ROAD MANAGEMENT after KOICA Training National Road No. 3 (Rehabilitation Project)
Presented by: TEP VIRITH 10/04/09
Contents
General Background ● ●
●
Plan for improving deteriorated roads due to heavy traffic and lack of maintenance was formulated. During the past decade, national roads were improved with financial assistance from international financing agencies but the project road has not been completely repaired. The project road was further deteriorated due to flood damage in 2000. Accordingly, this project road will contribute to the strengthening of national road network, reduction in transport cost, regional industrial development, poverty reduction and tourism development along the southern coastal areas including Bokor National Park.
Objectives ● ●
To prepare Detailed Design for the Rehabilitation of NR No.3 (Phnom Penh ~ Kampot ) Phase II Project. To invite and employ a contractor for execution of the project.
Project Description ● ●
Beginning and Ending points of the project road : Sta.9+600 ~ Sta.147+100 Detailed Design Period: October 2007 ~ April 2008 (6 months)
●
Summary of the Project Item Length
Width
Total
Remarks
137.5 km 4-Lanes : 5.35km (-2.75Km+2.60 Km) 2-Lanes :132.15 km 4-Lanes : B=16.6m
Sta.12+350 ~ Sta.14+000 Sta.146+150 ~ Sta.147+1000
2-Lanes : B=11.0m Design Speed
80 km/h
Bridge
575.0 m / 27units
Box
375.0 m / 30units
Pavement Type
Asphalt : 1.65Km DBST : 133.10km(132.15Km+0.95Km)
Downtown Area : 60 km/h
Execution Agency ● Ministry of Public Works and Transport (MPWT), Cambodia.
Engineering Consultants ● Korea Consultants International in association with Yoosin Engineering Corp. ● Sub-consultants are Khmer Consultant Engineering Corporation Ltd and Vido Engineering Consultant Co., Ltd
Classification of the Project Road ●
National Road NO.3
Design Speed ●
Design speed of 80km/hr was adopted based on the results of comprehensive reviews including accessibility to among major cities, connectivity of road networks, existing alignment plans, land used, traffic safety, etc.
●
Design speed of 60km/hr was adopted for modified alignment sections including poor alignment sections.
Geometric Design Standard Classification
Topography Flat
Rolling/Mountainous
Design Speed (km/hr)
80
60
Minimum Curve Radius (m)
255
135
> 4.5°
140
100
< 4.5°
630 / θ
450 / θ
Standard
4-6
5-9
Type 凸
30
15
Type 凹
28
15
Critical Grade Length for Design Speed (m)
500
300
Sight Distance (m)
115
70
3
3
1,250
-
6
6
Minimum Curve Length (m) Vertical Gradient (%) Minimum Vertical Curve Variation Rate (m/%)
Standard Slope of Cross Section (%) Curves with Adverse Cross fall (m) Maximum Super-elevation (%)
Minimum Width of Carriageway Classification General Road
Design Speed Rural Area (km/h)
Urban Area
More than 80
3.50
3.25
More than 70
3.25
3.25
More than 60
3.25
3.0
Less than 60
3.0
3.0
Remarks - Rural area of 3.5m ⇒ 2-Lanes - Urban area of 3.1m ⇒ 4-Lanes, connecting with the existing road
Road Shoulder Classification
Design Speed (km/h)
Minimum Shoulder (m)
Remarks
General Road
More than 80
2.00
Applied
Less than 80 ~ More than 60
1.50
Less than 60
1.50
Background of Investigation
TO
TA
N
I
OE AK T O
In this project route, most horizontal alignments are in good conditions and those of the existing road can be used. However, the alignment of the existing road between Sta. 22+400 and Sta. 24+200 is in poor condition and there are 3 big river bridges. It is considered to be necessary to take such actions as safety management, proper works, cost estimation and land acquisition for bridge construction.
