LAMPIRAN K.1 PERHITUNGAN REKLAMASI REVEGETASI LAHAN
Volume OB & Top Soil yang tersedia Volume Soil = 202437,5 LCM
1. Tahun 2019
Volume OB & Top Soil yang tersedia Volume Soil = 202.437,5 LCM
2. Tahun 2019
Biaya Pengangkutan Material Luas lahan yang direvegetasi = 910,41 m2 Volume material OB
= 910,41 m2 x 1,25 m = 1.138,0125 m3 = Volume OB / Swell Factor = 1.138,0125 m3 / 0,8 = 1.422,516 LCM
Volume material Top Soil
= 910,41 m2 x 0,75 m = 682,8075 m3 = Volume Top Soil / Swell Factor = 682,8075 m3 / 0,8 = 853,509 LCM
Total Volume
= Volume OB + Volume Top Soil = 1.422,516 LCM + 853,509 LCM = 2.276,025 LCM
Kebutuhan pengangkutan : Volume material
= 2.276,025 LCM / 6 hari = 379,3375 LCM/ 7 jam = 54,19 LCM/jam
K-1
Bulldozer Merk : Komatsu D20P-3 Kapasitas blade bulldozer
= lebar x (tinggi blade)2 = 2,18 m x 0,585 m2 = 1,275 m3
Tanah yang terisi
= kapasitas blade / factor blade = 1,275 m3 / 1 = 1,275 LCM
Jam kerja efektif
= 60 menit x EU = 60 menit x 0,8 = 48 menit
Effisiensi kerja terhadap alat = Jam kerja efektif x MA = 48 menit x 0,8 = 38,4 menit Untuk blade capacity
= 1,275 m³
Kecepatan maju
= 58 meter/menit
Kecepatan mundur
= 91,67 meter/menit
Waktu mendorong maju
= (jarak dorong) / (kecepatan maju x konversi) = (10 meter) / ( 58 meter/menit ) = 0,17 menit
Waktu untuk mundur
= (jarak dorong)/(kecepatan mundur x konversi) K-2
= (10 meter)/( 91,67 meter/menit) = 0,109 menit Cycle time bulldozer
= waktu maju + waktu ganti porsnelling & gear + waktu mundur = (0,17 + 0,5 + 0,109) menit = 0,779 menit
Jumlah trip/ jam
= (jam kerja efektif) / (cycle time) = (48 menit) / (1,67 menit) = 28,74 trip = 29 trip
Produksi bulldozer/jam
= jumlah trip x kapasitas blade = 29 trip/ jam x 1,275LCM = 36,975 LCM/ jam
Bulldozer yang bekerja dilapangan = (Volume tanah penutup/minggu)/(produksi per minggu) = (54,19LCM/jam)/(36,975 LCM/jam) = 1,46 bulldozer = 2 bulldozer Bulldozer disediakan
= (Jumlah bulldozer di lapangan)/MA = 2/0,8 = 2,5 ≈ 3 unit bulldozer
Bulldozer cadangan
= bulldozer disediakan – bulldozer di lapangan
K-3
=3–2 = 1 bulldozer Backhoe Model : Komatsu PC130-8 Ukuran bucket
= 0,5 m3
Cycle Time
= 20 detik/bucket
Fill factor bucket tanah penutup
= 0,7
Swell factor tanah
= 0,8
Tinggi Jenjang
= 8 meter
EU
= 80 %
MA
= 80 %
Kapasitas Dump Truck
= 12,21 m3
Banyak bucket
= (kapasitas Dump truck)/(kapasitas bucket) = (12,21 m3)/(0,5 m3 ) = 24,42 bucket ≈ 24 bucket
Waktu pengisin Dump Truck
= banyak bucket x cycle time = 24 bucket x 20 detik/bucket = 480 detik = 8 menit
K-4
Produksi backhoe untuk pengupasan tanah penutup : Produksi/jam
= 3600/CT x (bucket capacity x bucket fill factor ) x EU = (3600/20 detik) x (0,5 m³ x 0,7) x 0,8 = 50,4 LCM/jam
Backhoe di lapangan
=
(Volume
lapisan
tanah
penutup/jam)/(Produksi Backhoe/jam) = (54,19 LCM/jam)/( 50,4 LCM/jam) = 1,075 unit backhoe = 1 unit backhoe Backhoe disediakan
= (Jumlah backhoe di lapangan)/MA = 1/0,8 = 1,25 ≈ 2 unit Backhoe
