ANALYSIS OF RATES STANDARD CALCULATION FOR BRICK WORK AND MORTAR Assuming a 30 cm brick wall of area 100m2 = 30m3 (Nominal)
Vol. of B/W = 100x30/100
Actual volume = (29/100)x100 = 29 m3 Vol. of one symmetrical brick (i.e. with mortar) = 0.20x0.10x0.10 = 2000x10-6 m3 (or vol. of one standard or madular brck) Nos. of bricks in 29m3, volume = 29/2000x10-6 = 14500 nos. Nos. of bricks for 1 m3 of B/W = 14500/30x1 = 484 nos. Adding 5% for loose, breakage etc. For 10m3 of B/W, nos. of bricks = 5000 nos. 9″x4.5″x3″ → traditional brick 22.9 x 11.4 x 7.6 cm → 1984.056 cm3 20x10x10 = 2000 cm3 Cement Mortar Vol. of cement mortar (set) = 29 – (14500 x 0.19 x 0.09 x 0.09)
= 6.85 m3 Adding 15% extra for filling of frog, Unevnness of bricks and wastage/looses Vol. of C.M. reg. = 6.685x1.15 = 7.688 m3 Taking allowances for dry/loose vol. of C.M. as 25% Dry/loose vol. of CM = 7.688 x1.25 = 9.609 m3 (for 30m3 of B/W) Dry/loose vol. of C.M. for 10m3 B/W = (9.609/30) x 10 = 3.2 m3 For 100m3 of B/W dry/loose vol. of C.M. = 32m3 Or 32% of B/W
EARTHWORK IN EXCAVATION IN FOUNDATION INCLUDING (FILLING) UP TO TRENCH) UNIT -100 CUM. Take 100m3 (of work)
Particulars
Quantity
Rate (Rs)
Cost (Rs)
Mistri (Mason)
½ No.
380/no/d
190
Mazdoor (Beldar)
44 nos.
200/no./d
8800
Sundries, T&P etc.
Lump sum
120 L.S.
120
Materials Labours, etc.
Total of Material and Labour =
Add 10% contractor’s profit
=
9110
Rs. 911
Grand total
=
Rs. 10,021
Rate per m3
=
10021/100 = Rs. 100.21
1:5:10 CEMENT CONCRETE BLOCK 9 INCH THICK IN FOUNDATION Take – 10 cum.
Taking allowances for dry/loose volume as 52% Total dry/loose volume = 10+5.2 = 15.2 m3
15.2 Cement = x1 1 5 10
= 0.95 m3
$ No. of bags of cement = 0.95x30 = 28.50 bags Sand
15.2 x5 1 5 10
= 4.75 m3
15.2 3 1st class brick ballast = x10 = 9.50 m 1 5 10
Particulars
Quantity
Rate (Rs)
Cost (Rs)
28.5 bags
300/bag
8550
Sand (white)
4.75m3
671/m3
3187.25
1st
9.50 m3
1236/m3
11742
Mistri (Mason)
2 nos.
380/no/d
760
Mazdoor (Beldar)
30 nos.
200/no./d
6000
Sundries, T&P etc.
Lump sum
120 L.S.
120
Materials Cement (0.95m3)
class brick ballast
(40mm gauge) Labour etc
Total of materials and labour
= Rs. 30395.25
Adding 10% contractor’s profit = Rs. 3039.52
Adding 1.5% of water charges = Rs.455.93 Grand Total Rate per m3
= Rs.33890.7 = 33890.7/10 = Rs. 3389
1ST CLASS BRICK WORK 1:8 CEMENT SAND MORTAR IN FOUNDATION UP TO PLINTH Taking 10m3
As the no. of bricks for 1m3 = 500 nos. No. of bricks for 10m3 of B/W =500x10 = 5000 nos. Dry/loose volume of cement mortar for 10m3 of B/W = 3.2 m3 Therefore, 3 .2 Cement x1 1 8
= 0.35 m3
No. of bags = 0.35x30 = 10.66 bags = 11 bags 3.2 White sand = x8 1 8
Particulars
= 2.84 m3 Quantity
Rate (Rs)
Cost (Rs)
5000 nos.
