Parade Road. LTA had emphasised the use of lorry crane for loading and unloading shall be assessed on a case by case basis.
Info
2.9
JHZH suggested the marking of red paint on the hoarding at the machinery operator eye level to give visible information to the operator the hoarding boundaries location.
2.10
Mobilization of the machinery for sheet piling will begin on 6 Feb 2017.
Info
2.11
LTA reminded that any inspection work involving QPS shall be duly informed to the QPS.
Info
QPS mentioned the need to use steel plates for the movement of the machinery. JHZH shall review on it.
Page 2 of 3
Info
JHZH
Minutes ITEM
MATTERS DISCUSSED
3.0
Any Other Matters:
ACTION
LTA reminded on the PD visit to happen on the 14th Feb 17. Housekeeping is essential. A monthly PGI inspection will be conducted on the 7th Feb 17.
4.0
Info
Next Meeting The next meeting will be scheduled on 9 Feb 17 @ 9am (tentative). The topic will be on drainage excavation for Entrance A. The presentation will be conducted by Mr. Jong.
Page 3 of 3
All / Info
drain excavation.
2) All site personnel should be fully informed and clear with the work process concerning
and the mitigation measures to be adopted.
1) To identify the potential risk hazards concerning drain excavation activities at Entrance A
Objectives of this workshop (no.6):
Existing Hoarding
Extension of Noise Barriers (12m) w SheetPiling
Drain size ‐ 1.5m wide, 2‐3m depth & 80+‐ m long
Drain excavation between two rows of sheet piles
Ingress/ Egress
Damaged to :
Excavation work
Water pipe. Power grid cables. Telecom cables. High tension cables.
Hazard
Activity
Failure to conduct detection test.
Insufficient marking on site.
Unplanned excavation.
Hazard Cause
If unclear with the finding of services after reaching the 2m limit, conduct further detection to determine the presence of any services below.
•
• • •
• •
Thorough study of utilities drawings Cable detections by qualified LCDW Provide clear utilities marking on site Provide A3 size drawing of utility plan Apply permit to dig and implement “checklist for working near utility” Barricade work area while trenching Contact relevant utility agency for any presence of unidentified utility Always treat utility as `live’ if encountered Only manual digging allowed for trial trench Full time supervision during trial trench
• • • • •
Mitigation Measure
Drain Excavation Risks and Mitigation Measures
Tan WC LCDW Segar (ES Site Supervisor) Hari (ES Engineer)
Leonard Kok/ Tan WC
‐ ‐ ‐ ‐
Action Owner
Provide rigid barricade and warning signage. Provide proper access. Provide toe board. Provide adequate lighting if necessary. Never store material within 1 m from excavation edge. Provide proper shoring (in this case sheet pile) Never allow machineries to park close to excavation trench.
• • • • • •
Excavation collapse
Poor shoring
Missing fall protection provision
•
Put up extra support for the pine tree. Brief workers and excavator operator to be aware of the hazard.
• •
Workers hit by fallen pine tree
Damaged roots
Design and construct strutting work to prevent soil movement. Pre‐con survey on potential infrastructure / house.
Sub‐standard • soil restrain temporary • work
Soil movement affecting existing infrastructure
Mitigation Measure
Hazard Cause
Hazard
Excavation Worker / work material fall into excavation.
Activity
Drain Excavation Risks and Mitigation Measures
‐ ‐
‐ ‐
‐ ‐
‐ ‐
Segar (ES Site Supervisor) Jessica (JV Engineer)
Segar (ES Site Supervisor) Jessica (JV Engineer)
Segar (ES Site Supervisor) Jessica (JV Engineer)
Jessica (JV Engineer) Erin Rosli (SPRO)
Action Owner
Provide support for the pine tree
GI pipes
Pine tree
I beam
Drain Excavation Risks and Mitigation Measures
Ingress/ egress area to be covered with steel plate
Excavation work
Activity
Establish good communication at all times between operator and signalman Used of tag line to control swaying of load. Provision of steel plate for machinery Provision of signalman and traffic controller to guide machinery movement Provide exclusion zone to control movement of excavator.
•
• •
Negligence of operator
Ensure work zone is organized with good housekeeping. Proper barricade and demarcation of work zone to prevent unauthorized entry
•
Constraint of work zone
Failure to guide machineries movement •
•
•
Mitigation Measure
Hazard Cause
Collision of machinery and Uneven site people. ground
Hazard
Drain Excavation Risks and Mitigation Measures
‐ ‐
Segar (ES Site Supervisor) Jessica (JV Engineer)
Action Owner
Provide exclusion zone and banksman to prevent unauthorised entry.
Drain Excavation Risks and Mitigation Measures
Excavation works
Activity
Surface run‐ offs entering drain
Heavy rain (Flash flood)
Poor scheduling of work. Poor maintenance of excavator.
Noise level is above acceptable level
Flooding or clogging of existing drain
Hazard Cause
Hazard
• •
• • •
Exisiting drain to be clear regularly. Ensure ECM is functioning well. Provide sufficient manpower to maintain silt fence. No stock pile on site. Cover any residue spoil.
‐ ‐ ‐
Guna (LV ECO) Segar (ES Site Supervisor) Jessica (JV Engineer)
Segar (ES Site Supervisor)
‐
• • • Carryout drain excavation during day time. Proper maintenance of excavator. Provide noise barrier to mitigate noise.
Action Owner
Mitigation Measure
Drain Excavation Risks and Mitigation Measures
Portable treatment plant commissioned to ensure silty water are properly treated prior discharge into public drain.
Drain Excavation Risks and Mitigation Measures
Sufficient manpower deployed to ensure silt are properly maintain.
THANK YOU
drain excavation.
2) All site personnel should be fully informed and clear with the work process concerning
and the mitigation measures to be adopted.
1) To identify the potential risk hazards concerning drain wall bracing activities at Entrance A
Objectives of this workshop (no.7):
Existing Hoarding
Extension of Noise Barriers (12m) w SheetPiling Ingress/ Egress
Drain size ‐ 1.5m wide, 2‐3m depth & 80+‐ m long
Drain excavation between two rows of sheet piles
Drain wall bracing Risks and Mitigation Measures
Drain wall bracing Risks and Mitigation Measures
Drain wall bracing Risks and Mitigation Measures
Hazard
Crane topple
Activity
Lifting work
Ensure crane work within load radius and within max. capacity. Make known weight of I beam to lifting team. Ensure monthly mechanics inspection Conduct weekly boom down with mechanics Carry out daily inspection by operator Only appointed and certified R/S and LS are allowed to carryout lifting work. Enforce on PTW – lifting
• • • • •
Failure in LM mechanical part
Incompetent lifting team
No lifting plan
•
• •
Overload
Poor ground condition.
Design and COS crane access. Appoint LE to inspect ground condition after adverse weather. Provide steel plates on compacted ground.
Mitigation Measure • •
Hazard Cause
Drain wall bracing Risks and Mitigation Measures
‐ ‐
Jessica (JV Engineer) Segar (ES Site Supervisor)
Action Owner
•
•
Hoisted load too near to public / resident
Long bulky load not considered for lift plan
Load in contact with crane
Reduce length of I beam Provide adequate tag lines to prevent load from swing to public. Lift plan to include min. load radius RA to consider congested work area Always adopt 3X3 lifting principals
• •
• • •
Deploy competent lifting team Provide tag lines to control movement of load Never place body part in line of fire
‐ ‐ ‐
‐ ‐
‐ ‐
Jessica (JV Engineer) Segar (ES Site Supervisor) Killi (JV Lifting Engineer)
Jessica (JV Engineer) Segar (ES Site Supervisor)
Jessica (JV Engineer) Segar (ES Site Supervisor)
Jessica (JV Engineer) Segar (ES Site Supervisor)
‐ ‐
• Only appointed and certified R/S and LS are allowed to carryout lifting work. Provide exclusion zone and only authorised personnel are allowed to entre. Provide adequate tag lines.
Action Owner
Mitigation Measure
Poor footage • or missing tag • lines •
Interface with public
Body part place in line of fire
Poor rigging method
Fallen I beam
Lifting work
Missing tag lines
Hazard Cause
Hazard
Activity
Drain wall bracing Risks and Mitigation Measures
Provide exclusion zone and banksman to prevent unauthorised entry.
Drain wall bracing Risks and Mitigation Measures
Include min load radius in load chart
‐ Property damaged Fire and ‐ Injury to explosion public or workers
Welding work
Hazard Cause
Hazard
Activity
• •
• • • • •
• • • • PPE: Welding face shield, apron and gauntlet Proper housekeeping Method Statements Apply PTW (e.g. hot works) daily before commencements of works Daily welding set checklist/ inspection Standby fire extinguishers and fire blankets Reminder in Tool box meeting Certified welders Remove flammable items (timber, canvas etc.. )from welding premises Monthly inspection of welding equipment Apply Safe Work Procedure
Mitigation Measure
Drain wall bracing Risks and Mitigation Measures
‐ ‐
Segar (ES Site Supervisor) Segar (ES Site Supervisor)
Action Owner
Welding work with fire screen, extinguisher and fire watchman standby.
Drain wall bracing Risks and Mitigation Measures
No welding during wet weather.
THANK YOU
drain excavation.
2) All site personnel should be fully informed and clear with the work process concerning
and the mitigation measures to be adopted.
1) To identify the potential risk hazards concerning drain excavation activities at Entrance A
Objectives of this workshop (no.8):
Existing Hoarding
Extension of Noise Barriers (12m) w SheetPiling
Drain size ‐ 1.5m wide, 2‐3m depth & 80+‐ m long
Drain excavation between two rows of sheet piles
Ingress/ Egress
Sequent 1
CLG904D
Soil truck
Sequent 2
Soil truck
Excavator EC290
Damaged to :
Excavation work
Water pipe. Power grid cables. Telecom cables. High tension cables.
Hazard
Activity
Failure to conduct detection test.
Insufficient marking on site.
Unplanned excavation.
Hazard Cause
If unclear with the finding of services after reaching the 2m limit, conduct further detection to determine the presence of any services below.
Segar (ES Site Supervisor) Segar (ES Site Supervisor) Segar (ES Site Supervisor)
Segar (ES Site Supervisor) Hari (ES Engineer)
Leonard Kok/ Tan WC
‐ ‐ ‐
‐ ‐
•
• • •
• •
‐ ‐ ‐ ‐ ‐
Thorough study of utilities drawings Cable detections by qualified LCDW Provide clear utilities marking on site Provide A3 size drawing of utility plan Apply permit to dig and implement “checklist for working near utility” Barricade work area while trenching Contact relevant utility agency for any presence of unidentified utility Always treat utility as `live’ if encountered Only manual digging allowed for trial trench Full time supervision during trial trench
• • • • •
Tan WC LCDW Segar (ES Site Supervisor) Segar (ES Site Supervisor) Segar (ES Site Supervisor)
Action Owner
Mitigation Measure
Drain Excavation Risks and Mitigation Measures
Provide rigid barricade and warning signage. Provide proper access. Provide toe board. Provide adequate lighting if necessary. Never store material within 1 m from excavation edge. Provide proper shoring (in this case sheet pile) Never allow machineries to park close to excavation trench.
• • • • • •
Excavation collapse
Poor shoring
Missing fall protection provision
•
Put up extra support for the pine tree. Brief workers and excavator operator to be aware of the hazard.
• •
Workers hit by fallen pine tree
Damaged roots
Design and construct strutting work to prevent soil movement. Pre‐con survey on potential infrastructure / house.
Sub‐standard • soil restrain temporary • work
Soil movement affecting existing infrastructure
Mitigation Measure
Hazard Cause
Hazard
Excavation Worker / work material fall into excavation.
Activity
Drain Excavation Risks and Mitigation Measures
‐
‐
‐ ‐ ‐ ‐ ‐
Segar (ES Site Supervisor)
Segar (ES Site Supervisor)
Segar (ES Site Supervisor) Segar (ES Site Supervisor) Segar (ES Site Supervisor) Segar (ES Site Supervisor) Segar (ES Site Supervisor)
Peter (JV Superintendent) Segar (ES Site Supervisor)
Erin Rosli (SPRO)
‐
‐ ‐
Jessica (JV Engineer)
‐
Action Owner
Provide support for the pine tree
GI pipes
Pine tree
I beam
Drain Excavation Risks and Mitigation Measures
Ingress/ egress area to be covered with steel plate
Excavation work
Activity
Close proximity to existing canal
Soft ground
Failure to guide machineries movement
Stability of ground foundation
Over travel
Excavator topple
Grabber not stuck / struck at bracing
Hazard Cause
Hazard
•
•
• • •
Design excavator access COS for access Inspection ground stability after adverse weather condition Signaler man to guide excavator grabber out of bracing JV staff to perform standing supervision during drainage diversion work.
