SAP PS PROCESS MANUAL
PROJECT STRUCTURE CREATION
Contents:1. Project Definition creation 2. WBS creation 3. Network creation 4. Activity creation 5. Material Component Creation 6. Activity Element creation 7. User Status 8. System Status 9. Network Release 10. Calculate Costs, Update Costs & Costs Itemization 11. Open Existing Project 12. Related Reports
Page 1
SAP PS PROCESS MANUAL 1. Project Definition creation
To Create New Project then Click on
Create Project
Page 2
SAP PS PROCESS MANUAL
Page 3
SAP PS PROCESS MANUAL
Page 4
SAP PS PROCESS MANUAL
2. WBS Creation:
Page 5
SAP PS PROCESS MANUAL
Note: - Project Definition & Higher Level WBS Element coding mask & Description should be same (As shown in the Screenshot)
Page 6
SAP PS PROCESS MANUAL
Select Operative Indicators (For higher level WBS all the 3 Operative Indicators must be selected)
Planning Element Account Assignment Element Billing Element
Page 7
SAP PS PROCESS MANUAL
3. Network Creation:
Page 8
SAP PS PROCESS MANUAL
Page 9
SAP PS PROCESS MANUAL 4. Activity Creation:
Page 10
SAP PS PROCESS MANUAL
5. Material Component Creation :
Page 11
SAP PS PROCESS MANUAL
Page 12
SAP PS PROCESS MANUAL
6. Activity Element Creation: 6.1 Create Activity Element (Work):
Page 13
SAP PS PROCESS MANUAL
Page 14
SAP PS PROCESS MANUAL
Once All the Field Value is entered then Click On ENTER key.
6.2 Create Activity Element (Costs):
Page 15
SAP PS PROCESS MANUAL
Page 16
SAP PS PROCESS MANUAL
Page 17
SAP PS PROCESS MANUAL
List of Cost Elements Select Correct Cost Element
Once All the Field Value is entered then Click On ENTER key.
Page 18
SAP PS PROCESS MANUAL
7. Change User Status of the WBS:
Select the WBS for which the User Status needs to be changed
Page 19
SAP PS PROCESS MANUAL Go to EDIT USER STATUS SET & PASS ON
Page 20
SAP PS PROCESS MANUAL
First while creating WBS User Status of the WBS will be in INITIATE (INT), Change it one by one (Sequentially) till CONS (CONSTRUCTION) Note: - To Raise PR against any WBS the User status of that WBS must be set to Construction (CONS) & System Status must be set to Release (REL)
Page 21
SAP PS PROCESS MANUAL
8. System Status: Select PROJECT DEFINITION EDIT Status RELEASE (as shown below)
Page 22
SAP PS PROCESS MANUAL
9. Network Release: Select NETWORK EDIT STATUS RELEASE
Page 23
SAP PS PROCESS MANUAL
Page 24
SAP PS PROCESS MANUAL
10 Calculate Costs, Update Costs & Costs Itemization: 10.1 Calculate Costs:
Page 25
SAP PS PROCESS MANUAL
Page 26
SAP PS PROCESS MANUAL
10.2 Update Costs:
Page 27
SAP PS PROCESS MANUAL
To check the quantity and cost of the material, labors & equipment’s that are used in structure 10.3 Cost Itemization:
Page 28
SAP PS PROCESS MANUAL
Page 29
SAP PS PROCESS MANUAL
Save the Structure, so that Network Number is generated
Page 30
SAP PS PROCESS MANUAL
11. OPEN EXISTING PROJECT: Page 31
SAP PS PROCESS MANUAL
To open an existing Project then Click on
Open Enter the Project Definition Enter
Page 32
SAP PS PROCESS MANUAL Existing Project is opened.
12. Related Reports: Enter the Project Definition or WBS element in all the reports S_ALR_87013543 Act/plan/variance abs. / % var. CN52N - Material Components CJI3 – Project Actual Cost Line Items Report CJI5 – Project Commitment Line Report CN43N – WBS Elements Overview Report CN47N – Project Activities Report CN48N – Confirmations Report
S_ALR_87013543 Act/plan/variance abs. / % var. Report
Page 33
SAP PS PROCESS MANUAL
Page 34
SAP PS PROCESS MANUAL
CN52N - Material Components
Page 35
SAP PS PROCESS MANUAL
CJI3 – Project Actual Cost Line Items Report
Page 36
SAP PS PROCESS MANUAL CJI5 – Project Commitment Line Item Report
CN43N – WBS Elements Overview Report
Page 37
SAP PS PROCESS MANUAL CN47N - Project Activities Report
CN48N – Confirmations Overview Report
Page 38