System Formwork

  • Uploaded by: amurugesan
  • 0
  • 0
  • May 2020
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View System Formwork as PDF for free.

More details

  • Words: 1,335
  • Pages: 59
FORMWORK Larsen and toubro limited

Presentation by: Rachna Rajput (1030227) 08/28/09

1

LARSEN & TOUBRO LIMITED ECC DIVISION LUDHIANA CITY CENTRE

CONSTRUCTION OF RCC BASEMENT STRUCTURE

08/28/09

By : A.K. Mishra

2

THE CLIENT: TODAYHOMES AND INFRASTRUCTURE LUDHIANA

JOINT VENTURE WITH IMPROVEMENT TRUST

ARCHITECT: ASSOCIATES

CP KUKREJA AND

CONTRACTOR : LIMITED

LARSEN AND TOUBRO

08/28/09

3

LUDHIANA CITY CENTRE    





LOCATED IN HEART OF LUDHIANA BUILT ON 25 ACRES OF LAND 4 SIDE OPEN PLOT MAXIMUM NUMBER OF CAR PARKS UNDER ONE ROOF ONLY DEVELOPMENT OF INDIA WITH 5 STAR HOTEL,SHOPPING MALL,IT/OFFICE SPACE,HEALTH CARE,LIBRARY,MUESEAM UNDER 1 ROOF BIGGEST ATRIUM:2 LAKH SQUARE FEET

08/28/09

4

LUDHIANA CITY CENTRE CONSTRUCTION OF RCC BASEMENT STRUCTURE

Project Highlights     

JOB VALUE : DATE OF LOI: DATE OF COMMENCEMENT: DATE OF COMPLETION: DURATION OF PROJECT :

08/28/09

12400 lacs 30:1:2006 15:02:2006 14:02:2007 12 months 5

THE WORK FORMWORK PLANNING AND DESIGN OF ITS VARIOUS COMPONENTS

08/28/09

6







WHAT IS FORMWORK? FORMWORK IS A MOULD USED TO SHAPE CONCRETE UNTIL IT ATTAINS SUFFICIENT STRENGTH TO CARRY ITS OWN WEIGHT CAN BE ASSEMBLED BY UNSKILLED LABOUR CONSTITUTES 30% OF THE COST AND 60% OF THE TIME IN CONCRETE CONSTRUCTION

GOOD FORMWORK RESULTS IN 08/28/09 SPEED,QUALITY,ECONOMY AND SAFETY 

7

TRADITIONAL APPROACH 

BALLIES USED AS SUPPORT FOR SHUTTERING



UNSAFE AND UNRELIABLE



LOW REUSE VALUE



DOES NOT PRODUCE GOOD QUALITY CONCRETE

08/28/09

8

CHOICE OF RIGHT TYPE OF FORMWORK 



  

FORMWORK SHOULD BE ABLE TO BE DESHUTTERED AND DISMANTLED FAST SAFETY TO BE IMPROVED BY SITE PERSONNEL OVERALL COST SAVINGS GOOD SURFACE FINISH TO BE ACHIEVED OPTIMUM STOCK OF FORMWORK FOR SIZE OF WORKFORCE AND SPECIFIED TIME SCHEDULE

08/28/09

9

SYSTEM FORMWORK-L&T 

   

08/28/09

EARLIER CALLED DOKA FORMWORK INVERSIBLE FAST ERECTION MORE STABLE SAFE IN USE

10

FORMWORK PLANNING

STEP1.)  CONFIRMING HQ ON THE NEW JOBS BAGGED  IDENTIFYING TIME AND MATERIALS FOR CONSTRUCTION PROJECT STEP2.)  FINALIZING FORMWORK MATERIALS REQUIREMENTS FOR THE PROJECT  COLLATE THE REPORTS FROM RUNNING SITES AND CHECK SEPARABILITY FROM OTHER SITES WITHIN THE REGION  SENDING REQUEST FOR TRANSFER OF RESOURCES IF AVAILIBILIY IS CONFIRMED 08/28/09

11

CONTD….

08/28/09



RECEIVING NEW TARGETS ON PRODUCTIVITY FROM HQ



COMPARING THE RUNNING LMP COST FROM THE ACTUAL



IDENTIFYING TRAINING NEEDS OF STAFF 12

COMPONENT DETAILING 

FOUNDATION FORMWORK



HDT TOWER



SLAB/BEAM FORMWORK



WALL/COLUMN FORMWORK

08/28/09

13

FOUNDATION FORMWORK 





STEEL PANELS OF STANDERED SIZES MINIMIZE MAKING AT SITE USE OF VERSATILE COMPONENTS LIKE STEEL WALERS(2 ISMC BACK 2BACK) AND ALIGNMENT PROPS EASY ASSEMBLY WITH DIMENSIONAL ACCURACY

08/28/09

14

08/28/09

15

FOUNDATION FORMWORK MATERIAL CONTD.

08/28/09

16

CONTD…

08/28/09

17

CONTD….