Backhoe cadangan
= Backhoe disediakan – Backhoe di lapangan =2–1 = 1 unit Backhoe
Dump truck Model
= Dump Dutro 130HD
Jarak angkut untuk tanah penutup
= 0,501 km
Power
= 128,22 HP
Efisiensi mesin
= 85%
Ukuran bakPanjang
= 2,9 meter K-5
Lebar
= 1,945 meter
Tinggi
= 2,165 meter
Waktu ganti gear + menumpahkan
= 2 menit
muatan+ maneuver Berat truck kosong
= 2,355 ton
Beban sumbu roda belakang
= 60%
Beban sumbu roda belakang
= 40%
Rimpul untuk percepatan
= ? kg/ton
Kapasitas DumpTtruck
= panjang x lebar x tinggi = 2,9 m x 1,945 m x 2,165 m = 12,21 m³
Rute pengupasan batu andesit Jarak
= 0,501 km
Berat truck kosong
= 2,355 ton = 2.355 kg
Berat isi
= Kapasitas truck x bobot isi tanah penutup = 12,21 m³ x 1,2728 ton/m³ x 0,8 = 12,43271 ton = 12432,71kg
Beban total
= berat truck kosong + berat isi = 2,355 ton + 12,43271ton = 14,78771 ton = 14787,71 kg
K-6
Rimpullyang tersedia pada setiap gear Dump Truck Hino D: Gear Kecepatan (km/h) Eff Mekanis (%)
HP
Rimpull (lb)
1
8,205
85
128,22
4.981
2
14,04
85
128,22
2.911
3
26,27
85
128,22
1.556
4
40,87
85
128,22
1.000
5
55,38
85
128,22
0.738
Usable rimpull (yang digunakan)
= beban total x distribusi beban x CT = 14787,71 kg x 60% x 60% = 5.323,5756 kg
Karena rimpull yang digunakan > rimpul yang tersedia yaitu 5.323,5756 kg >4.981 kg maka dump truck tidak mengalami selip. Waktu tempuh bermuatan pengangkutan lapisan tanah penutup Jalur A-B RP untuk RR
= 7 %x 14787,71kg
= 1.035,14kg
RP untuk GR
= 0% x 20 kg/ton x 29,8914ton
= 0 kg
RP untuk percepatan = 20 kg/ton x 29,8914ton
= 597,828 kg
RP yang dibutuhkan
= 1.632,968kg
Karena rimpull yang dibutuhkan 1.632,968 kg, maka digunakan gear 3 dengan kecepatan 26,27 km/jam Waktu yang di butuhkan
=
Jarak angkut kecepatan 0,501km
= 26,27 km/jam K-7
= 0,019 jam = 1,14 menit Waktu kembali kosong Jalur B-A RP untuk RR
= 7 % x 2.355 kg
RP untuk GR
= 0 % x 20 kg/ton x 2,355 ton= 0 kg
RP untuk percepatan = 20 kg/ton x 2,355 ton RP yang dibutuhkan
= 164,85 kg
= 47.1 kg = 211,95kg
Karena rimpull yang dibutuhkan211,95kg, maka digunakan gear 5 dengan kecepatan 55,38km/jam, karena kecepatan di area penambangan < 50 km/jam, maka di gunakan gearr 4 dengan kecepatan 40,87 km/jam. Waktu yang di butuhkan
=
Jarak angkut kecepatan 0,501 km
= 40,87 km/jam = 0,012 jam = 0,72 menit Waktu tetap Pengisian
= CT x banyak bucket = 20 detik/bucket x 11bucket = 220 detik = 3,67menit
Waktu ganti gear + Menumpahkan muatan + manuver = 2 menit
K-8
Waktu variable Waktu tempuh bermuatan
= 1,14 menit
Waktu tempuh kosong
= 0,72 menit
Cycle time dump truck
= waktu tetap + waktu variable = 3,67 menit + 1,86menit = 5,46 menit
Jumlah trip/jam
60 menit
= 5,46
menit
= 10,9 trip ≈ 11 trip Produksi Dump Truck /jam
= kapasitas truk x jumlah trip/jam x EU = 12,21 LCM/trip x 11 trip/jam truck x 0,80 = 107,448 LCM/jam
Tanah penutup yang harus diangkut = 1.593,216LCM/minggu = 37,93 LCM/jam Dump Truck di lapangan