7000/1000 nos.
35000
Cement (0.35m3)
11 bags
300/bag
3300
Sand (white)
2.84 m3
671.08/m3
1905.86
7½
380 /no/d
2850
14 nos.
200/no./d
2800
Materials 1st Class Brick
Labour etc Mistri (Mason) Mazdoor (Beldar)
Sundries, T&P etc.
Lump sum
120 L.S.
Total of materials and labour = Adding 10% contractor’s profit = Rs.4597.58 Adding 1.5% of water charges = Rs.689.637 Grand Total Rate per m3
= Rs.51263.077 = 51263.077/10 = Rs. 5126.3077
120 45975.86
EARTHWORK IN FILLING TO RAISE THE LEVEL OF GROUND UPTO PLINTH – UNIT M
3
Taking 100 cum. Particulars
Quantity
Rate (Rs)
Cost (Rs)
½ No.
380/no/d
190
Mazdoor (Beldar)
175 nos.
200/no./d
35000
Sundries, T&P etc.
Lump sum
120 L.S.
120
Materials Labours, etc. Mistri (Mason)
Total of Material and Labour = Add 10% contractor’s profit Grand total
Rate per m3
35310.00
= Rs. 3531/= Rs. 38841 /= 38841/100 = Rs. 388.41
2.5 CM. THICK DPC (DAMP PROOF COURSE) WITH 1:2:4 CEMENT CONCRETE – UNIT M2 Taking 100 sqm.
2 .5 Volume of cement concrete = x100 = 2.50 m3 100
Adding 10% extra for unevenness of base, wastages etc. Vol. of cement concrete
= 2.50 x 1.1 = 2.75 m3
Dry/loose vol. of cement concrete
= 2.75x1.52 = 4.18 m3
(Taking allowances as 52%) 4.18 Cement x1
= 0.59 m3
1 2 4
No. of cement bags
= (0.59x30) = 17.7 bags = 18 bags
4.18 3 Sand (Mooram) = x 2 = 1.18 m 1 2 4
Stone ballast (20 mm gague)
4.18 x4 1 2 4
= 2.36 m3
Cem-seal or impremo = 1kg per bag of cement = 1x18 = 18 kg
Particulars
Quantity
Rate (Rs)
Cost (Rs)
Cement (0.59m3)
18 bags
300/bag
5400
Sand (Mooram)
1.18m3
671.08/m3
791.87
mm
2.36m3
1660.04 /m3
3917.69
Cem-seal or impermo (1 kg
18 kg
120/kg
2160
10 ½ nos.
380/no/d
3990
12 nos.
200/no/d
2400
Forms in sides
Lump sum
120 L.S.
120
Sundries, T&P etc.
Lump sum
150 L.S.
150
Materials
Stone
ballast
(20
gauge)
per bag of cement) Labours Mistri (Mason) Mazdoor( Beldar)
Total materials and Labours = Adding 10% contractor’s profit
=
Rs. 1892.95
Adding 1.5% water charges
=
Rs. 283.94
=
Rs. 21106.45
=
211.06
Grand total Rate per m2
18929.56
R.C.C. WORK IN COLUMN 1:1½ : 3 - UNIT 1M3 Taking - 10m3
Taking allowances for loose/dry conc.
= 52%
Dry loose vol. of conc. = 10x1.52
= 15.2m3
1.52 cement =
3 1 2.76m 2.76 30 83bags 1 1 . 5 3
Sand =
5.2 3 15 4.14m 1 1.5 3
Stone aggregate =
5.2 3 3 8.28m 1 1.5 3
Steel: 1% steel = 0.1m3 f
M M .vol. 78.5q / m 3 0.1m3 7.85q vol.
So for column taking 2% 2% steel = 15.7 q Binding are = 2% of total steel =
15.7 0.2 0.0314q 100
Particulars
Quantity
Rates (Rs.)
