LAMPIRAN K.1 PERHITUNGAN REKLAMASI REVEGETASI LAHAN 

Volume OB & Top Soil yang tersedia Volume Soil = 202437,5 LCM

1. Tahun 2019 

Volume OB & Top Soil yang tersedia Volume Soil = 202.437,5 LCM

2. Tahun 2019 

Biaya Pengangkutan Material Luas lahan yang direvegetasi = 910,41 m2 Volume material OB

= 910,41 m2 x 1,25 m = 1.138,0125 m3 = Volume OB / Swell Factor = 1.138,0125 m3 / 0,8 = 1.422,516 LCM

Volume material Top Soil

= 910,41 m2 x 0,75 m = 682,8075 m3 = Volume Top Soil / Swell Factor = 682,8075 m3 / 0,8 = 853,509 LCM

Total Volume

= Volume OB + Volume Top Soil = 1.422,516 LCM + 853,509 LCM = 2.276,025 LCM



Kebutuhan pengangkutan : Volume material

= 2.276,025 LCM / 6 hari = 379,3375 LCM/ 7 jam = 54,19 LCM/jam

K-1

Bulldozer Merk : Komatsu D20P-3 Kapasitas blade bulldozer

= lebar x (tinggi blade)2 = 2,18 m x 0,585 m2 = 1,275 m3

Tanah yang terisi

= kapasitas blade / factor blade = 1,275 m3 / 1 = 1,275 LCM

Jam kerja efektif

= 60 menit x EU = 60 menit x 0,8 = 48 menit

Effisiensi kerja terhadap alat = Jam kerja efektif x MA = 48 menit x 0,8 = 38,4 menit Untuk blade capacity

= 1,275 m³

Kecepatan maju

= 58 meter/menit

Kecepatan mundur

= 91,67 meter/menit

Waktu mendorong maju

= (jarak dorong) / (kecepatan maju x konversi) = (10 meter) / ( 58 meter/menit ) = 0,17 menit

Waktu untuk mundur

= (jarak dorong)/(kecepatan mundur x konversi) K-2

= (10 meter)/( 91,67 meter/menit) = 0,109 menit Cycle time bulldozer

= waktu maju + waktu ganti porsnelling & gear + waktu mundur = (0,17 + 0,5 + 0,109) menit = 0,779 menit

Jumlah trip/ jam

= (jam kerja efektif) / (cycle time) = (48 menit) / (1,67 menit) = 28,74 trip = 29 trip

Produksi bulldozer/jam

= jumlah trip x kapasitas blade = 29 trip/ jam x 1,275LCM = 36,975 LCM/ jam

Bulldozer yang bekerja dilapangan = (Volume tanah penutup/minggu)/(produksi per minggu) = (54,19LCM/jam)/(36,975 LCM/jam) = 1,46 bulldozer = 2 bulldozer Bulldozer disediakan

= (Jumlah bulldozer di lapangan)/MA = 2/0,8 = 2,5 ≈ 3 unit bulldozer

Bulldozer cadangan

= bulldozer disediakan – bulldozer di lapangan

K-3

=3–2 = 1 bulldozer Backhoe Model : Komatsu PC130-8 Ukuran bucket

= 0,5 m3

Cycle Time

= 20 detik/bucket

Fill factor bucket tanah penutup

= 0,7

Swell factor tanah

= 0,8

Tinggi Jenjang

= 8 meter

EU

= 80 %

MA

= 80 %

Kapasitas Dump Truck

= 12,21 m3

Banyak bucket

= (kapasitas Dump truck)/(kapasitas bucket) = (12,21 m3)/(0,5 m3 ) = 24,42 bucket ≈ 24 bucket

Waktu pengisin Dump Truck

= banyak bucket x cycle time = 24 bucket x 20 detik/bucket = 480 detik = 8 menit

K-4

Produksi backhoe untuk pengupasan tanah penutup : Produksi/jam

= 3600/CT x (bucket capacity x bucket fill factor ) x EU = (3600/20 detik) x (0,5 m³ x 0,7) x 0,8 = 50,4 LCM/jam

Backhoe di lapangan

=

(Volume

lapisan

tanah

penutup/jam)/(Produksi Backhoe/jam) = (54,19 LCM/jam)/( 50,4 LCM/jam) = 1,075 unit backhoe = 1 unit backhoe Backhoe disediakan