=
batu gamping yang harus di angkut produksi 𝑑𝑢𝑚𝑝 𝑡𝑟𝑢𝑐𝑘/jam 37,93 LCM/jam
= 107,448
LCM/jam truck
= 0,35unit Dump Truck 1 unit Dump Truck Dump Truck disediakan
=
Jumlah 𝐷𝑢𝑚𝑝 𝑇𝑟𝑢𝑐𝑘 di lapangan MA 1
= 0,8 = 1,25 unit ≈ 2 unit Dump Truck Dump Truck cadangan
=DT disediakan – DT di lapangan K-9
=2-1 = 1 unit Dump Truck
Biaya Upah Operator : Jumlah Buldozer
: 1 unit
Waktu kerja
: 7 jam/hari
Hari kerja
: 6 hari
Upah Per Jam
: Rp. 13.666,-
Biaya
: Rp. 13.666,- x 7 x 1 x 6 : Rp. 573.972,-
Jumlah Backhoe
: 1 unit
Waktu kerja
: 7 jam/hari
Hari kerja
: 6 hari
Upah Per Jam
: Rp. 13.666,-
Biaya
: Rp. 13.666,- x 7 x 1 x 6 : Rp. 573.972,-
Jumlah Dump Truck
: 1 unit
Waktu kerja
: 7 jam/hari
Hari kerja
: 6 hari
Upah Per Jam
: Rp. 13.666,-
Biaya
: Rp. 13.666,- x 7 x 1 x 6 : Rp. 573.972,-
Total Biaya Upah
= Rp. 573.972+ Rp. 573.972+ Rp. 573.972 = Rp. 1.721.916,-
K - 10
Konsumsi bahan bakar : Jumlah Buldozer
: 1 unit
Waktu kerja
: 7 jam/hari
Hari kerja
: 6 hari
Konsumsi BBM
: 10 liter/jam
Harga bio solar
: Rp. 9.800,-
Biaya
: Rp. 9.800/liter x 10 x 7 x 1 x 6 : Rp. 4.116.000,-
Jumlah Excavator
: 1 unit
Waktu kerja
: 7 jam/hari
Hari kerja
: 6 hari
Konsumsi BBM
: 15 liter/jam
Harga bio solar
: Rp. 9.800,-
Biaya
: Rp. 9.800/liter x 15 x 7 x 1 x 6 hari : Rp. 6.174.000,-
Jumlah DT
: 1 unit
Waktu kerja
: 7 jam/hari
Hari kerja
: 6 hari
Konsumsi BBM
: 12 liter/jam
Harg Bio solar
: Rp. 9.800,-
Biaya
: Rp. 9.800/liter x 12 x 7 x 1 x 6 : Rp. 4.939.200,-
Total anggaran
: Rp. 4.116.000+ Rp. 6.174.000+ Rp. 4.939.200+ Rp. 1.721.916= Rp.16.951.116,-
Pengadaan bibit Tahap 1 (Safety bench1)
K - 11
Luas lahan yang ditanami pohon jati
: 910,41m2= 0,091 Ha
Dimensi penanaman jati yaitu 4m x 4m
= 16 m2
Dimensi penanaman tanaman rambat yaitu 4m x 4m = 16m2 Setiap 10.000 m2 dibutuhkan 10.000/16 = 625 pohon/Ha Jadi tanaman rambat yang dibutuhkan keseluruhan : = 625 tanaman x 0,091 Ha = 57 tanaman Harga bibit tanaman merambat
= Rp 5000/bibit
Jumlah bibit tanaman merambat = 57 tanaman Biaya pembibitan
= 57 x Rp. 5000 = Rp 285.000,-
Jadi pohon jati yang dibutuhkan keseluruhan : = 625 pohon x 0,091 Ha = 57 pohon Harga satu bibit pohon jati = Rp 2500/pohon
Jumlah bibit pohon jati
= 57 bibit
Biaya pembibitan
= 57 x Rp.2500 = Rp.142.500,-
Pemeliharaan Bibit Waktu pemeliharaan bibit
= 1 tahun
Biaya buruh untuk pemeliharaan bibit
= Rp. 1.717.238/bulan
Jumlah buruh yang bekerja
= 2 orang
Biaya pemeliharaan untuk 2 orang dalam satu bulan : = Rp. 1.717.238 x 2 orang = Rp.3.434.476,Total biaya pemeliharaan selama1 tahun (12 bulan) : = Rp.3.434.476 x 12 bulan = Rp. 41.213.712,
Pembelian pupuk dasar kompos Volume pot = 0,30 m x 0,30 m x 0,30 m
= 0,027 m3
Perbandingan tanah dengan pupuk kompos
=1:1
Volume pupuk kompos yang diperlukan dalam satu pot : = 0,027 m3 : 2
K - 12
= 0,0135 m3 Volume pupuk kompos yang diperlukan untuk seluruh pot : = 0,0135 m3 x 57 pot = 0,7695 m3 Berat jenis pupuk kompos
