2/12/2006
PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Planning & Cost Control Manager
Time Management Processes Chapter 6
Time Management
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 2
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
AGENDA Time Management Processes What is Time Management? How does the PMBOK® Guide describe Time Management? Discussion
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 3
Planning & Cost Control Manager
[email protected] +20105394312
Time Management Processes required to accomplish timely completion of the project Activity Definition Activity Sequencing Activity Resource Estimating Activity Duration Estimating Schedule Development Schedule Control Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 4
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Key Elements Of Time Management n
Estimating
n
Network Analysis Techniques
n
There will be questions from both of these topics on the exam!
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 5
Planning & Cost Control Manager
[email protected] +20105394312
Estimating n
n
Time management involves a bottoms-up approach. Estimate the duration of each activity and combine that with the network diagram to build up the schedule to determine overall project duration. Top-Down estimating is not a recommended PMI method for establishing overall project duration. Noted/qualified exception: When there is a limited amount of detailed information about the project. Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 6
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Estimating Activity Duration Estimating n
n
Expert judgment guided by historical information used whenever possible Anything less is inherently uncertain and risky
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 7
Planning & Cost Control Manager
[email protected] +20105394312
Estimating Quantitatively Based Durations Example (Pipeline Construction) 200 m of pipe can be welded per day 30000 m of pipe are required 30000 m / 200 m per day = 150 days
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 8
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Estimating Quantitatively Based Durations Example (IT Y2K Planning) 1 program debugged and unit tested per week 20 programs to be corrected 20 programs / 1 program per week = 20 weeks Akram Al-Najjar, PMP. Slide 9
Source: pmbok guide 2004
Planning & Cost Control Manager
[email protected] +20105394312
Estimating PERT Duration Calculation Higher
Probability Of Occurrence
Most Likely (Used in original CPM Calculations)
(
PERT Weighted Average = Optimistic + 4 X Most Likely + Pessimistic 6 Beta Distribution
Optimistic
Lower Shorter
Pessimistic
Possible Durations
Longer Akram Al-Najjar, PMP.
Source: pmbok guide 2004
Slide 10
Planning & Cost Control Manager
[email protected] +20105394312
)
2/12/2006
Calculation of PERT PROBABILITIES n
TIME ESTIMATE
Te= a + 4b + c 6 n
a = OPTIMISTIC
n
b= MOST LIKEY
n
c = PESSIMISTIC
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 11
Planning & Cost Control Manager
[email protected] +20105394312
Calculation of PERT PROBABILITIES continue n
TIME VARIANCE
s =c–a 6 § §
V = s2
a = OPTIMISTIC c = PESSIMISTIC
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 12
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Normal Distribution
Statistically measures variability - commonly used in quality control -1σ
+1 σ
-2 σ -3σ
+2σ +3σ
T e, Project Duration
68.26% 95.46% 99.73% LCL
UCL
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 13
Planning & Cost Control Manager
[email protected] +20105394312
Network Diagram Analysis Critical Path Method n
Critical Path
n
Early/Late Start and Finish
n
Float
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 14
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Network Diagram Analysis 2 Days
12 Days
5 Days
A
B
C Finish
Start 6 Days
3 Days
7 Days
D
E
F
There are many ways to do this. This is just one approach. Find one you like and learn it. Slide 15
Source: pmbok guide 2004
Akram Al-Najjar, PMP. Planning & Cost Control Manager
[email protected] +20105394312
Network Diagram Analysis The Forward Pass … Early Start Box 0 0
Early Finish Box
2 Days 2 A
0
Early Start Date = Early Start Box + 1 Day
6 Days
Start 0
6 D
Early Finish Date = Early Finish Box Akram Al-Najjar, PMP.
Source: pmbok guide 2004
Slide 16
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Critical Path Method The Forward Pass … Early Start = Highest of predecessor’s Early Finish Times 2 Days 0 2 A 0
12 Days 2 14 B
5 Days 14 19 C 19
0 Start
6 Days 0 6 D
7 Days 6 13 E
19
Finish
3 Days 13 16 F
Akram Al-Najjar, PMP. Planning & Cost Control Manager
[email protected] +20105394312
Slide 17
Source: pmbok guide 2004
Critical Path Method The Backward Pass … 5 Days 14 Late Start Date = Late Start Box + 1 Day
19 C
19 19
14
13
Finish 19
3 Days Late Finish Date = Late Finish Box
19 19
16 F
Late Start Box
16
19
Late Finish Box Akram Al-Najjar, PMP.