Mitigation Measure
Drain Excavation Risks and Mitigation Measures
‐ ‐
‐ ‐ ‐
Segar (ES Site Supervisor) Jessica (JV Engineer)
Jessica (JV Engineer) Jessica (JV Engineer) Killi (JV Lift Engineer)
Action Owner
Excavation work
Activity
Uneven ground
Negligence of operator
Constraint of work zone
Hazard Cause
Moving steel plate in congested access
Collision of machinery and Failure to site people. guide machineries movement
Hazard
•
•
• • •
•
•
• Ensure work zone is organized with good housekeeping. Proper barricade and demarcation of work zone to prevent unauthorized entry Establish good communication at all times between operator and signalman Used of tag line to control swaying of load. Provision of steel plate for machinery Provision of signalman and traffic controller to guide machinery movement Provide exclusion zone to control movement of excavator. Define proper access for machines and man.
Mitigation Measure
Drain Excavation Risks and Mitigation Measures
‐ ‐ ‐ ‐
‐
‐
‐
Segar (ES Site Supervisor) Segar (ES Site Supervisor) Segar (ES Site Supervisor) Segar (ES Site Supervisor)
Segar (ES Site Supervisor)
Segar (ES Site Supervisor)
Segar (ES Site Supervisor)
Action Owner
Provide exclusion zone and banksman to prevent unauthorised entry.
Drain Excavation Risks and Mitigation Measures
Excavation work
Activity
Loose soil between sheet pile drop off.
Hazard Cause
Collapse of loose soil suck between sheet Excavator pile bucket not able to reach pocket of sheet pile.
Hazard
•
• •
Drain
Excavate not more than 1.2 m deep at one go. Workers to crowbar stuck soil between sheet pile. Never send workers into excavation without removing all loose soil between sheet piles.
Mitigation Measure
Drain Excavation Risks and Mitigation Measures
‐ ‐
Segar (ES Site Supervisor) Jessica (JV Engineer)
Action Owner
Excavation works
Activity
Bentonite over flow
•
Sheet pile too • near guide wall •
Provide adequate bund wall to contain bentonite. Close monitoring of bentonite flow from plant side. Deploy watch man throughout the period of de‐sanding.
‐ ‐
‐ ‐ ‐
Exisiting drain to be clear regularly. Ensure ECM is functioning well. Provide sufficient manpower to maintain silt fence. No stock pile on site. Cover any residue spoil.
• • •
Bentonite spill into drain
Heavy rain (Flash flood)
Flooding or clogging of existing drain
Segar (ES Site Supervisor) Jessica (JV Engineer)
Guna (LV ECO) Segar (ES Site Supervisor) Jessica (JV Engineer)
Segar (ES Site Supervisor)
‐
Carryout drain excavation during day time. Proper maintenance of excavator. Provide noise barrier to mitigate noise.
• • •
• •
Poor scheduling of work. Poor maintenance of excavator.
Noise level is above acceptable level
Action Owner
Mitigation Measure
Surface run‐ offs entering drain
Hazard Cause
Hazard
Drain Excavation Risks and Mitigation Measures
Portable treatment plant commissioned to ensure silty water are properly treated prior discharge into public drain.
Drain Excavation Risks and Mitigation Measures
Sufficient manpower deployed to ensure silt are properly maintain.
THANK YOU
Missing Risk: • Moving the steel plates for excavator access Constrain site • Define proper access for machineries and workmen. • Presentation and MS not in line. • Include calculation e.g. track seating on both side of sheet pipe. • MS for strut is not approved yet (comment given in Oct16). • Bentonite may spill into drain (Sheet pile very near to guide wall). • Standing supervision by JV staff.
Comment by LTA
drain excavation.
2) All site personnel should be fully informed and clear with the work process concerning
and the mitigation measures to be adopted.
1) To identify the potential risk hazards concerning lifting rebar cage activities at Entrance B
Objectives of this workshop (no.9):
Hazard
lifting work Crane collapse
Activity
Incompetent operator
Poor crane footage
Over load
Hazard Cause
If unclear with the finding of services after reaching the 2m limit, conduct further detection to determine the presence of any services below.
•
•
•
‐
Implement lift plan and PTW system for Lifting Use only competent lifting personnel Crane access must be design by PE. Crane access must be certify before usage. All load must be identified before lifting. Adopt 3X3 lifting principle. Always observe max. load radius to avoid overloading. Provide exclusion zone and warning sign to warn off unauthorised workman. Always reinspect crane access after increment weather
• • • • • • •
Leonard Kok/ Tan WC
Segar (ES Site Supervisor)
Action Owner
Mitigation Measure
Drain Excavation Risks and Mitigation Measures
Lifting rebar cage in congested work area
Provide rigid barricade and warning signage. Provide proper access. Provide toe board. Provide adequate lighting if necessary. Never store material within 1 m from excavation edge. Provide proper shoring (in this case sheet pile) Never allow machineries to park close to excavation trench.
• • • • • •
Excavation collapse
Poor shoring
Missing fall protection provision
•
Put up extra support for the pine tree. Brief workers and excavator operator to be aware of the hazard.
• •
Workers hit by fallen pine tree
Damaged roots
Design and construct strutting work to prevent soil movement. Pre‐con survey on potential infrastructure / house.
Sub‐standard • soil restrain temporary • work
Soil movement affecting existing infrastructure
Mitigation Measure
Hazard Cause
Hazard
Excavation Worker / work material fall into excavation.
Activity
Drain Excavation Risks and Mitigation Measures
‐
‐
‐ ‐ ‐ ‐ ‐
Segar (ES Site Supervisor)
Segar (ES Site Supervisor)
Segar (ES Site Supervisor) Segar (ES Site Supervisor) Segar (ES Site Supervisor) Segar (ES Site Supervisor) Segar (ES Site Supervisor)
Peter (JV Superintendent) Segar (ES Site Supervisor)
Erin Rosli (SPRO)
‐
‐ ‐
Jessica (JV Engineer)
‐
Action Owner
Provide support for the pine tree
GI pipes
Pine tree
I beam
Drain Excavation Risks and Mitigation Measures
Ingress/ egress area to be covered with steel plate
Excavation work
Activity
Close proximity to existing canal
Soft ground
Failure to guide machineries movement
Stability of ground foundation
Over travel
Excavator topple
Grabber not stuck / struck at bracing
Hazard Cause
Hazard
•
•
• • •
Design excavator access COS for access Inspection ground stability after adverse weather condition Signaler man to guide excavator grabber out of bracing JV staff to perform standing supervision during drainage diversion work.
Mitigation Measure
Drain Excavation Risks and Mitigation Measures
‐ ‐
‐ ‐ ‐
Segar (ES Site Supervisor) Jessica (JV Engineer)
Jessica (JV Engineer) Jessica (JV Engineer) Killi (JV Lift Engineer)
Action Owner
Excavation work
Activity
Uneven ground
Negligence of operator
Constraint of work zone
Hazard Cause
Moving steel plate in congested access
Collision of machinery and Failure to site people. guide machineries movement
Hazard
•
•
• • •
•
•
• Ensure work zone is organized with good housekeeping. Proper barricade and demarcation of work zone to prevent unauthorized entry Establish good communication at all times between operator and signalman Used of tag line to control swaying of load. Provision of steel plate for machinery Provision of signalman and traffic controller to guide machinery movement Provide exclusion zone to control movement of excavator. Define proper access for machines and man.
Mitigation Measure
Drain Excavation Risks and Mitigation Measures
Segar (ES Site Supervisor)
Segar (ES Site Supervisor)
‐ ‐
Segar (ES Site Supervisor) Segar (ES Site Supervisor) Segar (ES Site Supervisor) Segar (ES Site Supervisor)
Segar (ES Site Supervisor)
Segar (ES Site Supervisor)
Segar (ES Site Supervisor)
‐ ‐ ‐ ‐
‐
‐
‐
Action Owner
Provide exclusion zone and banksman to prevent unauthorised entry.
Drain Excavation Risks and Mitigation Measures
Excavation work
Activity
Loose soil between sheet pile drop off.
Hazard Cause
Collapse of loose soil suck between sheet Excavator pile bucket not able to reach pocket of sheet pile.
Hazard
•
• •
Drain
Excavate not more than 1.2 m deep at one go. Workers to crowbar stuck soil between sheet pile. Never send workers into excavation without removing all loose soil between sheet piles.
Mitigation Measure
Drain Excavation Risks and Mitigation Measures
‐ ‐
Segar (ES Site Supervisor) Jessica (JV Engineer)
Action Owner
Excavation works
Activity
Bentonite over flow
•
Sheet pile too • near guide wall •
Provide adequate bund wall to contain bentonite. Close monitoring of bentonite flow from plant side. Deploy watch man throughout the period of de‐sanding.
‐ ‐
‐ ‐ ‐
Exisiting drain to be clear regularly. Ensure ECM is functioning well. Provide sufficient manpower to maintain silt fence. No stock pile on site. Cover any residue spoil.
• • •
Bentonite spill into drain
Heavy rain (Flash flood)
Flooding or clogging of existing drain
Segar (ES Site Supervisor) Jessica (JV Engineer)
Guna (LV ECO) Segar (ES Site Supervisor) Jessica (JV Engineer)
Segar (ES Site Supervisor)
‐
Carryout drain excavation during day time. Proper maintenance of excavator. Provide noise barrier to mitigate noise.
• • •
• •
Poor scheduling of work. Poor maintenance of excavator.
Noise level is above acceptable level
Action Owner
Mitigation Measure
Surface run‐ offs entering drain
Hazard Cause
Hazard
Drain Excavation Risks and Mitigation Measures
Portable treatment plant commissioned to ensure silty water are properly treated prior discharge into public drain.
Drain Excavation Risks and Mitigation Measures
Sufficient manpower deployed to ensure silt are properly maintain.
THANK YOU
Missing Risk: • Moving the steel plates for excavator access Constrain site • Define proper access for machineries and workmen. • Presentation and MS not in line. • Include calculation e.g. track seating on both side of sheet pipe. • MS for strut is not approved yet (comment given in Oct16). • Bentonite may spill into drain (Sheet pile very near to guide wall). • Standing supervision by JV staff.
Comment by LTA
activity.
2) All site personnel should be fully informed and clear with the work process concerning this
and the mitigation measures to be adopted.
1) To identify the potential risk hazards concerning lifting bulky load activities at Entrance B
Objectives of this workshop (no.10):
T309 Site over view
Lifting Activities Risks and Mitigation Measures
Lifting rebar cage in congested work area
Due to the tight area, occasional lifting operation in entrance B involve the management of load swinging over hoarding supervised by our fully competent lifting team.
Lifting rebar cage in congested work area
lifting work
Crane collapse
Activity Hazard
Incompetent operator
Poor crane footage
Over load
Hazard Cause
• •
•
•
• • •
‐ ‐
‐
‐
‐ ‐ ‐
Thiah (HSL Engineer) Killi (JV Lift Engineer)
Shajahan (HSL Lifting Supervisor)
Shajahan (HSL Lifting Supervisor)
Shajahan (HSL Lifting Supervisor) Shajahan (HSL Lifting Supervisor) Shajahan (HSL Lifting Supervisor)
Omar (HSL Safety Coordinator) Desi (JV Engineer) Desi (JV Engineer) Desi (JV Engineer) Killi (JV Lift Engineer)
‐ ‐ ‐ ‐ ‐
• • • • • Implement lift plan and PTW system for Lifting Use only competent lifting personnel ‐ VOC Crane access must be design by PE. Crane access must be certify before usage. Always reinspect crane access after adverse weather All load must be identified before lifting. Adopt 3X3 lifting principle. Always observe max. load radius to avoid overloading. Provide exclusion zone and warning sign to warn off unauthorised workman. Ensure no excavation work to be carried out next to crane access (unless crane access integrity is designed and calculated to cater for it). Do not use degraded crane for lifting work. Conduct weekly boom down to ensure structure integrity of crane.
Action Owner
Mitigation Measure
Lifting Activities Risks and Mitigation Measures
lifting work
Load hit on crane e.g. wind screen
Hit by fallen load
Activity Hazard
‐ ‐ ‐
Inadequate load radius
Congested work area ‐ ‐
Incompetent lifting team ‐
‐
Lift plan got to take min load radius into consideration based on the physical load size. Adopt 3X3 lifting principle Competent rigger Proper communication between lift team members. Deploy additional measures for lift activities in congested area. Do not jerk or swing boom too fast. Provide sufficient tag lines
‐ ‐
‐
‐ ‐ ‐
‐
Ng Bok Soon (HSL Crane Operator) Shajahan (HSL LS)
Shajahan (HSL LS)
Shajahan (HSL LS) Junaet (HSL R/S) Shajahan (HSL LS)
Thiah (HSL Engineer)
Killi (JV Lift Eng) Junaet (HSL R/S) Omar (HSL Safety Coordinator) Shajahan (HSL LS) Shajahan (HSL LS) Ng Bok Soon (HSL Crane Operator) Shajahan (HSL LS) Shajahan (HSL LS)
‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐
‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐
Monthly colour code system No over loading Competent rigger Proper storage of LG Proper maintenance of LG No suspended over workmen at all times. Provide exclusion zone and warning signage. Identify approved lifting points of rebar cage.
