Supply Chain Management Production Planning Presented By :
Farhan Ahmed
Today discussions
Supply Chain Strategy Master Scheduling Capacity Planning Shop Floor Control Key Success Factors Questions
SUPPLY CHAIN STRATEGY
Supply Chain Strategy
Maximize customer service
Minimize Inventory
Minimize Operating Costs
Supply Chain strategy PRODUCTION PLAN
FINISHED GOODS INVENTORY
SALES PLAN
Production Planning • What product does the market want ? • How much of which products should be produced • and by when ?
• This activity includes the creation of Master production schedules that take into account plant Capacities , workload balancing, Quality control and Equipment maintenance.
MASTER SCHEDULING
The Master of all Schedules
What is the Master schedule ? The anticipated build schedule of those items (products) assigned to the Master scheduler.
The Master scheduler maintains this schedule and in turn, it becomes a set of planning numbers that drive material requirements planning.
What is the Master schedule ? Its represents what the company plans to produce expressed in specific configurations, quantities and dates. It is not a sale forecast , the master production schedules must take into account the forecast, the production plan, and other important consideration such as backlog, availability of capacity , management policy and goals, etc.
Master Schedule Sale & Operation Planning Master Scheduling Bills Of Material
Material Req. Planning Material Scheduling
Inventory Records
Order Types Planned Orders: • System suggested replenishment orders and not yet accepted by the planner. As requirements change, planned order dates and quantities are automatically adjusted in the system.
Firm Planned Orders: • No longer controlled by the system because they have been accepted, changed or created by the master scheduler planner. Quantities and dates are frozen. Cannot be changed by the system and require manual intervention to make changes.
Released Orders: • Open orders or Shop orders issued to production floor.
Planning Horizon (MPS Time Fences) MPS Horizon is the user defined period of time that is considered firm or frozen and has following attributes: – Allow Planner to stabilize production plan in MPS FIXED
TRADING
OPEN
Next 4 weeks
Weeks 5 - 12
Months 4 - 24
Shop Orders
Firm Planned Orders
Planned Orders
Firm Planned Orders
Planning time fence
Increasing Stability
Scheduling Establishing the timing of the use of equipment, facilities and human activities in an organization Effective scheduling can yield • Cost savings • Increases in productivity
Managing Change - Supply Time Fences EMERGENC Y CHANGES
TRADING AREA
STABILISE Today
CAPACITY FIRM FUTURE MATERIAL PLANNING Planning Release ORDERED 24 months Time Fence Time Fence COST
TODAY
ADDING & CHANGIN G
TIME
Impacts on Master Schedule Product Oversell
Inventory adjustments
Product Withdrawal
Changes to planning parameters
Product Launch Abnormal Demand Reduced / Cancelled Orders Changes in supply
Changes in business policy Seasonality Execution issues S & OP decisions
ALL changes to the Master Schedule will be managed
Master Schedule Conformance Measures the effective completion of Master Schedule Conformance
Total scheduled orders delivered on time Total orders due in the period measured
Tolerance : NLT 95%
CAPACITY PLANNING
CAPACITY “A MEASURED ABILITY TO ACCOMPLISH WORK”.
CAPACITY CONTROL : “The process of measuring production Output and comparing it with the capacity requirement plan, determining if the variance exceeds pre-established limits, and taking corrective action to get back on plan if the limits are exceeded”.
LOAD This is the amount of scheduled work ahead of a manufacturing facility, usually expressed in terms of hours of work of production, or a measured volume of work to be done. It must be stated in same units of measure.
WORK CENTER: A work center is a place where manual or machine work is performed. If the work center contains more than one work station, then any one of the work stations must be capable of performing the assigned work or task.
Input
Work Center
Output
STANDARD/ VALIDATED HOURS The time in hours required to complete a task. It is the most common unit of measurement for capacity.
MOVE TIME: The time required to move processed material to the next work center.
QUEUE TIME: The time an arriving shop order or production order must normally wait at the work center before being processing through the operation.
Work Center # 1
Work Center # 2
Output
The Lead Time Syndrome ORDERS IN
Q LT CAPACITY
WORK OUT
Capacity Planning in MPS Systems Long Range Resource Planning Rough Cut Capacity Planning
Production Planning Demand Management Master Production Scheduling
Medium Range Capacity Req’ts Planning
Short Range
Detailed Material Planning
Finite Loading Input / Output Analysis
Shop Floor Systems
Vendor Systems
Rough cut capacity Planning : Addresses the questions : ” Do we or will have enough equipment, enough people , enough materials, and enough time to meet the sales and operational plans as currently written?”
ROUGH CUT CAPACITY PLANNING
MPS
REVIEW WORK LOAD ON CRITICAL WORK CENTERS
YES PROBLEM
NO
RESOURCE REQUIREMENTS REPORT
PROBLEM
YES
Bottleneck A bottleneck is a task or machine speed that limits and therefore determines the capacity of an entire process – such
slowest machine on the line.
as the
Where is the bottleneck? Mach 1
Mach 2
Mach 3
Mach 4
160 Units/Min
100 Units/Min
220 Units/Min
600 Units/Min
Have less capacity than prior or following work centers
INITIAL LOAD PROFILE
Normal capacity
Hours of capacity
1
2
3
4
5
6
Time (weeks)
ADJUSTED LOAD PROFILE
Hours of capacity
Work an extra shift
Overtime
Push back
Pull ahead
1
Push back
2
3
4
5
6 Time (weeks)
Shop Floor Control
FLOW DIAGRAM SFC Production Scheduling (Weekly) Shop Packet Printing on Daily Basis •Data collection (Operation input ) • Monitoring of dispatch list on daily basis •Create ADR (if required) Control / Feed back Past due
Order Completed YES Order Review/ Disposition
YES
Problem Correctable NO
SHOP FLOOR CONTROL STEP BY STEP Shop floor Planner review the back log with Master Scheduler & adjust in next week plan. Master scheduler converts the firm order into the shop order. Shop floor planner Release shop order as per plan. Section Managers review the dispatch list on daily basis. If any change (ADR) recommended by Sectional Manager changes incorporated in the Dispatch list ADR raise by RMS manager in case of non-availability or delay in issuance of the material.
Key Success Factors Supply Plan Achievement
RCCP is a key to Supply plan achievement.
Plan execution
Master scheduler and Capacity planner are key player for MPS execution.
Balance plan
Detail capacity planning against individual work centers is essential to balance the Input and Output of work centers.
Cost Impact
Cost impact of different products mix in view of different work centers.
Shop Floor control
Use of dispatch list of individuals work centers.
Preventive maintenance
Use of preventive maintenance schedule in conjunction with capacity planning.
Q.A. integration Integrate QA with Supply Chain e.g. Dispatch list. Plan Accuracy
Accurate capacity planning as a result of work center wise calendar maintenance.
KEY FACTORS Lead time is sum of all move, process,queue and Q.A. testing times at all work centers listed on the routing.
Standard hours based on demonstrated Out put.
Engineering schedule maintenance is a part of Master scheduling, capacity planning and shop floor control.