Hindustan Petroleum Corporation Ltd. (A Government of India Enterprise)

BAHADURGARH TIKRIKALAN PIPELINE PROJECT

BID DOCUMENT FOR CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE

TENDER NO.: 9000203-HD-10002 (05/51/23LK/HPCL/001(i)) Procurement under National Competitive Bidding Prepared and issued by: MECON Limited (A Government of India Enterprise), 15th Floor, North Tower, SCOPE Minar Laxmi nagar District centre, Delhi-110092

Hindustan Petroleum Corporation Ltd. (A Government of India Enterprise)

BAHADURGARH TIKRIKALAN PIPELINE PROJECT

BID DOCUMENT FOR CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE VOL I OF IV (COMMERCIAL)

TENDER NO.: 9000203-HD-10002 (05/51/23LK/HPCL/001(i)) This Document is issued to: ----------------------------------------------------------------------------------------------------------------------------------------------------Issued by: DGM (Contracts) MECON Limited (A Government of India Enterprise), 15th Floor, North Tower, SCOPE Minar Laxmi nagar District centre, Delhi-110092

TABLE OF CONTENTS I

Section 1

Notice Inviting Tender (NIT) – National Competitive Bidding Request For Quotation (RFQ) including Cut-out Slips

II

Section 2

Instructions to Bidders

III

Section 3

Special Conditions of Contract Annexures to SCC, Particular Job Specifications

IV

Section 4

General Terms and Conditions of Works Contract

V.

Section 5

Bid Form

VI

Section 6

Agreed Terms & Conditions – Questionnaire

VII

Section 7

VIII

Section 8

IX

Section 9

Proforma/Annexures/Various Bank Guarantee Formats

Health, Safety and Welfare Plan During Construction Technical Specifications Attached separately as Vol II of IV, III of IV & IV of IV

X

XI

Section 10

Price Schedule

Section 11

Completion Schedule

SECTION – 1 -

NOTICE INVITING TENDER ( NIT ) REQUEST FOR QUOTATION (RFQ)

NOTICE INVITING TENDER TENDER FOR CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE PROJECT PROJECT OWNER HINDUSTAN PETROLEUM CORPORATION LIMITED (HPCL) (A Govt. of India Enterprises) 2nd Floor, Gresham Assurance House, Fort Mumbai

EPCM CONSULTANT MECON Limited 15th Floor, SCOPE Minar Laxmi Nagar, District Centre Delhi – 110 081 Ph No.: 22041872/22447417 Fax No.: 011-2241214/22401203 Email: [email protected], [email protected]

Electronic digitally signed & sealed (encrypted) e-tender are invited under two bid system as per details given below:A: TENDER NO. 9000203-HD-10002 (05/51/23LK/HPCL/001 (i)) TENDER FOR CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8”DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE PROJECT, HPCL 1.

DETAILS OF BID DOCUMENT: A1 A2 A3 A4 A5

2.

On-line confirmation for bid participation by bidder

From 18.12.2009 (1400 hours ) to 18.01.2010 (1000 Hours )

Tender submission due date

Up to 18.01.2010 (1500 Hours)

Online Un priced Bid opening

From 1530 Hours on 18.01.2010

Tender document fee

NIL

EMD

Rs.26.4 lacs

Bids are to be submitted online only at site http://eproc.hpcl.co.in. Bids received in any other form shall not be accepted. For viewing details including EMD, LOCATIONS etc. Please visit our web site www.hindustanpetroleum.com and go to tender section by clicking the link “Tenders”. For on-line bidding, please visit website http://eproc.hpcl.co.in . Bids received in any other form shall not be accepted. For viewing details including EMD, Locations etc. Please visit our website www.hindustanpetroleum.com and go to tender section by clicking the link “Tenders”. For online bidding please visit website http://eproc.hpcl.co.in. click the link “Vendor Instruction Manual” and follow the procedure given therein. HPCL reserves the right to extend price/ purchase preference as per prevailing guidelines of Government of India. DGM (Contracts) MECON Limited, Delhi

NOTICE INVITING TENDER (NIT) – NATIONAL COMPETITIVE BIDDING BID DOCUMENT NO9000203-HD-10002 (05/51/23LK/HPCL/001 (i)) TENDER FOR CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE PROJECT

MECON Limited, Delhi on behalf of M/s. Hindustan Petroleum Corporation Limited (HPCL), invites sealed bids under two bid system FOR CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8”DIA X 15 KM BAHADURGARH

(APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR TIKRIKALAN PIPELINE PROJECT, HPCL

1.0 Brief Project details M/s Hindustan Petroleum Corporation Limited proposed to lay 2 parallel pipeline from proposed dispatch station inside existing Bahadurgarh Terminal in Haryana to Tikarikalan, Delhi Border).Three petroleum products namely ULSHSD, ULMS & SKO from existing storage tank will be transported through these pipelines. Both the pipeline i.e 8” x 15 km (approx) for transporting ULMS & 10” x 15 km (approx) for transporting ULSHSD / SKO will be laid in the same trench. 2.0

SCOPE OF WORK: In brief scope is given below : i)

Construction of Tap-off / Hook-up from existing product tanks namely, ULSHSD, ULMS & SKO.

ii)

Construction of aboveground interconnecting piping & manifold from Tap-off at existing product tanks to Despatch Terminal inside Bahadurgarh Terminal.

iii)

Laying of 10” NB & 8” NB x ~ 15.0 km (Approx.) underground pipeline from Bahadurgarh Despatch Terminal to Tikarikalan Receiving Terminal in common trench.

iv)

Installation of TCP & impressed current permanent Cathodic Protection System for the pipeline.

v)

Installation of Metering Facility, MOVs ,Scrapper Traps at HPCL’s Despatch Terminal at Bahadurgarh & Receiving Terminal at Tikarikalan.

vi)

Construction of Control Room Building (36 m x 16 m) at Receiving Terminal, Tikarikalan.

vii)

Construction of a Building ( 16 m x 12 m) adjacent existing control room & inter-connected at Despatch Terminal, Bahadurgarh

viii)

Construction of electrical MCC room and DG yard

ix)

Construction of Structural Piping Shed for Piping Station.

x)

Laying of 12 Fiber OFC in 40 mm HDPE Duct for SCADA & Telecommunication System and hook-up with the existing SCADA & Telecommunication System.

3.0

xi)

All associated Electrical & Instrumentation Works.

xii)

The job involves all activities of Mainline Laying including road, canal, river, railway crossings alongwith associated terminal works including installation of pumps & metering facility, Mechanical, Civil & Structural, Architecture, Electrical, Instrumentation, SCADA and Telecommunication works.

xiii)

Supply of all materials under scope of supply except the free issue items.

xiv)

Installation of Centrifugal Pumps (8 Nos.) at HPCL Despatch Terminal at Bahadurgarh.

BID QUALIFICATION CRITERIA

Bidder shall meet all of the following criteria 3.1

Financial: The minimum annual turnover achieved by the bidder as per their audited financial results in each of the three preceding financial/calendar years ending with 31-03-09. (2006, 2007 & 2008 for companies having financial year ending in December or 2006-07, 2007-08 & 2008-09 for companies having financial year ending other than December) shall be Rs.28.0 Crores.

3.2

Technical

3.2.1 Bidder should have carried out and completed all of the following, within last seven years reckoned from 30-11-09 i) Laying including testing and Pre-commissioning of buried Cross country hydrocarbon Pipeline (coated) of minimum 6” in diameter and minimum 10km length. AND ii) Installation, testing & commissioning of Station Piping and mechanical equipments in petrochemical or hydrocarbon installations with owner supplied material and or contractor supplied material. AND iii) Construction of RCC building directly or by engaging civil contractor. Contract should be in the name of bidder. 3.2.2 Bidder during the last seven years reckoned from 30-11-09, shall have carried out and completed similar work as under: a. Three similar completed works, each costing not less than Rs.6.56 Crores. OR b. Two similar completed works, each costing not less than Rs.8.2 Crores. OR c. One similar completed work costing not less than Rs.13.12 Crores

Note: Similar works shall mean Laying, testing & commissioning of cross country hydrocarbon pipeline OR Installation testing and commissioning of Station Piping works in oil/Petrochemical industry OR Composite works comprising of Mechanical, electrical & instrumentation works in hydrocarbon industry.

3.3

3.3.1

3.3.2

WHO CAN BID: Parties who are affiliates of one another can decide which Affiliate will make a bid. Only one affiliate may submit a bid. Two or more affiliates are not permitted to make separate bids directly or indirectly. If 2 or more affiliates submit a bid, then any one or all of them are liable for disqualification. However up to 3 affiliates may make a joint bid as a consortium, and in which case the conditions applicable to a consortium shall apply to them. “Affiliate” of a Party shall mean any company or legal entity which: (a)

Controls either directly or indirectly a Party, or

(b)

Which is controlled directly or indirectly by a Party; or

(c)

Is directly or indirectly controlled by a company, legal entity or partnership which directly or indirectly controls a Party. “Control” means actual control or ownership of at least a 50% voting or other controlling interest that gives the power to direct, or cause the direction of, the management and material, business decisions of the controlled entity.

Bids may be submitted by: (a)

A single person/ entity (called sole bidder);

(b)

A newly formed incorporated joint venture (JV) which has not completed 3 financial years from the date of commencement of business.

(c)

A consortium (including an unincorporated JV) having a maximum of 3 (three) members

(d)

An Indian arm of a foreign company.

Fulfilment of Eligibility criteria and certain additional conditions in respect of each of the above 4 types of bidders are stated below, respectively: (a) (b)

The sole bidder (including an incorporated JV which has completed 3 financial years after date of commencement of business) shall fulfil each eligibility criteria. In case the bidder is a newly formed and incorporated joint venture and which has not completed three financial years from the date of commencement of business, then either the said JV shall fulfill each eligibility criteria or any one constituent member/ promoter of such a JV shall fulfill each eligibility criteria. If the bid is received with the proposal that one constituent member/ promoter fulfils each eligibility criteria, then this member/promoter shall be clearly identified and he/it shall assume all obligations under the contract and provide such comfort letter/guarantees as may be required by HPCL. The guarantees shall cover inter alia the commitment of the member/ promoter to complete the entire work in all respects and in a timely fashion, being bound by all the obligations under the

(c)

contract, an undertaking to provide all necessary technical and financial support to the JV to ensure completion of the contract when awarded, an undertaking not to withdraw from the JV till completion of the work, etc. In case the bidder(s) is/are a consortium (including an unincorporated JV), then the following conditions shall apply: 1. 2. 3.

4. 5. 6. 7.

8.

9.

No change in project plans, timetables or pricing will be permitted as a consequence of any withdrawal or failure to perform by a consortium member;

10.

No consortium member shall hold less than 25% stake in a consortium; Entities which are affiliates of one another are allowed to bid either as a sole bidder or as a consortium only; Any person or entity can bid either singly or as a member of only one consortium.

11. 12. (d)

Each member in a consortium may only be a legal entity and not an individual person. The Bid shall specifically identify and describe each member of the consortium; The consortium member descriptions shall indicate what type of legal entity the member is and its jurisdiction of incorporation (or of establishment as a legal entity other than as a corporation) and provide evidence by a copy of the articles of incorporation (or equivalent documents); One participant member of the consortium shall be identified as the “Prime member” and contracting entity for the consortium; This prime member shall be solely responsible for all aspects of the Bid/ Proposal including the execution of all tasks and performance of all consortium obligations; The prime member shall fulfill each eligibility criteria; A commitment shall be given from each of the consortium members in the form of a letter signed by a duly authorized officer clearly identifying the role of the member in the Bid and the member’s commitment to perform all relevant tasks and obligations in support of the Prime/lead member of the Consortium and a commitment not to withdraw from the consortium; No change shall be permitted in the number, nature or share holding pattern of the Consortium members after pre-qualification, without the prior written permission of the HPCL.

In case the bidder is an Indian arm (subsidiary, authorized agent, branch office or affiliate) of a foreign bidder, then the foreign bidder shall have to fulfill each eligibility criteria. If such foreign company desires that the contract be entered into with the Indian arm, then a proper back to back continuing (parent company) guarantee shall be provided by the foreign company clearly stating that in case of any failure of any supply or performance of the equipment, machinery, material or plant or completion of the work in all respects and as per the warranties/ guarantees that may have been given, then the foreign company shall assume all obligations under the contract. Towards this purpose, it shall provide such comfort letter/guarantees as may be required by HPCL. The guarantees shall cover inter alia the commitment of the foreign company to complete the entire work in all respects and in a

timely fashion, being bound by all the obligations undertaking to provide all necessary technical and Indian arm or to render the same themselves so as the contract when awarded, an undertaking not contract till completion of the work, etc.

under the contract, an financial support to the to ensure completion of to withdraw from the

4.0

Bid Security (Earnest Money Deposit – EMD)

4.1

AS STATED ABOVE.

5.0

COMPLETION SCHEDULE:

5.1

The entire work shall be completed as per completion schedule provided in Bid Document.

6.0 6.1

GENERAL: No extension in the bid due date shall be considered on account of delay in receipt of bid document by mail.

6.2

Bidder can download the Bid Document http://www.hindustanpetroleum.com or (www.meconlimited.co.in). However, the Bids have to Procurement site of HPCL only. Bid submitted in any accepted.

6.3

HPCL / MECON will not be responsible for cost incurred in preparation and delivery of bids, regardless of the conduct of outcome of the bidding process.

6.4

HPCL / MECON reserve the right to reject any or all the bids received at its discretion without assigning any reason whatsoever.

6.5

Bids received after stipulated due date and time, due to any reasons whatsoever including postal delays, will not be considered.

6.6

HPCL / MECON will follow purchase and price preference policies as per prevailing guidelines of Government of India.

6.7

EMD (original instrument: DD/Pay order/ Banker’s Cheque or Bank Guarantee) should be kept in separate envelope (superscribed with tender number, job & due date) and should be deposited by tender due date / time, in the tender box provided in the office at MECON, Delhi at the address provided above. While submitting the bid on-line, bidders would be required to upload the scanned copy of EMD instrument (DD / pay order / banker’s cheque or bank guarantee) or EMD exemption document ( self declaration in case of Public sector undertaking or copy of valid registration certificate in case of units registered with NSIC) at the place provided for the same.

from HPCL’s Website MECON’s website be submitted online in eother form would not be

Offer received without requisite EMD as explained above shall be rejected. For submitting the bid on-line it would be mandatory for bidders to obtain digital certificate (which will enable data encryption as well as digital signing). For information regarding digital certificate, bidders may visit http://www.cca.gov.in. For submitting the bid online, bidders are advised to follow the step by step procedure given under the link “Vendor Instruction Manual” at website http://eproc.hpcl.co.in. In case bidders are unable to access the site http://eproc.hpcl.co.in they may contact at Phone: (022) 32444300, or 9987715722 (Ms.

Soumya) at Mumbai on all working days during office hours. The on-line bidding would comprise broadly following steps – • Enrolment by vendor at http://eproc.hpcl.co.in (can be done without digital certificate) by clicking the link “Supplier Registration”. • The system generated challenge phrase will be sent to vendor at e-mail address provided by him during enrolment. • The vendor would be required to login at http://eproc.hpcl.co.in with this challenge phrase along with his user id & password. The vendor has to complete 2 page registration forms. • As soon as vendor fills two page registration forms, he should put a request letter on letterhead (giving tender number) to HPCL for approving his enrolment. The request may be sent through fax at , 022-22642352 or by e-mail to [email protected] • After enrolment, vendor would be required to login and register his digital certificate (to be obtained by vendor) at website. • After registering digital certificate vendor can participate in the public tender. • The vendors who are already enrolled at website: http://eproc.hpcl.co.in need not to enrol again and vendors who have already got valid digital certificate (enabling data encryption as well as digital signing) are not required to procure another digital certificate. v)

vi)

vii) viii) ix)

x)

HPCL will not be responsible for the cost incurred in preparation and submission of bids including the cost of digital certificate, regardless of the conduct of outcome of the biding process. HPCL shall not be responsible for any expenses incurred by bidders in connection with the preparation & submission of their bids, site visit and other expenses incurred during bidding process. Fax/e-mail bids shall not be accepted. HPCL reserves the right to accept or reject any one or all the tenders without assigning any reason. The evaluation of this tender is lowest delivered cost basis. HPCL shall not be bound to accept the lowest tender and reserves right to accept any or more tenders in part. Decision of HPCL in this connection shall be final. Hindustan Petroleum Corporation Ltd (HPCL) has developed the “Grievance Redressal Mechanism" to deal with references / grievances if any that is received from parties who participated/ intends to participate in the Corporation Tenders. The details of the same are available on this website. Completed Tenders in all respect should be submitted on-line at website http://eproc.hpcl.co.in by the tender due date/ time. Unpriced (Technical) bids shall be opened on-line and participating bidders can view / witness the same on-line by logging in at website http://eproc.hpcl.co.in. Bidders would not be allowed to submit their bid after stipulated tender due date and time. For details, please refer “INSTRUCTION TO BIDDERS”. HPCL will follow the purchase preference and price preference policy as per prevalent guidelines of Govt. of India.

REQUEST FOR QUOTATION RFQ.No. 9000203-HD-10002 (05/51/23LK/HPCL/001(i)) To:

Owner Project

Date: 18.12.2009

HINDUSTAN PETROLEUM CORPORATION LIMITED BAHADURGARH TIKRIKALAN PIPELINE PROJECT

Item

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8”DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES

Bid Due Date Unpriced Bid Opening

18.01.2010, UPTO 1500 HRS (IST) ONLINE 18.01.2010 at 1530 hrs

Pre-bid conference

At 11.00 hrs on 29.12.2010 at MECON, Delhi.

Priced Bid Opening

It will be e-tender opening – Date &Time will be as per the calender

Gentlemen, MECON Limited on behalf of HPCL invites you to submit bid under national competitive bidding for the above work in complete accordance with the Bid Documents / Attachments. IMPORTANT NOTE : BIDDERS ARE REQUESTED TO NOTE THAT ORIGINAL BID SECURITY (EMD AMOUNT) SHOULD PHYSICALLY REACH US AT BELOW MENTIONED ADDRESS BEFORE DUE DATE & TIME OF TENDER: DGM (CONTRACTS), MECON Limited, 15th Floor, North Tower, Scope Minar, Laxmi Nagar District centre, Delhi – 110092. Tel: 0091–11– 22401129; Fax: 011-22041214/22401203 IF ORIGINAL BID SECURITY (EMD AMOUNT) DOES NOT REACH OUR OFFICE BEFORE DUE DATE & TIME OF TENDER, BIDDERS OFFER WILL BE OUTRIGHTLY REJECTED. 1.0

FAX/Telex/Telegraphic bids/ E-Mail bids shall be rejected.

2.0

The work order/Purchase order will be issued by the Owner.

3.0

Owner reserves the right to allow Price Preference to Domestic Bidders and Purchase Preference to Public Undertakings as admissible under the prevailing policy.

4.0

HPCL/ MECON reserve the right to reject any or all the bids.

IMPORTANT: 1. 2.

No correspondence through Representative firm will be entertained. Please specify Tender Number in all your correspondence. .

THIS IS NOT AN ORDER

Yours faithfully,

for and on behalf of Hindustan Petroleum Corporation Limited DGM (Contracts) MECON Limited, Delhi

IMPORTANT: Please specify Bid Document Number in all your correspondence.

E – TENDER TERMS / INSTRUCTIONS TO BIDDERS

1) This is only a Tender Enquiry and not an order. 2) The tender should be submitted online at website http://eproc.hpcl.co.in only, by the due date and time, as specified in the tender. Late / delayed tenders submitted on line after the due date and time, for whatsoever reasons will not be considered. The Server Date & Time as appearing on the HPCL website (http://eproc.hpcl.co.in) shall only be considered for the cut-off date and time for receipt of tenders. Offers sent through post, telegram, fax, telex, e-mail, courier will not be considered. 3) Partially completed / incomplete tenders shall not be considered. 4) All communication regarding the tender including queries, if any, and submission of offers shall be done online within the e-Procurement system at website http://eproc.hpcl.co.in 5) Two Bid System Bidders are required to submit offer in Two parts, namely “Unpriced” & “Priced”. 6) Validity Quoted prices shall be valid for a period of 120 days from the due date / extended due date for the placement of order. 7) Bidders shall be required to arrange all resources, including Digital IDs and Internet Connections at their own cost, for participating in online tenders at HPCL e-Procurement site http://eproc.hpcl.co.in. 8) HPCL shall not be responsible for any delays reasons whatsoever in receiving as well as submitting offers, including connectivity issues. HPCL shall not be responsible for any postal or other delays in submitting EMD / tender cost wherever applicable. 9) HPCL will not be responsible for the cost incurred in preparation and submission of bids including the cost of digital certificate, regardless of the conduct of outcome of the biding process.

10)

EMD (EARNEST MONEY DEPOSIT)

!"

# $ ( *

! ) +

* .

(

*

,- $

/

$

%& '

#

% )

*

%

$

0' #

(

"

1

%

.

#

"# $ % & ' (&) *& $+ (,( + "$ *-+ $ ( +&) * )&()& +")$ + %& )*. $ # ))& -"& (/ / &) #)&+ * 0 "'122 223/ )

* *

!)

+ .

*

(

,- $ $ #

)1)

2)$3

! %

4

*

( !

#

( %

*

0'

.

) #

%

*

*

* 0' ( ,- $

# 0

# "

(

.

#

#

Units registered under NSIC are entitled to exemption from payment of earnest money, fee for tender documents and security deposit for performance up to specified limits of volumes. 55 0 )

(

4

4 %

#

/ (

# #

(

( (

*

" 56 Bidders are requested to quote all applicable taxes in % in the unpriced bid. The taxes mentioned by bidder in techno-commercial sheet on-line (service tax, works contract tax, any other tax etc.) will be calculated on the amount [ ( item quantity X item rate quoted by bidder)] except the education cess which would be calculated on service tax. For arriving at the total offer value of the bidder, the taxes quoted by him shall be added to ( item quantity X item rate quoted by bidder). In case bidder wants to apply particular tax on part of the contract value, bidder should mention the equivalent tax in % in technocommercial sheet / screen while quoting taxes on-line. For example if bidder wants to quote service tax as 12% on 40 % of ( item quantity X item rate), the bidder should mention the service tax as 4.8%. In case bidder quotes some / all taxes as 0%, it would be concluded that bidder’s quote is inclusive of all taxes applicable on tender due date / time or extended due date/ time.

The bidders not quoting taxes as above may mention applicability of taxes / item wise taxes under “EXCEPTION & DEVIATION STATEMENT (Bid Form)”. 13) Request for extension of tender submission due date, if any, received from bidders within 72 hours of tender submission due date / time, shall not be considered. 14) Clarifications sought/ queries received from bidders /vendors/parties on tender, within last seven days of bid due date, will not be entertained by HPCL. Please refer query end date / time in tender calendar after which no query posted by bidder shall be considered. However HPCL reserves

the right to respond the queries after cut off date / time mentioned in tender calendar. 15) Please note that queries related to scope of job, tender specifications, terms & conditions etc should be submitted on –line only (by logging in at http://eproc.hpcl.co.in) by the query end date / time specified in the tender consolidated view / NIT view/ tender calendar. The reply of queries sent by bidders/ messages issued by HPCL pertaining to tender shall be available on tender message borad. HPCL, at its sole discretion, may not entertain the queries sent by post / fax/ e-mail or through any other mode of communication. 16) Tender opening (unpriced bid as well as priced bid) will be done online at the time and dates specified in the tender. Vendors who have responded to the tender are requested to login at the specified date and time at HPCL eprocurement website (http://eproc.hpcl.co.in) for witnessing the tender opening (unpriced bid as well as priced bid in case of technically accepted vendors). 17) HPCL reserves the right to accept any tender in whole or in part or reject any or all tenders without assigning any reason. HPCL reserves right to accept any or more tenders in part. Decision of HPCL in this regard shall be final and binding on the bidder. 18) HPCL shall follow Purchase Preference / Price Preference as per prevailing guidelines of Government of India. 19)

Grievance Redressal Mechanism : Hindustan Petroleum Corporation Limited (HPCL) has developed a “Grievance Redressal Mechanism” to deal with references / grievances if any that are received from parties who participated / intend to participate in the Corporation Tenders. The details of the same are available on our website www.hindustanpetroleum.com.

SECTION – 2 INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO BIDDERS INDEX ARTICLE SR. NO.

DESCRIPTION

1.0

COST OF BIDDING

2.0

BID DOCUMENT

3.0

SEALING & MARKING OF BIDS

4.0

AMENDMENT OF BID DOCUMENT

5.0

LANGUAGE OF BID

6.0

DOCUMENTS COMPRISING THE BIDS

7.0

BID FORM AND PRICE SCHEDULE

8.0

FORMAT AND SIGNING OF BID

9.0

PREPARATION & SUBMISSION OF BIDS

10.0

BID DUE DATE

11.0

PERIOD OF VALIDITY OF BIDS

12.0

LATE BIDS

13.0

MODIFICATION & WITHDRAWAL OF BIDS

14.0

OPENING OF BIDS

15.0

EVALUATION OF BIDS

16.0

REJECTION CRITERIA

17.0

COMPARISON OF BIDS

18.0

CONTACTING THE OWNER / CONSULTANT

19.0

AWARD CRITERIA

20.0

OWNER’S / CONSULTANT’S RIGHT TO ACCEPT ANY BID AND TO REJECT ANY OR ALL BIDS

21.0

NOTIFICATION OF AWARD

22.0

ISSUE OF ORDER

23.0

PROJECT LOCATION

Instructions to Bidders 1.0

COST OF BIDDING:

1.1

The bidder shall bear all costs associated with the preparation and submission of the bid, and Hindustan Petroleum Corporation Limited (HPCL) / MECON Limited (MECON), will in no case, be responsible or liable for these costs, regardless of the conduct or outcome of the bidding process.

2.0

BID DOCUMENT

2.1

The bidder is expected to examine all instructions, forms, terms and specifications in the bid document. The Invitation for Bids (IFB) together all its attachments thereto, shall be considered to be read, understood and accepted by the bidder, unless deviations are specifically stated seriatim by the bidder. Failure to furnish all information required by the bid document or submission of a bid not substantially responsive to the bid document in every respect will be at bidder's risk and may result in the rejection of his bid.

2.2

The bidder’s scope of work as specified in the Technical Specification shall be in strict compliance with the scope detailed therein and in the bid document.

3.0

SEALING & MARKING OF BIDS:

3.7

Public Sector Enterprises and Firms registered with NSIC are exempted from submission of Bid Security. Public Sector Enterprises are requested to give a self declaration on their letter head to this effect, which should be submitted in a sealed envelope marked as Part -I as mentioned in Cl no. 3.1.1 above.

3.8

Bidders registered with NSIC are also requested to submit self declaration on their letter head to this effect alongwith a copy of their Valid Registration certificate, specifying limit of volume and other details which should be submitted in a separate sealed envelope no. 1 marked as Part – I as mentioned in Cl no. 3.1.1 above.

3.9

Bid Security strictly in the proforma attached with these documents shall be submitted in Original . Bids received without original bid security, shall not be opened for evaluation.

4.0

AMENDMENT OF BID DOCUMENT

4.1

At any time prior to the bid due date, the Owner/ Consultant may, for any reason, whether at its own initiative or in response to a clarification requested by a prospective Bidder, modify the Bid Document.

4.2

The amendment will be notified in writing to all prospective Bidders who have been issued the Bid Document and will be binding on them.

4.3

In order to afford prospective Bidder, reasonable time in which to take the amendment into account in preparing their bids, the Owner/ Consultant may, at its discretion, extend the bid due date.

5.0

LANGUAGE OF BID

5.1

The bid prepared by the Bidder and all correspondence/ drawings and documents relating to the bid exchanged by Bidder and the Owner/ Consultant shall be written in ENGLISH language, provided that any printed literature furnished by the Bidder may be written in another language so long as accompanied by an ENGLISH translation, in which case, for the purpose of interpretation of the bid, the ENGLISH translation shall govern.

6.0

DOCUMENTS COMPRISING THE BIDS

6.1

The bid prepared by the Bidder shall comprise the following components: UNPRICED BID a.

Original Bid Security to be submitted in physical form. - Bidders are advised to instruct their banks not to post Bid Security directly to Owner as the same has to be forwarded to MECON Limited at their Delhi office..

FOLOWING MUST BE SUBMITTED ONLINE:b.

Documentary evidence establishing Bidder’s claim for meeting qualification criteria as stipulated in the Bid Document.

c.

Audited Annual Report of previous three financial years.

d.

Documentary evidence establishing Bidder’s eligibility to bid and that the work conform to the Bid Document.

e.

Price Schedule (with Price figures blanked) completed in accordance with the requirements specified in the bid document.

f.

Agreed Terms & Conditions (Section 6) duly filled-in.

g.

Declaration with the bid qualification criteria that bidder has not been banned or delisted by any Government or quasi Government agencies or PSU's as per Section-7 of the Bid Document.

h.

Bidder shall furnish the concurrent commitment and execution plan considering the concurrent commitments.

i.

Integrity Pact duly stamped and signed.

j.

One set of tender document duly stamped and signed on each page as a token of acceptance.

k.

For the Instrumentation Works the Contractor shall submit a MOU entered with Instrumentation party who have carried out instrumentation works of this magnitude in hydrocarbon industry during the last 7 years.

l.

The contractor who intends to carryout civil works through subcontractor must submit MOU entered with them. The civil contractor must have carried out RCC civil buildings works within the time frame during the last 7 years.

m.

Any other information/details/documents/data required as per Bid Document.

PRICED BID : Price Bid must be submitted online on HPCL website. 7.0

DEVIATION SHEET

NAME OF WORK : …………………………………. BIDDING DOCUMENT NO. : ………………………………. EXCEPTION AND DEVIATIONS STATEMENT Bidder shall list all the deviations in the following given format only. Bidder may stipulate exceptions and deviations to Bidding Document, if considered unavoidable as per the following format:

Sl. No.

Page No. of Tender Document

Clause No.

Subject

Deviations

The exceptions/deviations should be uploaded in e-proc site only, any exceptions/deviations brought out elsewhere in the Bid shall not be construed as valid. SIGNATURE OF BIDDER ____________________ NAME OF BIDDER ____________________

8.0

FORMAT AND SIGNING OF BID void

9.0

PREPARATION & SUBMISSION OF BIDS

9.1

Bids shall be submitted online at e-procurement site of HPCL. Owner/ consultant shall be not responsible for Bids submitted at any other office of Consultant or the Owner.

9.2

Documents mentioned in the Bid Document shall be submitted along with the bid by the Bidder.

9.3

Addenda/Corrigenda to the Bid Document, if issued, must be signed and submitted along with the bid.

9.4

Bidders are advised to submit bids based strictly on the terms & conditions and specifications contained in the Bid Document and not to stipulate any deviations.

9.5

Each Bidder shall submit only one bid. A Bidder who submits more than one bid alternative bids will be rejected.

10.0

BID DUE DATE AND TIME

10.1

Bids must be received online by the Consultant/HPCL as specified in the Notice for Bids (IFB) not later than the date and time specified in the Bid Document.

10.2

The Consultant may, at its discretion, on giving reasonable notice by letter/fax/email, or any written communication to all prospective Bidders who have been issued the bid documents, extend the bid due date, in which case all rights and obligations of the Owner/ Consultant and the Bidders, previously subject to the bid due date, shall thereafter be subject to the new bid due date as extended.

11.0

PERIOD OF VALIDITY OF BIDS

11.1

Bids shall be kept valid for 120 days from the final bid due date. A bid valid for a shorter period shall be considered as non-responsive and rejected by the Owner/Consultant. The Bidder shall not be entitled during the said period of 120 days, without the consent in writing of the Owner/Consultant to revoke or cancel its bid or to vary the bid given or any term thereof. In case of Bidder revoking or canceling its bid without the consent of the Owner in writing, the Owner shall forfeit the Bid Security furnished by Bidder.

11.2

Notwithstanding above, the Owner/Consultant may solicit the Bidder’s consent to an extension of the period of bid validity. The request and the responses thereto shall be made in writing. The bid security shall also be accordingly extended.

12.0

LATE BIDS

12.1

Any bid received by the Consultant after the bid due date and time prescribed in IFB will not be opened and shall be rejected.

12.2

Telex/ Telegraphic/ Telefax/ E-mail offers will not be considered and shall be rejected.

13.0

MODIFICATION AND WITHDRAWAL OF BIDS No bid shall be allowed to be withdrawn in the interval between the deadline for submission of bids and the expiration of the period of bid validity specified by the Bidder. Withdrawal of a bid during this interval shall result in the forfeiture of Bidder’s bid security.

14.0

OPENING OF BIDS

14.1

Bids will be opened through e-procurement site of HPCL.

14.2

BID SECURITY AND UNPRICED BID (PART-I):

14.2.1 On the day and time of bid opening, Unpriced Bid (envelope- 1) shall be opened Online on HPCL’s e-procurement website. 14.3

PRICED BID OPENING (PART-II):

14.3.1 Only those bids who meet the qualification criteria, and are technically/commercially acceptable shall be qualified for opening of Priced bid (Envelope 2) at a later date, informed in advance. 15.0

EVALUATION OF BIDS

15.1

The Consultant will examine the bids to determine whether they are complete, whether any computational errors have been made, whether the documents have been properly signed and whether the bids are generally in order.

15.2

The bids without requisite Bid Security and/or not in the prescribed proforma will not be considered and bids of such Bidder(s) shall be rejected.

15.3

Qualification of Bidder: The experience details and financial, technical capabilities of the Bidders shall be examined to determine whether the Bidder(s) meet the Qualification Criteria mentioned in the Notice Inviting Tender (NIT).

15.4

To assist in the examination, evaluation and comparison of Unpriced bids, the owner/Consultant may, at its discretion, ask the Bidder clarifications on the bid. The request for such clarifications and the response thereto shall be in writing.

15.5

Prior to the evaluation and comparison of the bid, the Owner/Consultant will determine the substantial responsiveness of each bid to the bidding documents. For the purpose of this Article, a substantially responsive bid is one, which conforms to all the terms and conditions of the bidding document without material deviations or reservations. The Owner’s/Consultant’s determination of a bid responsiveness is to be based on the contents of the bid itself without recourse to the extrinsic evidence.

15.6

A bid determined as substantially non-responsive will be rejected by the Owner/Consultant and shall not subsequently be allowed by the Owner/Consultant to be made responsive by the Bidder by correction of the non-conformity.

16.0

REJECTION CRITERIA Bidder’s Bid shall be considered non-responsive and rejected, if deviations are taken to the under mentioned provisions of Bid Documents by the Bidder: Sl.NO.

CLAUSE

REFERENCE DOCUMENT

i) ii) iii)

Bid Security Security Deposit Period of validity of bids shorter than specified Force Majeure Defect Liability Period

Clause No 4.0 of NIT Clause No 4.b of GCC

iv) v)

Clause No 11.0 of ITB Clause No 13 of GCC Clause No 5.n of GCC

vi) vii) ix) xii)

Statutory Levies Payment terms sought by Bidder Liquidated Damages for delay in completion

Clause No 7.d of GCC Clause No 37 of SCC Clause No 10.0 of GCC

Integrity Pact duly stamped & signed to be submitted along with offer

As per Section 7

Definitions: SCC : SPECIAL CONDITIONS OF CONTRACT ITB : INSTRUCTIONS TO BIDDERS GCC : GENERAL CONDITIONS CONTRACT 16.1

Bids that do not meet the qualification criteria as specified in the bid document shall be rejected.

16.2

A bid with incomplete scope of work and/or which does not meet the technical requirements as specified in the bid document shall be considered as nonresponsive and rejected.

16.3

Price must be furnished in the Price Schedule format enclosed and shall be strictly based on the terms specified under "Bid Prices" & "Taxes & Duties" specified in the bid document. Non-compliance of this requirement shall make the bid liable for rejection.

16.4

Conditional bids will be liable for rejection.

17.0

COMPARISON OF BIDS

17.1

The Consultant will evaluate and compare bids previously determined to be substantially responsive pursuant to the provisions of the bid document.

17.2

Arithmetical errors will be rectified on the following basis:If there is a discrepancy between the unit price and the total price that is obtained by multiplying the unit price and quantity, the unit price shall prevail and the total price will be corrected. If there is a discrepancy between the total amount and the sum of total prices, the sum of the total prices shall prevail and the total bid amount will be corrected.

17.3

PURCHASE / PRICE PREFERENCE

17.3.1 Owner/Consultant reserves the right to allow purchase preference to Public Sector Undertaking / Enterprises and Purchase / Price preference to SSI units registered with NSIC as admissible under the existing policies of the Government of India. 17.3.2 Situations where preference not granted to Small Scale Units: To make the grant of price preference more meaningful, price preference should be

accorded on a tender to tender basis. The question of granting price preference will not arise in the following situations: 1.

Where the Small Scale Unit had succeeded in securing orders for same items, in competition (i.e. without price preference) with the large scale units during the preceding 12 months. For this purpose the SSI Unit will be required to give a declaration in writing in case they have obtained orders on the above lines.

2.

Where Small Scale Unit is lowest for some items without price preference and lowest for other items with price preference. (In such case, order for items where SSI is lowest with price preference will be placed only if SSI matches the rates with lowest delivered rates for those items).

3.

Where competition is amongst Small Scale Units alone.

4.

Where the items are exclusively reserved for purchase from the Small Scale Units.

5.

Where tenders are received from both Small Scale and Large Scale Units; and the lowest offer is from the Small Scale Unit and its capacity is more than sufficient to meet the requirement.

6.

Where the value of the tender exceeds the value limit given in the certificate produced by the SSI Unit or where the certificate does not cover the commodity tendered for.

18.

CONTACTING THE OWNER/ CONSULTANT

18.1

Subject to Article 15.4 above no Bidder shall contact the Owner/Consultant on any matter relating to its bid, from the time of bid opening to the time the Contract is awarded.

18.2

Any efforts by a Bidder to influence the Owner/Consultant in the Owner’s/ Consultant’s bid evaluation, bid comparison or contract award decisions may result in the rejection of the Bidder’s bid.

19.0

AWARD CRITERIA The Owner will award the Contract to the successful Bidder whose bid has been determined to be the lowest evaluated, responsive bid, provided further that the Bidder is determined to be qualified to satisfactorily perform the Contract.

20.0

OWNER’S/CONSULTANT’S RIGHT TO ACCEPT ANY BID AND TO REJECT ANY OR ALL BIDS

20.1

Owner/ Consultant reserves the right to accept or reject any bid, and to annul the bidding process and reject all bids, at any time prior to award of contract, without thereby incurring any liability to the affected Bidder or Bidders or; any obligations to inform the affected Bidder or Bidders of the ground for the Owner’s/Consultant’s action.

20.2

The submission of any bid connected with these documents and specifications shall constitute an agreement that the Bidder shall have no cause for action or claim, against the Owner for rejection of his bid. The Owner shall always be at liberty to reject or accept any bid or bids at his sole discretion and any such action will not be called into question and the Bidder shall have no claim in that regard against the Owner.

21.0

NOTIFICATION OF AWARD

21.1

Prior to the expiration of period of bid validity, the Owner/ Consultant will notify the successful Bidder in writing or by fax to be confirmed in writing, that his bid has been accepted. The Notification of Award will constitute the formation of the Contract.

21.2

Completion Period shall be counted from the date of notification of award (Letter/Fax of Intent).

22. 0 ISSUE OF ORDER 22.1

After the successful Bidder has been notified that his bid has been accepted, the Owner will send to such Bidder a detailed Order incorporating all the terms and conditions agreed between the parties.

22.2

Within 15 days of receipt of the detailed Order, the Bidder shall sign and return it to the Owner, in token of acceptance of the Order.

SECTION 3 SPECIAL CONDITIONS OF CONTRACT

GENERAL 1.1

Special Conditions of Contract (SCC) shall be read in conjunction with the General Conditions of Contract (GCC) also referred to as General Terms & Conditions of Contract, Schedule of Rates, specifications of work, drawings and any other document forming part of this Contract wherever the context so requires.

1.2

Not withstanding the sub-division of the document into these separate sections and volumes, every part of each shall be deemed to be supplementary of every other part and shall be read with and into the Contract so far as it may be practicable to do so.

1.3

Where any portion of the GCC is repugnant to or at variance with any provisions of the Special Conditions of Contract, then unless a different intention appears, the provision(s) of the Special Conditions of Contract shall be deemed to override the provision(s) of GCC only to the extent that such repugnancies or variations in the Special Conditions of Contract are not possible of being reconciled with the provisions of GCC.

1.4

Wherever it is stated in this Bidding Document that such and such a supply is to be affected or such and such a work is to be carried out, it shall be understood that the same shall be affected and /or carried out by the CONTRACTOR at his own cost, unless a different intention is specifically and expressly stated herein or otherwise explicit from the context. Contract Price shall be deemed to have included such cost.

1.5

The materials, design & workmanship shall satisfy the applicable relevant International / Indian Standards, the job specifications contained herein & codes referred to. Where the job specifications stipulate requirements in addition to those contained in the standard codes and specifications, these additional requirements shall also be satisfied. In the absence of any Standard / Specifications / Codes of practice for detailed specifications covering any part of the work covered in this bidding document, the instructions / directions of HPCL / MECON will be binding upon the CONTRACTOR.

1.6

In case of contradiction between relevant International / Indian standards, GCC, Special Conditions of Contract, Specifications, Drawings and Schedule of Rates, the

following shall prevail in order of precedence. i) ii) ii) iv) v) vi) vii) viii) ix) x) 1.7

Detailed Purchase Order along with Statement of Agreed Variations, if any, and its enclosures. Schedule of Rates with Quantities. Fax of Intent (FOI)/Letter of Intent (LOI) Scope of Work Technical Specifications Drawings Special Conditions of Contract General Conditions of Contract Instructions to Bidders Relevant Indian / International Standards/ Specifications.

SAFETY, FIRE FIGHTING AND SPECIFIC REQUIREMENTS OF HPCL / MECON CONTRACTOR shall supply Eight Nos IS Stamped DCP Fire Extinguishers and Eight

No.s Fire buckets with sand at SITE. These items can be taken back by the CONTRACTOR after completion of work at the respective sites. In case of damage to any of the above items, CONTRACTOR shall arrange for replacement/ repair within 48 hours. Sand shall also be maintained dry by the CONTRACTOR with fresh supply, whenever required. Work permit may not be issued by HPCL in the absence of above items. 1.7.2

Safety Helmets shall be provided to all the personnel employed by CONTRACTOR. Shoes and Gloves shall also be provided in adequate number by the CONTRACTOR.

1.7.3

Safety Belts and Harnesses shall be provided by the CONTRACTOR in adequate number for the workers working at heights

1.7.4

All Diesel driven equipment shall be provided with proper flame arrestors, Mufflers, etc as applicable.

1.7.5

Proper earthing shall be provided for all welding equipments and generators

2.

THE WORK

2.1

Scope of Work & Scope of Supply

2.1.1

The scope of work and Scope of Supply covered in this Contract will be as described in Scope of work for respective sections, Job Specifications, Standard Specifications, Drawings, and Schedule of Rates etc.

2.2

Time Schedule

2.2.1

It is described in detail elsewhere in the tender document.

2.2.2

Time is the essence of this Contract. The period of completion given includes the time required for mobilization as well as testing, rectifications, if any, retesting, demobilization and completion in all respects to the satisfaction of the HPCL / MECON.

2.2.3

A programme of execution of work will be prepared by the CONTRACTOR and the same will be reviewed and approved by HPCL / MECON. This programme will take into account the time of completion period of the Contract.

2.2.4

Monthly / weekly execution programme will be drawn up by the CONTRACTOR based on availability of materials, work fronts and the execution as referred to above. The CONTRACTOR shall scrupulously adhere to the Targets / Programmes by deploying adequate personnel, Construction Equipment, Tools and Tackles and also by Timely Supply of required materials coming within his scope of supply as per Contract. In all matters concerning the extent of target set out in the weekly / monthly programme and the degree of achievement, the decision of the HPCL / MECON will be final and binding upon the CONTRACTOR.

2.2.5

CONTRACTOR shall give every day category-wise labour and equipment deployment report along with the progress of work done on previous day in the Performa prescribed by the HPCL / MECON.

2.3

Measurement of Works

2.3.1

Mode of measurement will be as specified in Specifications or Schedule of Quantities.

2.4

Payment Office Payment will be released within 15 days of submission of duly certified Running Account Bills at Disbursement section at Mumbai after deduction of WCST(Works Contract Sales Tax) or VAT whichever is applicable, IT(lncome Tax) and any other statutory deduction as applicable from time to time, Any MRR(Materials Received Report- An internal document forwarded by HPCL Site in-Charge/ Engineer to Disbursement Section along with Contractor's Bill and duly certified measurement sheets for release of payment) Deductions, LD, etc. In case of Final Bill, Payment will be released within 45 days of submission of duly certified Final Bill along with all requisite documents, drawings, etc. Payment break up for various items covered in SOR/PRICED BID is as indicated as Appendix 1 to SCC. No further alteration is permitted in approved payment break up.

2.5

Temporary Works

2.5.1

All temporary works, enabling works, including dewatering of surface and Subsoil water, preparation and maintenance of temporary drains at the work site, preparation and maintenance of approaches to working areas, wherever required, for execution of the work, shall be the responsibility of the CONTRACTOR and all costs towards the same shall be deemed to have been included in the quoted prices.

2.6

Quality Assurance

2.6.1 Detailed quality assurance programme to be followed for the execution of Contract under various divisions of works will be mutually discussed and agreed to. 2.6.2

The CONTRACTOR shall establish, document and maintain an effective quality assurance system as outlined in the specifications and various codes and standards.

2.6.3

Quality Assurance System plans / procedures of the CONTRACTOR shall be furnished in the form of a QA manual. This document should cover details of the personnel responsible for the quality assurance, plans or procedures to be followed for quality.

2.6.4

The HPCL / MECON or their representative shall reserve the right to inspect/witness, review any or all stages of work at shop/site as deemed necessary for quality assurance and / or timely completion of the work.

2.6.5

In case HPCL / MECON feels that CONTRACTOR's Engineer(s)/ Supervisor are. Incompetent or insufficient, CONTRACTOR has to deploy other experienced Engineer(s)/ Supervisor as per site requirement and to the full satisfaction of HPCL / MECON.

2.6.6

Processing of bills for payment will be subject to compliance by the Contractor of the instruction given by HPCL / MECON.

2.7

Leads

2.7.1

For the various works, in case of contradiction, leads mentioned in the Schedule of Quantities shall prevail over those indicated in the Technical specifications.

2.8

Other Special Conditions of Contract

2.8.1

ROYALTY, INCOME TAX, SERVICE TAX AND PRICES Royalty

All royalties etc., as may be required for any Borrow Areas, including right of way etc., to be arranged by Contractor shall be deemed to have been included in the quoted prices. Income Tax Income Tax at the prevailing rate as applicable from time to time shall be deducted from Contractor’s Bills as per Income Tax Act and quoted rates shall be inclusive of this. Owner will issue the TDS(Tax Deduction at Source) Certificate. Firm Prices The contract price shall remain firm and fixed till the completion of work in all respects and no escalation in prices on any account shall be admissible to the Contractor. 2.8.2

Taxes, Duties, Octroi, Levies etc. The quoted prices shall be deemed to be inclusive of all taxes including Works Contract Sales Tax, Sales Tax, Service Tax, duties, octroi, levies, cess etc. and Contractor shall not be eligible for any compensation on these accounts. Any statutory variation / liability on account of taxes, duties, octroi, cess etc. shall also be to Contractor’s account. The Contractors shall note that in the state of Haryana they should comply to the provisions under BOCW Act 96, its central rule 98, BOCW cess Act 96 and Rules 98. As per the above acts 1% cost of construction is required to be paid for amending licence and this amount will be paid to Haryana Building and Construction worker’s welfare Board and the same will be recovered from the contractor. Contractor shall register this contract under 'Works Contract Service" as per sub clause (zzzza) of section 65(105) of the Finance Act.1994 as amended by Finance Act, 2007. Contractor shall exercise the option of payment of service tax either under "Works Contract (Composition Scheme for payment of service tax) Rules, 2007" or payment of service tax based on the Valuation under Rule 2A of the "Service tax (Determination of Value) Rules, 2006 ", whichever results in lower incidence of service tax to the Owner.