Cost (Rs.)
Cement (2.76m3) 83 bag
2.76m3
300/bag
24900.00
Coarse sand
4.14
777.04/m3
3216.94
Stone ballast
8.28m3
1660/m3
13745.13
M.S bars @ 2/-
15.7q
5000/q
78500
Binding wire
0.0314q
50/kg
157
Total=
120519.07
Materials:
Labour Mason
3 nos.
380/no/d
1140.00
Mazdoor
56 nos
200/no/d
11200.00
Sundries
L.S.
120 L.S
120.00
Black smith
12 nos.
400/no/d
4800.00
T&P
L.S.
150/-
150.00
Carpenter
10 nos.
400/no/d
4000.00
Timber planks and ballies
L.S.
600 L.S.
600.00
T&P
L.S.
150 L.S.
150.00
Total =
22160
Total of materials and labours = Rs. 142679.07 Adding 1 ½ % water charges
= Rs. 2140.18
Adding 10% contractor’s profit = 14267.9 Grand total
= Rs. 159087.15
Rate per m3
= Rs. 15908.715
1ST CLASS BRICK WORK IN SUPER STRUCTURE WITH
20X10X10
BRICK
WORK
SAND MORTAR - UNIT 1M3 Taking - 10m3 No. of bricks for 10m3 = 5000 nos. Dry/loose vol. of cement mortar for 10m3 = 3.2 m3
3.2 3 cement = 1 0.45m 0.45 30 135bags 1 6
3.2 3 Sand = 6 2.74m 1 6
1:6
CEMENT
Particulars
Quantity
Rates (Rs.)
Cost (Rs.)
Materials: 1st class brick
5000 nos 7000/-
35000.00
Cement (0.45 m3)
13.5 bag
300/bag
4050
Sand coarse
2.74 m3
777.04/m3
2129.08
Total =
41179.08
Labour Mason
10 nos.
380/no/d
3800.00
Mazdoor
17 nos
200/no/d
3400.00
Scaffolding
L.S.
200 L.S
200.00
Sundries T&P
L.S.
120 L.S.
120.00
Total =
7520.00
Total of material and labour
= Rs. 41179.08
Adding 1 ½ % water charges
= Rs. 617.68
Adding 10% contractor’s profit = Rs. 4117.90 Grand total
= Rs. 45913.85
Rate per m3
= Rs. 4591.38.
WOOD WORK IN CHAUKHAT OR FRAME - UNIT 1M3 (TEAK WORK)
Taking frame of (210x120) cm door of (18x12)cm section Particulars
Quantity
Rates (Rs.)
Cost (Rs.)
Materials: Timber 5.98x0.8x0.12
0.053m3
63576/m3
3369.528
0.003m3
63576/m3
190.728
Total =
3560.257
400/no/d
325
(L=2x2.14+1x1.2=5.48) Wastage 5%
Labour Carpenter
13/16 nos.
Helper
½ nos.
200/no/d
100.00
Sundries T&P
L.S.
150 L.S.
150.00
Total =
575
Total of material and labour
= Rs.4135.257
Adding 10% contractor’s profit
= 413.52
Grand total
= Rs 4548.77
Rate per m3
= Rs. 454.87
12 MM CEMENT PLASTERING IN CEILING 1:3 WITH COARSE SAND Taking - 100m3 = 100m2
Taking area
t = 12 mm = 0.012 m Volume = 1.2 m3 Adding 20% extra for unevenness of base joints and wastages, etc. Vol. of cement mortar reqd. 1.44 m3 Dry
loose vol. of C.M. = 1.44x1.52
= .8m3
(Taking 25% allowance) Cement
1.8 3 = 1 0.45m 0.45 30 35bags 1 3
1.8 3 Coarse sand = 3 1.35m 1 3
Particulars
Quantity
Rates (Rs.)
Cost (Rs.)