= 0,5 ton/m3
Berat pupuk kompos total yang diperlukan
= 0,5 ton/m3 x 0,7695m3 = 0,384755 ton
Harga pupuk kompos/karung (25 kg)
= Rp. 12.500,-
Harga pupuk kompos 1 ton
= Rp. 500.000,-
Jumlah pot
= 57 pot
Biaya pembelian pupuk kompos
= Rp. 500.000 x 0,384755 ton = Rp. 192.377,-
Biaya penanaman pohon jati Luas lahan yang direvegetasi
= 910,41 m2 = 0,091 Ha
Biaya penanaman pohon jati/Ha
=Rp 1.500.000
Biaya penanaman jati keseluruhan
= Rp 1.500.000 x 0,091 Ha = Rp 136.500,-
Pemeliharaan Pohon Jati Waktu pemeliharaan pohon jati
= 1 tahun
Biaya buruh untuk pemeliharaan jati
= Rp. 1.717.238/bulan
Jumlah buruh yang bekerja
= 2 orang
Biaya pemeliharaan untuk 2 orang dalam satu bulan : = Rp. 1.717.238 x 2 orang = Rp.3.434.476,Total biaya pemeliharaan selama1 tahun (12 bulan) : = Rp.3.434.476x 12 bulan = Rp. 41.213.712,-
K - 13
3. Tahun 2022 Volume Soil = 106.375LCM
Biaya Pengangkutan Material Luas lahan yang direvegetasi = 6667,42 m2 Volume material OB
= 6667,42 m2 x 1,25 m = 8334,275m3 / 0,8 = 10417,84375 LCM
Volume material Top Soil
= 6667,42 m2x 0,75 m = 5000,565 m3 = 5000,565 m3 / 0,8 = 6250,70625 LCM
Total Volume
= Volume OB + Volume Top Soil = 10417,84375 LCM + 6250,70625LCM = 16668,55 LCM
Kebutuhan pengangkutan : Volume material
= 16668,55 LCM/ 1 bulan = 694,523 LCM/ 7 jam = 99,2176 LCM/jam
Bulldozer Kapasitas blade bulldozer
= Lebar x (tinggi blade)2 = 2,18 m x 0,585 m2 = 1,275 m3
Tanah yang terisi
= kapasitas blade / factor blade = 1,275 m3 /1 = 1,275 LCM
Jam kerja efektif
= 60 menit x EU = 60 menit x 0,8 K - 14
= 48 menit Effisiensi kerja terhadap alat
= Jam kerja efektif x MA = 48 menit x 0,96 = 46,08 menit
Untuk blade capacity
= 2,3625 m³
Kecepatan maju
= 58 meter/menit
Kecepatan mundur
= 91,67 meter/menit
Waktu mendorong maju
=(jarak dorong)/(kecepatan maju x konversi) = (10 meter)/(58 meter/menit ) = 0,17 menit
Waktu untuk mundur
= (jarak dorong)/(kecepatan mundur x konversi) = (10 meter)/(91,67 meter/menit) = 0,109 menit
Cycle time bulldozer
= waktu maju + waktu ganti porsnelling& gear + waktu mundur = (0,17 + 0,5 + 0,109) menit = 0,779 menit
Jumlah trip/ jam
= (jam kerja efektif)/(cycle time) = (48 menit) / (1,67 menit) = 28,74 trip = 29 trip
Produksi bulldozer/jam
= jumlah trip x kapasitas blade K - 15
= 29 trip/ jam x 1,275LCM = 36,975 LCM/ jam Bulldozer yang bekerja dilapangan = (Volume tanah penutup/minggu)/(produksi per minggu) = (99,2176LCM/jam)/(36,975 LCM/jam) = 2,68 bulldozer = 3 bulldozer Bulldozer disediakan
= (Jumlah bulldozer di lapangan)/MA = 3/0,96 = 3,125 ≈ 4 unit bulldozer
Bulldozer cadangan
= bulldozer disediakan – bulldozer di lapangan =4–3 = 1 bulldozer
Backhoe Model Backhoe
= Komatsu PC200-6
Ukuran bucket
= 1,2 m3
Cycle Time
= 22 detik/bucket
Fill factor bucket tanah penutup
= 0,7
Tinggi Jenjang
= 8 meter
EU
= 85 %
MA
= 80 %
Kapasitas Dump Truck
= 222,5 m3
Banyak bucket