= (Jumlah backhoe di lapangan)/MA = 1/0,8 = 1,25 ≈ 2 unit Backhoe

Backhoe cadangan

= Backhoe disediakan – Backhoe di lapangan =2–1 = 1 unit Backhoe

Dump truck Model

= Dump Dutro 130HD

Jarak angkut untuk tanah penutup

= 0,501 km

Power

= 128,22 HP

Efisiensi mesin

= 85%

Ukuran bakPanjang

= 2,9 meter K-5

Lebar

= 1,945 meter

Tinggi

= 2,165 meter

Waktu ganti gear + menumpahkan

= 2 menit

muatan+ maneuver Berat truck kosong

= 2,355 ton

Beban sumbu roda belakang

= 60%

Beban sumbu roda belakang

= 40%

Rimpul untuk percepatan

= ? kg/ton

Kapasitas DumpTtruck

= panjang x lebar x tinggi = 2,9 m x 1,945 m x 2,165 m = 12,21 m³

Rute pengupasan batu andesit Jarak

= 0,501 km

Berat truck kosong

= 2,355 ton = 2.355 kg

Berat isi

= Kapasitas truck x bobot isi tanah penutup = 12,21 m³ x 1,2728 ton/m³ x 0,8 = 12,43271 ton = 12432,71kg

Beban total

= berat truck kosong + berat isi = 2,355 ton + 12,43271ton = 14,78771 ton = 14787,71 kg

K-6

Rimpullyang tersedia pada setiap gear Dump Truck Hino D: Gear Kecepatan (km/h) Eff Mekanis (%)

HP

Rimpull (lb)

1

8,205

85

128,22

4.981

2

14,04

85

128,22

2.911

3

26,27

85

128,22

1.556

4

40,87

85

128,22

1.000

5

55,38

85

128,22

0.738

Usable rimpull (yang digunakan)

= beban total x distribusi beban x CT = 14787,71 kg x 60% x 60% = 5.323,5756 kg

Karena rimpull yang digunakan > rimpul yang tersedia yaitu 5.323,5756 kg >4.981 kg maka dump truck tidak mengalami selip. Waktu tempuh bermuatan pengangkutan lapisan tanah penutup Jalur A-B RP untuk RR

= 7 %x 14787,71kg

= 1.035,14kg

RP untuk GR

= 0% x 20 kg/ton x 29,8914ton

= 0 kg

RP untuk percepatan = 20 kg/ton x 29,8914ton

= 597,828 kg

RP yang dibutuhkan

= 1.632,968kg

Karena rimpull yang dibutuhkan 1.632,968 kg, maka digunakan gear 3 dengan kecepatan 26,27 km/jam Waktu yang di butuhkan

=

Jarak angkut kecepatan 0,501km

= 26,27 km/jam K-7

= 0,019 jam = 1,14 menit Waktu kembali kosong Jalur B-A RP untuk RR

= 7 % x 2.355 kg

RP untuk GR

= 0 % x 20 kg/ton x 2,355 ton= 0 kg

RP untuk percepatan = 20 kg/ton x 2,355 ton RP yang dibutuhkan

= 164,85 kg

= 47.1 kg = 211,95kg

Karena rimpull yang dibutuhkan211,95kg, maka digunakan gear 5 dengan kecepatan 55,38km/jam, karena kecepatan di area penambangan < 50 km/jam, maka di gunakan gearr 4 dengan kecepatan 40,87 km/jam. Waktu yang di butuhkan

=

Jarak angkut kecepatan 0,501 km

= 40,87 km/jam = 0,012 jam = 0,72 menit Waktu tetap Pengisian

= CT x banyak bucket = 20 detik/bucket x 11bucket = 220 detik = 3,67menit

Waktu ganti gear + Menumpahkan muatan + manuver = 2 menit

K-8

Waktu variable Waktu tempuh bermuatan

= 1,14 menit

Waktu tempuh kosong

= 0,72 menit

Cycle time dump truck

= waktu tetap + waktu variable = 3,67 menit + 1,86menit = 5,46 menit

Jumlah trip/jam

60 menit

= 5,46

menit

= 10,9 trip ≈ 11 trip Produksi Dump Truck /jam

= kapasitas truk x jumlah trip/jam x EU = 12,21 LCM/trip x 11 trip/jam truck x 0,80 = 107,448 LCM/jam

Tanah penutup yang harus diangkut = 1.593,216LCM/minggu = 37,93 LCM/jam Dump Truck di lapangan

