HR COST DOWN ACTIVITY FOR FY 2008/2009 (An Example) No

Item / Activity

SectionPIC Jan-08 Feb-08 Mar-08 Apr-08 May-08 Jun-08 Jul-08 Aug-08 Sep-08 Oct-08 Nov-08 Dec-08 Jan-09 Feb-09

To reduce and minimize 15% cost of standard printing items, computer 1. supplies and stationery from the budgeted amount of FY2008/2009

Monitoring

Identify a root cause

Admin MFMN

Assigning section's PIC

Data collection

1st Quarter Report

Identify a root cause

To reduce telephone cost for the Company 2. less than 10% from budgeted amount of FY2008/2009

Data collection

Briefing to user

Data collection & information

To reduce immediate absent (focusing on 3. AWOL, EL and Late Coming) less than 2.75 % To reduce no of employees taken MC 4. less than 30% from total employee of the month To accomplish 80% of the plan training 5. program to be done on schedule To reduce staff turn over less than 2.0 % 6. from total number of employees

Identify a root HR

HR

RA/ NAN

RS/N AN

Data collection

Identify a root cause Data collection

Identify a root HR

MFMN /RA

Data collection

Identify a root HR

RA/ RS

Data collection

3rd Quarter Report

HOLD THE GAIN

Monitoring & follow-up

Briefing to PIC of Dept

Monitoring & follow-up 1st Quarter Report

SDC Installation Admin MFMN

2nd Quarter Report

Remarks

Full year report

3rd Quarter Report

2nd Quarter Report

Monitoring & follow-up

Annual budgeted for Computer supplier, standard printing items and stationery is RM110,633.60 @ RM9,219.46/month

Full year report

HOLD THE GAIN

Amount budgeted for telephone cost of FY2008/ 2009 is RM66,000/year @ RM5,500/ month

2nd quarter performance Review report on maintenance cost and cost3rd impact Quarter achievement Improvement & implementation HOLD THE GAIN

Monitoring & follow-up

Training on absenteeism 1st Quarter Report Assigning section's PIC

2nd Quarter Report

1st Quarter Report 1st Quarter Report Review induction course training syllabus

Full year report

HOLD THE GAIN

Monitoring & follow-up

Full year report

Monitoring & follow-up 2nd Quarter Report

1st Quarter Report

Assessment and updating ATP

3rd Quarter Report

Monitoring & follow-up 2nd Quarter Report

Review on ATP

HOLD THE GAIN

Monitoring & follow-up

3rd Quarter Report

Industrial norm for immediate absent is at 3.30%

Current rate is at 35%

Full year HOLD THE GAIN

Monitoring & follow-up Monitoring & follow-up 2nd Quarter Report

3rd Quarter Report

Monitoring & follow-up

Full year report HOLD THE GAIN

Current rate is at 2.0%

Related Documents

Hr Cost Down Activity
June 2020 5
Activity Cost Behavior.docx
November 2019 15
Activity Cost Behaviour.docx
November 2019 23
Down
May 2020 30
Down
October 2019 84