= (kapasitas Dump truck)/(kapasitas bucket) K - 16
= (22,5 m3)/(1,2 m3 ) = 18,75 bucket ≈ 19 bucket Waktu pengisin Dump Truck
= banyak bucket x cycle time = 19 bucket x 22 detik/bucket = 418 detik = 6,97 menit
Produksi backhoe untuk pengupasan tanah penutup : Produksi/jam
= 3600/CT x (bucket capacity x bucket fill factor ) x EU = (3600/22 detik) x (1,2 m³ x 0,7) x 0,85 = 116,8364 LCM/jam
Backhoe di lapangan
=
(Volume
lapisan
tanah
penutup/jam)/(Produksi Backhoe/jam) = (99,2176 LCM/jam)/( 116,8364 LCM/jam) = 0,85 unit backhoe Backhoe disediakan
1 unit backhoe
= (Jumlah backhoe di lapangan)/MA = 1/0,8 = 1,25 ≈ 2 unit Backhoe
Backhoe cadangan
= Backhoe disediakan – Backhoe di
lapangan =2–1
K - 17
= 1 unit Backhoe Dump truck Model
= Dump Truck HinoFM 260 JD
Jarak angkut untuk tanah penutup
= 0,341 km
Power
= 256 HP
Efisiensi mesin
= 85%
Ukuran bakPanjang
= 6,0 meter
Lebar
= 2,5 meter
Tinggi
= 1,5 meter
Waktu ganti gear + menumpahkan muatan+ maneuver
= 2,5 menit
Berat truck kosong
= 6,981 ton
Beban sumbu roda belakang
= 60%
Beban sumbu roda belakang
= 40%
Rimpul untuk percepatan
= 40,48 kg/ton
Kapasitas DumpTtruck
= panjang x lebar x tinggi = 6,35 m x 2,5 m x 1,5 m = 22,5 m³
Rute pengupasan batu gamping Jarak
= 0,501 km
K - 18
Berat truck kosong
= 6,981 ton = 6.981 kg
Berat isi
= Kapasitas truck x bobot isi x tanah penutup = 22,5 m³ x 1,2728 ton/m³ x 0,8 = 22,9104 ton = 22910,4 kg
Beban total
= berat truck kosong + berat isi = 6,981 ton + 22,9104 ton = 29,8914 ton = 29891,4 kg
Rimpullyang tersedia pada setiap gear Dump Truck Hino FM 260 JD : Gear Kecepatan (km/h) Eff Mekanis (%)
HP
Rimpull (lb)
1
9,02
85
256
9.046,56
2
12,44
85
256
6.559,48
3
17,33
85
256
4.708,60
4
23,93
85
256
3.409,95
5
32,80
85
256
2.487,80
6
45,24
85
256
1.803,71
7
63,04
85
256
1.294,42
8
87
85
256
937,93
Usable rimpull (yang digunakan)
= beban total x distribusi beban x CT = 29891,4 kg x 60% x 60%
K - 19
= 10760,904 kg Karena rimpull yang digunakan > rimpul yang tersedia yaitu 10760,904 kg >9.046,56 kg maka dump truck tidak mengalami selip. Waktu tempuh bermuatan pengangkutan lapisan tanah penutup Jalur A-B RP untuk RR
= 7 %x 29891,4 kg
= 2092,398 kg
RP untuk GR
= 0% x 20 kg/ton x 29,8914ton
= 0 kg
RP untuk percepatan = 20 kg/ton x 29,8914ton
= 597,828 kg
RP yang dibutuhkan
= 2690,226 kg
Karena rimpull yang dibutuhkan 2690,226 kg, maka digunakan gear 5 dengan kecepatan 32,80 km/jam Waktu yang di butuhkan
=
Jarak angkut kecepatan 0,501 km
= 32,80 km/jam = 0,015 jam = 0,9 menit Waktu kembali kosong Jalur B-A RP untuk RR
= 7 % x 6.981 kg
RP untuk GR
= 0 % x 20 kg/ton x 6,981 ton= 0 kg
RP untuk percepatan = 20 kg/ton x 6,981 ton RP yang dibutuhkan
= 488,67 kg
= 139,62 kg = 628,29kg
K - 20
Karena rimpull yang dibutuhkan 628,29 kg, maka digunakan gear 7 dengan kecepatan 87 km/jam, karena kecepatan di area penambangan < 50 km/jam, maka di gunakan gearr 6 dengan kecepatan 45,24 km/jam.
