SAP PS PROCESS MANUAL

PROJECT STRUCTURE CREATION

Contents:1. Project Definition creation 2. WBS creation 3. Network creation 4. Activity creation 5. Material Component Creation 6. Activity Element creation 7. User Status 8. System Status 9. Network Release 10. Calculate Costs, Update Costs & Costs Itemization 11. Open Existing Project 12. Related Reports

Page 1

SAP PS PROCESS MANUAL 1. Project Definition creation

To Create New Project then Click on

Create  Project

Page 2

SAP PS PROCESS MANUAL

Page 3

SAP PS PROCESS MANUAL

Page 4

SAP PS PROCESS MANUAL

2. WBS Creation:

Page 5

SAP PS PROCESS MANUAL

Note: - Project Definition & Higher Level WBS Element coding mask & Description should be same (As shown in the Screenshot)

Page 6

SAP PS PROCESS MANUAL

Select Operative Indicators (For higher level WBS all the 3 Operative Indicators must be selected)   

Planning Element Account Assignment Element Billing Element

Page 7

SAP PS PROCESS MANUAL

3. Network Creation:

Page 8

SAP PS PROCESS MANUAL

Page 9

SAP PS PROCESS MANUAL 4. Activity Creation:

Page 10

SAP PS PROCESS MANUAL

5. Material Component Creation :

Page 11

SAP PS PROCESS MANUAL

Page 12

SAP PS PROCESS MANUAL

6. Activity Element Creation: 6.1 Create Activity Element (Work):

Page 13

SAP PS PROCESS MANUAL

Page 14

SAP PS PROCESS MANUAL

Once All the Field Value is entered then Click On ENTER key.

6.2 Create Activity Element (Costs):

Page 15

SAP PS PROCESS MANUAL

Page 16

SAP PS PROCESS MANUAL

Page 17

SAP PS PROCESS MANUAL

List of Cost Elements Select Correct Cost Element

Once All the Field Value is entered then Click On ENTER key.

Page 18

SAP PS PROCESS MANUAL

7. Change User Status of the WBS:

Select the WBS for which the User Status needs to be changed

Page 19

SAP PS PROCESS MANUAL Go to EDIT  USER STATUS  SET & PASS ON

Page 20

SAP PS PROCESS MANUAL

First while creating WBS User Status of the WBS will be in INITIATE (INT), Change it one by one (Sequentially) till CONS (CONSTRUCTION) Note: - To Raise PR against any WBS the User status of that WBS must be set to Construction (CONS) & System Status must be set to Release (REL)

Page 21

SAP PS PROCESS MANUAL

8. System Status: Select PROJECT DEFINITION EDIT  Status  RELEASE (as shown below)

Page 22

SAP PS PROCESS MANUAL

9. Network Release: Select NETWORK  EDIT  STATUS  RELEASE

Page 23

SAP PS PROCESS MANUAL

Page 24

SAP PS PROCESS MANUAL

10 Calculate Costs, Update Costs & Costs Itemization: 10.1 Calculate Costs:

Page 25

SAP PS PROCESS MANUAL

Page 26

SAP PS PROCESS MANUAL

10.2 Update Costs:

Page 27

SAP PS PROCESS MANUAL

To check the quantity and cost of the material, labors & equipment’s that are used in structure 10.3 Cost Itemization:

Page 28

SAP PS PROCESS MANUAL

Page 29

SAP PS PROCESS MANUAL

Save the Structure, so that Network Number is generated

Page 30

SAP PS PROCESS MANUAL

11. OPEN EXISTING PROJECT: Page 31

SAP PS PROCESS MANUAL

To open an existing Project then Click on

Open  Enter the Project Definition Enter

Page 32

SAP PS PROCESS MANUAL Existing Project is opened.

12. Related Reports: Enter the Project Definition or WBS element in all the reports  S_ALR_87013543 Act/plan/variance abs. / % var.  CN52N - Material Components  CJI3 – Project Actual Cost Line Items Report  CJI5 – Project Commitment Line Report  CN43N – WBS Elements Overview Report  CN47N – Project Activities Report  CN48N – Confirmations Report

S_ALR_87013543 Act/plan/variance abs. / % var. Report

Page 33

SAP PS PROCESS MANUAL

Page 34

SAP PS PROCESS MANUAL

CN52N - Material Components

Page 35

SAP PS PROCESS MANUAL

CJI3 – Project Actual Cost Line Items Report

Page 36

SAP PS PROCESS MANUAL CJI5 – Project Commitment Line Item Report

CN43N – WBS Elements Overview Report

Page 37

SAP PS PROCESS MANUAL CN47N - Project Activities Report

CN48N – Confirmations Overview Report

Page 38