Logical Framework Analysis/Approach (LFA)
OBJECTIVES 1. Introduce Logical Framework Analysis/Approach (LFA) and its uses. 2. Familiarize with the main steps involved in conducting an LFA. 3. Give a concrete example. 4. Exercise on the Project Planning Matrix (?).
INTRODUCTION LFA was first developed by Practical Concepts Inc. in 1969 for the U.S. Agency for International Development (USAID). It has since been widely adopted and adapted by the international donor community and is used for participatory project planning, as an analytic tool for project approval, or as a monitoring and evaluation framework.
What is LFA? • A designing approach that can be used for planning, implementing and evaluating projects or programmes.
Purpose of LFA The purpose of LFA is to undertake participatory, objectives-oriented planning that spans the life of project or policy work to build stakeholder team commitment and capacity with a series of workshops. The technique requires stakeholders to come together in a series of workshops to set priorities and plan for implementation and monitoring.
The two terms Logical Framework (LF or Logframe) and the Logical Framework Approach (LFA) are sometimes confused. The LogFrame is a document, the Logical Framework Approach is a project design methodology. For most purposes the three terms; Logical Framework Approach, ZOPP and OOPP are terms for the same project design methodology or process. The terms OOPP and ZOPP mean respectively; Objectives Oriented Project Planning and in German Ziel Orientierte Projek Planung. All three terms refer to a structured meeting process
Steps LFA 1. Situation Analysis – Stakeholder Analysis – Problem Analysis – Objective Analysis 2. Strategy Analysis 3. Project Planning Matrix – Matrix – Assumptions – Objective Indicators – Verification 4. Implementation 5. Monitoring 6. Evaluation
The LFA approach begins by analyzing the existing situation and developing objectives for addressing real needs. A situation analysis has as its core task to find out the actual state of affairs with respect to an issue to be analyzed; it is focused by problems and an attempt to understand the system which determines the existence of the problems. The analysis phase is the most critical, yet most difficult, phase of the logframe approach. The analysis phase consists of three stages: 7.Analysis of stakeholders 8.Analysis of problems
Stakeholders Analysis In using the LFA approach, the stakeholder analysis is an analysis of the problems, fears, interests, expectations, restrictions and potentials of all: • important groups • organisations and institutions • implementing agencies • other projects and • individuals who may have an influence on a situation/(intended) project or are themselves affected by it. Those analyzed in detail should be limited to those who are perceived to: • be able to contribute to questions to be answered . •be important with regard to decisions to be taken. They should constantly be referred to in developing the LFA.
Who are the stakeholders involved in the project and how are they affected?
Key questions to ask in preparation for developing the logframe are:
3.Who will be involved in the logframe development? 4.Where will the development be conducted? 5.Who will facilitate the development of the logframe ? 6.What background materials, papers and expertise may be needed?
The Stakeholders Stakeholders include those who directly benefit from or have a legitimate interest in the company's activities and all those who have an impact and/or are affected by the impact, due to the company's performance and actions. The corporate community and the wider community are all stakeholders. Corporate community includes the management, employees, shareholders, joint ventures/partnerships/subsidiaries, suppliers and contractors, customers and consumers. Wider community includes the ecosystem, the local government, the host communities and the indigenous communities. Foremost, the
Problem Analysis The analysis phase usually begins with an analysis of problems. The problem analysis is undertaken by identifying the main problems and developing a 'problem tree' through an analysis of cause and effects. Key questions. 3.Which are the problems the project is addressing? 4.What are the root causes of those problems? 5.What is the larger picture in which those problems and their root causes exist?