Waktu yang di butuhkan
=
Jarak angkut kecepatan 0,501 km
= 45,24 km/jam = 0,011 jam = 0,66 menit Waktu tetap Pengisian
= CT x banyak bucket = 22 detik/bucket x 11bucket = 242 detik = 4,03menit
Waktu ganti gear + Menumpahkan muatan + manuver = 2,5 menit Waktu variable Waktu tempuh bermuatan
= 0,9 menit
Waktu tempuh kosong
= 0,66 menit
Cycle time dump truck
= waktu tetap + waktu variable = 4,03 menit + 1,56menit = 5,59 menit
Jumlah trip/jam
60 menit
= 5,59
menit
= 10,7 trip ≈ 11 trip
K - 21
Produksi Dump Truck /jam
= kapasitas truk x jumlah trip/jam x EU = 22,5 LCM/trip x 11 trip/jam truck x 0,85 = 210,375 LCM/jam
Tanah penutup yang harus diangkut = 4162,0572LCM/minggu = 99,0966 LCM/jam Dump Truck di lapangan
=
batu gamping yang harus di angkut produksi 𝑑𝑢𝑚𝑝 𝑡𝑟𝑢𝑐𝑘/jam 99,0966 LCM/jam
= 210,375 LCM/jam truck = 0,47unit Dump Truck 1 unit Dump Truck Dump Truck disediakan
=
Jumlah 𝐷𝑢𝑚𝑝 𝑇𝑟𝑢𝑐𝑘 di lapangan MA 1
= 0,8 = 1,25 unit ≈ 2 unit Dump Truck Dump Truck cadangan
=DT disediakan – DT di lapangan =2-1 = 1 unit Dump Truck
Biaya Upah Operator : Jumlah Buldozer
: 1 unit
Waktu kerja
: 7 jam/hari K - 22
Hari kerja
: 24 hari (1 Bulan)
Upar Per Jam
: Rp. 13.666,-
Biaya
: Rp. 13.666,- x 7 x 1 x 24 : Rp. 2.295.888,-
Jumlah Backhoe
: 1 unit
Waktu kerja
: 7 jam/hari
Hari kerja
: 24 hari (1 Bulan)
Upar Per Jam
: Rp. 13.666,-
Biaya
: Rp. 13.666,- x 7 x 1 x 24 : Rp. 2.295.888,-
Jumlah Dump Truck
: 1 unit
Waktu kerja
: 7 jam/hari
Hari kerja
: 24 hari (1 Bulan)
Upar Per Jam
: Rp. 13.666,-
Biaya
: Rp. 13.666,- x 7 x 1 x 24 : Rp. 2.295.888,-
Total Biaya
= Rp. 2.295.888+ Rp. 2.295.888+ Rp. 2.295.888 = Rp. 6.887.664,-
Konsumsi bahan bakar : Jumlah Buldozer
: 1 unit
Waktu kerja
: 7 jam/hari
Hari kerja
: 6 hari
Konsumsi BBM
: 10 liter/jam
Harga bio solar
: Rp. 9.800,-
Biaya
: Rp. 9.800/liter x 10 x 7 x 1 x 6 : Rp. 4.116.000,-
K - 23
Jumlah Excavator
: 1 unit
Waktu kerja
: 7 jam/hari
Hari kerja
: 6 hari
Konsumsi BBM
: 15 liter/jam
Harga solar
: Rp. 9.800,-
Biaya
: Rp. 9.800/liter x 15 x 7 x 1 x 6 hari : Rp. 6.174.000,-
Jumlah DT
: 1 unit
Waktu kerja
: 7 jam/hari
Hari kerja
: 6 hari
Konsumsi BBM
: 12 liter/jam
Harga solar
: Rp. 9.800,-
Biaya
: Rp. 9.800/liter x 12 x 7 x 1 x 6 : Rp. 4.939.200,-
Total anggaran
:Rp. 4.116.000+ Rp. 6.174.000+ Rp. 4.939.200+ Rp. 6.887.664= Rp.22.116.864,-
LAMPIRAN K.2 PERHITUNGAN PASCATAMBANG REVEGETASI LAHAN 1. Tahun 2023
K - 24
Biaya Pengangkutan Material Luas lahan yang direvegetasi = 17.089,58m2 Volume material OB
= 17.089,58m2 x 1,25 m = 21.361,975m3 / 0,8 = 26.702,4687LCM
Volume material Top Soil
= 17.089,58m2x 0,75 m = 12.817,185 m3/ 0,8 = 16.021,4812 LCM
Total Volume
= Volume OB + Volume Top Soil =26.702,4687 LCM + 16.021,4812 LCM = 42.723,9499 LCM
Kebutuhan pengangkutan : Volume material