T
31
CHHUK
ANKOR MEAS
3
146+150
22
U TO O
KOUK TRAB
4
3
AY SAR
12+350
9+600 AIR PORT
PREY NHUEK
147+100
NHAENG NHANG
TRAM KAK
Area
SECTION -1
SECTION -2
SECTION - 3
SECTION - 4
L=2.75km
L=1.65km
L=132.15km
L=0.95km
PROJECT ROAD / L=137.5km
Figure 6.2.1
Solution of route by section
Investigated Section Table 1. Present Conditions of Investigated Sections Classification Selection 1
Selection 2
Location
Sta.22+400~Sta 23+100
Sta.23+400~Sta 24+200
Length
L=700m
L=800km
Road Width Horizontal Alignment Bridge Obstacle
•Pavement Width : 6.0~7.0mm •Shoulder Width : 1.5m~2.0m
•Pavement Width : 5.0~7.0mm •Shoulder Width : 1.4m~1.8m
•Straight : 500m/2Nos •Curve : R=500/1Nos
•Straight : 730m/2Nos •Curve : R=70/1Nos
•37.5m/1Nos •Condition : Bad
•137m/2Nos •Condition : Good
•22+800(LHS) : Toek Tlar Pagoda
•22+800(RHS) : 7 January River
Alternative 1
Alternative 2
Sta.22+702
Sta.23+750
Sta.23+920
Bad Condition
Fair Condition
Good Condition
Result of Investigation (1) Section 1 Figure 1. Comparison of Alternative Alignments Classification
Alternative 1
Alternative 2
Existing Alignment
Modified Alignments
Krain Pourng Primary School
Alternative-2
River New Bridge
Toek Tla Pagada
22+400
22 22+5 +500 00
22+ 600 22+600
To Kampot
22+700
22+800 22+800
22+900 22+900
00 23+ +0000 23
23+100
Existing Bridge
Alternative-1 Length = 0.7km
To Phnom Penh
Sta.23+100
Sta.22+400
22+700
Alternative 1
Alternative 2
Alignment
R=500
R=700 (Good)
Existing Bridge
To be replaced
To be replaced
Location of Bridge Construction
Same location of the existing bridge
18m left of the existing bridge
Obstacle
Existing water gate
Toek Tlar Pagoda
Construction of Temporary Bridge
Temporary bridge required during construction.
Temporary bridge not required.
Workability
Bad
Good
Construction Cost
High
Low
Selection
◎
(2) Section 2 Figure 2, Comparison of Alternative Alignments Classification
Alternative 1
Alternative 2
Existing Alignment
Modified Alignments
Alternative-2 Alternative-1
Existing Bridge 00 23+8
Existing Bridge 23+ 900
To Kampot
00 23+7
24+ 00
00 23+6
23+400
23+500
23+600
23+800
23+700
23+900
0
24+000
24+1 00
New Bridge
Alternative-1 Alternative-2 Length = 0.8km
To Phnom Penh
New Bridge
Sta.24+200
Sta.23+400
24+20 0
Alternative 1
Alternative 2
Photo
Alignment Bridge Obstacle
● R=70 (Existing Alignment)
● Straight
● 2 Existing Bridges
● 2 New Bridges2
● No obstacle
● 7 January River compensation for additional lands
Construction ● Low Cost Selection
● High ◎
Typical Cross Section TYPE-1(4 LANES) 16,600 500
1,500 SHOULDER
3,100 CARRIAGEWAY
3,100 CARRIAGEWAY
200
3,100 CARRIAGEWAY
3,100 CARRIAGEWAY
1,500 500 SHOULDER
GUIDE POST (CONCRETE)
GUIDE POST (CONCRETE) CL OF ROADWAY
VAR
FINISHED GRADE
VAR
EXISTING PAVEMENT DOUBLE BITUMINOUS SURFACE TREATMENT BITUMINOUS PRIME COAT
AGGREGATE BASE COURSE SUBBASE COURSE
AGGREGATE BASE COURSE(T=200mm) SUBBASE COURSE(T=200mm)
SUBGRADE LEVEL
Typical cross section was made in consideration of the existing road and its connectivity.
