Lecture_no 8 And 12

  • Uploaded by: Shafiq Khan
  • 0
  • 0
  • December 2019
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Lecture_no 8 And 12 as PDF for free.

More details

  • Words: 1,824
  • Pages: 10
Lecture No-12 Hands-Out Questions and its solution. Some Important Formulas relating to labor cost. I have simplify/or re-write the formula in easy mode for your convenience, so whenever solve question from any reference book use that formulas. I hope so that solving of question would be very simple for you.

1. Basic salary = Actual hour worked x Rate per hour paid

2. Total/gross salary = Basic salary + Bonus

3. Halsay Premium Plan= (Bonus Calculation) = Time allowed – Time taken x Time rate (rate per hour) 2

4. Halsay-weir Premium Plan. = (Bonus Calculation) = Time allowed – Time taken x hourly paid rate x 33.336667% (That’s 33.33667% x is according to formula)

5. Rowan Premium bonus Plan = Time allowed – Actual time taken x 100% Time allowed

Example of solving this formula intention needed Wage rate per hour Time allowed for the job Time taken

Rs.1.50 16 hours 12 hours

= Time allowed – Actual time taken x 100 Time allowed = 16- 12 = 4 hours = 4 x 100 = 25% Time allowed 16 = Basic wages 12 x 1.50 = 18 Bonus 18@ 25% = 4.50 Total wages = 22.5

Alternate Rowan Plan Method: You may calculate Bonus according Rowan Plan Method, You may use that formula to calculate Rowan Plan Time taken x Time allowed

Time saved x rate per hour.

Basic salary = 12 x 1.50 = Bonus = 12 x 4(16-12) x 1.50 = 16

18 4.50 22.5

Answer to Question no 1 to 5

Answer no-1 Basic salary = Actual hour worked x Rate per hour paid Halsay Premium Plan= (Bonus Calculation) Employee A =

Time allowed – Actual time taken x hourly rate 2 Rs. Bonus = 70 – 50 x 7 = 70 2 Basic Pay = 50 x 7 = 350 Total Pay 420

Employee B = Time allowed – Actual time taken x hourly rate 2 Rs. Bonus = 60 – 48 x 8 = 48 2 Basic Pay = 48 x 8 = 384 Total Pay 432

Employee C =

Time allowed – Actual time taken x hourly rate 2 Rs. Bonus = 52.5 – 46 x 10 = 32.5 2 Basic Pay = 46 x 10 = 460 Total Pay 492.50

Calculation: Employee A Revised Time allowed for 200 units = (200 x 35/100) = 70 hours If we are intending to produced 200 units how much time will be taken Employee B Revised Time allowed for 150 units = (150 x 40/100) = 60 hours If we are intending to produced 150 units how much time will be taken Employee C Revised Time allowed for 125 units = (125 x 42/100) = 52.5 hours If we are intending to produced 125 units how much time will be taken

Halsay-weir Premium Plan. = (Bonus Calculation) Time allowed – Time taken x hourly paid rate x 33.336667% Employee A Bonus Calculation = 70 – 50 x 7 x 33.336667% = 46.67 Basic salary = 50 x7 = = 350 Total Pay = 397. Employee B Bonus Calculation = 60 – 48 x 8 x 33.336667% = 32 Basic salary = 48 x8 = = 384 Total Pay = 416

Employee C Bonus Calculation = 52.5 – 46 x 10 x 33.336667% = 22 Basic salary = 46 x10 = = 460 Total Pay = 482

Rowan Premium bonus Plan Time taken x Time saved x rate per hour. Time allowed Employee A Basic salary = 50 x 7 = Bonus = 50 x 20(70-50) x 7 = 70

350 100 450

Employee B Basic salary = 48 x 8 = Bonus = 48 x 12(60-48) x 8= 60

384 76.8 460.80

Employee C Basic salary = 46 x 10 = Bonus = 46 x 6.5 (52.5-46) x 10 = 52.5

460 57 517.

Knotty point in this question In normal question straight away Time allowed not tell about for how much units and actual how much units produced. Simply given as you have seen in previous Halsay plan example in hands-out. Time taken and time allowed but that question is knotty. So we have to revise our time allowed due to change in production quantity. Calculation of actual time allowed because according to question time allowed to A 35 hour for per 100 units produced, now he produced 200 units in 50 hours, suppose if we allowed him time to make 200 units, instead of making 100 units then time would be 70 hours. Now same working we do revise for rest of employee B and C

Question No-2 1- Compute the rate and amount of bonus for the week. Standard Production = 480 @ 200= 96000 pieces Actual Production = Differences

117,600 pieces 21,600

21,600/96000 x 0.5 = Rs. 0.1125 per hour Total Group Bonus = 0.1125 @ 480 = Rs.54

2- Employee A Total Pay Basic 41 @ 0.35 =

14.35

Bonus 0.1125 @ 41 = 4.6125 Total Pay=

18.9625

Employee B Total Pay. Basic 44 @ 0.30 = 13.2 Bonus 0.1125@ 44 = 4.95 Total Pay =

18.15

Question -03 Employee A Piece work (with guaranteed hourly rates) Actual production x piece rate. 200 x 0.12 = Rs. 24 Guarantee hourly rate Actual hours x rate 40 x 0.60 = Rs 24 Total Piece work (with guaranteed hourly rates) = Rs.48

Hourly rate: Actual hours x rate 40 x 0.60 = Rs.24

Bonus system (under which the employee receives 50% of time savings).