2.8.2. Bidders shall give the Undertaking that they are not on the Holiday list of HPCL. Any bidder found on Holiday list of HPCL will be rejected. 2.8.3. CONTRACTOR to specify the lay down area required for his working at site. HPCL has all the rights to finalize the area allocation and the same shall be binding on the CONTRACTOR. 2.8.4

Drilling of Bore well for construction waters shall be carried out by CONTRACTOR at

his own cost. Location of Bore Well identified within plot area by CONTRACTOR shall be acceptable to HPCL / MECON. Bore well should be retained after completion of work. Statutory approval for bore well drilling as necessary shall be in Contractor’s scope. 2.8.5. The successful bidder shall provide the methodology for mobilization of all the resources and also to provide job execution strategy to complete the job as per scope of this Tender well within the Time Schedule Stipulated. MECON and HPCL will review bidder strategy of job execution and on acceptance will enter into Memorandum Of Agreement (MOA) before issuing of the final Work Order to the successful bidder. 2.8.6. The following Insurances the contractor has to take while working in the site: 1.

The Contractor has agreed to abide bythe ESI act, 1948, he has to deduct the employees contribution, remit, file all the declarations, forms, maintain records etc.

2.

Inland transit insurance will be arranged by the contractor at his own cost.

3.

The Contractor has to take workman's compensation insurance. If the work is given to sub contractor, the sub contractor has to take the insurance. For employees not covered by the insurance taken by the sub contractor, the contractor has to take the insurance.

4.

Automobile Liability Insurance: The contractor has to take insurance to cover all risks for the vehicles plying.

5.

Fire Insurance: The Contractor within 2 weeks after award of the contract, as to insure the works, plant and equipment etc until the completion of the contract against loss or damage by accident, fire or any other cause with insurance company duly approved by HPCL / Consultant.

3.

ROYALTY

3.1

Royalty

3.1.1

All royalties etc., as may be required for any Borrow Areas, including right of way etc., to be arranged by Contractor shall be deemed to have been included in the quoted prices.

. 3.1.2

CONTRACTOR's quoted rates should include the royalty on different applicable items as per the prevailing State Government rates. Any increase in prevailing rate of royalty shall be borne by the CONTRACTOR at no extra cost to the HPCL / MECON.

4.

PROVIDENT FUND, LABOUR, LABOUR LAWS AND SITE REQUIREMENTS

4.1

Provident Funds

4.1.1

The CONTRACTOR shall strictly comply with the provisions of Employees Provident Fund Act and register himself with Regional Provident Fund Commissioner (RPFC) before commencing work. The CONTRACTOR shall deposit Employees and Employers

contributions to the RPFC every month. The CONTRACTOR shall furnish along with each Running bill, the challan / receipt for the payment made to the RPFC for the preceding month. The CONTRACTOR shall furnish the code number allotted by the RPFC Authority to the HPCL/MECON before commencing the work. 4.2

Labour License

4.2.1

Before starting of work, CONTRACTOR shall obtain a license from concerned authorities under the Contract Labour (Abolition and Regulation) Act 1970, and furnish copy of the same to HPCL / MECON.

4.3

Labour Relations

4.3.1

In case of labour unrest/labour dispute arising out of non-implementation of any law, the responsibility shall solely lie with the CONTRACTOR and he shall remove/resolve the same satisfactorily at his cost and risk.

4.3.2

The CONTRACTOR shall at all times take all reasonable precautions to prevent any unlawful, riotous or disorderly conduct by or amongst his staff and labour and to preserve peace and protection of persons and properly in the neighbourhood of the Works against such conduct.

4.4

Employment of Labour

4.4.1

The CONTRACTOR shall not recruit personnel of any category from among those who are already employed by other agencies working at site but shall make maximum use of local labour available.

4.5

House Keeping

4.5.1

It is the responsibility of the CONTRACTOR to maintain general cleanliness and proper housekeeping at work site. CONTRACTOR shall organize disposal of excavated earth /garbage/ rubbish/ scrape, electrode butts etc. on day to day basis to identified disposal areas/safe areas as per HPCL / MECON.

4.5.2

The CONTRACTOR shall dispose off the unserviceable materials, debris etc.,to the earmarked area within / outside the Plant premises as decided by the HPCL /MECON. No extra payment shall be paid on this account. Serviceable materials shall be stored in designate area separately after obtaining acknowledgement of HPCL Officer.

4.5.3

MECON Review/Approval of Drawings, Design and other documents submitted by CONTRACTOR

4.5.3.1 Mecon will normally require and utilize a maximum time frame of ten (10) working days from the date of Receipt for Review/Approval of Drawings, Design and other documents submitted by CONTRACTOR. Upon Review of the submitted documents, MECON may give their comments and ask for redesign/ resubmission after necessary rectifications/ modifications and the time frame of 10 working days will be applicable for same.

4.6

Protection of Existing Facilities

4.6.1

CONTRACTOR shall obtain all safety clearance (viz. Excavation, Hot/Cold work permit)

4.6.2

CONTRACTOR shall obtain plans and full details of all existing and planned underground services from HPCL / MECON and shall follow these plans closely at all times during the performance of work. CONTRACTOR shall be responsible for location and protection of all underground lines and structures at his own cost.

4.6.3

Despite all precautions, should any damage to any structure / utility etc. occur, the CONTRACTOR shall contact the HPCL / MECON / authority concerned and CONTRACTOR shall forthwith carry out repair at his expenses under the direction and to the satisfaction of HPCL / MECON and the HPCL / MECON/concerned authority.

4.6.4 CONTRACTOR shall take all precautions to ensure that no damage is caused to the existing pipelines, cables etc., during construction. Existing structures, existing Compound wall, Tiling and other items damaged / disturbed during construction shall be repaired and restored to their original condition by CONTRACTOR after completion of construction to the complete satisfaction of HPCL / MECON. 4.6.5

If required, CONTRACTOR shall in consultation with HPCL / MECON and the concerned authorities, take adequate measures for strengthening the existing electric poles, Cast iron pipes, sewer lines, GI Pipelines telephone poles etc in the proximity of proposed Construction works. CONTRACTOR shall take adequate protective measures to prevent damage to these facilities during construction.

4.6.6

CONTRACTOR shall have to adopt such method of construction as will be suitable for working in these areas using the limited space available and without causing any damage to these facilities. CONTRACTOR shall be deemed to have taken cognizance of all such constraints, etc. while working in this area and CONTRACTOR shall not be entitled to claim any extra at a later stage.

4.7

Work Front

4.7.1

The work involved under this Contract may include such works as have to be taken up and completed after other agencies have completed their jobs. The CONTRACTOR will be required and bound to take up and when the fronts are available for the same and no claim of any sort whatsoever shall be admissible to the CONTRACTOR on this account.

4.8

Site Facilities

4.8.1

The CONTRACTOR shall arrange for the following facilities at site, for workmen deployed/ engaged by him at his own: i) ii) iii) iv)

Arrangement for First Aid. Arrangement for clean & potable drinking water. A creche where 10 or more women workers are having children below the age of years. Any other facility/utility as may be required under the Contract as per the

existing legislation. v) Rest rooms / toilets for site staff / labour. 4.9

CONTRACTOR's Site Office and Stores

4.9.1

HPCL shall provide space only for CONTRACTOR's site office and stores and fabrication yard, if any at site. However, same shall be dismantled prior to submission of Final Bill.

4.9.2 The CONTRACTOR's Labour and Staff will be permitted to stay within the premises at designated locations identified by HPCL It is proposed that such labour camps shall be confined to 1 location. 4.9.3

The CONTRACTOR shall remove all temporary buildings / facilities etc., before leaving the site after completion of works in all respect.

4.9.4

The CONTRACTOR will be responsible for carry out the warehouse management & material control of his supplied items in accordance with approved warehousing & material control procedure, which is to be submitted by the CONTRACTOR during kickoff meeting.

4.10

Construction

4.10.1 Rules and Regulations CONTRACTOR shall observe in addition to Codes specified in respective specification, all national and local laws, ordinances, rules and regulations and requirements pertaining to the work and shall be responsible for extra costs arising from violations of the same. 5.

Procedures

5.1

CONTRACTOR shall prepare & submit all the plans, procedures & documents to HPCL/ MECON as specified in the contract.

5.2

Construction Execution plan CONTRACTOR shall submit Construction Execution Plan to HPCL/ MECON for review/approval pre award of Work Order, while providing the Project Execution Strategy. The Plan shall detail the execution methodology of the CONTRACTOR during construction phase of the PROJECT covering following aspects as minimum:

5.2.1

CONTRACTOR’S Construction Execution Plan shall include:

5.2.1.1 CONTRACTOR’S manpower and equipment deployment schedule on monthly basis, also to be provided pre award of Work Order, while providing the Project Execution Strategy. 5.2.1.2 Other plans of CONTRACTOR and procedures to be submitted at least four (4) weeks prior to start of respective activity at site include the following as a minimum: a. b.

Temporary facilities, etc. Monsoon counter measures and preparation

c. d.

Emergency Evacuation Procedure Storm Management Plan

5.3

Security

5.3.1

The CONTRACTOR shall arrange to obtain through the HPCL / MECON, well in advance, all necessary entry permits/gate passes for his staffs and labourers and entry and exit of his men and materials shall be subject to vigorous checking by the security staff.

5.4

Drawings and Documents

5.4.1

Drawings accompanying the Bidding Document are indicative of scope of work and issued for bidding purpose only. Purpose of these drawings is to enable the tenderers to make an offer in line with the requirements of the HPCL / MECON.

5.4.2

The CONTRACTOR as per scope of work shall carry out preparation of detailed and working drawings. Detailed construction layout drawings as needed shall be prepared by CONTRACTOR and got reviewed by HPCL / MECON before taking up the work.

5.5

Survey and Level/Setting out Work

5.5.1

The HPCL / MECON shall furnish the relevant existing grid point with Bench Mark on the land. It shall be CONTRACTOR's responsibility to shift the existing benchmark to his work site to set out the necessary control points and alignment of the various works. The CONTRACTOR shall have to employ efficient survey team for this purpose and the accuracy of such setting out works shall be the CONTRACTOR's sole responsibility.

5.5.2

The CONTRACTOR shall at his own expense provide all assistance, which the HPCL / MECON may require for checking the setting out of works.

5.5.3

The CONTRACTOR shall be entirely responsible for the horizontal and vertical alignment, the level and correctness of every part of the work and shall rectify any errors or imperfections therein. The CONTRACTOR at his own cost shall carry out such rectifications, when instructions are issued to his effect by the HPCL / MECON or his representative.

5.6

Checking of Levels

5.6.1

CONTRACTOR shall be responsible for checking levels / orientation / alignment of all Foundations, fixtures, etc. well in advance of taking up erection work, and bring to the notice of HPCL / MECON, discrepancies, if any. Necessary rectifications on account of any minor variations shall be carried out by the CONTRACTOR within the contracted rates.

5.7

Construction Equipment & Mechanisation of Construction Activities

5.7.1

The CONTRACTOR shall without prejudice to his overall responsibility to execute and complete the work as per specifications and Time Schedule, progressively deploy adequate equipments, and tools & tackles and augment the same as decided by the HPCL / MECON depending on the exigencies of the work so as to suit the

construction schedule. The HPCL / MECON shall supply no construction Equipment, CONTRACTOR to ensure deployment of all required tools, tackles & equipments and take all safety precautions during execution of work. 5.7.2

The CONTRACTOR shall mechanize the construction activities to the maximum extent by deploying all necessary construction equipment / machinery in adequate numbers and capacities.

5.8

Rounding off

5.8.1

All payments to and recoveries from the CONTRACTOR shall be rounded off to the nearest rupee. Wherever the amount to be paid / recovered consists of a fraction of a rupee (paise), the amount shall be rounded off to the next higher rupee if the fraction consists of 50 (fifty) paise or more and if the faction of a rupee is less than 50 (fifty) paise, the same shall be ignored.

5.9

CONTRACTOR's Billing System

5.9.1

HPCL will provide an approved format for Measurement sheets, Bill Summary and Bill Abstract. CONTRACTOR has to ensure that these data are updated for each subsequent RA and Final Bill. CONTRACTOR has to capture measurements, Abstract and Bill on format provided by HPCL on PC.

5.9.2 HPCL will utilize these data for processing and verification of the CONTRACTOR’s bill. 5.10 Site Organization 5.10.1 The CONTRACTOR shall without prejudice to his overall responsibility to execute and complete the works as per specifications and time schedule progressively deploy adequate qualified and experienced personnel together with skilled /unskilled manpower and augment the same as decided by HPCL / MECON depending on the exigencies of work to suit the construction schedule without any additional cost to HPCL. 5.10.2 CONTRACTOR shall provide all necessary superintendence during the execution of the Works and as long thereafter as the HPCL / MECON may consider necessary for the proper fulfilling of the CONTRACTOR's obligations under the Contract Such superintendence shall be given by sufficient persons having adequate knowledge of the operations to be carried out (including the methods and techniques required, the hazards likely to be encountered and methods of preventing accidents) for the satisfactory and safe execution of the Work. The workmen deployed by the CONTRACTOR should also possess the necessary license etc., if required under the existing laws, rules and regulations. 5.11 Additional / Extra Works HPCL reserves the right to execute any additional works / extra works, during the execution of work, either by themselves or by appointing any other agency, even though such works are incidental to and necessary for the completion of works awarded to the CONTRACTOR. The CONTRACTOR identified vide this tender shall not raise any objections, whatsoever to all such steps taken by HPCL.

5.12 Responsibility of CONTRACTOR 5.12.1 It shall be the responsibility of the CONTRACTOR to obtain the approval for any revision and/or modifications decided by the CONTRACTOR from the HPCL / MECON before implementation. Also such revisions and / or modifications if accepted / approved by the HPCL / MECON shall be carried out at no extra cost to the HPCL. Any change required during functional requirements or for efficient running of system, keeping the basic parameters unchanged and which has not been indicated by the CONTRACTOR in the data / drawings furnished along with the offer shall be carried out by the CONTRACTOR at no extra cost to the HPCL. 5.12.2 All expenses towards mobilization at site and demobilization including bringing in equipment, work force, materials, dismantling the equipment, clearing the site etc. shall be deemed to be included in the prices quoted and no separate payments on account of such expenses shall be entertained. It shall be noted that the quoted rates are deemed to include mobilization of workforce equipments, tools & tackles and working during time extension granted by HPCL 5.12.3 It shall be entirely the CONTRACTOR's responsibility to provide, operate and maintain all necessary construction equipment, scaffoldings and safety gadgets, lifting tackles, tools and appliances to perform the work in a workman like and efficient manner and complete all the jobs as per time schedule. 5.12.4 Preparing approaches and working area for the movement and operation of the lifting equipments, leveling the areas for assembly and erection shall also be responsibility of the CONTRACTOR. The CONTRACTOR shall acquaint himself with access availability facilities, local labour etc. to provide suitable allowances in his quotation. The CONTRACTOR may have to build temporary access roads to aid his own work, which shall also be taken care of while quoting for the work. 5.12.5 The procurement and supply in sequences and at the appropriate time of all Materials, and consumables shall be entirely the CONTRACTOR's responsibility and his rates for execution of work will be inclusive of supply of all these items. 5.13 Coordination with other agencies 5.13.1 CONTRACTOR shall be responsible for proper coordination with other agencies operating at the site of work so that work may be carried out concurrently, without any hindrance to others. The HPCL/ MECON shall resolve disputes, if any, in this regard, and there decision shall be final and binding on the CONTRACTOR. 5.14 Underground and overhead structures 5.14.1 The CONTRACTOR will familiarize himself with and obtain information and details from the HPCL / MECON in respect of all existing structures, overhead lines, existing pipelines and utilities existing at the job site before commencing work. The CONTRACTOR shall execute the work in such a manner that the said structures, utilities, pipelines etc. are not disturbed or damaged, and shall indemnify and keep indemnified the HPCL from and against any destruction thereof or damages thereto. 5.15

Statement of final bills -issue of No Claim/ No Due Certificate

5.15.1 The CONTRACTOR shall furnish a No-Due declaration indicating that there are no balances dues to his sub-vendor/sub-CONTRACTORs along with the Final Bill and a No-Claim Certificate declaring that there are no balances or pending Claims from HPCL towards the subject PO. 5.16

Working hours Depending upon the requirement, time schedule / drawing programmes and the target set to complete the job in time, the works may have to continue beyond normal working hours to the extent of round the clock and Holidays also, for which no extra claim shall be entertained.

6.

TESTS, INSPECTION ANO COMPLETION

6.1

Tests and Inspection

6.1.1

The CONTRACTOR shall carry out the various tests as enumerated in the technical specifications of this Bidding Document and technical documents that will be furnished to him during the performance of the work at no extra cost to the HPCL.

6.1.2

All the tests either on the field or at outside laboratories concerning the execution of the work and supply of materials by the CONTRACTOR shall be carried out by CONTRACTOR at his cost.

6. 1.3 The work is subject to inspection at all times by the HPCL / MECON. The CONTRACTOR shall carry out all instructions given during inspection and shall ensure that the work is being carried out according to the technical specifications of this bidding document, the technical documents that will be furnished to him during performance of work and the relevant codes of practice. 6.1.4

Compressed air for carrying out works shall be arranged by the CONTRACTOR at his own cost, For material supplied by HPCL, CONTRACTOR shall carry out the tests, if required by the HPCL / MECON, and the cost of such tests shall be reimbursed by the HPCL at actual to the CONTRACTOR on production of documentary evidence.

6.1.5

All results of inspection and tests will be recorded in the inspection reports, proforma of which will be approved by the HPCL / MECON. These reports shall form part of the completion documents. Any work not conforming to execution drawings, specifications or codes shall be rejected and the CONTRACTOR shall carry out the rectifications at his own cost.

6.2

Final Inspection

6.2.1

After completion of all tests as per specification the whole work will be subject to a final inspection to ensure that job has been completed as per requirement. If any defect is noticed, the CONTRACTOR will be notified by the HPCL / MECON and he shall make good the defects with utmost speed. If however, the CONTRACTOR fails to attend to these defects within a reasonable time (time period shall be fixed by the HPCL / MECON) then HPCL / MECON may have defects rectified at CONTRACTOR's cost. Inspection of Supply Items

6.3

6.3.1

All inspection and tests on bought out items shall be made as required by specifications forming part of this contract. Various stages of inspection and testing shall be identified after receipt of Quality Assurance Programme from the CONTRACTOR / manufacturer.

6.3.2

Inspection calls shall be given for association of HPCL / MECON, as per mutually agreed programme in prescribed proforma, giving details of equipment and attaching relevant test certificates and internal inspection report of the CONTRACTOR. All drawings, general arrangement and other contract drawings, specifications, catalogues etc. pertaining to equipment offered for inspection shall be got approved by HPCL / MECON and copies shall be made available to HPCL / MECON before hand for undertaking inspection.

6.3.3

The CONTRACTOR shall ensure full and free access to the inspection engineer of HPCL / MECON at the CONTRACTOR's or their sub-CONTRACTOR's premises at any time during contract period to facilitate him to carry out inspection and testing assignments

6.3.4

The CONTRACTOR / sub -CONTRACTOR shall provide all instruments, tools, necessary testing and other inspection facilities to inspection engineer of HPCL / MECON free of cost for carrying out inspection.

6.3.5

Where facilities for testing do not exist in the CONTRACTOR's / sub-CONTRACTOR's laboratories, samples and test pieces shall be drawn by the CONTRACTOR / subCONTRACTOR in presence of Inspection Engineer of HPCL / MECON and duly sealed by the latter and sent for tests in Government approved test house or any other testing laboratories approved by the Inspection Engineer at the CONTRACTOR's cost.

6.3.6

The CONTRACTOR shall comply with the instructions of the Inspection Engineer fully and with promptitude.

6.3.7

The CONTRACTOR shall ensure that the equipment / assemblies / component of the item required to be inspected are not assembled or dispatched before inspection.

6.3.8

The CONTRACTOR shall not offer any item for inspection in painted conditions unless otherwise agreed in writing with the HPCL / MECON.

6.3.9

The CONTRACTOR shall ensure that the items once rejected by the inspection engineer are not used in the subsequent works. Where parts rejected by the inspection engineer have been rectified or altered, such parts shall be segregated for separate inspection and approval, before being used in the work.

6.3.10 On satisfactory completion of final inspection and testing, inspection certificate shall be issued in requisite copies for all accepted items. For stage inspection and for rejected items, only inspection memo shall be issued indicating therein the details of observations and remarks. 6.3.11 All inspections and tests shall be made as required by the specifications forming part of this contract. CONTRACTOR shall advise HPCL in writing at least fifteen days in advance of the date of final inspection / tests. Manufacturer’s inspection or testing certificate for items and materials supplied may be considered for acceptance, at the

discretion of HPCL / MECON. All costs towards testing etc. shall be borne by the CONTRACTOR within their quoted rates. 6.4

Documentation

6.4.1 Completion Documents The following documents shall also be submitted by the CONTRACTOR in Triplicate as part of completion documents: a) b) c) d) e)

Test certificate for materials supplied by the CONTRACTOR. Certified records of field tests on materials / equipment, as applicable. Material appropriation statement as required. Construction drawings showing therein the a built conditions of the work duly approved by the HPCL / MECON along with one set of reproducible on polyester film (drawings prepared by CONTRACTOR) Other documents as mentioned in Technical Specification.

6.4.2 "AS BUILT" Drawings Upon completion of work, the CONTRACTOR shall complete all drawings to "As built" status (including all vendor / Sub -vendor's drawings for bought out items) and provide the MECON, the following: a) b)

One complete set of all original tracings / reproducible. Three complete sets of prints.

7.

OTHERS

7.1

Project Scheduling and Monitoring

7.1.1

The following schedules / documents / reports shall be prepared and submitted by the CONTRACTOR for review / approval at various stages of the contract.

7.2.1 Along With Bid The Bidder is required to submit as Project Time Schedule in PERT/Bar Chart Form, along with the Bid. The Schedule shall cover all activities including mobilization etc. as per the completion time stipulated in the Bidding Document. 7.2.2 After placement of Purchase Order Upon placement of Purchase Order, CONTRACTOR has to furnish a detailed PERT/bar chart as spelt out in the section Scope of Work for this work. CONTRACTOR to submit procurement plans for various item falling under their scope to supply under this tender along with PERT/Bar Chart. 7.2.3 Project Review Meetings The CONTRACTOR shall present the programme and status at various review meetings as required. CONTRACTOR will provide his authorized nominee at site to take participation in weekly meeting to sign the Records of Meeting.

i)

Weekly Review Meeting Level of participation: HPCL’S Site-in-charge / MECON and Contractors engineers on the job.

Agenda:

a) b)

ii)

Weekly programme v/s actual achieved week and programme for next week. Remedial Actions and hold up analysis.

in

the

past

Monthly Review Meeting Level of partaicipation: HPCL's Senior officials, Consultant & Contractor

Agenda:

a) b) c) d) e) f)

Progress Status / statistics. Completion Outlook Major hold ups / slippages. Assistance required. Critical issues. Client query / approval.

Venue

As decided by HPCL / MECON.

7.2.4 Progress Reports i)

Monthly Progress Report CONTRACTOR shall provide industry accepted weightages for the various jobs covered in the work including procurements as per HPCL / MECON directions. Scheduled vs Actual progress shall be reported on a monthly basis in S-Curve form. Necessary catch-up plan for any lags noticed shall be formulated by CONTRACTOR and submitted for HPCL / MECON's review & approval. The catchup plan shall be duly implemented by the CONTRACTOR. This report shall be submitted in three copies on a monthly basis within ten calendar days from cut-off date as agreed upon, covering overall scenario of the work. The report shall include but not be limited to the following: a) b) c)

Brief introduction of the work Activities executed / Achievements during the month. Scheduled vs actual percentage progress and progress curves for subordering, manufacturing / delivery, sub-contracting, construction activities and overall quantum wise status of purchase orders against scheduled.

d)

Areas of concern / problems / hold ups, impact and action plans. e) Resource deployment status Annexure giving status summary for Material Requisitions and deliveries, sub contracting and construction

f)

Distribution: MECON Two copies & One at Site.

ii)

Weekly Report This report (3 copies) will be prepared and submitted by the CONTRACTOR on weekly basis and will cover following items: a) b) c) d) e) f)

Activities programmed and completed during the week. Resources deployment status (manpower and machineries) Qty. achieved against target in construction. Record of Man-days lost. Areas of concern Construction percentage progress scheduled and

actual.

Distribution: MECON Two Copies & One at Site. iii)

Daily Report: Daily report in duplicate as out lined in 2.2.5 of SCC and any other additional information/data/guideline/job procedure sought by HPCL / MECON shall be submitted without fail to HPCL / MECON at site by CONTRACTOR. CONTRACTOR will submit on daily basis Progress Report to be generated at site in E Form through E-Mail @ the address provided by HPCL / MECON giving all the details including valid reasons for delay if any vis-a-vis to commitment i.e weekly plan /monthly plan /approved bar chart.

7.3

General Environment Requirement

7.3.1

The CONTRACTOR has to ensure efficient use of natural resources like water, fuel oil and lubricants. The CONTRACTOR should ensure proper awareness to workers to maintain a green and clean environment inside / outside the plant. The CONTRACTOR must collect and dispose of all the waste and scrap materials at the designated place only as directed by Engineer -in -Charge.

8.

General

8.1

It shall be distinctly understood that notwithstanding the reviews and suggestions if any, by the HPCL / MECON, the sole and ultimate responsibility for the stability and performance of the form work and staging and all other temporary works shall be that of the CONTRACTOR.

8.2

The partners or Directors of the CONTRACTOR shall meet the officers of the HPCL/ MECON at the site of works or at their respective offices whenever requested to do so.

8.3

In order to exercise the required degree of constant control over the ingredients of concrete and their proportions the CONTRACTOR shall set up proper supervision. A Measuring Glass for checking the silt content of sand shall be maintained and same shall be diligently recorded for every lot of sand on daily basis. Any other apparatus deemed necessary by the HPCL / MECON or its consultants for proper control shall be provided by the CONTRACTOR at his own cost.

8.4

HPCL / MECON may ask for any tests to be performed on any construction material.

Such test shall be performed at the CONTRACTOR's expenses either at site, in the site laboratory or elsewhere as directed by HPCL / MECON. The opinion of HPCL / MECON on the mode of testing and interpretation of the results thereof shall be final and binding on the CONTRACTORs and shall be without appeal. 8.5

HPCL reserves the right to use the premises and any portion of site for execution of any work not included in this contract which the HPCL may desire to get executed by other agencies. The CONTRACTOR shall allow all reasonable facilities for the execution of such work but shall not be required to provide any plant or material for which work except by special arrangement with the HPCL in such a manner as not to impede the progress of the works included in this contract and the CONTRACTOR shall not be responsible for any damage or delay which may happen or be occasioned by such work.

8.6

In addition to previous stipulations, the CONTRACTOR shall be represented at site at all times during the tenure of the contract by responsible and qualified engineers approved by HPCL / MECON. Such engineers shall form the CONTRACTOR's project management and site supervisory team. They shall be in constant attendance upon all activities of the work.

8.7

Limited area will be provided within the Premises by HPCL for storing materials. However, partition and temporary roof if required for ensuring proper storage shall be provided by the CONTRACTOR. Safety & Security of the materials brought by the party will be totally their own and HPCL / MECON cannot be held responsible in any manner.

8.8

The CONTRACTOR shall confirm to the provisions of the Govt. Act relating to the work and to the regulations and bylaws of the local authorities. The CONTRACTOR shall give all notices required by the said Act and obtain all required permissions and licenses and pay all fees payable to such authorities in connection with constructing and maintaining temporary power and water supply at the site for the said project. All aspects of temporary works including their stability shall be the sole and ultimate responsibility of the CONTRACTOR.

8.9

Labour camp shall be erected with the prior approval of HPCL / MECON. Frequency of testing of various materials shall be as per QAP/ITP. Testing of various materials should be carried out as per the relevant IS standards/ International Standards mentioned in the technical specifications attached to the tender. Party should submit manufacturer's certificates for the various materials and the above tests will be carried out in addition to the certificates submitted. Cost of testing should be borne by the party. In case of delay in testing materials, HPCL / MECON reserves the right to have the same tested at party's cost.

8.10

Frequency of testing of various materials shall be as per QAP/ITP. Testing of various materials should be carried out as per the relevant is standards / international standards mentioned in the technical specifications attached to the tender. party should submit manufacturer’s certificates for the various materials and the above tests will be carried out in addition to the certificates submitted. Cost of testing should be borne by the party. In case of delay in testing materials, HPCL/MECON reserves the right to have the same tested at party’s cost.

8.11

This project is subjected to inspection by various audit/vigilance agencies of government of India/Hindustan Petroleum Corporation Ltd. If any inspection of works is carried by such agencies, CONTRACTOR shall extend his full co-operation to these agencies in examining records, works etc. On inspection by such agencies, in their inspection report, if it is pointed out that CONTRACTOR has not carried out work according to guideline laid down in these tender documents and also if any recoveries in some items are pointed out therein, same shall be recovered from CONTRACTOR's R/A bills / final bill. The items under dispute shall not be paid in full till inspection agency gives their No-Objection report.

8.12

Sand has to be tested for silt content, particle size and organic impurities. If silt content is more than 8% the fine aggregate / sand has to be profusely washed and cleaned to reduce silt content to acceptable level.

9.

WATER: Contractor shall arrange the supply of Water for Construction.

10.

POWER: Power required for this work shall be arranged by CONTRACTOR only.

11.

SITE DRAINAGE All water, which may accumulate on the site during the progress of work or in trenches and excavations from other than, expected risk shall be removed from the site to the satisfaction of HPCL / MECON at the CONTRACTOR’s expense.

12.

The CONTRACTOR shall at all times give access to the staff of the statutory bodies as well as other agencies associated with the project and shall provide them all facilities like scaffolding, water, lighting etc. at site for discharging their duties.

13.

CONTRACTOR’s Personnel shall be available at all reasonable working hours to receive instructions, notices or communications and clear away on completion and make good all works distributed.

14.

The CONTRACTOR shall provide and maintain proper temporary sheds for the storage and protection of materials etc. and other work that may be brought or executed in the site including the tools and materials of CONTRACTORs and remove on completion. Sheds for storage of cement of adequate capacity as directed by HPCL / MECON shall be provided and the same have floors raised from the ground. The CONTRACTOR will be responsible for storage of cement in good and water tight condition.

15.

The CONTRACTOR shall provide at his cost all temporary lighting arrangement required for the works to enable the CONTRACTORs to complete the work in the specified time including that for the work man of any CONTRACTOR or special tradesman

16.

Watching and Lighting: The CONTRACTOR shall provide and maintain at his own expense all lights, night illumination of the premises, Guards, fencing and watching as and when necessary or required by the HPCL/ MECON for the protection of works

or for the safety and convenience of those employed on the works or the public. 17.

Theodolite, levels, plump bobs, prismatic compass, chain, steel and metallic tape and all other surveying instruments found necessary on the works shall be provided by the CONTRACTOR for the due performance of their contracts as instructed by HPCL / MECON. HPCL/ MECON will use any or all measure instruments or tools belonging to the CONTRACTOR as and when he chooses for checking the complete works as well as the work in progress

18.

All scaffolding and ladders that may be necessary for taking measurements at site will be provided by the CONTRACTOR.

19.

No work shall be done during the absence of HPCL / MECON representative.

20.

The CONTRACTOR shall not be permitted to enter on (other than for inspection purpose) or Take possession of site until instructed to do so by HPCL / MECON in writing. The portions of the site to be occupied by the CONTRACTOR shall be defined and/or marked on the site plan failing which these shall be indicated by HPCL/ MECON at site and the operations beyond the areas, in respect of any land permitted by the HPCL for the use of the CONTRACTOR for the purpose of or in connection with the contract, the same shall be subject to the following and such other terms and condition as may be imposed by HPCL. Such use or occupations shall not confer any right of tenancy of the land to the CONTRACTOR.

21.

The CONTRACTOR shall have no right to put up any construction of his own of any nature or type on HPCL’s land except temporary constructions for storage of equipment’s for the work under the contract or as a resting place for the labourers employed by him for the work provided that he obtain the requisite previous permission in writing from HPCL / MECON. In accordance with the HPCL procedure with permission they would be entitled to refuse in their absolute discretion. Such construction will be erected at the CONTRACTORs own cost. The CONTRACTOR shall at his own cost demolish all such constructions and remove the debris thereof. As also all his materials and equipment’s and clean and level the site thereof before handing over the completed work to the HPCL. The CONTRACTOR shall provide if necessary or if required for the site all temporary access thereof and shall alter adapt and maintain the same as required from time to time and shall take up and clear them away as and when no longer required and as and when ordered by HPCL / MECON and make good all damages done to the site. The CONTRACTOR shall note that the final bill will not be certified for payment till the action as above is completed by the CONTRACTOR to the entire satisfaction of HPCL / MECON.

22.

23.

All drawings, tracings, photo prints and writing (except letter) shall be the sole property of HPCL and must be returned to them on completion of work. The drawings maintained on the site are to be carefully mounted on boards of appropriate size. They are to be protected from ravages from termites, ants, silverfish and other insects.

24.

The completion of the work may entitle working in the monsoon also. The CONTRACTOR must maintain labour force as may be required for the job and plan and execute the construction and erection according to the prescribed schedule No extra rate will be considered for such work in monsoon. The Time schedule includes

monsoon window period also. Hence request for time Extension due to monsoon may not be entertained by HPCL. 25.

During the execution of the work CONTRACTOR must check his work with his drawings. The CONTRACTOR shall be responsible for all the errors in this connection and shall have to rectify all defects and / or error at his own cost failing which HPCL reserves the rights to get the same rectified at the risk and cost of the CONTRACTOR.

26.

During inclement weather the CONTRACTOR shall suspend concreting and plastering for such time as HPCL / MECON may direct and shall protect from injury all works in the course of erection.

27.

Should the work be suspended by reason of rain, strike, lockouts or other cause the CONTRACTOR shall take all precautions necessary for the protection of the work at his own expense shall make good any damages arising from any of this cause.

28.

All rubbish including muck and water, as it accumulates from time to time during the progress of the work shall be cleared through proper drainage arrangement so as not to hamper the progress of various other site works in progress such as tankages etc.

29.

The CONTRACTOR shall provide suitable pillar with flat tops and build the same in concrete for temporary benchmarks. All the pegs for setting out the works and fixing the necessary levels required for the execution thereof shall if desired by the HPCL / MECON likewise be built in masonry at such places and in such manner as the HPCL may determine

30.

The CONTRACTOR shall cover up and protect from injury due to any cause to all new work and any other requisite protection for the whole of the works executed whether by himself or special tradesman or sub CONTRACTORs and any damage caused must be made good by the CONTRACTORs at his own expense.

31.

Identity Cards

31.1

The CONTRACTOR shall be given approved identity cards to all his workers, which will have to be produced by the CONTRACTORs’ workmen as and when demanded by the HPCL’s representatives or Security men.

31.2. Action where there is no specification In case of any class of work over which there is no specification mentioned, the same shall be carried out in accordance with the latest edition of Indian Standard Specifications subject to the approval of the Consultants and Client. 31.3. Typographical or Clerical Errors The HPCL / MECONs clarifications regarding partially omitted particulars or typographical or clerical errors shall be final and binding on the CONTRACTOR. 31.4. As Built Drawings CONTRACTOR shall within one month of completion of work submit ’As Built’

drawings (original tracings and 3 sets of prints) of all the works carried out by him. CONTRACTOR will not receive final payment in case of failure to comply with this condition. 31.5

Removal of Debris CONTRACTOR shall arrange to dispose off debris and any other waste product created while carrying out the work, outside Client’s premises. The CONTRACTOR shall take due care while disposing of such waste materials and ensure that any rules/regulations laid down by Municipal Corporation, Client or any other statutory Body are not violated. The CONTRACTOR shall be responsible and answerable to any complaint arising out of improper disposal of wastage. Quoted rate shall involve the cost of same and no extra payment shall be made towards this account.

31.6

The CONTRACTOR shall submit original copies of invoices for verification if asked by HPCL/MECON, order forms for any materials purchased for project work, to HPCL/ MECON.

32.

The rates quoted by the tenderer in the schedule of quantities will be deemed to be for the finished work and shall include all charges for: a) b) c) d) e) f)

Plant, double scaffolding, frame work, English ladders, ropes, nails, spikes, tools, materials and workmen, protection from weather, temporary supports, platform and the maintenance of the same. All temporary canvas, lights, tarpaulin, barricade, water shoots etc. All such temporary weather-proof sheds at such places and in a manner approved by the Consultants for the storage and protection of materials against the effects of sun and rain. All testing of materials. No tools and plants shall be issued by the Client under the Contract. The CONTRACTOR should provide the temporary ply partition to cover certain location of Bank premises wherever necessary. Rates quoted by CONTRACTOR are deemed to include deployment of competent Quality Control Engineers from Start to completion of work for upkeep and maintain all QA/QC records in accordance to ITP/QAP/Relevant codes/any other requirement as specified in Tender.

33.

No scaling of any drawings shall be carried out at site by workmen/labour during execution of work. The details required for the execution of any item shall be timely given by the client/consultants in weekly co-ordination site meetings.

34.

Weekly site co-ordination meetings shall be attended by the CONTRACTORs working on site & proper intimation should be given to the client/consultants in order to monitor the project more efficient way. The relative decision for the execution of tender items shall be given in these meetings by client/consultants by producing working drawings/hand-made sketches if any.

35.

Working on holidays For timely completion of project, CONTRACTOR is required to deploy more labour & fluent material supply as required on site as directed by consultant and HPCL. The normal working hours will be from 0900 hrs to 1730 hrs on normal working days

from Monday through Saturday and excluding Sundays and holidays. Permission for working beyond 1730 hrs on normal working days from Monday through Saturday and for working on Sundays & Holidays may be permitted by HPCL based on written request by CONTRACTOR. Concreting activity may not be permitted to be carried out after daylight hours. It is therefore imperative that the CONTRACTOR mobilises sufficient manpower and tools & tackles to complete the work within 0900 hrs to 1730 hrs from Monday through Saturday only excluding Sundays & holidays. 36.

Audits Of Contract: The project is subject to inspection by various audit/vigilance agencies of government of India/Hindustan Petroleum Corporation Ltd., if any inspection of works is carried by such agencies, CONTRACTOR shall extend his full cooperation to these agencies in examining records, works etc. On inspection by such agencies, if it is pointed out that CONTRACTOR has not carried out work according to guidelines laid down in the tender document, immediate rectifications shall be taken up at no extra cost; and also if any recoveries against some items are pointed out therein, the same shall be recovered from CONTRACTOR’s RA bills/final bill. The items under dispute shall not be paid in full till the job is completed to satisfaction of the inspection agency.

37.

Payment Terms Refer Annexure-I to SCC

38.

Clause 3.6 of GCC stands modified and shall now read as follows : The quantities indicated in the Tender are approximate. The approved schedule of rates of the contract will be applicable for variations upto plus 25% of the contract value and for minus variations without any limit. No revision of schedule of rates will be permitted for such variations in the contract value, including variations of individual quantities, addition of new items, alterations, additions/deletions or substitutions of items, as mentioned above. Quantities etc. mentioned and accepted in the joint measurement sheets shall alone be final and binding on the parties.

39.

Unless otherwise stated the tender is on item rate basis. The quantities in the Schedule of Quantities approximately indicates the total extent of work. Payment will be made on the actual quantities installed at site and any excess supply shall be taken back by the Contractor.

40.

Liability Clause It is expressly understood and agreed by and between Bidder and M/s Hindustan Petroleum Corporation Limited, (Indian Public Sector Undertaking) that M/s Hindustan Petroleum Corporation Limited is entering into this agreement solely on its own behalf and not on behalf of any other person or entity. In particular, it is expressly understood and agreed that the Government of India is not a party to this agreement and has no liabilities, obligations or rights hereunder. It is expressly understood and agreed that M/s Hindustan Petroleum Corporation Limited is an

independent legal entity with power and authority to enter into contracts solely on its own behalf under the applicable Laws of India and general principles of Contract Law. The Bidder expressly agrees, acknowledges and understands that M/s Hindustan Petroleum Corporation Limited. is not an agent, representative or delegate of the Government of India. It is further understood and agreed that the Government of India is not and shall not be liable for any acts, omissions, commissions, breaches or other wrongs arising out of the contract. Accordingly Bidder hereby expressly waives, releases and foregoes any and all actions or claims, including cross claims, impleader claims or counter claims against the Government of India arising out of this contract and covenants not to sue to Government of India as to any manner, claim, cause of action or thing whatsoever arising of or under this agreement. 41.

DEFINITIONS / NOTES

41.1

The terms ‘Bidder’, ‘Contractor’, `Seller’, `Supplier’ or ‘Vendor’ stated anywhere in the Bid Document carry the same meaning.

41.2

The terms `Client’, ‘Owner’, ‘Purchaser’ stated any where in the Bid Document refer to Hindustan Petroleum Corporation Limited (HPCL).

41.3

The term `Consultant’ shall means MECON Limited.

41.4

The term ‘Contract’, ‘Order’ stated anywhere in the Bid Document carry the same meaning.

42.

Arbitration: Public Sector vs Government Dept. vice versa

42.1

In the event of any dispute or difference between the parties hereto such dispute or difference shall be resolved amicably by mutual consultation or through the good offices of empowered agencies of the Govt . If such resolution is not possible then the unresolved dispute of difference shall be referred to arbitration of an arbitrator to be nominated by Secretary, Dept of Legal Affairs (Law Secretary) The arbitration and Conciliation act , 1996 shall not be applicable to the arbitration under this clause. The award of the arbitrator shall be binding upon the parties to the dispute provided however that any party aggrieved by such award may appeal for setting aside or revision of the award to Law Secretary whose decision shall bind the parties finally and conclusively. The said appeal should be filed within the period specified in the award of the arbitrator.

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ANNEXURES TO SPECIAL CONDITIONS OF CONTRACT

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

MECON LIMITED

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

ANNEXURES TO SCC CONTENTS

Annexure-1

:

Scope of Work

Annexure-2

:

Scope of Supply

Annexure-3

:

Time Schedule

Annexure-4

:

Measurement Work

Annexure-5

:

Terms of Payment

Annexure-6

:

Specification for Quality Assurance System requirements from Bidders

Annexure-7

:

Specification Management

Annexure-8

:

Conditions for issue & reconciliation of material

Annexure-9

:

List of minimum nos. of construction equipment to be deployed

Annexure-9A

:

List of Minimum Equipments required to be owned by the tenderer

Annexure-9B

:

List of hired/ Leased equipment alongwith MOU from the owner to be submitted by the single bidder/ leader of the consortium

Annexure-10

:

Minimum no. of skilled labour to be deployed

Annexure-11

:

Schedule of Labour Rate

Annexure-12

:

Schedule of Equipment Rate

Annexure-12A

:

Recovery Rate for Non-Deployment of Minimum Equipment

Annexure-12B

:

Recovery Rate for Non-Deployment of Minimum Manpower

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

for

Health,

Safety

and

Environment

(HSE)

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

SCOPE OF WORK (ANNEXURE-1 TO SPECIAL CONDITIONS OF CONTRACT)

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ANNEXURE-1 TO SCC 1.0

SCOPE OF WORK Scope of work shall be as detailed in Particular Job Specification, Technical Specifications, Schedule of Rates & various other parts of this Bidding Document.

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

SCOPE OF SUPPLY (ANNEXURE-2 TO SPECIAL CONDITIONS OF CONTRACT)

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ANNEXURE-2 TO SCC 1.0

SCOPE OF SUPPLY

1.1

Owner’s Scope of Supply Owner’s scope of supply shall be as specified in Particular Job Specification, Technical Specifications, Schedule of Rates & various other parts of the Bidding Document. Free Issue Materials shall be issued to the Contractor from the designated store(s) of Owner. Contractor shall be responsible for lifting the free issue materials from Owner’s storage point(s) and transporting the same to work site(s) at his own cost. HPCL’s designated store for this project shall be located at HPCL Bahadurgarh, Haryana. Conditions for Issue And Reconciliation of Materials shall be as per Document enclosed as Annexure-8 to Special Conditions of Contract.

1.2

Contractor’s Scope of Supply All materials except what is under Owner’s scope of supply as mentioned in Clause No. 1.1 above, and required for successful completion of works in all respects shall be supplied by the Contractor and the cost of such supply shall be deemed to have been included in the quoted price without any additional liability on the part of Owner.

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

TIME SCHEDULE (ANNEXURE-3 TO SPECIAL CONDITIONS OF CONTRACT)

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ANNEXURE-3 TO SCC

TIME SCHEDULE Name of Work CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE

Time of Completion COMPLETION OF CONSTRUCTION WORKS OF TWO PARALLEL 10’’X15 KM AND 8” X 15 KM U/G PIPELINES TRENCH FROM BAHADURGARH TO TIKARIKALAN, TAPOFF/HOOK UP WITH EXISTING PRODUCT TANKS, INTERCONNECTING ABOVE GROUND COMPLETE PIPING SYSTEM, DISPATCH & RECEIVING TERMINAL WORKS INCLUDING COMPLETE ERECTION OF ALL PUMPS (8 NOS) AND COMMISSIONING ASSISTANCE, CONTROL ROOMS, STRUCTURAL SHEDS AND ALL ASSOCIATED MECHANICAL, CIVIL, STRUCTURAL, ELECTRICAL, INSTRUMENTATION, SCADA & TELECOMMUNICATION WORKS, CP WORKS AT BAHADURGARH & TIKARIKALAN AS PER SCOPE OF WORKS GIVEN IN TENDER WITHIN THE TIME PERIOD AS DETAILED BELOW: 26 WEEKS FROM THE DATE OF FOI. IT SHOULD BE NOTED THAT THE PERIOD OF COMPLETION GIVEN INCLUDES PREPARATION OF DRAWINGS (IF REQUIRED), PROCUREMENT AND SUPPLY OF MATERIAL INCLUDING THEIR INSPECTION AND TESTING, MOBILISATION AT SITE, CONSTRUCTION, LAYING, FABRICATION, ERECTION, INSPECTION, TESTING, RECTIFICATION (IF ANY) AND UPTO PRECOMMISSIONING OF FOLLOWING FACILITIES : A) PIPELINE UPTO HYDRO-TESTING (READY FOR TAKING PRODUCT) B) TERMINALS AFTER TESTING (READY FOR TAKING PRODUCT) C) PUMPS (READY FOR TAKING PRODUCT) D) CP SYSTEM READY FOR COMMISSIONING E) ELECTRICAL & INSTRUMENTATION READY FOR FINAL INTEGRATED TESTING & COMMISSIONING 4 WEEKS FOR OVERALL COMMISSIONING IN ALL RESPECTS TO THE ENTIRE SATISFACTION OF HPCL/MECON FROM THE

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

DATE OF ADVISE COMMISSIONING.

MECON LIMITED

TO

COMMENCE

Note: 1)

The time of completion shall be reckoned from the date of award of contract, which shall be the date of issue of letter/ Fax of Intent.

2)

The time indicated is for completing all the works in all respects as per specifications, codes, drawings and instructions of Engineer-in-charge.

_______________________________ (STAMP & SIGNATURE OF BIDDER)

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

MEASUREMENT OF WORK (ANNEXURE-4 TO SPECIAL CONDITIONS OF CONTRACT)

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ANNEXURE-4 TO SCC MEASUREMENT OF WORK 1.0

GENERAL

1.1

The mode of measurement shall be as mentioned in relevant standard specification incorporated in the Bidding Document. Any other mode of measurements not covered in above specifications shall be followed in accordance with relevant BIS codes/ Schedule of Rates/ Specifications etc. and/ or as decided by Engineer-in-charge.

1.2

Payment will be made on the basis of joint measurements taken by Contractor and certified by Engineer-in-charge. Measurement shall be based on “Approved for Construction” drawings, to be the extent that the work conforms to the drawings and details are adequate.

1.3

Wherever work is executed based on instructions of Engineer-in-charge or details are not adequate in the drawings, physical measurements shall be taken by Contractor in the presence of Engineer-in-charge.