=

batu gamping yang harus di angkut produksi 𝑑𝑢𝑚𝑝 𝑡𝑟𝑢𝑐𝑘/jam 37,93 LCM/jam

= 107,448

LCM/jam truck

= 0,35unit Dump Truck 1 unit Dump Truck Dump Truck disediakan

=

Jumlah 𝐷𝑢𝑚𝑝 𝑇𝑟𝑢𝑐𝑘 di lapangan MA 1

= 0,8 = 1,25 unit ≈ 2 unit Dump Truck Dump Truck cadangan

=DT disediakan – DT di lapangan K-9

=2-1 = 1 unit Dump Truck

Biaya Upah Operator : Jumlah Buldozer

: 1 unit

Waktu kerja

: 7 jam/hari

Hari kerja

: 6 hari

Upah Per Jam

: Rp. 13.666,-

Biaya

: Rp. 13.666,- x 7 x 1 x 6 : Rp. 573.972,-

Jumlah Backhoe

: 1 unit

Waktu kerja

: 7 jam/hari

Hari kerja

: 6 hari

Upah Per Jam

: Rp. 13.666,-

Biaya

: Rp. 13.666,- x 7 x 1 x 6 : Rp. 573.972,-

Jumlah Dump Truck

: 1 unit

Waktu kerja

: 7 jam/hari

Hari kerja

: 6 hari

Upah Per Jam

: Rp. 13.666,-

Biaya

: Rp. 13.666,- x 7 x 1 x 6 : Rp. 573.972,-

Total Biaya Upah

= Rp. 573.972+ Rp. 573.972+ Rp. 573.972 = Rp. 1.721.916,-

K - 10

Konsumsi bahan bakar : Jumlah Buldozer

: 1 unit

Waktu kerja

: 7 jam/hari

Hari kerja

: 6 hari

Konsumsi BBM

: 10 liter/jam

Harga bio solar

: Rp. 9.800,-

Biaya

: Rp. 9.800/liter x 10 x 7 x 1 x 6 : Rp. 4.116.000,-

Jumlah Excavator

: 1 unit

Waktu kerja

: 7 jam/hari

Hari kerja

: 6 hari

Konsumsi BBM

: 15 liter/jam

Harga bio solar

: Rp. 9.800,-

Biaya

: Rp. 9.800/liter x 15 x 7 x 1 x 6 hari : Rp. 6.174.000,-

Jumlah DT

: 1 unit

Waktu kerja

: 7 jam/hari

Hari kerja

: 6 hari

Konsumsi BBM

: 12 liter/jam

Harg Bio solar

: Rp. 9.800,-

Biaya

: Rp. 9.800/liter x 12 x 7 x 1 x 6 : Rp. 4.939.200,-

Total anggaran

: Rp. 4.116.000+ Rp. 6.174.000+ Rp. 4.939.200+ Rp. 1.721.916= Rp.16.951.116,-



Pengadaan bibit Tahap 1 (Safety bench1)

K - 11

Luas lahan yang ditanami pohon jati

: 910,41m2= 0,091 Ha

Dimensi penanaman jati yaitu 4m x 4m

= 16 m2

Dimensi penanaman tanaman rambat yaitu 4m x 4m = 16m2 Setiap 10.000 m2 dibutuhkan 10.000/16 = 625 pohon/Ha Jadi tanaman rambat yang dibutuhkan keseluruhan : = 625 tanaman x 0,091 Ha = 57 tanaman Harga bibit tanaman merambat

= Rp 5000/bibit

Jumlah bibit tanaman merambat = 57 tanaman Biaya pembibitan

= 57 x Rp. 5000 = Rp 285.000,-

Jadi pohon jati yang dibutuhkan keseluruhan : = 625 pohon x 0,091 Ha = 57 pohon Harga satu bibit pohon jati = Rp 2500/pohon



Jumlah bibit pohon jati

= 57 bibit

Biaya pembibitan

= 57 x Rp.2500 = Rp.142.500,-

Pemeliharaan Bibit Waktu pemeliharaan bibit

= 1 tahun

Biaya buruh untuk pemeliharaan bibit

= Rp. 1.717.238/bulan

Jumlah buruh yang bekerja

= 2 orang

Biaya pemeliharaan untuk 2 orang dalam satu bulan : = Rp. 1.717.238 x 2 orang = Rp.3.434.476,Total biaya pemeliharaan selama1 tahun (12 bulan) : = Rp.3.434.476 x 12 bulan = Rp. 41.213.712,