08/28/09

18

AFTER ERECTION Steel panel Pipe waler clamp Pipe waler Alignment prop welar 08/28/09

19

HDT TOWER     



BASIC FRAME HORIZONTAL BRACE DIAGNOL BRACE TAKES LOAD OF 250KN HIEGHT ADJUSTMENTS UPTO 800MM POSSIBLE TRANSPORT DEVICES CAN BE ATTATCHED

08/28/09

20

COMPONENT DETAILING

08/28/09

21

CONTD….

08/28/09

22

AFTER ERECTION Coupler and spring lock pin Foot plate Tower spindle

08/28/09

23

WALL/COLUMN FORMWORK 

SHOP MADE SHUTTER



ACCORDING TO THE HIEGHT OF WALL OR COLUMN SPLICING CAN BE DONE



ISMC WALERS ARE USED FOR BEARING

08/28/09

24

COMPONENT DETAILING

08/28/09

25

CONTD….

08/28/09

26

CONTD……

08/28/09

27

COLUMN FORMWORK WORKING AT 4.8M HIEGHT

08/28/09

28

COLUMN FORMWORK

08/28/09

29

WALL FORMWORK 1.8M HIEGHT

08/28/09

30

SLAB/BEAM FORMWORK

08/28/09



SHEATHING MEMBER



H-BEAM(SECONDARY MEMBER)



WELAR(PRIMARY MEMBER)



HDT TOWER

31

AFTER ERECTION Sheathing H-beam welar tower

08/28/09

32

DESIGN OF FORMWORK









FORMWORK MUST SUPPORT ALL THE VERTICAL AND LATERAL LOADS ALL LOADS ARE ASSUMED TO BE UNIFORMLY DISTRIBUTED BEAMS SUPPORTED OVER 3 OR MORE SPANS ARE TAKEN AS CONTINUOUS APPROXIMATE FORMULAE ARE USED

08/28/09

33

AN IMPORTANT POINT 

SHEATHING SPAN DECIDES H-BEAM SPACING



H-BEAM SPAN DECIDES WALER SPACING



WELAR SPAN DECIDES TOWER SPACING

“SPAN” HERE MEANS THE DISTANCE BETWEEN TWO REACTION POINTS 08/28/09

34

DESIGN PROCEDURE EXAMPLE

LOADS TO BE TAKEN DEAD LOAD(1) (THICKNESS OF MEMBER*DENSITY OF CONCRETE) 

08/28/09



LIVE LOAD(2)



SELF WEIGHT(3)



DESIGN LOAD,W=(1)+(2)+(3) 35

DESIGN PROCEDURE CHECKS TO BE APPLIED

  





BENDING MOMENT CONDITION SHEAR FORCE CONDITION DEFLECTION CONDITION THE MINIMUM OF ALL 3 SPANS IS TAKEN AS SPAN FOR THE MEMBER ACCORDING TO HEIGHT OF WALL OR COLUMN THE REQUIRED LENGTH OF H-BEAM(AN I SECTION ) HIGH STRENGTH TIE SYSTEM BEAR LARGE CONCRETE PRESSURE

08/28/09

36

DESIGN PROCEDURE CONTD….     

DESIGN DONE FROM TOP TO BOTTOM 1. SHEATHING MEMBER 2.H-BEAM(SECONDARY MEMBER) 3.WELAR(PRIMARY MEMBER) HDT TOWER

08/28/09

37



SELF WEIGHT OF CONCRETE WITH REINFORCEMENT=25KN/M^3



SELF WEIGHT OF FORMWORK VARIES BETWEEN 0.5KN/M^2 TO .75KN/M^2



MINIMUM LIVE LOAD =2.5KN/M^2



MINIMUM DESIGN LOAD=5.0 KN/SQM

08/28/09

38

SHEATHING MEMBER: END CONDITION ASSUMED TO BE A PROPPED CANTILEVER  BM=W*L^2/8<=.2KNM/M 



SHEAR=5*W*L/8<=6.16KN/M

DEFLECTION=W*L^4/(185*E*I)<=1.852*10^-3M MINIMUM OF ABOVE THESE 3 SPANS IS TAKEN AS SPACING BETWEEN H-BEAMS 

08/28/09

39

SECONDARY MEMBER(H BEAM): END CONDITION IS ASSUMED TO BE SIMPLY SUPPORTED  LOAD INTENSITY =DESIGN LOAD*SPAN OF SHEATHING MEMBER  BM=W*L^2/8<=3KNM  SHEAR=W*L/2<=6KN  DEFLECTION=5*W*L^4/(384*E*I) MINIMUM OF ALL 3 IS TAKEN AS SPAN FOR H-BEAM 