1.4

Measurements of weights shall be in metric tonnes corrected to the nearest Kilogram. Linear measurements shall be in meters corrected to the nearest centimeters.

1.5

The weights mentioned in the drawing or shipping list shall be the basis for payment. If mountings for panels etc. are packed separately, their erection weights shall include all mountings.

1.6

Welds, bolts, nuts, washers etc. shall not be measured. Rates for structural steel work shall be deemed to include the same.

1.7

No other payment either for temporary works connected with this Contractor for any other item such as weld, shims, packing plates etc. shall be made. Such items shall be deemed to have been included for in the rates quoted.

1.8

Measurement will be made for various items under schedule of rates on the following basis as indicated in the unit column. i) ii) iii) iv) v)

Weight Length Number Volume Area

: : : : :

MT or Kg M (Metre) No. Cu.M Sq.M

2.0

PIPING

2.1

Length of pipes shall be measured along the curvilinear centre of the pipelines laid/ installed and shall include all types of specials, fittings, mitre bends etc. but excluding all types of valves. Length of valves shall be excluded from piping measurement and shall be considered on number basis.

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

TERMS OF PAYMENT (ANNEXURE-5 TO SPECIAL CONDITIONS OF CONTRACT)

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

MECON LIMITED

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

ANNEXURE-5 TO SCC TERMS OF PAYMENT Pending completion of the whole works, provisional progressive payments for the part of work executed by the contractor shall be made by Owner on the basis of said work completed and certified by the Owner’s representative as per the agreed milestone payment schedule and the percentage break-ups given below. Contractor shall submit his invoices to the Owner’s representative fortnightly in the manner as instructed by Owner. Each invoice will be supported by documentation acceptable to Owner and certified by the Owner’s representative. Payments made by owner to the contractor for any part of the work shall not deem that the Owner has accepted the work. All payments against running bills are advance against the work and shall not be taken as final acceptance of work / measurement carried out till the final bill. Owner will release payment through e-payments only as detailed in the bidding document. 1.0

MAINLINE WORKS

1.1

Pipeline Laying with Associated Works

1.1.1

Completion of site development, stacking, clearing and grading of ROU, trenching by excavation

:

15% progressively

1.1.2

Completion of fabrication, alignment, stringing, field welding, radiography (NDT).

:

25% progressively

1.1.3

Completion of joint coating & lowering

:

20% progressively

1.1.4

Completion of tie-ins, NDT, Joint Coating and backfilling

:

10% progressively

1.1.5

Completion of hydro testing, dewatering, swabbing

:

15% progressively

1.1.6

Completion of magnetic cleaning plus electronic geometry pigging and restoration

:

5% progressively

1.1.7

Completion of all activities and their acceptance. Submission of final documents, final bill and acceptance of these by owner thereafter for successful closure of work order.

:

10%

The above payment shall be made subject to the following : i)

The stage payment of 10% as per sub-clause 1.1.4 above will be released on completion of continuous stretch of 5 km.

ii)

For discontinuity on account of major crossings specified in SOR, crossing length shall not be taken into account for (i) above for payment purposes. The payment towards such crossings shall be made on the basis of item rate in SOR.

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

1.2

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

For Lumpsum Items For all lumpsum items included in schedule of rates, contractor shall furnish price break-up for quoted lumpsum prices for the approval of Engineer-in-charge. Payment for such item shall be made accordingly. In this regard decision of Engineer-in-charge shall be final and binding to the bidder.

1.3

2.0

Major Crossing & Other items not covered above or elsewhere in the Tender a)

Completion of individual items of work

: 90% progressively

b)

Completion of all activities and their acceptance. Submission of final documents, final bill and acceptance of these by owner thereafter for successful closure of work order.

: 10%

CATHODIC PROTECTION WORKS The basis for payment against various items shall be as follows :

2.1

2.2

Temporary Cathode Protection System a)

5% on placement of order on sub-vendor.

b)

5% on design approval of TCP Package.

c)

60% on receipt of material at site and acceptance thereof.

d)

20% on installation, testing, pre-commissioning and commissioning.

e)

10% on completion of all activities and their acceptance. Submission of final documents, final bill and acceptance of these by owner thereafter for successful closure of work order.

Permanent Cathode Protection System a)

5% on placement of order on sub-vendor.

b)

5% on design approval of PCP Package.

c)

50% on receipt of material at site and acceptance thereof.

d)

30% on installation, testing, ON / OFF PCP Survey, CIPL Survey interference detection & its mitigation of the entire length of 10” pipeline, pre-commissioning and commissioning,

e)

10% on completion of all activities and their acceptance. Submission of final documents, final bill and acceptance of these by owner thereafter for successful closure of work order.

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

3.0

Other items not covered above or elsewhere in the tender a)

Completion of individual item of work as per SOR including supplies wherever involved

: 90% progressively

b)

Completion of all activities and their acceptance. Submission of final documents, final bill and acceptance of these by owner thereafter for successful closure of work order.

: 10%

4.0

TERMINALS WORKS

4.1

Piping Works a) b) c) d)

4.2

90% on completion of work on prorate basis as certified in running bills. 10% on completion of all activities and their acceptance. Submission of final documents, final bill and acceptance of these by owner thereafter for successful closure of work order.

Structural Works a) b) c) d) e)

4.4

55% on fabrication of piping. 25% on erection, alignment, welding complete to achieve mechanical completion. 10 on flushing, testing, draining, drying, etc. 10% on completion of all activities and their acceptance. Submission of final documents, final bill and acceptance of these by owner thereafter for successful closure of work order.

Civil Works (Except control room building which shall be paid as indicated in respective SOR) a) b)

4.3

MECON LIMITED

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

5% on approval of fabrication drawings. 55% on supply and acceptance of material at site. 15% on fabrication. 15% on erection, alignment, welding, painting, etc. 10% on completion of all activities and their acceptance. Submission of final documents, final bill and acceptance of these by owner thereafter for successful closure of work order.

Items including supply of finished goods (Mechanical, Electrical & Instrumentation) a) b) c) d) e)

5% on placement of order on sub-vendor. 65% on receipt of material at site and acceptance thereof. 15% on erection, alignment, welding, grouting, painting, etc. 5% on testing. 10% on completion of all activities and their acceptance. Submission of final documents, final bill and acceptance of these by owner thereafter for successful closure of work order.

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

4.5

45% on transportation and installation in position. 30% after initial alignment, leveling and grouting. 15% after final alignment and making ready for commissioning. 10% on completion of all activities and their acceptance. Submission of final documents, final bill and acceptance of these by owner thereafter for successful closure of work order.

Electrical and Instrumentation Works a) b) c)

4.7

MECON LIMITED

Equipment Erection Works (Installation of Pumps, Scrapper Trap, Basket Filter, etc.) a) b) c) d)

4.6

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

80% on completion of installation. 10% on testing. 10% on completion of all activities and their acceptance. Submission of final documents, final bill and acceptance of these by owner thereafter for successful closure of work order.

For Lumpsum Items For all lumpsum items included in schedule of rates, contractor shall furnish price break-up for quoted lumpsum prices for the approval of Engineer-in-charge. Payment for such item shall be made accordingly. In this regard decision of Engineer-in-charge shall be final and binding to the bidder.

4.8

Supply of Materials and All Other Works a)

Completion of individual items of work

: 90% progressively

b)

Completion of all activities and their acceptance. Submission of final documents, final bill and acceptance of these by owner thereafter for successful closure of work order.

: 10%

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

SPECIFICATION FOR QUALITY ASSURANCE SYSTEM REQUIREMENTS (Annexure - 6 to SCC ) (For Details – Refer our Technical Specification No. 05/62/S/66 of the same enclosed in Vol-II of the Tender)

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

STANDARD SPECIFICATION FOR HEALTH, SAFETY AND ENVIRONMENTAL (HSE) MANAGEMENT AT CONSTRUCTION SITES (ANNEXURE – 7 to SCC ) (FOR DETAILS – REFER OUR TECHNICAL SPECIFICATION No. 05/62/S/65 OF THE SAME ENCLOSED IN VOL-II OF THE TENDER)

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

CONDITIONS FOR ISSUE AND RECONCILIATION OF MATERIAL (ANNEXURE – 8 to SCC)

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

MECON LIMITED

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

ANNEXURE-8 TO SCC 1.0

CONDITIONS FOR ISSUE OF MATERIALS Whenever any material is issued by Owner, following conditions for issue of material in addition to other conditions specified in the contract shall be applicable.

1.1

Necessary indents will have to be raised by the Contractor as per procedure laid down by the Engineer-in-charge from time to time, when he requires the above material for incorporation in permanent works.

1.2

Materials will be issued only for permanent works and not for temporary works, enabling works etc. unless specifically approved by the Engineer-in-charge and the same shall not be taken into account for the purpose of materials reconciliation.

1.3

The contractor shall beer all other cost including lifting, carting from issue points to work site/ contractor’s store, custody and handling etc. and return of surplus/ serviceable scrap materials to Owner’s storage points to be designated by the Engineer-in-charge etc. No separate payment for such expenditure will be made.

1.4

No material shall be allowed to be taken outside the plant without a gate pass.

1.5

The contractor shall be responsible for proper storage, preservation and watch & ward of the materials.

1.6

Reconciliation of Owner supplied materials

1.6.1

Every month, the contractor shall submit an account for all materials issued by Owner in the proforma prescribed by the Engineer-in-charge. On completion of the work the contractor shall submit “Material Appropriation Statement” for all materials issued by the Owner in the proforma prescribed by the Engineer-in-charge. All coated line pipes as per line pipe specifications enclosed elsewhere in the bidding document, shall be issued on linear measurement basis. Optical Fibre Cables shall be issued in drum lengths of 4 km on linear measurement basis. Joints etc. shall be issued on number basis. All other piping materials shall be issued on numbers basis. All cut pieces pipes measuring in length measuring 2m to 9m when returned to Owner’s storage points after bevelling, shall be considered as serviceable material. All cut pieces of pipes measuring less than 2m will be treated as wastage/ scrap. All pipes above 9m will be considered as good pipe. a)

For the purpose of accounting of coated line pipes following maximum allowances shall be permitted. i) ii) iii)

Unaccountable wastage Scrap (all cut pieces of pipes measuring less than 2 m) Serviceable materials (all cut pieces of pipes measuring 2m upto 9m)

0.1% 0.25% 0.5%

Unaccountable wastage/ scrap shall be at actuals as per site assessment subject to maximum as stated above.

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

The percentage allowance shall be accounted on the basis of final weld book chainage for main pipeline and erected/ approved fabrication drawings for station piping as mentioned below : b)

For the purpose of accounting of station piping, all cut pieces measuring in length of 1m and above when returned to Owner’s storage points after bevelling, shall be treated as serviceable materials. All cut pieces of pipes measuring less than 1m will be treated as scrap. For the purpose of station piping following maximum allowances shall be permitted: i) ii) iii)

Unaccountable wastage Scrap (all cut pieces of pipes measuring less than 1 m) Serviceable materials (all cut pieces of pipes measuring 1m and above)

0.1% 1.0% 2.0%

Unaccountable wastage/ scrap shall be at actuals as per site assessment subject to maximum as stated above. c)

For the purpose of accounting of optical fibre cable & other materials used in telecommunication works. Reconciliation work for Owner supplied materials shall be carried out as per the scope detailed in particular scope of work, SOR and relevant specification enclosed elsewhere with the tender. For the purpose of cables following maximum allowances shall be permitted : i) ii) iii)

Unaccountable wastage Scrap (all cut pieces of cables measuring less than 40m) Serviceable materials (all cut pieces of cables measuring 40 meter and above)

0.1% 0.25% 0.25%

Unaccountable wastage/ scrap shall be at actuals as per site assessment subject to maximum as stated above. 1.6.2

All unused, scrap materials and salvageable materials shall be the property of the Owner and shall be returned by the Contractor category-wise at his cost to the Owner’s designated store yard(s). In case the Contractor fails to do so/ or exceeds the limits of allowances specified above for scrap/ serviceable materials, then recovery for such quantities not returned as well as returned in excess of permitted limit by the Contractor will be done at the penal rate i.e. 125% of landed cost at the time of final bill/ closing of contract by Engineer-in-charge shall be effected from the Contractor’s bill(s) or from any other dues of the Contractor to the Owner. Contractor shall be responsible for the adjustment/ weighment/ measurement of the surplus materials to be returned to the store. Contractor shall also be responsible for suitable segregation of returned materials into separate stacks of serviceable and scrap materials.

1.6.3

Wherever certain material is covered under Contractor’s scope of supply whether part or in full for any item of work covered under SOR, no allowance towards wastage/ scrap etc. shall be accounted for during execution stage.

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

MINIMUM NO. OF MAJOR EQUIPMENTS/ MOBILISATION EQUIPMENT SCHEDULE TO BE DEPLOYED (Annexure-9, 9A & 9B of Special Condition of Contract)

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ANNEXURE-9 TO SCC LIST OF MINIMUM NOS. OF CONSTRUCTION EQUIPMENT TO BE DEPLOYED Sl. No. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29. 30.

Equipment Description Grader Dozer D7/ D6 Or, Equivalent Excavator or Back-Hoe (≥ Hitachi 100 or equivalent) Side Boom or Pipe Layer Or, Equivalent Hydra-( 8-10 MT) Diesel Welding Machine DG Set 120 kVA + Stabilizer Automatic Bevelling Machine Internal Clamp ND 10” External Clamp ND 10” Internal X-ray Unit External X-ray Unit Gamma Ray Unit Radiography Film Viewer Sand Blasting Unit Air Compressor (Minimum 300 CFM) Air Compressor (Minimum 600 CFM) Holiday Detector Dewatering Pump Water Filling Pump of Adequate Capacity Dosing Pump of Adequate Capacity Pressurization Pump – Motorised (Adequate capacity) Dead weight tester, pressure recorder, temperature recorder) Pipe Bending Machine with Pneumatic Mandrel (10” NB) Horizontal Augur Boring Machine Pipe Trailers of adequate size Concrete mixture machine Rock breaking M/c Hand Drill (Pneumatic) with compressor Pipe Locator

Qty. (Nos.) 1 2 2 4 4 16 As required 2 4 4 2 2 2 2 4 2 1 4 6 3 1 2 2 Sets 2 1 4 8 1 2 1

Note: 1.

Meeting the requirement of minimum construction equipments as given above, is a part of Bidder Evaluation Criteria. Bidder shall confirm compliance for deployment of above equipments.

2.

Bidder is required to mobilise the above minimum critical equipments in good working condition and suitable to lay this 10” diameter pipeline. Bidder is required to augment the above list with additional numbers / categories of equipments as per actual requirement and instruction of Engineer-In-Charge without any additional financial implication to client.

3.

Bidder shall replace any defective / damaged equipments promptly to complete the work without any time & cost implication to the client / owner.

4.

After completion of certain activities, in case equipments are not required the same can be demobilised with prior approval of Engineer-In-Charge.

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ANNEXURE-9A TO SCC LIST OF MINIMUM EQUIPMENTS REQUIRED TO BE OWNED BY THE BIDDER Sl. No

Equipment Description

1. 2. 3. 4. 5.

Hydra – 8-10 MT Excavator or Back-Hoe (≥ Hitachi 100 or equivalent) Bending Machine with Pneumatic Mandrel (10” NB) Internal Clamp ND 10” Diesel Welding Machine

Nos. 2 1 1 2 6

Note: Bidder are required to submit documentary evidence of ownership of the above equipments as indicated below :1. The bidder shall submit either of the following documents to establish that they own the equipment. a) b) c)

d) e)

2.

Registration certificate issued by regulating authority OR Insurance coverage OR Certificate from Chartered Accountant, certifying that the bidder owns the equipments and the same are available for this Project. OR Invoice / Delivery Challan. OR "For equipment to be purchased" - Purchase order duly accepted by equipment supplier and with equipment delivery to project site, meeting the equipment deployment schedule.

Certificate from Chartered Engineer certifying that the bidder own equipments are under good health and working condition.

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ANNEXURE-9B TO SCC LIST OF HIRED/ LEASED EQUIPMENT TO BE SUBMITTED BY THE BIDDER CATEGORY-1 Sl. No. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21.

Equipment Description Grader Dozer D7/ D6 Or, Equivalent Excavator or Back-Hoe (≥ Hitachi 200 or equivalent) Excavator or Back-Hoe (≥ Hitachi 100 or equivalent) Side Boom or Pipe Layer Or, Equivalent Hydra-( 8-10 MT) Diesel Welding Machine Internal Clamp ND 10” Internal X-ray Unit External X-ray Unit Gamma Ray Unit Radiography Film Viewer Sand Blasting Unit Air Compressor (Minimum 600 CFM) Water Filling Pump of Adequate Capacity Dosing Pump of Adequate Capacity Pressurization Pump – Motorised (Adequate capacity) Dead weight tester, pressure recorder, temperature recorder) Pipe Bending Machine with Pneumatic Mandrel (10” NB) Horizontal Augur Boring Machine Rock breaking machine with excavator

Qty. (Nos.) 1 2 1 1 4 2 10 2 2 2 2 2 4 2 3 1 2 2 Sets 2 1 1

CATEGORY-2 Sl. No. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Note: 1)

2)

Equipment Description DG Set 120 kVA + Stabilizer Automatic Bevelling Machine External Clamp ND 10” Air Compressor (Minimum 300 CFM) Holiday Detector Dewatering Pump Pipe Trailers of adequate size Concrete mixture machine Hand Drill (Pneumatic) with compressor Pipe Locator

Qty. (Nos.) As required 4 8 2 4 3 4 8 2 2

For equipment under Category-1 bidders are required to submit the documentary evidence for Ownership/ Hiring/ Lease of equipments listed in this category. a) For Hired/ Lease Equipments : The documentary evidence shall be MOU from the hiring/ lease agency of the equipment alongwith the bid. Bidder shall be responsible for timely delivery of these equipments at the site at stipulated time. b) For Owned Equipments : The proofs of ownership will be as stated in Annexure-9A. Equipments in Category-2 : No documents are required to be submitted alongwith the bid.

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 58

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

MINIMUM NO. OF SKILLED MANPOWER TO BE DEPLOYED (Annexure-10 of Special Condition of Contract)

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 35

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ANNEXURE-10 TO SCC MINIMUM NUMBER OF SKILLED MANPOWER TO BE DEPLOYED Sl. No 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27.

Description Linepipe Welders Station Pipeline Welders Sand Blaster Insulators Heavy Equipment Operators Other Equipment Operators Pipe Fitters Gas Cutters Radiographer Level-II Mechanic Grinder Drivers (Backhoe/ Crane/ Dover) Riggers/ Helper Survey Teams Foreman Supervisors Engineer Project Manager Engineer (M/L Civil & Mechanical) Terminal-in-charge Terminal Engineer (Mechanical) Terminal Engineer (Civil) Terminal Engineer (Electrical) Terminal Engineer (Instrumentation) Engineer (Telecom Work) QC In-charge & Engineer for Welding QC In-charge & Engineer for NDT

Requirement 15 Nos. 5 Nos. 3 Nos. 4 Nos. As per Eqpt. List As per Eqpt. List 6 Nos. 4 Nos. 2 Nos. 5Nos. As required As required As required 2 Nos. 4Nos. One for each activity 4 Nos. 2 Nos. 2 Nos. 2 Nos. 2 Nos. 2 Nos. 2 Nos. 2 Nos. 2 Nos. 1 No. 1 No.

The above proposed list of skilled manpower is the minimum to be deployed by Contractor

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 35

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

SCHEDULE OF LABOUR RATES (Annexure-11 of Special Condition of Contract)

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 35

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ANNEXURE –11 to SCC

SCHEDULE OF LABOUR RATES (FOR EXTRA WORKS) _________________________________________________________________ Sl. Classification Rates in INR for 8 hours No. Personnel _________________________________________________________________ Standard Time (Rs) _________________________________________________________________ 1. Engineer 2. Surveyor Foreman 3. Pipe Fitter 4. Pipe Welder 5. Gas Cutter 6. Grinder 7. Mason 8. Plumber 9. Carpenter 10. Painter 11. Electrician 12. Cable Jointer 13. Instrument Technician 14. Rigger 15. Watchman/Helper 16. Concrete Mixer Operator 17. Heavy Machine Operator

750/500/200/500/200/200/200/200/200/200/200/175/300/150/100/150/300/-

_______________________ (SIGNATURE OF BIDDER) NOTES:Rates are final and Tenderer is to sign only without deviation.

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 35

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

EQUIPMENT HOURLY RENTAL RATES FOR EXTRA WORKS/ RECOVERY RATES (Annexure-12, 12A & 12B of Special Condition of Contract)

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 35

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

MECON LIMITED

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

ANNEXURE-12 TO SCC

EQUIPMENT HOURLY RENTAL RATES FOR EXTRA WORKS

-------------------------------------------------------------------------------------------SL. DESCRIPTION OF HOURLY RENTAL RATES FOR NO. EQUIPMENT EXTRA WORKS INCLUDING CONSUMABLES 1. Dozers Rs. 1100/2. Back Hoe 1.2 m3 Rs. 1500/3. Back Hoe 0.7 m3 Rs. 1000/4. Side Boom 45 ton Rs. 2000/5. Side Boom 15 ton Rs. 1200/6. Boring machine Rs. 7040/7. Bending machine Rs. 400/8. Welding machine Rs. 300/9. Compressors 210 CFM Rs. 500/10. Crane upto 15 T Rs. 1100/11. Dewatering Pumps Rs. 125/12. Internal Clamps Rs. 50/13. Holiday detector Rs. 50/14. Diesel operated power generators Rs. 200/15. Grinding machine Rs. 50/16. Gas cutting set with cylinders Rs. 100/17. Compressor 600 CFM Capacity Rs. 750/18. Trucks Rs. 225/19. Car/Jeep Rs. 200/20. Pipe beveling m/c Rs. 150/21. Tractor with trolley Rs. 225/22. Tripod with 5 Tons Chain Rs. 100/Pulley Block 23. Pipe Trailor 20 T capacity Rs. 450/24. High pressure test pump Rs. 450/upto 200 Bar capacity 25. Dumper Rs. 350/26. External x-ray with generator Rs. 500/---------------------------------------------------------------------------------------------------------------

_______________________ (SIGNATURE OF BIDDER)

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 35

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ANNEXURE-12A TO SCC RECOVERY RATE FOR NON-DEPLOYMENT OF MINIMUM EQUIPMENT Sl. No.

1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29. 30. 31.

Description

Grader Dozer D7/ D6 Excavator/ Back-Hoe (≥ Hitachi 200 or equivalent) Side Boom/ Pipe Layer or equivalent JCB Or, Excavator/ Back-Hoe (≥ Hitachi 100 or equivalent) Hydra(≥ 8.5 MT)/ Crane Diesel Welding Machine/ Welding Rectifier DG Set 120 kVA + Stabilizer Automatic Bevelling Machine Internal Clamp ND 10” External Clamp ND 10”/ 6”/ 4” Internal X-ray Unit (Complete) External X-ray Unit (Complete) Gamma Ray Unit (Complete) Radiography Film Viewer Sand Blasting Unit (Complete) Air Compressor (Minimum 300 CFM) Air Compressor (Minimum 600 CFM) Holiday Detector Dewatering Pump Water Filling Pump of Adequate Capacity Pressurizing / Hydrotesting Pump – Motorised of adequate capacity Complete hydrotesting kit (dead weight tester, pressure instrument, temperature, inst. etc.) Pipe Bending Machine Horizontal Augur Boring Machine Pipe Trailor of adequate size Concrete mixture Rock breaking machine with excavator Dosing pump of adequate capacity Hand Drill (Pneumatic) with compressor Pipe Locator

Minimum Recovery Rate per day (Minimum 8 Hours) for nonmobilisation of equipment 4000 4000 3200 3500 3000 3500 2000 1600 750 600 600 4500 4500 4500 500 1000 1500 3000 400 500 500 1200 3000 4000 2700 3000 500 4000 1000 1000 500

Note: Refer SCC for detail of recovery procedure.

________________________ (SIGNATURE OF BIDDER)

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 35

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ANNEXURE-12B TO SCC RECOVERY RATE FOR NON-DEPLOYMENT OF MINIMUM MANPOWER Sl. No 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27.

Description

Linepipe Welders Station Pipeline Welders Sand Blaster Insulators Heavy Equipment Operators Other Equipment Operators Pipe Fitters Gas Cutters Radiographer Level-II Mechanic Grinder Drivers (Backhoe/ Crane/ Dover) Riggers/ Helper Survey Teams Foreman Supervisors Engineer Project Manager Engineer (M/L Civil & Mechanical) Terminal-in-charge Terminal Engineer (Mechanical) Terminal Engineer (Civil) Terminal Engineer (Electrical) Terminal Engineer (Instrumentation) Engineer (Telecom Work) QC In-charge & Engineer for Welding QC In-charge & Engineer for NDT

Minimum Recovery Rate per day (Minimum 8 Hours) for non-deployment of manpower 1500 1500 500 750 1000 750 500 300 800 500 400 1000 250 700 400 500 1200 1800 1200 1200 1200 1200 1200 1200 1200 1500 1400

The above proposed list of skilled manpower is the minimum to be deployed by Contractor

D:\HPCL-BTPL\composite works\Final tender\Annexures-SCC.doc

Page 0 of 35

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

9.0

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

PARTICULAR JOB SPECIFICATION

[CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE PROJECT]

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 1 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

CONTENTS Sl.No. 1.0

Description General & Project Description

2.0

Work Tendered

3.0

Scope of Work

4.0

Scope of Supply

5.0

Documents, Specifications, Standards & Drawings

6.0

Resources/ Facilities

7.0

Project Scheduling & Monitoring

8.0

Construction

9.0

Documentation

10.0

Survey and Level/ Setting out Work

11.0

Order of Works/ Permissions/ Right of Entry/ Care of Existing Services

12.0

Make of Material/ Bought Out Items

13.0

Inspection of Supply Items

14.0

Escalation

15.0

Documents to be submitted alongwith R.A. Bills

16.0

Insurance for Free Issue Material

17.0

Special Points pertaining to Specification

18.0

Appendix-I (List of Approved Parties for Bought out items)

19.0

Appendix-II ( Data Sheets for Mechanical Items etc.)

20.0

Appendix-III (Amendment to Technical Specification / Standard)

21.0

Annexures to PJS Annexure-I : Technical Input of Civil & Structural Works Annexure-II : Technical Input of Instrumentation Works Annexure-III : Technical Input of Telecom Works Annexure-IV : Technical Input of Cathodic Protection Works Annexure-V : Technical Input of Fire Fighting Works

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 2 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

1.0

GENERAL & PROJECT DESCRIPTION

1.1

GENERAL

1.1.1

Special Condition of Contract shall be read in Conjunction with the General Conditions of Contract, specification of work, Drawing and any other documents forming part of this contract wherever the context so requires.

1.1.2

Notwithstanding the sub-division of the documents into these separate sections and volumes every part of each shall be deemed to be supplementary to and complementary of every other part and shall be read with and into the contract so far as it may be practicable to do so.

1.1.3

Where any portion of the General Condition of Contract is repugnant, to or at variance with any provisions of the Special Conditions of Contract, unless a different intention appears, the provisions of the Special Conditions of Contract shall be deemed to over-ride the provisions of the General Condition of Contract and shall to the extent of such repugnancy, or variations, prevail.

1.1.4

The materials, design and workmanship shall satisfy the relevant INDIAN STANDARDS, the TECHNICAL SPECIFICATIONS contained herein and CODES referred to. Where the technical specification stipulate requirements in addition to those contained in the standard codes and specifications, these additional requirements shall also be satisfied.

1.1.5

Wherever it is mentioned in the specifications that the CONTRACTOR shall perform certain work or provide certain facilities, it is understood that the CONTRACTOR shall do so at his cost and the VALUE OF CONTRACT shall be deemed to have included cost of such performance and provisions, so mentioned.

1.1.6

It will be Contractor’s responsibility to bring to the notice of Engineer-in-charge any irreconcilable conflict in the contract documents before starting the work(s) or making the supply with reference which the conflict exists.

1.1.7

In the absence of any specifications covering any material, design of work(s) the same shall be performed/ supplied/ executed in accordance with Standard Engineering Practice as per the instructions/ directions of the Engineer-in-charge, which will be binding on the Contractor.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 3 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

1.2

MECON LIMITED

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

PROJECT DESCRIPTION M/s Hindustan Petroleum Corporation Limited proposed to lay 2 parallel pipeline from proposed dispatch station inside existing Bahadurgarh Terminal in Haryana to Tikarikalan Delhi Border).Three petroleum products namely ULSHSD, ULMS & SKO from existing storage tank (some future tanks also considered ) will be transported through these pipelines. Both the pipeline i.e 8”x 15 km proposed for ULMS & 10”x15km proposed for ULSHSD / SKO transportation. Will be laid in the same trench. The 8” x 15 km will transport 250 m3/hr (6 hrs pumping per day) of ULMS & 10” x 15 km will transport 350 m3/hr (6 hrs pumping per day) of ULSHSD / SKO as per requirement from Bahadurgarh Dispatch (Near Delhi Border)Terminal to proposed Tikarikalan receipt station. The following main facilities are envisaged. (a)

Pumping cum Despatch station at Bahadurgarh.

(b)

Cross country pipeline between Bahadurgarh dispatch station to Tikarikalan receipt station.

(c)

Receipt at Tikarikalan.

Products to be transported   

ULSHSD ULMS SKO

(Ultra Low Sulphur High speed Diesel ) (Ultra Low Sulphur Motor Spirit ) (Superior Kerosine Oil )

The pipeline network is enclosed MEC/23LK/05/21/M/000/1021, R0.

as

schematic

drawing

no.

Project Details Description of Sections - Mainline and Terminals 1.2.1

General The work being tendered is covered as indicated below : Main line Sl. No. 1.

Sections

Scope of Work

Bahadurgarh Despatch Terminal (HPCL premises) To Tekarikalan Terminal

- Laying of both U/G Pipeline in common trench in HPCL ROU as per alignment sheet

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 4 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd. Sl. No. 2.

Bid Doc. No.: 05/51/23LK/HPCL/001(i) Sections Tap –off cum Despatch Terminal at Bahadurgarh

MECON LIMITED

Scope of Work Mechanical: - Tap off shall be provided from existing pipeline of different product tanks as follows: - Tap off /hookup form existing product tanks out let piping For SKO,ULMS, ULMS(Future),ULSHSD and ULSHD(new) as per construction drawing. -

Installation of MOVs Installation of Filtration & Metering Facilities. Installation of Scrapper Launcher Installation of pumps (8 Nos.) Installation of TSV All connecting under ground/above ground terminal piping system Installation of TCP & impressed current permanent Cathodic Protection System Fire fighting facilities Erection of DG Set Sump Tank & Pumps Corrosion Inhibitor Dosing Pumping System, tank etc. Rupture Disk Rotometer Pumps - Complete erection & assistance in commissioning of main & booster Pumps including Instrumentation Works.

Instrumentation: - Field mounted/control room instruments as per P&ID and PJS (instrumentation) Scada & Telecommunication: - 12 Fiber OFC shall be laid in 40 mm HDPE Duct shall be used for SCADA & Tele-communication System - Hook-up with existing scada & telecom system Structural: - Construction of structural shed for main pumps & booster pump Sets . - Pipe supports Civil: - Construction of building (16 x12 sqm) adjacent to existing control room building - Area pavement , pipe supports - Extension of existing control room (3 m along length x 8 m along width). Fire fighting : Extension of fire fighting facilities.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 5 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd. Sl. No. 3.

Bid Doc. No.: 05/51/23LK/HPCL/001(i) Sections Receiving Terminal at Tikarikalan

MECON LIMITED

Scope of Work Mechanical: -Erection of Pressure control valve, basket filter,Turbine flow meter,TSV, Meter proving facilities etc Installation of MOVs Installation of Filtration & Metering Facilities. Installation of Scrapper receiver system All connecting under ground/above ground terminal piping system - Installation of TCP & impressed current permanent Cathodic Protection System - Fire fighting facilities. -

Instrumentation: - Turbine flow meter and flow computer - Field mounted/control room instruments as per P&ID and PJS (instrumentation) - Fire & leak detection system Scada & Telecommunication: - 12 Fiber OFC shall be laid in 40 mm HDPE Duct shall be used for SCADA & Tele-communication System Structural: - Construction of structural shed for main pumps & booster pump Sets . - Car Parking shed - Pipe supports Civil: -Construction of control room building ( 36 x16 sqm) -Area pavement & pipe supports - Equipment foundation - Electrical DG Room - Sump tank - SW/RW Sump and Pump House - DW Sump and pump House

1.2.2

Description of the facilities covered in the above are described in following clauses.

1.2.2.1

Tap-off (from different product tanks areas) to proposed Dispatch inside HPCL Terminal a)

The following Tap –off /hook up from the existing product tank out let piping shall be constructed :

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 6 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

Product Tanks

Existing pipeline size

Tap-off)

14” 16” -------16” ---------

14” 10” 10” 16” 16”

SKO ULMS ULMS (FUTURE) ULSHSD ULSHSD (NEW) b)

MECON LIMITED

Aboveground piping The above ground piping for different product viz. ULSHSD, ULMS & SKO size 16’’ shall be constructed between various product tank to the proposed Dispatch Terminal as per approved constriction drawing and P&IDs.

1.2.2.2

Dispatch Terminal Tap-off cum Despatch Terminal will have following facility : 1)

MOV: 2 nos. each line - 14’’ for SKO,16” for ULSHSD and 10” for ULMS.

2)

Pumping facility: Service- ULMS

a) b)

Booster Pump Mainline pump

2 nos (1 Working + 1 Sand by) 2 nos (1 Working + 1 Sand by) for ULMS service

a) b)

Service- ULSHSD/SKO Booster Pump 2 nos ( 1 Working + 1 Sand by) Mainline pump 2 nos ( 1 Working + 1 Sand by) for ULMS service Corrosion Inhibitor dosing Pumps Service Service : Corrosion inhibitor No. of Pump:

3)

2 nos for ULMS (1W+1S) 2 nos for ULSHSD/SKO (1W+1S)

Filtration Facility: Turbine Flow Meter

2 nos. (1 W + 1 S) for SKO/ ULSHSD service 2 no. (1 W + 1 S) for ULMS service

4)

Metering Facility:

2 nos (1 W + 1 S) for SKO/ ULSHSD service 2 nos (1 W + 1 S) for ULMS service

5)

Cathodic Protection : Impressed current type CP system to be provided

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 7 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

1.2.2.3

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

6)

Local PG, TG and Control Room based instruments.

7)

TSV all TSV vents shall be connected in existing system.

8)

Control room: existing control room shall be extended. Proposed facilities are to be hooked-up with the existing control system. Only field mounted and control room mounted instruments have been envisaged. A separate building shall be constructed adjustment to the existing control room building to cater the further requirement.

9)

Construction of 2 nos of pump sheds for Booster and mainline pump

10)

Existing fire fighting facilities available at Bahadurgarh Terminal end shall be utilized in receiving terminal.

11)

All associated civil, structural, electrical, instrumentation, Scada & Telecommunication work.

Proposed New Pipeline The proposed new pipeline shall be originated from Pump outlet manifold located at existing Bahadurgarh Terminal in Haryana & shall be terminate at Tikarikalan (Delhi Border). The new pipeline will be 8” O.D. & 15 km (approx.) & other will be 10” O.D. & 15 km (approx.) in length. The basic objective of these new pipeline are to transport ULSHSD/ SKO (6 hrs per day) at 350 m3/hrs & ULMS to 250 m3/hrs (6 hrs per day) to Tikarikalan.

1.2.2.3.1

Details of Proposed Pipeline Mainline Section

:

HPCL’s Despatch Terminal at Bhadurgarh to Tikarikalan Receiving Station.

Length of Pipeline

:

30 Km (Approx.) (15 km each for 8” & 10”)

Flow Rate

:

350 m3/hr (for ULSHSD / SKO) 250 m3/hr (for ULMS)

Pipeline Diameter

:

Pipeline Thickness

:

10” NB (ULSHSD/ SKO) 8 ”NB (ULMS) 6.4 and 7.1 mm

Material

:

API 5L (ERW)

Pipeline Grade

:

Gr.-B , PSL-2

Material of Construction

:

CS (Carbon Steel)

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 8 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Pipeline Rating

:

300# Rating

Corrosion Allowance

:

0.5 mm

Roughness (micron)

:

45

Pigging facilities

:

Permanent pigging facilities suitable for “Intelligent Pigs” are provided

Operating Pressure

:

20.8 kg/cm2(g) (for ULSHSD/SKO) 20.5 kg/cm2(g) (for ULMS)

Design Pressure

:

49 kg/cm2(g)

Design Temp.

:

+ 0 to 65 0C (aboveground) + 0 to 45 0C (underground)

External Coating

:

3 LPE

Pig Launcher / Receiver

:

Considered

Class Location

:

Zone-IV

Pipeline Operating Life

:

35 Years

Onstream Days/ Year

:

300 days /Year (6 hrs @ per day)

Pipeline Diameter

:

10” NB (ULSHSD/ SKO) 8” NB (ULMS)

Pipeline Length

:

(15 km each for 8” & 10” )

Design Code

:

ANSI/ ASME B31.4

Pipeline Laying

:

Buried

Sub-Soil Temperature

:

25°C through out the entire length of pipeline (1.0 meter below ground)

Pipeline Design Parameters

Pipeline Corrosion protection system:

1.2.2.4

3 LPE External Coating as well as Impressed Current Cathodic Protection System for entire pipeline.

Receiving Terminal at Tikarikalan : The following facility shall be provided at Receiving Terminal :

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 9 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

i) ii) iii) iv) v) vi) vii) viii)

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

Pressure Control Valve with Bypass Basket Filter Turbine Flow Meter Flow Computer (Panel Mounted) TSV Meter Proving Facility Leak Detection System Fire Fighting Facilities

: : : : : :

MECON LIMITED

2 No. 4 Nos. 6 Nos. 6 Nos. 20 Nos

IR Based Detection System IR based detection system having adequate nos. of fixed detectors at various critical locations in the Receiving Terminal shall be provided for continuous monitoring of hydrocarbon level in the air in the proximity of filtration, pressure reduction & metering unit, piping etc. the basis of location for the same shall be based on wind direction, component density and coverage of detections in Receiving Terminal & same shall be integrated with SCADA, RTU through serial communication. -

The panel (completely wired) for housing the monitor/ controller for detectors with delays, hooters/ annunciates indicating the location shall be provided in the control room.

viii)

Fire & leak Detection System : Suitable fire and detection system for control room and field area are to be provided with receiver instruments in control room with fire alarm siren and siren power supply shall be from 3 . The supply shall include fire detectors monitor / controllers and enunciators in fire panel to be placed in control room. The fire and detector system layout shall cover the entire plant area system as per NFPA-72 standard.

The location & type of fire and detection system to be provided in different areas in as follows : Location

Type

Detectors : Fixed Type Thermal Detector : IR Type Gas Detector : Manual Call Point / Break Glass :

Control room and in all closed room Control room Filtration, Pressure Reduction & Metering Area Exist doors of the control room building in receiving terminal.

ix)

CP System : impressed current type permanent catodic protection system shall be provided for 10’’ and 8” pipeline

x)

Civil Works :

i)

Area Pavement, Pipe Support.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 10 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ii) iii) iv) v) vi) vii) viii) ix) x) xi)

Equipment foundation for Basket Filter, Metering skid etc. Control Room Building . Electrical DG Room. Sump Tank. Area for SRVS & Control valve. Metering Basket filter and DT SW/RW Sump and Pump House. DW Sump and Pump House. Scrapper Area. Car Parking Shed.

xii)

All associated civil, structural, electrical, instrumentation, scada & Tele communication work as per repective particular job specification.

2.0

WORK TENDERED

2.1

The work tendered in this bid package consists of supply (in CONTRACTOR's scope), fabrication, installation, testing and commissioning of the terminal piping, mainline, Despatch terminal at Bahadurgarh, Receiving terminal at Tikarikalan including all equipment and Associated Mechanical, Civil, Structural, Electrical, Instrumentation & SCADA works.

2.2

All works of the section & terminals included in the scope will be done simultaneously from the date of issue of FOI. Bidder will organise equipment and manpower accordingly to meet this requirement as per instruction of Engineer-incharge.

3.0

SCOPE OF WORK The scope of work shall generally be, but not limited to the following:-

3.1

Procurement

3.1.1

CONTRACTOR shall procure and supply all the materials other than OWNER supplied materials, required for permanent installation of main pipeline and terminals in sequence and at appropriate time. All equipment, materials, components etc. shall be suitable for the intended service. Approved vendor list has been indicated in the bid package for various items. For items, which are not covered in the vendor list, CONTRACTOR shall obtain Owner’s prior approval for the vendor. Equipment requiring specialized maintenance or operation shall be avoided as far as possible. Equipment offered shall be field proven.

3.1.2

CONTRACTOR shall procure all materials, components, equipment, consumable etc. required for successful completion of the pipeline system. CONTRACTOR shall also procure and supply spares required for pre-commissioning and commissioning/ start up as recommended for all items supplied by him as per specifications provided in the bid package. Where no specification is available in the contract, the same shall be prepared by the CONTRACTOR based on the piping material specification and shall be subject to Owner’s approval.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 11 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

3.1.3

Material take-off with complete description of size, rating, material, thickness and specifications.

3.1.4

Only single offer shall be provided by the bidder fully complying to specifications/ drawings/ requirements for Owner’s review and approval. CONTRACTOR shall provide for inspection of the items at vendor's works by the OWNER/ Owner’s REPRESENTATIVE or by a reputed inspection agency and shall submit inspection reports for Owner’s clearance.

3.1.5

Stores management for contractor supply items as well as free issue materials including receipt, warehousing, preserving the material in good condition, issue of material to construction site, reconciling/ handing over surplus material to OWNER for OWNER supplied items at Owner’s store.

3.1.6

Carryout proper documentation of inspection and quality assurance programmes for all equipment and bulk materials duly approved by OWNER. CONTRACTOR shall maintain an accurate and traceable listing of procurement records for the location, quality and character of all permanent materials in the Project.

3.1.7

CONTRACTOR shall immediately report to the OWNER of all changes, which will affect material quality, and recommend any necessary corrective actions to be taken.

3.1.8

Submit periodic manufacturing progress reports highlighting hold ups and slippages, if any, to OWNER and take remedial measures.

3.1.9

Interact with authorities such as Sales Tax, Octroi, Excise, Customs etc. as necessary and arrange for transportation of the materials under his scope of supply to site.

3.1.10

All purchase requisitions including purchase orders shall be approved by OWNER/ Owner’s REPRESENTATIVE.

3.1.11

Compliance with vendor's and supplier's instructions and recommendations for transportation, handling, installation & commissioning.

3.2

Construction

3.2.1

General

3.2.1.1

All construction works shall be carried out as per "Approved for Construction" drawings, procedures, specification and applicable codes and standards. Any changes at site shall also need prior approval from the OWNER and revision of drawings. Construction drawings will be furnished to the Contractor in a phased manner and as per the requirement in accordance with the procurement and construction plan prepared and furnished by him & agreed by Owner/ Consultant.

3.2.1.2

Statutory Approvals The Owner shall provide to the Contractor free of cost the construction right-of-use

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 12 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

for the pipeline and permissions and permits (if any) necessary to lay the pipeline, systems as governed by the clauses defined elsewhere in the tender document. All other permissions, permits and licenses necessary for the performance of the work shall be obtained by the Contractor at his own cost and initiative. Insofar as any such permission, permit or license required for the performance of the work by the contractor can only be granted at the request or recommendation of the Owner, the Owner shall at the request of the Contractor, provide recommendatory letters to the contractor to obtain or procure the same. The contractor shall not, however be entitled to any additional compensation over and above contracted rates of services for any hardship or increased cost caused by any idleness, suspension or disruption of work or any other account whatsoever as a result of the inability of the contractor to obtain the permission(s), permit(s), license(s) aforesaid to match with the progress of the work nor shall the same constitute a ground for extension of time. a)

The approval from any authority required as per statutory rules and regulations of Central/ State Government, PWD, Irrigation Deptt., Pollution Control Broad (PCB), Ministry of Environment & Forest (MOEF) etc. shall be the contractor’s responsibility unless otherwise specified in the tender document. The application on behalf of the Owner for submission to relevant authorities along with copies of required certificates complete in all respects shall be prepared and submitted by the Contractor well ahead of time so that the actual construction/ commissioning of the work is not delayed for want of the approval/ inspection by concerned authorities. The inspection of the works by the authorities shall be arranged by the Contractor and necessary coordination and liaison work in this respect shall be the responsibility of the Contractor. However statutory fees paid, if any, for all inspections and approvals by such authorities shall be reimbursed at actuals by the Owner to the Contractor on production of documentary evidence.

b)

The defective work, resulting from poor workmanship and/ or material supplied by contractor, as pointed out by any statutory authority shall be rectified by the contractor at no extra cost to the Owner. Any change/ addition required to be made to meet the requirements of the statutory authorities, the same shall be carried out by the contractor free of charge. The inspection and acceptance of the work by statutory authorities shall, however, not absolve the contractor from any of his responsibilities under this contract.

3.2.1.3

The CONTRACTOR shall be responsible for claims if any arising out of damage/ obstruction to public utilities like lines of DOT etc. where the claims will cover the restoration costs as well as loss of revenue due to down time.

3.2.1.4

Providing schedules, progress reporting, organisation chart at construction site, quality assurance plan and developing quality control procedures, as per requirements indicated elsewhere in the bid package.

3.2.1.5

Coordination and supervising the work of sub-contractors.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 13 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

3.2.1.6

Transportation of appropriate materials and taking delivery of Company supply materials, store, worksite, intermediate storage points, maintaining and operating an adequate material control procedure at worksite.

3.2.1.7

Fabrication of all piping, structural components as per approved drawings.

3.2.1.8

All Civil / Structural Works, Electrical, Instrumentation & SCADA Works, laying and commissioning works shall be performed in accordance with relevant specifications and requirements enclosed elsewhere in the bid package.

3.2.1.9

CONTRACTOR shall provide complete details of manpower, equipment etc. to be deployed. Mobilising and providing all equipments, manpower (skilled and unskilled), consumable and other resources etc. for each spread as required for the execution of the complete job defined herein and thereafter demobilising the same upon completion of work.

3.2.1.10

Provide, maintain and operate all temporary facilities required for the construction related works and remove after completion of work.

3.2.1.11

Hook up/ tie-in of pipeline and piping system with terminal facilities.

3.2.1.12

All works related to testing, dewatering, swabbing, drying pre-commissioning and commissioning of the work tendered.

3.2.1.13

Idle time preservation of pipeline, if required.

3.2.1.14

All incidental and associated works and any other works not specifically listed therein but are required to be carried out to complete entire work related to pipelines and terminals.

3.2.2

Main Pipeline

3.2.2.1

Topographic Survey

3.2.2

Main Pipeline

3.2.2.1

Topographic Survey Both the proposed 10” dia. And 8’’ dia pipelines is to be laid parallel in same trench within ROU of the whole route. The available alignment sheets are enclosed with the tender. The plan and ground profile details to the extent available are being furnished to the Bidder along with bid document. Any additional topographic surveys required for local detours during execution of the project shall be carried out by Contractor in a similar manner without any extra cost to the Owner. However, laying and construction of entire pipeline including detoured portion shall be within the scope of contractor and governed by SOR of tender without any cost implication. Contractor shall be deemed to have considered such eventualities while formulating his bid. Pipeline route maps/ alignment sheets showing the pipeline route are also enclosed with the bid package.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 14 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

As-Built Alignment Sheets and P&ID drawings for scraper launcher and receiver stations are included in the Bid package. These drawings are indicative only and are furnished to enable Bidder to estimate the quantum of work and to quote a firm price for the work. Final drawings marked `Issued for Construction (IFC)' shall be furnished by Owner to Contractor at project execution stage. The IFC drawings may vary to some extent from the drawings included in the Bid Package. Contractor shall carry out all works in accordance with the IFC drawings. 3.2.2.2

Familiarization of Pipeline Route Bidders are advised to make site visits to familiarise themselves with all the salient features of subsoil, terrain and available infrastructure along the pipeline route. Contractor shall be deemed to have considered all constraints and eventualities on account of site conditions along pipeline route while formulating his bid. Contractor shall not be eligible for any compensation in terms of cost and/ or time, on account of site conditions along pipeline route varying to any extent from whatever described in the Bid Package and the drawings furnished along with the Package.