Pembelian pupuk dasar kompos Volume pot = 0,30 m x 0,30 m x 0,30 m

= 0,027 m3

Perbandingan tanah dengan pupuk kompos

=1:1

Volume pupuk kompos yang diperlukan dalam satu pot : = 0,027 m3 : 2

K - 12

= 0,0135 m3 Volume pupuk kompos yang diperlukan untuk seluruh pot : = 0,0135 m3 x 57 pot = 0,7695 m3 Berat jenis pupuk kompos

= 0,5 ton/m3

Berat pupuk kompos total yang diperlukan

= 0,5 ton/m3 x 0,7695m3 = 0,384755 ton

Harga pupuk kompos/karung (25 kg)

= Rp. 12.500,-

Harga pupuk kompos 1 ton

= Rp. 500.000,-

Jumlah pot

= 57 pot

Biaya pembelian pupuk kompos

= Rp. 500.000 x 0,384755 ton = Rp. 192.377,-



Biaya penanaman pohon jati Luas lahan yang direvegetasi

= 910,41 m2 = 0,091 Ha

Biaya penanaman pohon jati/Ha

=Rp 1.500.000

Biaya penanaman jati keseluruhan

= Rp 1.500.000 x 0,091 Ha = Rp 136.500,-



Pemeliharaan Pohon Jati Waktu pemeliharaan pohon jati

= 1 tahun

Biaya buruh untuk pemeliharaan jati

= Rp. 1.717.238/bulan

Jumlah buruh yang bekerja

= 2 orang

Biaya pemeliharaan untuk 2 orang dalam satu bulan : = Rp. 1.717.238 x 2 orang = Rp.3.434.476,Total biaya pemeliharaan selama1 tahun (12 bulan) : = Rp.3.434.476x 12 bulan = Rp. 41.213.712,-

K - 13

3. Tahun 2022 Volume Soil = 106.375LCM 

Biaya Pengangkutan Material Luas lahan yang direvegetasi = 6667,42 m2 Volume material OB

= 6667,42 m2 x 1,25 m = 8334,275m3 / 0,8 = 10417,84375 LCM

Volume material Top Soil

= 6667,42 m2x 0,75 m = 5000,565 m3 = 5000,565 m3 / 0,8 = 6250,70625 LCM

Total Volume

= Volume OB + Volume Top Soil = 10417,84375 LCM + 6250,70625LCM = 16668,55 LCM



Kebutuhan pengangkutan : Volume material

= 16668,55 LCM/ 1 bulan = 694,523 LCM/ 7 jam = 99,2176 LCM/jam

Bulldozer Kapasitas blade bulldozer

= Lebar x (tinggi blade)2 = 2,18 m x 0,585 m2 = 1,275 m3

Tanah yang terisi

= kapasitas blade / factor blade = 1,275 m3 /1 = 1,275 LCM

Jam kerja efektif

= 60 menit x EU = 60 menit x 0,8 K - 14

= 48 menit Effisiensi kerja terhadap alat

= Jam kerja efektif x MA = 48 menit x 0,96 = 46,08 menit

Untuk blade capacity

= 2,3625 m³

Kecepatan maju

= 58 meter/menit

Kecepatan mundur

= 91,67 meter/menit

Waktu mendorong maju

=(jarak dorong)/(kecepatan maju x konversi) = (10 meter)/(58 meter/menit ) = 0,17 menit

Waktu untuk mundur

= (jarak dorong)/(kecepatan mundur x konversi) = (10 meter)/(91,67 meter/menit) = 0,109 menit

Cycle time bulldozer

= waktu maju + waktu ganti porsnelling& gear + waktu mundur = (0,17 + 0,5 + 0,109) menit = 0,779 menit

Jumlah trip/ jam

= (jam kerja efektif)/(cycle time) = (48 menit) / (1,67 menit) = 28,74 trip = 29 trip

Produksi bulldozer/jam

= jumlah trip x kapasitas blade K - 15

= 29 trip/ jam x 1,275LCM = 36,975 LCM/ jam Bulldozer yang bekerja dilapangan = (Volume tanah penutup/minggu)/(produksi per minggu) = (99,2176LCM/jam)/(36,975 LCM/jam) = 2,68 bulldozer = 3 bulldozer Bulldozer disediakan

