SUPPLIER INSTRUCTION
RBAU AUTHOR
Section 9. Supplier PPAP
PUR
ISSUED BY
PAGE
OF
PUR
1
5
ED./AMEND.
ISSUE DATE
3/0
15/06/01
CONTENTS
1.
2
INTRODUCTION
2
1.2
Purpose
2
1.3
Applicability
2
1.4
Definitions
2
PROCEDURE 2.1
When Submission is Required
3
2.2
Submission of PPAP
3
2.3
Approval Process
4
2.4
Delivery Types Summary
5
Effective Date
Change History
15/06/01
Reviewed & revised
18/09/00
Adjustments to 2.2 Submission of PPAP
04/12/98
New procedure
If printed, document is uncontrolled and is the user’s responsibility to check that this document reflects the latest revision level. Print Date: 26/07/01
SUPPLIER INSTRUCTION
RBAU AUTHOR
PUR
1
Section 9. Supplier PPAP
ISSUED BY
PAGE
OF
PUR
2
5
ED./AMEND.
ISSUE DATE
3/0
15/06/01
Introduction Production part review and approval is required for each part before the first shipment of production quantities to RBAU. Review of the Purchased parts at RBAU is in accordance with the requirements of the QS9000 PPAP (Production Part Approval Process).
1.2
Purpose The purpose of Production Part Approval Process is to determine if all RBAU Production drawing and specification requirements have been met by the supplier, and to ensure that the manufacturing process has the potential to meet these requirements on an ongoing basis. Production parts are only to be delivered to RBAU after the PPAP has been approved, or with a prior approved RBAU concession to authorise shipment from supplier. The Concession number must be quoted on the delivery documentation for all stock shipped under Concession. The Supplier has the responsibility to ensure that Concession authorised quantities and expiry dates are not exceeded.
1.3
Applicability All direct production materials supplied to RBAU.
1.4
Definitions RBAU :
Robert Bosch (Australia) Pty. Ltd.
PGQP:
Purchased Goods Quality Plan
PLP:
Purchasing Launch Plan
PPAP:
Production Part Approval Process
PUR:
Purchasing – RBAU Dept.
RFQ:
Request For Quotation
QS9000:
Quality System as defined by GM, Chrysler & Ford. Automotive Industry Standard
OOPT:
Out of Present Tooling
QS9000 Manuals available from: AIAG (USA):
26200 Lahser Road, Suit 200 Southfield, MI 48034Ph. (248) 358 3003 Fax: (248) 358 3253
FAPM (Aust):
GPO Box 295, Canberra ACT 2601, Ph. (612) 6247 4177 Fax (612) 6257 4651 E-mail:
[email protected]
If printed, document is uncontrolled and it is the user’s responsibility to check that this document reflects the latest revision level. Print date: 26/07/01
SUPPLIER INSTRUCTION
RBAU AUTHOR
PUR
Section 9. Supplier PPAP
2
Procedure
2.1
When Submission is Required
ISSUED BY
PAGE
OF
PUR
3
5
ED./AMEND.
ISSUE DATE
3/0
15/06/01
Production Part Approval Process by RBAU is always required before the first production shipment of product for situations specified in “When Submission is Required” section of the QS9000 PPAP Manual. Make sure to contact your RBAU Buyer or Supplier Quality Engineer if there is any question concerning the PPAP. The Supplier will be requested by RBAU to prepare a PPAP submission for any of these situations. It is the responsibility of the Supplier to notify the RBAU Supplier Quality Engineer when any of the changes requiring submission in the QS9000 PPAP Manual, will occur or have occurred without prior instruction from RBAU. The supplier will be advised by RBAU of the resulting obligation for PPAP submission. 2.2
Submission of PPAP
2.2.1
New Projects/Parts/Suppliers: Once RBAU has selected the supplier, a PLP (refer PLP Instruction) is sent to the supplier stating PPAP submission requirements. If specified in the PLP, a PGQP (refer PGQP Instruction) is to be agreed upon by RBAU & Supplier to ensure the necessary controls are in place for the quality manufacture of production stock. The PPAP Submission is to be compiled by the supplier in accordance with the PLP Checklist. If the samples or documentation do not comply fully with RBAU specifications and/or the PLP Checklist, the supplier must correct or obtain a written acceptance from RBAU via the Supplier Quality Engineer. This acceptance must be submitted with PPAP. The supplier is to pack PPAP Samples & Documentation together but separate from other deliveries. This package is to be clearly marked “PPAP Submission”, and the PPAP Order Number is to be quoted on all delivery documentation. The PPAP will be assessed by RBAU and the supplier advised of the disposition. PPAP Re-submission: The Re-Approval of a part may be initiated by either RBAU or the supplier. When the Re-Submission is initiated by RBAU, the supplier will be instructed to resubmit PPAP, and will be provided a PLP to nominate the requirements for the PPAP. If there is a change at the suppliers premises that necessitates Re-Submission, as specified by the QS 9000 guidelines, this must be advised to RBAU Purchasing buyer or the relevant Supplier Quality Engineer.