Cement (0.45m3)
13.5 bag
300/bag
4050
Coarse sand
1.35m3
777.08/m3
1049
Total=
5099
Materials:
Labour Mason
12 nos.
380/no/d
4560.00
Mazdoor
15 nos
200/no/d
3000.00
200 L.S.
200.00
Total =
7760.00
Scaffolding, T&P sundries L.S. etc
Total of material and labour
= Rs. 12859
Adding 1 ½ % water charges
= Rs. 192.885
Adding 10% contractor’s profit = Rs. 1285.9 Grand total Rate per m2
= Rs. 14337.78 = Rs. 143.37
TOR STEEL REINFORCEMENT @ 1% OF R.C.C. WORK UNIT – 1 CU.M. Taking 10m3 Particulars
Quantity
Rates (Rs.)
Cost (Rs.)
Materials: Steel , Mild steel bar @ 1% = 1.0 cum @ 8.5 q/cum = 7.85 q Per 10 cum
7.85q
5000/q
39250.00
Binding wire
1.50 kg
50/kg
75.00
Black smith
8 nos.
400/no/d
3200
Mazdoor
8 nos
200/no/d
1600.00
T&P etc.
L.S.
150 L.S.
150.00
Total =
44275
Labour
Total of labours and materials or (bending and binding of steel = Rs. 44275.00 Adding 10% contractor’s profit = 4427.50 Grand total
= Rs. 48702.5
Rate per m3
= Rs. 487.02
MILD STEEL FRAMES OF DOORS AND WINDOWS OF (35X35X5) MM ANGLE SECTION:
Taking a frame of (1200x2100) sq.m. door of (35x35x5) mm angle section of mild steel Length = [2x(2.1+0.04)+(1x1.2)] = 5.48 m (Taking 4 cm insertion into the ground Quality
= 5.48x2.61 @ kg/m = 14.3028 kg Particulars
Quantity
Rates (Rs.)
Cost (Rs.)
Labours: Black smith 1st class
¾ nos.
400/day
300.00
Helper
½ nos.
200/day
100.00
Sundries T&P etc.
L.S.
150/L.S.
150.00
Total=
550
Total of materials and labours = Rs. 550 Adding 10% contractor’s profit = Rs. 55 Grand total
= Rs. 605
Rate per door frame
= Rs. 1200
Rate per quintal
= Rs. 6000.00
R.C.C. work in (M20 GRADE) in beam, slabs and lintels Unit- 1cu.m Taking - 10m3 grade = M20 (1:1 ½ : 3)
Taking 52% extra dry volume Thus dry volume = 15.2 cum Material calculation Cement =
152 1 2.8cu.m 84bags 1 1.5 3
15.2 Coarse sand =
1 4.2cu.m 1 1 . 5 3
Stone ballast =
15.2 3 3 8.4m 1 1.5 3
Particulars
Quantity
Rates (Rs.)
Cost (Rs.)
Materials: Cement (84 bag)
2.8m3
300/bag
25200.00
Coarse sand
4.2 m3
777.08/m3
3263.73
Stone ballast (20mm gauge)
8.4m3
1660.04/m3
13944.336
Total=
42408.066
Labour Mason
3 ½ nos. 380/no/d
1330.00
Mazdoor + (Water man)
35+2=37 200/no/d
7400.00
Sundries T&P
L.S.
150.00
150 L.S
Timber planks and balies
L.S.
200 L.S.
200.00
Carpenter IInd class
10 Nos.
300/-
3000.00
Mazdoor
10 nos.
200/no/d
2000.00
Nails
L.S.
300 L.S.
300.00
T&P
L.S.
150 L.S.
150.00
Total =
14530
Total of materials, labours & centering and shuttering = Rs. 56938.066 Adding 1 ½ % water charges
= Rs. 854.07
Adding 10% contractor’s profit = Rs. 5693.80 Grand total Rate per 1 cum
= Rs. 63485.936 = Rs. 6348.59
TEAK WOOD WORK IN DOOR AND WINDOWS SHUTTER GLAZING IN WINDOW SHUTTERS: Taking a door shutter 1064x2032 mm = 2.162m2
Particular/ details of
No.
items
L (m)
B/W Thick Quantity
Rate
Cost
(m)
(m)
(Rs.)
