Piping System Acceptance Record Project #
Date
Package/System Package Requirement
Yes
No
Weld In-Process Checklists' Complete & Approved Non-Destructive Testing Complete & Approved Weld Maps Complete & Approved Flange Checklists' Complete & Approved Pipe Support Checklists' Complete & Approved Valve & Instrumentation Checklist' Complete & Approved Hydrostatic Test Record' Complete & Approved Pipe Insulation Checklists' Complete and Approval Remarks
Wanzek Construction, Inc. certifies that the pipe in this system is ready for commissioning.
QC Inspector
Date
Wanzek Supervisor
Date
Client Representive
Date
Company