If printed, document is uncontrolled and it is the user’s responsibility to check that this document reflects the latest revision level. Print date: 26/07/01
SUPPLIER INSTRUCTION
RBAU AUTHOR
Section 9. Supplier PPAP
PUR
ISSUED BY
PAGE
OF
PUR
4
5
ED./AMEND.
ISSUE DATE
3/0
15/06/01
RBAU will advise the supplier of the PPAP requirements, and provide the supplier with a PLP to specify the requirements for the PPAP submission. 2.3
Approval Process Confirmation of the PPAP disposition will be via letter from PUR. The supplier PPAP submission will be evaluated for conformance to the requirements specified in the PLP and PPAP order. The following table shows the options for the disposition of the PPAP. The scores allocated to each PPAP are also shown. These scores are used for evaluation the suppliers PPAP performance. Approved
Fully Approved (Part Fully Conforms to RBAU Requirements).
0
Approved
Fully Approved (Drawing to be updated with OOPT waivers).
0
Approved
Fully Approved but Submission Delivered Late
1
Approved
Fully Approved but Submission Documents Incomplete
2
Approved
Fully Approved but Submission Delivered Late and Production Affected
5
Provisional
PPAP Parts used on Concession
1
Rejected
Parts are non conforming
3
Rejected
Parts are non conforming and Production Affected
5
Rejected
Parts are non conforming and rejected on Re-Submission
6
Rejected
Parts are non-conforming and Rejected on Re-Submission and Production Affected
8
Rejected
Parts conforming to specification, functionally non conforming
0
If printed, document is uncontrolled and it is the user’s responsibility to check that this document reflects the latest revision level. Print date: 26/07/01
SUPPLIER INSTRUCTION
RBAU AUTHOR
PUR
1.4
Section 9. Supplier PPAP
ISSUED BY
PAGE
OF
PUR
5
5
ED./AMEND.
ISSUE DATE
3/0
15/06/01
Delivery Types Summary: This Matrix clarifies the different types of part deliveries to RBAU: Engineering Samples
PPAP Submission
Production Deliveries PPAP Approved
Concession
Order Type:
Engineering Samples Order
PPAP Order
Production Order
Approved Concession + Production Order
Parts Ordered for:
Engineering Prototype Samples
PPAP Approval Submission Only
RBAU Production
RBAU Production
PPAP Order exclusively used for PPAP submissions including all documents.
Part must be PPAP Approved by RBAU.
If part is not PPAP approved by RBAU, stock must not be shipped unless a concession has been authorised.
RBAU process evaluation RBAU Part Evaluation Delivery Instructions:
Pack Separately from other parts. Separate Delivery Documents. Identify delivery as “Engineering Samples”.
Pack samples and all documents together but separate from other deliveries.
Ship stock to Production schedule.
Quote Concession Number on delivery documents for all shipments.
Package labelled as “PPAP Submission”
Supply to production schedule but concession quantity/date limits must not be exceeded.
PPAP delivery documents to quote PPAP Order Number. Supplier Instruction:
Engineering Samples
PPAP, PLP, (PGQP)
PPAP, Delivery
PPAP, Delivery