= (Jumlah bulldozer di lapangan)/MA = 3/0,96 = 3,125 ≈ 4 unit bulldozer

Bulldozer cadangan

= bulldozer disediakan – bulldozer di lapangan =4–3 = 1 bulldozer

Backhoe Model Backhoe

= Komatsu PC200-6

Ukuran bucket

= 1,2 m3

Cycle Time

= 22 detik/bucket

Fill factor bucket tanah penutup

= 0,7

Tinggi Jenjang

= 8 meter

EU

= 85 %

MA

= 80 %

Kapasitas Dump Truck

= 222,5 m3

Banyak bucket

= (kapasitas Dump truck)/(kapasitas bucket) K - 16

= (22,5 m3)/(1,2 m3 ) = 18,75 bucket ≈ 19 bucket Waktu pengisin Dump Truck

= banyak bucket x cycle time = 19 bucket x 22 detik/bucket = 418 detik = 6,97 menit

Produksi backhoe untuk pengupasan tanah penutup : Produksi/jam

= 3600/CT x (bucket capacity x bucket fill factor ) x EU = (3600/22 detik) x (1,2 m³ x 0,7) x 0,85 = 116,8364 LCM/jam

Backhoe di lapangan

=

(Volume

lapisan

tanah

penutup/jam)/(Produksi Backhoe/jam) = (99,2176 LCM/jam)/( 116,8364 LCM/jam) = 0,85 unit backhoe Backhoe disediakan

1 unit backhoe

= (Jumlah backhoe di lapangan)/MA = 1/0,8 = 1,25 ≈ 2 unit Backhoe

Backhoe cadangan

= Backhoe disediakan – Backhoe di

lapangan =2–1

K - 17

= 1 unit Backhoe Dump truck Model

= Dump Truck HinoFM 260 JD

Jarak angkut untuk tanah penutup

= 0,341 km

Power

= 256 HP

Efisiensi mesin

= 85%

Ukuran bakPanjang

= 6,0 meter

Lebar

= 2,5 meter

Tinggi

= 1,5 meter

Waktu ganti gear + menumpahkan muatan+ maneuver

= 2,5 menit

Berat truck kosong

= 6,981 ton

Beban sumbu roda belakang

= 60%

Beban sumbu roda belakang

= 40%

Rimpul untuk percepatan

= 40,48 kg/ton

Kapasitas DumpTtruck

= panjang x lebar x tinggi = 6,35 m x 2,5 m x 1,5 m = 22,5 m³

Rute pengupasan batu gamping Jarak

= 0,501 km

K - 18

Berat truck kosong

= 6,981 ton = 6.981 kg

Berat isi

= Kapasitas truck x bobot isi x tanah penutup = 22,5 m³ x 1,2728 ton/m³ x 0,8 = 22,9104 ton = 22910,4 kg

Beban total

= berat truck kosong + berat isi = 6,981 ton + 22,9104 ton = 29,8914 ton = 29891,4 kg

Rimpullyang tersedia pada setiap gear Dump Truck Hino FM 260 JD : Gear Kecepatan (km/h) Eff Mekanis (%)

HP

Rimpull (lb)

1

9,02

85

256

9.046,56

2

12,44

85

256

6.559,48

3

17,33

85

256

4.708,60

4

23,93

85

256

3.409,95

5

32,80

85

256

2.487,80

6

45,24

85

256

1.803,71

7

63,04

85

256

1.294,42

8

87

85

256

937,93

Usable rimpull (yang digunakan)

= beban total x distribusi beban x CT = 29891,4 kg x 60% x 60%

K - 19

= 10760,904 kg Karena rimpull yang digunakan > rimpul yang tersedia yaitu 10760,904 kg >9.046,56 kg maka dump truck tidak mengalami selip. Waktu tempuh bermuatan pengangkutan lapisan tanah penutup Jalur A-B RP untuk RR

= 7 %x 29891,4 kg

= 2092,398 kg

RP untuk GR

= 0% x 20 kg/ton x 29,8914ton

= 0 kg

RP untuk percepatan = 20 kg/ton x 29,8914ton

= 597,828 kg

RP yang dibutuhkan

= 2690,226 kg

Karena rimpull yang dibutuhkan 2690,226 kg, maka digunakan gear 5 dengan kecepatan 32,80 km/jam Waktu yang di butuhkan

=

Jarak angkut kecepatan 0,501 km

= 32,80 km/jam = 0,015 jam = 0,9 menit Waktu kembali kosong Jalur B-A RP untuk RR

= 7 % x 6.981 kg

RP untuk GR

= 0 % x 20 kg/ton x 6,981 ton= 0 kg

RP untuk percepatan = 20 kg/ton x 6,981 ton RP yang dibutuhkan

= 488,67 kg

= 139,62 kg = 628,29kg

K - 20

Karena rimpull yang dibutuhkan 628,29 kg, maka digunakan gear 7 dengan kecepatan 87 km/jam, karena kecepatan di area penambangan < 50 km/jam, maka di gunakan gearr 6 dengan kecepatan 45,24 km/jam.