Action Owner
Mitigation Measure
Bulky load
Suspended load over people
LG failure
Hazard Cause
Lifting Activities Risks and Mitigation Measures
Diverted hoarding
Lifting Activities Risks and Mitigation Measures
Existing hoarding alignment
Lifting Activities Risks and Mitigation Measures
Traffic control when hoisting material above hoarding
Hazard
Workmen lifting work being crushed by moving cranes
Activity
Failure to control traffic
Blind spot
Hazard Cause
• •
Desi (JV Engineer) Desi (JV Engineer) Killi (JV Lift Engineer) Segar (ES Site Supervisor) Desi (JV Engineer)
‐ ‐ ‐ ‐ ‐
• • Provide exclusion zone and warning signs. Ensure rigger/signaller are deployed to prevent unauthorised entry into lift zone. Never place tools/material on lifting machines. Avoid working in congested work area.
Action Owner
Mitigation Measure
Lifting Activities Risks and Mitigation Measures
THANK YOU
activity.
2) All site personnel should be fully informed and clear with the work process concerning this
the mitigation measures to be adopted.
1) To identify the potential risk hazards concerning Noise Barrier erection at Elliod Walk and
Objectives of this workshop (no.11):
Elliod Walk
Elliod Walk
Existing noise barriers
Noise barrier Erection
Activity
MEWP topple
Hit by fallen object
Fall from height
Risk
Over loading of MEWP
Poor footage
Failure to provide control
•
•
Familiarisation briefing prior appointment.
Licensed MEWP operator.
Provide adequate work platform.
Provide proper access.
• •
Establish PTW‐Height system.
•
‐
‐
‐
‐
‐
Richee Supervisor
Richee Supervisor
Richee Supervisor
Richee Supervisor
JV Safety Dept.
Richee engineer
‐
•
Failure to provide fall protection provision Provision of Fall Protection Plan.
Action Owner
Mitigation Measure
Hazard Cause
Noise Barrier Erection – Elliod Walk
Ensure proper MEWP footage
Noise Barrier Erection – Elliod Walk
Max. 2 person in MEWP bucket
Noise barrier Erection
Activity
MEWP topple
Hit by fallen object
Fall from height
Risk
Over loading of MEWP
Poor footage
Failure to provide control
Firm and compacted ground for MEWP access. Provide adequate exclusion zone and signage. Provide banksman to ensure no authorised
• • •
entry in to work zone.
Max. weight 120kg.
Limit max. 2 person on MEWP.
netting to contain material.
•
•
•
Failure to provide fall protection provision Enveloped MEWP work platform with scaffold
Mitigation Measure
Hazard Cause
Noise Barrier Erection – Elliod Walk
‐
‐
‐
‐
‐
‐
Richee Supervisor
Richee Supervisor
JV Engineer
MEWP Operator
Richee Supervisor
Richee Supervisor
Action Owner
Lifting work
Activity
Crane hit surrounding structures, e.g. silo
Crane Toppling
Risk
•Load hit onto crane
•Instability of working platform
•Failure of loose material equipment/ rebar cages
Hazard Cause
Noise Barrier Erection – Elliod Walk
‐
Richee LS
Richee SC
‐ • Look into min load radius when hoisting bulky items e.g. rebar cage. •Only R/S can give signal. Trade supervisor cannot involved in lifting work.
Richee R/S
Richee LS
Richee CO Richee LS
‐
‐
‐ ‐
•Signaler to communicate with crane operator
•Safety zone established
•Material shall be stacked safely and within stacking limit and load
•Low speed in lifting and lowering
JV Engineer
JV LE
‐
•Approved lifting plan, reviewed by LE and approved by PM
‐
Richee LS
‐
•Lift load by 300mm, stabilized for 3 seconds.
•Lifting points to be identified and approved
Action Owner
Mitigation Measure
Provide exclusion zone and banksman to prevent unauthorised entry.
Noise Barrier Erection – Elliod Walk
Include min load radius in load chart
Lifting work
Activity
Crane hit surrounding structures, e.g. silo
•Banksmen to guide crawler crane movement, ensuring no tracking over drain, trench or uneven ground.
Richee R/S
Richee LS
‐ ‐
JV PM
Richee supervisor
‐
‐
Richee supervisor
‐
•Put in place the lifting permit system and display the relevant details on site.
•Instability of working platform •Ensure no overloading of crane •Failure of loose material •Signaler to communicate with crane equipment/ rebar cages operator •Lack of communication •Approved lifting plan, reviewed by LE and approved by PM •Inadequate supervision and control •Lifting operation supervised by lifting supervisor
JV Superintendent
‐
•Provide adequate hardstanding /firm working platform
crane Toppling
Action Owner
Mitigation Measure
Hazard Cause
Risk
Noise Barrier Erection – Elliod Walk
Welding work with fire screen, extinguisher and fire watchman standby.
Noise Barrier Erection – Elliod Walk
No welding during wet weather.
THANK YOU
By: Tommy Lee/ Peter Nugent
activity.
Date: 26 Apr 17
2) All site personnel should be fully informed and clear with the work process concerning this
and the mitigation measures to be adopted.
1) To identify the potential risk hazards concerning Noise Barrier erection at Laguna Park
Objectives of this workshop (no.12):
Traffic Diversion Stage 1C
Traffic Diversion Stage 1C
Traffic Diversion Stage 1C
Traffic Diversion Stage 1C
Traffic Diversion Stage 1C
Traffic Diversion Stage 1C
Utility Bridge– Siglap link
Temporary Drain Diversion
TD1C
Noise barrier Erection
Activity
MEWP topple
Hit by fallen object
Fall from height
Risk
Over loading of MEWP
Poor footage
•
•
•
Familiarisation briefing prior appointment.
Licensed MEWP operator.
Provide adequate work platform.
Provide proper access.
•
‐
‐
Sayeed Hassan (Richee LS)
Sayeed Hassan (Richee LS)
Sayeed Hassan (Richee LS)
Sayeed Hassan (Richee LS)
‐
Establish PTW‐Height system.
•
‐
JV Safety Dept.
‐
Failure to provide control
Sayeed Hassan (Richee LS)
‐
•
Failure to provide fall protection provision Provision of Fall Protection Plan.
Action Owner
Mitigation Measure
Hazard Cause
Noise Barrier Erection – Laguna Park
Ensure proper MEWP footage
Noise Barrier Erection – Laguna Park
Max. 2 person in MEWP bucket
Noise barrier Erection
Activity
MEWP topple
Hit by fallen object
Fall from height
Risk
Over loading of MEWP
Poor footage
Failure to provide control
Firm and compacted ground for MEWP access. Provide adequate exclusion zone and signage. Provide banksman to ensure no authorised
• • •
entry in to work zone.
Max. weight 120kg.
Limit max. 2 person on MEWP.
netting to contain material.
•
•
•
Failure to provide fall protection provision Enveloped MEWP work platform with scaffold
Mitigation Measure
Hazard Cause
Noise Barrier Erection – Laguna Park
‐
‐
‐
‐
‐
‐
Sayeed Hassan (Richee LS)
Sayeed Hassan (Richee LS)
Jay Cel Galura (JV Engineer)
Atique/ Biswas (MEWP Operator)
Sayeed Hassan (Richee LS)
Sayeed Hassan (Richee LS)
Action Owner
Lifting work
Crane hit surrounding structures, e.g. silo
Crane Toppling
•Material shall be stacked safely and within stacking limit and load
•Low speed in lifting and lowering
•Lifting points to be identified and approved
•Approved lifting plan, reviewed by LE and approved by PM
‐
•Lift load by 300mm, stabilized for 3 seconds.
‐
‐
•Only R/S can give signal. Trade supervisor cannot involved in lifting work.
‐
• Look into min load radius when hoisting bulky items e.g. rebar cage.
operator
‐
‐
Sayeed Hassan (Richee LS)
Sayeed Hassan (Richee LS) Sayeed Hassan (Richee LS) Sayeed Hassan (Richee LS) Sayeed Hassan (Richee LS) Sayeed Hassan (Richee LS)
Jay Cel (JV Engineer)
‐
‐
Killi (JV LE)
‐
Sayeed Hassan (Richee LS)
Action Owner
Mitigation Measure
•Instability of working platform •Safety zone established •Load hit onto crane •Signaler to communicate with crane
•Failure of loose material equipment/ rebar cages
Noise Barrier Erection – Laguna Park Activity Risk Hazard Cause
Provide exclusion zone and banksman to prevent unauthorised entry.
Noise Barrier Erection – Laguna Park
Include min load radius in load chart
Lifting work
Activity
Crane hit surrounding structures, e.g. silo
•Instability of working platform •Ensure no overloading of crane •Failure of loose material •Signaler to communicate with crane equipment/ rebar cages operator •Lack of communication •Approved lifting plan, reviewed by LE and approved by PM •Inadequate supervision and control •Lifting operation supervised by lifting supervisor
crane Toppling
•Banksmen to guide crawler crane movement, ensuring no tracking over drain, trench or uneven ground.
•Put in place the lifting permit system and display the relevant details on site.
‐
•Provide adequate hardstanding /firm working platform
‐
Sayeed Hassan (Richee LS)
Sayeed Hassan (Richee LS) Frank Yi (JV PM) Sayeed Hassan (Richee LS)
‐ ‐ ‐
Sayeed Hassan (Richee LS)
‐
Peter Nugent (JV Superintendent)
Action Owner
Mitigation Measure
Hazard Cause
Risk
Noise Barrier Erection – Laguna Park
Welding work with fire screen, extinguisher and fire watchman standby.
Noise Barrier Erection – Laguna Park
No welding during wet weather.
THANK YOU
Minutes Title: Risk Register Workshop No 12 Date: 26 Apr 2017 Time: 10.00am-11.00am Held at: LTA level 2 meeting room
Chaired by: Tommy Lee/ Peter Nugent Minuted by: Tommy Lee Distribution date: 4 May 17
Attendees list See attached
Apologies list
Page 1 of 3
Minutes ITEM
MATTERS DISCUSSED
1.0
Introduction
ACTION
Risk Workshop will be on Noise Barrier installation at Laguna Park held on 26 Apr 2017 was submitted. This is the no. 12 workshop held.
Info
The complete flow of the process will be demonstrated via a short slide presentation The project superintendent will provide the necessary information required to mitigate risks on Noise Barrier installation.
2.0
Slide presentation on Noise Barrier performed at Laguna Park Area
Peter
2.1
LTA informed JHZH that Lighting shall be sufficient for the street after installation of Noise Barrier.
JHZH
2.2
QPS informed JHZH when tighening the bolt, JHZH shall inform RTO.
JHZH
2.3
QPS informed that the spacing of the support between the noise barrier shall be checked and reinforced.
JHZH
2.4
QPS informed that once inspected, no changes shall be made.
JHZH
2.5
LTA informed that MEWP specification shall be attached in the permit. Safety hardness anchorage point must be identified and all approved personnel to operate the MEWP shall be displayed clearly.
JHZH
2.6
LTA informed that flashback arrester shall be available with the hot works equipment.
JHZH
2.7
LTA informed that utilities cable shall be boxed-up/ encased to prevent damage.
JHZH
2.8
JHZH commented that CCTV location has been identified and proposed.
Info
Page 2 of 3
Minutes ITEM
MATTERS DISCUSSED
3.0
Any Other Matters:
ACTION
The next workshop shall cover TD1 connection to canal works at Entrance A or L-shap D-wall panel installation between Entrance B and C.
4.0
INFO
Next Workshop The next workshop will be scheduled on 4 May 17 @ 10am
Page 3 of 3
All / Info
Drainage Diversion.
2) All site personnel should be fully informed and clear with the work process concerning
and the mitigation measures to be adopted.
1) To identify the potential risk hazards concerning Drainage Diversion TD1 at Entrance A
Objectives of this workshop (no.13):
Drainage Diversion TD1 details
Drain Length: 77.5m (37.3m+ 40.2m) Width: 1.5m Depth: Max. 3.15m
Start: 10 Apr 17 Finish: 18 May 17
Drainage Diversion TD1 details
Scope of works 1. Underground Utility detection/ trial trenching 2. Sheetpiling 3. Installation of working platform 4. Excavation, Installation of walers and struts and access 5. Subgrade compaction 6. Concrete pouring and casting at base 7. Laying Precast Channel and pipe installation and hardcore 8. Sandbag installation at drain/canal connection 9. Water Pump installation upstream to downstream 10. Sheetpile connection to existing drain 11. Backfill and demolish existing drain
Excavation TD1 details
Drainage Diversion TD1 details
Damaged to :
Excavation work
Water pipe. Power grid cables. Telecom cables. High tension cables.