(Rs)
Materials Timber: Style
04
2.032 0.10
0.04
0.0325
Top rail
01
1.064 012
0.04
0.051
Freeze rail
01
1.064 0.12
0.04
0.051
Lock rail
01
1.064 0.18
0.04
0.0077
Bottom rail
01
1.064 015
0.04
0.0064
Pannels total sum of 01 length and breadth L=203.2-(2x12) (18+15)+(6x1.2)=153.4 = 1.534 m B=(106.4+1.2)-4x10 +4x1.2=72.4=0.724 m
1.534 0.724 0.025
0.0278
Insertion = 1.2 cm Central overlap= 1.2cm Total
0.0846
Adding 5% for wastage
0.002
Grand total
0.0888
63576 5645.55
cu.m
/m3
S.No.
Particulars
Quantity
Rates
Cost (Rs.)
(Rs.) Brass fitting Tower bolts (30cm) upper
1 no.
30/no.
30.00
Tower bolts (35cm) lower
1 no.
20/no.
20.00
Hinges (10cm)
6 nos.
15/no.
90.00
Brass handle
2 nos.
45/no.
90.00
Wooden cleat
2 nos.
15/no.
30.00
15/nos.
30.00
Hinges 2.5 cm (for wooden 2 nos. cleat) Screw (40mm)
20 nos.
1/no.
20.00
Screw (20 mm)
80 nos.
0.50/no.
40.00
Sliding bolt
L.S.
60 LS
60.00
Labour Carpenter I-class
1/15 nos. 400/no/d
26.66
Carpenter II-class
4 nos.
300/no/d
1200.00
Helper
2 nos.
200/no/d
400.00
Putty, glues etc
L.S.
150 L.S.
150.00
Sundries T&P
L.S.
150 L.S.
150.00
Total =
2336.66
Total of materials, labours & fittings = Rs. 2336.66 Adding 10% contractor’s profit = Rs. 233.66 Grand total
= Rs. 2570.32
Rate per sq.m. (for doors) = Rs. 1188.86 Taking a window shutter 100x150 cm, (area = 1.5 m2) Particular/
No. L
details of items
B/W
Thick Quantity Rate
Cost
(m)
(m)
(m)
(Rs)
1.5
0.075 0.04
0.018
1.0
0.075 0.04
0.006
(Rs.)
Timber: Style
04
Top & bottom rail 2 Sash bars verticals
(15mm insertion) L=150-
2
1.38 0.04
0.04
0.004
50- 6
0.38 0.04
0.04
0.004
(2x7.5)+(2x1.5) = 1.38 m Sash
bar
horizontal (15mm insertion) L
=
(2x7.5)+(3x1.5) = 38cm = 0.38m Total Add
0.032 5%
for
0.002
wastage Grand total
0.034
63576 2161.58
cum
/m3
Particulars
Quantity Rates (Rs.)
Cost (Rs.)
Fittings Tower bolts (30cm) upper
1 no.
30/no.
30.00
Tower bolt (15cm) lower
1 no.
20/no.
20.00
Hinges (10cm)
4 nos.
15/no.
60.00
Brass handle
1 nos.
50/no.
50.00
Wooden cleat
2 nos.
15/no.
30.00
Hinges 2.5 cm (for wooden cleat)
2 nos.
15/nos.
30.00
Screw (40mm)
20 nos.
1/no.
20.00
Screw (20 mm)
50 nos.
.50/no.
25.00
40/sqft
430.40
L.S.
25.00
25.00
Carpenter I-class
1/15
400/nos.
26.66
Carpenter II-class
2 nos.