3.2.2.3

Soil Investigation Contractor has carried out soil textural classification and soil resistivity survey. It shall be Bidder's responsibility to verify the available data and satisfy himself with regard to accuracy and utility of data. Contractor shall not be entitled for any compensation in time or cost in case of any variation in actual site conditions from the data furnished in the Bid Package. It shall be Bidder's responsibility to familiarise himself with sub-soil conditions along the pipeline route, and work the lengths of pipeline to be laid in different subsoil conditions including quantum of rock excavation that would be necessary. Unit rates for pipeline construction as quoted by Bidder shall include the above and be inclusive of all excavation. No extra compensation shall be payable to Contractor for any kind of excavation whatsoever.

3.2.2.4

The agricultural fields may have lots of PVC or other pipelines being used by farmers for irrigation purposes. CONTRACTOR shall ensure that these lines shall not be damaged/ cut affecting the water supply to adjoining fields. Wherever required temporary arrangement for water flow to adjoining fields have to be maintained.

3.2.2.5

Right-of-Use (ROU) For pipeline construction purposes, in general, a 18 metre minimum wide ROU will be made available to Contractor by the Owner. Proposed 10” dia. & 8” dia pipelines are to be laid parallel in the common trench in same ROU. However, in certain restricted areas such as orchards, private holdings, congested areas, etc., the ROU may be restricted to a width less than 18m. Where the pipeline passes through forest areas, the ROU will be restricted to required width as made available by forest department. Wherever ROU is restricted to a width less than the one indicated, Contractor shall arrange at his own any additional area without cost implication. All safety precaution as per recommended practice of construction for proposed underground pipeline parallel to existing underground pipeline within same ROU shall be followed strictly to the entire satisfaction of Engineer-in-charge, before

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 15 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

carrying out any type of job for laying of underground proposed pipeline till completion of the complete work. Contractor shall carry out construction work in the width as made available to him with no time and cost implication to the Owner. It shall be Contractor's sole responsibility to make arrangement for any additional land required for fabrication, construction, storage and all other work areas, if required. The contractor shall notify the owner the probable date of commencement of work at ROU site at least two (2) weeks in advance to enable the owner to arrange handing over of the ROU/ site on the date requested. Should contractor fail in such notification, the owner shall not be liable for any claim by contractor, of whatsoever nature, for delay in the available of a ROU/ site. 3.2.2.6

"Receiving and Taking-over" as defined in the specifications of OWNER supplied externally and internally corrosion-coated and bare line pipes at Owner’s designated stacking yards/ dump site. Management of dumpsite after receiving and taking over of pipes transportation including loading/ unloading, handling, stacking, hauling and stringing of pipes from Owner’s stacking yards to Contractor’s worksite(s)/ workshop(s)/ pipeline Right-of-use (ROU), including arranging all necessary intermediate storage area(s) required thereof till the pipes are installed in permanent installation.

3.2.2.7

Carrying out inspection of OWNER supplied line pipes and pipe corrosion coating at the time of receiving and taking-over. Carrying out all repairs, to pipe and pipe coating, including supply of all materials. All handling, lifting, stacking of coated/ bare pipes required during inspection.

3.2.2.8

Carrying out repairs (including supply of all materials) of line pipe and pipe coating which will include repair of all defects/ damages occurring during transportation and / or handling after receiving and taking over.

3.2.2.9

Loading, unloading, handling, stacking, storing and transportation to workshop / work site of all materials that may be used for the construction of pipeline system either supplied by OWNER at their designated stack yard/ dump site / store and / or by CONTRACTOR as the case may be.

3.2.2.10

ROU acquisition/ permission of laying the pipeline including permission for all crossing i.e. rail, road, river, foreign hydrocarbon pipeline etc. shall be responsibility of Owner. However obtaining all necessary approvals and work permits from concerned local authorities and respective Owner’s having jurisdiction, as applicable for performing the work including shifting/ relocation and restoration of telephone/ electrical poles and underground pipes and other utilities etc. as required by local authorities and as directed by OWNER shall be responsibility of contractor.

3.2.2.10A

Part of the ROU of pipeline is rocky. Blasting is not permissible. Contractor shall deployed mechanical tools & tackles for rock breaking.

3.2.2.11

Stacking, clearing, grading, fencing of Right-of-Use (ROU) as required, trenching to all depths in all types of soil including soft, hard rock, controlled rock by special techniques, chiseling or otherwise cutting etc. to a width to also accommodate the cable conduit as per relevant standards, drawings, specification etc. Transportation

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 16 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

of coated pipes to ROU along the route, stringing, aligning, bending, welding, NDT including radiography by X-ray and ultrasonic (if required), inspection, field weld joint coating including supply of all materials, protective coating of long radius bends including supply of materials as per specifications, sand padding, laying and lowering of the pipeline, back filling, slope breakers as required, carrying out rail, road, canal, utility and submerged minor and major water course crossings including installation of carrier pipe inside casing pipe at cased crossings wherever required, bank stablisation of water course crossings as required, crossing of river/ canal by conventional method and arranging all additional temporary land/ area required for construction purposes. Supply and installation of antibuoyancy measures viz. continuous concrete coating, saddle weights, extra cover etc. on pipeline as shown in approved drawings and as directed by OWNER, installation of supports wherever required, supply of select backfill material as required, clean-up, pigging, flushing, gauging, hydrostatic testing with the quantity of inhibitor as required, dewatering with the additive, at required dosage, swabbing, pre-commissioning and commissioning of complete pipeline system, including all associated works as per relevant specifications, standards and approved drawings. 3.2.2.12

Welding of all tie-in joints including tie-in joints and bends on either side of major river crossings/ with adjoining pipeline installed by others/ other facilities as required, cutting of test header, rebevelling and tie-in with adjacent pipeline segments.

3.2.2.13

Field weld joint coating shall be by heat shrink sleeve/ other suitable material as per specification enclosed with bid package compatible of pipe coating material.

3.2.2.14

Carrying out corrosion coating of Long Radius (LR) bends if any. Coating shall be carried out by heat shrink sleeve (Raychem or equivalent) / other suitable material as per specification enclosed with bid package for field joint coating as mentioned in clause 3.2.2.13 above.

3.2.2.15

Installation of casing pipes (by open cut/ jacking/ boring) assembly, including supply of all materials (excluding free issue material if any) viz. casing pipe, casing insulators and end seals, vents and drains etc. complete, at cased crossings as per the drawings/ specifications enclosed with bid package. Cased crossings shall be installed at locations indicated in alignment sheets. The number of crossings indicated in alignment sheets is subject to change based on engineering, construction and statutory requirements or the requirements of the authority having jurisdiction over a utility crossing.

3.2.2.16

All works/ provisions including installation of slope breakers to be provided in the trench in areas where slope is more than 1 in 10.

3.2.2.17

Sand/ soft soil padding around pipe wherever required in areas where trenching has been done in rock including supply of sand/ soft soil. The thickness of sand/ soft soil padding at the bottom of pipe shall be 300mm in rocky areas.

3.2.2.18

Installation of all inline/ online instruments/ valves/ insulation joints/ appurtenances etc. as per requirements of approved drawings.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 17 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

3.2.2.19

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Crossings Major number of crossings to be encountered for this project are as under:i) ii) iii) iv) v) vi)

National Highway Crossing – 2 Nos. River Crossing – nil. approx. Railway Crossing – 2 No. Other Metal / Asphalt Road – 4 Nos. Nallah Crossing – 8 Nos. Existing pipeline crossing by HDD method – 01

For all crossing, including above mentioned shall be crossed by heaviest wall thickness carrier pipe among available pipes at site or as per approved drawings/ as decided by Engineer-in-charge. 3.2.2.19.1

Railway Crossings (If applicable as per SOR) The general arrangement drawings for railway crossings shall be approved by Indian Railways and construction shall be carried out accordingly. These drawings shall be made available to the Contractor at appropriate time during the execution of the project. Pipeline at railway crossings shall be provided with a casing pipe. The casing pipe shall be at least three nominal pipe sizes larger than carrier and shall be installed by boring/ jacking. It should be noted that the extent of casing pipe generally specified by Railways, is 15.0m beyond centrelines of the outermost tracks on either side or 0.6 meter beyond the ROU limits of railways on either side, whichever is more. All railway crossings shall be cased crossings. The railway crossing shall comply with the requirements of API 1102 and Indian Railway regulations. The crossing angle shall be as close to 90° as possible.

3.2.2.19.2

Road Crossings i)

The method of crossing of roads such as open cut/ boring shall be firmed up by Contractor in consultation with concerned authorities and Company. The Contractor shall also take due care to identify and take due precautions so as not to disturb or damage the utilities like cables, water lines and other structures.

ii)

After laying the pipeline in a road crossing by open cut method, the Contractor shall completely restore the road to its original condition.

iii)

While laying the pipeline in road crossings by open cut method the Contractor should ensure that the traffic is not stopped during the execution of work. This may be done by cutting half of the road at a time so as to enable the traffic to pass on the remaining half of the road. Alternatively, the Contractor can provide diversion roads to maintain the flow of traffic.

iv)

The Contractor shall provide proper caution boards during day time and danger lights during night time when the cutting operation of the road is going on.

For cased crossings, the pipeline should be taken through the casing pipe which should be at least 1.2 metres below the road top as specified or as per the

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 18 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

requirements of local authorities, whichever is higher. All national highway and state highway as indicated in relevant drawings/ alignment sheets/ or as directed by Engineer-in-charge shall be cased crossing. 3.2.2.19.3

Crossings of rivers/ streams/ canals by conventional method : i) ii) iii) iv) v)

vi) vii) viii) ix)

x) 3.2.2.19.4

No damage should be caused to any irrigation sources, while laying the pipeline through canal crossings. The flood banks of the River/ Canal should be brought to the original condition, if they are damaged by the laying of the pipeline. Stablisation of banks shall be carried out as per requirements of concerned authorities. In general the top of the pipeline shall be taken at least 2.5 metre below the scour level of river crossing, unless specified otherwise. The top of pipeline shall be at least 1.5m to 2.0m below the drain/ canal bed unless specified other wise. Pre-construction survey, preparation of the detailed construction methodology/ plan and time etc. shall have to be finalised by Contractor in consultation with concerned authorities having jurisdiction over canals/ rivers. Company shall provide assistance by providing introductory letters. Pre-construction surveys, preparation of detailed construction method statement and calculations for Owner’s approval. Geo-technical investigations, if required. Site preparation, arranging required land for setting up of string fabrication yard and obtaining necessary permissions from concerned authorities. Preparation of pipeline Launch way, continuous concrete coating of pipes, repair of damages to corrosion and concrete coating, string preparation, field welding, NDT including radiography, pretest of completed strings, corrosion and concrete coating of field joints, trenching, laying at approved depth, stabilisation of banks, post installation hydro-test, capping, providing and installing of markers, etc. The major canals with lining/ perennial canals need to be crossed by HDD/ boring method only.

Crossings by Horizontal Directional Drilling (HDD) Contractor shall cross the road/ canal etc. by HDD at locations as directed by Owner/ Consultant as per crossings survey drawing enclosed with tender. Before start of HDD, the contractor shall ascertain by pre-construction survey all underground obstacles namely electrical/ telecommunication cable, foreign pipeline, water line, drain/ sewerage line and prepare crossing profile drawings showing all elevations & levels. The contractor shall also ascertain, the type of soil & their terrain whether rocky or normal by way of trial pit etc. before start of job. The contractor shall submit procedure, profile drawing with complete design calculations of HDD as per requirement of ASME B31.4/ OISD norms and safety requirement that pipe is not under stress during and after crossing for Owner/ Consultant’s approval prior to start the execution of works. Contractor shall determine the minimum allowable elastic bend radius for pipe from the following considerations:

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 19 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

i)

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Maximum longitudinal stress during installation Total maximum longitudinal stress in the pipeline due to tension and bending at any location shall not exceed 90% of the SMYS of the pipe material. Contractor shall in order to check this requirement evaluate the maximum tensile forces to which the pipeline is subjected to at any phase of its installation during the pulling operation.

ii)

Maximum equivalent stress during final hydrostatic test After installation the pipeline shall be hydrostatically tested (for 6 hours) at a pressure stipulated in the Special Conditions of Contract. During hydrostatic testing the combined equivalent stress in the pipeline due to bending and test pressure shall not exceed 90% of the SMYS of pipe material.

iii)

Maximum equivalent stress during service Permissible values of maximum equivalent stress during service shall be governed by the requirements of ANSI B31.4 as applicable. The details of pipeline operating parameters are provided in the Special Conditions of Contract.

The minimum allowable radius of curvature for the pipeline shall be the highest value of the minimum pipeline elastic radius as computed from the considerations outlined in clause no. i), ii) & iii) above after correction for drilling inaccuracies (or multiplication by the factor 1.85) whichever results in the highest permissible value of minimum elastic bend radius. Contractor shall ensure all safety norms regarding distances from end point or from bottom of crossing and also ensure that external coating of pipe is not damaged during pulling & handling of pipe for crossing. For field joint coating in pipeline string made for HDD, special type of heat shrink sleeve shall be used as per specification enclosed with the tender. For line pipe coating repair, special type of high shear strength repair patch material shall be used which characteristic shall be same or equivalent as original wrapround heat shrink sleeve used in pipeline string for HDD crossing. The contractor shall ensure that no U/G existing utilities/ pipelines/ cables etc. are damaged. It shall be responsibility of contractor to compensate any loss or damage to other agency if damaged while crossing. All statutory permission from concerned authority shall be arranged by Contractor before start of job. Contractor shall deploy only HPCL’s/ MECON approved HDD Agency and approval of agency shall be sought before deploying HDD agency. 3.2.2.20

Hydrostatic Testing, Dewatering, Swabbing and Drying of Pipeline Contractor shall hydrotest the pipeline as per specification enclosed with tender. The test duration shall be minimum 24 hours. After successful completion of hydrostatic

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 20 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

testing of the pipeline, Contractor shall dewater the pipeline. The dewatering operation shall consist of at least two dewatering runs of four-cup bi-directional pigs propelled by compressed air. As a minimum, Contractor shall continue the dewatering operation until the volume of water removed by the last pig train is less than volume of 2 metres of full pipe length. After completion of dewatering operations, Contractor shall carry out swabbing of pipeline by running several pig trains consisting of high/ medium/ low density foam pigs propelled by compressed air through the pipeline. Prior to their launching, Contractor shall weigh the pigs. On arrival of the pigs at the receiving end they shall be re-weighed. The swabbing operation shall be repeated till the weight of the last received foam pig does not increase by more than 50% or 10 runs of foam pigs whichever is earlier. The pipeline/ section(s) of pipeline shall never be left empty (filled with air) after dewatering/ swabbing. Contractor shall take up dewatering and swabbing of pipeline after hydrotesting only when Contractor is ready for carrying out the drying operation immediately following pipeline swabbing. Till such time Contractor is ready to start drying of pipeline, the pipeline/ section(s) of pipeline after hydro testing shall be kept filled with inhibited water or the pipeline/ section(s) of pipeline shall not be dewatered. Preservation of pipeline using inhibited water from the time of completion of hydro testing till Contractor is ready for drying of pipeline shall be carried out by Contractor as part of his scope of work at no extra cost to Owner. After the results of swabbing operation has been accepted by Owner, nitrogen purging of line may be started for pre-commissioning activities as per specification. 3.2.2.20(A)

Leak Detection Contractor shall submit a detailed procedure for detection of anticipated/ probable leak which is likely to be found during hydro test. Such method of detection shall consume minimum possible time to complete the hydro test activity within contractual completion schedules. This procedure needs prior approval. For Major Leak/ Burst (attributable to Owner), which can be traced visually by reexcavation – rates for locating and rectification shall be paid as per item included in mainline SOR for each Leak/ Burst. For Minor suspected Leak (attributable to Owner) which can not be visually located and which requires sectionalising of pipeline or any other suitable means, rates of activities for leak detection shall be derived from rates of equipments and manpower available in the Contract. However for the pipe which needs to be replaced after the leak has been located, the payment will be made as per SOR item i.e. same as (b) above. In case after sectionalisation / other method no leak is detected, for such eventuality no payment will be made for efforts made for sectionalising/ other means.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 21 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

3.2.2.21

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Hydrostatic Test Pressure The pipeline from shall be hydrostatically tested to a minimum test pressure of 1.4 times the design pressure of 49 kg/cm2 such that the highest point of the test section shall be subjected to the same but limited to 90% of SMYS of the pipe material.

3.2.2.22

All tie-in joints including tie-ins with existing facilities, if any. All tie-ins shall be welded tie-ins.

3.2.2.23

Markers Installation of all types of markers including all associated civil works. Any other work not specifically mentioned above but required for making the entire pipeline system ready for operation.

3.2.2.24

Cathodic Protection System Cathodic Protection System is included in this tender’s scope, however for detail refer Annexure-IV of Particular Job Specification.

3.2.2.25

Priorities The Contractor shall start the execution work for entire length of mainline simultaneously and shall deploy adequate manpower, machinery, tool & tackles etc. accordingly. However, Owner may, at its sole option, assign priority of construction to either any spread or any section in spread of total pipeline length or to any part/ segment of the work. Contractor shall comply with such priority of execution and their deployment without any time and cost implication to the Owner.

3.2.2.26

Survey Pillars Owner has got the entire pipeline route surveyed and survey pillars have been established along the pipeline centreline or the ROW centreline and along the pipeline route. However, the pipeline route survey had been carried out sometime back and when Contractor mobilise at site, some of the survey pillars may be missing from ground. It shall be Contractor's responsibility to re-establish all missing survey pillars based on the survey data furnished by the Owner. Such work shall be done at no extra cost or time to Owner.

3.2.2.27

Forest/ Plantation Areas Where the pipeline route passes through forest/ plantation areas, Contractor shall clear only the minimum width required for laying the pipeline as per Owner approved procedure for pipeline construction. Number of trees/ plants to be felled down shall be restricted to a minimum. Re-plantation as per guideline / norms by Ministry of Environment & Forest.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 22 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

3.2.2.28

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Restoration of ROU Clean-up and restoration of ROW and other conveniences like road, rail, canals, cultivable land etc. to original conditions as per specification and drawings to the entire satisfaction of OWNER and/ or Authorities having jurisdiction over the same, including disposal of surplus construction materials to a location identified by CONTRACTOR approved by local authority without causing any disturbance to environment, locals and to the entire satisfaction of OWNER. Upon restoration of ROU the Contractor shall furnish documentary evidence in support of acceptance of the same duly signed by land Owner without any extra cost.

3.2.2.29

Preparation and submission of as built drawings, pipe books, documents, photographs of major activities, and project records as per specification and instructions of the OWNER including furnishing of all Test Certificates/ Inspection Reports for all materials used for permanent installation in requisite numbers as mentioned elsewhere in this document.

3.2.2.30

Idle Time Preservation of the Pipeline - DELETED

3.2.2.31

ROW Clearing During ROU clearing, the vegetation shall be cut off at ground level leaving the roots intact. Only stumps and roots directly over the trench shall be removed for pipeline installation.

3.2.2.32

Pre-commissioning and Commissioning Assistance

3.2.2.32.1

Drying and pre-commissioning including supply of all materials, consumables and manpower of the complete pipeline system and terminal piping work.

3.2.2.32.2

Making the entire system ready for commissioning and providing assistance during the complete duration of commissioning operations.

3.2.2.32.3

Completion of all mainline activities as detailed in SOR.

3.2.3

Terminals (Despatch & Receiving Terminal Station)

3.2.3.1

Piping Works • •

Erection of all valves and equipments viz. Basket Filter, Pumps, scraper launcher/receiver, sump tank etc. as detailed in SOR. Supply of assorted pipe, fasteners, gaskets, fittings, flanges & utility piping & piping supports and other supply wherever specified as per SOR.



Taking delivery of free issue materials from HPCL’s designated stores and its transportation to site.



All fabrication, erection, testing and commissioning of piping above ground at all elevations and below ground at all depths including installation of scrapper

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 23 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

traps, pig handling system, all valves and valve actuators, insulating joints, pig signallers, flow tees, TSV and other fittings and associated piping works as per drawings and specifications. All mechanical works of under ground and above ground, complete piping including fabrication, welding, all non destructive testing of welds repairs/ pretesting, hydrostatic testing, cleaning/ flushing, functional testing, cutting of mainline and bevelling (if required), excavation in all types of soil for installation of piping and pipe supports.

3.2.3.2

• •

Installation of all inline/ online instruments. Obtaining all necessary approvals and work permits from concerned local authorities having jurisdiction including hot work permit as applicable for performing the work.



Carrying out welding including cutting, edge preparation (inclusive of grinding the edges on fittings, flange, etc. to match with the matching edges of different thickness wherever required, bending, pre-heating wherever required, NDT including radiography of gamma-ray and other non-destructive tests specified. NDT requirements for process and other piping shall be in accordance with relevant specifications enclosed with the tender document.



Preparation of isometric drawings and final bill of material based on piping GAD supplied by MECON.



Cleaning and servicing of all free issue materials including equipment, valves to make it suitable for installation.



All utility and fire hydrant lines as detailed in SOR.



Completion of all piping and mechanical works as detailed in SOR.



Terminal station piping shall be hydrostatically tested to the test pressure in accordance with Specification for piping fabrication, erection. Test pressure shall be 1.4 times design pressure and minimum duration of test shall be six (6) hours. All ball and plug valves in the piping network being hydro tested shall be kept in the partially open position.

Equipment and Vessels Installation of scrapper launcher and receiver including pig handling system, Basket Filters, TSVs & Pumps etc. along with other vessels as detailed in SOR.

3.2.3.2A

Erection of Rotating Equipment (Main Pump & Booster Pumps) Transportation of Rotating Equipments and accessories from Owner’s stores to site, assembly of sub-assemblies / parts, erection of Rotating Equipments on foundation, levelling, aligning and grouting, preparation of Rotating Equipments for trial runs, carrying out no load / trial runs, return of any unused material to the owners store sand hand over in fit condition for the start-up of the Plant, as per instructions of Engineer-in-charge. Defects due to Contractor’s fault noticed during trial runs shall be rectified by him. The detailed indicate in SOR estimated numbers, dimensions and weights of the

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 24 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Rotating Equipments. The actual data dimensions and weights will be in the vendor data manuals. The term Rotating Equipments signifies all pumps, compressors, steam & gas turbines, diesel engine / steam turbine / gas turbine generator sets along with drivers accessories & auxiliary systems. 

DRAWINGS, SPECIFICATIONS AND CODES: The following drawings will be provided by the Owner, which are to be followed for erection of each Rotating Equipment.



i)

General Arrangement foundation details.

drawings

with

outline

dimensions

including

ii)

Manufacturer's instruction manuals / erection drawings as available from them.

ERECTION OF ROTATING EQUIPMENTS : -

All Rotating Equipment erection shall be done by experienced fitters. For this purpose the contractor shall employ experienced and suitably qualified erection supervisor and crew who have done similar jobs.

-

The Rotating Equipment manufacturer's instructions as available regarding installation and trail runs will be passed on to the Contractor during the course of work, The requirement prescribed therein shall be met in addition to what is stated in these specifications. Erection shall be carried out as per instructions of the Rotating Equipment manufacturer’s representative, whenever present at site. In all other cases instructions of the Engineer-incharge, regarding procedure / sequence of erection shall be binding on the contractor.

-

For all Rotating Equipment, the Contractor shall follow the proper sequence for assembly and erection. Couplings of rotating equipment received along with driver in assembled condition, shall be dismantled by the Contractor, if required and alignment shall be rechecked. Realignment, if required, shall be done before recoupling.

-

Where drivers and couplings are provided separately, drilling and tapping of holes in the base plates for fixing drivers, fixing of coupling on shafts, after enlarging the pilot bores to the correct size with key way etc. and dowelling including provision of dowel pins bores to the similar arrangements for retaining the alignment shall be carried out by the Contractor as part of erection work. Shims & wedges as required for

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 25 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

alignment shall be supplied by the contractor. The contractor's quoted rates shall be deemed to be inclusive of these of works / supplies. -

All process and utility (such as cooling water, steam flushing, quenching, lubricating oil, sealing etc.) connections connected with rotating equipment and its auxiliaries shall be fabricated and / or installed by the Contractor from materials supplied by the Owner as per drawings, specification and instructions of the Engineer-in-charge.

-

All piping and accessories supplied with the rotating equipment such as seal oil system cooling water system & Lube oil system etc. shall be tagged separately and kept in Contractor's stores till erection. All flanged connections and openings snail be kept blanked with dummies / plugs to prevent entry of foreign matter.

-

All the instruments such as pressure gauges, sight glasses, temperature recorders etc. including instrument panels, if any, with necessary connections, shall be installed by the Contractor as part of rotating equipment erection and no separate payment will be made.

-

After initial alignment, the Rotating Equipment shall be properly grouted. Grouting shall be carried out as per the specifications and instructions of Engineer-in-Charge. Wherever grout holes are provides in the base plates, grout shall be filled through them also.

-

The special grouting materials used i.e. whether non-shrinking grout or epoxy grout shall be as per the equipment manufacturer's specifications.

-

Unless otherwise specified by the equipment manufacturer, the grouting material shall be non-shrinking grout of pre-mix type with a minimum compressive strength (28 day) of 40 N/mm2. The grout material shall be supplied and applied by the contractor and deemed to be included in the quoted rates in the Schedule of Rates (SOR).

-

Where the equipment manufacturer recommends epoxy grout, the same shall be supplied and applied by the contractor. Extra cost for the same shall be applicable as quoted by the contractor in the Schedule of Rates (SOR).

-

After the piping has been connected, the alignment shall be re-checked by the Contractor, to ensure that piping connections do not induce any undue stresses on the Rotating Equipments. After making necessary corrections on the piping, if any, re-alignment shall be done by the Contractor and he will ensure that no undue stresses are induced on the Rotating Equipment.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 26 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.



Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

SPECIAL INSTRUCTIONS -

Contractor in addition to general instructions for erection as out lined in para above, shall also follow the following special instructions. Pumps Pumps shall be supplied for erection as follows :

3.2.3.3

(a)

Pumps with drivers and accessories fully assembled on a common skid (Base plate).

(b)

Pumps mounted on base plate and couplings and driver supplied loose in separate packings.

(c)

Various major components such as pump, drivers, couplings, gear boxes & base plates in separate packings

Civil & Structural Works Civil Works Civil works shall be carried out as per the scope detailed in particular scope of work as detailed in Technical Input (Annexure-I) and SOR. Structural Works Structural works shall be carried out as per the scope detailed in particular scope of work as detailed in Technical Input (Annexure-I) and SOR.

3.2.3.4

Instrumentation Instrumentation works shall be carried out as per the scope of work as detailed in Technical Input (Annexure-II) and SOR enclosed elsewhere with the tender.

3.2.3.5

Telecom Telecom works shall be carried out as per the scope of work as detailed in Technical Input (Annexure-III) and SOR enclosed elsewhere with the tender.

3.2.3.6

Cathodic Protection System Cathodic Protection System works shall be carried out as per the scope of work as detailed in Technical Input (Annexure-IV) and SOR enclosed elsewhere with the tender.

3.2.3.7

Fire Fighting System Fire Fighting System works shall be carried out as per the scope of work as detailed in Technical Input (Annexure-V) and SOR enclosed elsewhere with the tender.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 27 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

3.2.3.8

3.2.3.9

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Painting •

Painting (including supply of all materials) of all equipment, piping, structural steel elements for pipe supports, and all structural miscellaneous items as required and as directed by Company. Paint shall be suitable for highly corrosive environment as per specification providing total DFT of 345 minimum as per Specification No. 05/62/S/07A. Painting shall include primer and finish coats as per specifications. Prior to painting surface shall be sand blasted as per instruction of Engineer-in-charge.



Wherever the gas charged piping network exists, the sand blasting may be replaced by soft material such as copper grit blasting to avoid sparking.



For equipment, valves and other free issue items only one finish coat of final paint will be provided.

Other Works •

Obtaining all necessary approvals and work permits, as applicable, for performing the work.



Carrying out all additional surveys, test and collection of data not furnished by company but required for construction of facilities.



Provision is to be kept in the terminal for installation of Permanent Cathodic System.



Extension/ provision of the utilities at desired locations from the consumers battery limit; the utilities are firewater, instrument air, plant air, drinking water, service water and electrical power.



Any other work not specifically listed herein but required for the construction of the terminals and making it ready for the operation.

4.0

SCOPE OF SUPPLY

4.1

Material to be supplied by Company as Free Issue

4.1.1

Linepipe (Bare/ Coated) Three Layer PE Coated line pipes as per details indicated in clause 1.2 Company shall supply bare and externally corrosion coated line pipe with 3-Layer polyethylene coating. Contractor shall receive and take over the pipes at designated place of issue from coating supplier at their works. At the time of taking-over contractor shall perform inspection of pipes and pipe coating and record all defects noticed in the presence of Company’s Representative. Contractor shall repair all defects recorded at the time of taking-over of pipes, and shall be compensated as per rates set forth in the Schedule of Rates.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 28 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Any repairs to 3-Layer Polyethylene coating shall be carried out by Contractor using suitable material compatible with parent coating system and meeting the requirements of coating system specified in specification for 3-layer polyethylene coating. The coating repair material and procedure for application shall be submitted to MECON for approval prior to start of construction. 4.1.2

All types of valves i.e. Ball, Globe, Gate, Plug & TSV , ARV and Check Valves valves only Size 8’’ and above. Rest of the valve size 6‘’ and below are in contractor scope of supply.

4.1.3

Flow Control Valve

4.1.4

Turbine Flow Meter

4.1.5

Centrifugal Pumps

4.1.6

Basket Filters

4.1.7

Surge relief system

4.1.8

Density transmitter

4.1.9

Scrapper Launcher & Receiver

4.1.10

DG Set

4.1.11

Mechanical, Instrumentation, SCADA, Civil & Structural items as elaborated in respective scope of supply and SOR enclosed elsewhere with the tender document.

4.2

Company storage point for issue of materials shall be from the Company’s store as indicated below: Line pipe shall be issued at designated store of HPCL. Contractor has to lift, coated pipe from storage/ dumpyard located Bahadurgarh. However, other free issue materials as soon as reached at site, HPCL may directly hand over the same to contractor at site or shall hand over from its store / dump yard at Bahadurgarh and from nearby storage yard in the region. Contractor shall preserve the received material in good condition along with required documentation as per clause no. 4.3 mentioned below. Contractor shall also return materials after completion of work to HPCL’s designated store at above-mentioned location as directed by Owner/ Engineer-in-charge.

4.3

Conditions for issue of Company Supplied Material Contractor shall prepare and submit Material Issue Vouchers to enable stage wise issue of materials. All materials shall be issued for incorporation in permanent works only and shall not be used for any temporary or ancillary works without the written consent of Engineer-in-charge. These materials shall be issued to the contractor from the Owner’s storage points. Contractor shall be responsible, at this own cost, for lifting of the materials from Owners issue points, measuring, weighing, loading, unloading, transportation and return of materials to designated storage points. Contractor shall also be responsible for constructing covered godowns with adequate supports and clearances

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 29 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

for safe storage of materials. Every month the contractor shall submit an account for all the materials issued by the owner in the proforma prescribed by the Engineer-in-charge. On completion of the work, the contractor shall submit materials appropriation statement for all materials issued by Owner. 4.3.1

All materials issued by the COMPANY to the CONTRACTOR shall be preserved against deterioration and corrosion. Any damages/losses suffered on account of poor or improper storage while under CONTRACTOR'S custody and non-compliance with the requirements stipulated herein shall be considered as losses suffered due to willful negligence on the part of the CONTRACTOR and he shall be liable to compensate the COMPANY, for the losses suffered, at penal rates as elaborated elsewhere in the bid document. Various equipments/ materials intended for the installation will be received by COMPANY in unpacked, skidded, crated, packed or loose condition and will be stored in the COMPANY warehouses & open yards. In general, material will be issued to the CONTRACTOR in "as-received" condition. It will be the CONTRACTOR'S responsibility to draw, load and transport all materials from COMPANY's designated place (s) of issue to the point of installation. All materials supplied by the COMPANY shall be duly protected by the CONTRACTOR at his own cost with appropriate preservative like primer/lacquer coating, grease etc, if required. The Contractor shall be required to take Insurance Cover in terms of general conditions of contract.

4.3.2

The CONTRACTOR shall check that valves, fittings and pipes are not subject to corrosion from hydrostatic test liquid remaining saturated in the packings. Any such conditions when detected should be brought to the notice of the Engineer-in-charge and remedial measures taken as directed. Small and medium size pipe fittings shall be stored in rack to be constructed from this purpose in a covered godown. When large size pipe fittings are to be stored, these may be kept in the open on surfaced storage yards on proper wooden supports.

4.3.3

All machined surfaces shall be properly greased and shall be maintained and protected from damages.

4.3.4

Openings of equipment, machinery, valves etc. shall be kept blocked/ covered with blinds to prevent entry of foreign matter.

4.3.5

All valves, instruments, control valves, actuated valves, pressure gauges, thermometers etc. supplied independently, as well as alongwith equipment and machinery shall be stored separately, inside the covered godown on racks.

4.3.6

As far as possible materials shall be transported to the erection site, just prior to their actual erection and shall not be left laying around indefinitely. Instructions for the Engineer-in-charge shall be followed strictly in this regard.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 30 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

4.3.7

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Repairs of Pipe Defects Immediately prior to aligning pipe for welding, the bevelled ends of each joint of pipe and the area immediately adjacent thereto (at least 25 mm from the edge on the inside and outside of the pipe) shall be thoroughly cleaned of paint, rust mill scale, dirt or other foreign matter by use of power driven wire buffing wheels, disc sanders, or by other method approved by COMPANY. This shall be done at no extra cost. All damaged ends of pipe that are bent, cut or otherwise mutilated such that, in the opinion of the COMPANY, faulty alignment or unacceptable welding would result, shall be repaired or cut-off and rebevelled to the correct angle with a bevelling machine of a type approved by COMPANY. No compensation shall be allowed by reason of such re-cutting or bevelling, except when required because of the original bevel being damaged before the pipe is "taken over" by CONTRACTOR. Dents in bevels with a depth of less than 1 mm shall be removed by CONTRACTOR during cleaning and grinding, ahead of the welding in the field. No compensation shall be paid to Contract or on this account. CONTRACTOR shall rebevel dented bevel ends with a depth of dent between 1 and 3 mm. Dents over 3 mm depth shall be repaired by cutting and rebevelling. The CONTRACTOR shall be entitled for extra compensation only for cutting and rebevelling of defects recorded at the time of taking delivery as per the rate set forth in the "Schedule of Rates".

4.4

Material to be Supplied by Contractor The procurement and supply, in sequence and at the appropriate time, of all materials and consumables required for completion of the work as defined in this Bid document except the materials specifically listed under para 4.1 above, shall be entirely the CONTRACTOR'S responsibility and item rates quoted for the execution of the CONTRACT shall be inclusive of supply of all these materials. The material to be supplied by the Contractor shall be as per specification and preferred make as indicated in Appendix-I or duly approved / recommended for use by HPCL/ MECON. The materials will be, but not by way of limitations, as follows:-

4.4.1

Mainline

4.4.1.1

Field joint coating material for 3 layer PE coated pipes comprising of heat shrinkable wrap around sleeves (HTLP 80 or equivalent) complete with adhesive/ other suitable material compatible with pipe coating material. Special sleeve for HDD string as per specification. The cutback length shall be 120 + 25(-0)mm.

4.4.1.2

Coating repair material compatible and suitable for 3 layer PE coated line pipe comprising of repair patches complete with adhesive.

4.4.1.3

All materials for all types of pipeline markers including cement, sand, reinforcements, structural steel etc.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 31 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

4.4.1.4

All materials required for continuous concrete coating/ saddle weights for providing negative buoyancy to the pipeline wherever required.

4.4.1.5

Supply of nitrogen and other consumables, tools and tackles required for venting, predrying, purging and filling of mainline.

4.4.1.6

Supply of bare casing pipe including all other material like casing insulators, end seals, vent & drain assembly etc. for cased crossing if required as indicated in SOR.

4.4.1.7

All other items/ materials as may be required for completion of contractual scope of work and not covered under material to be supplied by company as free issue material at 4.1.

4.4.1.8

Supply of Long Radius Bends in Contractor scope as detailed in SOR. However, bare pipe shall be free issue.

4.4.2

Terminals

4.4.2.1

Piping, Equipment & Vessels a) b) c) d) e) f)

Piping material assorted pipe, flanges, and fittings in Contractor’s scope as detailed in SOR. Contractor shall supply complete material for utility lines indicated in SOR. Studs, nuts, washers, U bolts, clamps, clips, pipe supports, gaskets for piping works. Shims, wedges and packing plates (machined wherever required). Galvanized steel piping of all sizes for instrument air/ service air. Fire fighting system as indicated in SOR. Painting material

All other items/ materials as may be required for completion of contractual scope of work and in SOR but not covered under material to be supplied by company as free issue material at 4.1. 4.4.2.2

Civil & Structural All materials as elaborated in respective SOR and scope of work enclosed as Annexure-I elsewhere with the tender.

4.4.2.3

Instrumentation All instrumentation item as per particular SOR and scope of work for instrumentation item Annexure-II SOR in Contractor’s scope of supply.

4.4.2.4

Telecom All telecom item as per particular SOR and scope of work for instrumentation item Annexure-III SOR in Contractor’s scope of supply.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 32 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

4.4.2.5

All painting materials. Paint shall be suitable for highly corrosive environment.

4.4.2.6

Detailed list of items to be procured and supplied by contractor for mainline & terminal shall be as indicated below:i) ii) iii) iv) v) vi) vii) viii) ix) x) xi) xii) xiii) xiv) xv) xvi) xvii) xviii) xix) xx) xxi)

Joint Coating Sleeves LR Bends (Pipe by Client) Insulating Joints Flow tees TSVs U/G sump tanks, sump pumps 4 nos. Strainer Coating Repair Material C P system (TCP & PCP) Corrosion inhibitor dosing system tank, pumps set and associated items. Fire Fighting System Air Conditioners Special Sleeves for HDD Strings Assorted Pipe Flanges Fittings ‘T’ Type Strainer Control Panel & Field Mounted Instruments SCADA Instrumentation Items Any other item required to complete the job/ as indicated in SOR.

4.4.3

General

4.4.3.1

All consumables for welding such as oxygen, acetylene, inert gases and all types of electrodes suitable for pipes of grades as specified in the specification, low hydrogen electrodes, filler wire, solder wire, brazing rods, flux etc. for welding / cutting and soldering purpose.

4.4.3.2

Equipment like hydrostatic pump etc., water and corrosion inhibitor for water used for hydrostatic testing including all pipes, fittings and equipment, metallic blinds, temporary gaskets as required for filling, pressurising and dewatering in connection with hydrostatic testing completion.

4.4.3.3

All pigs for cleaning, gauging, filling, dewatering and swabbing of pipeline.

4.4.3.4

All pipes, fittings and equipment metallic blinds temporary gaskets as required for filling, pressuring and dewatering in connection with hydrostatic testing completion.

4.4.3.5

All consumables for welding of structural steel.

4.4.3.6

Materials and equipment required for all types of test such as radiography, magnetic particle and dye penetrant examination.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 33 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

4.4.3.7

All safety tools/tackles, devices / apparatus / equipment etc. including ladders and scaffoldings etc. complete as required.

4.4.3.8

Supply of nitrogen and other consumables, tools and tackles required for venting, predrying, purging and filling of station piping.

4.4.3.9

Any other material not specifically listed herein, but required for the execution of the work.

4.4.3.10

List of materials required to be supplied and quantities indicated in SOR is tentative. These quantities can vary during execution to any extent and the same unit rate shall be applicable for payment. Final quantities will be based on the drawing issued to the contractor for construction. Quantities covered in SOR are for as erected quantities. Bidder will procure additional materials as required to cover cutting, scraps, wastages and damages during erection, testing and commissioning. For these extra quantities no additional payment will be made.

5.0

DOCUMENTS, SPECIFICATION, STANDARDS AND DRAWINGS

5.1

Owner shall furnish piping and Instrumentation diagrams (P & I D), preliminary plot plan for the construction of Terminal alongwith the tender. Owner shall also supply design & engineering drawings and construction drawings including general arrangement drawings for piping, electrical, mechanical & instrumentation systems and other related/ required systems, at appropriate times and as requisitioned by contractor in his time schedule.

5.2

Contractor shall prepare isometric drawings & bill of materials and submit the same for Owner/ Consultant’s approval/ record. Contractor shall prepare drawing for utilities line as required as per SOR and submit the same for Owner/ Consultant’s approval/ record.

5.3

No construction small or big shall be carried out without proper construction drawings duly approved by Owner's Engineers at Delhi or site office or Owner's representative duly authorised to do so. For Mainline route survey alignment sheets and crossing survey details shall be furnished alongwith bid by Owner. However, detail crossing drawings with crossing methodology shall be submitted by Contractor for prior approval. Any additional survey and data required to complete above shall be done by Contractor without any extra cost.

5.4

After Completion of construction & commissioning of Terminal, Contractor shall incorporate all the correction in drawings, prepare and issue the drawings "as-built drawings" as listed below to Owner as final submission of drawings. For Mainline pipeline alignment sheet, all X-ing details, all CP drawings, pipe book etc. and for Terminals P&ID, layout drg., piping GAD, Isometric, all electrical & instrumentation drg., all civil drawings. For final submission only 4 sets of documents plus the original transparencies shall be handed over by Contractor. Any construction done by Contractor without duly approved drawings shall be wholly at his risk and cost.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 34 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Contractor shall also submit soft copy of pipe book in excel alongwith hard copy. Soft copy of all as-built drawings shall be also submitted in AutoCAD. Video graphy/ photograph of all major activities/ milestone achieved shall also be arranged and submitted by the Contractor. For details of documentation to be submitted for mainline and terminal refer enclosed specification for documentation for pipeline construction Specification NO. MEC/S/05/62/09R enclosed elsewhere with the tender. 5.5

Specifications The work shall be carried out by CONTRACTOR strictly in accordance with the following specifications enclosed in Volume II of this document: VOLUME-II OF IV

1.

Specification for Mainline Construction (Onshore)

MEC/S/05/21/01

2.

Specification for Welding of Onshore Gas Pipelines

MEC/S/05/21/02

3.

Specification for Hydrostatic Testing of Onshore Pipeline

MEC/S/05/21/03

4.

Specification for Major Water Crossings (Conventional)

MEC/S/05/21/04

5.

Specification for Pipeline Crossing Roads, Railroads, Minor Water and Other Crossings

MEC/S/05/21/05

6.

Specification for Piping Fabrication and Erection

MEC/S/05/21/06

7.

Specification for Shop and Field Painting

MEC/S/05/21/07

8.

Specification for Repair of Pipeline Corrosion Coating

MEC/S/05/21/08

9.

Specification for Pipeline Markers

MEC/S/05/21/10

10.

Specification for Flushing and Testing of Piping Systems

MEC/S/05/21/11

11.

Specification for Casing Insulators and End Seals

MEC/S/05/62/12

12.

Specification for Field Joint Coating (Onshore Pipelines)

MEC/S/05/21/13

13.

Specification for Vents, Drains and Wells

MEC/S/05/21/15

14.

Specification for Temporary Cathodic Protection System

MEC/S/05/21/016A

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 35 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

15.

Specification for Permanent Cathodic Protection System

MEC/S/05/21/016B

16.

Specification for Corrosion Survey

MEC/TS/05/21/016C

17.

Specification for Gaskets, Bolts and Nuts

MEC/S/05/21/19

18.

Specification for Sump Tank

MEC/S/05/21/21A

19.

Specification for Centrifugal Pump

MEC/S/05/21/24A

20.

Specification for Reciprocating Pump (Metering)

MEC/S/05/21/24B

21.

Specification for Piping Material Specification

MEC/23LK/05/21/M/000/1092

22.

Specification for Pre-Commissioning and Commissioning

MEC/S/05/21/61

23.

Specification for Health, Safety and Environment Management (HSE)

MEC/S/05/21/65

24.

Specification for Quality Assurance System Requirements

MEC/S/05/62/66

25.

Specification for Documentation for Pipeline Construction

MEC/S/05/21/69

26.

Specification for Caliper Pigging

MEC/S/05/62/70

27.

Specification for Field Joint Coatings of Pipeline for HDD Crossing

MEC/S/05/21/74

28.

Specification for Pipeline Crossings Using HDD Method

MEC/S/05/21/75

29.

Specification for Long Radius Bends

MEC/TS/05/62/015, R-1

30.

Specification for Seamless Fittings and Flanges [Size up to DN 400mm (16") NB]

MEC/S/05/21/025

31.

Specification for Assorted Pipes

MEC/TS/05/62/059A

32.

Specification for Ball Valves

MEC/TS/05/21/002

33.

Specification for Plug Valves (NB>2)

MEC/TS/05/62/003, Rev-2

34.

Technical Notes for Gate & Globe Valves

-

35.

Specification for Insulating Joints

MEC/TS/05/21/009

36.

Specification for Y / T Type Strainer

MEC/TS/05/21/010

37.

Fire Alarm System

MEC/TS/05/21/081H

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 36 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

38.

Medium Velocity Water Spray System

MEC/TS/05/21/081K

39.

Deluge Valve

MEC/TS/05/21/081F/B

40.

Landing Valve

MEC/TS/05/21/081E

41.

Water Monitor

MEC/TS/05/21/081C/A

42.

Hose Cabinet

MEC/TS/05/21/081O

43.

Hose Pipe

MEC/TS/05/21/081C/B

44.

DCP Type Portable Extinguisher

MEC/TS/05/21/081D/A

45.

CO2 Type Portable Extinguisher

MEC/TS/05/21/081D/B

46.

Fire Bucket

MEC/TS/05/21/081D/D

47.

Fire Man’s Axe

MEC/TS/05/21/081C/C

48.

Gas Flooding System

MEC/TS/05/21/081L

49.

First Aid Hose Reel

MEC/TS/05/21/081P

50.

Stand Post Type Fire Hydrant

MEC/TS/05/21/081N VOLUME-III

1.

Technical Specification for Civil & Architectural Works

2.

Technical Specification for Structural Works

3.

Specification for Installation of Instruments

MEC/S/05/26/01

4.

Specification for Instrument Tubing

MEC/S/05/26/02

5.

Specification for Inlet Outlet Sections & FS

MEC/S/05/26/03

6.

Specification for Instrument Tube Fittings

MEC/S/05/26/04

7.

Specification for Instrument Valves and Manifolds

MEC/S/05/26/05

8.

Specification for Junction Boxes and Cable Glands

MEC/S/05/26/06

9.

Specification for Signal Cable

MEC/S/05/26/07

10.

General Technical Specification for Instrumentation

MEC/S/05/26/08

11.

Specification for Cabling

MEC/S/05/26/21

12.

Specification for Earthing

MEC/S/05/26/23A

13.

Specification for Optical Fiber Cable & HDPE Duct Laying and Associated Work

MEC/S/05/E5/T/001

14.

Specification / Procedure for Optical Fiber Cable Testing

MEC/S/05/E5/T/002

15.

Technical Specification for Optical Fiber Cable & Accessories

MEC/TS/05/E5/T/096

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 37 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

16.

Technical Specification PLE HDPE Telecom Duct and Accessories

MEC/TS/05/E5/T/037

17.

Technical Specification of Warning Mats for OFC & Telecommunication HDPE Duct

MEC/TS/05/E5/T/042

Drawings 5.6

The following drawings are included in Vol-IV of the bid package for BIDDER’s reference purpose only; Bidders are advised to go through these drawings and also visit the site before submitting their bids. The Contractor shall develop the drawings for all crossings and detour of pipeline alignment. VOLUME-IV

I.

Mechanical Drawings

1.

Schematic Route Diagram

MEC/23LK/05/21/M/000/1021

2.

P&I Diagram for Bahadurgarh Despatch Station Suction Manifold

MEC/23LK/05/21/M/001/1001, (Sheet 1 of 7)

3.

P&I Diagram for Bahadurgarh Despatch Station Booster Pumps (ULSHSD / SKO)

MEC/23LK/05/21/M/002/1001, (Sheet 2 of 7)

4.