Hazard
Activity
Failure to conduct detection test.
Insufficient marking on site.
Unplanned excavation.
Hazard Cause
If unclear with the finding of services after reaching the 2m limit, conduct further detection to determine the presence of any services below.
•
• • •
• •
Thorough study of utilities drawings Cable detections by qualified LCDW Provide clear utilities marking on site Provide A3 size drawing of utility plan Apply permit to dig and implement “checklist for working near utility” Barricade work area while trenching Contact relevant utility agency for any presence of unidentified utility Always treat utility as `live’ if encountered Only manual digging allowed for trial trench Full time supervision during trial trench
• • • • •
Mitigation Measure
Drain Excavation Risks and Mitigation Measures
Tan WC LCDW Segar (ES Site Supervisor) Hari (ES Engineer)
Leonard Kok/ Tan WC
‐ ‐ ‐ ‐
Action Owner
Provide rigid barricade and warning signage. Provide proper access. Provide toe board. Provide adequate lighting if necessary. Never store material within 1 m from excavation edge. Provide proper shoring (in this case sheet pile) Never allow machineries to park close to excavation trench.
• • • • • •
Excavation collapse
Poor shoring
Missing fall protection provision
•
Put up extra support for the pine tree. Brief workers and excavator operator to be aware of the hazard.
• •
Workers hit by fallen pine tree
Damaged roots
Design and construct strutting work to prevent soil movement. Pre‐con survey on potential infrastructure / house.
Sub‐standard • soil restrain temporary • work
Soil movement affecting existing infrastructure
Mitigation Measure
Hazard Cause
Hazard
Excavation Worker / work material fall into excavation.
Activity
Drain Excavation Risks and Mitigation Measures
‐ ‐
‐ ‐
‐ ‐
‐ ‐
Segar (ES Site Supervisor) Jessica (JV Engineer)
Segar (ES Site Supervisor) Jessica (JV Engineer)
Segar (ES Site Supervisor) Jessica (JV Engineer)
Jessica (JV Engineer) Erin Rosli (SPRO)
Action Owner
Support for the pine tree
GI pipes
Pine tree
I beam
Drain Excavation Risks and Mitigation Measures
Excavation work
Activity
Establish good communication at all times between operator and signalman Used of tag line to control swaying of load. Provision of steel plate for machinery Provision of signalman and traffic controller to guide machinery movement Provide exclusion zone to control movement of excavator.
•
• •
Negligence of operator
Ensure work zone is organized with good housekeeping. Proper barricade and demarcation of work zone to prevent unauthorized entry
•
Constraint of work zone
Failure to guide machineries movement •
•
•
Mitigation Measure
Hazard Cause
Collision of machinery and Uneven site people. ground
Hazard
Drain Excavation Risks and Mitigation Measures
‐ ‐
Segar (ES Site Supervisor) Jessica (JV Engineer)
Action Owner
Provide exclusion zone and banksman to prevent unauthorised entry.
Drain Excavation Risks and Mitigation Measures
Excavation works
Activity
Surface run‐ offs entering drain
Heavy rain (Flash flood)
Poor scheduling of work. Poor maintenance of excavator.
Noise level is above acceptable level
Flooding or clogging of existing drain
Hazard Cause
Hazard
• •
• • •
Existing drain to be clear regularly. Ensure ECM is functioning well. Provide sufficient manpower to maintain silt fence. No stock pile on site. Cover any residue spoil.
‐ ‐ ‐
Guna (LV ECO) Segar (ES Site Supervisor) Jessica (JV Engineer)
Segar (ES Site Supervisor)
‐
• • • Carryout drain excavation during day time. Proper maintenance of excavator. Provide noise barrier to mitigate noise.
Action Owner
Mitigation Measure
Drain Excavation Risks and Mitigation Measures
Sufficient manpower deployed to ensure silt are properly maintain.
Drain Excavation Risks and Mitigation Measures
THANK YOU
Minutes Title: Risk Register Workshop No 13 Date: 4 May 2017 Time: 10.00am-11.00am Held at: LTA level 2 meeting room
Chaired by: Tommy Lee/ Peter Nugent Minuted by: Tommy Lee Distribution date: 12 May 17
Attendees list See attached
Apologies list
Page 1 of 3
Minutes ITEM
MATTERS DISCUSSED
1.0
Introduction
ACTION
Risk Workshop will be on TD1 canal works at Entrance A held on 4 May 2017 was submitted. This is the no. 13 workshop held.
Info
The complete flow of the process will be demonstrated via a short slide presentation The project superintendent will provide the necessary information required to mitigate risks on TD1 canal works.
2.0
2.1
2.2
2.3
Slide presentation on TD1 canal works performed at Entrance A LTA informed JHZH that any close out drain needs to inform LTA project team as it may lead to environmental issues such as mosquito breeding. LTA informed that there should be a standard procedure to evacuate personnel who have accessed into drain.
JHZH informed that the pine tree at Ent A shall be inspected and maintained during the construction phase.
2.4
Peter
JHZH
JHZH
JHZH
JHZH LTA informed to check any impact on D-wall when clearing out the old canal.
2.5
JHZH JHZH informed that only two types of barriers are to be within the site. The fixed and movable type. Water barriers are to be only used for road works.
2.6
2.7
JHZH informed that permanent ECM is in use during construction.
JHZH commented that CCTV location has been identified and proposed.
Page 2 of 3
JHZH
JHZH
Minutes ITEM
MATTERS DISCUSSED
3.0
Any Other Matters:
ACTION
The next workshop shall cover TD1 connection to canal works at Entrance A during 3 months look ahead programme.
4.0
INFO
Next Workshop The next workshop will be scheduled on 19 May 17 @ 10am. It will be a 3 month look ahead programme.
Page 3 of 3
All / Info
such work activities.
2) All site personnel should be fully informed and clear with the work process concerning
and the mitigation measures to be adopted.
1) To identify the potential risk hazards concerning mob and demob of heavy machineries
Objectives of this workshop (14):
Mob / demo heavy machineries
Activity
Workers hit by topple machineries
Machines topple
Hazard
Poor supervision
Poor planning
Hazard Cause
Ensure proper footage Mob/demob on clear weather condition
‐ ‐
Provide exclusion zone and banksman Only relevant staff are allowed to be involved in mob/demob Risk assessment must be approved prior activity Never mob/demob at congested work area Always ensure height limit is <4.5m Operator deployed must be appointed and licensed (if applicable) Machines must be approved by LTA prior mobilisation New machines to comply with LTA “Approval Procedure for new machine”.
‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐
Never mob/demob during wet weather condition
Angle of ramp within machine manufacturer recommendation
‐
‐
Ramp of trailer must be equal or wider than machine crawler belt.
‐
trailers is used for mob / demob
JV LE (Killi) Sub con supervisor
‐ ‐
Sub con supervisor JV LE (Killi) JV super. (Peter) JV super. (Peter) Sub con supervisor Sub con supervisor JV LE (Killi) JV LE (Killi)
‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐
Sub con supervisor
JV LE (Killi)
‐
‐
JV LE (Killi)
‐
JV LE (Killi)
‐
‐
Obtained machineries technical information to ensure fix for purpose
Action Owner
Mitigation Measure
Mob / demobilisation Risk and measures
New machines – Seek approval by submission of relevant document and requirement prior mobilisation.
Mob / demobilisation Risk and measures
Never mob/demob at congested work area
Avoid mob/demob on night shift
Mob/demob on clear and dry weather condition
Ground preparation to ensure stable footage for mobilisation
Mob / demobilisation Risk and measures
• Turning radius of trailers etc
• Length and height of trailers
• Capacity of trailers
trailers <4.5m.
• Total height of loaded machines on
• Weight of machine
• Width of machine
• Width of machine track
FOS)
• Max angle of machines travel (giving
Obtain technical information of machineries such as;
Mob / demobilisation Risk and measures
conditions etc.
• Machineries in good working
submitted and accepted.
• All required documentation
• Approval of machines by LTA / JV
accordance with design
• Area to park and steel plate layout
machineries (giving FOS)
• Ground bearing for heavy
Obtain other information such as;
Provide exclusion zone for mob‐demob activity
Conduct pre‐check prior mob/demob of machines
Mob / demobilisation Risk and measures
Alcohol check on operator involved in mob/demob prior operation
Traffic control in place to ensure smooth transition into worksite
Only relevant personnel are allowed to get involved in mob/demob operation
Mob / demobilisation Risk and measures
Conduct briefing to relevant personnel involved in mob/demob activity
End
activity.
2) All site personnel should be fully informed and clear with the work process concerning this
mitigation measures to be adopted.
1) To identify the potential risk hazards concerning Walkway erection at Elliot Walk and the
Objectives of this workshop (no.15):
Location of walkway Erection ‐ Elliot Walk
Erected walkway: Length: 80m Width: 1.5m
Elliot Walk
Workers work platform
Walk way Erection
Activity
Slip trip and fall
Hit by fallen object
Fall into drain
Risk
Poor footage
Mishandling of I beam
Failure to provide proper access
Hazard Cause
Noise Barrier Erection – Elliot Walk
•
Ensure proper barricades are put up. Provide adequate toe board.
•
Provide proper work access for erectors.
• •
Provide anti skid platform.
Sreedam (LE Supervisor) Sreedam (LE Supervisor)
•
Sreedam (LE Supervisor)
• •
Sreedam (LE Supervisor)
Sreedam (LE Supervisor)
Sreedam (LE Supervisor)
•
Only qualified welders allowed to carry out welding. •
area.
Storage of materials only at designated storage
•
•
•
Sreedam (LE Supervisor)
•
• Provide proper walk way – footage over drain
Action Owner
Mitigation Measure
‐ Property damaged Fire and ‐ Injury to explosion public or workers
Welding work
Hazard Cause
Hazard
Activity
• •
• • • • •
‐ ‐
‐ ‐ ‐ ‐ ‐
Sreedam (LE Supervisor) Sreedam (LE Supervisor)
Sreedam (LE Supervisor) Sreedam (LE Supervisor) Sreedam (LE Supervisor) Sreedam (LE Supervisor) Sreedam (LE Supervisor)
Sreedam (LE Supervisor) Sreedam (LE Supervisor) Sreedam (LE Supervisor) Sreedam (LE Supervisor)
‐ ‐ ‐ ‐
• • • • PPE: Welding face shield, apron and gauntlet Proper housekeeping Method Statements Apply PTW (e.g. hot works) daily before commencements of works Daily welding set checklist/ inspection Standby fire extinguishers and fire blankets Reminder in Tool box meeting Certified welders Remove flammable items (timber, canvas etc.. )from welding premises Monthly inspection of welding equipment Apply Safe Work Procedure
Action Owner
Mitigation Measure
Drain wall bracing Risks and Mitigation Measures
Welding work with fire screen, extinguisher and fire watchman standby.
Walk Way Erection – Elliot Walk
No welding during wet weather.
Manual Handling
Activity
Load dropped on foot
Back strain
Risk
Poor footage
Insufficient manpower
Load too heavy
Hazard Cause
Noise Barrier Erection – Elliot Walk
•
• • •
‐
Sreedam (LE Supervisor)
Sreedam (LE Supervisor) Sreedam (LE Supervisor) Sreedam (LE Supervisor) Sreedam (LE Supervisor) Sreedam (LE Supervisor) Sreedam (LE Supervisor) Sreedam (LE Supervisor) Sreedam (LE Supervisor)
‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐
• • • • Position load (I beam) close to the body. Use two hand rather than one hand. Plan your routes. Proper communication if more than one person are lifting. Introduce proper task rotation. Introduce short and frequent work‐rest cycles. Try using large muscles groups instead of small. Minimized the number of time the load is lifted.
Action Owner
Mitigation Measure
• Minimized the number of time the load is lifted.
• Try using large muscles groups instead of small.
• Introduce short and frequent work‐rest cycles.
• Introduce proper task rotation.
• Proper communication if more than one person are lifting.
• Plan your routes.
• Use two hand rather than one hand.
• Position load (I beam) close to the body.
Manual Handing ‐ Risk Control
Noise Barrier Erection – Elliot Walk
Lift load using thigh and calf muscles. Load maintain close to body.
Ensure firm grip is applied, bend knees and straighten back.
THANK YOU
activity.
2) All site personnel should be fully informed and clear with the work process concerning this
measures to be adopted.