= 42.723,9499 LCM / 288 hari = 148,347LCM/ hari = 21,192 LCM/jam
Bulldozer Merk : Komatsu D20P-3 Kapasitas blade bulldozer
= lebar x (tinggi blade)2 = 2,18 m x 0,585 m2 = 1,275 m3
Tanah yang terisi
= kapasitas blade / factor blade = 1,275 m3 / 1 = 1,275 LCM
Jam kerja efektif
= 60 menit x EU = 60 menit x 0,8 = 48 menit
Effisiensi kerja terhadap alat
= Jam kerja efektif x MA K - 25
= 48 menit x 0,8 = 38,4 menit Untuk blade capacity
= 1,275 m³
Kecepatan maju
= 58 meter/menit
Kecepatan mundur
= 91,67 meter/menit
Waktu mendorong maju
= (jarak dorong) / (kecepatan maju x konversi) = (10 meter) / ( 58 meter/menit ) = 0,17 menit
Waktu untuk mundur
= (jarak dorong)/(kecepatan mundur x konversi) = (10 meter)/( 91,67 meter/menit) = 0,109 menit
Cycle time bulldozer
= waktu maju + waktu ganti porsnelling & gear + waktu mundur = (0,17 + 0,5 + 0,109) menit = 0,779 menit
Jumlah trip/ jam
= (jam kerja efektif) / (cycle time) = (48 menit) / (1,67 menit) = 28,74 trip = 29 trip
Produksi bulldozer/jam
= jumlah trip x kapasitas blade = 29 trip/ jam x 1,275LCM
K - 26
= 36,975 LCM/ jam Bulldozer yang bekerja dilapangan = (Volume tanah penutup/minggu)/(produksi per minggu) = (21,192 LCM/jam)/(36,975 LCM/jam) = 0,57 bulldozer = 1 bulldozer Bulldozer disediakan
= (Jumlah bulldozer di lapangan)/MA = 1/0,8 = 1,25 ≈ 2 unit bulldozer
Bulldozer cadangan
= bulldozer disediakan – bulldozer di lapangan =2–1 = 1 bulldozer
Backhoe Model : Komatsu PC130-8 Ukuran bucket
= 0,5 m3
Cycle Time
= 20 detik/bucket
Fill factor bucket tanah penutup
= 0,7
Swell factor tanah
= 0,8
Tinggi Jenjang
= 8 meter
EU
= 80 %
MA
= 80 %
Kapasitas Dump Truck
= 12,21 m3
Banyak bucket
= (kapasitas Dump truck)/(kapasitas bucket) K - 27
= (12,21 m3)/(0,5 m3 ) = 24,42 bucket ≈ 24 bucket Waktu pengisin Dump Truck
= banyak bucket x cycle time = 24 bucket x 20 detik/bucket = 480 detik = 8 menit
Produksi backhoe untuk pengupasan tanah penutup : Produksi/jam
= 3600/CT x (bucket capacity x bucket fill factor ) x EU = (3600/20 detik) x (0,5 m³ x 0,7) x 0,8 = 50,4 LCM/jam
Backhoe di lapangan
=
(Volume
lapisan
tanah
penutup/jam)/(Produksi Backhoe/jam) = (21,192 LCM/jam)/( 50,4 LCM/jam) = 0,42 unit backhoe = 1 unit backhoe Backhoe disediakan
= (Jumlah backhoe di lapangan)/MA = 1/0,8 = 1,25 ≈ 2 unit Backhoe
Backhoe cadangan
= Backhoe disediakan – Backhoe di lapangan =2–1 = 1 unit Backhoe
K - 28
Dump truck Model
= Dump Dutro 130HD
Jarak angkut untuk tanah penutup
= 0,501 km
Power
= 128,22 HP
Efisiensi mesin
= 85%
Ukuran bakPanjang
= 2,9 meter
Lebar
= 1,945 meter
Tinggi
= 2,165 meter
Waktu ganti gear + menumpahkan
= 2 menit
muatan+ maneuver Berat truck kosong
= 2,355 ton
Beban sumbu roda belakang
= 60%
Beban sumbu roda belakang
= 40%
Rimpul untuk percepatan
= ? kg/ton