Problem Tree A main output of the problem analysis is the problem tree. The first procedure in problem analysis is brainstorming. Before the brainstorming exercise commences it is important that the facilitator explain the process and the group agrees on some rules for
Agreement and Consensus
If there is no agreement between participants on the statement of the problem, it is unlikely there will be agreement on the solution. This stage therefore seeks to get consensus on the detailed aspects of the
Brainstorming Brainstorming techniques can be used to identify the main problems. All participants are invited to write their problem ideas on small cards. (approximately 8 in by 4 in.) The participants may write as many cards as they wish. The participants then group the cards or look for cause-effect relationship between the themes on the cards by
Clustering After all of the problems are displayed they should then be clustered into groups of similar issues The problem tree is developed by: 1. moving problems from the clusters of problems 2. adding new problems that emerge 3. problems can be moved up or down the tree as required
Objective Analysis A procedure for systematically 1. identifying 2. categorizing 3. specifying 4. balancing out objectives of all parties involved in a specific situation
Objective Tree In this step the problem statements are converted into objective statements and if possible into an objective tree. 3.Problems are restated as objectives The problem tree is transformed into an objectives tree by restating the problems as objectives. 2. Positive mirror image of the problem tree The objectives tree can be viewed as the
Means and Ends The objectives tree can be considered as an 'ends- means' diagram. The top of the tree is the end that is desired and the lower levels are the means to achieving the end. Based on this objectives tree, certain means are feasible and some are perhaps outside the scope of the problem. Nonetheless, these means provide the foundation for developing programmes, projects or strategies to address the problems discussed earlier.
Just as the problem tree shows causeeffect relationships, the objective tree shows means-end relationships. The means-end relationships show the means by which the project can achieve the desired ends or future desirable conditions. Frequently there are many possible areas that could be the focus of an "intervention" or development project. The next step addresses those choices.
Strategy Analysis • searching for and deciding on solutions • follows the problems and objectives analysis • prerequisite to designing action strategies Points to consider • overall concepts, strategic plans, objectives • people, target groups, organizations, agencies
Conducting a Strategy Analysis 1. ordering sequence of the problem and objective trees 2. clustering objectives 3. feasibility of different interventions 4. continuous task in project management
Alternatives Analysis The objective tree usually shows the large number of possible strategies or means-end links that could contribute to a solution to the problem. Since there will be a limit to the resources that can be applied to the project, it is necessary for the participants to examine these alternatives and select the most promising strategy. After selection of the decision criteria, these are applied in order to select one or more means-end chains to become the set of objectives that will form the project strategy.
Project Planning Matrix (1) (2) (3) (4)
Matrix Assumptions Objective Indicators Verification
Objectively Verifiable Means of Verification External Factors Narrative Summary Indicators - OVIs -MOVs (Assumptions)
Development Objective
Immediate Objective
Outputs (Results) 1. 2. 3.
Activities 1. 2. 3. 4.
Inputs 1.1 1.2 1.3 1.4
Column headings definition of terms Narrative Summary: This term used to describe the text that "narrates" the objectives. It could have been given the title "Hierarchy of Objectives", but this might be misleading because the bottom cell in the column is a summary of the
Column headings definition of terms Objectively Verifiable Indicators (OVIs): These are the measures, direct or indirect that will verify to what extent the objectives have been fulfilled. The term "objectively" implies that if these should be specified in a way that is independent of possible bias of the observer.
Column headings definition of terms Means of Verification (MOVs): These statements specify source of the information for the measurements or verification specified in the indicators column. For example, will statistics from an external source be used for the verification or will project resources be used to gather the
Column headings definition of terms External Factors (Assumptions): These are important events, conditions, or decisions which are necessarily outside the control of the project, but which must remain favorable for the project objective to be attained. The implication here is the design team have an obligation to consider what might derail their efforts and to plan responsibly to reduce that risk of
Row headings definition of terms Development Objective: The higher level objective that the project is expected to contribute to. The addition of the word "contribute' implies that this project alone is not expected to achieve the development objective. Other project's immediate objectives are
Row headings definition of terms Immediate Objective: The effect which is expected to be achieved as the result of the project delivering the planned outputs. There is a tendency for this to be expressed in terms of the "change in behavior" of a group, or institution and the project outputs are expected to facilitate this
Row headings definition of terms Outputs: These are the "deliverables" the tangible results that the project management team should be able to guarantee delivering. The objective statements should specify the group or organization that will benefit.