P&I Diagram for Bahadurgarh Despatch Station Main Line Pumps (ULSHSD / SKO)

MEC/23LK/05/21/M/003/1001, (Sheet 3 of 7)

5.

P&I Diagram for Bahadurgarh Despatch Station Booster Pumps (ULMS)

MEC/23LK/05/21/M/004/1001, (Sheet 4 of 7)

6.

P&I Diagram for Bahadurgarh Despatch Station Main Line Pumps (ULMS)

MEC/23LK/05/21/M/005/1001, (Sheet 5 of 7)

7.

P&I Diagram for Tikrikalan Receipt Station (Filtration)

MEC/23LK/05/21/M/006/1001, (Sheet 6 of 7)

8.

P&I Diagram for Tikrikalan Receipt Station (Metering and Sump Tank)

MEC/23LK/05/21/M/007/1001, (Sheet 7 of 7)

9.

Overall Plot Plan for Tap-off, suction manifold & Despatch Terminal at Bahadurgarh

MEC/23LK/05/21/M/001/1011

10.

Plot Plan for dispatch Terminal at Bahadurgarh

MEC/23LK/05/21/M/002/1012

11.

Plot Plan for Receiving Terminal at Tikrikalan

MEC/23LK/05/21/M/004/1013

12.

Detail of Trench Dimension & Backfilling for U/G P/L

MEC/23LK/05/21/M/000/1029

13

Drawing of ‘T’ Type Strainer

MEC/23LK/05/21/M/001/2010

14.

Drawing of Sump Tank

MEC/23LK/05/21/M/000/VS-001

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 38 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd. 15.

16. 17. 18. 19. 20. 21. 22.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Alignment Sheets (Tikrikalan Spur Line) SECTION: BAHADURGARH TO TIKRIKALAN Chainage 0/000.00 KM TO 1/750.00 KM

HPCL/MDPL/TSL/ALN-01

Alignment Sheets (Tikrikalan Spur Line) Chainage 1/750.00 KM TO 3/500.00 KM

HPCL/MDPL/TSL/ALN-02

Alignment Sheets (Tikrikalan Spur Line) Chainage 3/500.00 KM TO 5/250.00 KM Alignment Sheets (Tikrikalan Spur Line) Chainage 5/250.00 KM TO 7/000.00 KM

HPCL/MDPL/TSL/ALN-04

Alignment Sheets (Tikrikalan Spur Line) Chainage 7/000.00 KM TO 8/750.00 KM

HPCL/MDPL/TSL/ALN-05

Alignment Sheets (Tikrikalan Spur Line) Chainage 8/750.00 KM TO 10/500.00KM

HPCL/MDPL/TSL/ALN-06

Alignment Sheets (Tikrikalan Spur Line) Chainage 10/500.00KM TO 11/858.84 KM

HPCL/MDPL/TSL/ALN-07

HPCL/MDPL/TSL/ALN-03

Crossing Sheets (Tikrikalan Spur Line) a) b) c) d) e) f) g) h) i) j) k) h)

B.G. Northern Railway Main Line Crossing Asphalted Road Crossing Mud Road Crossing Drain Crossing Asphalted Road Crossing Drain Crossing Major District Road- 138 Crossing Asphalted Road Crossing Mumgashpur Drain Crossing Mud Road Crossing B.G. Northern Railway Main Line Crossing Asphalted Road Crossing

HPCL/MDPL/TSL/CS-01 HPCL/MDPL/TSL/CS-02 HPCL/MDPL/TSL/CS-03 HPCL/MDPL/TSL/CS-04 HPCL/MDPL/TSL/CS-05 HPCL/MDPL/TSL/CS-06 HPCL/MDPL/TSL/CS-07 HPCL/MDPL/TSL/CS-08 HPCL/MDPL/TSL/CS-09 HPCL/MDPL/TSL/CS-10 HPCL/MDPL/TSL/CS-11 HPCL/MDPL/TSL/CS-08

23.

Route Map

HPCL/MDPL/TSL/RM-01

24.

Resistivity Report

To be collected from MECON, Delhi office

II.

Civil/ Structural Drawings 1. 2. 3. 4. 5. 6.

Standard Details of Septic Tank & Soak Septic Tank and Soak Pit Main Pump House at Despatch Terminal Bahadurgarh Booster Pump House at Despatch Terminal Bahadurgarh Typical Details of Chain link Fencing & Gate Dosing Shed at Despatch Terminal Bahadurgarh Car Parking Shed at Receiving Terminal Tikrikalan (Plan of columns, cross-section & elevation).

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

MEC/05/011/STD/01 (3 Sheets) MEC/23LK/05/12/S/00/1066 MEC/23LK/05/12/S/00/1067 MEC/23LK/05/12/S/00/1070 MEC/23LK/05/12/S/100/1069 MEC/23LK/05/12/S/004/1068

Page 39 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd. III

3. 4. 5. 6.

MCC Room Building at Despatch Terminal Control Room Building for Receiving Terminal at Tikrikalan New Control Room Building for Despatch Terminal at Bahadurgarh Electrical Room Building at Tikrikalan Extension of Existing Control Room Building for Despatch Terminal at Bahadurgarh Sub Station at Despatch Terminal at Bahadurgarh

MEC/23LK/05/48/001 MEC/23LK/05/48/002 MEC/23LK/05/48/003 MEC/23LK/05/48/004 MEC/23LK/05/48/005 MEC/23LK/05/48/006

Fire Fighting Drawing 1. 2. 3. 4.

V.

MECON LIMITED

Architectural Drawings 1. 2.

IV

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

Layout of Fire Water System for Despatch Terminal at Bahadurgarh Layout of Fire Water System for Receiving Terminal at Tikrikalan Installation Details Fire Water Hydrant Installation Details of Water Cum Foam Monitor

MEC/23LK/05/21/M/FF/001 MEC/23LK/05/21/M/FF/002 MEC/23LK/05/21/M/FF/003 MEC/23LK/05/21/M/FF/004

Telecommunications Drawings 1.

Standard Sketch for OFC laying (OFC through

MEC/05/E5/T/002

HDPE) (Normal Terrain) 2.

Standard Sketch for OFC laying (OFC through

MEC/05/E5/T/002A

HDPE) (Rocky Terrain) 3.

Standard Sketch for OFC laying (Common

MEC/05/E5/T/002-WM

Warning Mat) (Normal Terrain)

VI.

4.

Standard Drawing OFC Laying (Separate Trench) (OFC through HDPE)

MEC/05/E5/T/005

5.

OFC Laying (Cased Crossing) (One HDPE Duct)

MEC/05/E5/T/008

6.

Standard Sketch OFC Joining Pit / Blowing Pit

MEC/05/E5/T/009

7.

OFC Joint Marker

MEC/05/E5/T/010

Instrumentation Drawings: 1 2 3 4 5 6 7 8

INSTALLATION DIAGRAM FOR PRESSURE TRANSMITTER. MOUNTING DETAILS FOR RTD ON THERMOWELLS. INSTALLATION DIAGRAM FOR DIFERENTIAL PRESSURE GAUGE. INSTALLATION DIAGRAM FOR PRESSURE GUAGE. INSTALLATION DIAGRAM FOR TEMPERATURE GUAGE & RTD. MOUNTING DETAILS FOR THERMOWELLS (RTD). MOUNTING DETAILS FOR THERMOWELLS (T G). SCHEMATIC DIAGRAM FOR SKIN TEMPERATURE MEASUREMENT SYSTEM

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

MEC/05/E5/SD/PT/001 MEC/05/E5/SD/RTD/002 MEC/05/E5/SD/DPG/003 MEC/05/E5/SD/PG/004 MEC/05/E5/SD/TG-RTD/005 MEC/05/E5/SD/RTD-TW/006 MEC/05/E5/SD/TG-TW/007 MEC/05/E5/SD/SF-RTD/008

Page 40 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd. 9

SUPPORT DETAILS FOR JUNCTION BOXES.

10.

INSTRUMENT SUPPORT SINGLE INSTRUMENT

11.

INSTRUMENT SUPPORT TWO INSTRUMENT

12.

FABRICATED CANOPY FOR INSTRUMENTS. PERFORATED TRAY SUPPORTS & CABLES CLAMPING DETAILS

13. VII.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

MEC/05/E5/SD/JB/009 MEC/05/E5/SD/IS/010A (Sheet1 to 3) MEC/05/E5/SD/IS/010B (Sheet1 to 3) MEC/05/E5/SD/CY/011 MEC/05/E5/SD/CB-LY/012

Cathodic Protection Works - Standard Drawings 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14.

PREPACKED ZINC ANODE MAGNESIUM RIBBON ANODE FOR GROUNDING DETAILS OF TEST STATION FOR TCP TEST STATION CONNECTION SCHEMES ZINC RIBBON ANODE FOR CASED CROSSINGS WITH COATED CASINGS PIPELINE GROUNDING THROUGH POLARISATION CELL AND GALVANIC ANODES DETAILS OF ZINC GROUNDING CELL PERMANENT COPPER – COPPER SULPHATE REFERENCE CELL & INSTALLATION DETAILS SHALLOW ANODE GROUND BED (PCP) ANODE LEAD JUNCTION BOX CASING PIPE DETAILS TEST STATION FOR POLARIZATION CELL DETAILS OF THERMIT WELD FOR CABLE TO PIPE JOINT EARTH ELECTRODE IN TEST PIT

MEC/SD/05/21/16/01 MEC/SD/05/21/16/03 MEC/SD/05/21/16/04 MEC/SD/05/21/16/05 MEC/SD/05/21/16/07 MEC/SD/05/21/16/08 MEC/SD/05/21/16/09 MEC/SD/05/21/16/10 MEC/SD/05/21/16/11 MEC/SD/05/21/16/12 MEC/SD/05/21/16/13 MEC/SD/05/21/16/14 MEC/SD/05/21/16/18 MEC/SD/05/E9/02/01

5.7

Drawing and Documents

5.7.1

The drawings accompanying the Bid document are indicative of scope of work and issued for tendering / bidding purpose only. These drawings indicate the general scheme as well as the layout to enable the contractor to make an offer in line with the requirements of the owner. Final construction shall be done as per approved construction drawings issued by COMPANY.

5.7.2

"Approved for Construction" drawings will be furnished to the contractor progressively based on construction progress achieved by Contractor. No extra claims whatsoever shall be entertained for any variation between Bid Drawings and Approved for Construction Drawing.

6.0

RESOURCES FACILITIES

6.1

Recruitment of Personnel by Contractor The Contractor shall not recruit personnel of any category from among those who are already employed by the other agencies working at the sites but shall make maximum use of local labour available.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 41 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

6.2

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Construction Water and Power Supply No water and power will be provided by the owner. It should be the responsibilities of the contractor to arrange water and power at his own cost.

6.3

Land for Residential Accommodation Owner shall not provide any land for residential accommodation of contractors staff and labour.

7.0

PROJECT SCHEDULING & MONITORING The following schedules/documents/reports shall be prepared and submitted by the Bidder/Contractor for review/approval at various stages of the contract.

7.1

Alongwith Bid a)

Time Schedule The Completion Time Schedule for the work (including mobilization period) as per Appendix-I to Invitation for bid, PART-A of Tender in all respect, from the date of issue of telex/telegram/letter/Fax of Intent. The Bidder is required to submit a Project Time Schedule in Bar Chart Form, alongwith the Bid. The Schedule shall cover all aspects like sub-ordering, manufacturing and delivery, indicated in the Bid Document. The Owner interface activities shall be clearly identified with their latest required dates. Owner reserves the right to disqualify the Bidder if the above Schedule submitted by the Bidder is not in line with the over all Project requirement.

b)

7.2

Scheduling & Monitoring System The Bidders should describe their system of Project Scheduling and monitoring, the extent of computerization, level of detailing, tracing methodology etc. with the name of computer package and sample outputs.

After the Award of Contract a)

Overall Project Schedule The Contractor shall submit within 1 week of Fax of Intent, a sufficiently detailed over all Project Schedule in the activity network form, clearly indicating the major milestones, interrelationship/ interdependence between various activities together with analysis of critical path and floats. The network will be reviewed and approved by Engineer- in-Charge and the comments if any shall be incorporated in the network before issuing the same for implementation. The network thus finalised shall form part of the contract document and the same shall not be revised without the prior permission from Engineer-in- Charge during the entire period of contract.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 42 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

b)

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Progress Measurement Methodology The contractor is required to submit within 1 week of award of WORK, the methodology of progress measurement of sub-ordering, manufacturing/ delivery, sub- contracting construction and commissioning works and the basis of computation of overall services/physical progress informed. Owner reserves the right to modify the methodology in part or in full.

c)

Functional Schedules The contractor should prepare detailed functional schedules in line with network for functional monitoring and control and submit scheduled progress covers for each function viz. ordering, delivery and construction.

7.3

Project Review Meetings The Contractor shall present the programme and status at various review meetings as required. a)

Weekly Review Meeting Level of Participation

:

Contractor’s/Consultant’s RCM/ Site Incharge & Job Engineers.

Agenda

:

a) b) c)

Venue b)

:

Weekly programme v/s actual achieved in the past week & programme for next week. Remedial Actions and hold up analysis. Client query/ approval.

Site Office

Monthly Review Meeting Level of Participation

:

Senior Officers of HPCL/MECON and Contractors.

Agenda

:

a) b) c) d) e) f)

Venue

:

HPCL/MECON Office/ Site at the discretion of Owner/ MECON

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Progress Status/ Statistics Completion Outlook Major hold ups/slippages Assistance required Critical issues Client query/ approval

Page 43 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

7.4

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Progress Reporting Proforma A)

Monthly Progress Report This report shall be submitted on a monthly basis within 10(ten) calendar days from cut-off date, as agreed upon covering overall scenarios of the work. The report shall include, but not limited to the following : a) b) c)

d) e) f) g) B)

Brief Introduction of the work. Activities executed/ achievements during the month. Schedule versus actual percentage progress and progress curves for Detail Engg. Sub-ordering, Manufacturing/ Delivery, Subcontracting, Construction, Commissioning and Overall and quantum wise status & purchase orders against schedule. Area of concern/ problem/ hold-ups, impacts and action plans. Resources deployment status. Annexures giving status summary for drawings, MRs, deliveries, sub-contracting and construction. Procurement status for items to be supplied by Contractor.

Weekly Reports The report will be prepared and submitted by the Contractor on weekly basis and will cover following items : a) Activities programmed and completed during the week. b) Resource deployed men and machines. c) Quantities achieved against target in construction d) Record of Mandays lost. e) Construction percentage progress schedule and actual.

C)

Daily Repots a) b) c)

Activity programme for the day Progress of the previous day and commutative progress. Manpower & machinery deployed.

7.5

Progress Reports

7.5.1

CONTRACTOR shall make every effort to keep the OWNER adequately informed as to the progress of the WORK throughtout the CONTRACT period. CONTRACTOR shall keep the OWNER informed well in advance of the construction schedule so as to permit the OWNER to arrange for requisite inspection to be carried out in such a manner as to minimize interference with progress of WORK. It is imperative that close coordination be maintained with the OWNER during all phases of WORK.

7.5.2

By the 10th (tenth) of each month, CONTRACTOR shall furnish the OWNER a detailed report covering the progress as of the last day of the previous month. These reports will indicate actual and scheduled percentage of completion of construction

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 44 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

as well as general comments of interest or the progress of various phases of the WORK. The frequency of progress reporting by the CONTRACTOR shall be weekly. 7.5.3

Once a week, CONTRACTOR shall submit a summary of the WORK accomplished during the preceding week in form of percentage completion of the various phases of the WORK, to the OWNER.

7.5.4

Progress reports shall be supplied by CONTRACTOR with documents such as chart, networks, photographs, test certificate etc. Such progress reports shall be in the form and size as may be required by the OWNER and shall be submitted in at least 3 (three) copies.

7.5.5

Contractor shall prepare daily progress report (DPR) in the desired format and submit it to Engineer-in-charge alongwith schedule of next day to Engineer-incharge.

8.0

CONSTRUCTION OWNER reserves the right to inspect all phases of CONTRACTOR's operations to ensure conformity to the SPECIFICATIONS. Owner will have Engineers, Inspectors or other duly authorised representatives, made known to the CONTRCTOR present during progress of the WORK and such representatives shall have free access to the WORK at all times. The presence or absence of a OWNER's representative does not relieve the CONTRACTOR of the responsibility for quality control in all phases of the WORK. In the event that any of the WORK being done by the CONTRACTOR or any SUB-CONTRACTOR is found by OWNER's representatives to be unsatisfactory or not in accordance with the DRAWINGS, procedures and SPECIFICATIONS, the CONTRACTOR shall, upon verbal notice of such, revise the work in a manner to conform to the relevant DRAWINGS, procedures and SPECIFICATIONS.

8.1

Rules & Regulations CONTRACTOR shall observe in addition to Codes specified in respective specification, all National and Local Laws, Ordinances, Rules and Regulations and requirements pertaining to the WORK and shall be responsible for extra costs arising from violations of the same.

8.2

Procedures Various procedures and method statements to be adopted by CONTRACTOR during the construction as required in the respective specifications shall be submitted to OWNER in due time for APPROVAL. No such construction activity shall commence unless approved by OWNER in writing.

8.3

Field Inspection CONTRACTOR shall have at all times during the performance of the WORK, a Competent Superintendent on the premises. Any instruction given to such superintendent shall be construed as having been given to the CONTRACTOR.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 45 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

8.4

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Erection and Installation The CONTRACTOR shall carry out required supervision and inspection as per quality Assurance plan and furnish all assistance required by the OWNER in carrying out inspection work during this phase. The OWNER will have engineers, inspectors or other authorised representatives present who are to have free access to the WORK at all times. If an OWNER's representative notifies the CONTRACTOR's authorised representative not lower than a Foreman of any deficiency, or recommends action regarding compliance with the SPECIFICATIONS, the CONTRACTOR shall make every effort to carry out such instructions to complete the WORK conforming to the SPECIFICATIONS and approved DRAWINGS in the fullest degree consistent with best industry practice.

8.5

Construction Aids, Equipment, Tools & Tackles CONTRACTOR shall be solely responsible for making available for executing the work, all requisite Construction Equipments, Special Aids, Cranes, Tools, Tackles and testing equipments and appliances. Such construction equipments etc. shall be subject to examination by owner and approval for the same being in first class operating condition. Any discrepencies pointed out by OWNER shall be immediately got rectified, repaired or the equipment replaced altogether, by CONTRACTOR. OWNER shall not in any way be responsible for providing any such equipment, machinery, tools and tackles. The OWNER reserves the right to rearrange such deployment depending upon the progress and priority of work in various sections. Tie-end between main line and starting point of terminal is included in the scope of contract, as and when main line section is available for Tie-ins.

9.0

DOCUMENTATION

9.1

"As Built" Drawings Notwithstanding the provisions contained in standard specifications, upon completion of WORK, the CONTRACTOR shall complete all of the related drawings to the "AS BUILT" stage and provide the OWNER, the following :a) One complete set of all original tracings. b) Six complete bound sets of CONTRACTOR's specifications including design calculations. c) Six complete sets, in the form of hand bound volumes, of the manufacturer's data book for all the equipments, instruments etc. including certified prints and data. Data books shall be completed with index as to tag numbers associated with manufacturer's data shown, Equipment data shall include as a minimum requirement the principle and descriptions of operations, installation and maintenance instructions, drawings and dimensions, parts list and priced purchase orders including those of major sub-vendors and suppliers. Requirements pertaining to "VENDOR DATA REQUIREMENT"

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 46 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

d) e) f)

g) 9.2

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

attached with standard specifications for the documents to be included in the Data Book for each equipment, instruments etc. shall also be complied with. Six bound copies each of the Spare Parts Data Books and the Lubricants Inventory Schedule. Soft copy of all the as built drawings prepared in AutoCAD in one set of rewritable compact Disc and photographs covering measure activities at site. The Contractor shall submit coloured photographs covering all the activities of pipeline constructions highlighting the progress or other areas of work in 2 sets to Engineer-in-charge at site office alongwith monthly progress report. Similarly photographs for problem areas should be submitted well in advance with a proposed methodology to execute the works and meet the construction schedule. The cost of same shall be deemed to be inclusive in the rates and no separate payment shall be made. All as-built drawings as mentioned in specification for documentation enclosed elsewhere in the tender.

Completion Document The following documents shall be submitted in hard binder by the CONTRACTOR in THREE sets, as a part of completion documents :a) Welding Procedure Qualification Report. b) Welder Qualification Report. c) Radiographic Procedure Qualification. d) Radiographic Report alongwith radiographs (Radiographs only with the original). e) Batch Test Certificate from manufacturers for electrodes. f) Pretesting and final Hydrostatic and other Test results and reports. g) All other requirements as specified in the respective specifications. h) Test results and reports. i) Pre-commissioning/commissioning check list. j) Completion Certificate issued by Owner’s Site Engineer. k) No claim certificate by the Contractor. l) Consumption statements of steel and cement certified by Owner’s Site Engineer. m) Completion certificate for embedded and covered up works wherever applicable. n) Recovery statement, if any. o) Statement for reconciliation of all the payments and recoveries made in the progress bills. p) Copies of deviation statement and order of extension of time, if granted.

9.3

Submission of Coloured Photographs The Contractor shall shoot, prepare and submit coloured photographs in 2 sets to MECON / HPCL site office along with monthly progress report covering all the activities of pipeline constructions highlighting the progress or other areas of work. Similarly photographs for problem areas should be submitted well in advance with a proposed methodology to execute the works and meet the construction schedule. The cost of same shall be deemed to be inclusive in the rates and no separate payment shall be made.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 47 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

9.4

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Videotape Contractor shall develop and submit a videotape of three hours duration covering the construction activities showing the nature and magnitude of the work. The tape shall be shot and edited to Indian broadcast standards. Professional camerapersons shall shoot videotape recorded in field. Tape shall cover, but not limited to the following construction activities:             

Mobilization of equipment/ machinery ROW cleaning/grading Trenching Stringing Welding NDT Pipe laying Back filling River crossings Rail/Road/Canal crossings Hydro testing Pre-drying and drying Restoration of ROU Various construction and installation at sectionalizing valve station etc.

Videotape shall also have coverage on new/special techniques used in the Contract and major problems encountered, if any, and the measures taken to resolve them. The tape shall be supplemented with suitable narration and subtitles explaining the job, techniques and methodology, etc. The video shall be prepared with two narration tracks, one in Hindi one in English. Professional narrators shall voice both. The script shall include explanations of job activities techniques used methodologies etc. Elements of the video programme sequencing and editing techniques shall be discussed with Owner and mutually agreed to before videotaping begins. Draft script shall be submitted to Owner for approval before editing commences. Following completion of editing and review and approval of programme by Owner, Contractor shall deliver edited master tape to Owner plus six VHS-Format copies of the programme 10.0

SURVEY AND LEVEL/SETTING OUT WORK

10.1

Before the WORK or any part thereof are begun, the CONTRACTOR's agent and the Engineer-in-Charge's representative shall together survey and take levels of the SITE and decide all particulares on which the survey is to be made, and on which measurements of the WORK are to be based. Such particulars shall be plotted by the CONTRACTOR and after agreement the drawings shall be signed by the Engineer-in-Charge.

10.2

The CONTRACTOR shall be entirely responsible for the horizontal and vertical alignment, the level and correctness of every part of the WORK and shall rectify any

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 48 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

errors or imperfections therein. Such rectifications shall be carried out by the CONTRACTOR at his own cost, when instructions are issued to this effect by the Engineer-in-Charge or his representative. 10.3

The Engineer-in-Charge shall furnish the relevant existing grid point with Bench Mark on the land. It shall be CONTRACTOR's responsibility to set out the necessary control points in and to set out the alignment of the various works. The CONTRACTOR shall have to employ efficient survey team for this purpose and the accuracy of such setting out work shall be CONTRACTOR's responsibility.

10.4

The CONTRACTOR shall give the Engineer-in-Charge not less than 24 (twenty four) hours notice in writing of his intention to set out or give levels for any part of the WORK so that arrangements may be made checking the same.

10.5

WORK shall be suspended for such times as necessary for checking lines and levels on any part of the WORK.

10.6

The CONTRACTOR shall at his own expense provide all assistance, which the Engineer-in-Charge may require for checking the setting out ot WORKS.

10.7

Before commencement of any activity, contractor's quality control set up duly approved by company must be available at site.

11.0

ORDER OF WORKS/PERMISSIONS/RIGHT OF ENTRY/CARE OF EXISTING SERVICES.

11.1

The order in which the WORK shall be carried out shall be subject to the approval of the Engineer-in-charge and shall be so as to suit the detailed method of construction adopted by the CONTRACTOR, as well as the agreed joint programme. The WORK shall be carried out in a manner so as to enable the other contractors, if any, to work concurrently. OWNER reserves right to fix up priorities which will be conveyed by Engineer-in-Charge and the CONTRACTOR shall plan and execute work accordingly.

11.2

Existing Service

11.2.1

Drains, pipes, cables, overhead wires and similar services encountered in course of the works shall be guarded from injury by the CONTRACTOR at his own cost, so that they may continue in full and uninterrupted use to the satisfaction of the Owners thereof, or otherwise occupy any part of the SITE in a manner likely to hinder the operation of such services.

11.2.2

Should any damage be done by the CONTRACTOR to any mains, pipes, cables or lines (whether above or below ground etc.), whether or not shown on the drawings the CONTRACTOR must make good or bear the cost of making good the same without delay to the satisfaction of the Engineer-in-Charge.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 49 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

12.0

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

MAKE OF MATERIAL/BOUGHT OUT ITEMS An Appendix-I of approved vendors for various major items is enclosed with this tender specification. The bidder shall consider such names only as indicated in the aforesaid list and clearly indicate in the bid the name(s) as selected against these items. For any other item not covered in the list enclosed with this tender document, prior approval shall be obtained by the contractor for its make/ supplier’s name.

13.0

INSPECTION OF SUPPLY ITEMS All inspections and tests shall be made as required by the specifications forming part of this contract. Contractor shall advise Owner/ Consultant in writing at least 10 days in advance of the date of final inspection/tests. Manufactures inspection or testing certificates for equipment and materials supplied, may be considered for acceptance at the discretion of Owner/ Consultant. All costs towards testing etc. shall be borne by the contractor within their quoted rates. All inspection of various items shall be carried out based on Quality Assurance Plan, which will be submitted by the Contractor and duly approved by Owner/ Consultant.

14.0

ESCALATION The Unit Rates quoted shall be kept firm till completion of work, and no price Escalation shall be paid.

15.0

DOCUMENTS TO BE SUBMITTED/ PRODUCED ALONGWITH R.A. BILLS i) ii) iii) iv) v) vi) vii)

Computerized R.A. Bill/ Manual Bill, with IT No./ ST No./ Labour Licence No. printed thereon. ESI/ EPF clearance certificates for the last month alongwith R.A. Bills. Insurance Policy as per relevant clauses of Contract Agreement. Attendance Register and Salary Records. Photocopy of the measurement book to be attached with R.A. Bills. Any other document required for the purpose of processing the bills. Registration Certificate with Sales tax authorities of state concerned.

16.0

INSURANCE FOR FREE ISSUE MATERIAL

16.1

Insurance for Free Issue Material Contractor shall at his own expense arrange, secure and maintain insurance cover for Owner’s supplied free issue materials as defined in Tender Document. Contractor’s quoted price shall be inclusive of all costs on account of insurance liabilities covered under the Contract. Contractor to note that the beneficiary of insurance cover shall be M/s Hindustan Petroleum Corporation Limited. (The approximate cost of free issues material is Rs. 20.0 crores). The Contractor may take the insurance as per the following schedule.

16.1.1 16.1.2 16.1.3

Upto 2 months – 40% of the value Upto 4 months – 80% of the value Upto 6 months – 100% of the value

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 50 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

16.2

Insurances in India

16.2.1

In addition to the insurance covers specified in the General conditions of Contract to be obtained and maintained by the Contractor, Contractor shall at his own expense arrange, secure and maintain insurance with Indian insurance companies to the satisfaction of the owner as may be necessary and to its full value for all such amounts to protect the works in progress from time to time and the interest of Owner against all risks as detailed herein. The form and the limit of such insurance as defined herein together with the under writer works thereof in each case should be as acceptable to the Owner. However, irrespective of work acceptance the responsibility to maintain adequate insurance coverage at all times during the period of Contract shall be that of Contractor alone. Contractor’s failure in this regard shall not relieve him of any of this responsibilities and obligations under Contractor.

16.2.2

Any loss of damage to the equipment during inland transportation, storage, erection and commissioning till such time the Work is taken over by Owner shall be to the account of Contractor. Contractor shall be responsible for preferring of all claims and make good for the damage or loss by way of repairs and/ or replacement of the parts of the Work damaged or lost. Contractor shall provide the Owner with a copy of all insurance policies and documents shall be submitted to the owner immediately upon the Contractor having taken such insurance coverage. Contractor shall also inform the Owner regarding the expiry cancellation and/ or changes in any of such documents and ensure revalidation/ renewal etc., as may be necessary well in time.

16.2.3

The risks that are to be covered under the insurance shall include, but not be limited to the loss or damage in handling, transit, theft, pilferage, riot, civil commotion, weather conditions, accidents of all kinds, fire, war risk etc. The scope of such insurance shall cover the entire value of supplies of equipments, plants and materials.

16.2.4

All cost on account of insurance liabilities covered under this Contract will be to Contractor’s account and will be included in Contract Price. However, the Owner may from time to time, during the currency of the Contract, ask the Contractor in writing to limit the insurance coverage risk and in such a case, the parties to the Contract will agree for a mutual settlement, for reduction in Value Of Contract to the extent of reduced premium amounts.

16.2.5

Contractor as far as possible shall cover insurance with Indian Insurance Companies.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 51 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

17.0

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

SPECIAL POINTS PERTAINING TO SPECIFICATION Following amendment are pertaining to technical specification of Vol-II of IV. 1.

Specification No. MEC/S/05/62/10 for Pipeline Markers. Refer Sketch No. MEC/SD/05/62/10/02 for ROU boundary marker of above specification. Height of marker above ground level marked as 350mm shall be increased to 650mm.

2.

Specification No. MEC/S/05/62/03A for Hydrostatic Testing Refer Clause 6.0 equipment and instrumentation. Fill pump capacity shall be such that pig travel speed is approx. 2 km/hr.

3.

Specification No. MEC/S/05/62/02A – Welding of Onshore Cross-Country Pipeline. Refer Clause No. 12.5 “Non-Destructive Examination” Following to be noted : i) ii) iii) iv) v)

4.

Standards of acceptability shall be strictly as per API 1104. Any requirement over and above, this mentioned anywhere in this specification shall not be applicable for this project. Ultrasonic inspection – No UT is required for tie-in/ cut-out joints where more than 20mm cutting is involved. Dye penetration test for checking lamination is required. Welding qualification, testing and acceptance criteria shall be as per API 1104. Re-repair of joints shall be permitted as per API 1104 provided all procedure is followed as stipulated in API 1104. Gamma-ray radiography may be used for tie-in joint provided slow film like D4 radiography film is used by contractor for better sensitivity.

Specification No. MEC/S/05/62/06 – Terminal Piping, Fabrication and Erection. Following changes shall be considered: i) Gamma ray shall be used for Terminal Pipe welding provided slow film like D4 film is used. ii) Acceptability Criteria shall be only as per API-1104

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 52 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

18.0

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

LIST OF SUPPLIERS OF MAJOR BOUGHT-OUT ITEMS (Appendix-I to Particular Job Specification of Work)

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 53 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Appendix-I To Particular Job Specification of Work LIST OF SUPPLIERS OF MAJOR BOUGHT-OUT ITEMS A)

Mainline & Mechanical Pipes C.S. 1. TISCO, Calcutta 2. BHEL, Tiruchirapalli 3. Maharashtra Seamless, Mumbai 4. Jindal Pipes Ltd., New Delhi 5. SAIL, Calcutta 6. ISMT, Pune 7. Surya Roshni, New Delhi 8. Kalyani Steel, Pune Pipes (1239/3589) 1. TISCO, Calcutta 2. Jindal Pipes, New Delhi 3. Ajanta Tubes, New Delhi 4. Gujrat Steel Tubes 5. Indus Tubes, New Delhi Ball Valves 1. 2. 3. 4. 5.

Larsen & Toubro Virgo Microfinish Valves Flow Chem Shalimar Valves, Navi Mumbai

Plug Valves Nordstrom Valves Inc., USA Serck Audco Valves, UK Breda Energia Sesto Industria Spa, Italy Sumitomo Corporation, New Delhi Fisher Xomox Sanmar India Ltd., New Delhi Larsen & Toubro Ltd. (Audco India Limited, Chennai) Flanges M/s Aditya Forge Ltd., Vadodara M/s Amforge Industries Ltd., Mumbai M/s CD Engineering Co., Ghaziabad M/s Echjay Forgings Pvt. Ltd. (Bombay), Mumbai M/s Echjay Industries Ltd., Rajkot M/s Forge & Forge Pvt. Ltd., Rajkot M/s Golden Iron & Steel Works, New Delhi M/s JK Forgings, New Delhi M/s Metal Forgings Pvt. Ltd., Mumbai M/s Perfect Marketings Pvt.Ltd,New Delhi M/s Sky Forge,Faridabad M/s S & G Faridabad

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 54 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Choudhary Hammer, Ghaziabad Engineering Services Ent., Kolkata Pipefit Engineers, Baroda Sawan Engineers, Baroda Vivial Forge, Baroda Gujarat Infrastructures, Baroda Stewarts & Lloyds, Kolkata Fittings M/s Commercial Supplying Agency, Mumbai M/s Eby Industries, Mumbai M/s Flash Forge Pvt. Ltd., Vishakhapatnam M/s Gujarat Infra Pipes Pvt. Ltd., Vadodara M/s M.S. Fittings Mfg. Co. Pvt. Ltd., Kolkata M/s Stewarts & Lloyds of India Ltd., Kolkata M/s Teekay Tubes Pvt. Ltd., Mumbai M/s Pipe Fit,Baroda M/s Sky Forge, Ballabhgarh M/s S & G Faridabad M/s Sawan Engineers, Baroda Engineering Services Ent., Kolkata Vivial Forge, Baroda Gaskets 1. 2. 3. 4.

IGP Engineers (P) Ltd., Madras Madras Industrial Products, Madras Dikson & Company, Bombay Banco Products (P) Ltd., Vadodara

Fasteners 1. 2. 3. 4. 5. 6. 7.

Nireka Engg. Co. (P) Ltd., Calcutta Precision Taps & Dies, Bombay AEP Company, Vithal Udyoug Nagar Fix Fit Fasteners, Calcutta Precision Engg. Industries, Baroda Echjay Forgings Pvt. Ltd., Bombay Capital Industries, Bombay

Welding Electrodes 1. For Mainline – Lincon make 2. For Terminal – Lincon & D&H or equivalent Fire Fighting Equipments a) Fire Extinguishers Avon Services (Production & Agencies) Pvt. Ltd., Bombay Kooverji Devshi & Co., Bombay Zenith Fire Services, Bombay Safex Fire Services, Bombay Reliable (Fire Protection) India Ltd., Bombay

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 55 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

b) 1. 2. 3. 4. 5. 6. 7. 8. 9.

Fire Hydrants, Monitors, Deluge Valve, Nozzles Zenith Fire, Mumbai Minimax Newage, Mumbai HD Fire, Jalgaon Vijay Fire Fire Tech, Mumbai Nitin Fire, Mumbai Atlas Fire Tech, New Delhi Vimal Fire, Mumbai

c)

R.R.L.Hose

1. 2.

Jayshree Newage

D)

Hoses

1. 2. 3. 4. 5. 6. 7. 8. 9.

Ashit Sales Corporation, Bombay Royal India Corporation, Bombay Gayatri Industrial Corporation, Mumbai Simplex Rubber Products Ltd., Ahmedabad Zaverchand Marketing Pvt. Ltd., Baroda Presidency Rubber Mill, Calcutta The Cosmopolite, Calcutta Simplex Rubber Products, Thane KPC Flexi, New Delhi

MECON LIMITED

Chain Pulley Block 1. 2. 3. 4. 5. B)

M/s Hercules Hoist M/s Tractel Trifor M/s HAFA Equipment M/s Simplicity Project M/s Lifting Equipment & Accessories

INSTRUMENTATION Field Mounted Instruments like PG, TG 1. 2. 3. 4.

AN Instruments General Instruments Wika Wari

SS Tubes Fittings Swagelok, (Delhi / Bangalore Fluid Systems) Parker, Hannifin, Navi Mumbai

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 56 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Sandvik, Sweden Excellsior Hydair Reliance Multimetal Astec Installation. Choksi Tubes Ratnamani Metals & Tubes NFC Aura INC, New Delhi Fluid Control, Mumbai Panam Engineers, Mumbai Circor Instruments, Mumbai Excel Hydro, Mumbai Inst. Valves & Manifolds 1. 2. 3. 4. 5. 6. 7. 8.

Micro-Precision Hydair Engg. Technomatic India Excellisior Engg. Indocean Engineers Circor Instruments, Mumbai Excel Hydro, Mumbai Aura INC, New Delhi

Temperature Safety Valve (TSV) 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. C)

Emerson Process ( Erstwhile M/s Fisher Rosemount ) Instrumentation Ltd., Palghat Keystone Valves, Baroda Mekaster Valves & Engineering Services (P) Ltd., Vadodara (formally M/s Sebim Valves India (P) Ltd., New Delhi) Tyco Sanmar, New Delhi Parcol SPA Tai Milano SPA Nuopignone, Italy Sarasin, France Fainger Leser, Mumbai

NDT AGENCY 1. 2. 3. 4. 5. 6. 7. 8.

NDT Services, Ahmedabad GEECY Industrial Services Pvt. Ltd., Mumbai Corrosion Control Services, Mumbai Perfect Metal Testing & Inspection Agency, Calcutta Inter Ocean Shipping Co., New Delhi RTD, Mumbai Sievert, Mumbai X-Tech, Vizag

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 57 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

D)

MECON LIMITED

Basket Filters 1) 2) 3) 4) 5) 6) 7) 8) 9) 10) 11)

G)

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

M/s Axsia Howmar Ltd. (UK) M/s Faudi Filters systems GMBH (Germany) M/s Filtan Filter Anlagenbau GMBH (Germany) M/s Forain S.R.L. (Italy) M/s Grand Prix Fab (Pvt.) Ltd. (New Delhi) M/s Gujarat Otofilt, Ahmedabad M/s Perry Equipment Corp. (USA) M/s Plenty Filters (UK) M/s Ravi Techno Systems, Mumbai M/s Siirtec NIGI S.p.A. (Italy) M/s Ultra Filters (India) Pvt. Ltd (Banglore)

“T” TYPE STRAINER 1) 2) 3) 4) 5) 6) 7) 8) 9) 10)

M/s Gujarat Otofilt, Ahmedabad M/s Genius Filters & Systems (P) Ltd., Vishakapatnam M/s Delta Filters & Separators (P) Ltd., Navi mumbai M/s Multitex Filters (P) Ltd., New Delhi M/s Bhagwati Filters (P) Ltd., Ahmedabad M/s Patel Filters Ltd., Ahmedabad M/s Industrial Filtration Services M/s Forum Filters & fabricators, Ankleshwar M/s Filteration & Separation, Kalpavruksh M/s Grand Prix Fab. (P) Ltd., New Delhi

Note: 1) Successful bidders shall take prior approval of the make for the items not covered above for which complete technical credentials of the proposed vendors shall be required to be submitted for evaluation by Purchaser/Consultant. 2) In case of subletting of works/ part of works by the prime bidder to other agency not specified in above list, bidder may propose for prior approval to Engineer-in-charge before engaging the sub-contractors strictly as per guideline mentioned in clause no. 37.0 of GCC. 3) For any other items which are not listed above, shall be subject to prior approval from HPCL / MECON.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 58 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

19.0

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

DATA SHEETS & QAP FOR MECHANICAL ITEMS ETC.

(Appendix-II to Particular Job Specification of Work)

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 59 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

DATA SHEETS & QAP FOR MECHANICAL ITEMS ETC. CONTENTS 1.

Data Sheet for LR Bends

MEC/23LK/05/21/M/000/001/DS-015-01

2.

QAP for LR Bends

-

3.

Data Sheet for ‘T’ Type Strainer

MEC/23LK/05/21/M/001/DS-010A TO 010H

4.

QAP for ‘T’ Type Strainer

-

5.

Data Sheet - Corrosion Inhibitor Dosing Pump for ULMS

MEC/23LK/05/21/M/001/DS-CIP/01

6.

Data Sheet - Corrosion Inhibitor Dosing Pump for ULSHSD SKO

MEC/23LK/05/21/M/001/DS-CIP/02

7.

Data Sheet - Corrosion Inhibitor Dosing Tank

MEC/23LK/05/21/M/001/DS-CIT/01

8.

Data Sheet for Level Gauge

9.

Data Sheet for Level Transmitter

10. Data Sheet for Pressure Gauges 11. Data Sheet for Pressure Transmitters 12. Rupture Disk Device Specification Sheet

MEC/23LK/05/21/M/001/DS-024A/02

13. Data Sheet for Thermal Safety Valves

MEC/23LK/05/21/M/001/DS-TSV/01 02

To

14. Data Sheet for Ball Valves

MEC/23LK/05/21/M/001/DS/BV001 009

To

15. Data Sheet for Plug Valves

MEC/23LK/05/21/M/001/DS/PV001

16. Data Sheet for Check Valves

MEC/23LK/05/21/M/001/DS/CV001 002

17. Data Sheet for Gate Valves

MEC/23LK/05/21/M/001/DS00(GATE) To 003(GATE)

18. Data Sheet for Globe Valves

MEC/23LK/05/21/M/001/DS/GV001 004

19. Insulating Joint (10” NB)

MEC/23LK/05/21/M/000/DS-009-01

20. Insulating Joint (8” NB)

MEC/23LK/05/21/M/000/DS-009-02

21. Flow Tees (10” x 10”)

MEC/23LK/05/21/M/000/DS-011-1

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

To

To

Page 60 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

22. Flow Tees (8” x 8”)

MEC/23LK/05/21/M/000/DS-011-2

23. Data Sheet for Sump Tank

MEC/DS/05/21/23LK/ST/01

24. Data Sheet for Vertical Submersible Pumps For Sump Tank (MS)

MEC/DS/05/21/23LK/VSP/001

25. Data Sheet for Vertical Submersible Pumps For Sump Tank (ULSHSD_SKO)

MEC/DS/05/21/23LK/VSP/002

26. Data Sheet for Rotameters

MEC/23LK/05/E5/DS/IROT/01

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 61 of 153

DATA SHEET FOR LONG RADIUS BENDS 1)

LR BEND MFR.

:

2)

PURCHASER SPECIFICATION NO.

: MEC/TS/05/21/015 Rev 00

3)

MANUFACTURING CODE

: MSS-SP-75

4)

DIMENSIONAL TESTING

: REQUIRED AS PER SPEC.

5)

DESTRUCTIVE TESTING

: REQUIRED AS PER SPEC.

6)

NON-DESTRUCTUVE TESTING

7)

PIGGING

: REQUIRED AS PER NOTE NO.3

8)

HYDROSTATIC TEST PRESSURE

: 73.5 BAR(G)

(TENSILE / CHARPY /HARDNESS) : REQUIRED AS PER SPEC.

TABLE-I Sl. No.

Details of free issue P/L material NB

Thk.

Bend

Material

End Type

Radius

mm

Qty.

Angle

(Nos.)

Strainght

Pipe length reqd. to

Length

(R)

fabricate the bend

after

m/ bend

Total

curvature

@

length

(mm)  1. 2.

10" 8"

To Indicated by Contractor To Indicated by Contractor

API 5L Gr B

6D*

BE

Note-2

API 5L Gr B

6D*

BE

Note-2

(m) @

TABLE-II Pipe length required for fabrication of bends NB x Thk. (mm)

@Total Length

@Total Nos. of double

(m)

random length of pipe

From Table-I

(11.5 to 12.5m length) required

10" X Thk. 8" x Thk. * BE

= "D" - denotes nominal dia. of pipe

@

= Bevel End



= Vendor to indicate = Straight length after curvature will be minimum 500mm.

Note: 1)

Test Bend shall be of 90°

2)

Quantity & angles of LR Bends shall be finalized during detailed engineering activities

3)

A check shall be performed on each bend by passing gauging pig consisting of two discs having a diameter equal to 95% of the nominal internal diameter of the pipe, connected rigidly together at a distance equal to 500mm. Details of the gauging pig, including its dimensions shall be approved by Purchaser.

REV. NO.

APPRD DATE

ZONE

DESCRIPTIONS

SECTION: OIL&GAS

BY

CLIENT : DSGN

NAME

DATE

REFERENCES

DRG. NO.

REVISIONS

CHKD

DRWN

DATE

PROJECT :

APPROVED

d:\fateh\ipp-kg basin\tender rfq\LR bend\LR Bends BTPL

HINDUSTAN PETROLEUM CORPORATION LIMITED BAHADURGARH TEKRIKALAN PIPELINE PROJECT

DATA SHEET FOR LONG RADIUS BENDS

MECON LIMITED

SCALE : DATA SHEET NO.: MEC/23LK/05/21/M/000//001/DS-015-01

REV 0

Tender No: 05/51/23LK/HPCL/001(i) FORM NO. 11.20(4.4)F-09 REV-0

QUALITY ASSURANCE PLAN FOR

CONTRACTOR ORDER NO. & DATE

STRUCTURAL AND MECHANICAL EQUIPMENT

SUB-CONTRACTOR ORDER NO. & DATE

INSTRUCTIONS FOR FILLING UP :

Code 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12.

Sl. No.

1 1.0

Description (with equipment heading, place of use and brief specifications)

PACKAGE NO. : PACKAGE NAME :

LR BEND TS No.: MEC/TS/05/62/015

MR NO. :

CODES FOR EXTENT OF INSPECTION, TESTS, TEST CERTIFICATES & DOCUMENTS :

1. QAP shall be submitted for each of the equipment separately with break up of assembly/sub-assembly & part/component or for group of equipment having same specification. 2. Use numerical codes as indicated for extent of inspection & tests and submission of test certificates & documents. Additional codes & description for extent of inspection & tests may be added as applicable for the plant and equipment 3. Separate identification number with quantity for equipment shall be indicated wherever equipment having same specifications belonging to different facilities are grouped together. 4. Weight in kilograms must be indicated under Column-5 for each item. Estimated weights may be indicated wherever actual weights are not available.

ABBREVIATIONS USED : CONTR : CONTRACTOR MFR : MANUFACTURER H : HOLD R : REVIEW W : WITNESS

PROJECT :

KEY TO SYMBOLS : *

: MFR/ CONTRACTOR - AS APPLICABLE

** : TEST TO BE PERFORMED, IF APPLICABLE

EQUIPMENT DETAILS Identification Quantity Unit No. No./M Weight (MR Item No.) (Kg) 3

4

5

13. 14. 15. 16. 17.

Description

Code

Visual Dimensional Fitment & Alignment Physical Test (Sample) Chemical Test (Sample) Ultrasonic Test Magnetic Particle Test (MPI) Radiography Test Dye Penetration Test Metallographic Exam. Welder’s Qualification & Weld Procedure Test Approval of Test and Repair Procedure Heat Treatment Pressure Test Leakage Test Balancing Vibration Test

Manufacturer's Name and Address

Expected Schedule of Final Inspn.

6

7

LR BEND As per SOR

18. 19. 20. 21. 22. 23.