TYPE-2 (2 LANES) GENERAL SECTION 11,000 500
1,500 SHOULDER
3,500 CARRIAGEWAY
3,500 CARRIAGEWAY
1,500 500 SHOULDER
GUIDE POST SEE DETAIL "A"
(CONCRETE) C L OF ROADWAY
VAR
FINISHED GRADE
EXISTING PAVEMENT DOUBLE BITUMINOUS SURFACE TREATMENT
AGGREGATE BASE COURSE SUBBASE COURSE SUBGRADE LEVEL
BITUMINOUS PRIME COAT AGGREGATE BASE COURSE(T=200mm) SUBBASE COURSE(T=200mm)
VAR
TYPICAL CROSS SECTION TYPE-3 (2 LANES) RAISED SECTION 500
1,500 SHOULDER
11,000
3,500 CARRIAGEWAY
3,500 CARRIAGEWAY
1,500 500 SHOULDER
GUIDE POST
GUIDE POST
(CONCRETE)
(CONCRETE) CL OF ROADWAY
FINISHED GRADE
EXISTING PAVEMENT
EMBANKMENT
DOUBLE BITUMINOUS SURFACE TREATMENT BITUMINOUS PRIME COAT
AGGREGATE BASE COURSE SUBBASE COURSE
AGGREGATE BASE COURSE(T=200mm) SUBBASE COURSE(T=200mm)
SUBGRADE LEVEL SUB- GRADE(T=450mm)
Applied Section : Areas expected to be submerged (based on field study and data of MPWT) TYPE-4 (2 LANES) BUILT-UP SECTION
Section: Sta. 43+200 – 44+100, Sta. 54+500 – 55+289 Sta. 74+200 – 75+000, Sta. 107+000 – 107+604 11,000
2,000
3,500 CARRIAGEWAY
CL OF ROADWAY
HOUSE
3,500 CARRIAGEWAY
2,000
HOUSE FINISHED GRADE
SIDE PIPE CULVERT(D=800mm)
SIDE PIPE CULVERT(D=800mm) EXISTING PAVEMENT
DOUBLE BITUMINOUS SURFACE TREATMENT AGGREGATE BASE COURSE SUBBASE COURSE SUBGRADE LEVEL
BITUMINOUS PRIME COAT AGGREGATE BASE COURSE(T=200mm) SUBBASE COURSE(T=200mm)
Bridge Layout
Bridge Type Classification
Bridge Name
No.
Length (m)
Width (m)
3
230.5
8.0-9.0
Using of Existing Bridge
Three bridges including SLAKOU Bridge
P.S.C. deck Bridge
21 bridges including BR. 1
21
415.0
11.0-12.0
R.C. Slab Bridge BR. 3, 9, 18, 20, 23 and 26
6
160.0
11.0-12.0
30
805.5
Total
Remarks good condition
Typical Cross Section Using of Existing Bridge
Town Bridge w/Sidewalk
P.S.C. Deck Bridge
R.C. Slab Bridge
Results of the Investigation ● ●
There are 51 bridges including 2 new ones under this project scheme which consist of 43 bridges with span length less than 20m and 8 bridges more than 20m. The results of investigation about conditions of superstructures are described in Table 2 and further details on each type of bridge superstructure are described in Table 3.
Table 2. Summary of Condition of the Existing Bridges Type
Span Length
Numbers
Good
PSC Beam
7~40m
2
2
RCS, RCT
4~14m
35
35
S.T. Truss GR.
12~50m
13
13
S.T. Plate GR.