Source: pmbok guide 2004
Slide 18
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Critical Path Method The Backward Pass … Lowest of successor’s Late Finish = Late Start Times 12 Days 2 Days 5 Days 2 14 14 19 0 2 B A C 2 14 0 2 14 19 0 0 Start 6 Days 7 Days 3 Days 0 0 13 16 0 6 6 13 D E F 3 9 9 16 16 19
19 19 Finish 19 19
Akram Al-Najjar, PMP. Slide 19
Source: pmbok guide 2004
Planning & Cost Control Manager
[email protected] +20105394312
Critical Path Method FLOAT The amount of time a task can be delayed without delaying the end date of the project. The difference between either the Late and Early Start or the Late and Early Finish.
0
0 Start 0 0 Float = (0)
2 Days 0 2 A 0 2 (0) 6 Days 0 6 D 3 9 (3) Source: pmbok guide 2004
12 Days 2 14 B 2 14 (0) 7 Days 6 13 E 9 16 (3)
5 Days 14 19 C 14 19 19 19 (0) Finish 19 19 3 Days (0) 13 16 F 16 19 Akram Al-Najjar, PMP. & Cost Control Manager (3)Planning
[email protected] Slide 20
+20105394312
2/12/2006
Critical Path Method Critical Path = The longest path through the network = The path through the network with all tasks at 0 Float = Start-A-B-C-Finish 12 Days 2 Days 5 Days 2 14 14 19 0 2 B A C 2 14 0 2 14 19 19 19 0 0 (0) (0) (0) Finish Start 19 19 6 Days 7 Days 3 Days 0 0 (0) 0 6 6 13 13 16 Float = (0) D E F 3 9 9 16 16 19 Akram Al-Najjar, PMP. (3) (3) (3) Planning & Cost Control Manager
[email protected] Slide 21
Source: pmbok guide 2004
+20105394312
PERT Calculations -1σ
+1 σ
-2 σ -3σ
+2σ +3σ
Te, Project Duration
50%
84.13% 97.73%
99.86%
Project Start Date
• Normal Distribution: Ø 50% chance - using expected time durations ( Te, ) Ø 84%Source: chance - (Te , ) + 1 σ , etcSlide pmbok guide 2004
Akram Al-Najjar, PMP.
22
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
PERT Example Expected Project Duration: 12.33 days B
A
Standard Deviation of Critical Path: .8988 VARIANCE =0.67x0.67+0.5x0.5+0.33x0.33=0.8078
Task D Time, Days PERT standard Activity OptimisticMost Likely Pessimistic Expected deviation C
A
2
4
6
4
.67
B
2
3
5
3.33
.5
C
4
7
10
7
1
D
4
5
6
Source: pmbok guide 2004
5Akram Al-Najjar,.33 PMP. Slide 23
Planning & Cost Control Manager
[email protected] +20105394312
PMBOK® Chapter 6 There are 5 major Processes: 1.
Activity Definition
2.
Activity Sequencing
3.
Activity Resource Estimating
4.
Activity Duration Estimating
5.
Schedule Development
6.
Schedule Control Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 24
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Time Management Planning 6.1 Activity Definition
6.2 Activity Sequencing
Controlling
6.3 Resource Estimating 6.5 Schedule Development
6.5 Schedule Control
6.4 Activity Duration Estimating
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 25
Planning & Cost Control Manager
[email protected] +20105394312
Slide 26
Planning & Cost Control Manager
[email protected] +20105394312
Akram Al-Najjar, PMP. Source: pmbok guide 2004
2/12/2006
Activity Definition
n
Identifying the specific schedule activities that need to be performed to produce the various project deliverables.