Calculation of time allowed Time allowed 23 hours for 100 units but actual production is 200 units so time allowed would recalculate 23/100 x 200 =46 hours. 32/100 x 125 = 40hours, 38/100 x 150= 57 hours Bonus = Time allowed – Time taken x hourly rate 2 46 – 40/2 x 0.60= Rs.1.8

Employee B Piece work (with guaranteed hourly rates) Actual production x piece rate. 125 x 0.20 = Rs. 25 Guarantee hourly rate Actual hours x rate 42 x 0.75 = Rs 31.5 Total Piece work (with guaranteed hourly rates) = Rs.56.5

Hourly rate: Actual hours x rate 42 x 0.75 = Rs.31.5

Bonus system (under which the employee receives 50% of time savings). Calculation of time allowed Time allowed 23 hours for 100 units but actual production is 200 units so time allowed would recalculate 23/100 x 200 =46 hours. 32/100 x 125 = 40hours, 38/100 x 150= 57 hours

Bonus = Time allowed – Time taken x hourly rate 2 40 – 42/2 x 0.75= Rs.0 Not entitled for bonus because hour taken more then hour allowed.

Employee C Piece work (with guaranteed hourly rates) Actual production x piece rate. 150 x 0.15 = Rs. 22.5 Guarantee hourly rate Actual hours x rate 39 x 0.50 = Rs 19.5 Total Piece work (with guaranteed hourly rates) = Rs.42

Hourly rate: Actual hours x rate 39 x 0.50 = Rs.19.5

Bonus system (under which the employee receives 50% of time savings). Calculation of time allowed Time allowed 23 hours for 100 units but actual production is 200 units so time allowed would recalculate 23/100 x 200 =46 hours. 32/100 x 125 = 40hours, 38/100 x 150= 57 hours

Bonus = Time allowed – Time taken x hourly rate 2 57 – 39/2 x 0.50= Rs.4.5

Question No 4 Data is not available, something missing in hands-out. I will offer you another Question Question no -05 Commission Rs 20,000 @ 5% = 1000 15,000@ 7.5% = 1125 Earned commission = 2125 Deductions 1500 + 2500 = 4000 4000@ 5% =

200 = 200

Net commission = 1925

Lecture No -08 (Solution file). Question no -01 Re-order level: Maximum consumption x Lead Time [maximum] 130 x 30=3900 units. Maximum stock level: Reorder level – (Minimum consumption x Lead time [minimum]) + EOQ 3900 – (60 x 25) + 5000 3900 – 1500 + 5000 = 7400 units Minimum stock level: Reorder level – (Average consumption x lead time [Average]) Average lead time = Maximum + Minimum 2 3900 – (400 x 25 + 30) 2 3900 – (400 x 27.5) 3900 – 11000 = 7100 units Danger stock level: Average consumption x Emergency lead time 400 x 25(If no emergency time given then minimum reorders period considered emergency lead time) 400 x 25=10,000 units

Question no -02 Maximum stock level: B Reorder level – (Minimum consumption x Lead time [minimum]) + EOQ 4750 – (700 x3) +5000=7650 units. Working Weekly production varies from 175 to 225 units, averaging 200 units. Working= minimum weekly production is 175 units x per unit of product required material use=4 (175 x 4= 700) RE ORDER QUANTITY CONSIDERED Economic order quantity. Minimum stock level: A Reorder level – (Average consumption x lead time [Average]) Average lead time = Maximum + Minimum 2 8,000 – (2000 x 2) 8000 – 4000= 4000 units. Working Weekly production varies from 175 to 225 units, averaging 200 units. Average production of unit x units x per unit of product required material use= 200 x 10= 2000 Average lead time is given. Re order level of C is already given = 2,000 Danger stock level: Average consumption x Emergency lead time 2000 x 1 =2000 Working Minimum delivery period would be considered emergency lead time.

Question no -03 Re-order level: A (material) Maximum consumption x Lead Time [maximum] 75 x 6 = 450 units. Re-order level: B (material) Maximum consumption x Lead Time [maximum] 75 x 4 = 300 units. Maximum stock level: A Reorder level – (Minimum consumption x Lead time [minimum]) + EOQ 450 – (25 x 4) + 400 =750 units. Maximum stock level: B Reorder level – (Minimum consumption x Lead time [minimum]) + EOQ 300 – (25 x 2) + 600 = 850 units. Minimum stock level: A Reorder level – (Average consumption x lead time [Average]) Average lead time = Maximum + Minimum 2 450 – (50 x 5) 450 – 250 = 200 units. Minimum stock level: B Reorder level – (Average consumption x lead time [Average]) Average lead time = Maximum + Minimum 2 300 – (50x 3) = 150 units. Danger stock level: A Average consumption x Emergency lead time 50 x 4 =200 units Danger stock level: B Average consumption x Emergency lead time 50 x 2 = 100 units.

Question no -04 Re-order level: Maximum consumption x Lead Time [maximum] 400 x 6 = 2400 units Maximum stock level: Reorder level – (Minimum consumption x Lead time [minimum]) + EOQ 2400 – (250 x 4) + 1500 = 2900 units Minimum stock level: Reorder level – (Average consumption x lead time [Average]) Average lead time = Maximum + Minimum 2 2400 – (30 x 5) = 2250 units. Danger stock level: Average consumption x Emergency lead time 30 x 4 minimum re order period considered emergency lead time.

Question no -05 Just skip that question. It is not up to the mark, I will give you another good question.

Related Documents

Lecture_no 8 And 12
December 2019 11
8-12
October 2019 9
8-12
May 2020 4
Waza2fy 12-8
May 2020 0
Haw 8 Oct. 12
June 2020 5

More Documents from ""

Lecture_no 8 And 12
December 2019 11
June 2020 17
Sutus Product Brochure
June 2020 17
02-bresenhams.txt
May 2020 9