Network Planning With Pert

  • October 2019
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Network Planning With Pert as PDF for free.

More details

  • Words: 1,078
  • Pages: 24
Network planning with PERT

Network analysis: methodology PERT CPM

project evaluation and review technique critical path method

• enumeration of necessary activities, with indication of immediately preceding and necessarily finished activities • activities placed in a logical network by means of presentation with arrows. Each arrow presents an activity and is preceded and followed by an event

Network analysis • Analysing and planning of the subsequent activities, necessary to complete the project • Basis of cost calculation and timing of project • Evaluation of possible measures to reduce the duration of the project • Basis of monitoring and evaluation of the project

Definitions • A network is a logical presentation of the activities of a project. It shows the relations that exist between activities • An activity is a basic task necessary to complete the project. The activity needs time and resources • An event is a situation that defines the beginning or the end of a (number of) activit(y)(ies)

0

0

7

24

7

24

B 2

A

1

Start

7

5

110 17

D 24

K

26

E H

3

23 0

0

24

G

0

C

50

L

M 4 50

33

0

Critical path sequence TL Dummy Activity = TE min= slack (TLkf of normal max((TEkp activities time –TA) activity = LF for + TA) –which with EF duration TE = TL0

31 6

15 14

F

4 38

46 8

0

J 7

7 57

57 0

Finish

Activity Schedule – ES earliest starting time • ES = TE start event of the activity

– EF earliest finishing time • EF = ES + TA

– LF latest finishing time • LF = TL end event of the activity

– LS latest starting time • LS = LF – TA

ES (TE)

LS (LF-TA)

EF (ES+TA)

LF (TL)

Activity slack (LF-EF)

A

0

0

7

7

0

B

7

13

18

24

6

C

24

26

55

57

2

D

7

7

24

24

0

E

24

24

24

24

0

F

24

24

50

50

0

G

0

1

23

24

1

H

24

35

39

50

11

J

50

50

57

57

0

K

0

5

33

46

13

L

24

32

38

46

8

M

38

46

42

50

8

Float • • • •

Free float = ES of the next activity – EF of the activity Total float = LF – ES -TA interfering float = total float – free float independent float = ES of the next activity – LF of the activity

Crash activities

4

4

10

15

6 B

0

D

4

0

2

17

4

7 2

C

4

8

23

23

6

6 A

17

E

10

10

F

G

The optimal crash sequence therefore is; A - B @ £500 per unit time. F - G @ £1000 per unit time. B - E @ £2000 per unit time. E - F @ £3000 per unit time

Crash A-B .Crash A -B by 2 weeks. • Project completion reduces by 2 weeks. • Project cost increases by £1000. • Revised project cost = £19,500 + £1000 = £20,500 • Revised project completion = 23 - 2 = 21 weeks. • Check the critical path 2

2

8

13

6 B

0

D

2

0

2

15

4

7 2

C

4

6

21

21

6

6 A

15

E

8

8

F

G

Crash F-G Crash F -G by 1 week. • Project completion reduces by 1 weeks. • Project cost increases by £1000. • Revised project cost = £20,500 + £1000 = £21,500 • Revised project completion = 21 -1 = 20 weeks. • Check the critical path 2

2

8

13

6 B

0

D

2

0

2

15

4

7 2

C

4

6

20

20

5

6 A

15

E

8

8

F

G

Crahs B-E Crash B - E by 1 week. • Project completion reduces by 1 weeks. • Project cost increases by £2000. • Revised project cost = £21,500 + £2000 = £23,500 • Revised project completion = 20 -1 = 19 weeks • Check the critical path 2

2

8

12

6 B

0

D

2

0

2

14

4

7 2

C

4

5

19

19

5

5 A

14

E

7

7

F

G

Crash E-F Crash E - F by 1 week. • Project completion reduces by 1 weeks. • Project cost increases by £3000. • Revised project cost = £23,500 + £3000 = £26,500 • Revised project completion = 19 -1 = 18 weeks • Final critical path 2

2

8

11

6 B

0

D

2

0

2

13

4

6 2

C

4

5

18

18

5

5 A

13

E

7

7

F

G

Final crash curve Cost

18 weeks @ £26500

£26.5K

19 weeks @ £23500

Crash E - F

20 weeks £23.5K

@ £21500 Crash E - F 21 weeks

£21.5K

@ £20500

Crash E - F

£20.5K Crash E - F £19.5K Original condition 18

19

20

21

23

Time

Typical crash curve Cost

Cost-ineffective crash. Maximum effective crash

Minimum cost Origin

Time

Typical extended crash curve Cost

Non-critical crashing Maximum crash Optimum time-cost point

Best cost

Fixed costs

Best time

CPM with Uncertainty • Steps leading to network are same as before • Added complexity of having time estimates – Optimistic Time =a – Most Likely Time=m – Pessimistic time=p

• Expected time calculated as ET=(a+4m+b)/6

• Variance calculated as 2 σ

= ( b - a) 2 / 36

CPM with uncertainty • Given any path we can calculate – Expected completion time of path • Just add the expected times (ET)

– Variance of the path • Just add the variances

• Critical Path Determined Exactly as before – Only difference, we will now use expected times.

Completion Probability Assuming (which is the case) that the completion time follows a normal distribution with mean as ET and 2 σ variance as , we can calculate the following: What is the probability that the project is completed in T time units.

Completion Probability Take the critical path( determined as before, but now with expected times). We know ET for this critical path. We also know its std. dev (σ ) . We will always assume that the time of completion is Normally distributed. Hence: If X=Time of completion.

T − ET P( X ≤ T ) = P( Z ≤ ) σ

Related Documents

Network Planning With Pert
October 2019 26
Network Planning
December 2019 30
Network Planning Guide
November 2019 28
Pert
April 2020 26