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Planning & Cost Control Manager
[email protected] +20105394312
Slide 27
Activity Definition Tools & Techniques • • • • •
Decomposition Templates Rolling Wave Planning Expert Judgment Planning Component
Inputs • Enterprise Environmental Factors • Organizational Process Assets • Project Scope Statement • WBS • WBS Dictionary • Project Management Plan Source: pmbok guide 2004
Outputs • • • •
Activity list Activity Attributes Milestone List Requested Changes Akram Al-Najjar, PMP.
Slide 28
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Activity Definition Inputs n
Enterprise Environmental Factors
:
(Section 4.1.1.3) that can be considered include availability of project management information systems and scheduling software tools. n
Organizational process assets (Section 4.1.1.4) contain the
existing formal and informal activity planning- related policies, procedures, and guidelines that are considered in developing the activity defini tions. The lessons -learned knowledge n
Project Scope Statement : The project deliverables, constraints, and assumptions documented in the project scope statement (Secti on 5.2.3.1) are considered explicitly during activity definition.
n
WBS (Section 5.3.3.2)
n
WBS Dictionary (Section 5.3.3.3)
n
Project Management Plan : contains the schedule management plan
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 29
Planning & Cost Control Manager
[email protected] +20105394312
Activity Definition Tools & Techniques n
Decomposition –
n
Template –
n
Rolling Wave Planning : is progressive detailing of the
Subdividing project work packages into smaller, more manageable components An activity list from a previous project or an activity list for a WBS element from the current project project plan indicating that planning is an iterative and ongoing process.
n n
Expert Judgment Planning Component Control Account. (specific components at selected levels) Planning Package. (a WBS component below the control account, but above the work package.)
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 30
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Activity Definition Outputs –
n
Activity list
n
Activity Attributes– include the activity identifier, activity
A list of all the activities that will be performed on the project and a description of each
codes, activity description, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, assumptions, person responsible and geographic area
Milestone List : identifies all milestones and indicates whether the milestone is mandatory (required by the contract) or optional (based upon project requirements or historical information). n
Requested Changes : that can affect the project scope statement and WBS.
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 31
Planning & Cost Control Manager
[email protected] +20105394312
Activity Sequencing
n
Identifying and documenting dependencies among schedule activities.
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 32
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Activity Sequencing Tools & Techniques • Precedence diagramming method (PDM) • Arrow diagramming method (ADM) • Schedule network templates • Dependency determination • Applying leads and lags
Inputs
Outputs
• • • • •
• Project Schedule network diagram • Activity list (updates) • Activity Attributes (updates) • Requested Change Akram Al-Najjar, PMP.
Project Scope Statement Activity list Activity Attributes Milestone List Approved Requested Changes Source: pmbok guide 2004
Slide 33
Planning & Cost Control Manager
[email protected] +20105394312
Inputs n
Activity list (6.1.3.1)
n
Activity Attributes (6.1.3.2)
n
Milestone List (6.1.3.3)
n
Approved Requested Changes (4.4.1.4)
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 34
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Tools & Techniques n
Precedence diagramming method (PDM) n
Nodes represent activities and arrows show dependencies A
B E
Start
C
Finish
D Akram Al-Najjar, PMP.
Source: pmbok guide 2004
Planning & Cost Control Manager
[email protected] +20105394312
Slide 35
Activity Sequencing Process Finish-to-Start – Activity A must finish before Activity B can start , the initiation of the work of the successor depends upon the completion of the work of the predecessor.
A
B
Start-to-Start – Activity A must start before Activity B can start , the initiation of the work of the successor depends upon the initiation of the work of the predecessor.
A
B Akram Al-Najjar, PMP.
Source: pmbok guide 2004
Slide 36
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Activity Sequencing Process Finish-to-Finish – Activity A must finish before Activity B can finish , the completion of the work of the successor depends upon the completion of the work of the predecessor.
B
A
Start-to-Finish – Activity A must start before Activity B can finish , the completion of the successor is dependent upon the initiation of the predecessor.
A
B Akram Al-Najjar, PMP. Planning & Cost Control Manager
[email protected] +20105394312
Slide 37
Source: pmbok guide 2004
Tools and Techniques n
(cont.)