1) To identify the potential hazards concerning TD1C construction and the mitigation
Objectives of this workshop (no.16):
Traffic diversion – 1C
Elliot Walk
Traffic diversion – 1C
Traffic Diversion
Activity
Poor planning
Hazard Cause
Noise
Complaints from stakeholder
Traffic jam / congestion
Lack of coordination
Workers hit by Lack of traffic communication
Motorist confusion
Public confusion
Risk
Risk mitigation
Traffic diversion – 1C
Apply for lane closure Close lane in accordance with COP Traffic control Put up sufficient advance warning signage
• •
parties on personnel on process of diversion.
Briefing session to be conducted with all relevant
parties
Organise “work session” to brief all relevant
LTA
Coordinate closely with relevant authority e.g.
•
•
•
•
Sufficient and clear notification signage to
• motorist – e.g. VMS
Clear and advance notification to all stake holders
•
Mitigation Measure
Jay Cel (JV Site Engineer) Hari (ES Engineer) Jay Cel (JV Site Engineer)
• •
Jay Cel (JV Site Engineer)
• •
Jay Cel (JV Site Engineer)
Jay Cel (JV Site Engineer)
Jay Cel (JV Site Engineer)
Erin (JV SPRO)
•
•
•
•
Action Owner
Traffic Diversion
Activity
Noise
Complaints from stakeholder
Traffic jam / congestion
Lack of coordination •
•
Inform NEA about late traffic diversion work
•
Workers hit by Lack of communication traffic
Carry out traffic diversion off peak hours.
•
Poor planning
Motorist confusion
batons
Traffic controllers to equipped with light
Ensure workers put on reflective vest.
– Potential noise issue
start
Brief TCP to all relevant person prior work
Mitigation Measure •
Hazard Cause
Public confusion
Hazard
Risk mitigation
Traffic diversion – 1C
•
Hari (ES Engineer)
Mike (JV Safety)
Arron (JV ECO)
• •
Jay Cel (JV Site Engineer)
Jay Cel (JV Site Engineer)
•
•
Action Owner
Communication ‐ Authority
Traffic diversion – 1C
Notification to eRMA with the help of LTA project team
LTA communication with Main contractors
Communication – LTA / Main Contractors /Sub contractors
Traffic diversion – 1C
Contractors communication
Main contractors to stake holders
Communication – Stakeholders/residents
Traffic diversion – 1C
Briefing to stakeholders
Presentation to Laguna Park Residents
Communication – Laguna Park resident
Traffic diversion – 1C
Communication – Motorist
Traffic diversion – 1C
Information will change accordingly
Traffic Closure
Traffic diversion – 1C
Deployment of APO at strategic location for traffic controls
Traffic Closures ‐ Auxiliary Police Officers
Traffic diversion – 1C
THANK YOU
Minutes Title: Risk Register Workshop No 16 Date: 22 Jun 2017 Time: 10.30am-11.30am Held at: LTA level 2 meeting room
Chaired by: Tommy Lee/ Peter Nugent Minuted by: Tommy Lee Distribution date: 28 Jun 17
Attendees list See attached
Apologies list
Page 1 of 3
Minutes ITEM
MATTERS DISCUSSED
1.0
Introduction
ACTION
Risk Workshop will be on Traffic Diversion 1C on 22 Jun 2017 was submitted. This is the no. 16 workshop held.
Info
The complete flow of the process will be demonstrated via a short slide presentation The project superintendent together with site engineer will provide the necessary information required to mitigate risks on Traffic Diversion 1C works.
2.0
2.1
2.2
2.3
2.4
2.5
2.6
Slide presentation on TD1C performed at Laguna Park
T309P informed that VMS recovery takes long. JHZH said currently we have 12 batteries on standby and the recovery should be manageable. T309P informed that Elliot at East Coast Park shall be notified on the change of footpath by sending out a simplified circular. JHZH informed walkway at the back is in progress. T309P informed that JHZH shall follow up on the implementation that residents use proper footpath. JHZH and subcon will continue to educate the drivers and pedestrians to use designated crossing, footpath and follow road direction. Once pedestrian path close at Ent D, additional signage may be required. T309P informed that the hoarding needs to be properly closed.
T309P informed that emergency reporting must be in place and use of whatsapp to inform.
JHZH informed a separate session on the 20 hours road closure will be presented to LTA addressing each stage of the traffic control zone.
Peter/ Jay Cel JHZH
JHZH
JHZH
JHZH
JHZH
Note
2.7 T309P mentioned some of the risks are not covered, risks on road works, shifting of bus stop, managing live traffic near siglap link, marine parade road and laguna park exit intersection. It will be conducted covering these risks on 6th Jul 17.
Page 2 of 3
JHZH
Minutes ITEM
MATTERS DISCUSSED
3.0
Any Other Matters:
ACTION
The next workshop shall cover utilities services in general.
4.0
INFO
Next Workshop The next workshop will be scheduled on 29 Jun 17 @ 10am. It will be a weekly programme.
Page 3 of 3
All / Info
such work activities.
2) All site personnel should be fully informed and clear with the work process concerning
and the mitigation measures to be adopted.
1) To identify the potential risk hazards concerning mob and demob of heavy machineries
Objectives of this workshop (18):
Mob / demo heavy machineries
Activity
Workers hit by topple machineries
Machines topple
Hazard
Poor supervision
Poor planning
Hazard Cause
Ensure proper footage Mob/demob on clear weather condition
‐ ‐
Provide exclusion zone and banksman Only relevant staff are allowed to be involved in mob/demob Risk assessment must be approved prior activity Never mob/demob at congested work area Always ensure height limit is <4.5m Operator deployed must be appointed and licensed (if applicable) Machines must be approved by LTA prior mobilisation New machines to comply with LTA “Approval Procedure for new machine”.
‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐
Never mob/demob during wet weather condition
Angle of ramp within machine manufacturer recommendation
‐
‐
Ramp of trailer must be equal or wider than machine crawler belt.
‐
trailers is used for mob / demob
JV LE (Killi) Sub con supervisor
‐ ‐
Sub con supervisor JV LE (Killi) JV super. (Peter) JV super. (Peter) Sub con supervisor Sub con supervisor JV LE (Killi) JV LE (Killi)
‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐
Sub con supervisor
JV LE (Killi)
‐
‐
JV LE (Killi)
‐
JV LE (Killi)
‐
‐
Obtained machineries technical information to ensure fix for purpose
Action Owner
Mitigation Measure
Mob / demobilisation Risk and measures
New machines – Seek approval by submission of relevant document and requirement prior mobilisation.
Mob / demobilisation Risk and measures
Never mob/demob at congested work area
Avoid mob/demob on night shift
Mob/demob on clear and dry weather condition
Ground preparation to ensure stable footage for mobilisation
Mob / demobilisation Risk and measures
• Turning radius of trailers etc
• Length and height of trailers
• Capacity of trailers
trailers <4.5m.
• Total height of loaded machines on
• Weight of machine
• Width of machine
• Width of machine track
FOS)
• Max angle of machines travel (giving
Obtain technical information of machineries such as;
Mob / demobilisation Risk and measures
conditions etc.
• Machineries in good working
submitted and accepted.
• All required documentation
• Approval of machines by LTA / JV
accordance with design
• Area to park and steel plate layout
machineries (giving FOS)
• Ground bearing for heavy
Obtain other information such as;
Provide exclusion zone for mob‐demob activity
Conduct pre‐check prior mob/demob of machines
Alcohol check on operator involved in mob/demob prior operation
Mob / demobilisation Risk and measures
Traffic controllers to guide mob/demob in/out site assisted by LE and relevant staff
Traffic control in place to ensure smooth transition into worksite
Only relevant personnel are allowed to get involved in mob/demob operation
Mob / demobilisation Risk and measures
Conduct briefing to relevant personnel involved in mob/demob activity
End
such work activities.
2) All site personnel should be fully informed and clear with the work process concerning
measures to be adopted.
1) To identify the potential risk hazards concerning recharge well and the mitigation
Objectives of this workshop (19):
Recharge Well Installation
Cooling Tower
Cooling Tower Works
Damaged to :
Recharge well works
Insufficient marking on site.
Unplanned Drilling.
Hazard Cause
Permit to work system
Water pipe. Power grid cables.
Risk
Activity
1) Recharge well– Risk mitigation
Works at Ent. A
•
Trial Trench
LCDW Carry out cable detection
‐
TBM briefing
Peter (JV Super)
Tan WC (JV UE) LCDW Tan WC (JV UE) Peter (JV Super) Peter (JV Super)
‐ ‐ ‐ ‐ ‐
• • • • • Thorough study of utilities drawings Cable detections by qualified LCDW Provide clear utilities marking on site Provide A3 size drawing of utility plan Apply permit to dig and implement “checklist for working near utility” Barricade work area while drilling
Action Owner
Mitigation Measure
Damaged to :
Recharge well works
Telecom cables. High tension cables.
Hazard
Activity
•
•
•
• • • •
‐
‐
‐
‐ ‐ ‐ ‐
Peter (JV Super)
Tan WC
Peter (JV Super)
Peter (JV Super) Peter (JV Super) Peter (JV Super) Peter (JV Super)
Tan WC (JV UE)
‐
• Contact relevant utility agency for any presence of unidentified utility Always treat utility as `live’ if encountered Only manual digging allowed for trial trench Full time supervision during trial trench No mechanical drilling within 3m from identified utilities. Brief utility plan in language understood by the workmen. Provide watch man to watchout for utilities during excavation Senior staff to be involved in site inspection prior to PTW approval.
Action Owner
Mitigation Measure
Mark out detected cable clearly on site. Drill only when identified cables are exposed. Utilities marker are only allowed to shift or remove unless approved by JV UE.
Only manual excavation is allowed for trial trench works
Failure to conduct detection test.
Hazard Cause
1) Recharge well– Risk mitigation
Works at Ent. A
“A’ frame topple
Recharge well work
Fingers / hand caught in rotating parts
Injury to public
Risk
Activity
Incompetent crew
Poor ground condition
Poor footage
Poor mobilization planning
Hazard Cause
Recharge Well work – Risk mitigation
• •
• •
• •
•
‐ ‐
‐ ‐
‐ ‐
‐
JV Lift Engineer Sub‐con lifting supervisor
Sub‐con supervisor Sub‐con supervisor
Sub‐con supervisor Sub‐con supervisor
Sub‐con Engineer
JV Superintendent JV Supervisor
‐ ‐
• • Ensure work assess is planned. Ensure adequate access for work mobilisation and public access. Only competent lifting crew is allowed to involved in mobilisation. PTW‐Lifting approved prior unloading. Provide proper exclusion zone to segregate work and public. Provide warning signs. Provide blinker lights to alert night motorist and /or pedestrian. Ensure footage is firm and level at all times. Never drag load. Lift vertically.
Action Owner
Mitigation Measure
4) Recharge Well work – Risk mitigation
Sample of ground preparation for recharge well
Sample of exclusion zone for recharge well
Risk
Silty water flowing out of work area / public area
Activity
Recharge well work
Incompetent crew •
• •
•
Exposed ground condition
‐
‐ ‐
‐
‐
•
Poor planning
JV ECO
Sub‐con supervisor JV ECO
Sub‐con supervisor
Sub‐con Engineer
JV Superintendent JV Supervisor
‐ ‐
• •
Poor ECM planning
Ensure minimum soil exposed area. All exposed soil to be covered with canvas sheet Silty water to be channel to appropriate sump for pumping into ECM plant. Silt fence to be put up prevent silty water from flowing out of the site. No drilling work during wet weather condition. Ensure designated workers to standby and ensure water treatment plant is powered and properly connected for proper operation. Treatment plant to connect to permanent power instead of generator.
Action Owner
Mitigation Measure
Hazard Cause
Recharge Well work – Risk mitigation
Portable treatment plant commissioned to ensure silty water are properly treated prior discharge into public drain.
Drain Excavation Risks and Mitigation Measures
Sufficient manpower deployed to ensure silt are properly maintain.
End
Minutes Title: Risk Register Workshop No 19 Date:7 Sep 2017 Time: 11.00am-12.00am Held at: LTA level 2 meeting room
Chaired by: Peter Nugent/ Jong Minuted by: Tommy Lee Distribution date: 29 Sep 17
Attendees list See attached
Apologies list
Page 1 of 2
Minutes ITEM
MATTERS DISCUSSED
1.0
Introduction
ACTION
Risk Workshop will be on Recharge well. The complete flow of the process will be demonstrated via a short slide presentation
Info
The project superintendent, Peter Nugent will present the presentation and the mitigation measures.
2.0
Slide presentation on Recharge well
2.1
T309P reminded JHZH to submit a set TRA audit records on a weekly basis.
Peter/ Jay Cel JHZH
TRA audit records was submitted on 3 Oct 17.