52.5m
1
1
51
3
Summary of Condition
Fair
Poor
48
Figure
Mdech Popel Bridge (Sta. 67+097, RC Slab)
Slakou Bridge (Sta. 65+796, PSC Beam)
Determination of water level and design level of bridges The water level for each bridge was measured and in the bridge No.3, the height of the highest reservoir gate was used as H.W.L. The bridge No.50 & 51 which has some flood problems, recommendations made by MPWT in Phnom Penh, was designed to raise design level by 1.0 m to solve the problems in accordance with recommendations made by MPWT in Phnom Penh. Applying all of these, the design levels were determined to have clearance more than 60cm below bridge bearings.
Structure Plan 1) Vertical Alignment Necessity for superstructure replacement was investigated in view of raising the design level of superstructure for bridges to be potentially inundated and to have low clearances. In case, design level should be higher, the height of the substructure should also be raised, and that makes construction work more difficult. Thus, in case of replacing a superstructure of an existing bridge, it was decided that a substructure as well as a superstructure would be replaced considering maintenance in the future even if the substructure is in good condition. Because of insufficient hydrological data, H.W.L. in each bridge was estimated by means of interviewing with local officials and residents. For a bridge across a reservoir, it was estimated as high as the embankment.
Table 3. Current Status and Plan of Existing Bridges Current Status
Plan
NO.
Sta.
Type
Length (m)
Width (m)
Type
Length (m)
1
18+644
RC SLAB
6.5
8.9
BOX
35
2
21+120
RC SLAB
4.2
6.7
BOX
35
3
22+702
RC SLAB
37.2
9.8
PSC DECK
4
23+749
PSC BEAM
78.0
10.0
USE
35
5
23+917
ST PLATE
52.5
12.0
USE
35
6
24+900
ST DECK
15.0
4.6
PSC DECK
15
11
56
7
25+735
ST DECK
36.6
6.2
RC SLAB
40
12
66
8
31+358
ST DECK
12.0
4.4
PSC DECK
12
11
81
9
45+688
RCT
4.1
10.2
BOX
10
56+595
RC SLAB
11.4
7.0
PSC DECK
15
11
52
11
57+280
ST DECK
17.1
4.3
PSC DECK
25
11
96
12
60+353
RC SLAB
8.8
7.8
BOX
13
62+415
ST DECK
13.9
5.6
PSC DECK
14
65+796
PSC BEAM
100.0
12.0
USE
15
66+695
ST DECK
56.0
4.2
PSC DECK
55
11
52
16
67+093
RC SLAB
6.9
7.0
RC SLAB
20
11
108
45
Width (m)
11
Raising of Vertical Alignment (cm)
88
35
35 15
11
58 35
Current Status
Plan
NO.
Sta.
Type
Length (m)
Width (m)
Type
Length (m)
17
68+875
ST DECK
6.1
4.0
BOX
35
18
69+745
RCT
8.5
6.9
BOX
35
19
71+645
RCT
6.6
6.7
BOX
35
20
74+819
RCT
6.8
6.7
PSC DECK
21
79+036
RCT
4.7
6.0
BOX
35
22
79+708
RC SLAB
6.2
7.3
BOX
35
23
80+737
RC SLAB
8.9
6.2
BOX
35
24
81+355
RC SLAB
14.7
7.2
PSC DECK
15
11
53
25
88+835
RC SLAB
7.4
8.0
PSC DECK
10
11
73
26
91+559
ST DECK
12.3
5.0
PSC DECK
15
11
57
27
92+345
RCT
12.0
7.7
PSC DECK
12
11
64
28
93+995
RCT
8.9
9.2
BOX
29
97+375
RCT
12.4
7.8
PSC DECK
15
12
53
30
98+022
RCT
12.2
7.8
PSC DECK
12
11
52
31
99+261
RC SLAB
8.3
9.1
BOX
35
32
99+698
RC SLAB
8.1
PIPE
35
33
101+424
RC SLAB
6.3
4.5
BOX
35
34
102+243
RCT
10.3
4.1
BOX
35
15
Width (m)
11
Raising of Vertical Alignment (cm)
52
35
Current Status
Plan
NO.
Sta.