Waktu yang di butuhkan

=

Jarak angkut kecepatan 0,501 km

= 45,24 km/jam = 0,011 jam = 0,66 menit Waktu tetap Pengisian

= CT x banyak bucket = 22 detik/bucket x 11bucket = 242 detik = 4,03menit

Waktu ganti gear + Menumpahkan muatan + manuver = 2,5 menit Waktu variable Waktu tempuh bermuatan

= 0,9 menit

Waktu tempuh kosong

= 0,66 menit

Cycle time dump truck

= waktu tetap + waktu variable = 4,03 menit + 1,56menit = 5,59 menit

Jumlah trip/jam

60 menit

= 5,59

menit

= 10,7 trip ≈ 11 trip

K - 21

Produksi Dump Truck /jam

= kapasitas truk x jumlah trip/jam x EU = 22,5 LCM/trip x 11 trip/jam truck x 0,85 = 210,375 LCM/jam

Tanah penutup yang harus diangkut = 4162,0572LCM/minggu = 99,0966 LCM/jam Dump Truck di lapangan

=

batu gamping yang harus di angkut produksi 𝑑𝑢𝑚𝑝 𝑡𝑟𝑢𝑐𝑘/jam 99,0966 LCM/jam

= 210,375 LCM/jam truck = 0,47unit Dump Truck 1 unit Dump Truck Dump Truck disediakan

=

Jumlah 𝐷𝑢𝑚𝑝 𝑇𝑟𝑢𝑐𝑘 di lapangan MA 1

= 0,8 = 1,25 unit ≈ 2 unit Dump Truck Dump Truck cadangan

=DT disediakan – DT di lapangan =2-1 = 1 unit Dump Truck

Biaya Upah Operator : Jumlah Buldozer

: 1 unit

Waktu kerja

: 7 jam/hari K - 22

Hari kerja

: 24 hari (1 Bulan)

Upar Per Jam

: Rp. 13.666,-

Biaya

: Rp. 13.666,- x 7 x 1 x 24 : Rp. 2.295.888,-

Jumlah Backhoe

: 1 unit

Waktu kerja

: 7 jam/hari

Hari kerja

: 24 hari (1 Bulan)

Upar Per Jam

: Rp. 13.666,-

Biaya

: Rp. 13.666,- x 7 x 1 x 24 : Rp. 2.295.888,-

Jumlah Dump Truck

: 1 unit

Waktu kerja

: 7 jam/hari

Hari kerja

: 24 hari (1 Bulan)

Upar Per Jam

: Rp. 13.666,-

Biaya

: Rp. 13.666,- x 7 x 1 x 24 : Rp. 2.295.888,-

Total Biaya

= Rp. 2.295.888+ Rp. 2.295.888+ Rp. 2.295.888 = Rp. 6.887.664,-

Konsumsi bahan bakar : Jumlah Buldozer

: 1 unit

Waktu kerja

: 7 jam/hari

Hari kerja

: 6 hari

Konsumsi BBM

: 10 liter/jam

Harga bio solar

: Rp. 9.800,-

Biaya

: Rp. 9.800/liter x 10 x 7 x 1 x 6 : Rp. 4.116.000,-

K - 23

Jumlah Excavator

: 1 unit

Waktu kerja

: 7 jam/hari

Hari kerja

: 6 hari

Konsumsi BBM

: 15 liter/jam

Harga solar

: Rp. 9.800,-

Biaya

: Rp. 9.800/liter x 15 x 7 x 1 x 6 hari : Rp. 6.174.000,-

Jumlah DT

: 1 unit

Waktu kerja

: 7 jam/hari

Hari kerja

: 6 hari

Konsumsi BBM

: 12 liter/jam

Harga solar

: Rp. 9.800,-

Biaya

: Rp. 9.800/liter x 12 x 7 x 1 x 6 : Rp. 4.939.200,-

Total anggaran

:Rp. 4.116.000+ Rp. 6.174.000+ Rp. 4.939.200+ Rp. 6.887.664= Rp.22.116.864,-

LAMPIRAN K.2 PERHITUNGAN PASCATAMBANG REVEGETASI LAHAN 1. Tahun 2023

K - 24



Biaya Pengangkutan Material Luas lahan yang direvegetasi = 17.089,58m2 Volume material OB