Arrow diagramming method (ADM) – Uses arrows to represent activities and connecting nodes to show dependencies Start
A B C D
E Finish
n
ADM uses finish-to-start dependencies only and uses dummy activities to show logical relationships Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 38
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Tools & Techniques (cont.) n
n
n
Schedule Network templates – Can include an entire project or just a portion of it (i.e., subnets and fragnets) Dependency determination : -Mandatory dependencies (Hard logic) – Determined by the qualities of work to be done -Discretionary dependencies (Soft logic) Defined by the project management team -External dependencies – Relationships between project activities and non-project activities Applying Leads and Lags Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 39
Planning & Cost Control Manager
[email protected] +20105394312
Outputs n
n
Project Schedule network diagram – Schematic display of project’s activities and dependencies Activity list updates – Dividing or redefining activities so that the relationships are correctly diagrammed
n
Activity Attributes (Updates)
n
Requested Changes Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 40
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Activity Resource Estimating
n
Estimating the type and quantities of resources (persons, equipment, or materiel) required to perform each schedule activity.
Akram Al-Najjar, PMP. Slide 41
Source: pmbok guide 2004
Planning & Cost Control Manager
[email protected] +20105394312
Activity Resource Estimating Tools & Techniques • • • • •
Expert judgment Alternatives Analysis Published Estimating Data Project Management Software Bottom-up Estimating
Inputs • Enterprise Environmental Factors • Organizational Process Assets • Activity List • Activity Attributes • Resource Availability • Project Management Plan Source: pmbok guide 2004
Outputs • • • • •
Resource requirements Activity Attributes (Updates) Resource Breakdown Structure Resource Calendar (Updates) Requested Changes Akram Al-Najjar, PMP. Slide 42
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Inputs n
Enterprise Environmental Factors: The
n
Organizational Process Assets : provide the
n
Activity List
n
Activity Attributes
n
Resource Availability
n
Project Management Plan
Activity Resource Estimating process uses the infrastructure resource availability information included in enterprise environmental factors (Section4.1.1.3). policies of the performing organization regarding staffing and the rental or purchase
Source: pmbok guide 2004
Slide 43
Akram Al-Najjar, PMP. Planning & Cost Control Manager
[email protected] +20105394312
Tools & Techniques n
Expert judgment – Expertise, provided by any
n
Alternatives Analysis (make-or-buy decisions
group or individual, used to assess the inputs to this process n Other units within organization n Consultants n Professional and technical associations n Industry groups regarding the resource )
n n n
Published Estimating Data Project Management software Bottom-up Estimating Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 44
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Outputs n
Resource requirements – Description of the types (e.g., skill levels) and numbers of resources required by each element of the WBS
n
Activity Attributes (Updates)
n
Resource Breakdown Structure :(RBS) is a
n
Resource Calendar (Updates)
n
Requested Changes
hierarchical structure of the identified resources by resource category and resource type.
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 45
Planning & Cost Control Manager
[email protected] +20105394312
Activity Duration Estimating n
The process of estimating schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
• Elapsed time (Delay) – Work periods between the finish of one activity and the start of another activity
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 46
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Activity Duration Estimating Tools & Techniques • • • • •
Inputs
• Enterprise Environmental Factors • Organizational Process Assets • Project Scope Statement • Activity list • Activity Attributes • Activity Resource requirements • Resource Calendar • Project Management Plan Risk Register Activity Cost Estimates. Source: pmbok guide 2004
Expert judgment Analogous estimating Parametric estimating Three-Point Estimates Reserve Analysis
Outputs • Activity duration estimates • Activity Attributes (Updates)
Akram Al-Najjar, PMP. Slide 47
Planning & Cost Control Manager
[email protected] +20105394312
Inputs n
n
n
n n n
Enterprise Environmental Factors: One or more of the
organizations involved in the project may maintain duration estimating databases and other historical reference data. Organizational Process Assets: Historical information (Section 4.1.1.4) on the likely durations of many categories of activities is often available. Project Scope Statement : The constraints and assumptions from the project scope statement (Section 5.2.3.1) are considered when estimating the schedule activity durations. Activity List Activity Attributes Resource requirements – The estimated activity resource requirements (Section 6.3.3.1) will have an effect on the duration of the schedule activity.
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 48
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Inputs
( Cont.)
n
Resource Calendar
n
Project Management Plan Risk Register: The risk register has information on
identified project risks that the project team considers when producing estimates of activity durations and adjusting those durations for risks.