Row headings definition of terms Activities: These are the activities that have to be undertaken by the project to produce the outputs. The activities take time to perform.
Row headings definition of terms Inputs: These are the resources that the project "consumes" in the course of undertaking the activities. Typically they will be human resources, money, materials, equipment, and time.
Vertical Logic • Vertical Logic: The vertical logic is the reasoning which "connects" the three levels of objectives in the matrix; the outputs, the purpose, and the goal. For example achievement of all the output level objectives should lead to achieving the purpose. Each of these links between the objectives is connected by a hypotheses. • For example at the bottom level - the implementation hypotheses the implication is "we believe that in the environment of this project the planned outputs will produce the planned result. At
Horizontal Logic • The horizontal logic has similar features to the vertical logic. In this case, the links between the levels of objectives are the items in the External Factors column. • For example, if the project is successful in implementing all of the planned activities, we ask ourselves, what circumstances or decisions (outside the project's control) could
Implementation Operational phase of a project to achieve the expected outputs/results Plan of Operations 3.workplans / work schedules 4.project budget / resources plans 5.personnel plans 6.material and equipment plan / procurement plan / staff 7.training plans
Plan of Operations Implementation should have a plan of operations i.e. the detailed plan for the implementation of project. It is established by the project team and will be documented as: •workplans / work schedules •project budget / resources plans •personnel plans •material and equipment plan / procurement plan / staff •training plans. The work plan and the project budget constitute the core of the Plan of Operations.
SWOT Analysis S-W
Strengths Weaknesse s
O-T Opportunitie S-O W-O s STRATEGY STRATEGY Threats
S-T W-T STRATEGY STRATEGY
Strengths
• Scholarship program indicates high possibility of continuing demand • High competence in the Adult Education Program • Intervention through CADT giving sense of security to the IPs • Innovative approaches to sourcing of funds • Has established credibility among the donors; increasing interest of funders in Cartwheel’s programs • Developed social capital within government agencies, other
Weaknesses • Low level of success in the PreSchool Program • Mismatch of the products and services to real clients needs • Some programs (medical/dental, etc.) not within their competence • Heavily dependent on grants and donations • Donations showing a downward trend
Opportunities • High demand in secondary, post-secondary education, & adult education • CADT assures the IPs ownership and management of the lands they are tilling • Availability of uncultivated land suitable for high yield vegetables & coffee • Need for sustainable dev’t program demanded by ADSDPP as mandated by NCIP • Available funding for sustainable and capacity-building program • Issues for IPs and needs of the IPs not given significance / priority of the • LGU is one of the major coffee-producing regions •• Low attainment the IPs like , , , , etc., haveeducational several export marketsof for coffee • Lack of access to secondary schools • IPs lack the capacity to participate in the socio-political affairs of the municipality • Volatile peace and order situation • Farming is the primary source of income
Threats
S-O STRATEGY
W-O STRATEGY
S-T STRATEGY
W-T STRATEGY
• Implementation of ADSDPP (political empowerment, peace and order, cultural preservation) • Shift program to adult / secondary / post-secondary • Capacity-building of IPs; education (education) expansion of Adult Education • development (economic (education) benefits) • Bridging market and community (economic benefit) • Capacity-building of IPs through education (education) • development (economic benefits)