Description

Code Description

34. Internal Inspection Report by Contractor 35. Hardness Test 36. Spark Test for Lining 37. Calibration 38. Safety Device Test 39. Ease of Maintenance 24. 40. Fire Test (Type Test) 25. 41. Charpy V-Notch Test 26. 42. Operational Torque Test 27. 43. ENP (Electroless Nickel Plating) 28. Execution 29. 44. Painting 45. Anti-Static Test 30. 46. Hydrostatic Double Block & 31. Bleed Test 32. 47. Functional Test 48. Pneumatic Double Block & 33. Bleed Test 49. Proof Test (Type Test) 50. Dielectric Test 51. Bending parameter INSPECTION AND TESTS Test Certificates & Raw Material and In-Process Final Inspection/ Test by Documents to be Stage Inspection submitted to MECON MFR CONTR MECON MFR CONTR MECON 8 1,2,4,5, 6, ,35,41,

9

10 -

11 1,2,6,5, 13,15,51

12 *

13 1,2,5 15,51

QAP NO. For MECON (Stamp & Signature)

For CONTRACTOR/ SUB-CONTRACTOR (Stamp & Signature)

Code DOCUMENTS:

Amplitude Test Sponge Test Dust/ Water Ingress Test Friction Factor Test Adhesion Test Performance Test/Characteristic Curve No Load/ Free Running Test Load/ Overload Test Measurement of Speeds Accoustical Test Geometrical Accuracy Repeatability and Positioning Accuracy Proving Test Surface Preparation Manufacturer's Test Certificates for bought-out items IBR/ Other Statutory agencies compliance certificate

SHEET 1 OF 1

14 1,2,4,5,6, 13,15, 41,51,D9

D1. Approved GA drawings D2. Information and other reference drg/ stamped drgs released for mfg. D3. Relevant catalogues D4. Bill of matl./Item no./ Identification D5. Matchmarks details D6. Line/ Layout diagram D7. Approved erection procedures D8. Unpriced sub P.O. with specification and amendments, if any D9. Calibration Certificate of all measuring instruments and gauges D10. X-Ray Reports

Acceptance Criteria Standards/ IS/ BS/ ASME/ Norms and Documents

REMARKS/ SAMPLING PLAN

15 D1, D2 , MECON's T.S. & Relevant Standards mentioned therein

16 100%

REV 0

DATA SHEET 1.0

JOB NO. : 23LK

2.0

VENDOR :

3.0

OPERATING CONDITIONS :

4.0

ITEM NO. : ST-0201A, ST-0201B 

QUANTITY : 2 (TWO) NOS.

FLUID HANDLED : ULSHSD/ SKO/ S-SKO

FLOW RATE , M3/Hr, Normal/ Max. 350 / 385

FLUID DENSITY@PT, KG/M3 :775-870

FLUID VISC., CS :1.6 - 8.0

OPER. PR., KG/CM2 : FLOODED

OPER. TEMP., °C : 15-45

MESH MESH SPECIFICATION

20 MESH 22 SWG

5.0

OPENING (IN)





SCREENING AREA %



PR. DROP, KG/CM2, CLEAN/ DIRTY :

MAX. ALLOWABLE PR. DROP, KG/CM2, DIRTY : 0.2 6.0

MATERIAL OF CONSTRUCTION EQUAL TEE :A-234 Gr. WPB

WNRF FLANGES : SA105

BLIND FLANGE : SA 105 GASKET : SS316 SPIRAL WOUND WITH CAF FILLED

FASTENER : A193Gr.B7/ A194Gr.2H

FILTER ELEMENT : 304L 7.0

DESIGN AND CONSTRUCTION TYPE :T-TYPE DESIGN PR., KG/CM2G :19

DESIGN TEMP., °C :65

HYDROTEST PRESSURE : 28.5 KG/CM2G FLANGE TYPE :

WNRF

FLANGE RATING : 150#

FLANGE FINISH : SMOOTH FINISH

CORROSION ALLOWANCE, MM : 3.0 8.0

DIMENSIONAL DETAILS (REF. ATTACHED DRG.) OVERALL LENGTH (L), MM :



OVERALL HEIGHT (H), MM :



OVERALL FILTER ELEMENT SIZE (H1)x(A), MMxMM:

9

INLET/ OUTLET CONNECTION PIPE: 12"NB x 6.4 MM THK. (API 5L Gr.B, PSL-2)

10

DIMENSIONAL STANDARDS



FLANGE & FITTING : ASME B16.5/ B16.9 FASTENERS GASKET 11

: B 18.2 : ASME 16.20 ANSI B16.5 (5 mm . Thickness)

PAINTING : AS PER T.S. ENVIRONMENT FOR PAINTING : CORROSIVE INDUSTRIAL COLOUR OF FINISH PAINT; SHALL BE INTIMATED TO SUCCESSFUL VENDOR.

12.0

INSPECTION & TESTING : AS PER T.S.

RADIOGRAPHY :100%

NOTE: 

1

VENDOR TO SPECIFY

2

REFER STRAINER DRAWING (MEC/23LK/05/21/M/001/2010) ENCLOSED WITH THIS DATA SHEET.



READ THIS DATA SHEET TOGETHER WITH STANDARD SPECIFICATION NO. : MEC/TS/05/21/010. THE EFFECTIVE FREE AREA OF BASKET SHALL BE MIN. THREE TIMES THE INLET NOZZLE AREA.



REV. NO.

DATE

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS SECTION OIL & GAS NAME DSGN

DATE

REFERENCES CLIENT : HINDUSTAN PETROLEUM CORPORATION LTD.

CHKD

DATE

MECON LIMITED

PROJECT :BAHADURGARH - TIKARIKALAN PIPELINE PROJECT

DRWN

T- TYPE STRAINER APPROVED

TAG NO. :ST- 0201A,ST-0201B

SCALE : DATA SHEET NO. : MEC/23LK/05/21/M/001/DS-010A

This document and the design it covers are the property of MECON and issued for the specific project mentioned therein. This is not to be copied or used for other projects unless expressly permitted by MECON.

REV 0

DATA SHEET 1.0

JOB NO. : 23LK

2.0

VENDOR :

3.0

OPERATING CONDITIONS :

4.0

ITEM NO. : ST-0303A, ST- 0303B 

QUANTITY : 2(TWO)NOS.

FLUID HANDLED : ULSHSD/ SKO/ S-SKO

FLOW RATE , M3/Hr, Normal/ Max. 350 / 385

FLUID DENSITY@PT. KG/M3 :775-870

FLUID VISC, CS :1.6 - 8.0

OPER. PR. (MLC) : 20 - 50

OPER. TEMP., °C : 15-45

MESH MESH SPECIFICATION

20 MESH 22 SWG

5.0

OPENING (IN)





SCREENING AREA %



PR. DROP, KG/CM2, CLEAN/ DIRTY :

MAX. ALLOWABLE PR. DROP, KG/CM2, DIRTY : 0.2 6.0

MATERIAL OF CONSTRUCTION EQUAL TEE :A-234 Gr. WPB

WNRF FLANGES : SA105

BLIND FLANGE : SA 105 GASKET : SS316SPIRAL WOUND WITH CAF FILLED

FASTENER : A193Gr.B7/ A194Gr.2H

FILTER ELEMENT : 304L 7.0

DESIGN AND CONSTRUCTION TYPE :T-TYPE DESIGN PR. KG/CM2G :49

DESIGN TEMP., °C :65

HYDROTEST PRESSURE : 73.5 KG/CM2G FLANGE TYPE :

WNRF

FLANGE RATING : 300#

FLANGE FINISH : SMOOTH FINISH

CORROSION ALLOWANCE, MM : 3.0 8.0

DIMENSIONAL DETAILS (REF. ATTACHED DRG.) OVERALL LENGTH (L), MM :



OVERALL HEIGHT (H), MM :



OVERALL FILTER ELEMENT SIZE(H1)x(A), MMxMM:

9

INLET/ OUTLET CONNECTION PIPE: 12"NB X 10.3 MM THK. (API 5L Gr.B, PSL-2)

10

DIMENSIONAL STANDARDS



FLANGE & FITTING : ASME B16.5/B16.9 FASTENERS

: B 18.2

GASKET 11

: ASME 16.20 ANSI B16.5 (5 mm . Thickness)

PAINTING : AS PER T.S. ENVIRONMENT FOR PAINTING : CORROSIVE INDUSTRIAL COLOUR OF FINISH PAINT; SHALL BE INTIMATED TO SUCCESSFUL VENDOR.

12.0

INSPECTION & TESTING : AS PER T.S.

RADIOGRAPHY :100%

NOTE: 

1

VENDOR TO SPECIFY

2

REFER STRAINER DRAWING(MEC/23LK/05/21/M/001/2010) ENCLOSED WITH THIS DATA SHEET.



READ THIS DATA SHEET TOGETHER WITH STANDARD SPECIFICATION NO. :MEC/TS/05/21/010. THE EFFECTIVE FREE AREA OF BASKET SHALL BE MIN. THREE TIMES THE INLET NOZZLE AREA.



REV. NO.

DATE

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS SECTION PROCESS & PIPING NAME DSGN

DATE

REFERENCES CLIENT : HINDUSTAN PETROLEUM CORPORATION LTD.

CHKD

DATE

MECON LIMITED

PROJECT :BAHADURGARH - TIKARIKALAN PIPELINE PROJECT

DRWN

T- TYPE STRAINER APPROVED

TAG NO. :ST- 0303A, ST- 0303B

SCALE : DATA SHEET NO. : MEC/23LK/05/21/M/001/DS-010B

This document and the design it covers are the property of MECON and issued for the specific project mentioned therein. This is not to be copied or used for other projects unless expressly permitted by MECON.

REV 0

DATA SHEET 1.0

JOB NO. : 23LK

2.0

VENDOR :

3.0

OPERATING CONDITIONS :

4.0

ITEM NO. : ST-0401A, ST-0401B 

QUANTITY : 2 (TWO) NOS.

FLUID HANDLED : ULMS

FLOW RATE , M3/Hr, Normal/ Max. 250 / 275

FLUID DENSITY@PT, KG/M3 :720-775

FLUID VISC., CS :0.5 - 0.7

OPER. PR., KG/CM2 : FLOODED

OPER. TEMP., °C : 15-45

MESH MESH SPECIFICATION

20 MESH 22 SWG

5.0

OPENING (IN)





SCREENING AREA %



PR. DROP KG/CM2, CLEAN/ DIRTY :

MAX. ALLOWABLE PR. DROP, KG/CM2, DIRTY : 0.2 6.0

MATERIAL OF CONSTRUCTION EQUAL TEE :A-234 Gr. WPB

WNRF FLANGES : SA105

BLIND FLANGE : SA 105 GASKET : SS316 SPIRAL WOUND WITH CAF FILLED

FASTENER : A193Gr.B7/ A194Gr.2H

FILTER ELEMENT : 304L 7.0

DESIGN AND CONSTRUCTION TYPE :T-TYPE DESIGN PR., KG/CM2G :19

DESIGN TEMP., °C :65

HYDROTEST PRESSURE : 28.5 KG/CM2G FLANGE TYPE :

WNRF

FLANGE RATING : 150#

FLANGE FINISH : SMOOTH FINISH

CORROSION ALLOWANCE, MM : 3.0 8.0

DIMENSIONAL DETAILS (REF. ATTACHED DRG.) OVERALL LENGTH (L), MM :



OVERALL HEIGHT (H), MM :



OVERALL FILTER ELEMENT SIZE(H1)x(A), MMxMM:

9

INLET/ OUTLET CONNECTION PIPE: 12"NB X 6.4 MM THK. (API 5L Gr.B, PSL-2)

10

DIMENSIONAL STANDARDS



FLANGE & FITTING : ASME B16.5/ B16.9 FASTENERS

: B 18.2

GASKET 11

: ASME 16.20 ANSI B16.5 (5 mm . Thickness)

PAINTING : AS PER T.S. ENVIRONMENT FOR PAINTING : CORROSIVE INDUSTRIAL COLOUR OF FINISH PAINT; SHALL BE INTIMATED TO SUCCESSFUL VENDOR.

12.0 INSPECTION & TESTING : AS PER T.S.

RADIOGRAPHY :100%

NOTE: 

1

VENDOR TO SPECIFY

2

REFER STRAINER DRAWING (MEC/23LK/05/21/M/001/2010) ENCLOSED WITH THIS DATA SHEET.



READ THIS DATA SHEET TOGETHER WITH STANDARD SPECIFICATION NO. : MEC/TS/05/21/010. THE EFFECTIVE FREE AREA OF BASKET SHALL BE MIN. THREE TIMES THE INLET NOZZLE AREA.



REV. NO.

DATE

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS SECTION PROCESS & PIPING NAME DSGN

DATE

REFERENCES CLIENT : HINDUSTAN PETROLEUM CORPORATION LTD.

CHKD

DATE

MECON LIMITED

PROJECT :BAHADURGARH - TIKARIKALAN PIPELINE PROJECT

DRWN

T- TYPE STRAINER APPROVED

TAG NO. :ST- 0401A, ST-0401B

SCALE : DATA SHEET NO. : MEC/23LK/05/21/M/001/DS-010C

This document and the design it covers are the property of MECON and issued for the specific project mentioned therein. This is not to be copied or used for other projects unless expressly permitted by MECON.

REV 0

DATA SHEET 1.0

JOB NO. : 23LK

2.0

VENDOR :

3.0

OPERATING CONDITIONS :

4.0

ITEM NO. : ST-0501A, ST-0501B 

QUANTITY : 2 (TWO) NOS.

FLUID HANDLED : ULMS

FLOW RATE , M3/Hr, Normal/ Max. 250 / 275

FLUID DENSITY@PT, KG/M3 :720-775

FLUID VISC., CS :0.5 - 0.7

OPER. PR. (MLC) : 20 - 50

OPER. TEMP., °C : 15-45

MESH MESH SPECIFICATION

20 MESH 22 SWG

5.0

OPENING (IN)





SCREENING AREA %



PR. DROP, KG/CM2, CLEAN/ DIRTY :

MAX. ALLOWABLE PR. DROP, KG/CM2, DIRTY : 0.2 6.0

MATERIAL OF CONSTRUCTION EQUAL TEE :A-234 Gr. WPB

WNRF FLANGES : SA105

BLIND FLANGE : SA 105 GASKET : SS316 SPIRAL WOUND WITH CAF FILLED

FASTENER : A193Gr.B7/ A194Gr.2H

FILTER ELEMENT : 304L 7.0

DESIGN AND CONSTRUCTION TYPE :T-TYPE DESIGN PR., KG/CM2G :49

DESIGN TEMP., °C :65

HYDROTEST PRESSURE : 73.5 KG/CM2G FLANGE TYPE :

WNRF

FLANGE RATING : 300#

FLANGE FINISH : SMOOTH FINISH

CORROSION ALLOWANCE, MM : 3.0 8.0

DIMENSIONAL DETAILS (REF. ATTACHED DRG.) OVERALL LENGTH (L), MM :



OVERALL HEIGHT (H), MM :



OVERALL FILTER ELEMENT SIZE(H1)x(A), MMxMM:

9

INLET/ OUTLET CONNECTION PIPE: 10"NB X 6.4 MM THK. (API 5L Gr.B, PSL-2)

10

DIMENSIONAL STANDARDS



FLANGE & FITTING : ASME B16.5/ B16.9 FASTENERS

: B 18.2

GASKET 11

: ASME 16.20 ANSI B16.5 (5 mm . Thickness)

PAINTING : AS PER T.S. ENVIRONMENT FOR PAINTING : CORROSIVE INDUSTRIAL COLOUR OF FINISH PAINT; SHALL BE INTIMATED TO SUCCESSFUL VENDOR.

12.0

INSPECTION & TESTING : AS PER T.S.

RADIOGRAPHY :100%

NOTE: 

1

VENDOR TO SPECIFY

2

REFER STRAINER DRAWING (MEC/23LK/05/21/M/001/2010) ENCLOSED WITH THIS DATA SHEET.



READ THIS DATA SHEET TOGETHER WITH STANDARD SPECIFICATION NO. : MEC/TS/05/21/010. THE EFFECTIVE FREE AREA OF BASKET SHALL BE MIN. THREE TIMES THE INLET NOZZLE AREA.



REV. NO.

DATE

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS SECTION PROCESS & PIPING NAME DSGN

DATE

REFERENCES CLIENT : HINDUSTAN PETROLEUM CORPORATION LTD.

CHKD

DATE

MECON LIMITED

PROJECT :BAHADURGARH - TIKARIKALAN PIPELINE PROJECT

DRWN

T- TYPE STRAINER APPROVED

TAG NO. :ST- 0501A, ST - 0501B

SCALE : DATA SHEET NO. : MEC/23LK/05/21/M/001/DS-010D

This document and the design it covers are the property of MECON and issued for the specific project mentioned therein. This is not to be copied or used for other projects unless expressly permitted by MECON.

REV 0

DATA SHEET 1.0

JOB NO. : 23LK

2.0

VENDOR :

3.0

OPERATING CONDITIONS :

4.0

ITEM NO. : ST-0202 

QUANTITY : 1 (ONE) NO.

FLUID HANDLED : ULSHSD/ SKO/ S-SKO/ SLOP

FLOW RATE , M3/Hr, Normal/ Max. 18 / 30

FLUID DENSITY@PT, KG/M3 :775-870

FLUID VISC., CS :1.6 - 8.0

OPER. PR., KG/CM2 : ATMOSPHERIC

OPER. TEMP., °C : 15-45

MESH MESH SPECIFICATION

20 MESH 22 SWG

5.0

OPENING (IN)





SCREENING AREA %



PR. DROP, KG/CM2, CLEAN/ DIRTY :

MAX. ALLOWABLE PR. DROP, KG/CM2, DIRTY : 0.2 6.0

MATERIAL OF CONSTRUCTION EQUAL TEE :A-234 Gr. WPB

WNRF FLANGES : SA105

BLIND FLANGE : SA 105 GASKET : SS316 SPIRAL WOUND WITH CAF FILLED

FASTENER : A193Gr.B7/ A194Gr.2H

FILTER ELEMENT : 304L 7.0

DESIGN AND CONSTRUCTION TYPE :T-TYPE DESIGN PR., KG/CM2G :19

DESIGN TEMP., °C :65

HYDROTEST PRESSURE : 28.5 KG/CM2G FLANGE TYPE :

WNRF

FLANGE RATING : 150#

FLANGE FINISH : SMOOTH FINISH

CORROSION ALLOWANCE, MM : 3.0 8.0

DIMENSIONAL DETAILS (REF. ATTACHED DRG.) OVERALL LENGTH (L), MM :



OVERALL HEIGHT (H), MM :



OVERALL FILTER ELEMENT SIZE (H1)x(A), MMxMM:

9

INLET/ OUTLET CONNECTION PIPE: 2"NB x 5.5 MM THK. [ASTM A 106 GR. B (CHARPY)]

10

DIMENSIONAL STANDARDS



FLANGE & FITTING : ASME B16.5/ B16.9 FASTENERS GASKET 11

: B 18.2 : ASME 16.20 ANSI B16.5 (5 mm . Thickness)

PAINTING : AS PER T.S. ENVIRONMENT FOR PAINTING : CORROSIVE INDUSTRIAL COLOUR OF FINISH PAINT; SHALL BE INTIMATED TO SUCCESSFUL VENDOR.

12.0

INSPECTION & TESTING : AS PER T.S.

RADIOGRAPHY :100%

NOTE: 

1

VENDOR TO SPECIFY

2

REFER STRAINER DRAWING (MEC/23LK/05/21/M/001/2010) ENCLOSED WITH THIS DATA SHEET.



READ THIS DATA SHEET TOGETHER WITH STANDARD SPECIFICATION NO. : MEC/TS/05/21/010. THE EFFECTIVE FREE AREA OF BASKET SHALL BE MIN. THREE TIMES THE INLET NOZZLE AREA.



REV. NO.

DATE

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS SECTION OIL & GAS NAME DSGN

DATE

REFERENCES CLIENT : HINDUSTAN PETROLEUM CORPORATION LTD.

CHKD

DATE

MECON LIMITED

PROJECT :BAHADURGARH - TIKARIKALAN PIPELINE PROJECT

DRWN

T- TYPE STRAINER APPROVED

TAG NO. :ST- 0202

SCALE : DATA SHEET NO. : MEC/23LK/05/21/M/001/DS-010E

This document and the design it covers are the property of MECON and issued for the specific project mentioned therein. This is not to be copied or used for other projects unless expressly permitted by MECON.

REV 0

DATA SHEET 1.0

JOB NO. : 23LK

2.0

VENDOR :

3.0

OPERATING CONDITIONS :

4.0

ITEM NO. : ST-0402 

QUANTITY : 1 (ONE) NO.

FLUID HANDLED : ULMS

FLOW RATE , M3/Hr, Normal/ Max. 18 / 30

FLUID DENSITY@PT, KG/M3 :720-775

FLUID VISC., CS :0.5 - 0.7

OPER. PR., KG/CM2 : ATMOSPHERIC

OPER. TEMP., °C : 15-45

MESH MESH SPECIFICATION

20 MESH 22 SWG

5.0

OPENING (IN)





SCREENING AREA %



PR. DROP, KG/CM2, CLEAN/ DIRTY :

MAX. ALLOWABLE PR. DROP, KG/CM2, DIRTY : 0.2 6.0

MATERIAL OF CONSTRUCTION EQUAL TEE :A-234 Gr. WPB

WNRF FLANGES : SA105

BLIND FLANGE : SA 105 GASKET : SS316SPIRAL WOUND WITH CAF FILLED

FASTENER : A193Gr.B7/ A194Gr.2H

FILTER ELEMENT : 304L 7.0

DESIGN AND CONSTRUCTION TYPE :T-TYPE DESIGN PR., KG/CM2G :19

DESIGN TEMP., °C :65

HYDROTEST PRESSURE : 28.5 KG/CM2G FLANGE TYPE :

WNRF

FLANGE RATING : 150#

FLANGE FINISH : SMOOTH FINISH

CORROSION ALLOWANCE, MM : 3.0 8.0

DIMENSIONAL DETAILS (REF. ATTACHED DRG.) OVERALL LENGTH (L), MM :



OVERALL HEIGHT (H), MM :



OVERALL FILTER ELEMENT SIZE (H1)x(A), MMxMM:

9

INLET/ OUTLET CONNECTION PIPE: 2"NB x 5.5 MM THK. [ASTM A 106 GR. B (CHARPY)]

10

DIMENSIONAL STANDARDS



FLANGE & FITTING : ASME B16.5/ B16.9 FASTENERS

: B 18.2

GASKET 11

: ASME 16.20 ANSI B16.5 (5 mm . Thickness)

PAINTING : AS PER T.S. ENVIRONMENT FOR PAINTING : CORROSIVE INDUSTRIAL COLOUR OF FINISH PAINT; SHALL BE INTIMATED TO SUCCESSFUL VENDOR.

12.0 INSPECTION & TESTING : AS PER T.S.

RADIOGRAPHY :100%

NOTE: 

1

VENDOR TO SPECIFY

2

REFER STRAINER DRAWING (MEC/23LK/05/21/M/001/2010) ENCLOSED WITH THIS DATA SHEET.



READ THIS DATA SHEET TOGETHER WITH STANDARD SPECIFICATION NO. : MEC/TS/05/21/010. THE EFFECTIVE FREE AREA OF BASKET SHALL BE MIN. THREE TIMES THE INLET NOZZLE AREA.



REV. NO.

DATE

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS SECTION PROCESS & PIPING NAME DSGN

DATE

REFERENCES CLIENT : HINDUSTAN PETROLEUM CORPORATION LTD.

CHKD

DATE

MECON LIMITED

PROJECT :BAHADURGARH - TIKARIKALAN PIPELINE PROJECT

DRWN

T- TYPE STRAINER APPROVED

TAG NO. :ST- 0402

SCALE : DATA SHEET NO. : MEC/23LK/05/21/M/001/DS-010F

This document and the design it covers are the property of MECON and issued for the specific project mentioned therein. This is not to be copied or used for other projects unless expressly permitted by MECON.

REV 0

DATA SHEET 1.0

JOB NO. : 23LK

2.0

VENDOR :

3.0

OPERATING CONDITIONS :

4.0

ITEM NO. : ST-0701 

QUANTITY : 1 (ONE) NO.

FLUID HANDLED : ULSHSD/ SKO/ S-SKO/ SLOP

FLOW RATE , M3/Hr, Normal/ Max. 18 / 30

FLUID DENSITY@PT, KG/M3 :775-870

FLUID VISC., CS :1.6 - 8.0

OPER. PR., KG/CM2 : ATMOSPHERIC

OPER. TEMP., °C : 15-45

MESH MESH SPECIFICATION

20 MESH 22 SWG

5.0

OPENING (IN)





SCREENING AREA %



PR. DROP, KG/CM2, CLEAN/ DIRTY :

MAX. ALLOWABLE PR. DROP, KG/CM2, DIRTY : 0.2 6.0

MATERIAL OF CONSTRUCTION EQUAL TEE :A-234 Gr. WPB

WNRF FLANGES : SA105

BLIND FLANGE : SA 105 GASKET : SS316 SPIRAL WOUND WITH CAF FILLED

FASTENER : A193Gr.B7/ A194Gr.2H

FILTER ELEMENT : 304L 7.0

DESIGN AND CONSTRUCTION TYPE :T-TYPE DESIGN PR., KG/CM2G :19

DESIGN TEMP., °C :65

HYDROTEST PRESSURE : 28.5 KG/CM2G FLANGE TYPE :

WNRF

FLANGE RATING : 150#

FLANGE FINISH : SMOOTH FINISH

CORROSION ALLOWANCE, MM : 3.0 8.0

DIMENSIONAL DETAILS (REF. ATTACHED DRG.) OVERALL LENGTH (L), MM :



OVERALL HEIGHT (H), MM :



OVERALL FILTER ELEMENT SIZE(H1)x(A), MMxMM:

9

INLET/ OUTLET CONNECTION PIPE: 2"NB x 5.5 MM THK. [ASTM A 106 GR. B (CHARPY)]

10

DIMENSIONAL STANDARDS



FLANGE & FITTING : ASME B16.5/ B16.9 FASTENERS GASKET 11

: B 18.2 : ASME 16.20 ANSI B16.5 (5 mm . Thickness)

PAINTING : AS PER T.S. ENVIRONMENT FOR PAINTING : CORROSIVE INDUSTRIAL COLOUR OF FINISH PAINT; SHALL BE INTIMATED TO SUCCESSFUL VENDOR.

12.0

INSPECTION & TESTING : AS PER T.S.

RADIOGRAPHY :100%

NOTE: 

1

VENDOR TO SPECIFY

2

REFER STRAINER DRAWING (MEC/23LK/05/21/M/001/2010) ENCLOSED WITH THIS DATA SHEET.



READ THIS DATA SHEET TOGETHER WITH STANDARD SPECIFICATION NO. : MEC/TS/05/21/010. THE EFFECTIVE FREE AREA OF BASKET SHALL BE MIN. THREE TIMES THE INLET NOZZLE AREA.



REV. NO.

DATE

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS SECTION OIL & GAS NAME DSGN

DATE

REFERENCES CLIENT : HINDUSTAN PETROLEUM CORPORATION LTD.

CHKD

DATE

MECON LIMITED

PROJECT :BAHADURGARH - TIKARIKALAN PIPELINE PROJECT

DRWN

T- TYPE STRAINER APPROVED

TAG NO. :ST- 0701

SCALE : DATA SHEET NO. : MEC/23LK/05/21/M/001/DS-010G

This document and the design it covers are the property of MECON and issued for the specific project mentioned therein. This is not to be copied or used for other projects unless expressly permitted by MECON.

REV 0

DATA SHEET 1.0

JOB NO. : 23LK

2.0

VENDOR :

3.0

OPERATING CONDITIONS :

4.0

ITEM NO. : ST-0702 

QUANTITY : 1 (ONE) NO.

FLUID HANDLED : ULMS

FLOW RATE , M3/Hr, Normal/ Max. 18 / 30

FLUID DENSITY@PT, KG/M3 :720-775

FLUID VISC., CS :0.5 - 0.7

OPER. PR., KG/CM2 : ATMOSPHERIC

OPER. TEMP., °C : 15-45

MESH MESH SPECIFICATION

20 MESH 22 SWG

5.0

OPENING (IN)





SCREENING AREA %



PR. DROP, KG/CM2, CLEAN/ DIRTY :

MAX. ALLOWABLE PR. DROP, KG/CM2, DIRTY : 0.2 6.0

MATERIAL OF CONSTRUCTION EQUAL TEE :A-234 Gr. WPB

WNRF FLANGES : SA105

BLIND FLANGE : SA 105 GASKET : SS316 SPIRAL WOUND WITH CAF FILLED

FASTENER : A193Gr.B7/ A194Gr.2H

FILTER ELEMENT : 304L 7.0

DESIGN AND CONSTRUCTION TYPE :T-TYPE DESIGN PR., KG/CM2G :19

DESIGN TEMP., °C :65

HYDROTEST PRESSURE : 28.5 KG/CM2G FLANGE TYPE :

WNRF

FLANGE RATING : 150#

FLANGE FINISH : SMOOTH FINISH

CORROSION ALLOWANCE, MM : 3.0 8.0

DIMENSIONAL DETAILS (REF. ATTACHED DRG.) OVERALL LENGTH (L), MM :



OVERALL HEIGHT (H), MM :



OVERALL FILTER ELEMENT SIZE (H1)x(A), MMxMM:

9

INLET/ OUTLET CONNECTION PIPE: 2"NB x 5.5 MM THK. [ASTM A 106 GR. B (CHARPY)]

10

DIMENSIONAL STANDARDS



FLANGE & FITTING : ASME B16.5/ B16.9 FASTENERS

: B 18.2

GASKET 11

: ASME 16.20 ANSI B16.5 (5 mm . Thickness)

PAINTING : AS PER T.S. ENVIRONMENT FOR PAINTING : CORROSIVE INDUSTRIAL COLOUR OF FINISH PAINT; SHALL BE INTIMATED TO SUCCESSFUL VENDOR.

12.0 INSPECTION & TESTING : AS PER T.S.

RADIOGRAPHY :100%

NOTE: 

1

VENDOR TO SPECIFY

2

REFER STRAINER DRAWING (MEC/23LK/05/21/M/001/2010) ENCLOSED WITH THIS DATA SHEET.



READ THIS DATA SHEET TOGETHER WITH STANDARD SPECIFICATION NO. : MEC/TS/05/21/010. THE EFFECTIVE FREE AREA OF BASKET SHALL BE MIN. THREE TIMES THE INLET NOZZLE AREA.



REV. NO.

DATE

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS SECTION PROCESS & PIPING NAME DSGN

DATE

REFERENCES CLIENT : HINDUSTAN PETROLEUM CORPORATION LTD.

CHKD

DATE

MECON LIMITED

PROJECT :BAHADURGARH - TIKARIKALAN PIPELINE PROJECT

DRWN

T- TYPE STRAINER APPROVED

TAG NO. :ST- 0702

SCALE : DATA SHEET NO. : MEC/23LK/05/21/M/001/DS-010+

This document and the design it covers are the property of MECON and issued for the specific project mentioned therein. This is not to be copied or used for other projects unless expressly permitted by MECON.

REV 0

Tender No: 05/51/23LK/HPCL/001(i) FORM NO. 11.20(4.4)F-09 REV-0

QUALITY ASSURANCE PLAN FOR STRUCTURAL AND MECHANICAL EQUIPMENT

CONTRACTOR ORDER NO. & DATE SUB-CONTRACTOR ORDER NO. & DATE

INSTRUCTIONS FOR FILLING UP :

Code 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12.

Sl. No.

1 1.0

Description (with equipment heading, place of use and brief specifications)

TENDER NO. : ITEM NAME :

T/Y TYPE STRAINER TS No.: MEC/TS/05/21/010

MR NO. :

CODES FOR EXTENT OF INSPECTION, TESTS, TEST CERTIFICATES & DOCUMENTS :

1. QAP shall be submitted for each of the equipment separately with break up of assembly/sub-assembly & part/component or for group of equipment having same specification. 2. Use numerical codes as indicated for extent of inspection & tests and submission of test certificates & documents. Additional codes & description for extent of inspection & tests may be added as applicable for the plant and equipment 3. Separate identification number with quantity for equipment shall be indicated wherever equipment having same specifications belonging to different facilities are grouped together. 4. Weight in kilograms must be indicated under Column-5 for each item. Estimated weights may be indicated wherever actual weights are not available.

ABBREVIATIONS USED : CONTR : CONTRACTOR MFR : MANUFACTURER H : HOLD R : REVIEW W : WITNESS

PROJECT : Bahadurgarh Tikarikalan Pipeline Project

KEY TO SYMBOLS : *

: MFR/ CONTRACTOR - AS APPLICABLE

** : TEST TO BE PERFORMED, IF APPLICABLE

EQUIPMENT DETAILS Identification Quantity Unit No. No./M Weight (MR Item No.) (Kg) 1

4

5

13. 14. 15. 16. 17.

Description

Code

Visual Dimensional Fitment & Alignment Physical Test (Sample) Chemical Test (Sample) Ultrasonic Test Magnetic Particle Test (MPI) Radiography Test Dye Penetration Test Metallographic Exam. Welder’s Qualification & Weld Procedure Test Approval of Test and Repair Procedure Heat Treatment Pressure Test Leakage Test Balancing Vibration Test

Manufacturer's Name and Address

Expected Schedule of Final Inspn.

6

7

T/Y TYPE STARINER As per SOR

18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29. 30. 31. 32. 33.

Description

Code Description

Amplitude Test Sponge Test Dust/ Water Ingress Test Friction Factor Test Adhesion Test Performance Test/Characteristic Curve No Load/ Free Running Test Load/ Overload Test Measurement of Speeds Accoustical Test Geometrical Accuracy Repeatability and Positioning Accuracy Proving Test Surface Preparation Manufacturer's Test Certificates for bought-out items IBR/ Other Statutory agencies compliance certificate

Code DOCUMENTS:

34. Internal Inspection Report by Contractor 35. Hardness Test 36. Spark Test for Lining 37. Calibration 38. Safety Device Test 39. Ease of Maintenance 40. Fire Test (Type Test) 41. Charpy V-Notch Test 42. Operational Torque Test 43. ENP (Electroless Nickel Plating) Execution 44. Painting 45. Anti-Static Test 46. Hydrostatic Double Block & Bleed Test 47. Functional Test 48. Pneumatic Double Block & Bleed Test 49. Proof Test (Type Test) 50. Dielectric Test

Test Certificates & INSPECTION AND TESTS Documents to be Raw Material and In-Process Final Inspection/ Test by submitted to MECON Stage Inspection MFR CONTR MECON MFR CONTR MECON 8 1,2,3,4,5, 6,7,11, ,12,41

9 *

10 -

11 1,2,3,7, 8,9,14 31,44

12 *

13 1,2,3,7, 9,14

14 1,2,3,4,5,6, 7,8,9,11,14,31, 32,34,44,D9

QAP NO. For MECON (Stamp & Signature)

For MANUFACTURER/ VENDOR (Stamp & Signature)

SHEET 1 OF 1

D1. Approved GA drawings D2. Information and other reference drg/ stamped drgs released for mfg. D3. Relevant catalogues D4. Bill of matl./Item no./ Identification D5. Matchmarks details D6. Line/ Layout diagram D7. Approved erection procedures D8. Unpriced sub P.O. with specification and amendments, if any D9. Calibration Certificate of all measuring instruments and gauges D10. X-Ray Reports

Acceptance Criteria Standards/ IS/ BS/ ASME/ Norms and Documents

REMARKS/ SAMPLING PLAN

15 D1, D2 , MECON's T.S.DataSheet &Relevant Standards mentioned therein

16 100%

REV

PROJECT : BAHADURGARH TIKARIKALAN PIPELINE PROJECT LOCATION : BAHADURGARH DESPATCH STATION ITEM NO. : P-0301A/B OPERATING UNITS 2 PROPERTIES OF LIQUID LIQUID HANDLED PUMPING TEMPERATURE VISCOSITY AT PUMPING TEMPERATURE VAPOUR PRESSURE AT PUMPING TEMPERATURE LIQUID DENSITY AT PUMPING TEMPERATURE PRESENCE OF CORROSIVE / TOXIC COMPONENTS SOLIDS IN SUSPENSION POUR POINT (FOR CONGEALING SERVICE) OPERATING CONDITIONS FOR ONE PUMP FLOW RATE NORMAL MAXMIMUM MINIMUM SUCTION PRESSURE DISCHARGE PRESSURE DIFFERENTIAL PRESSURE DIFFERENTIAL HEAD NPSH AVAILABLE

CLIENT : HPCL JOB NO.: 23LK SERVICE : CORROSION INHIBITOR CHEMICAL DOSING (FOR ULMS) TYPE OF PUMP : RECIPROCATING (METERING PUMP)

DEG C

CORROSION INHIBITOR CHEMICAL AMBIENT 55 - 95 cSt @ 40 DEG C NEGLIGIBLE 930 @ 15.6 DEG C MILD CORROSIVE NO -

L/HR L/HR L/HR KG/CM2 A KG/CM2 A KG/CM2 A METERS METERS

3 0.4 ~ ATM 12 11 118 10.3 (W/O ACCL. HEAD)

DEG C CS KG/CM2 A KG/M3

CAPACITY CONTROL FOR VOLUMETRIC PUMPS METHOD OF CONTROL TYPE OF CONTROL CONTROL RANGE PRECISION AT MINIMUM RATE

AUTOMATIC / MANUAL BY VFD CONTROL 0 - 100%

MECHANICAL DATA DESIGN PRESSURE MAXIMUM SUCTION PRESSURE DESIGN TEMPERATURE MATERIAL OF CONSTRUCTION CASING IMPELLER SEAL TYPE LINE RATING DRIVER

KG/CM2 G KG/CM2 G DEG C

NOTE-4

19 ATM 65 AISI - 316 AISI - 316 PACKING SUCTION 150# DISCHARGE 150# ELECTRIC MOTOR (VARIABLE SPEED) NOTE - 3

STEAM TURBINE DATA INLET PRESSURE KG/CM 2 INLET TEMPERATURE DEG C DESIGN PRESSURE KG/CM2 G DESIGN TEMPERATURE DEG C DESIGN TEMPERATURE KG/CM2 G EXHAUST PRESSURE LINE RATING SUCTION DISCHARGE NOTES: 1 STRAINER, SAFETY VALVE ON DISCHARGE, PULSATION DAMPNER, CALIBRATION PLOT, ETC. SHALL BE UNDER PUMP VENDOR'S SCOPE. 2 SAFETY VALVE SET PRESSURE SHALL BE 110% OF RATED DISCHARGE PRESSURE. 3 BASED ON FLOWRATE OF PRODUCT, CORROSION INHIBITOR DOSING RATE WILL BE VARIED TO MAINTAIN SET PPM BY VFD CONTROL SYSTEM

4 MANUAL STROKE ADJUSTMENT FACILITY SHALL BE AVALIABLE.

SECTION OIL & GAS NAME DSGN DRWN

APPROVED

CLIENT : DATE

CHKD

Hindustan Petroleum Corporation Limited

Maeka$Na ilim4eD

DATE

Project : Bahadurgarh Tikarikalan Pipeline Project of M/s HPCL DATA SHEET FOR CORROSION INHIBITOR CHEMICAL DOSING PUMP (P-0301 A/B)

MECON LIMITED SCALE : DS NO. MEC/23LK/05/21/M/001/DS-CIP/01 SHEET 1 of 1

REV 0

PROJECT : BAHADURGARH TIKARIKALAN PIPELINE PROJECT LOCATION : BAHADURGARH DESPATCH STATION ITEM NO. : P-0302A/B OPERATING UNITS 2 PROPERTIES OF LIQUID LIQUID HANDLED PUMPING TEMPERATURE VISCOSITY AT PUMPING TEMPERATURE VAPOUR PRESSURE AT PUMPING TEMPERATURE LIQUID DENSITY AT PUMPING TEMPERATURE PRESENCE OF CORROSIVE / TOXIC COMPONENTS SOLIDS IN SUSPENSION POUR POINT (FOR CONGEALING SERVICE) OPERATING CONDITIONS FOR ONE PUMP FLOW RATE NORMAL MAXMIMUM MINIMUM SUCTION PRESSURE DISCHARGE PRESSURE DIFFERENTIAL PRESSURE DIFFERENTIAL HEAD NPSH AVAILABLE

DEG C

CLIENT : HPCL JOB NO.: 23LK SERVICE : CORROSION INHIBITOR CHEMICAL DOSING (FOR ULSHSD/SKO) TYPE OF PUMP : RECIPROCATING (METERING PUMP) CORROSION INHIBITOR CHEMICAL AMBIENT 55 - 95 cSt @ 40 DEG C NEGLIGIBLE 930 @ 15.6 DEG C MILD CORROSIVE NO -

L/HR L/HR L/HR KG/CM2 A KG/CM2 A KG/CM2 A METERS METERS

5 1 ~ ATM 12 11 118 10.3 (W/O ACCL. HEAD)

DEG C CS KG/CM2 A KG/M3

CAPACITY CONTROL FOR VOLUMETRIC PUMPS METHOD OF CONTROL TYPE OF CONTROL CONTROL RANGE PRECISION AT MINIMUM RATE

AUTOMATIC / MANUAL BY VFD CONTROL 0 - 100%

MECHANICAL DATA DESIGN PRESSURE MAXIMUM SUCTION PRESSURE DESIGN TEMPERATURE MATERIAL OF CONSTRUCTION CASING IMPELLER SEAL TYPE LINE RATING DRIVER

KG/CM2 G KG/CM2 G DEG C

NOTE-4

19 ATM 65 AISI - 316 AISI - 316 PACKING SUCTION 150# DISCHARGE 150# ELECTRIC MOTOR (VARIABLE SPEED) NOTE - 3

STEAM TURBINE DATA INLET PRESSURE KG/CM 2 INLET TEMPERATURE DEG C DESIGN PRESSURE KG/CM2 G DESIGN TEMPERATURE DEG C DESIGN TEMPERATURE KG/CM2 G EXHAUST PRESSURE LINE RATING SUCTION DISCHARGE NOTES: 1 STRAINER, SAFETY VALVE ON DISCHARGE, PULSATION DAMPNER, CALIBRATION PLOT, ETC. SHALL BE UNDER PUMP VENDOR'S SCOPE. 2 SAFETY VALVE SET PRESSURE SHALL BE 110% OF RATED DISCHARGE PRESSURE. 3 BASED ON FLOWRATE OF PRODUCT, CORROSION INHIBITOR DOSING RATE WILL BE VARIED TO MAINTAIN SET PPM BY VFD CONTROL SYSTEM

4 MANUAL STROKE ADJUSTMENT FACILITY SHALL BE AVALIABLE.

SECTION OIL & GAS NAME DSGN DRWN

APPROVED

TKM

CLIENT : DATE

CHKD BND

Hindustan Petroleum Corporation Limited

Maeka$Na ilim4eD

DATE

Project : Bahadurgarh Tikarikalan Pipeline Project of M/s HPCL DATA SHEET FOR B.N. DAS CORROSION INHIBITOR CHEMICAL DOSING PUMP (P-0302 A/B)

MECON LIMITED SCALE : DS NO. MEC/23LK/05/21/M/001/DS-CIP/02 SHEET 1 of 1

REV 0

PROJECT : BAHADURGARH TIKARIKALAN PIPELINE PROJECT LOCATION : BAHADURGARH DESPATCH STATION ITEM NO. : T-0301 SERVICE : CORROSION INHIBITOR DOSING TANK (FOR ULMS) PROCESS DATA FLUID HANDLED OPERATING PRESSURE KG/CM2 G OPERATING TEMPERATURE DEG C. DESIGN PRESSURE KG/CM2 G DOES VESSEL REQUIRE FULL VACUUM DESIGN DESIGN TEMPERATURE DEG C.

CLIENT : HPCL JOB NO.: 23LK TYPE

VERTICAL (CONICAL)

CORROSION INHIBITOR ATMOSPHERIC AMB. FULL OF WATER NO 65

MECHANICAL DATA MATERIAL OF CONSTRUCTION

MARK I B V LT LG H

NOTE:

SHELL AISI - 304 LINER CORROSION ALLOWANCE MM NIL INSULATION REQUIRED NO TYPE INSULATION THICKNESS MM IS INLET BAFFLE DEFLECTOR REQUIRED NO VESSEL SUBJECTED TO STEAM OUT CONDITIONS NO IF 'YES' STEAM TEMPERATURE DEG C STEAM PRESSURE KG/CM2 G VORTEX BREAKER REQUIRED NO TYPE DEMISTER REQUIRED NO IF 'YES' REF DATA SHEET NUMBER IS DESIGN FOR NACE CODE REQUIRED NO NOZZLES AND CONNECTIONS RATING FOR VESSEL NOZZLES 150# A1A NUMBER SIZE, IN SERVICE MARK 1 2 FEED INLET 1 2 BOTTOM OUTLET 1 2 VENT 1 2 LEVEL TRANSMITTER 1 2 LEVEL GAUGE (RADAR TYPE) 1 BY HANDHOLE WITH HINGE CLOSURE VENDOR

NUMBER SIZE, INSERVICE

LEVEL TRANSMITTER SHALL BE OF ULTRASONIC TYPE WITH LOCAL DISPLAY

SECTION OIL & GAS NAME DSGN DRWN

APPROVED

CLIENT : Hindustan Petroleum Corporation Limited DATE

CHKD

Maeka$Na ilim4eD

DATE

Project : Bahadurgarh Tikarikalan Pipeline Project of M/s HPCL DATA SHEET FOR CORROSION INHIBITOR DOSING TANK (T-0301)

MECON LIMITED SCALE : D/S NO. MEC/23LK/05/21/M/001/DS-CIT/01 SHEET 1 of 1

REV 0

BAHADURGARH TIKARIKALAN PIPELINE PROJECT MECON LTD. DELHI

LEVEL GAUGE UNITS : - Flow : Liquid --> M3/Hr, Gas --> MMSMD Steam --> Kg/Hr, Pressure --> Kg/Cm2G, Temp --> °C, Level / Length --> mm

1 Gauge

Cocks (X)

Column (X)

6

Power supply

Uuassembled

Area class Enclosure

GAUGE GLASSES 2 Type

Illuminator (back)

Assemblies with Nipple (X)

Cable entry

Reflex (X)

Transparent

Tubular

Large chamber

7

Heating Jackets Medium

Other

Max. Temp. / Press.

3 Chamber connection

Conncetions : -

Size Type

FLNG

Inlet

Location

Top and Bottom (X)

Outlet

Side Back

8

Other Vent & Drain

* * *

COCKS Offset (X) Straight

Type

Required

9

Type of connection Vessel

3/4" NPT (F) WITH UNION

Cover Plate

Gauge

3/4" NPT (F) WITH UNION

Studs ASTM

Vent

1/2" NPT WITH CAP

4 Material chamber

Nuts ASTM

1/2" NPT WITH CAP

Drain

Gaskets

ASTM A 105

Material Body

5 OPTIONS

SS 316 (NOTE-2)

Trim

(a) Mica shield

Closing

(b) Illuminator

Bonnet Type

Plain

Screwed Union

(c) Heating jacket (d) Calibrated scale

Extended

Required with 10 mm graduation

(e) Non frost extn. (f) IBR Certificate TAG NO.

LG-0301

Quick (X)

Bolted (X)

VISIBLE LENGTH MM

C TO C DIST. MM

*

**

MAX. OPER. PRESS KG/CM2

Ball check

(X)

Renewable seals

(X) VESSEL CONNECTION

TEMP °C (DESIGN)

FLUID

ULMS, ULHSD/ SKO

OPTIONS

LOCATION

CORROSION INHIBITOR DOSING TANK

SIDE

BOTTOM

*

*

NOTES: 1 VENDOR TO SUBMIT NOZZLE ELEVATIONS AND SKETCHES FOR LG ON VESSELS FOR REVIEW & ENSURE MATCHING. 2 CONTRACTOR SHALL REFER PROCESS DATA SHEET AND SUBMIT FILLED IN DATA SHEET FOR APPROVAL BY MECON/HPCL. 3 LEVEL GAUGES SHALL BE READABLE FROM GRADE/PLATFORM. ENSURE WITH PROPER NOZZLE ORIENTATION. 4 ON/OFF SWITCH SHALL BE PROVIDED FOR GAUGE ILLUMINATOR AT THE CONTROL ROOM/MCC ROOM. 5 GAUGE SHALL HAVE AN OVER LAP OF 100 MM IN CASE OF TWO LEVEL GAUGES ARE REQUIRED TO COVER VISIBLE LENGTH. 6 * BY CONTRACTOR DURING DETAILED ENGINEERING. 7 ** VENDOR TO SPECIFY.