= 17.089,58m2 x 1,25 m = 21.361,975m3 / 0,8 = 26.702,4687LCM

Volume material Top Soil

= 17.089,58m2x 0,75 m = 12.817,185 m3/ 0,8 = 16.021,4812 LCM

Total Volume

= Volume OB + Volume Top Soil =26.702,4687 LCM + 16.021,4812 LCM = 42.723,9499 LCM

Kebutuhan pengangkutan : Volume material

= 42.723,9499 LCM / 288 hari = 148,347LCM/ hari = 21,192 LCM/jam

Bulldozer Merk : Komatsu D20P-3 Kapasitas blade bulldozer

= lebar x (tinggi blade)2 = 2,18 m x 0,585 m2 = 1,275 m3

Tanah yang terisi

= kapasitas blade / factor blade = 1,275 m3 / 1 = 1,275 LCM

Jam kerja efektif

= 60 menit x EU = 60 menit x 0,8 = 48 menit

Effisiensi kerja terhadap alat

= Jam kerja efektif x MA K - 25

= 48 menit x 0,8 = 38,4 menit Untuk blade capacity

= 1,275 m³

Kecepatan maju

= 58 meter/menit

Kecepatan mundur

= 91,67 meter/menit

Waktu mendorong maju

= (jarak dorong) / (kecepatan maju x konversi) = (10 meter) / ( 58 meter/menit ) = 0,17 menit

Waktu untuk mundur

= (jarak dorong)/(kecepatan mundur x konversi) = (10 meter)/( 91,67 meter/menit) = 0,109 menit

Cycle time bulldozer

= waktu maju + waktu ganti porsnelling & gear + waktu mundur = (0,17 + 0,5 + 0,109) menit = 0,779 menit

Jumlah trip/ jam

= (jam kerja efektif) / (cycle time) = (48 menit) / (1,67 menit) = 28,74 trip = 29 trip

Produksi bulldozer/jam

= jumlah trip x kapasitas blade = 29 trip/ jam x 1,275LCM

K - 26

= 36,975 LCM/ jam Bulldozer yang bekerja dilapangan = (Volume tanah penutup/minggu)/(produksi per minggu) = (21,192 LCM/jam)/(36,975 LCM/jam) = 0,57 bulldozer = 1 bulldozer Bulldozer disediakan

= (Jumlah bulldozer di lapangan)/MA = 1/0,8 = 1,25 ≈ 2 unit bulldozer

Bulldozer cadangan

= bulldozer disediakan – bulldozer di lapangan =2–1 = 1 bulldozer

Backhoe Model : Komatsu PC130-8 Ukuran bucket

= 0,5 m3

Cycle Time

= 20 detik/bucket

Fill factor bucket tanah penutup

= 0,7

Swell factor tanah

= 0,8

Tinggi Jenjang

= 8 meter

EU

= 80 %

MA

= 80 %

Kapasitas Dump Truck

= 12,21 m3

Banyak bucket

= (kapasitas Dump truck)/(kapasitas bucket) K - 27

= (12,21 m3)/(0,5 m3 ) = 24,42 bucket ≈ 24 bucket Waktu pengisin Dump Truck

= banyak bucket x cycle time = 24 bucket x 20 detik/bucket = 480 detik = 8 menit

Produksi backhoe untuk pengupasan tanah penutup : Produksi/jam

= 3600/CT x (bucket capacity x bucket fill factor ) x EU = (3600/20 detik) x (0,5 m³ x 0,7) x 0,8 = 50,4 LCM/jam

Backhoe di lapangan

=

(Volume

lapisan

tanah

penutup/jam)/(Produksi Backhoe/jam) = (21,192 LCM/jam)/( 50,4 LCM/jam) = 0,42 unit backhoe = 1 unit backhoe Backhoe disediakan

= (Jumlah backhoe di lapangan)/MA = 1/0,8 = 1,25 ≈ 2 unit Backhoe

Backhoe cadangan

= Backhoe disediakan – Backhoe di lapangan =2–1 = 1 unit Backhoe

K - 28

Dump truck Model

= Dump Dutro 130HD

Jarak angkut untuk tanah penutup

= 0,501 km

Power

= 128,22 HP

Efisiensi mesin

= 85%

Ukuran bakPanjang

= 2,9 meter

Lebar

= 1,945 meter

Tinggi

= 2,165 meter

Waktu ganti gear + menumpahkan

= 2 menit

muatan+ maneuver Berat truck kosong

= 2,355 ton

Beban sumbu roda belakang

= 60%

Beban sumbu roda belakang

= 40%

Rimpul untuk percepatan

= ? kg/ton

Kapasitas DumpTtruck

= panjang x lebar x tinggi = 2,9 m x 1,945 m x 2,165 m = 12,21 m³

Rute pengupasan batu andesit Jarak

= 0,501 km

Berat truck kosong

= 2,355 ton = 2.355 kg

Berat isi

= Kapasitas truck x bobot isi tanah penutup = 12,21 m³ x 1,2728 ton/m³ x 0,8 K - 29