08/28/09

40

WELAR (PRIMARY MEMBER) SIMPLY SUPPORTED END CONDITION IS ASSUMED  NOW WIDTH OF LOADING IS THE SPAN FOR H-BEAM AND W=DESIGN LOAD*WIDTH OF LOADING  BM=W*L^2/8<=12.67KNM/M  SHEAR=W*L/2<=103.4KN/M  DEFLECTION=5*W*L^4/(384*E*I)<=6.67*10^-3 MINIMUM OF THESE 3 IS TAKEN AS THE DISTANCE BETWEEN 2 TOWERS 

08/28/09

41

08/28/09

42



DESIGN FOR WALL/COLUMN FORMWORK CONCRETE EXERTS A FLUID PRESSURE Dh

ON THE FORMWORK  Pmax= D[C1*R^.5-(C2*K*(H-C1*R^.5)^.5) OR Dh whichever is smaller VALUE OF C1 FOR WALLS=1 FOR COLUMNS=1.5 08/28/09

43



   

 

VALUE OF C2 DEPENDS ON CONSTITUENT MATERIALS OF CONCRETE D=WEIGHT DENSITY OF CONCRETE H=VERTICAL FORM HIEGHT h=VERTICAL POUR HIEGHT K=TEMPERATURE COEFFICIENT TAKEN AS (36/T+16)^2 R=RATE OF RISE M/H T=TEMPERATURE OF CONCRETE AT PLACING (degree celsius)

08/28/09

44

PRESSURE DISTRIBUTION DIAGRAM

Pmax/D H

P max

08/28/09

45

DESIGN OF WALER – DESIGNED AS LATERALLY UNSUPPORTED BEAM 

    

SIGMAbc=.66*Fcb*Fy/(Fcb^n+Fy^n)^1/n Fcb=ELASTIC CRITICAL STRESS(N/MM^2) Fy= YIELD STRESS OF STEEL IN( N/MM^2) N=FACTOR TAKEN AS 1.4 Fcb=K1*(X+K2*Y)*C2/C1 PERMISSIBLE SHEAR STRESS=0.4*Fy PERMISSIBLE DEFLECTION=L(SPAN)/325 BENDING STRESS=M/Z SHEAR STRESS=F/Aweb 08/28/09

46

STRIPPING TIME FOR FORMWORK 

VERTICAL FORMWORK TO COLUMN, WALL AND BEAM :16-24HOURS



SOFFIT FORMWORK TO SLABS(PROPS TO BE REFIXED AFTER REMOVAL OF FORMWOK) :3DAYS



SOFFIT FORMWORK TO BEAMS :7DAYS

08/28/09

47

SAFETY IN FORMWORK 









BEFORE ERECTION OF STEEL FRAME STAGING THOROUGH INSPECTION DIAGNOL BRACES SHOULD BE IN PROPER POSITION ALL CONNECTING DEVICES SHOULD BE IN PLACE BRACING SHOULD BE PROVIDED IF TOWER HEIGHT INCREASES 6M AT HIEGHTS SAFETY BELTS SHOULD BE USED BY WORKMEN

08/28/09

48

Ladder Safety Follow the 4:1 rule when using extension ladders

6 m (20 ft)

1.5 m (5 ft.)

08/28/09

49

–Erect First Tower – Adjust and ensure the top level is same. Connect all pin bracing

08/28/09

50

08/28/09

51

08/28/09

52

Use of lifeline above 2m

08/28/09

53

LABOUR PRODUCTIVITY 

PRODUCTIVITY IS MAXIMUM OUTPUT FROM MINIMUM INPUT



UNITS ARE SQM/MANDAY



WORKING OF 8 HRS=1MANDAY



PRODUCTIVITY= SHUTTERING AREA ACHIEVED DURING THE MONTH/MANDAYS

08/28/09

54

MATERIAL PRODUCTIVITY 





MATERIAL PRODUCTIVITY IS COMPARED WITH STANDERED PRODUCTIVITY STANDERED PRODUCTIVITY CALCULATED ON THE BASIS OF SHUTTERING AREA COMPLETED AND KG MONTH PER SQM TOTAL REQUIRED KG= SHUTTERING AREA *KG MONTH PER SQM

08/28/09

55



ACTUAL PRODUCTIVITY IS TAKEN AS AVERAGE STOCK LEFT

PRODUCTIVITY IN %= (ACTUALPRODUCTIVITY/STANDE RED PRODUCTIVITY)*100 

08/28/09

56

RATE ANALYSIS ON THE BASIS OF NUMBER OF CARPENTER KHALASI AND HELPER,NUMBER OF HOURS OF WORK AND RATE/HR THE TOTAL AMOUNT IS CALCULATED FOR SHIFTING ,FIXING AND REMOVING PRODUCTIVITY IN SQM/MANDAYS IS CALCULATED

08/28/09

57

BATCHING OF CONCRETE      

08/28/09

PAN TYPE BATCHING PLANT CAPACITY OF 60M^3/HR WEIGHED BATCHING MIXING TRANSPORTATION PLACING

58

THANK YOU

08/28/09

59

Related Documents


More Documents from "NURLINURLINDA"

System Formwork
May 2020 2