2.2
2.3
3.0
T309P commented on the filling and taking measurement for the water in the recharge well. The recharge well will be connected to the PUB water source. It is controlled by controlled valve, with flow meter and pressure gauge for switching on. For monitoring of water level and pressure, piezometer and water standpipe will be in place. Daily monitoring of water level will be carried out.
T309P requested to provide drawings for the recharge well. It will be provided in the submission.
JHZH
Any Other Matters: The next workshop topic will be proposed accordingly.
4.0
JHZH
INFO
Next Workshop The next workshop will be scheduled on 5 Oct 17. . It will be a weekly programme.
Page 2 of 2
All / Info
Sep 2017
Tommy Lee, Risk Management Facilitator
Civil Construction Safety Submission (CNSS) - Package 2
Construction of Siglap Station Thomson-East Coast Line
Contract T309
2
Doc no. T309-JHZH-PRS-PWD-GEN-0002
› Hazards and Mitigation Measures
› Instrumentation and Monitoring
› Construction Stage and Programme
› Geological Profile
› Value Engineering
› Optimization of Traffic Diversion
• Project Overview- Package 2
• PSR Committee endorsement scope
• Objectives
• Key Organization
• Major Key Dates
Content
3
Doc no. T309-JHZH-PRS-PWD-GEN-0002
: 30 June 2020 : 30 October 2020 : 28 February 2023
BSC- Entrance A
BSC- Entrance B,C,D
Completion of the Whole of the Works
Doc no. T309-JHZH-PRS-PWD-GEN-0002
: 30 June 2020
BSC of Station
4
: 17 March 2016
Contract Award
Major Key Dates
QP Design:
5
Doc no. T309-JHZH-PRS-PWD-GEN-0002
RC Subcontractor: China Jiangsu Construction Corporation
QP Supervision: LYL Consultants
One smart Engineering
Aurecon Singapore
Noma Consulting (Temporary Structure)
ARUP (Permanent Structure)
Main Contractor: John Holland Zhen Hua Joint Venture (JHZHJV)
Land Transport Authority
Client:
Key Organization
To demonstrate the control measures to mitigate these risks
To address the construction hazards and their mitigation measures
•To seek PSR committee’s endorsement to commence the works
6
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Package 1 Diaphragm wall, bored piles, ground improvement and enabling works Endorsed – Sep‘16 Package 2 Bulk Excavation, Strutting, Reinforced Concrete works, Flood Protection Plan. Submission – Sep’17
Our Submission for PSR committee’s Endorsement for Construction Activities are:
PSR Comm. Endorsement scope
To demonstrate the residual hazards transferred from Civil DSS
Objectives of Civil Construction Safety Submission are
Objectives
7
Package 2 – Project Overview
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Year 2016 to 2023
Project Timeline
8
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Package 2
• • • • •
U-shape canal upgrade
Box Culvert
Box Drain
Entrance D
Entrance A
9
Entrance C
Entrance B
Doc no. T309-JHZH-PRS-PWD-GEN-0002
1. Total Length: 350m 2. Top-down Station box (220L x 39W x 21D) 3. Cut & Cover Tunnel/Subway (77L x 6W x 21D) 4. Canal Upgrading (length - 157m) 5. 2 nos. Access Bridges to VS
Main Station
4 Entrances (Ent. A,B,C,D) 4 main slabs (Roof, Concourse, Platform, Under Platform) Parameter Dwall (0.8m/1.2m thick) Top Down Method Final Excavation level 22.6m
T309- Siglap Station
Victoria School
Villa Marina
Kee Sun Avenue
T309- Stakeholders
Laguna Park
Marine Parade Road
Elliot at East Coast
10
Doc no. T309-JHZH-PRS-PWD-GEN-0002
St Andrew’s Autism School
- 11 Traffic Diversions required till final reinstatement
Stage TD1C
WORK ZONE
• • • • • •
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Improved the overall safety on the project Separates the Construction Area to Public Elimination of High Risk Works Reduce complex temporary works Reduce congested work zone Reduce public crossing the live traffic
- 3 Traffic Diversions required till final reinstatement
Work Zone
Optimization of Traffic Diversion
Zone 1
Sheetpile
Zone 2
Sheetpile
Zone 3
Zone 4
Traffic Diversion TD1C
Value Engineering (Main Station)
Zone6
1
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Zone5
D-wall
The original Design
Value Engineering (Main Station)
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Value-Engineering Design
Cooling Tower/ Main Station
Geological Profile
14
Doc no. T309-JHZH-PRS-PWD-GEN-0002
D-wall toe level – 77-80 m RL
OA – 87-97 m RL
KF – 90-103 m RL
15
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Package 2 – Construction Stage and Programme
Nov 2018 May 2019 Apr 2019
Excavate & Construct Under Platform
Construct Platform
Internal Structure Works (incl. Ent A,B,C,D)
Sep 2020
Nov 2019
Sep 2019
Jul 2019
Mar 2019
Finish Date
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Jul 2018
Excavate & Construct Concourse
16
Nov 2017
Start Date
Excavate & Construct Roof Slab
Activity
Construction Stage and Programme
Zone 1
Zone 3
Zone 4
Traffic Diversion TD1C
Y
Zone6
Entrance B
1
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Zone5
Entrance C
Permanent openings (Use as construction openings)
Construction openings
Zone 2
Entrance D
Entrance A
Y
Construction Stage and Programme
103.3m RL 101.5m RL
Main Station
Sheet Pile
Section Y-Y
3.5m
Sheet Pile
Sheet Pile
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Cooling Tower
Excavate to Roof level at Cooling Tower
Main Station
98.00m RL
103.3m RL
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Cooling Tower Section Y-Y
Construct Roof Slab (Cooling Tower)
Main Station
98.00m RL
103.3m RL
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Cooling Tower Section Y-Y
Construct Roof Slab (Main Station)
Main Station
98.00m RL
103.3m RL
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Cooling Tower Section Y-Y
Stage 1D
Waterproofing above roof slab Backfilling to Ground level Stage 1D Road works, Implement Stage 1D
98.00m RL
103.3m RL
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Cooling Tower Section Y-Y
Stage 1D
Main Station
Excavate to Concourse
90.90 m RL
98.00m RL
103.3m RL
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Cooling Tower Section Y-Y
Stage 1D
Main Station
Construct Concourse Slab
Main Station
90.90 m RL
98.00m RL
103.3m RL
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Cooling Tower Section Y-Y
Stage 1D
Excavate to Under Platform Level
Main Station
82.63m RL
90.90 m RL
98.00m RL
103.3m RL
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Cooling Tower Section Y-Y
Stage 1D
Construct Under Platform Level Slab
Main Station
82.63m RL
90.90 m RL
98.00m RL
103.3m RL
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Cooling Tower Section Y-Y
Stage 1D
Construct Platform Slab Skin wall (1st lift) and Platform
Main Station
82.63m RL
90.90 m RL
98.00m RL
103.3m RL
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Cooling Tower Section Y-Y
Stage 1D
Construct Skin wall 2nd lift RC internal walls from Platform to Concourse
Main Station
82.63m RL
90.90 m RL
98.00m RL
103.3m RL
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Cooling Tower Section Y-Y
Stage 1D
Construct Skin and RC internal structures from Concourse to Roof
Main Station
82.63m RL
90.90 m RL
98.00m RL
103.3m RL
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Cooling Tower Section Y-Y
Stage 1D
Construct RC Structures to Threshold level Above ground structures
4a
3a
Stage 1C Road Diversion
4a
3a
5
4
3
2
1
Sequence
4
2
Activity Name
[TD1C] [Z2] [GL 1 to 6, A to E] Construct Roof Slab
[TD1C] [Z2] [EA] Construct Roof Slab
[TD1C] [Z6] [EB] Construct Roof Slab
[TD1C] [Z4] [GL 15 to 18+ / A to E] Construct Roof Slab
[TD1C] [Z3] [GL 6 to 15 / A to E] - Construct Roof Slab
[TD1C] [Z4] [CT] Construct Roof Slab
[TD1C] [Z3] [CT] Construct Roof Slab
3
1 5
04-May-18
05-Mar-18
07-Feb-18 06-Mar-18
22-May-18
20-May-18
14-Apr-18
20-Jan-18
09-Jan-18
Finish
09-May-18
15-Apr-18
26-Jan-18
10-Dec-17
07-Dec-17
Start
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Construction Stage and Programme
3
2
Stage 1D Road Diversion
6
5
4
3
2
1
Sequence
[TD1D] [Z6] [EB] Construct Remaining Roof Slab
[TD1D] [Z5] [EC] Remaining Structure Works to Roof
[TD1D] [Z5] [EC] Construct Roof Slab
[TD1D] [Z1] [ED] Construct Roof Slab
[TD1D] [Z2] [GL 1 to 3, A to C] Construct Roof Slab
[TD1C] [Z5] [EC] [SUB] Construct Roof Slab
Activity Name
4
1 5
6
15-Mar-20
31-Oct-19
18-Feb-19
22-Jan-19
01-Jan-19
29-Sep-18
Start
28-Mar-20
09-Dec-19
03-Mar-19
18-Feb-19
21-Jan-19
01-Nov-18
Finish
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Construction Stage and Programme
32
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Package 2 – Instrumentation and Monitoring
30
Settlement contour
33
30
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Monitoring for stakeholders
Instrumentation and Monitoring
34
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Monitoring for Station works
35
Instrumentation and Monitoring
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Monitoring for Utilities
36
Traffic Diversion 1C
Instrumentation and Monitoring
Doc no. T309-JHZH-PRS-PWD-GEN-0002
37
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Package 2 – Hazards and Mitigation Measures
Excavation and Strutting RC Works Box Culvert Works
5 18 52 2
A B C D
-
No.
Risk Class
Summary Initial Risk Class
38
A B C D
Risk Class
0 0 74 3
No.
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Intolerable Undesirable Tolerable Acceptable
Summary of Residual Risk Class
Civil Construction Safety Submission (CNSS)
39
Doc no. T309-JHZH-PRS-PWD-GEN-0002
ES1.Instability of ERSS/ temporary Works ES2.Ground instability during excavation ES3. Prevention of excessive wall deflection and ground movement ES4.Noise Protection Measures ES5.Vibration Protection Measures
Associated with Excavation and Strutting Works
Hazards
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Sufficient review of instruments monitoring results by Instrument Engineer and QPS
Independent Instrumentation Monitoring Specialist
Ensure construction sequence is in accordance with design
ES1. Instability of ERSS/ temporary Works
Instability of temporary works (station boxes or linkways)
Hazard
Hazard Cause
• Poor workmanship
• Insufficient control of the works
•Insufficient monitoring
•Design implementation incorrect
Identified Risks
41
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Good control on the welding quality – UT for butt weld & MPT for fillet weld
•Ensure correct grade, dimensions of steel materials used in strutting system as per details construction drawings.
•Close coordination and required actions to be carried out by CM
•Review of monitoring results by instrumentation engineer and QPS
•Independent Instrumentation / monitoring to monitor strut loads
•Ensure construction sequence is in accordance with design
Mitigation Measures
ES1. Instability of ERSS/ temporary Works
-
-
42
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Recharge well to be installed before excavation commences
ES2. Ground instability during excavation
-
43
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Monitor alert level and suspension level of instruments Ensure all instrumentation are in place before excavation commencement Excavation sequence in accordance with design
ES2.Ground instability during excavation
Ent D
Ent C
Subway
44
Locations of strain gauge
Location of Load Cell Doc no. T309-JHZH-PRS-PWD-GEN-0002
Ent B
Monitor inclinometer (daily) and strut load readings (real-time)
Independent monitoring of ERSS including struts loads, and joint review of instrumentation results by Instrumentation Engineer & QP(S).