REV

DATE

BY

CHKD

APPD

BAHADURGARH TIKARIKALAN PIPELINE PROJECT MECON LTD. DELHI

LEVEL TRANSMITTER UNITS : - Flow : Liquid --> M3/Hr, Gas --> Nm3/Hr, Steam --> Kg/Hr, Pressure --> Kg/Cm2G, Temp --> °C, Level / Length --> mm

TAG. NO.

LT-0301

2

SERVICE

CORROSION INHIBITOR DOSING TANK T-0301

3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

INTERNAL / EXTERNAL

1 General

Body /Cage

Displacer or Float

Trans./Con troller/Swit ch

Option

Service Conditions

EXTERNAL

BODY OF CAGE MATERIAL FLANGE MATERIAL CONN. SIZE TYPE & RATING FLANGE RATING & FINISH LOCATION UPPER LOCATION LOWER CASE ORIENTATION ROTATABLE HEAD FINNED EXTENSION VENT DRAIN CONN. SIZE DISPLACER OR FLOAT DIAMETER OR LENGTH MM. INSERTION DEPTH MM DISPLACER EXTN. MM DISPLACER OR FLOAT MATERIAL SPRING/TORQUE TUBE MATERIAL

* *

TRANSMIT, INDICATE 4-20 mA DC, 2-WIRE

FUNCTION OUTPUT CONTROL MODES DIFFERENTIAL CONTROLLER ACTION

28

ELEC. AREA CLASSIFICATION

29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51

ELEC. POWER / AIR SUPPLY SWITCH TYPE QTY. FORM CONTACT RATING ON LEVEL INC. CONTACT ON LEVEL DEC. CONTACT CABLE ENTRY SINGLE/DUAL ENCLOSURE INTRINSICALLY SAFE FILTER REGULATOR WITH GAUGE JACKETING - MEDIUM CONN. - TEMP. °C PRESS TORQUE TUBE FLUSHING CONN. O/P METER, W/P & INTRN. SAFE UPPER LIQUID LOWER LIQUID M. W. PRESS NOR. TEMP. °C - NOR. MAKE / MODEL NO. QUANTITY IBR CERTIFICATION

*

S. G. MAX. MAX.

NEC CLASS-1, DIV.2, GROUP-C&D 24 V DC

1/2" NPTF (SINGLE) NEMA - 4 (MIN.) YES

* * *

* * * * AS PER P&ID NA

Notes: 1. TRANSMITTER SHALL BE CAPABLE OF DRIVING LOAD OF 600 OHMS AT 24 V DC 2. (*) INFORMATION TO BE PROVIDED BY THE VENDOR 3. VENDOR TO REFER PROCESS DATA AND SUBMIT FILLED-IN DATA SHEET FOR MECON'S APPROVAL 0 REV

DATE

BY

CHKD

APPD.

Sh. 2 of 2

BAHADURGARH TIKARIKALAN PIPELINE PROJECT MECON LIMITED DELHI

PRESSURE GAUGES Units:- Flow : Liquid-T/hr Gas-MMSCMD Steam- kg/hr Pressure- Kg/cm2 (G) Temperature- C Level/Length-mm 1 Type Direct Wetted parts --material 2 Mounting Local Element --3 Dial size 150 mm Lower body --Colour White (Non rusting plastic Non wetted parts --with black engraving) 4 Case material Cast aluminium Process connection --5 Bezel ring Screwed Size --6 Window material Shatter proof glass Rating --7 Enclosure IP 55 / NEMA 4 Facing &Finish --8 Pressure element Bourdon tube Capillary material --9 Element material SS 316 Capillary length --10 Socket material SS 316 Flushing & Filling --11 Accuracy Over range 130% of range  1% FSD 16 protection 12 Zero adjustment Micrometer pointer Blow out Required 17 (Internal) protection 18 Options 13 Connections ½” NPT (M) a) Snubber 14 15

Conn. Location Movement Diaphragm seal Type

Bottom SS 304

b) c) d) e)

----19

Pressure Operating Design

Make & Model

Design Temp.

Tag No.

Range

PI-0301 PI-0302

*

*

*

*

*

*

*

*

Syphon Gauge saver Liquid filled casing 2 Way Manifold *

Service

Fluid

Options

NOTES: 1) ‘*’ Information to be supplied by the Vendor / Contractor. 2) Make of the PG shall be from approved vendor list of Mecon /Client.

Rev.

Date

By

Chkd

Appd

BAHADURGARH TIKARIKALAN PIPELINE PROJECT MECON LIMITED DELHI

PRESSURE TRANSMITTERS Units:- Flow : Liquid-T/hr Gas-MMSCMD Steam- kg/hr Pressure- Kg/cm2(G) Temperature-C Level/Length-mm GENERAL 1

Function

2

Type

3 4

Case Mounting

5

Enclosure

Transmit & Indicate Electronic Smart P Based Mfg. Std. Yoke Weather proof to IS2147 Explosion proof to IS2148 Enclosure class

6 7 8 9 10 11 12 13

Service

25

Element

Diaphragm

26 27

Body Material Element Material

Carbon Steel SS 316L

28

Process Connections

½” NPT(F)

Process Conn. Locn.

NEMA 4 & NEMA 7 Zone-I, Gr.IIA & IIB, T3

Elec. Area Class.

MEASURING UNIT Pressure

24

29

Diaphragm Seal:-

Intrinsically safe & Required Flameproof Air supply N.A Power supply 24 VDC Cable entry ½” NPT(F) Accuracy + 0.075% of SPAN Repeatability + 0.05% TRANSMITTER 4 – 20 mA DC, Two Output wire

Mfg. Std. Not Required

Type

---

Wetted Parts Matl. Other Material Process Conn.:Size and Rating Facing and Finish Capillary Material:-

-----------

Armour Flexible

No. of positions

30

17 18

Set Point Adj. Manual Regulator

31 a)

19

Mode

b) c)

20 21 22 23

RECORDER Chart Chart Drive Moving Parts Matl. Chart speed

Armour Flexible --Matl. Capillary length, --mm Flush / Filling --Conn. with plug MISCALLANEOUS Over Range 130% of Range Protection Options Output Meter W.P. Intr Safe(note 2) Mounting accessories for 2” Mounting Pipe Mounting – Accessories Material (SS 316) 3 -Way Manifold Required

32

Make & Model

14

Trans. Power supply

24 V DC

CONTROLLER 15

Output

16

A/M switch

Tag No.

Operating Pressure

*

Range

Design Press.

DesignTemp.

Service Span

Set

PT-0301

*

*

*

*

*

PT-0302

*

*

*

*

*

Options

NOTES:

1) ‘*’ Information to be supplied by the Vendor / Contractor. 2 ) Over range protection shall be 130% of maximum static pressure. 3) Local Digital Output meter should indicate the line pressure in Kg/cm2g. 4) Environmental cover to be provided for each transmitter 5) Transmitter shall have zero elevation /suppression for the service specified. 6) Make of the PT shall be from approved vendor list of Mecon /Client.

Rev.

Date

By

Chkd

Appd

RUPTURE DISK DEVICE SPECIFICATION SHEET GENERAL 1.

TAG NUMBER

2.

SERVICE, LINE OR EQUIPMENT NUMBER

RD-0701

RD-0702

12” – ULSHSD-02-0701-A1A

10” – ULMS-02-0703-A1A

API 520

API 520

ULSHSD/SKO/SLOP* (LIQUID)

ULMS* (LIQUID)

SERVICE CONDITIONS 3.

DESIGN CODE (ASME, DIN, ETC.)

4.

FLUID AND STATE

3

5.

REQUIRED CAPACITY AND UNITS

6.

SPECIFIC GRAVITY AT FLOWING TEMPERATURE

7.

VISCOSITY AT FLOWING TEMPERATURE (CSt) 2

3

385 m /h

275 m /h

0.775 – 0.87

0.72 – 0.775

1.6 – 8.0

0.5 – 0.7

8.

OPERATING PRESSURE kg/cm .g

3

3

9.

MAXIMUM ALLOWABLE WORKING PRESSURE OR 2 DESIGN PRESSURE, kg/cm .g

19

19

10.

BURST TEMPERATURE C

45

45

0

0

11.

RELIEVING TEMPERATURE C

45

45

12.

SUPERIMPOSED BACK PRESSURE

2

2

13.

VACUUM PRESSURE PRESENT. INLET OR OUTLET 2 kg/cm .g

-

-

14.

ALLOWABLE OVERPRESSURE, AS A PERCENT

10%

10%

15.

COMPRESSIBILITY FACTOR

-

-

16.

RATIO OF SPECIFIC HEATS

-

-

17.

FRAGMENTATION ALLOWED (YES OR NO)

NO

NO

18.

DESIGN TYPE

SCORED TENSION – LOADED RUPTURE DISK WITH ALARM SYSTEM

SCORED TENSION – LOADED RUPTURE DISK WITH ALARM SYSTEM

19.

NUMBER REQUIRED

1

1

6” NB

CONNECTIONS 20.

SIZE

6” NB

21.

FLANGE CLASS (ANSI)

150#

150#

22.

FACING TYPE (FLAT, RTJ, ETC.)

SMOOTH

SMOOTH

23.

PIPING CONNECTIONS, SCHEDULE/BORE

6”, 6.4 MM

6”, 6.4 MM

RUPTURE DISK HOLDERS 24.

HOLDER MATERIAL, INLET

SS 304

SS 304

25.

HOLDER MATERIAL, OUTLET

SS 304

SS 304

26.

GAUGE TAP SIZE, INLET OR OUTLET

___________

___________

RUPTURE DISK HOLDER ACCESSORIES

___________

27.

EYEBOLTS, JACKSCREWS, MATERIAL

SS 304

SS 304

28.

TELLTALE ASSEMBLY, MATERIAL

SS 304

SS 304

SECTION: LONG DISTANCE PIPELINES NAME PREP. BY CHKD SIGNATURE/ DATE DSGN

APPROVED

CLIENT: HPCL PROJECT : BAHADURGARH – TIKARIKALAN PIPELINE PROJECT

RUPTURE DISK DEVICE SPECIFICATION SHEET (RD-0701, RD-0702)

MECON LIMITED DATA SHEET NO. MEC/23LK/05/21/M/001/DS-024A/02 Sheet No. 1 of 2

RUPTURE DISK DEVICE SPECIFICATION SHEET RUPTURE DISKS 29.

QUANTITY (INCLUDE SPARES)

2

2

30.

SIZE (NOMINAL PIPE SIZE)

___________

___________

31.

TYPE

SCORED TENSION – LOADED RUPTURE DISK WITH ALARM SYSTEM

SCORED TENSION – LOADED RUPTURE DISK WITH ALARM SYSTEM

32.

SPECIFIED BURST CONDITION kg/cm .g, C

___________

___________

33.

MANUFACTURING RANGE

___________

___________

34.

ALLOWABLE BURST TOLERANCE

___________

___________

2

0

MANUFACTURER’S DATA 35.

MANUFACTURER

___________

___________

36.

PREVIOUS LOT NUMBER

___________

___________

37.

MODEL NUMBER (RUPTURE DISK)

___________

___________

38.

MODEL NUMBER (HOLDER)

___________

___________

39.

MODEL NUMBER (OTHER)

___________

___________

SS – 304

SS – 304

MATERIALS – ALL RUPTURE DISKS 40.

DISK MATERIAL

41.

VACUUM SUPPORT

___________

___________

42.

LINER

___________

___________

43.

COATINGS

___________

___________

44.

RINGS

___________

___________

MATERIALS – COMPOSITE RUPTURE DISKS 45.

TOP SECTION

___________

___________

46.

SEAL

___________

___________

NOTES:RUPTURE DISC TO BE PROVIDED WITH ALARM SYSTEM. THE ALARM TO BE PROVIDED IN CONTROL ROOM OF HPCL THROUGH EXISTING PLC. * ULSHSD – ULTRA LOW SULPHUR HIGH SPEED DIESEL * SKO – SUPERIOR KEROSENE OIL * SLOP – MIXTURE OF ULSHSD & SKO * ULMS – UNLEADED MOTOR SPIRIT

SECTION: LONG DISTANCE PIPELINES NAME PREP. BY CHKD SIGNATURE/ DATE DSGN

APPROVED

CLIENT: HPCL PROJECT : BAHADURGARH – TIKARIKALAN PIPELINE PROJECT

RUPTURE DISK DEVICE SPECIFICATION SHEET (RD-0701, RD-0702)

MECON LIMITED DATA SHEET NO. MEC/23LK/05/21/M/001/DS-024A/02 Sheet No. 2 of 2

TYPICAL DATA SHEET FOR THERMAL SAFETY VALVES

PROJECT : BAHADURGARH TIKARIKALAN PIPELINE PROJECT 1 2 3 4 5 6 7 8 9

TAG NO.

CLIENT : HPCL JOB NO. : 23LK TSV-0102, 0401 TO 0405, 0707 TO 0709, 0711 (10 NOS.)

TSV-0101, 0103, 0201 TO 0205, 0701 TO 0706, 0710 (14 NOS.)

ULMS ¾" LINE 1" LINE

ULSHSD / SKO ¾" LINE 1" LINE

ULMS HC, LIQUID 15-45

ULSHSD / SKO HC, LIQUID 15-45

10

CASE NO. (IF ANY) SERVICE INLET LINE NO. OUTLET LINE NO. VESSEL NO. FLUID DISCHARGED FLUID STATE @ SV INLET OPERATING TEMPERATURE

DEG C DEG C

11

RELIEVING TEMPERATURE

KG/CM2 G

65

65

12 13

OPERATING PRESSURE

KG/CM2 G

ATM - 12

ATM - 12

SET PRESSURE MAXIMUM BACK PRESSURE

KG/CM2 G

19

19

14 15

BACK PRESSURE CONST/VARIABLE

CONSTANT

CONSTANT

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61

% OVER PRESSURE

REV. NO.

BASIS OF SELECTION VALVE DISCHARGE TO VALVE FULL NOZZLE / MODIFIED NOZZLE BONNET TYPE CONV. / BELLOWS / PILOT OPERATED CAP OVER ADJ. BOLT SCREWED / BOLTED TEST GAG INLET CONNECTION MATERIAL BODY & BONNET NOZZLE & DISC SPRING DATA AT SV INLET REQD DISCHARGE CAPACITY LIQUID KG/HR VAPOUR / GAS KG/HR LIQUID PROPERTIES SP GR. @ 15°C VISCOSITY AT 20°C, cSt

25

25

LIQUID THERMAL RELIEF SUMP TANK

LIQUID THERMAL RELIEF SUMP TANK

MODIFIED NOZZLE CLOSED CONVENTIONAL YES BOLTED YES ¾", 150#, RF, SERR.FIN. 1", 150#, RF, SERR.FIN.

MODIFIED NOZZLE CLOSED CONVENTIONAL YES BOLTED YES ¾", 150#, RF, SERR.FIN. 1", 150#, RF, SERR.FIN.

ASTM A216 GR. WCB SS 316 SS 316

ASTM A216 GR. WCB SS 316 SS 316

NOMINAL

NOMINAL

0.720 - 0.775 0.7

0.775 - 0.87 1.6 - 8.0

GAS AND VAPOUR PROPERTIES MOLECULAR WEIGHT COMPRESSIBILITY FACTOR CP / CV FOR GAS FILLED VESSEL UNDER FIRE M2 VESSEL SURFACE AREA VESSEL WALL TEMPERATURE DEG C CORROSIVE CONSTITUENTS NOTE :

DATE

ZONE

DESCRIPTIONS

SECTION OIL & GAS NAME DSGN

DRWN

APPROVED

DATE

BY

CLIENT : CHKD

APPRD

Hindustan Petroleum Corporation Limited

DATE

PROJECT :

Project : Bahadurgarh Tikarikalan Pipeline Project of M/s HPCL

SPECIFICATION & DATA SHEET FOR THERMAL SAFETY VALVES

MECON LIMITED

SCALE : DATA SHEET NO. MEC/23LK/05/21/M/001/DS-TSV/01

REV 0

TYPICAL DATA SHEET FOR THERMAL SAFETY VALVES

PROJECT : BAHADURGARH TIKARIKALAN PIPELINE PROJECT 1 2 3 4 5 6 7 8 9

TAG NO.

CLIENT : HPCL JOB NO. : 23LK TSV-0501 TO 0503, 0605 TO 0608 (7 NOS.)

TSV-0305 TO 0307, 0601 TO 0604 (7 NOS.)

ULMS ¾" LINE 1" LINE

ULSHSD / SKO ¾" LINE 1" LINE

ULMS HC, LIQUID 15-45

ULSHSD / SKO HC, LIQUID 15-45

10

CASE NO. (IF ANY) SERVICE INLET LINE NO. OUTLET LINE NO. VESSEL NO. FLUID DISCHARGED FLUID STATE @ SV INLET OPERATING TEMPERATURE

DEG C DEG C

11

RELIEVING TEMPERATURE

KG/CM2 G

65

65

12 13

OPERATING PRESSURE

KG/CM2 G

ATM - 25

ATM - 25

SET PRESSURE MAXIMUM BACK PRESSURE

KG/CM2 G

49

49

14 15

BACK PRESSURE CONST/VARIABLE

CONSTANT

CONSTANT

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61

% OVER PRESSURE

REV. NO.

BASIS OF SELECTION VALVE DISCHARGE TO VALVE FULL NOZZLE / MODIFIED NOZZLE BONNET TYPE CONV. / BELLOWS / PILOT OPERATED CAP OVER ADJ. BOLT SCREWED / BOLTED TEST GAG INLET CONNECTION MATERIAL BODY & BONNET NOZZLE & DISC SPRING DATA AT SV INLET REQD DISCHARGE CAPACITY LIQUID KG/HR VAPOUR / GAS KG/HR LIQUID PROPERTIES SP GR. @ 15°C VISCOSITY AT 20°C, cSt

25

25

LIQUID THERMAL RELIEF SUMP TANK

LIQUID THERMAL RELIEF SUMP TANK

MODIFIED NOZZLE CLOSED CONVENTIONAL YES BOLTED YES ¾", 300#, RF, SMOOTH 1", 150#, RF, SERR.FIN.

MODIFIED NOZZLE CLOSED CONVENTIONAL YES BOLTED YES ¾", 300#, RF, SMOOTH 1", 150#, RF, SERR.FIN.

ASTM A216 GR. WCB SS 316 SS 316

ASTM A216 GR. WCB SS 316 SS 316

NOMINAL

NOMINAL

0.720 - 0.775 0.7

0.775 - 0.87 1.6 - 8.0

GAS AND VAPOUR PROPERTIES MOLECULAR WEIGHT COMPRESSIBILITY FACTOR CP / CV FOR GAS FILLED VESSEL UNDER FIRE M2 VESSEL SURFACE AREA VESSEL WALL TEMPERATURE DEG C CORROSIVE CONSTITUENTS NOTE :

DATE

ZONE

DESCRIPTIONS

SECTION OIL & GAS NAME DSGN

DRWN

APPROVED

DATE

BY

CLIENT : CHKD

APPRD

Hindustan Petroleum Corporation Limited

DATE

PROJECT :

Project : Bahadurgarh Tikarikalan Pipeline Project of M/s HPCL

SPECIFICATION & DATA SHEET FOR THERMAL SAFETY VALVES

MECON LIMITED

SCALE : DATA SHEET NO. MEC/23LK/05/21/M/001/DS-TSV/02

REV 0

1.0

Valve Manufacturer

:

2.0

Valve Size (NB), mm (inch)

:(20)3/4", (25)1"

3.0

Connecting Pipeline Design Pressure, kg/cm2(g)

4.0 4.1 4.2 4.3

Connecting Pipe Specification Material Diameter (OD), mm (inch) Thickness, mm

5.0 5.1 5.2

Valve Construction Design Bore End Connections

5.3

Flanges (wherever applicable)

5.4

Valve Type

6.0

Valve Material Specification Part Specified Material

6.1 6.2 6.3 6.4 6.5 6.6 6.7 6.8

Body Ball Body Seat Gland Stem Body Seal Stem Seal Body Studs/Nuts

7

: : : :

ANSI Rating : 800#

o

: --

Design Temperature, °C :0 C to +65°C

N.A.

Service

Location

:

Above Ground

9.0

Stem Extension Requirement

:

Yes

No



10.0

Gear Operator Requirement

:

Yes

No



11.0

Gas Powered Actuator Requirement

:

Yes

No



12.0

Fire Resistant Design Requirement

:

13.0

Valve Testing Requirement

13.1

Hydrostatic Test

13.2

Air Test

Test Pressure (min.), kg/cm2(g) 210 155 7.0

Anti-Static Testing Requirement

:

2. 3. 4. 5. 6. 7. 8. 9. 10.

REV. NO.

 

Material Offered

8.0

1.

NA NA

ASTM A 105 13% Cr Steel RPTFE/ DELRIN 13% Cr Steel 13% Cr Steel (No Casting) Grafoil Grafoil ASTM A 193 Gr B7/ A194 Gr. 7

1.5 mm

16

ULHSD/ULMS/SKO

 Reduced Full Socket Welded (as per ASME B16.11) 100mm Extension Pups in ASTM A106 Gr. B (Sch. 160) at both ends : a) RF FF RTJ b) Serrated Smooth(125 to 200 microinches AARH) : Floating Ball

:

15.0 15.1 15.2

:

: :

Corrosion Allowance

14

Design Standard : BS:5351(Latest)

Body Seat



Buried Length of Stem Extension, m : N.A.

Actuator Specification No.: N.A. Actuator Data Sheet No.:N.A. Type-Test as per Standard API 607/ BS:6755 (Part-II)(Latest)

Minimum Duration, minutes 2 2 15

As per Standard BS:5351 (Latest)

Valve Painting Specification : Surface preparation by Short Blasting as per grade SA 2 1/2, Swedish Standard SIS-055 909. Three coats of paint shall be applied with minimum thickness of 300 micron. (Permissible thickness in each coat shall be within 80 to 120 micron.) Lock Open/ Lock Close Requirement : As indicated in Material Requisition Notes: Charpy V- notch test for body, ball, gland, stem & studs/ nuts will be conducted as per relevant material code i.e; at 0°C on three samples having average value of 27J and minimum value shall be 22J. Material test certificates and hydrostatic test reports shall be furnished prior to despatch. Detailed dimensional drawings showing cross-section with part numbers and materials shall be submitted for Purchaser's approval prior to manufacture of the valves. All tests shall be as per BS:6755 (Part-I)(Latest). Valves shall have ball position indicator. Stops shall be provided to ensure positive alignment of ball with ports and ensure proper installation of handle. Each valve shall be provided with a wrench. Valves shall be inspected and approved by Purchaser before despatch. Gland packing assembly shall permit repair of gland packing under full line pressure. Inspection and Testing shall be as per this specification, BS:6755 (Part-I) (Latest) and other relevant standards and clause no. 5.0 of T.S. No.: MEC/TS/05/62/002, Ed. 1, Rev-0. DATE

ZONE

DESCRIPTIONS

BY

APPRD REFERENCES

SECTION PROCESS & PIPING NAME

DSGN

BB

DATE

CHKD

CLIENT : DATE

DRG. NO.

Hindustan Petroleum Corporation Limited

PROJECT :Bahadurgarh-Tikrikalan Pipeline Project

MECON LIMITED

DRWN

APPROVED

SPECIFICATION AND DATA SHEET FOR BALL VALVES (NB < 2'')

SCALE : DS NO. : MEC/23LK/05/21/M/001/DS/BV001

REV 0

1.0

Valve Manufacturer

:

2.0

Valve Size (NB), mm (inch)

:(25)1"

3.0

Connecting Pipeline Design Pressure, kg/cm2(g)

4.0 4.1 4.2 4.3

Connecting Pipe Specification Material Diameter (OD), mm (inch) Thickness, mm

5.0 5.1 5.2 5.3

Valve Construction Design Bore End Connections Flanges (wherever applicable)

5.4

Valve Type

6.0

Valve Material Specification Part

6.1 6.2

Body Ball

6.3 6.4 6.5 6.6 6.7

Body Seat Rings Seat Seal Stem Stem Seals Stud Bolts/ Nuts

: : : :

ANSI Rating : 800#

Design Standard : BS:5351(Latest) Design Temperature, °C :0oC to +65°C

: --

N.A.

Service

: Reduced Full  : Flanged (as per ASME B16.5) : a) RF  FF RTJ b) Serrated Smooth (125 to 200 microinches AARH) : Floating Ball

Specified Material

1.5 mm

8.0

Location

:

Above Ground

9.0

Stem Extension Requirement

:

Yes

No



10.0

Gear Operator Requirement

:

Yes

No



11.0

Gas Powered Actuator Requirement

:

Yes

12.0

Fire Resistant Design Requirement

:

13.0

Valve Testing Requirement Hydrostatic Test

13.2

Air Test

14 15.0 15.1 15.2

16 1. 2. 3. 4. 5. 6. 7. 8. 9. 10.

REV. NO.



NA NA

Length of Stem Extension, m : N.A.



Actuator Specification No.: N.A. Actuator Data Sheet No.: N.A. Type-Test as per Standard API 607/ BS:6755 (Part-II)(Latest)

:

Anti-Static Testing Requirement

Buried

No

Test Pressure (min.), kg/cm2(g) Body 210 Seat 155 7.0

Minimum Duration, minutes 2 2 15

As per Standard BS:5351 (Latest)

Valve Painting Specification : Surface preparation by Short Blasting as per grade SA 2 1/2, Swedish Standard SIS-055 909. Three coats of paint shall be applied with minimum thickness of 300 micron. (Permissible thickness in each coat shall be within 80 to 120 micron.) : As indicated in Material Requisition Lock Open/ Lock Close Requirement Notes: Charpy V- notch test for body, ball, gland, stem & studs/ nuts will be conducted as per relevant material code i.e; at 0°C on three samples having average value of 27J and minimum value shall be 22J. Material test certificates and hydrostatic test reports shall be furnished prior to despatch. Detailed dimensional drawings showing cross-section with part numbers and materials shall be submitted for Purchaser's approval prior to manufacture of the valves. All tests shall be as per BS:6755 (Part-I)(Latest). Valves shall have ball position indicator. Stops shall be provided to ensure positive alignment of ball with ports and ensure proper installation of handle. Each valve shall be provided with a wrench. Valves shall be inspected and approved by Purchaser before despatch. Gland packing assembly shall permit repair of gland packing under full line pressure. Inspection and Testing shall be as per this specification, BS:6755 (Part-I) (Latest) and other relevant standards and clause no. 5.0 of T.S. No.: MEC/TS/05/62/002, Ed. 1, Rev-0. DATE

ZONE

DESCRIPTIONS

BY

APPRD REFERENCES

SECTION PROCESS & PIPING NAME

DSGN



Material Offered

:

13.1

ULHSD/ULMS/SKO

ASTM A 216 Gr. WCB/A 234 Gr. WPB/ASTM A 350 LF2/ A 352 Gr. LCB ASTM A 216 Gr. WCB/A 234 Gr. WPB/ASTM A 350 LF2/ A 352 Gr. LCB/ SS 316 with ENP coating/ SS 316 with ENP coating AISI 4140 + ENP coating/SS 316 with ENP coating VITON AISI 4140 + ENP coating/SS 316 with ENP coating VITON/PTFE ASTM A 193 Gr. B7/ A194 Gr. 2H

Corrosion Allowance

7

:

BB

DATE

CHKD

DRG. NO.

CLIENT : Hindustan Petroleum Corporation DATE

Limited

PROJECT Bahadurgarh-Tikrikalan Pipeline Project

MECON LIMITED

DRWN

APPROVED

SPECIFICATION AND DATA SHEET FOR BALL VALVES (NB < 2'')

SCALE : DS NO. : MEC/23LK/05/21/M/001/DS/BV002

REV 0

1.0

Valve Manufacturer

:

2.0

Valve Size (NB), mm (inch)

: 50(2")

3.0

MECON's Technical Specification No.

:

4.0

Connecting Pipeline Design Pressure, kg/cm2(g)

5.0 5.1 5.2 5.3

Connecting Pipe Specification : Material Diameter (OD), mm Thickness, mm

6.0 6.1. 6.2. 6.3.

Valve Construction Design Bore End Connections Flanges (wherever applicable)

ANSI Rating : 150#

Design Standard : API 6D

MEC/TS/05/62/002, Ed. 1 Rev-0

: ULHSD/ULMS

Design Temperature, °C : 0oC to +65°C

: 19

: Reduced : Flanged as per ASME B 16.5 : a) RF  FF



Full

RTJ Smooth (125 to 200 microinches AARH)

b) Serrated :

Service

6.4

Valve Type

7.0

Valve Material Specification Part

7.1 7.2

Body Ball

7.3 7.4 7.5 7.6 7.7 8.0

Body Seat Rings Seat Seal Stem Stem Seals Stud Bolts/ Nuts

Corrosion Allowance

:

1.5 mm

9.0

Location

:

Above Ground

10.0

Stem Extension Requirement

:

Yes

No



11.0

Gear Operator Requirement

:

Yes

No



12.0

Gas Powered Actuator Requirement

:

Yes

No



13.0

Fire Resistant Design Requirement

:

API 6FA

14.0

Valve Testing Requirement



NA NA

Floating Ball

Specified Material

Material Offered

ASTM A 216 Gr. WCB/A 234 Gr. WPB/ASTM A 350 LF2/ A 352 Gr. LCB ASTM A 216 Gr. WCB/A 234 Gr. WPB/ASTM A 350 LF2/ A 352 Gr. LCB/ SS 316 with ENP coating/ SS 316 with ENP coating AISI 4140 + ENP coating/SS 316 with ENP coating VITON AISI 4140 + ENP coating/SS 316 with ENP coating VITON/PTFE ASTM A 193 Gr. B7/ A194 Gr. 2H



Buried

Test Pressure (min.), kg/cm2(g) 32 23 7.0

Minimum Duration, minutes 2" NB As per API 6D As per API 6D As per API 6D

14.1

Hydrostatic Test

14.2

Air Test

15.0

Anti-Static Testing Requirement

16.0 16.1 16.2

Valve Painting Specification : Surface preparation by Short Blasting as per grade SA 2 1/2, Swedish Standard SIS-055 909. Three coats of paint shall be applied with minimum thickness of 300 micron. (Permissible thickness in each coat shall be within 80 to 120 micron.)

17.0

: As indicated in Material Requisition Lock Open/ Lock Close Requirement Notes: 1. This Valve Data Sheet shall be read in conjunction with MECON's Technical Specification No. MEC/TS/05/62/002, Ed. 1, Rev-0 2. Inspection and Testing shall be as per attached QAP, this Data Sheet, MECON's T.S., API 6D and other relevant standards. 3. Stops shall be provided for positive alignment of ball with ports and ensure proper installation of handle. 4. Short pattern valves as per API 6D are not permitted, only long pattern valves are to be supplied. 5. Charpy V- notch test for body, ball, gland, stem & studs/ nuts will be conducted as per relevant material code i.e; at 0°C on three samples having average value of 27J and minimum value shall be 22J. 6. Ball & stem shall be ENP coated for minimum thickness of 80 microns.

REV. NO.

DATE

Body Seat

Length of Stem Extension, mm : N.A

ZONE

:

As per Standard API 6D (2002 Ed.)

DESCRIPTIONS

BY

APPRD REFERENCES

SECTION PROCESS & PIPING NAME

DSGN

BB

DATE

CHKD

CLIENT : DATE

DRG. NO.

Hindustan Petroleum Corporation Limited

PROJECT : Bahadurgarh-Tikrikalan Pipeline Project

MECON LIMITED

DRWN SCALE :

APPROVED

DATA SHEET FOR BALL VALVES (NB > 2")

DATA SHEET NO.:MEC/23LK/05/21/M/001/DS/BV003

REV 0

1.0

Valve Manufacturer

:

2.0

Valve Size (NB), mm (inch)

: 50(2")

3.0

MECON's Technical Specification No.

:

4.0

Connecting Pipeline Design Pressure, kg/cm2(g)

5.0 5.1 5.2 5.3

Connecting Pipe Specification : Material Diameter (OD), mm Thickness, mm

2" ASTM A 106 Gr. B(Charpy) (2.375)60.3 5.5

6.0 6.1. 6.2. 6.3.

Valve Construction Design Bore End Connections Flanges (wherever applicable)

: Reduced Full : Butt Weld as per ASME B 16.25

6.4

Valve Type

7.0

Valve Material Specification Part

7.1 7.2

Body Ball

7.3 7.4 7.5 7.6 7.7 8.0

Body Seat Rings Seat Seal Stem Stem Seals Stud Bolts/ Nuts

Corrosion Allowance

:

1.5 mm

9.0

Location

:

Above Ground

10.0

Stem Extension Requirement

:

Yes

No



11.0

Gear Operator Requirement

:

Yes

No



12.0

Gas Powered Actuator Requirement

:

Yes

No



13.0

Fire Resistant Design Requirement

:

API 6FA

14.0

Valve Testing Requirement

ANSI Rating : 150#

Design Standard : API 6D

MEC/TS/05/62/002, Ed. 1 Rev-0

Service

: ULHSD/ULMS o

: 19

Design Temperature, °C : 0 C to +65°C

: a) RF b) Serrated : Floating Ball



FF

RTJ

NA NA

Smooth(125 to 200 microinches AARH)

 

Material Offered

Specified Material

ASTM A 216 Gr. WCB/A 234 Gr. WPB/ASTM A 350 LF2/ A 352 Gr. LCB ASTM A 216 Gr. WCB/A 234 Gr. WPB/ASTM A 350 LF2/ A 352 Gr. LCB/ SS 316 with ENP coating/ SS 316 with ENP coating AISI 4140 + ENP coating/SS 316 with ENP coating VITON AISI 4140 + ENP coating/SS 316 with ENP coating VITON/PTFE ASTM A 193 Gr. B7/ A194 Gr. 2H



Buried

Test Pressure (min.), kg/cm2(g)

Minimum Duration, minutes 2" NB As per API 6D As per API 6D As per API 6D

14.1

Hydrostatic Test

14.2

Air Test

15.0

Anti-Static Testing Requirement

16.0 16.1 16.2

Valve Painting Specification : Surface preparation by Short Blasting as per grade SA 2 1/2, Swedish Standard SIS-055 909. Three coats of paint shall be applied with minimum thickness of 300 micron. (Permissible thickness in each coat shall be within 80 to 120 micron.)

17.0

Lock Open/ Lock Close Requirement : As indicated in Material Requisition Notes: 1. This Valve Data Sheet shall be read in conjunction with MECON's Technical Specification No. MEC/TS/05/62/002, Ed. 1, Rev-0 2. Inspection and Testing shall be as per attached QAP, this Data Sheet, MECON's T.S., API 6D and other relevant standards. 3. Stops shall be provided for positive alignment of ball with ports and ensure proper installation of handle. 4. Short pattern valves as per API 6D are not permitted, only long pattern valves are to be supplied. 5. Charpy V- notch test for body, ball, gland, stem & studs/ nuts will be conducted as per relevant material code i.e; at 0°C on three samples having average value of 27J and minimum value shall be 22J. 6. Ball & stem shall be ENP coated for minimum thickness of 80 microns.

REV. NO.

DATE

Body Seat

Length of Stem Extension, mm : N.A

ZONE

32 23 7.0 :

As per Standard API 6D (2002 Ed.)

DESCRIPTIONS

BY

APPRD REFERENCES

SECTION PROCESS & PIPING NAME

DSGN

BB

DATE

CHKD

CLIENT : DATE

DRG. NO.

Hindustan Petroleum Corporation Limited

PROJECT : Bahadurgarh-Tikrikalan Pipeline Project

MECON LIMITED

DRWN SCALE :

APPROVED

DATA SHEET FOR BALL VALVES (NB > 2")

DATA SHEET NO.:MEC/23LK/05/21/M/001/DS/BV004

REV 0

1.0

Valve Manufacturer

:

2.0

Valve Size (NB), mm (inch)

:(25)1"

3.0

Connecting Pipeline Design Pressure, kg/cm2(g)

4.0 4.1 4.2 4.3

Connecting Pipe Specification Material Diameter (OD), mm (inch) Thickness, mm

5.0 5.1 5.2 5.3

Valve Construction Design Bore End Connections Flanges (wherever applicable)

5.4

Valve Type

6.0

Valve Material Specification Part

6.1 6.2 6.3 6.4 6.5 6.6 6.7

Body Ball Body Seat Rings Seat Seal Stem Stem Seals Stud Bolts/ Nuts

: : : :

ANSI Rating : 800#

Design Standard : BS:5351(Latest) Design Temperature, °C :0oC to +65°C

: --

N.A.

Service

: Reduced Full  : Flanged (as per ASME B16.5) : a) RF  FF RTJ b) Serrated Smooth (125 to 200 microinches AARH) : Floating Ball

Specified Material

1.5 mm

8.0

Location

:

Above Ground

9.0

Stem Extension Requirement

:

Yes

No



10.0

Gear Operator Requirement

:

Yes

No



11.0

Gas Powered Actuator Requirement

:

Yes

12.0

Fire Resistant Design Requirement

:

13.0

Valve Testing Requirement

13.1

Hydrostatic Test

13.2

Air Test

Test Pressure (min.), kg/cm2(g) 210 155 7.0

Anti-Static Testing Requirement

:

15.0 15.1 15.2

16 1. 2. 3. 4. 5. 6. 7. 8. 9. 10.

REV. NO.

Body Seat

NA NA



Buried Length of Stem Extension, m : N.A.



Actuator Specification No.: N.A. Actuator Data Sheet No.: N.A. Type-Test as per Standard API 607/ BS:6755 (Part-II)(Latest) No

Minimum Duration, minutes 2 2 15

As per Standard BS:5351 (Latest)

Valve Painting Specification : Surface preparation by Short Blasting as per grade SA 2 1/2, Swedish Standard SIS-055 909. Three coats of paint shall be applied with minimum thickness of 300 micron. (Permissible thickness in each coat shall be within 80 to 120 micron.) : As indicated in Material Requisition Lock Open/ Lock Close Requirement Notes: Charpy V- notch test for body, ball, gland, stem & studs/ nuts will be conducted as per relevant material code i.e; at 0°C on three samples having average value of 27J and minimum value shall be 22J. Material test certificates and hydrostatic test reports shall be furnished prior to despatch. Detailed dimensional drawings showing cross-section with part numbers and materials shall be submitted for Purchaser's approval prior to manufacture of the valves. All tests shall be as per BS:6755 (Part-I)(Latest). Valves shall have ball position indicator. Stops shall be provided to ensure positive alignment of ball with ports and ensure proper installation of handle. Each valve shall be provided with a wrench. Valves shall be inspected and approved by Purchaser before despatch. Gland packing assembly shall permit repair of gland packing under full line pressure. Inspection and Testing shall be as per this specification, BS:6755 (Part-I) (Latest) and other relevant standards and clause no. 5.0 of T.S. No.: MEC/TS/05/62/002, Ed. 1, Rev-0. DATE

ZONE

DESCRIPTIONS

BY

APPRD REFERENCES

SECTION PROCESS & PIPING NAME

DSGN



Material Offered

:

14

ULHSD/ULMS/SKO

ASTM A 351 Gr. CF8 ASTM A 351 Gr. CF8/SS 304 with ENP coating SS 304 with ENP coating VITON SS 304 with ENP coating VITON/PTFE ASTM A 193 Gr. B7/ A194 Gr. 2H

Corrosion Allowance

7

:

BB

DATE

CHKD

DRG. NO.

CLIENT : Hindustan Petroleum Corporation DATE

Limited

PROJECT Bahadurgarh-Tikrikalan Pipeline Project

MECON LIMITED

DRWN

APPROVED

SPECIFICATION AND DATA SHEET FOR BALL VALVES (NB < 2'')

SCALE : DS NO. : MEC/23LK/05/21/M/001/DS/BV005

REV 0

1.0

Valve Manufacturer

:

2.0

Valve Size (NB), mm (inch)

: 50(2")

3.0

MECON's Technical Specification No.

:

4.0

Connecting Pipeline Design Pressure, kg/cm2(g)

5.0 5.1 5.2 5.3

Connecting Pipe Specification : Material Diameter (OD), mm Thickness, mm

6.0 6.1. 6.2. 6.3.

Valve Construction Design Bore End Connections Flanges (wherever applicable)

ANSI Rating : 150#

Design Standard : API 6D

MEC/TS/05/62/002, Ed. 1 Rev-0

:

ULHSD/ULMS/SKO

Design Temperature, °C : 0oC to +65°C

: 19

: Reduced : Flanged as per ASME B 16.5 : a) RF  FF



Full

RTJ Smooth (125 to 200 microinches AARH)

b) Serrated :

Service

6.4

Valve Type

7.0

Valve Material Specification Part

7.1 7.2 7.3 7.4 7.5 7.6 7.7 8.0

Body Ball Body Seat Rings Seat Seal Stem Stem Seals Stud Bolts/ Nuts

Corrosion Allowance

:

1.5 mm

9.0

Location

:

Above Ground

10.0

Stem Extension Requirement

:

Yes

No



11.0

Gear Operator Requirement

:

Yes

No



12.0

Gas Powered Actuator Requirement

:

Yes

No



13.0

Fire Resistant Design Requirement

:

API 6FA

14.0

Valve Testing Requirement



NA NA

Floating Ball

Specified Material

Material Offered

ASTM A 351 Gr. CF8 ASTM A 351 Gr. CF8/SS 304 with ENP coating SS 304 with ENP coating VITON SS 304 with ENP coating VITON/PTFE ASTM A 193 Gr. B7/ A194 Gr. 2H



Buried

Test Pressure (min.), kg/cm2(g) 32 23 7.0

Minimum Duration, minutes 2" NB As per API 6D As per API 6D As per API 6D

14.1

Hydrostatic Test

14.2

Air Test

15.0

Anti-Static Testing Requirement

16.0 16.1 16.2

Valve Painting Specification : Surface preparation by Short Blasting as per grade SA 2 1/2, Swedish Standard SIS-055 909. Three coats of paint shall be applied with minimum thickness of 300 micron. (Permissible thickness in each coat shall be within 80 to 120 micron.)

17.0

: As indicated in Material Requisition Lock Open/ Lock Close Requirement Notes: 1. This Valve Data Sheet shall be read in conjunction with MECON's Technical Specification No. MEC/TS/05/62/002, Ed. 1, Rev-0 2. Inspection and Testing shall be as per attached QAP, this Data Sheet, MECON's T.S., API 6D and other relevant standards. 3. Stops shall be provided for positive alignment of ball with ports and ensure proper installation of handle. 4. Short pattern valves as per API 6D are not permitted, only long pattern valves are to be supplied. 5. Charpy V- notch test for body, ball, gland, stem & studs/ nuts will be conducted as per relevant material code i.e; at 0°C on three samples having average value of 27J and minimum value shall be 22J. 6. Ball & stem shall be ENP coated for minimum thickness of 80 microns.

REV. NO.

DATE

Body Seat

Length of Stem Extension, mm : N.A

ZONE

:

As per Standard API 6D (2002 Ed.)

DESCRIPTIONS

BY

APPRD REFERENCES

SECTION PROCESS & PIPING NAME

DSGN

BB

DATE

CHKD

CLIENT : DATE

DRG. NO.

Hindustan Petroleum Corporation Limited

PROJECT : Bahadurgarh-Tikrikalan Pipeline Project

MECON LIMITED

DRWN SCALE :

APPROVED

DATA SHEET FOR BALL VALVES (NB > 2")

DATA SHEET NO.:MEC/23LK/05/21/M/001/DS/BV006

REV 0

1.0

Valve Manufacturer

:

2.0

Valve Size (NB), mm (inch)

: 50(2")

3.0

MECON's Technical Specification No.

:

4.0

Connecting Pipeline Design Pressure, kg/cm2(g)

5.0 5.1 5.2 5.3

Connecting Pipe Specification : Material Diameter (OD), mm Thickness, mm

6.0 6.1. 6.2. 6.3.

Valve Construction Design Bore End Connections Flanges (wherever applicable)

ANSI Rating : 300#

Design Standard : API 6D

MEC/TS/05/62/002, Ed. 1 Rev-0

:

ULHSD/ULMS/SKO

Design Temperature, °C : 0oC to +65°C

: 49

: Reduced : Flanged as per ASME B 16.5 : a) RF  FF



Full

RTJ Smooth (125 to 200 microinches AARH)

b) Serrated :

Service

6.4

Valve Type

7.0

Valve Material Specification Part

7.1 7.2

Body Ball

7.3 7.4 7.5 7.6 7.7 8.0

Body Seat Rings Seat Seal Stem Stem Seals Stud Bolts/ Nuts

Corrosion Allowance

:

1.5 mm

9.0

Location

:

Above Ground

10.0

Stem Extension Requirement

:

Yes

No



11.0

Gear Operator Requirement

:

Yes

No



12.0

Gas Powered Actuator Requirement

:

Yes

No



13.0

Fire Resistant Design Requirement

:

API 6FA

14.0

Valve Testing Requirement



NA NA

Floating Ball

Specified Material

Material Offered

ASTM A 216 Gr. WCB/A 234 Gr. WPB/ASTM A 350 LF2/ A 352 Gr. LCB ASTM A 216 Gr. WCB/A 234 Gr. WPB/ASTM A 350 LF2/ A 352 Gr. LCB/ SS 316 with ENP coating/ SS 316 with ENP coating AISI 4140 + ENP coating/SS 316 with ENP coating VITON AISI 4140 + ENP coating/SS 316 with ENP coating VITON/PTFE ASTM A 193 Gr. B7/ A194 Gr. 2H



Buried

Test Pressure (min.), kg/cm2(g) 78 57 7.0

Minimum Duration, minutes 2" NB As per API 6D As per API 6D As per API 6D

14.1

Hydrostatic Test

14.2

Air Test

15.0

Anti-Static Testing Requirement

16.0 16.1 16.2

Valve Painting Specification : Surface preparation by Short Blasting as per grade SA 2 1/2, Swedish Standard SIS-055 909. Three coats of paint shall be applied with minimum thickness of 300 micron. (Permissible thickness in each coat shall be within 80 to 120 micron.)

17.0

: As indicated in Material Requisition Lock Open/ Lock Close Requirement Notes: 1. This Valve Data Sheet shall be read in conjunction with MECON's Technical Specification No. MEC/TS/05/62/002, Ed. 1, Rev-0 2. Inspection and Testing shall be as per attached QAP, this Data Sheet, MECON's T.S., API 6D and other relevant standards. 3. Stops shall be provided for positive alignment of ball with ports and ensure proper installation of handle. 4. Short pattern valves as per API 6D are not permitted, only long pattern valves are to be supplied. 5. Charpy V- notch test for body, ball, gland, stem & studs/ nuts will be conducted as per relevant material code i.e; at 0°C on three samples having average value of 27J and minimum value shall be 22J. 6. Ball & stem shall be ENP coated for minimum thickness of 80 microns.

REV. NO.

DATE

Body Seat

Length of Stem Extension, mm : N.A

ZONE

:

As per Standard API 6D (2002 Ed.)

DESCRIPTIONS

BY

APPRD REFERENCES

SECTION PROCESS & PIPING NAME

DSGN

BB

DATE

CHKD

CLIENT : DATE

DRG. NO.

Hindustan Petroleum Corporation Limited

PROJECT : Bahadurgarh-Tikrikalan Pipeline Project

MECON LIMITED

DRWN SCALE :

APPROVED

DATA SHEET FOR BALL VALVES (NB > 2")

DATA SHEET NO.:MEC/23LK/05/21/M/001/DS/BV007

REV 0

1.0

Valve Manufacturer

:

2.0

Valve Size (NB), mm (inch)

: 50(2")

3.0

MECON's Technical Specification No.

:

4.0

Connecting Pipeline Design Pressure, kg/cm2(g)

: 49

5.0 5.1 5.2 5.3

Connecting Pipe Specification : Material Diameter (OD), mm Thickness, mm

2" ASTM A 106 Gr. B(Charpy) (2.375)60.3 5.5

6.0 6.1. 6.2. 6.3.