Activity Cost Estimates: provide estimated resource
quantities for each schedule activity in the project activity list.
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 49
Planning & Cost Control Manager
[email protected] +20105394312
Tools & Techniques n n
n
n n
Expert judgment – guided by historical information Analogous estimates (Top-down estimating) –
Uses duration of a previous, similar activity as the basis for the of estimate of a future activity Parametric Estimating: Estimating the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate. Three-Point Estimates: Most likely, Optimistic, and Pessimistic. Reserve Analysis: An additional time frame, called time reserve, contingency, or buffer, that can be added to the activity duration or elsewhere in the schedule as recognition of schedule risk
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 50
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Outputs n
n
Activity Duration estimates – Quantitative assessments of the likely number of work periods required to complete an activity Activity Attributes (Updates) : The activity attributes (Section 6.1.3.2) are updated to include the durations for each schedule activity, the assumptions made in developing the activity duration estimates, and any contingency reserves. Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 51
Planning & Cost Control Manager
[email protected] +20105394312
Schedule Development Determining the start and finish dates of project activities
If start and finish dates are not realistic, the project is unlikely to be finished on schedule
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 52
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Schedule Development Tools & Techniques
Inputs • • • • • • • • •
Organizational Process Assets Project Scope Statement Activity List Activity Attributes Project Schedule Network Diagrams Activity Resource Requirements Resource Calendars Activity Duration Estimates Project Management Plan Risk Register.
• • • • • • • • • •
Schedule Network Analysis Critical Path Method Schedule Compression What-If Scenario Analysis Resource Leveling Critical Chain Method Project Management Software Applying Calendars Adjusting Leads and Lags Schedule Model
Outputs • • • • • • • •
Project schedule Schedule Model Data Schedule Baseline Resource-requirement updates Activity Attributes (Updates) Project Calendar (Updates) Requested Changes Project Management Plan (Updates) Akram Al-Najjar, PMP.
Source: pmbok guide 2004
Slide 53
Planning & Cost Control Manager
[email protected] +20105394312
Inputs n
n n n n n n n n
Organizational Process Assets: such as a project calendar (a calendar of working days or shifts that establishes dates on which schedule activities are worked, and nonworking days on which schedule activities are idle). Project Scope Statement: (Section 5.2.3.1) contains assumptions and constraints Activity List Activity Attributes Project Schedule Network Diagrams Activity Resource Requirements Resource Calendars Activity Duration Estimates Project Management Plan: Risk Register. Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 54
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Tools & Techniques n
Schedule Network Analysis It employs a schedule model and various analytical techniques, such as critical path method, critical chain method, what-if analysis, and resource leveling to calculate the early and late start and finish dates,
n
Critical Path Method
n
Schedule Compression : n
n
Crashing – Analyzing cost and schedule tradeoffs to determine how to obtain the greatest amount of compression for the least incremental cost Fast tracking – Doing activities in parallel that would normally be done in sequence Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 55
Planning & Cost Control Manager
[email protected] +20105394312
Tools & Techniques n
What-if analysis : such as delaying a major component
n
Resource-leveling (Resource-based method) – Changing
delivery, extending specific engineering durations, or introducing external factors, such as a strike or a change in the permitting process. the schedule to accommodate resources
Critical Chain Method: The critical chain method adds
duration buffers that are non-work schedule activities to maintain focus on the planned activity durations. Once the buffer schedule activities are determined, the planned activities are scheduled to their latest possible planned start and finish dates. Consequently, In lieu of managing the total float of network paths, the critical chain method focuses on managing the buffer activity durations and the resources applied to planned schedule activities. Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 56
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Tools & Techniques (con.)