Excavation sequence in accordance with design
ES3.Excessive wall deflection and ground movement
Zone 1
Noise Barrier
Zone 2
Zone 3
Zone 4
Traffic Diversion TD1C
ES4. Noise Protection Measures
Zone6
4
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Zone5
46
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Equipment and machinery with noise insulating material Setting up of noise barrier around work site Monitoring of site noise level and keep within limits Adhere to designated work hours Keeping stakeholders informed on activities and gather feedback
ES4. Noise Protection Measures
Zone 1
Zone 2
Noise Monitoring
Zone 3
Zone 4
D-wall and buttress wall remove by wire cut
ES5. Vibration Protection Measures
Zone6 4
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Zone5
Wirecutting of D-wall
Hazard
Hazard Cause
•Breakage of wire during cutting
Identified Risks
48
Doc no. T309-JHZH-PRS-PWD-GEN-0002
• Hoarding/ Protection shield of wire breakage and loose material
• Approved safe work procedure in place
• Machinery to be maintained as per manufacturers requirements
• Trained and experienced operator to utilise machinery only
• Proper guard of around moving parts of the machine
• Ensure safe distance to wire saw is in place during cutting process (remote control when possible)
• Dedicated exclusion zone maintained around work area, no access by personnel during wire cutting process
Mitigation Measures
ES5. Vibration Protection Measures
49
Doc no. T309-JHZH-PRS-PWD-GEN-0002
RC1.Fall from Height RC2.Working in Confined Space, Hazardous atomsphere RC3. Formwork Structural Failure RC4. Failure in Concrete Placement RC5. Water Leakage between D-wall and Slab
Associated with RC Works
Hazards
Zone 1
Zone 3
Y
Zone 4
Traffic Diversion TD1C
Y
Zone6
Entrance B
5
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Zone5
Entrance C
Permanent openings (Use as construction openings)
Construction openings
Zone 2
Entrance D
Entrance A
RC1- Fall from Height
-
-
TYPICAL EXAMPLE OF CONSTRUCTION OPENINGS AND REQUIREMENT FOR EDGE PROTECTION
Guard rail
Retaining wall
51
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Retaining Wall to be cast (Roof Slab level) Guard Rail to be installed (Concourse level and below)
RC1 - Fall from Height
Fall from Height - Construction openings - Penetration covers
Hazard
• Penetration covers to be mechanically secured
•Penetration covers not secured
52
Doc no. T309-JHZH-PRS-PWD-GEN-0002
• Maintain clear exclusion zone for no storage of material near openings
• Placing of signages to warn of lifting activities/ drop objects around openings
• Proper access/ ladders/ platforms as provided in designated locations
• Construction openings to be secured with guard rail/ cast with retaining wall (secured with edge protection)
•Temporary Construction Openings not secured
Mitigation Measures • Ensure edges are barricaded (with netting) when possible
Hazard Cause
•Working at edge
Identified Risks
RC1. Fall From Height
Working in confined space or constrained site
Hazard
Hazard Cause
•Handling of temporary steelwork within confined site
•-Craning steel members through restricted worksite openings
•Hazardous atmosphere
•Ventilation insufficient, Lighting insufficient
•Staff identification not accounted
Identified Risks
53
Doc no. T309-JHZH-PRS-PWD-GEN-0002
•Signal man to guide operation, tag line when possible
•Dedicated site safety officer
•Securing material on site, inspection by lifting supervisor on lifting prior to lifting
•Planning of storage and handling routes within crane age access
•Barricade of work zone
•Approved lifting plan and method statement in place
• Provision of gas detectors and monitoring every 4 hours interval
• Provision of adequate pumps and blowers, Installation of ventilation duct
•Adequate construction works and ventilation
•Design adequate space for machinery
•Installation of lighting
• Implement Confined Space permit systems
• Implementation of RFID system to monitor the movement of workers working inside station box
• Adhere to confined spaces specification
Mitigation Measures
RC2- Working in Confined Space
Doc no. T309-JHZH-PRS-PWD-GEN-0002
ENT “A” ,COOLING TOWER & ENT “B” EVACUATION ROUTE
Emergency Response
Doc no. T309-JHZH-PRS-PWD-GEN-0002
ENT D & SIGLAP LINK EVACUATION ROUTE
Emergency Response
Wall System Formwork 56
Temporary Propping as part of Design (Stairshaft landing, bottom up construction)
RC3. Formwork Structural Failure
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Scaffold System
-Use of insufficient or poor quality material and poor design
-Installation not as per PE shop drawings
•Design/ installation not being certified by PE
•Ground foundation unstable
•Early formwork removal
Hazard
•due to poor workmanship
•Structural failure due to use of insufficient or poor quality material and poor design
•Ground not compacted to specification, due to insufficient lining of blinding concrete
•The formwork dismantling shall be cordoned off in order to prevent unauthorized entry into work area
•Structural failure due to unauthorized removal prior to concrete achieving design strength
57
Doc no. T309-JHZH-PRS-PWD-GEN-0002
• Emergency response planning including Contingency planning
• Ensure material and design and approved and installed accordingly
•Supervision by engineer to ensure installation is as per shop drawings and according to method statement and RA assessment
•Inspection by PE prior to concreting
•Formwork design shall be endorsed by PE
Ground shall be compacted and level/ cast with blinding concrete
•Proper formwork removal sequence to be followed
•Temporary props are to be secured and not removed unless approved by engineer
•Ensure concrete strength is achieved prior to removal
•Removal inspection checklist to be endorsed
•Formwork removal shall be approved by formwork supervisor.
Mitigation Measures
Hazard Cause
Identified Risks
RC3. Formwork Structural Failure
58
Concrete will typically be placed via concrete boom pump and static lines
Doc no. T309-JHZH-PRS-PWD-GEN-0002
RC4. Failure in Concrete Placement
Concrete Fall from Height Placement with boom/ line/ stationary pump
Hazard
Hazard Cause
•Fatigue management of workers
•Hit by loose concrete
•Concrete pipe burst or choked during concrete casting
•Penetration covers not secured
•Failure of static •Temporary Construction line while Openingsconcrete pumping
•Working •Poor ground at edge conditions
Identified Risks
Additional bin to catch the spillage
59
Doc no. T309-JHZH-PRS-PWD-GEN-0002
• Ensure workers are working on a shift and provide adequate shades/ protection/ water to keep workforce hydrated and alert
• - Use of gunny sack/ bend the rubber hose
• - Use of tagline (for rubber hose)
• If choked or pipe burst, stoppage of work and isolate the issue. Address the issue through close coordination between concrete pump operator and supervisor.
• Static line pipe to be fixed to temporary concrete anchors in accordance with manufacturers recommendations
•
• Ensure ground condition is survey necessary COS is edges are barricaded whenand possible obtained (if applicable) • Use of safety harness • Static line shall be regularly maintained and checking during pre• Construction openings to be covered when not in use at all times start and regular inspections. • Penetration covers to be secured • Spare lengths of rubber concrete hose and steel static line pipe • Proper access/ on ladders/ platforms as provided to be available site during concrete pour • Placing ofcoupling signagesoftostatic warnline fall from height locations Sufficient
Mitigation Measures
RC4. Failure in Concrete Placement
60
Doc no. T309-JHZH-PRS-PWD-GEN-0002
RC5. Water Leakage between D-wall and Slab
Leakage at the interface between Dwall and Roof/ Concourse
Hazard
• Define levels of leak treat accordingly, mark affected area
• Honey comb in concrete
61
Doc no. T309-JHZH-PRS-PWD-GEN-0002
• Approved method statement for different D-wall leakage scenarios in place
• Apply grouting/ injection on affected zone
• Review suitability of grouting system
Perform regular inspection during RC work activities
•
• Poor workmanship
Mitigation Measures • Ensure all D-wall activities control are in place (e.g.water-stop joints, concrete pouring and curing, alignment, rebar placement)
Hazard Cause
• Waterstop joints not continuous
Identified Risks
RC5. Water Leakage between D-wall/ Roof or Concourse
Canal Upgrading Works
62 62
Doc no. T309-JHZH-PRS-PWD-GEN-0002
63
BC1. Flood from Opera Estate Canal BC2. Silty Water Discharge into Canal BC3. Damage to utility bridge
Associated with Box Culvert Works
Hazards
Doc no. T309-JHZH-PRS-PWD-GEN-0002
64
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Sheetpile to enclose the work area and prevent flooding
BC1. Flood from Opera Estate Canal
Discharge into Canal/ Drain during heavy rain
Hazard
•ECM Plan in place
•Surface run off, construction material (bentonite, concrete, grout)
65
•Contingency planning
Doc no. T309-JHZH-PRS-PWD-GEN-0002
•Regular inspection on site by ECO at affected zones
•Silt fence protection at all open drains/ canal
•Insufficient control on site
Mitigation Measures •Concrete/ Retaining wall for flood mitigation
Hazard Cause
•Heavy rain
Identified Risks
BC2- Silty Water Discharge into Canal
66
BC3- Damage to utility bridge
Doc no. T309-JHZH-PRS-PWD-GEN-0002
Damage to LV cable HV cable
Damage to water pipe
Hazard
Hazard Cause
•Excavator hitting protection pipe
•Accidental damage
•Excavator hitting protection pipe
•Accidental damage
Identified Risks Mitigation Measures
67
Doc no. T309-JHZH-PRS-PWD-GEN-0002
• Positive identification of utiltiies
• Serve affect resident notice during water diversion works
• Apply Utilities service damage plan and utilities prevention plan
• Clear demarcation of work zone
• Ensure team is at work zone within 1hour of issues
• Additional cables to create slag and prevent tension
• Use of heavy duty flexible hose to protect cable
• Bracket to be fabricated and installed according to design and use of correct material
• Positive identification of utiltiies
• Elbow joints to be haunched
• PUB Technician to supervise valve closing operation
• Supply of water bag/ water tank during water disruption by PUB
• Apply Utilities service damage plan and utilities preventation plan
• Clear demarcation of work zone
• Ensure team is at work zone within 1hour of issues
• Bracket to be fabricated and installed according to design and use of correct material
BC3- Damage to utility bridge
68
Thank You
Doc no. T309-JHZH-PRS-PWD-GEN-0002
No 1 Hamsphire Road Block 1 Level 4, Singapore 219428 Tel: (65) 6396 2178
PSR(SUB-COMMITTEE) MEETING
Page 1 of 15 Prepared by : Tan Ming Wooi, PRE(GTT) Vetted by (PRMGTT)
: Dr Chepurthy Veeresh
Approved by : Ow Chun Nam (representing Chairman) AGENDA: 1. Presentation on T315 CNSS for Underpass and A&A Construction with Related Viaduct and Stitching Works 2. Discussion on T315 CNSS for Underpass and A&A Construction with Related Viaduct and Stitching Works 3. Presentation on T309 CNSS Bulk Excavation, Strutting, Flood Protection Plan, Decking and Reinforced Concrete Works 4. Discussion on T309 CNSS Bulk Excavation, Strutting, Flood Protection Plan, Decking and Reinforced Concrete Works 5. Presentation on T212 CNSS CP Permanent Lining & Waterproofing Works 6. Discussion on T212 CNSS CP Permanent Lining & Waterproofing Works 7. Follow-Up Presentation on T301 CNSS Amendment on Bulk Excavation on Rail Depot – Package 2a 8. Discussion on T301 CNSS Amendment on Bulk Excavation on Rail Depot – Package 2a 9. Confirmation of 167th PSR Sub-Committee Minutes of Meeting 10. Next Meeting MEETING ATTENDED BY: PSR (Sub-Com) Members: Ow Chun Nam Song Siak Keong Dr Chepurthy Veeresh Andrew Tan Absent with Apologies: Paul Fok Choo Chai Foong
Ad-hoc Participants: D(TUN) D(CT3)DTL3 PRM(GTT) Representing DDGTT M(SH) Representing DDSA GDIDE DyGDIDE(ISP)
Aman Aboobucker Diong Kim Jun Tan Jui Hock Heng Kok Hui
LCBC LCBC LCBC Tritech
Chuah Eow Tong
Tritech
Hector Perez Ooi Ah Choon Simon L
LTA LTA JHZH
PSR SUB-COMMITTEE MEETING Meeting No: 165 No
Page 2 of 5 Report By: Tan Ming Wooi
Item Discussed
Goh Kok Hun Rama Venkta Chuah Han Leong Liu Png Hock Chelliah Murugamoorthy R Jaysankar Henry Foo Goh Kok Hwa Tan Kian Tong Tan Kok Jin Kulaindran Ariaratnam Chang Kin Boon Simon Hoblyn Alvin Soong
Action
Frank Yi JHZH Chan Gi Jeong JHZH Tommy Lee JHZH Aris Himawan Arup Yong Kuan Yau LYL/QPS Vima LTA Juthamard Subongkot LTA Kong Xiaolei LTA N. Nakamura SKS Masaaki Suzuki SKS RKChaudhary Kenhin Ei Ei Nue Calibre Danilah Norahim Lee Calibre Sharul Rizal LTA Mohiadeen LTA Lin Su Qi LTA Darryl Chen LTA Kek Shu Hua LTA Wong Dikai LTA Jay Jeong GS R. Sarvananthan GS M. Givakumar GS Dae Young You GS Richard Ting TYLin Khoo Kok Sing TY Lin Hu Xiang Bin R&K Siew Kim Choi R&K Hoon Yat Meng LTA CC: Chairman PSR(Road & Rail), Secretary PSR (Road), Secretary PSR (Rail)
3 3.1
4
DD(GTT) DCL D(RLE) DSPP D(CT1)DTL3 DCPRF D(CT3)TEL D(CT1)TEL D(CT6)TEL D(CT2)TEL 1D(CT5)TEL D(CT2)DTL3 1DD(TUN) DDSA
Presentation on T309 CNSS Bulk Excavation, Strutting, Flood Protection Plan, Decking and Reinforced Concrete Works Mr Tommy Lee (RMF) from John Holland Zhen Hua JV (JHZH) presented on T309 CNSS Bulk Excavation, Strutting, Flood Protection Plan, Decking and Reinforced Concrete Works.