300/no/d
600.00
Glass panels 16 nos x 18.5 x 33.75 1.0 2 cm = 1.0 m2 B=1/2[50-2x7.5-1(2x1.5)] = 18.5 cm HT = ¼[150-(2.75)-(3x1)+ (2x1.5) = 33.75 cm Putting, glues & nails for fixing Labours
Helper
1 nos.
200/no/d
200.00
L.S.
150 L.S.
150.00
Total =
1697.00
Putty, glues etc Sundries T&P
Total of materials, labours & fittings = Rs. 3858.58 Adding 10% contractor’s profit
= Rs. 385.85
Grand total
= Rs. 4244.43
Rate per m3
= Rs. 2829.62
PLASTERING ON WALLS WITH 1:5 CEMENT SAND MORTAR (OUTSIDE & INSIDE) UNIT-1M3 Taking - 100m3
Thickness of plaster = 12 mm Volume of cement mortar = 100x0.012 = 1.2 m3 Adding 30% extra for filling joints unevenness etc Volume of cement mortar = 1.2x1.3 = 1.56 m3 Taking allowances for loose/dry vol. of mortar as = 25% Dry/loose vol. of cement mortar= 1.56x1.52 = 1.95m3 = 2.0 m3
2.0 3 Cement = 1 0.33m 10bags 1 2 3
2.0 3 Sand (Fine) = 3 1.0m 1.0bags 1 2 3
2.0 Sand (Coarse) = 2 0.67 1 2 3
Particulars Materials:
Quantity
Rates (Rs.)
Cost (Rs.)
Cement (10 bags)
0.333m3
300/bag
3000.00
Fine sand
1.0 m3
671.08/m3
671.08
Coarse sand
0.67m3
777.04/m3
52.06
Total=
3723.14
Labour Mason
11 nos.
380/no/d
4180.00
Mazdoor
20 nos
200/no/d
4000.00
Scaffolding
L.S.
500 L.S
500.00
Sundries T&P
L.S.
150 L.S
150.00
Total =
8830.0
Total of materials and labours = Rs. 12553.14 Adding 1 ½ % water charges
= Rs. 188.29
Adding 10% contractor’s profit = 1255.31 Grand total
= Rs. 13996.74
Rate per m3 = Rs. 139.96
MOSAIC FLOORING OVER BASE CONCRETE 1:2:4 (CEMENT, COARSE SAND, STONE AGGREGATE) Taking – 100m2
6 mm thick mosaic layer 1: 1 ½ over 7.5 cm thick cement concrete (1:2:4) Total dry vol. of materials for cement concrete = 12.4 m3 (with allowances 53% & 10% for voids and unevenness respectively)
12.4 3 Cement = 1 1.8m 54bags 1 2 4
12.4 3 Coarse Sand = 2 3.5m 1 2 4
12.4 Sand (Coarse) = 4 7.1 1 2 4
Total dry vol. of materials for 6 mm thick mosaic layer (with allowances 50% & 20% for voids and finishing and cutting respectively) = 1.08 m3 1.08 3 Cement = 1 0.43m 12.9bags 1 1.4
Marble chips = 0.43 x 1.5 = 0.65 m5
Particulars
Quantity
Rates (Rs.)
Cost (Rs.)
Materials: 75 mm CC. (1:2:4) Stone ballast 12 mm gauge
7.1 m3
1660/m3
11786.284
Coarse sand
35m3
777.04/m3
27196.4
Cement (54 bags)
1.8m3
300/bag
16200
Cement (12.9 bags)
0.4 m3
300/bag
3870
Marble chips (3mm gauge)
0.65m3
3000/m3
1950
Marble dust
0.04m3
1500/m3
60
Mason
21 nos.
380/no/d
7980
Beldar
20 nos
200/no/d
4000.00
Polisher
120 nos.
200/no/d
24000.
Polishing stone
L.S.
150 L.S
150.00
Axalic acid powder
L.S.
100/-
100
Side forms
L.S.
120/-
120
Sundries T&P etc.
L.S.