= 12,43271 ton = 12432,71kg Beban total

= berat truck kosong + berat isi = 2,355 ton + 12,43271ton = 14,78771 ton = 14787,71 kg

Rimpullyang tersedia pada setiap gear Dump Truck Hino D: Gear Kecepatan (km/h) Eff Mekanis (%)

HP

Rimpull (lb)

1

8,205

85

128,22

4.981

2

14,04

85

128,22

2.911

3

26,27

85

128,22

1.556

4

40,87

85

128,22

1.000

5

55,38

85

128,22

0.738

Usable rimpull (yang digunakan)

= beban total x distribusi beban x CT = 14787,71 kg x 60% x 60% = 5.323,5756 kg

Karena rimpull yang digunakan > rimpul yang tersedia yaitu 5.323,5756 kg >4.981 kg maka dump truck tidak mengalami selip. Waktu tempuh bermuatan pengangkutan lapisan tanah penutup Jalur A-B RP untuk RR

= 7 %x 14787,71kg

= 1.035,14kg

RP untuk GR

= 0% x 20 kg/ton x 29,8914ton

= 0 kg

RP untuk percepatan = 20 kg/ton x 29,8914ton

= 597,828 kg

K - 30

RP yang dibutuhkan

= 1.632,968kg

Karena rimpull yang dibutuhkan 1.632,968 kg, maka digunakan gear 3 dengan kecepatan 26,27 km/jam Waktu yang di butuhkan

=

Jarak angkut kecepatan 0,501km

= 26,27 km/jam = 0,019 jam = 1,14 menit Waktu kembali kosong Jalur B-A RP untuk RR

= 7 % x 2.355 kg

RP untuk GR

= 0 % x 20 kg/ton x 2,355 ton= 0 kg

RP untuk percepatan = 20 kg/ton x 2,355 ton RP yang dibutuhkan

= 164,85 kg

= 47.1 kg = 211,95kg

Karena rimpull yang dibutuhkan211,95kg, maka digunakan gear 5 dengan kecepatan 55,38km/jam, karena kecepatan di area penambangan < 50 km/jam, maka di gunakan gearr 4 dengan kecepatan 40,87 km/jam. Waktu yang di butuhkan

=

Jarak angkut kecepatan 0,501 km

= 40,87 km/jam = 0,012 jam = 0,72 menit Waktu tetap Pengisian

= CT x banyak bucket

K - 31

= 20 detik/bucket x 11bucket = 220 detik = 3,67menit Waktu ganti gear + Menumpahkan muatan + manuver = 2 menit Waktu variable Waktu tempuh bermuatan

= 1,14 menit

Waktu tempuh kosong

= 0,72 menit

Cycle time dump truck

= waktu tetap + waktu variable = 3,67 menit + 1,86menit = 5,46 menit

Jumlah trip/jam

60 menit

= 5,46

menit

= 10,9 trip ≈ 11 trip Produksi Dump Truck /jam

= kapasitas truk x jumlah trip/jam x EU = 12,21 LCM/trip x 11 trip/jam truck x 0,80 = 107,448 LCM/jam

Tanah penutup yang harus diangkut = 1.593,216LCM/minggu = 37,93 LCM/jam Dump Truck di lapangan

= =

batu gamping yang harus di angkut produksi 𝑑𝑢𝑚𝑝 𝑡𝑟𝑢𝑐𝑘/jam 37,93 LCM/jam 107,448 LCM/jam truck

= 0,35unit Dump Truck 1 unit Dump Truck

K - 32

Dump Truck disediakan

=

Jumlah 𝐷𝑢𝑚𝑝 𝑇𝑟𝑢𝑐𝑘 di lapangan MA 1

= 0,8 = 1,25 unit ≈ 2 unit Dump Truck Dump Truck cadangan

=DT disediakan – DT di lapangan =2-1 = 1 unit Dump Truck