• Strengthening and expansion of scholarship program (education)
• Support H/S (St. Therese of • Building collaboration with Miarayon) (education) government, NGOs and the business sector (political & social • development (economic capital, economic benefit) benefits)
Stakehold er
Interest on the Program
MILALITTRA Security of land tenure; productivity / Tribal Leaders Women’s Help provide food for the family; Group additional income; education for the children Fr. Kit Miarayon becoming a pilgrimage site Bautista CFI Parish Priest / Principal Gina – PreSchool CFI
and a bridge between the poorest of the poor and richest of the rich Increased enrolment in high school; improved quality of education; evangelization and preservation of culture equal access to quality Provide education to as many children in the country Increase literacy rate and improve
Position on the Impact of the Program Program Support Capacity-building; political participation; livelihood opportunities Support Additional source of income; Support
Support
Potential opposition Support
self-sufficiency of IPs Barangay Officials
Peace and order; improvement of income of IPs
NCIP
Traders’ group Religious nuns
Promotion and protection of the rights Support of IPs; implementation of IPRA and ADSDPP Promotion of general welfare; local Support autonomy; delivery of basic services; agricultural productivity; peace and order profit from trading activities More Potential opposition Evangelization; promotion of Support education
Land claimants
Legitimization of claims on lands allegedly purchased from the IPs
LGU – Talakag
Support
Oppose
capacity-building; education of children Realization of his dream;
Influenc e on the Program High Moderate High
abridgement of social gaps between rich and poor Increased enrolment; expansion High of services; improvement of educational facility Phasing-out of pre-school High Financial sustainability; focusing High of programs; matching services to needs of IPs Increased employment for the Moderate people; improved peace and order condition Increased performance of High advocacy Increased trust for IPs’ capacity; High improved peace and order condition; increased revenue Decreased income due to Moderate rerouting of products Increased enrolment; potential High increase of the faithful Loss of rights to claim and use the land
High
Action Plan coffee project Activities
Target Output Qty. Quality
Planning
One (1) year plan drafted
Specifications drafted
Sourcing of funds
1 Project funded
Identification of coffee areas for rehabilitation
Time Frame July 2005
In-Charge
Resources
CFI Ex. Dir. & Consultant, BOD
Funds, data
Appropriate and July – on-time December 2005
CFI
Project Proposal
1,000 hectares identified
Suitable for coffee plantation
July – December 2005
CFIMILALITTRA
Funds, staff
Lending of Initial capital
1,000 farmers entered into MOA through MILALITTRA
Credible and reliable partners
Jan 2006 onwards
CFI
Project Funds, staff
Monitoring
1,000 hectares Seasonal and plantation monitored regular
Planting: May-Dec of every year, 2006-2010
CFI staff
Transpo cost, supplies
Establishment of trading partners
At least 2 partners identified (Figaro, Monk’s Blend)
Medium term
Sept- Dec 2005
CFI
Communication
Buying and Trading
At 80% target volume attained
Medium term
2007
CFI
Project Funds
Activities Planning
Target Output Qty. 1 Action Plan
Phasing-out of Pre-schools 2 pre-schools
Quality
Time Frame
In-Charge
Attainable
Resources
August 2005 CFI BOD, TESDA Acceptable terms July 2005 – CFI May 2006
Funds
None
CFI & Therese H/S
None
Signing of MOA with St. Therese H/S
1 MOA signed
Acceptable terms July 2005 – May 2006
Review / Reformulation of Adult Education modules
1 standard module developed
Adult Literacy Program
450 IPs
Appropriate, July 2005 – CFI staff, attuned to May 2006 teachers, indigenous DepEd culture Can read & write, 2006-2010 CFI staff and learned spiritual, teachers cultural, and social values
TNA
At least 3 skills training identified; ex. Food processing, farming tech., etc.