– Used to assist schedule development and to display schedule-development outputs
n
PM Software
n
Applying Calendars: Project calendars (Section 4.1.1.4) and resource calendars (Section 6.3.3.4) identify periods when work is allowed.
n
Adjusting Leads and Lags: Since the improper use of
leads or lags can distort the project schedule, the leads or lags are adjusted during schedule network analysis to develop a viable project schedule. n
Schedule Model : Schedule data and information are compiled into the schedule model for the project. The schedule model tool and the supporting schedule model data are used in conjunction with manual methods or project management software to perform schedule network analysis to generate the project schedule. Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 57
Planning & Cost Control Manager
[email protected] +20105394312
Outputs n
n n n n n n n
Project schedule : includes at least a planned start date and planned finish date for each schedule activity. Project schedule network diagrams. Bar charts. Milestone charts. Schedule Model Data Schedule Baseline : baseline is a specific version of the project schedule developed Resource Requirements (Updates) Activity Attributes (Updates) Project Calendar (Updates) Requested Changes Project Management Plan (Updates) Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 58
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Network Calculation Start Date 6/1 6/6 6/10
B 6/1 6/5
5
6/11 6/15
A
5
6/1 6/5 0
5 6/6 6/15
C
6/16 6/25
6/26 6/30
D
E
10
6/16 6/25 0
5
6/26 6/30 0
Finish Date 6/30
10
6/6 6/15 0 Calculations Forward Pass – Determine early start and early finish dates Backward Pass – Determine late start and late finish dates and float Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 59
Planning & Cost Control Manager
[email protected] +20105394312
Basic Terminology n
n
Total float (Slack) – Amount of time an activity can be delayed and the project finish date not be effected Free Float – Amount of time an activity can be delayed and the early start of the follow-on activity not be effected
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 60
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Gantt Charts n
n
Bar chart – Displays activity start and end dates, as well as expected durations Milestone chart – Displays scheduled start or completion of major deliverables
Akram Al-Najjar, PMP. Planning & Cost Control Manager
[email protected] +20105394312
Slide 61
Source: pmbok guide 2004
Typical Gantt Chart Activity
Task A Task B Task C Task D June
July
Aug
Sep
Time Source: pmbok guide 2004
Oct
Nov Akram Al-Najjar, PMP.
Slide 62
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Typical Milestone Chart
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 63
Planning & Cost Control Manager
[email protected] +20105394312
Schedule Control Schedule control is concerned with: n Determining the current status of the project schedule n Influencing the factors that create schedule changes n Determining that the project schedule has changed n Managing the actual changes as they occur. Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 64
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Schedule Control Tools & Techniques • • • • • •
Progress Reporting Schedule Change Control System Performance Measurement Project Management Software Variance Analysis Schedule Comparison Bar Charts
Outputs Inputs • • • •
Schedule Management Plan Schedule Baseline Performance Reports Approved Change Requests
Source: pmbok guide 2004
• • • • • • • •
Schedule Model Data (Updates) Schedule Baseline (Updates) Performance Measurements Recommended Corrective Actions Organizational Process Assets (Updates) Activity List (Updates) Activity Attributes (Updates) Project Management (Updates Akram Plan Al-Najjar, PMP. ) Slide 65
Planning & Cost Control Manager
[email protected] +20105394312
Inputs n n n n
Schedule Management Plan : (Section 4.3) Schedule Baseline: (Section 6.5.3.1) Performance Reports: (Section 10.3.3.1) Approved Change Requests : (Section 4.4.1.4)
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 66
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Tools & Techniques n
n
n
n n
includes information such as actual start and finish dates, and the remaining durations for unfinished schedule activities. Progress Reporting:
Schedule Change Control System: includes the paperwork, tracking systems, and approval levels necessary for authorizing changes. Performance Measurement: Performance measurement techniques produce the Schedule Variance (SV) (Section 7.3.2.2) and Schedule Performance Index (SPI) (Section 7.3.2.2) Variance Analysis: Comparing target schedule dates with the actual/forecast start and finish dates Schedule Comparison Bar Charts Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 67
Planning & Cost Control Manager
[email protected] +20105394312
Outputs n
Schedule Model Data (Updates)
n
Schedule Baseline (Updates)
n
Performance Measurements
n
Requested Changes
n
Recommended Corrective Actions
n
Organizational Process Assets (Updates)
n
Activity List (Updates)
n
Activity Attributes (Updates)
n
Project Management Plan (Updates)
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 68
Planning & Cost Control Manager
[email protected] +20105394312
2/12/2006
Short Break n
Any questions?
Akram Al-Najjar, PMP. Source: pmbok guide 2004
Slide 69
Planning & Cost Control Manager
[email protected] +20105394312