Earned Value Analysis
PERT
CV = EV ‐ AC CPI = EV / AC SV = EV ‐ PV SPI = EV / PV ETC = EAC ‐ AC EAC = BAC / CPI VAC = BAC – EAC EAC ‘fundamentally flawed’ = AC + ETC EAC ‘atypical’ = AC + BAC ‐ EV EAC ‘over budget + deadline’ = AC + ((BAC ‐ EV) / CPI * SPI)) ETC ‘atypical’ = BAC ‐ EV ETC ‘typical’ = (BAC ‐ EV) / CPI ETC ‘flawed’ = new estimate Percent Complete = EV / BAC * 100 EV = % complete * BAC TCPI ‘based on BAC’ = (BAC – EV) / (BAC – AC) TCPI ‘based on EAC’ = (BAC – EV) / (EAC – AC)
PERT 3‐point = (Pessimistic+(4*Most Likely)+Optimistic)/6 PERT = (P + 4MP + O) / 6 PERT σ = (Pessimistic ‐ Optimistic) / 6 PERT σ = (P ‐ O) / 6 PERT Activity Variance = ((Pessimistic ‐ Optimistic) / 6) ² PERT v = ( ( P ‐ O) / 6) ²
Communications
Probability
Communication Channels = n * (n – 1 ) / 2 Where “n” is the number of channels
EMV = Probability * Impact in currency EMV = P * I
Project Selection PV = FV / (1+r) ⁿ FV = PV * (1+r) ⁿ BCR = Benefit / Cost CBR = Cost / Benefit
Values to Remember 1 sigma = 68.26% 2 sigma = 95.46% 3 sigma = 99.73% Six sigma = 99.99% Pareto Diagram = 80/20
Network Diagram
Project Selection
EF = ES + duration ‐ 1 PV = FV / (1+r)^n ES = EF of predecessor + 1 FV = PV * (1+r)^n LF = LS of successor ‐ 1 BCR = Benefit / Cost LS = LF ‐ duration + 1 CBR = Cost / Benefit Activity Duration = EF ‐ ES + 1 or Rough Order of Magnitude estimate = ‐50% to +50% Activity Duration = LF ‐ LS + 1 Preliminary estimate = ‐15% to + 50% Total Float = LS ‐ ES or Budget estimate = ‐10% to +25% Total Float = LF – EF Definitive estimate = ‐5% to +10% Free Float = ES of Following ‐ ES of Present ‐ DUR of Present Depreciation Double Declining Balance Method: Sum‐of‐Years' Digits Method: Straight‐line Depreciation: Depreciation Rate = 2 * (100% / Useful Sum of digits = Useful Life + (Useful Depreciation Expense = Asset Cost (– Life) Life ‐ 1) + (Useful Life ‐ 2) + etc. Scrap Value) / Useful Life Depreciation Expense = Depreciation Depreciation rate = fraction of years Depreciation Rate = 100% / Useful Life Rate * Book Value at Beginning of Year left and sum of the digits (i.e. 4/15th Book Value = Book Value at beginning of year ‐ Depreciation Expense
Edited By:
© Copyright PPCTotal 2009
PPC Total PPC Total – PM
Planning, Performing and Controlling Projects to Succeed
formul@s - Quick Reference Guide for Project
Common Acronyms AC Actual Cost ACWP Actual Cost of Work Performed AD Activity Description ADM Arrow Diagramming Method AE Apportioned Effort AF Actual Finish date AOA Activity‐on‐Arrow AON Activity‐on‐Node AS Actual Start date BAC Budget at Completion BCWP Budgeted Cost of Work Performed BCWS Budgeted Cost of Work Scheduled BOM Bill Of Materials CA Control Account CAPM Certified in Associate Project Management CAP Control Account Plan CCB Change Control Board COQ Cost of Quality CPF Cost‐Plus‐Fee CPFF Cost‐Plus‐Fixed‐Fee CPI Cost Performance Index CPIF Cost‐Plus‐Incentive‐Fee CPM Critical Path Method CPPC Cost‐Plus‐Percentage of Cost CV Cost Variance CWBS Contract Work Breakdown Structure DD Data Date DU Duration DUR Duration EAC Estimate at Completion EF Early Finish date
EMV Expected Monetary Value ES Early Start date ETC Estimate to Complete EV Earned Value EVM Earned Value Management EVT Earned Value Technique FF Finish‐to‐Finish FF Free Float FFP Firm‐Fixed‐Price FMEA Failure Mode and Effect Analysis FPIF Fixed‐Price‐Incentive‐Fee FS Finish‐to‐Start IFB Invitation for Bid LF Late Finish date LOE Level of Effort LS Late Start date OBS Organizational Breakdown Structure OD Original Duration PC Percent Complete PCT Percent Complete PDM Precedence Diagramming Method PF Planned Finish date PM Project Management PM Project Manager PMBOK® Project Management Body of Knowledge PMIS Project Manag. Information System PMO Program Management Office PMO Project Management Office PMP® Project Management Professional
PS Planned Start date PSWBS Project Summary Work Breakdown Structure PV Planned Value QA Quality Assurance QC Quality Control RAM Responsibility Assignment Matrix RBS Resource Breakdown Structure RBS Risk Breakdown Structure RD Remaining Duration RFP Request for Proposal RFQ Request for Quotation SF Scheduled Finish date SF Start‐to‐Finish SOW Statement of Work SPI Schedule Performance Index SS Scheduled Start date SS Start‐to‐Start SV Schedule Variance SWOT Strengths, Weaknesses, Opportunities, and Threats TC Target Completion date TF Target Finish date TF Total Float TOC Theory of Constrains T&M Time and Material TQM Total Quality Management TS Target Start date VE Value Engineering WBS Work Breakdown Structure
To learn how to use the formulas and practices on exercises with project data Please refer to our Tool “PPC Total- PM Formul@s®” And practice with about 150 typical Questions including the answers and explanations.
About PPC Total Company focus on supporting the Modern Project Management, using the most updated standards and helping the candidates to take the certification exam for the PMP®, CAPM®, PMI-SP®.