Type
Length (m)
Width (m)
Type
Length (m)
Width (m)
Raising of Vertical Alignment (cm)
35
103+681
RC SLAB
5.7
4.9
BOX
36
105+847
ST DECK
48.4
5.6
PSC DECK
50
11
64
37
106+928
ST DECK
18.3
4.0
RC SLAB
20
12
77
38
108+976
ST DECK
16.7
5.1
PSC DECK
15
11
53
39
110+090
RC SLAB
7.6
5.7
BOX
35
40
112+991
RC SLAB
6.9
6.9
BOX
35
41
115+943
ST DECK
39.0
5.3
RC SLAB
40
11
57
42
119+580
RC SLAB
7.7
5.0
PSC DECK
10
12
58
43
121+196
RC SLAB
10.0
4.7
BOX
35
44
125+739
RC SLAB
4.5
8.2
BOX
35
45
128+952
RC SLAB
12.4
6.2
PSC DECK
12
11
56
46
130+137
RC SLAB
18.5
5.5
RC SLAB
20
11
58
47
136+717
RC SLAB
12.0
7.3
PSC DECK
12
11
53
48
138+057
RC SLAB
14.3
6.7
PSC DECK
15
11
57
49
140+055
RC SLAB
6.5
5.8
BOX
50
143+740
RC SLAB
15.3
5.8
RC SLAB
20
11
1.35
51
145+721
ST DECK
24.1
5.2
PSC DECK
25
12
1.43
35
35
Pavement Type Classification
Asphalt Concrete
DBST
Cross Section
Results of Comparison
Selection
●The beginning section which is planned to be 4-lane road was paved with asphalt concrete and has a heavy traffic volume. Therefore, asphalt concrete pavement would be advantageous since it has low deterioration rate and low maintenance cost during the service life. ●The section after Sta. 14+000 which is planned to be 2~4 lane road will be connected with the road between Kampot ~ Trapang (NR No. 3) constructed with DBST pavement. Therefore, DBST pavement would be advantageous in consideration of the connectivity with NR No. 3, low initial investment cost, constructability and economic viability. ● 4 Lanes (L=1065 km) ● Sta. 12+350 ~ Sta. 14+000
● 2 Lanes (L=132.15 km) ● 4 Lanes (L=0.95 km)
Pavement Thickness Item
Urban Area (4 Lanes)
Rural Area (2 Lanes)
Pavement Type
Asphalt Concrete
DBST
Applied Design Standard 18 Kips ESAL Traffic
AASHTO
10 years
3.066x106
1.797x106
20 years
8.418x106
4.868x106
A/C Surface(t=7.0cm)
DBST
Base Course(t=22.0cm)
Base Course(t=20.0cm)
Layer Composition and Thickness
Subbase Course(t=35.0cm) Construction Cost Overlay
US$208,000/km
Subbase Course(t=30.0cm)
US$124,000/km
T=5cm, 10th year from road opening to service (Year 2021)
Background Materials survey for establishing their supply plan as well as reviewing their mechanical characteristics of coarse aggregates, fine coarse aggregates and subgrade materials was conducted to explore the material sources available in the areas of alreadydeveloped sites and potential material source sites. It would be better to use self-plant to be constructed rather than purchased from existing plants because conveyance distances from the existing plants are long and the quality of materials from the self-plant will be guaranteed.
Aggregate Sites Aggregate Sites
Address
Distance (km)
Capacity (㎥ )
Remarks
A-1
Stung Slakou in Takeo Province
66
100,000
66k (fine aggregate)
Borrow Pits Borrow Pits
Address
Distance (km)
Capacity (㎥ )
Remarks
B-1
Veal in Kampong Speu Province
41
100,000
39k+000 RHS 2km
B-2
Stung Slakou in Takeo Province
66
300,000
65k+900 RHS 100m
B-3
Phnom Noreay in Kampot Province
96
250,000
96k+000 RHS 150m
B-4
Phnom Troryoeung in Kampot Province
128
250,000
127k+900 RHS 100m
THE END