150/-
150
6 mm mosaic (1:1 ½ )
Labours
(carborndom)
Total of materials and labours = Rs. 97562.68
Adding 1 ½ % water charges
= Rs. 1463.44
Adding 10% contractor’s profit = 9756.26 Grand total
= Rs. 108782.38
Rate per m3 = Rs. 1087.82
GLAZED TILE WORK IN KITCHEN AND TOILET UPTO DOOR LEVEL UNIT – 1M2 Taking – 100m2
Glazed tile laid over 12 mm thick cement sand mortar Total dry vol. of mortar = 2m3 Cement = 2/(1+3) = 0.5 m3 = (15 bags) Coarse Sand = 0.5x3 = 1.5 Assuming size of tile = 150mm x 150 mm No. of tiles = 100/0.15x0.15 = 4445 Nos. Adding 5% extra for breakage and wastage etc. No. of tiles req. 4445x1.05 = 4667.2 = 4670 Nos. Particulars
Quantity
Rates (Rs.)
Cost (Rs.)
Glazed tiles: (15x15)cm (4670 nos.)
100 sqm. 25/piece
116750
Cement (15 bags)
0.50 m3
300/m3
4500
Coarse sand
1.5m3
777.04/m3
1165.56
Cement for tiles and joints
6 bags
300/bag
1800
Mason
16 nos.
380/no/d
6080
Mazdoor
15 nos
200/no/d
3000
Labours
Polisher
120 nos.
200/no/d
24000
Polishing stone
L.S.
150 L.S
150.00
Axalic acid
L.S.
100/-
100
Sundries T&P
L.S.
150/-
150
Total
157695.56
Total of materials and labours = Rs. 157695.56 Adding 1 ½ % water charges
= Rs. 2365.43
Adding 10% contractor’s profit = 15769.55 Grand total Rate per m3
= Rs. 175821.54 = Rs. 1758.21
WHITE WASHING AND COLOUR WASHING ON WALLS AND CEILING (3 COATS) UNIT – 1M2 Taking – 100m2 Particulars
Quantity
Rates (Rs.)
Cost (Rs.)
Materials: 1st White lime un slaked
30kg
8/kg
240
Glue powder
L.S.
150 L.S.
150
Coloring pigment (10kg/kg)
300q
0.40 L.S.
120
Total =
510.00
Labours White washer
1 ½ Nos. 300/d
450
Mazdoor
1 ½ Nos. 200/d
350
Sundries T&P
L.S.
150 L.S.
150.00
Total =
950.00
Total of material and labour
= Rs. 1460
Adding 10% contractor’s profit = 146 Grand total Rate per m2
= Rs. 1606.00 = Rs. 16.06
ROOF TERRACING WORK WITH BRICK TILE LAID OVER MUD PHUSKA UNIT-1M2 Taking - 10m2
Mud phuska roofing 10cm thick below one layer of brick tile with two coat of bitumen painting below mud phuska and tile one laid 1:3 cement mortar No. of brick tile = 381 nos. for 10m2 Total dry material for mortar = 0.23 m3 0.23 3 Cement = 1 0.05m 1.7bags 1 3
0.23 3 Sand = 3 0.1725m 1 3
Particulars
Quantity
Rates (Rs.)
Cost (Rs.)
Materials: Brick tiles (23x12x4)
381 nos.
Cement (1.7 bags)
0.0575m3 300/bag
510
Sand (coarse)
0.1725m3 777.04/m3
134.039
Earth (loamy soil)
1.0m3
150/m3
150
Bhusa cow dung etc.
L.S.
150L.S.
150
Bitumen
20kg
150/kg
3000
Labour
5000/d
1905
Mason
2 nos.
380/no/d
760
Mazdoor
5 nos
200/no/d
1000
Sundries T&P
L.S.
150 L.S
150
Total =
5849.039
Total of materials and labours = Rs. 5849.039 Adding 1 ½ % water charges
= Rs. 87.73
Adding 10% contractor’s profit = 584.9 Grand total Rate per m2
= Rs. 6521.66 = Rs. 65.21