TUGAS METODE PELAKSANAAN KONSTRUKSI

Contoh: Badan jalan baru, L = 200 Ha. Hasil survei: Data-data kondisi hutan/Ha. < φ 30 cm 1.500

Jumlah Pohon/Ha per Kelas Diameter 31 – 60 cm 61 – 90 cm 91 – 120 cm 121 – 180 cm N1 N2 N3 N4 4 3 2 -

> φ 180 cm -

Kayu 30%-nya adalah Pohon Ulin. Buat Metode Pelaksanaannya! Jawab: I.

Koreksi Lapangan (Faktor Produksi):  Pohon berdiameter < φ 30 cm = 1.500 Pohon/Ha (> 1.480 Pohon/Ha)  P = 2 dan

q1 =1.  Pohon berdiameter > φ 180 cm = 0 Pohon/Ha  D = 0 dan F = 0.  Kayu keras (Pohon Ulin) = 30% (25%-74%)  q2 = 1.  Metode penebangan > 1× operasi  q3 = 1,50.  Hasil penebangan mengharuskan tidak ada tunggul dan akar tertinggal  t1 = 1.  Metode penimbunan menggunakan 1 (satu) traktor  t2 = 1.  Tidak ada tanaman merambat di lapangan  r = 0,7. P 2 II.

q1 q2 q3 t1 t2 1

1

1,5

1

1

r 0,7

Data Tabel: Traktor 200

Felling

M1 0,5

Waktu Pengerjaan M2 M3 M4 1,8 3,6 11

Pilling

0,4

0,7

Pekerjaan

2,7

5,4

B 62 13 5

F -

TUGAS METODE PELAKSANAAN KONSTRUKSI

1. Tebas Tebang (Under Brushing): T = (P.B).q1.q2 = (2.62).1.1 = 124 menit/Ha T200 =

200 Ha × 124 menit/Ha = 59 hari. (7 × 60 menit)/hari

2. Felling: T = (P.B + M1.N1 + M2.N2 + M3.N3 + M4.N4 + D.F).q1.q2.q3. T = (2.62 + 0,5.4 + 1,8.3 + 3,6.2 + 11.0 + 0.0).1.1.1,5. T = (124 + 2 + 5,4 + 7,2 + 0 + 0).1,5. T = (138,6).1,5. T = 207,9 menit/Ha. T200 =

200 Ha × 207,9 menit/Ha = 99 hari. (7 × 60 menit)/hari

3. Pilling: T = (r.B + M1.N1 + M2.N2 + M3.N3 + M4.N4 + D.F).

t1. t2.

T = (0,7.135 + 0,4.4 + 0,7.3 + 2,7.2 + 5,4.0 + 0.0).1.1. T = (94,5 + 1,6 + 2,1 + 5,4 + 0 + 0).1. T = (103,6).1 T = 103,6 menit/Ha. T200 =

200 Ha × 103,6 menit/Ha = 49 hari. (7 × 60 menit)/hari

4. Bakar (Burning): T = ± 2 – 3 jam/Ha  Diperkirakan T = 2 jam/Ha.

T200 =

200 Ha × 2 jam/Ha = 57 hari. 7 jam/hari

TUGAS METODE PELAKSANAAN KONSTRUKSI

Kesimpulan:  Jika ada batas waktu dan ingin pekerjaan cepat selesai, tambah alat berat yang digunakan.  Jika ingin mempercepat pencairan dana, majukan (ke depankan) pekerjaan yang bobotnya besar.  Jika alat berat yang tersedia jumlahnya terbatas, gunakan secara bergantian. Kadang mengerjakan suatu pekerjaan secara bersamaan, kadang mengerjakannya masing-masing.