Info
Discussion on T309 CNSS Bulk Excavation, Strutting, Flood Protection Plan, Decking and Reinforced Concrete Works
PSR SUB-COMMITTEE MEETING Meeting No: 165 No
4.1
Page 3 of 5 Report By: Tan Ming Wooi
Item Discussed
D(TUN) raised concerns about the following risk whether these have been addressed: -
Action
T309
Bored pile necking Bored pile not in position Water-stop bar
JHZH to revert and clarify. JHZH Response: Bored pile necking and bore pile not in position risks will be added. Water stop bar risks have been addressed in the risk register. 4.2
D(TUN) reminded T309 to include a shying distance when placing barriers on the roads to prevent motorist from the tendency of going into other’s lane.
Info
JHZH Response: Will comply. 4.3
D(TUN) pointed out that AE should come out with a new risk register for the value-engineering. JHZH to revert and clarify.
T309
JHZH Response: JV will request AE for a new register for value engineering. 4.4
JHZH concurred with D(TUN)’s advice to provide a good clutching sheet pile system to ensure water-tight structure.
T309
JHZH Response: Current sheet pile system is using a clutch interlocking method. 4.5
D(TUN) queried about the type of ventilation system that JHZH would be providing. JHZH to revert and clarify.
T309
JHZH Response: Will be using force and extraction ventilation method. 4.5
D(TUN) spoke about the risk associated with working inside a confined space and asked whether JHZH has address the following: -
Evacuation (track the worker at entry and exit point through RFID and biometric system) Lifting Concreting Management of fire hazard (no tarpaulin sheets allowed and duct must be fire-retardant)
T309
PSR SUB-COMMITTEE MEETING Meeting No: 165 No
Page 4 of 5 Report By: Tan Ming Wooi
Item Discussed
-
Action
Ventilation (air change, chiller, etc.) Fire staircase route
JHZH to revert and clarify. JHZH Response: All the above risks have been addressed in the risk register 4.6
D(TUN pointed out that leakages of diaphragm wall must be addressed immediately and not wait until the end of excavation. It must be carried It must be sealed off before proceeding to the next stage of excavation. JHZH informed they would conform.
Info
JHZH Response: Will comply.
4.7
D(TUN) asked JHZH to ensure the subgrade underlying the roof slab must be sufficient to support the slab because of the presence of Kallang Formation. JHZH noted they would conform.
Info
JHZH Response: Will comply.
4.8
On the issue of cutting the diaphragm wall, D(TUN) was concerned about the vibration induced by the hacking of the diaphragm wall would damage the waterproofing membrane. JHZH to revert and clarify.
T309
JHZH Response: Hacking and cutting of diaphragm wall method will be used. Both options and the waterproofing membrane detailing will be reevaluated prior to commencement of works. 4.9
D(TUN) reminded JHZH to capture whatever that’s left behind of the temporary works after the construction to be reflected in the as-built drawing. JHZH noted they would conform.
Info
JHZH Response: Will comply and is currently in practise.
4.10
JHZH concurred with D(TUN)’s suggestion to ensure the excavation area in the station should be lighted up just as good as what is practice (100 lux) in the tunnel. JHZH Response: Noted.
Info
PSR SUB-COMMITTEE MEETING Meeting No: 165 No
4.11
Page 5 of 5 Report By: Tan Ming Wooi
Item Discussed
D(TUN) reminded to have dedicated power points and not loose points on the floor which can cause risk of tipping hazard due to cables laying around on the floor. Cables like that could cause electrocution if floor is wet. JHZH noted they would conform.
Action
Info
JHZH Response: Cables will be hung on mounted brackets and sufficient power points will be allocated for tapping of power within the work zone premises.
4.12
D(TUN) raised concerns about pipe burst connecting the concrete boom pump especially at the joint which is prone to breakage if the joint is the groove type. He asked JHZH to check on this. D(CT3)DTL3 added that the line could only be used for a certain period of time Checking must alert the sub-contractor to change it if necessary. JHZH noted and would engage the right sub-contractor.
Info
JHZH Response: Joints will be inspected periodically and change when necessary. JV had engaged CJCC as the RC works subcontractor. 4.13
D(TUN) cautioned not to use tarpaulin sheet to cover concrete during curing as the material is flammable. JHZH noted and would conform.
Info
JHZH Response: Will comply. 4.14
IR mentioned that all other comments given to T309 CNSS Bulk Excavation, Strutting, Flood Protection Plan, Decking and Reinforced Concrete Works had been addressed. IR recommended PSR SubCommittee to endorse the CNSS for T309.
Info
4.15
PSR Sub-Committee endorsed T309 CNSS Bulk Excavation, Strutting, Flood Protection Plan, Decking and Reinforced Concrete Works subject to comments and recommendations made.
Info
Sheet Piling.
2) All site personnel should be fully informed and clear with the work process concerning
to be adopted.
1) To identify the potential risk hazards concerning Sheet Piling and the mitigation measures
Objectives of this workshop (no.21):
1
Total distance
55m
22.6m
97.6m
65.3m
8.3m
ID
1
2
3
4
5
4
2 3
21 Nos
163 Nos
244 Nos
57 Nos
138 Nos
Sheetpile qty
Sheet Piling locations and programme (ERSS)
5
12m
6m
6m
12m
12m
Sheetpile length
15 Dec – 18 Dec 17
6 Dec ‐14 Dec 17
21 Nov‐ 5 Dec 17
15 Nov‐ 20 Nov 17
6 Nov‐ 14 Nov 17
Construction Timeline
Section of Sheet Pile
1. 2. 3. 4. 5. 6. 7. 8. 9.
Mobilization/ Demobilization of machinery Collision of Machinery and Site staff Accidental dislodge of sheet pile during driving Welding‐ Fire damage Failure of lifting mechanism Noise Protection Measures Damaged to: 1) Water pipe 2) Bentonite pipe Gaps in sheet piles Sheetpile stacking
Hazards
Mobilization of Machinery
Hazard
Installation Mobilization of sheet and pile Demobilization of machinery
Activity
Mitigation Measure ‐ Ramp width to be min. track width of crane ‐ Experience operator ‐ Banksman to guide the crane during operation ‐ Safety zone to be established ‐ Barricade the operation zone ‐ Establish safe work procedure
Hazard Cause
‐Toppling of crane ‐Ramp failure ‐Inexperience operator
SheetPiling Risks and Mitigation Measures
Walter Lai/ Fan Yuhua Walter Lai Walter Lai Walter Lai/ Crawford Walter Lai Walter Lai/ Crawford
Action Owner
Hazard
Hazard Cause
‐Submit lifting plan and machinery record prior to start of operation ‐Provision of signalman and traffic controller to guide machinery movement ‐Full compaction and void filled with quarry dust or mill waste.
Absence of lifting plan
Failure to guide machineries movement
Uneven ground
‐Establish good communication at all times between operator and signalman ‐Used of tag line to control swaying of load. ‐Provision of steel plate for machinery
‐Ensure work zone is organized with good housekeeping ‐Proper barricade and demarcation of work zone to prevent unauthorized entry
Mitigation Measure
Negligence of operator
Installation Collision of Constraint of of sheet machinery and work zone piles site staff
Activity
SheetPiling Risks and Mitigation Measures
Walter Lai
Walter Lai/ Killi
Walter Lai
Walter Lai
Walter Lai/ Fan Yuhua
Walter Lai/ Jessica Ng
Action Owner
Accidental dislodge of sheet pile during driving
Installatio n of sheet piles
Negligent operator Faulty vibro head
Hazard Cause
Walter Lai
Walter Lai
Action Owner
Sling will only be removed after sheet pile is fully driven into the ground.
Employ skilled operator and perform daily checks prior to start of operation Additional sling tied to sheet pile and machine as extra protection in case if grabber gives way.
Mitigation Measure
Additional sling tied to sheet pile and machine
Hazard
Activity
SheetPiling Risks and Mitigation Measures
Hazard
Hazard Cause
Installatio Using of poor Structure n of sheet condition failure of piles machinery machinery
Activity
Maintenance service report, AE inspection checklist and certificate
Action Owner
Machine to be inspected and certified by AE. Walter Lai Regular monthly maintenance of machinery
Mitigation Measure
SheetPiling Risks and Mitigation Measures
Ensuring the alignment and verticality of the pile.
SheetPiling Risks and Mitigation Measures
Hazard
Hazard Cause
Mitigation Measure
Installatio Failure of n of sheet lifting pile mechanism
Brake motor failed Failure of sling and chain
Monthly inspection of lifting mechanism Colour coding all lifting mechanisms Safety zone to be established Lift load for 3 sec, 300mm and personnel 3 m away
Installatio Welding‐ Fire Combustible Clear of combustible material n of sheet damage material pile Inappropriat Provide PPE‐ Welding face shield, apron, gauntlet e welding Daily welding set checklist/inspection rod Provision of fire blanket and fire extinguisher
Activity
SheetPiling Risks and Mitigation Measures
Walter Lai/ Killi Walter Lai Walter Lai/ Crawford Walter Lai
Walter Lai Crawford Ang
Walter Lai
Walter Lai/ Fan Yuhua
Action Owner
Equipment and machinery with noise insulating material Setting up of noise barrier around work site Monitoring of site noise level and keep within limits Adhere to designated work hours Keeping stakeholders informed on activities and gather feedback
Noise Protection Measures
SheetPiling Risks and Mitigation Measures
12
Damaged to : ‐Unplanned excavation ‐Water pipe ‐Insufficient marking on ‐Bentonite site pipe ‐Failure to conduct detection test
Locating of Utility services
Hazard Cause
Hazard
Activity
‐If unclear with the finding of services after reaching the 2m limit, conduct further detection to determine the presence of any services below.
Tan WC/ Walter Lai Tan Hock Huat/ Tan WC Tan WC Tan WC Walter Lai Walter Lai Tan WC
‐Thorough study of utilities drawings ‐Cable detections by qualified LCDW ‐Provide clear utilities marking on site ‐Provide A3 size drawing of utility plan ‐Apply permit to dig ‐Barricade work area while trenching ‐Contact relevant utility agency for any presence of unidentified utility ‐Always treat utility as `live’ if encountered ‐Only manual digging allowed for trial trench ‐Full time supervision during trial trench
Tan WC
All Walter Lai Fan Yuhua/ Thomas Ng
Action Owner
Mitigation Measure
SheetPiling Risks and Mitigation Measures
Hazard
Hazard Cause
Installatio Gaps in sheet '‐ Leakage through n of sheet piles gap in the walls piles ‐Damage to services Groundwater drawdown ‐ Localized collapse of soil in the gap during excavation
Activity
SheetPiling Hazards and Mitigation Measures
Walter Lai/ Fan Yuhua
Minimize gaps by interlocking sheetpile‐ Utilities diverted from excavation wherever possible ‐ Instrumentation around gap area when necessary
Olive/ Walter Lai
Tan WC/ Walter Lai
Action Owner
Mitigation Measure
SheetPiling Risks and Mitigation Measures
Standard Weight of Material
8.6.3) Sheet pile stacking rules - Not more than 4 pieces of sheet pile 2 layer 1000 mm high for stacking sheet pile.
THANK YOU
General Hazards 8. T309/CNSS/121/001‐ Fire or explosion during construction (Page 20) 9. T309/CNSS/997/004‐ Toppling of crane, Ramp failure, Inexperience operator (Page 25) 10. T309/CNSS/999/015‐ Fire explosion due to gas leak (Page 27) 11. T309/CNSS/999/016‐ Electrocution due to electrical leak (Page 27)
New/Revised Risk: D‐wall 1. T309/CNSS/100/008‐ Instability of temporary works (trenches), open trench, open trench w/o cage, open trench w/ cage (page 4) Bulk Excavation 2. T309/CNSS/104/003‐ Ground instability during excavation to strut S1 level for area with the diverted traffic. (Page 11) RC Works 3. T309/CNSS/117/011‐ Concrete Placement with boom/ line/ stationary pump (Page 17) 4. T309/CNSS/117/017‐ Strutting failure (Page 18) 5. T309/CNSS/117/018‐ Work from height (Page 18) 6. T309/CNSS/117/019‐ Overloading of Structural slab (Page 18) 7. T309/CNSS/117/020‐ Reinforcement collapse – horizontal slab, walls (Page 18)
Closed Risk: T309/CNSS/109/002‐ Obstruction of seawall (Page 14)