Evaluation of Cleco Settlement Proposal March 11, 2008
Outline
Summary of Proposed Power Supply Agreement Summary of the Existing Arrangement Savings Analysis Uncertainty Analysis Conclusions
Privileged and Confidential, Attorney Work Product
2
Proposed Power Sales Agreement
Current draft – 3/2/08 Term – 12 Years (Oct. 1 or earlier)
Meets COA’s supplemental needs above RPS2 & SWPA Capacity charge on supplemental capacity
Option – 5 year extensions 24 month termination notice
2008: $4.50/kW-mo 2009-2019: $10.40/kW-mo (coincident w/ COD RPS3)
Energy charge based on Cleco average system fuel cost, plus $2/MWh Privileged and Confidential, Attorney Work Product
3
Proposed Power Sales Agreement (cont.) Capacity credit for DG Hunter – Option for a prepayment to COA DG Hunter dispatched by Cleco (Cleco pays fuel cost) COA required to maintain DG Hunter Provides for operation of DG Hunter by COA during emergency conditions Provides for Cleco O&M payments above 4 starts per unit and 4,000 MWh per year
Privileged and Confidential, Attorney Work Product
4
Proposed Power Sales Agreement (cont.)
Provides for Network Integrated Transmission Service under the Cleco OATT Requires other agreements with Cleco (Reliability & Interconnection, Control Area) Requires Bond Counsel reviews (tax issues) & release from LEPA Requires confirmation of transmission service by Cleco & Entergy (SWPA)
Privileged and Confidential, Attorney Work Product
5
Existing Arrangement with Cleco
COA provides for its own capacity needs COA retains RPS2 and SWPA purchases COA operates and maintains DG Hunter (can be dispatched by Cleco or COA) CLECO Special Energy
Energy requirements above RPS2 and SWPA Rate is lower of average cost of Cleco gas generation or market purchases, plus $2/MWh management fee
Firm and non-firm point-to-point transmission arranged on COA’s behalf Privileged and Confidential, Attorney Work Product
6
Savings Analysis
Privileged and Confidential, Attorney Work Product
7
Projected Power Costs (2008 – 2019) Incremental Power Costs ($/MWh)
120
100
80
60
40
20
Represents incremental power supply costs 0 2004
2005
2006
2007
2008
2009
2010
2011
Existing Arrangement
2012
2013
2014
2015
2016
2017
2018
2019
CLECO Proposal Privileged and Confidential, Attorney Work Product
8
Projected Results (2008 – 2019)
Projected Nominal Power Costs
Existing Arrangement - $844 Million Proposed Arrangement - $786 Million Difference - $58 Million
Projected Present Value Power Costs
Existing Arrangement - $607 Million Proposed Arrangement - $566 Million Difference - $41 Million
Present value rate = 5%
Privileged and Confidential, Attorney Work Product
9
Projected Savings
Projected Nominal Power Cost Savings
Average over first 5 years (2008-2012)
$3.5 million or $4.10/MWh
Average over Initial Term (2008–2019)
$4.8 million or $5.50/MWh
Privileged and Confidential, Attorney Work Product
10
Uncertainty Analysis
Privileged and Confidential, Attorney Work Product
11
Primary Risk Considerations
Carbon Legislation Purchased Power Prices Fuel Prices Unit Outages COA Load Growth
Privileged and Confidential, Attorney Work Product
12
Comparison of Projected Power Costs 20%
Cumulative Nominal (2008-2019)
18% 16%
Probability
14% 12% 10% 8% 6% 4% 2% 0% 700
720
740
760
780
800
820
840
860
880
900
920
940
960
980
Cumulative Power Costs ($M) Cleco Proposed PSA
Current Arrangement Privileged and Confidential, Attorney Work Product
13
Difference in Projected Power Costs Existing v. Proposed Arrangement 12%
Cumulative Nominal (2008-2019)
10%
Probability
8%
6%
4%
2%
0% -20
-10
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
Cumulative Power Cost Savings ($M) Privileged and Confidential, Attorney Work Product
14
Comparison of Projected NPV Power Costs 30%
Net Present Value (2008-2019)
25%
Probability
20%
15%
10%
5%
0% 500 510 520 530 540 550 560 570 580 590 600 610 620 630 640 650 660 670 680 690 700 710
NPV Power Costs ($M; $2007) Cleco Proposed PSA
Current Arrangement Privileged and Confidential, Attorney Work Product
15
Difference in Projected NPV Power Costs Existing v. Proposed Arrangement 16%
Net Present Value (2008-2019)
14%
Probability
12%
10%
8%
6%
4%
2%
0% -20 -15 -10 -5
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95 100
NPV Power Cost Savings ($M; $2007) Privileged and Confidential, Attorney Work Product
16
Conclusions
Under expected assumptions, the Cleco Proposal is projected to be $58 million ($41 million NPV) lower than the Existing Arrangement. Power supply costs under the Cleco Proposal are projected to vary less than under the Existing Arrangement. Savings under the Cleco Proposal are projected to be between $27 million and $93 million (90% confidence interval) on a nominal basis for the major risks evaluated. Privileged and Confidential, Attorney Work Product
17
Major Assumptions
Privileged and Confidential, Attorney Work Product
18
Major Modeling Assumptions – Existing Arrangement
Special Energy rate
Cleco natural gas generation cost reflects only existing Cleco gas-fueled units Includes CO2 allowance costs beginning 2012 Cost of market purchases based on R. W. Beck’s power market forecast
Reserve capacity
Reserves purchased to meet 13.6% reserve margin Reserve capacity price assumed to be $5/kW-mo, escalated at inflation Privileged and Confidential, Attorney Work Product
19
Major Modeling Assumptions – Cleco Proposal
Fuel charge
Average system fuel cost adjusted for 2% losses Includes CO2 allowance costs beginning 2012
Reserve capacity assumed to be provided by Cleco, other than for RPS2 COA incurs no additional DG Hunter O&M cost resulting from dispatch by Cleco
Privileged and Confidential, Attorney Work Product
20
Economic Assumptions Inflation rate - 2.3% per year Discount rate - 5.0%
Privileged and Confidential, Attorney Work Product
21
Alexandria Load Forecast
Econometric load forecast completed in Feb 2007 by R. W. Beck
Historical analysis over 1990-2006 Explanatory variables included population and personal income in Rapides Parish, the retail price of electricity, and weather
Adjusted to reflect expected addition of a large industrial customer (RSI) Privileged and Confidential, Attorney Work Product
22
Fuel Forecasts Coal price forecast prepared by a coal market consultant for R. W. Beck Petroleum coke (RPS3 fuel) forecast developed based on historical relationship between coal and pet coke Natural gas price forecast developed by R. W. Beck (Henry Hub and basis differential to Cleco region)
Privileged and Confidential, Attorney Work Product
23
Emission Allowances Existing laws regarding SO2 and NOX are assumed to remain in effect throughout study period CO2 cap and trade system is assumed to be in effect beginning 2012 ($12/ton in 2012, increasing at inflation)
Privileged and Confidential, Attorney Work Product
24
Cleco Energy Cost Model
Cleco energy costs projected based on a production cost simulation model
O&M costs of existing units from FERC Form I reports Rodemacher 3 (RPS3) assumed to be on-line 1/1/2010 Cost of RPS3 based on publicly available information and industry data Generic CT & CC units added based on a generation expansion optimization model Privileged and Confidential, Attorney Work Product
25
Electricity Market Prices
Market prices for electricity for the Cleco region are based on R. W. Beck’s proprietary U.S. power market model (2007 Q3)
Privileged and Confidential, Attorney Work Product
26