Kapasitas DumpTtruck
= panjang x lebar x tinggi = 2,9 m x 1,945 m x 2,165 m = 12,21 m³
Rute pengupasan batu andesit Jarak
= 0,501 km
Berat truck kosong
= 2,355 ton = 2.355 kg
Berat isi
= Kapasitas truck x bobot isi tanah penutup = 12,21 m³ x 1,2728 ton/m³ x 0,8 K - 29
= 12,43271 ton = 12432,71kg Beban total
= berat truck kosong + berat isi = 2,355 ton + 12,43271ton = 14,78771 ton = 14787,71 kg
Rimpullyang tersedia pada setiap gear Dump Truck Hino D: Gear Kecepatan (km/h) Eff Mekanis (%)
HP
Rimpull (lb)
1
8,205
85
128,22
4.981
2
14,04
85
128,22
2.911
3
26,27
85
128,22
1.556
4
40,87
85
128,22
1.000
5
55,38
85
128,22
0.738
Usable rimpull (yang digunakan)
= beban total x distribusi beban x CT = 14787,71 kg x 60% x 60% = 5.323,5756 kg
Karena rimpull yang digunakan > rimpul yang tersedia yaitu 5.323,5756 kg >4.981 kg maka dump truck tidak mengalami selip. Waktu tempuh bermuatan pengangkutan lapisan tanah penutup Jalur A-B RP untuk RR
= 7 %x 14787,71kg
= 1.035,14kg
RP untuk GR
= 0% x 20 kg/ton x 29,8914ton
= 0 kg
RP untuk percepatan = 20 kg/ton x 29,8914ton
= 597,828 kg
K - 30
RP yang dibutuhkan
= 1.632,968kg
Karena rimpull yang dibutuhkan 1.632,968 kg, maka digunakan gear 3 dengan kecepatan 26,27 km/jam Waktu yang di butuhkan
=
Jarak angkut kecepatan 0,501km
= 26,27 km/jam = 0,019 jam = 1,14 menit Waktu kembali kosong Jalur B-A RP untuk RR
= 7 % x 2.355 kg
RP untuk GR
= 0 % x 20 kg/ton x 2,355 ton= 0 kg
RP untuk percepatan = 20 kg/ton x 2,355 ton RP yang dibutuhkan
= 164,85 kg
= 47.1 kg = 211,95kg
Karena rimpull yang dibutuhkan211,95kg, maka digunakan gear 5 dengan kecepatan 55,38km/jam, karena kecepatan di area penambangan < 50 km/jam, maka di gunakan gearr 4 dengan kecepatan 40,87 km/jam. Waktu yang di butuhkan
=
Jarak angkut kecepatan 0,501 km
= 40,87 km/jam = 0,012 jam = 0,72 menit Waktu tetap Pengisian
= CT x banyak bucket
K - 31
= 20 detik/bucket x 11bucket = 220 detik = 3,67menit Waktu ganti gear + Menumpahkan muatan + manuver = 2 menit Waktu variable Waktu tempuh bermuatan
= 1,14 menit
Waktu tempuh kosong
= 0,72 menit
Cycle time dump truck
= waktu tetap + waktu variable = 3,67 menit + 1,86menit = 5,46 menit
Jumlah trip/jam
60 menit
= 5,46
menit
= 10,9 trip ≈ 11 trip Produksi Dump Truck /jam
= kapasitas truk x jumlah trip/jam x EU = 12,21 LCM/trip x 11 trip/jam truck x 0,80 = 107,448 LCM/jam
Tanah penutup yang harus diangkut = 1.593,216LCM/minggu = 37,93 LCM/jam Dump Truck di lapangan
= =
batu gamping yang harus di angkut produksi 𝑑𝑢𝑚𝑝 𝑡𝑟𝑢𝑐𝑘/jam 37,93 LCM/jam 107,448 LCM/jam truck
= 0,35unit Dump Truck 1 unit Dump Truck
K - 32
Dump Truck disediakan
=
Jumlah 𝐷𝑢𝑚𝑝 𝑇𝑟𝑢𝑐𝑘 di lapangan MA 1
= 0,8 = 1,25 unit ≈ 2 unit Dump Truck Dump Truck cadangan
=DT disediakan – DT di lapangan =2-1 = 1 unit Dump Truck
K - 33