Understandable & measurable
2006-2010
CFI staff, Questionnaire TESDA & other agencies
IEC on Environmental Management
15-20 IP leaders informed
Appropriate & understandable
July 2005
CFI, NCIP, MILALITTRA, & DENR
Funds, resource persons
Tribal Leaders’ Consultation
15-20 IP leaders consulted
participative
Aug 2005
CFI, NCIP, & MILALITTRA
Funds, resource persons
Supplies
Rooms, teachers, teaching materials
Drafting of ADSDPP
Narrative Summary
Objectively Verifiable Indicators (OVI)
Means of Verification
Assumptions & Risks
Goal Poverty reduction of IPs 60% HH poverty NSO census of 2010; reduction by year 2010 NEDA Report Objectives: •Enterprise Development 1,000 HH involved in CFI Annual Report •Capability-Building livelihood activities MILALITTRA LGU Annual Performance representation in the Report MDC by 2007 Actual implementation CFI Report / MILALITTRA of ADSDPP by year Report to NCIP Output: •Enterprise Development 2008 • reduction of poverty 60% increased family Municipal Treasurer’s incidence income Report • increased productivity • Capability-Building conceptualized by NCIP report • conceptualization 2005; implemented by LGU annual performance and implementation 2006 report of ADSDPP 10% increase in LGU annual performance • increased literacy literacy rate report rate 10% reduction in crime •improved peace and rate
ADSDPP completed and implemented Funds accessed Training conducted
Funds are accessed from funding agency Training conducted
Narrative Summary Activities
Objectively Verifiable Indicators (OVI)
Means of Verification
Assumptions & Risks
EMTERPRISE DEVELOPMENT Planning
One (1) year plan drafted by July 2005
CFI Plan of Action
Sourcing of funds
1 Project funded by January 2006
Identification of coffee areas for rehabilitation
1,000 hectares identified by 2005
Memomorandum of Collaboration with Agreement with funding concerned agencies agency and business sector established Report of Project Director
Lending of Initial capital 1,000 farmers entered into MOA through MILALITTRA by 2006 Monitoring 1,000 hectares plantation monitored by 2010 Establishment of trading At least 2 partners partners identified (Figaro, Monk’s Blend) by 2005 Buying and Trading 80% target volume of sales attained by 2007
CFI Annual Report Report of Project Director MOA with Figaro and Monk’s Blend CFI Sales Report
Funds are accessed from funding agency
Narrative Summary
Objectively Verifiable Indicators (OVI)
Means of Verification
Assumptions & Risks
Activities CAPABILITY BUILDING Planning 1 Action Plan drafted Action Plan document by August 2005 Phasing-out of Pre2 pre-schools phased- CFI Annual Report schools out by May 2006 Signing of MOA with St. 1 MOA signed by May MOA with St. Therese Therese H/S 2006 Review / Reformulation 1 standard module Written curriculum of Adult Education developed by May approved by DepEd modules 2006 IPs trained by CFI Annual Report Adult Literacy Program 450 TNA 2010 At least 3 skills training CFI Annual Report and identified; ex. Food DepEd Promotion Report processing, farming tech., etc.; by 2010 IEC on Environmental 15-20 IP leaders Evaluation Report on Management informed by July 2005 Seminar Workshop Tribal Leaders’ 15-20 IP leaders ADSDPP Report / NCIP Consultation consulted by August Report 2005 Precondition Cartwheel adopts this management plan Collaboration established with
How stakeholders are affected by the main problem? Stakeholder
How is the stakeholder affected by the problem?
Capacity / Motivation to participate in addressing the problem Fund sourcing
Relationship with other stakeholders
1. LGU
Potential income is not realized
Give directions to other stakeholder
2. BLGU
Potential income is not realized
Provide counterpart
Sympathetic with the households and can be source of information
3. RHU
Additional workload
Right agency to address the problem
Close coordination with the barangay
4. DAF
Additional workload
Responsible agency for farming technology
Supervise and monitor the beneficiaries
5. Households Directly and most affected
Interest and willingness to participate in the program
Dependent on government agencies and dependent only on available resources
6. HKI
Willing to address the problem
Maybe able to provide assistance to the program
Coordinate with the LGU and other stakeholders
7. Other donors
Willing to address the problem
Maybe able to provide assistance to the program
Coordinate with the LGU and other stakeholders
Expected effect of possible project interventions among stakeholders
Stakeholder
Stakeholder’s main objective
1. LGU
Address the problem
2. BLGU
Address the problem
3. RHU
Implement what is mandated by law
4. DAF 5. Households
Improve health condition
6. HKI
Help and assist project implementation
7. Other donors
Positive impact/benefits
Reduce the incidence of malnutrition among children ages 5 and below
Negative impact/costs
Slow realization of result
Net Impact
Long-term – weight improve, decrease morbidity rate, availability of sources of nutritious food