Valve Construction Design Bore End Connections Flanges (wherever applicable)

ANSI Rating : 300#

Design Standard : API 6D

MEC/TS/05/62/002, Ed. 1 Rev-0

Service

:

ULHSD/ULMS/SKO

Design Temperature, °C : 0oC to +65°C



: Reduced Full : Butt Welded as per ASME B 16.25 : a) RF b) Serrated

:

FF

RTJ Smooth (125 to 200 microinches AARH)

6.4

Valve Type

7.0

Valve Material Specification Part

7.1 7.2

Body Ball

7.3 7.4 7.5 7.6 7.7 8.0

Body Seat Rings Seat Seal Stem Stem Seals Stud Bolts/ Nuts

Corrosion Allowance

:

1.5 mm

9.0

Location

:

Above Ground

10.0

Stem Extension Requirement

:

Yes

No



11.0

Gear Operator Requirement

:

Yes

No



12.0

Gas Powered Actuator Requirement

:

Yes

No



13.0

Fire Resistant Design Requirement

:

API 6FA

14.0

Valve Testing Requirement

NA NA

 

Floating Ball

Material Offered

Specified Material

ASTM A 216 Gr. WCB/A 234 Gr. WPB/ASTM A 350 LF2/ A 352 Gr. LCB ASTM A 216 Gr. WCB/A 234 Gr. WPB/ASTM A 350 LF2/ A 352 Gr. LCB/ SS 316 with ENP coating/ SS 316 with ENP coating AISI 4140 + ENP coating/SS 316 with ENP coating VITON AISI 4140 + ENP coating/SS 316 with ENP coating VITON/PTFE ASTM A 193 Gr. B7/ A194 Gr. 2H



Buried

Test Pressure (min.), kg/cm2(g) 78 57 7.0

Minimum Duration, minutes 2" NB As per API 6D As per API 6D As per API 6D

14.1

Hydrostatic Test

14.2

Air Test

15.0

Anti-Static Testing Requirement

16.0 16.1 16.2

Valve Painting Specification : Surface preparation by Short Blasting as per grade SA 2 1/2, Swedish Standard SIS-055 909. Three coats of paint shall be applied with minimum thickness of 300 micron. (Permissible thickness in each coat shall be within 80 to 120 micron.)

17.0

: As indicated in Material Requisition Lock Open/ Lock Close Requirement Notes: 1. This Valve Data Sheet shall be read in conjunction with MECON's Technical Specification No. MEC/TS/05/62/002, Ed. 1, Rev-0 2. Inspection and Testing shall be as per attached QAP, this Data Sheet, MECON's T.S., API 6D and other relevant standards. 3. Stops shall be provided for positive alignment of ball with ports and ensure proper installation of handle. 4. Short pattern valves as per API 6D are not permitted, only long pattern valves are to be supplied. 5. Charpy V- notch test for body, ball, gland, stem & studs/ nuts will be conducted as per relevant material code i.e; at 0°C on three samples having average value of 27J and minimum value shall be 22J. 6. Ball & stem shall be ENP coated for minimum thickness of 80 microns.

REV. NO.

DATE

Body Seat

Length of Stem Extension, mm : N.A

ZONE

:

As per Standard API 6D (2002 Ed.)

DESCRIPTIONS

BY

APPRD REFERENCES

SECTION PROCESS & PIPING NAME

DSGN

BB

DATE

CHKD

CLIENT : DATE

DRG. NO.

Hindustan Petroleum Corporation Limited

PROJECT : Bahadurgarh-Tikrikalan Pipeline Project

MECON LIMITED

DRWN SCALE :

APPROVED

DATA SHEET FOR BALL VALVES (NB > 2")

DATA SHEET NO.:MEC/23LK/05/21/M/001/DS/BV008

REV 0

1.0

Valve Manufacturer

:

2.0

Valve Size (NB), mm (inch)

: 100(4")

3.0

MECON's Technical Specification No.

:

4.0

Connecting Pipeline Design Pressure, kg/cm2(g)

: 49

5.0 5.1 5.2 5.3

Connecting Pipe Specification : Material Diameter (OD), mm Thickness, mm

4" ASTM A 106 Gr. B(Charpy) (4.5)114.3 6.0

6.0 6.1. 6.2. 6.3.

Valve Construction Design Bore End Connections Flanges (wherever applicable)

ANSI Rating : 300#

Design Standard : API 6D

MEC/TS/05/62/002, Ed. 1 Rev-0

Service

:

ULHSD/ULMS/SKO

Design Temperature, °C : 0oC to +65°C

 : Reduced Full : Butt Welded as per ASME B 16.25 : a) RF b) Serrated :

FF

RTJ Smooth (125 to 200 microinches AARH)

6.4

Valve Type

7.0

Valve Material Specification Part

7.1 7.2

Body Ball

7.3 7.4 7.5 7.6 7.7 8.0

Body Seat Rings Seat Seal Stem Stem Seals Stud Bolts/ Nuts

Corrosion Allowance

:

1.5 mm

9.0

Location

:

Above Ground

10.0

Stem Extension Requirement

:

Yes

No



11.0

Gear Operator Requirement

:

Yes

No



12.0

Gas Powered Actuator Requirement

:

Yes

No



13.0

Fire Resistant Design Requirement

:

API 6FA

14.0

Valve Testing Requirement

NA NA

 

Floating Ball

Specified Material

Material Offered

ASTM A 216 Gr. WCB/A 234 Gr. WPB/ASTM A 350 LF2/ A 352 Gr. LCB ASTM A 216 Gr. WCB/A 234 Gr. WPB/ASTM A 350 LF2/ A 352 Gr. LCB/ SS 316 with ENP coating/ SS 316 with ENP coating AISI 4140 + ENP coating/SS 316 with ENP coating VITON AISI 4140 + ENP coating/SS 316 with ENP coating VITON/PTFE ASTM A 193 Gr. B7/ A194 Gr. 2H



Buried

Test Pressure (min.), kg/cm2(g) 78 57 7.0

Minimum Duration, minutes 4" NB As per API 6D As per API 6D As per API 6D

14.1

Hydrostatic Test

14.2

Air Test

15.0

Anti-Static Testing Requirement

16.0 16.1 16.2

Valve Painting Specification : Surface preparation by Short Blasting as per grade SA 2 1/2, Swedish Standard SIS-055 909. Three coats of paint shall be applied with minimum thickness of 300 micron. (Permissible thickness in each coat shall be within 80 to 120 micron.)

17.0

: As indicated in Material Requisition Lock Open/ Lock Close Requirement Notes: 1. This Valve Data Sheet shall be read in conjunction with MECON's Technical Specification No. MEC/TS/05/62/002, Ed. 1, Rev-0 2. Inspection and Testing shall be as per attached QAP, this Data Sheet, MECON's T.S., API 6D and other relevant standards. 3. Stops shall be provided for positive alignment of ball with ports and ensure proper installation of handle. 4. Short pattern valves as per API 6D are not permitted, only long pattern valves are to be supplied. 5. Charpy V- notch test for body, ball, gland, stem & studs/ nuts will be conducted as per relevant material code i.e; at 0°C on three samples having average value of 27J and minimum value shall be 22J. 6. Ball & stem shall be ENP coated for minimum thickness of 80 microns.

REV. NO.

DATE

Body Seat

Length of Stem Extension, mm : N.A

ZONE

:

As per Standard API 6D (2002 Ed.)

DESCRIPTIONS

BY

APPRD REFERENCES

SECTION PROCESS & PIPING NAME

DSGN

BB

DATE

CHKD

CLIENT : DATE

DRG. NO.

Hindustan Petroleum Corporation Limited

PROJECT : Bahadurgarh-Tikrikalan Pipeline Project

MECON LIMITED

DRWN SCALE :

APPROVED

DATA SHEET FOR BALL VALVES (NB > 2")

DATA SHEET NO.:MEC/23LK/05/21/M/001/DS/BV009

REV 0

1.0

Valve Manufacturer

:

2.0

Valve Size (NB), mm (inch)

:

3.0

MECON's Technical Specification No.

:

4.0

Connecting Pipeline Design Pressure, kg/cm2(g)

5.0 5.1 5.2 5.3

Connecting Pipe Specification Material Diameter (OD), mm (inch) Thickness, mm

6.0 6.1. 6.2.

Valve Construction Design Pattern End Connections

15(1/2") - 20(3/4")

ANSI Rating :800#

: --

Design Standard : BS:5353

Design Temperature, °C : 0 to +65

: : : :

N.A.

: : :

Short Flanged both ends Socket Weld both ends

Regular

 

Venturi as per ASME B16.11

Flanged one end, Socket weld other end 6.3.

Flanges (wherever applicable)

: a) RF b) Serrated

FF

RTJ Smooth(125 to 200 microinches AARH)

7.0

Valve Material Specification Part

7.1 7.2 7.3 7.4 7.5 7.6 7.7 7.8

Body Plug (Lubricated) Bung (Screwed) Stem (No Casting) Gland Gland Packing Gasket Body Studs/Nuts

8.0

Corrosion Allowance

:

1.5 mm

9.0

Location

:

Above Ground

10.0

Stem Extension Requirement

:

Yes

No



11.0

Gear Operator Requirement

:

Yes

No



12.0

Gas Powered Actuator Requirement

:

Yes

No



13.0

Fire Resistant Design Requirement

:

14.0

Valve Testing Requirement

14.1

Hydrostatic Test

14.2

Air Test

Test Pressure (min.), kg/cm2(g) 210 155 7.0

15.0 15.1 15.2

Valve Painting Specification Suitable for Environment Type Manufacturer's Painting Spec. No.

: :

1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. REV. NO.

Specified Material

 

Material Offered (Equivalent or Superior)

ASTM A105 ASTM A105 + 75 microns ENP ASTM A105 AISI 410 ASTM A105 Graphite/ PTFE N.A. N.A.

Body Seat

Service : ULHSD/ULMS 

Buried Length of Stem Extension, m : N.A.

Actuator Specification No.: N.A. Actuator Data Sheet No.:N.A. Type-Test as per Standard BS:6755 (Part-II)

Minimum Duration, minutes 2 2 15

Corrosive Industrial Environment Manufacturer to furnish

Notes: Valves shall have an inherent feature using the line pressure to ensure that the line pressure cannot cause taper locking of the plug/ plug movement into the taper, i.e., valves shall be of "pressure-balanced design". Painting of valves shall be as per Manufacturer's standard. Material test certificates and hydrostatic test reports shall be furnished prior to despatch. Detailed dimensional drawings showing cross-section with part numbers and materials shall be submitted for Purchaser's approval prior to manufacture of the valves. All tests shall be as per BS:6755 (Part-I). Valves shall have valve position indicator. Stops shall be provided to ensure positive alignment of plug with ports and ensure proper installation of handle. Each valve shall be provided with a wrench. Valves shall be inspected and approved by Purchaser before despatch. Gland packing assembly shall permit repair of gland packing under full line pressure. Inspection and Testing shall be as per this specification, BS:6755 (Part-I) and other relevant standards. DATE

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS

SECTION OIL & GAS NAME DSGN

NA NA

BB

DRWN

APPROVED

DATE

REFERENCES

CLIENT : CHKD

DRG. NO.

Hindustan Petroleum Corporation Limited

DATE

PROJECT : Bahadurgarh-Tikrikalan Pipeline Project

SPECIFICATION AND DATA SHEET FOR PLUG VALVES (NB 15mm - 40mm)

d:\fateh\IPPs KG Basin\tender rfq\Plug Valves\vd55\Data Sheet - PV - 001

MECON LIMITED SCALE : Data Sheet No.: MEC/23LK/05/21/M/001/DS/PV001

REV 0

1.0

Valve Manufacturer

:

2.0

Valve Size (NB), mm (inch)

: 50(1")

3.0

MECON's Technical Specification No. :

4.0

Connecting Pipeline Design Pressure, kg/cm2(g)

5.0 5.1 5.2 5.3

Connecting Pipe Specification Material Diameter (OD), mm (inch) Thickness, mm

: : : :

6.0 6.1.

Valve Construction Design Port

:

Full

6.2.

End Connections

: :

Flanged both ends Butt Weld both ends Flanged one end, butt weld other end

6.3.

Flanges (wherever applicable)

: a) RF  b) Serrated

7.0

ANSI Rating : 800#

MEC/TS/05/62/004, Rev-2

Service

: ULHSD/ULMS

Design Temperature, °C : 0oC to +65oC

: ----

N.A.



Regular

FF

7.4 7.5 7.6 7.7 7.8 7.9 7.10 8.0

Corrosion Allowance

:

1.5 mm

9.0

Location

:

Above Ground

10.0

Stem Extension Requirement

:

N.A.

11.0

Gear Operator Requirement

:

N.A.

12.0

Gas Powered Actuator Requirement

:

N.A.

13.0

Fire Resistant Design Requirement

:

N.A.

14.0

Valve Testing Requirement



Flanged (as per ASME B16.5)



NA NA

Material Offered (Equivalent or Superior)

Buried

Test Pressure (min.), kg/cm2(g) Body Seat



RTJ Smooth (125 to 200 microinches AARH)

Valve Material Specification Part Specified Material Body ASTM A 216 Gr. WCB Cover ASTM A 216 Gr. WCB Disc/ Plates (ASTM A 216 Gr. WCB + 13% Cr Steel Facing) / 13% Cr Steel Body Seat Rings (See Note-3) ASTM A 216 Gr. WCB + 13% Cr Steel Facing Disc Hinge ASTM A 216 Gr. WCB Hinge Pin 13% Cr Steel (No Casting) Cover Stud Bolts ASTM A 193 Gr. B7 Nuts ASTM A 194 Gr. 2H Cover Gasket SS 304 Spiral Wound with C.A. Filler Spring Inconel X-750

7.1 7.2 7.3

Design Standard : BS: 5353

Minimum Duration, minutes As per BS:5353 As per BS:5353

14.1

Hydrostatic Test

15.0 15.1 15.2

Valve Painting Specification Suitable for Environment Type Manufacturer's Painting Spec. No.

: :

Corrosive Industrial Environment Manufacturer to furnish

16.0

Lock Open/ Lock Close Requirement

:

As indicated in Material Requisition

32 23

Notes: 1. This Valve Data Sheet shall be read in conjunction with MECON's Technical Specification No. MEC/TS/05/62/004, Rev-2 2. Inspection and Testing shall be as per this Data Sheet, MECON's T.S., BS:5353 and other relevant standards. 3. Seats shall be non-renewable integral type. 4. Charpy 'v' notch test for body, disc, body seat rings, stem & studs/ nuts will be conducted as per relevant material code. REV. NO.

DATE

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS

SECTION PROCESS & PIPING NAME

DATE

CHKD

CLIENT :

REFERENCES

DRG. NO.

Hindustan Petroleum Corporation Limited

DATE

PROJECT : DSGN

MECON LIMITED

Bahadurgarh-Tikrikalan Pipeline Project

BB

DRWN

SCALE :

APPROVED

A.K. JOHRI

DATA SHEET FOR CHECK VALVES (NB > 2")

DATA SHEET NO. : MEC/23LK/05/21/M/001/DS/CV002

REV 0

1.0

Valve Manufacturer

:

2.0

Valve Size (NB), mm (inch)

: 50(2"), 100(4")

3.0

MECON's Technical Specification No. :

4.0

Connecting Pipeline Design Pressure, kg/cm2(g)

5.0 5.1 5.2 5.3

Connecting Pipe Specification Material Diameter (OD), mm (inch) Thickness, mm

: : : :

6.0 6.1.

Valve Construction Design Port

:

Full

6.2.

End Connections

: :

Flanged both ends Butt Weld both ends Flanged one end, butt weld other end

6.3.

Flanges (wherever applicable)

: a) RF  b) Serrated

7.0

ANSI Rating : 150#

MEC/TS/05/62/004, Rev-2

Service

: ULHSD/ULMS

Design Temperature, °C : 0oC to +65oC

: 19

N.A.

Regular

FF

7.4 7.5 7.6 7.7 7.8 7.9 7.10 8.0

Corrosion Allowance

:

1.5 mm

9.0

Location

:

Above Ground

10.0

Stem Extension Requirement

:

N.A.

11.0

Gear Operator Requirement

:

N.A.

12.0

Gas Powered Actuator Requirement

:

N.A.

13.0

Fire Resistant Design Requirement

:

N.A.

14.0

Valve Testing Requirement





Flanged (as per ASME B16.5)



NA NA

Material Offered (Equivalent or Superior)

Buried

Test Pressure (min.), kg/cm2(g) Body Seat



RTJ Smooth (125 to 200 microinches AARH)

Valve Material Specification Part Specified Material Body ASTM A 216 Gr. WCB Cover ASTM A 216 Gr. WCB Disc/ Plates (ASTM A 216 Gr. WCB + 13% Cr Steel Facing) / 13% Cr Steel Body Seat Rings (See Note-3) ASTM A 216 Gr. WCB + 13% Cr Steel Facing Disc Hinge ASTM A 216 Gr. WCB Hinge Pin 13% Cr Steel (No Casting) Cover Stud Bolts ASTM A 193 Gr. B7 Nuts ASTM A 194 Gr. 2H Cover Gasket SS 304 Spiral Wound with C.A. Filler Spring Inconel X-750

7.1 7.2 7.3

Design Standard : API 6D

Minimum Duration, minutes API 6D API 6D

14.1

Hydrostatic Test

15.0 15.1 15.2

Valve Painting Specification Suitable for Environment Type Manufacturer's Painting Spec. No.

: :

Corrosive Industrial Environment Manufacturer to furnish

16.0

Lock Open/ Lock Close Requirement

:

As indicated in Material Requisition

32 23

Notes: 1. This Valve Data Sheet shall be read in conjunction with MECON's Technical Specification No. MEC/TS/05/62/004, Rev-2 2. Inspection and Testing shall be as per this Data Sheet, MECON's T.S., API 6D and other relevant standards. 3. Seats shall be non-renewable integral type. 4 Short pattern Valves are not acceptable, only large pattern Valves as per API-6D to be quoted 5. Charpy 'v' notch test for body, disc, body seat rings, stem & studs/ nuts will be conducted as per relevant material code. REV. NO.

DATE

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS

SECTION PROCESS & PIPING NAME DSGN

DATE

CHKD

CLIENT : DATE

REFERENCES

Corporation Limited

PROJECT : Bahadurgarh-Tikrikalan

BB

DRG. NO.

Hindustan Petroleum

MECON LIMITED

Pipeline Project

DRWN

SCALE :

APPROVED

A.K. JOHRI

DATA SHEET FOR CHECK VALVES (NB > 2")

DATA SHEET NO. : MEC/23LK/05/21/M/001/DS/CV002

REV 0

DATA SHEET FOR GATE VALVES 1.

Valve Manufacturer

:

2.

Service

: ULHSD/ULMS

3.

Size

4.

Purchaser's Specification

:

Refer Technical notes for Gate & Globe Valves

5.

Design Pressure

:

19 kg/cm2(g)

6.

Bore

:

Reduced

7.

Corrosion Allowance

:

1.5mm

8.

End Connections

:

 Flanged both ends as per ASME B 16.5 Butt Weld both ends Socket Welded ( as per ASME B 16.11) {with 100mm Pup Pieces on both sides as per ASTM A 106 Gr. B(Sch 160)} Flanged one end butt weld other end

9.

Flanges (where applicable)

: a) RF

:

50(2"), 100(4")

Rating : ANSI 150#



FF

RTJ

N.A.

Smooth (125 to 200 AARH)

Pipe Specification

11.

Valve Material Specification (or Equivalent/ Superior) : a) Body : A 216 Gr. WCB/ A234 Gr. WPB b) Bonnet (Bolted) : A 216 Gr. WCB/ A234 Gr. WPB c) Stem (Rising) : 13% CR. Steel (No casting) b) Wedge Disc : 13% CR. Steel (Stellited) e) Body Seat Ring : 13% CR. Steel (Stellited) f) Stem Packing (Renewable : Graphited Braided Asbestos with sacrifical with valve open on stream) inhibitor & Inconel wire reinforcement g) Hand Wheel (Rising) : Malleable Iron/ Cast Steel/ Fab. Steel h) Bonnet Bolts : ASTM A193 Gr. B7 i) Bonnet Nuts : ASTM A194 Gr. 2H j) Bonnet Gasket : Spiral Wound SS 304/316 + CA Filler k)Gear Operation Requirement : Not required.

13.

API-602

Full

10.

12.

:

:

Design Temperature : 0oC to +65°C 

b) Serrated

Design Standard



N.A.

N.A.

Hydrostatic Test Pressure a) Body b) Seat

: :

32 kg/cm 2(g) 23 kg/cm 2(g)

Time 2 2

Test Pressure with Air

:

7.0 kg/cm 2(g)

15

Material Offered : : : : : : : : : :

Notes: 1. 2. 3. 4. 5.

REV. NO.

DATE

Valve specification seet shall be read in conjunction with technical notes for valves. Valve shall be designed for intrinsically fire safe. Testing shall be as per API-598. Bidder shall clearly write all/ any deviation against each part/ material of valve in the space provided for . Wherever bidder agrees with MECON's data sheet, bidder shall clearly indicate "agreed". Paint shall be suitable for corrosive industrial environment.

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS

SECTION PROCESS & PIPING NAME DSGN

BB

DRWN

DATE

CHKD

CLIENT : DATE

REFERENCES

DRG. NO.

Hindustan Petroleum Corporation Limited

PROJECT : Bahadurgarh-Tikrikalan Pipeline Project

MECON LIMITED SCALE :

APPROVED

A.K. JOHRI DATA SHEET FOR GATE VALVES

DATA SHEET NO. MEC/23LK/05/21/M/001/DS001(GATE)

REV 0

DATA SHEET FOR GATE VALVES 1.

Valve Manufacturer

:

2.

Service

: ULHSD/ULMS

3.

Size

4.

Purchaser's Specification

:

5.

Design Pressure

:

49 kg/cm2(g)

6.

Bore

:

Reduced

7.

Corrosion Allowance

:

1.5mm

8.

End Connections

:

Flanged both ends as per ASME B 16.5  Butt Weld both ends as per ASME B 16.25 Socket Welded ( as per ASME B 16.11) {with 100mm Pup Pieces on both sides as per ASTM A 106 Gr. B(Sch 160)} Flanged one end butt weld other end

9.

Flanges (where applicable)

: a) RF

:

(80)3", (100)4"

Rating : ANSI 300#

API-602

:

Design Temperature : 0oC to +65°C 

FF

Full

RTJ

N.A.



Smooth (125 to 200 AARH)

10.

Pipe Specification

11.

Valve Material Specification (or Equivalent/ Superior) : a) Body : A 216 Gr. WCB/ A234 Gr. WPB b) Bonnet (Bolted) : A 216 Gr. WCB/ A234 Gr. WPB c) Stem (Rising) : 13% CR. Steel (No casting) b) Wedge Disc : 13% CR. Steel (Stellited) e) Body Seat Ring : 13% CR. Steel (Stellited) f) Stem Packing (Renewable : Graphited Braided Asbestos with sacrifical with valve open on stream) inhibitor & Inconel wire reinforcement g) Hand Wheel (Rising) : Malleable Iron/ Cast Steel/ Fab. Steel h) Bonnet Bolts : ASTM A193 Gr. B7 i) Bonnet Nuts : ASTM A194 Gr. 2H j) Bonnet Gasket : Spiral Wound SS 304/316 + CA Filler k)Gear Operation Requirement : Not required.

13.

:

Refer Technical notes for Gate & Globe Valves

b) Serrated

12.

Design Standard

N.A.



ASTM A 106 Gr.B (Charpy) Sch STD for 3" & ASTM A 106 Gr.B (Charpy) Sch S40 for 4"

Hydrostatic Test Pressure a) Body b) Seat

: :

78 kg/cm 2(g) 57 kg/cm 2(g)

Test Pressure with Air

:

7.0 kg/cm 2(g)

Material Offered : : : : : : : : : :

Time 2 2 15

Notes: 1. 2. 3. 4. 5.

REV. NO.

DATE

Valve specification seet shall be read in conjunction with technical notes for valves. Valve shall be designed for intrinsically fire safe. Testing shall be as per API-598. Bidder shall clearly write all/ any deviation against each part/ material of valve in the space provided for . Wherever bidder agrees with MECON's data sheet, bidder shall clearly indicate "agreed". Paint shall be suitable for corrosive industrial environment.

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS

SECTION PROCESS & PIPING NAME DSGN

BB

DRWN

DATE

CHKD

CLIENT : DATE

REFERENCES

DRG. NO.

Hindustan Petroleum Corporation Limited

PROJECT : Bahadurgarh-Tikrikalan Pipeline Project

MECON LIMITED SCALE :

APPROVED

A.K. JOHRI DATA SHEET FOR GATE VALVES

DATA SHEET NO. MEC/23LK/05/21/M/001/DS002(GATE)

REV 0

DATA SHEET FOR GATE VALVES 1.

Valve Manufacturer

:

2.

Service

: ULHSD/ULMS

3.

Size

4.

Purchaser's Specification

:

Refer Technical notes for Gate & Globe Valves

5.

Design Pressure

:

49 kg/cm2(g)

6.

Bore

:

Reduced

7.

Corrosion Allowance

:

1.5mm

8.

End Connections

:

 Flanged both ends as per ASME B 16.5 Butt Weld both ends as per ASME B 16.25 Socket Welded ( as per ASME B 16.11) {with 100mm Pup Pieces on both sides as per ASTM A 106 Gr. B(Sch 160)} Flanged one end butt weld other end

9.

Flanges (where applicable)

: a) RF

:

(100)4"

Rating : ANSI 300#



FF

RTJ

N.A.

Smooth (125 to 200 AARH)

Pipe Specification

11.

Valve Material Specification (or Equivalent/ Superior) : a) Body : A 216 Gr. WCB/ A234 Gr. WPB b) Bonnet (Bolted) : A 216 Gr. WCB/ A234 Gr. WPB c) Stem (Rising) : 13% CR. Steel (No casting) b) Wedge Disc : 13% CR. Steel (Stellited) e) Body Seat Ring : 13% CR. Steel (Stellited) f) Stem Packing (Renewable : Graphited Braided Asbestos with sacrifical with valve open on stream) inhibitor & Inconel wire reinforcement g) Hand Wheel (Rising) : Malleable Iron/ Cast Steel/ Fab. Steel h) Bonnet Bolts : ASTM A193 Gr. B7 i) Bonnet Nuts : ASTM A194 Gr. 2H j) Bonnet Gasket : Spiral Wound SS 304/316 + CA Filler k)Gear Operation Requirement : Not required.

13.

API-602

Full

10.

12.

:

:

Design Temperature : 0oC to +65°C 

b) Serrated

Design Standard



N.A.

NA

Hydrostatic Test Pressure a) Body b) Seat

: :

78 kg/cm 2(g) 57 kg/cm 2(g)

Test Pressure with Air

:

7.0 kg/cm 2(g)

Material Offered : : : : : : : : : :

Time 2 2 15

Notes: 1. 2. 3. 4. 5.

REV. NO.

DATE

Valve specification seet shall be read in conjunction with technical notes for valves. Valve shall be designed for intrinsically fire safe. Testing shall be as per API-598. Bidder shall clearly write all/ any deviation against each part/ material of valve in the space provided for . Wherever bidder agrees with MECON's data sheet, bidder shall clearly indicate "agreed". Paint shall be suitable for corrosive industrial environment.

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS

SECTION PROCESS & PIPING NAME DSGN

BB

DRWN

DATE

CHKD

CLIENT : DATE

REFERENCES

DRG. NO.

Hindustan Petroleum Corporation Limited

PROJECT : Bahadurgarh-Tikrikalan Pipeline Project

MECON LIMITED SCALE :

APPROVED

A.K. JOHRI DATA SHEET FOR GATE VALVES

DATA SHEET NO. MEC/23LK/05/21/M/001/DS003(GATE)

REV 0

DATA SHEET FOR GLOBE VALVES 1.

Valve Manufacturer

:

2.

Size

: (50)2", (100)4"

3.

Purchaser's Specification

:

Refer Technical notes for Gate & Globe Valves

4.

Design Pressure

:

19 kg/cm2(g)

5

Corrosion Allowance

:

1.5mm

6

End Connections

:

Flanged both ends as per ASME B 16.5 Butt Weld both ends as per ASME 16.25 Flanged one end butt weld other end

7

Flanges (where applicable)

: a) RF

Rating : ANSI 150#



FF

RTJ



Stem Extension Requirement

:

Yes

9

Pipe Specification

:

N.A

10

Valve Material Specification (or Equivalent/ Superior) : a) Body : A 216 Gr. WCB/ A234 Gr. WPB b) Bonnet (Bolted) : A 216 Gr. WCB/ A234 Gr. WPB c) Stem (Rising) : 13% Cr Steel(No Casting) b) Disc(Loose Plug/Ball Type) : A 216 Gr. WCB+13% Cr Steel(facing) /13% Cr Steel e) Body Seat Ring : A 216 Gr. WCB+13% Cr Steel(facing) /13% Cr Steel f) Stem Packing (Renewable : Graphited Braided Asbestos with sacrifical with valve open on stream) inhibitor & Inconel wire reinforcement g) Hand Wheel (Rising) : Malleable Iron/ Cast Steel/ Fab. Steel h) Bonnet Bolts : ASTM A193 Gr.B7 i) Bonnet Nuts : ASTM A194 Gr. 2H j) Bonnet Gasket : Spiral Wound SS 304 + CA Filler Hydrostatic Test Pressure a) Body b) Seat

: :

32 kg/cm2(g) 23 kg/cm2(g)

12

Test Pressure with Air

:

7.0 kg/cm (g)

13

Schedule of Quantity Valve Size, NB

Notes: 1. 2. 3. 4. 5. 6.



Smooth (125 to 200 AARH) No

ULHSD/ULMS

NA

8

2", 4"

: 0oC to + 65°C

Design Temperature

Service :

b) Serrated

11

Design Standard : BS:1873



NA

Length of Stem Extension, mm : N.A

Material Offered

: : : : : : : :

2

: Quantity (Nos.) As per SOR

Valve specification seet shall be read in conjunction with technical notes for valves. Valve shall be designed for intrinsically fire safe. Testing shall be as per API-598. Bidder shall clearly write all/ any deviation against each part/ material of valve in the space provided for . Wherever bidder agrees with MECON's data sheet, bidder shall clearly indicate "agreed". Paint shall be suitable for corrosive industrial environment. Charpy V- notch test for body, ball, gland, stem & studs/ nuts will be conducted as per relevant material code i.e; at 0°C on three samples having average value of 27J and minimum value shall be 22J.

Painting Specifications: 1 Surface preparation by Short Blasting as per grade SA 2 1/2, Swedish Standard SIS-055 909. 2 Three coats of paint shall be applied with minimum thickness of 300 micron. (Permissible thickness in each coat shall be within 80 to 120 micron.) REV. NO.

DATE

ZONE

DESCRIPTIONS

BY

APPRD REFERENCES

SECTION PROCESS & PIPING NAME

DATE

CHKD

CLIENT :

Corporation Limited

DATE

PROJECT : DSGN

BB

DRG. NO.

Hindustan Petroleum Bahadurgarh-Tikrikalan Pipeline Project

MECON LIMITED

DRWN SCALE :

APPROVED

A.K. JOHRI DATA SHEET FOR GLOBE VALVES

DATA SHEET NO. MEC/23LK/05/21/M/001/DS/GV001

REV 0

DATA SHEET FOR GLOBE VALVES 1.

Valve Manufacturer

:

2.

Size

: (25)1"

3.

Purchaser's Specification

:

Refer Technical notes for Gate & Globe Valves

4.

Design Pressure

:

-----

5

Corrosion Allowance

:

1.5mm

6

End Connections

:

Flanged both ends as per ASME B 16.5 Butt Weld both ends as per ASME 16.25 Flanged one end butt weld other end

7

Flanges (where applicable)

: a) RF

Rating : ANSI 800#

Design Standard : BS:5352



Service :

FF

b) Serrated

RTJ



Stem Extension Requirement :

Yes

9

Pipe Specification

N.A

10

Valve Material Specification (or Equivalent/ Superior) : a) Body : ASTM A 351 Gr. CF8 b) Bonnet (Bolted) : ASTM A 351 Gr. CF8 c) Stem (Rising) : SS 304(No Casting) b) Disc(Loose Plug/Ball Type) : ASTM A 351 Gr. CF8+ SS 304(facing) e) Body Seat Ring : ASTM A 351 Gr. CF8+ SS 304(facing) f) Stem Packing (Renewable : Graphited Braided Asbestos with sacrifical with valve open on stream) inhibitor & Inconel wire reinforcement g) Hand Wheel (Rising) : Malleable Iron/ Cast Steel/ Fab. Steel h) Bonnet Bolts : ASTM A193 Gr.B7 i) Bonnet Nuts : ASTM A194 Gr. 2H j) Bonnet Gasket : Spiral Wound SS 304 + CA Filler

11

Hydrostatic Test Pressure a) Body b) Seat

: :

32 kg/cm2(g) 23 kg/cm2(g)

12

Test Pressure with Air

:

7.0 kg/cm2(g)

13

Schedule of Quantity Valve Size, NB 1"

Notes: 1. 2. 3. 4. 5. 6.



Smooth (125 to 200 AARH) No

ULHSD/ULMS

NA

8

:

: 0oC to + 65°C

Design Temperature



NA

Length of Stem Extension, mm : N.A

Material Offered

: : : : : : : :

: Quantity (Nos.) As per SOR

Valve specification seet shall be read in conjunction with technical notes for valves. Valve shall be designed for intrinsically fire safe. Testing shall be as per API-598. Bidder shall clearly write all/ any deviation against each part/ material of valve in the space provided for . Wherever bidder agrees with MECON's data sheet, bidder shall clearly indicate "agreed". Paint shall be suitable for corrosive industrial environment. Charpy V- notch test for body, ball, gland, stem & studs/ nuts will be conducted as per relevant material code

Painting Specifications: 1 Surface preparation by Short Blasting as per grade SA 2 1/2, Swedish Standard SIS-055 909. 2 Three coats of paint shall be applied with minimum thickness of 300 micron. (Permissible thickness in each coat shall be within 80 to 120 micron.) REV. NO.

DATE

ZONE

DESCRIPTIONS

BY

APPRD REFERENCES

SECTION PROCESS & PIPING NAME

DATE

CHKD

CLIENT :

Corporation Limited

DATE

PROJECT : DSGN

BB

DRG. NO.

Hindustan Petroleum Bahadurgarh-Tikrikalan Pipeline Project

MECON LIMITED

DRWN SCALE :

APPROVED

A.K. JOHRI DATA SHEET FOR GLOBE VALVES

DATA SHEET NO. MEC/23LK/05/21/M/001/DS/GV002

REV 0

DATA SHEET FOR GLOBE VALVES 1.

Valve Manufacturer

:

2.

Size

: 2"

3.

Purchaser's Specification

:

Refer Technical notes for Gate & Globe Valves

4.

Design Pressure

:

49 kg/cm2(g)

5

Corrosion Allowance

:

1.5mm

6

End Connections

:

Flanged both ends as per ASME B 16.5 Butt Weld both ends as per ASME 16.25 Flanged one end butt weld other end

7

Flanges (where applicable)

Rating : ANSI 300#

Design Standard : BS:1873

Design Temperature

Service :

: a) RF

FF

b) Serrated

RTJ

9

Pipe Specification

10

Valve Material Specification (or Equivalent/ Superior) : a) Body : A 216 Gr. WCB/ A234 Gr. WPB b) Bonnet (Bolted) : A 216 Gr. WCB/ A234 Gr. WPB c) Stem (Rising) : 13% Cr Steel(No Casting) b) Disc(Loose Plug/Ball Type) : A 216 Gr. WCB+13% Cr Steel(facing) /13% Cr Steel e) Body Seat Ring : A 216 Gr. WCB+13% Cr Steel(facing) /13% Cr Steel f) Stem Packing (Renewable : Graphited Braided Asbestos with sacrifical with valve open on stream) inhibitor & Inconel wire reinforcement g) Hand Wheel (Rising) : Malleable Iron/ Cast Steel/ Fab. Steel h) Bonnet Bolts : ASTM A193 Gr.B7 i) Bonnet Nuts : ASTM A194 Gr. 2H j) Bonnet Gasket : Spiral Wound SS 304 + CA Filler

11

:

: :

78 kg/cm2(g) 57 kg/cm2(g)

12

Test Pressure with Air

:

7.0 kg/cm (g)

13

Schedule of Quantity Valve Size, NB

Notes: 1. 2. 3. 4. 5. 6.

Yes



No

NA



Length of Stem Extension, mm : N.A

ASTM A 106 Gr.B(Charpy) Sch XS

Hydrostatic Test Pressure a) Body b) Seat

2"



Smooth (125 to 200 AARH)

Stem Extension Requirement

ULHSD/ULMS



NA

8

:

: 0oC to + 65°C

Material Offered

: : : : : : : :

2

: Quantity (Nos.) As per SOR

Valve specification seet shall be read in conjunction with technical notes for valves. Valve shall be designed for intrinsically fire safe. Testing shall be as per API-598. Bidder shall clearly write all/ any deviation against each part/ material of valve in the space provided for . Wherever bidder agrees with MECON's data sheet, bidder shall clearly indicate "agreed". Paint shall be suitable for corrosive industrial environment. Charpy V- notch test for body, ball, gland, stem & studs/ nuts will be conducted as per relevant material code i.e; at 0°C on three samples having average value of 27J and minimum value shall be 22J.

Painting Specifications: 1 Surface preparation by Short Blasting as per grade SA 2 1/2, Swedish Standard SIS-055 909. 2 Three coats of paint shall be applied with minimum thickness of 300 micron. (Permissible thickness in each coat shall be within 80 to 120 micron.) REV. NO.

DATE

ZONE

DESCRIPTIONS

BY

APPRD REFERENCES

SECTION PROCESS & PIPING NAME

DATE

CHKD

CLIENT :

Corporation Limited

DATE

PROJECT : DSGN

BB

DRG. NO.

Hindustan Petroleum Bahadurgarh-Tikrikalan Pipeline Project

MECON LIMITED

DRWN SCALE :

APPROVED

A.K. JOHRI DATA SHEET FOR GLOBE VALVES

DATA SHEET NO. MEC/23LK/05/21/M/001/DS/GV003

REV 0

DATA SHEET FOR GLOBE VALVES 1.

Valve Manufacturer

:

2.

Size

: 100(4")

3.

Purchaser's Specification

:

Refer Technical notes for Gate & Globe Valves

4.

Design Pressure

:

49 kg/cm2(g)

5

Corrosion Allowance

:

1.5mm

6

End Connections

:

Flanged both ends as per ASME B 16.5 Butt Weld both ends as per ASME 16.25 Flanged one end butt weld other end

7

Flanges (where applicable)

: a) RF

Rating : ANSI 300#

Design Standard : BS:1873

Service :



FF

b) Serrated

RTJ

Stem Extension Requirement

9

Pipe Specification

10

Valve Material Specification (or Equivalent/ Superior) : a) Body : A 216 Gr. WCB/ A234 Gr. WPB b) Bonnet (Bolted) : A 216 Gr. WCB/ A234 Gr. WPB c) Stem (Rising) : 13% Cr Steel(No Casting) b) Disc(Loose Plug/Ball Type) : A 216 Gr. WCB+13% Cr Steel(facing) /13% Cr Steel e) Body Seat Ring : A 216 Gr. WCB+13% Cr Steel(facing) /13% Cr Steel f) Stem Packing (Renewable : Graphited Braided Asbestos with sacrifical with valve open on stream) inhibitor & Inconel wire reinforcement g) Hand Wheel (Rising) : Malleable Iron/ Cast Steel/ Fab. Steel h) Bonnet Bolts : ASTM A193 Gr.B7 i) Bonnet Nuts : ASTM A194 Gr. 2H j) Bonnet Gasket : Spiral Wound SS 304 + CA Filler

11

: :

78 kg/cm2(g) 57 kg/cm2(g)

12

Test Pressure with Air

:

7.0 kg/cm (g)

13

Schedule of Quantity Valve Size, NB

Notes: 1. 2. 3. 4. 5. 6.

Yes





No

NA Length of Stem Extension, mm : N.A

ASTM A 106 Gr.B(Charpy) Sch XS

Hydrostatic Test Pressure a) Body b) Seat

4"



Smooth (125 to 200 AARH) :

ULHSD/ULMS

NA

8

:

: 0oC to + 65°C

Design Temperature

Material Offered

: : : : : : : :

2

: Quantity (Nos.) As per SOR

Valve specification seet shall be read in conjunction with technical notes for valves. Valve shall be designed for intrinsically fire safe. Testing shall be as per API-598. Bidder shall clearly write all/ any deviation against each part/ material of valve in the space provided for . Wherever bidder agrees with MECON's data sheet, bidder shall clearly indicate "agreed". Paint shall be suitable for corrosive industrial environment. Charpy V- notch test for body, ball, gland, stem & studs/ nuts will be conducted as per relevant material code i.e; at 0°C on three samples having average value of 27J and minimum value shall be 22J.

Painting Specifications: 1 Surface preparation by Short Blasting as per grade SA 2 1/2, Swedish Standard SIS-055 909. 2 Three coats of paint shall be applied with minimum thickness of 300 micron. (Permissible thickness in each coat shall be within 80 to 120 micron.) REV. NO.

DATE

ZONE

DESCRIPTIONS

BY

APPRD REFERENCES

SECTION PROCESS & PIPING NAME

DATE

CHKD

CLIENT :

Corporation Limited

DATE

PROJECT : DSGN

BB

DRG. NO.

Hindustan Petroleum Bahadurgarh-Tikrikalan Pipeline Project

MECON LIMITED

DRWN SCALE :

APPROVED

A.K. JOHRI DATA SHEET FOR GLOBE VALVES

DATA SHEET NO. MEC/23LK/05/21/M/001/DS/GV004

REV 0

DATA SHEET FOR INSULATING JOINTS

A = OVERALL LENGTH OF IJ TO BE CONFIRMED BY MANUFACTURER.

REV. NO.

1.

INSULATING JOINTS MFR.

:

2.

PURCHASER'S SPECIFICATION NO.

: MEC/TS/05/21/009

3.

RATING

: 300#

4.

DESIGN PRESSURE

: 49 Kg/cm 2

5.

DESIGN TEMPERATURE

: 0°C to 65°C

6.

SERVICE

: ULHSD/ULMS/SKO

7.

CORROSION ALLOWANCE

: 1.5 MM

8.

SIZE NB MM (INCHES)

: 250(10")

9.

END CONNECTION

: BUTT-WELD AT BOTH ENDS

10.

DESIGN CODE

: ASME SECTION-VIII DIV-I

11.

DESIGN FACTOR

: 0.5

12.

HYDROSTATIC TEST PRESSURE

: 73.5 Kg/cm 2

13.

CHARPY TEST(BODY, WELDING ENDS)

: REQUIRED AS PER SPEC.

14.

HARDNESS TEST

: REQUIRED AS PER SPEC.

15.

MATERIALS SPECIFICATION (EQUIVALENT OR SUPERIOR) A) BODY B) PUPS C) INSULATING MATERIAL

: ASTM A 105 : API 5L GR. B, 7.1 mm THK.(MIN.) : AS PER MANUFACTURER'S STANDARD

16.

CONNECTING PIPE SPECIFICATION SIZE, NB, MM (INCHES) 250 (10") WALL THICKNESS, MM(MIN.) 7.1 GRADE API 5L Gr. B

17.

SPECIAL REQUIREMENTS

: INSULATION JOINT SHALL BE SUITABLE FOR ABOVE GROUND INSTALLATION

18.

QUANTITY

: 2 NOS.

DATE

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS

SECTION OIL & GAS NAME DSGN DRWN

DATE

CLIENT : CHKD

REFERENCES

MECON LIMITED

Corporation Limited

DATE

PROJECT :

DRG. NO.

Hindustan Petroleum Bahadurgarh Tikrikalan Pipeline Project SCALE :

APPROVED

DATA SHEET FOR INSULATING JOINTS

DATA SHEET NO.: MEC/23LK/05/21/M/000/DS-009-01

REV 0

DATA SHEET FOR INSULATING JOINTS

A = OVERALL LENGTH OF IJ TO BE CONFIRMED BY MANUFACTURER.

REV. NO.

1.

INSULATING JOINTS MFR.

:

2.

PURCHASER'S SPECIFICATION NO.

: MEC/TS/05/21/009

3.

RATING

: 300#

4.

DESIGN PRESSURE

: 49 Kg/cm 2

5.

DESIGN TEMPERATURE

: 0°C to 65°C

6.

SERVICE

: ULHSD/ULMS/SKO

7.

CORROSION ALLOWANCE

: 1.5 MM

8.

SIZE NB MM (INCHES)

: 200 (8")

9.

END CONNECTION

: BUTT-WELD AT BOTH ENDS

10.

DESIGN CODE

: ASME SECTION-VIII DIV-I

11.

DESIGN FACTOR

: 0.5

12.

HYDROSTATIC TEST PRESSURE

: 73.5 Kg/cm 2

13.

CHARPY TEST(BODY, WELDING ENDS)

: REQUIRED AS PER SPEC.

14.

HARDNESS TEST

: REQUIRED AS PER SPEC.

15.

MATERIALS SPECIFICATION (EQUIVALENT OR SUPERIOR) A) BODY B) PUPS C) INSULATING MATERIAL

: ASTM A 105 : API 5L GR. B, 7.1 mm THK.(MIN.) : AS PER MANUFACTURER'S STANDARD

16.

CONNECTING PIPE SPECIFICATION SIZE, NB, MM (INCHES) 200 (8") WALL THICKNESS, MM(MIN.) 7.1 GRADE API 5L Gr. B

17.

SPECIAL REQUIREMENTS

: INSULATION JOINT SHALL BE SUITABLE FOR ABOVE GROUND INSTALLATION

18.

QUANTITY

: 2 NOS.

DATE

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS

SECTION OIL & GAS NAME DSGN DRWN

DATE

CLIENT : CHKD

REFERENCES

MECON LIMITED

Corporation Limited

DATE

PROJECT :

DRG. NO.

Hindustan Petroleum Bahadurgarh Tikrikalan Pipeline Project SCALE :

APPROVED

DATA SHEET FOR INSULATING JOINTS

DATA SHEET NO.: MEC/23LK/05/21/M/000/DS-009-02

REV 0

DATA SHEET FOR FLOW TEES

DESIGN DATA 1.

FLOW TEE MFR.

2.

PURCHASER'S SPECIFICATION NO. : MEC/TS/05/21/011

3.

RATING

: 300#

4.

DESIGN PRESSURE

: 49 BAR(G)

5.

DESIGN TEMPERATURE

:0°C to 65°C

6.

SERVICE

: ULHSSD / SKO / ULMS

7.

CORROSION ALLOWANCE

: 1.5 MM

8.

SIZE NB MM(INCHES)

: 250 X 250 X 250 (10" X 10" X 10")

9.

END CONNECTION

: BUTT-WELD AT BOTH ENDS

10.

DESIGN CODE

: ASME B31.8

11.

DESIGN FACTOR

: 0.5

12.

HYDROSTATIC TEST PRESSURE

: 73.5 BAR(G)

13.

CHARPY TEST(TEES, END PIECES)

: REQUIRED AS PER SPEC.

14.

HARDNESS TEST

: REQUIRED AS PER SPEC.

15

SUITABILITY OF FLOW TEE

: FOR PIGS AND SPHERES

16

FLOW DIRECTION

: BI - DIRECTIONAL

17

MATERIALS SPECIFICATION (EQUIVALENT OR SUPERIOR) 1) TEE 2) END PIECES 3) INTERNAL SLEEVE

18

: MSS - SP - 75 Gr. WPHY 42 : ASTM A - 694 F - 42 : API 5L Gr. B

CONNECTING PIPE SPECIFICATION TAG NO. RUN PIPE DETAILS SL. NO. D1 T1 THK.(Min.) MATERIALS

1

NOTE:

:

NB (INCH)

(MM)

10

7.1

-

D2 NB (INCH)

API 5L Gr. B

BRANCH PIPE DETAILS T2 THK.(Min.) MATERIALS

10

(MM)

7.1

API 5L Gr. B

19

SPECIAL REQUIREMENTS

1 2

MANUFACTURE TO INDICATE DIMENSIONS MARKED A & B IN THE SKETCH ABOVE. MANUFACTURER TO FURNISH DETAILS OF THE HOLES IN INTERNAL SLEEVE. THE AREA OF THE HOLES SHALL BE MINIMUM EQUAL TO THE INTERNAL AREA OF THE BRANCH PIPE. RELEVENT CALCULATIONS TO THIS EXTENT SHALL BE FURNISHED. THE WALL THICKNESS OF ALL PARTS OF FLOW TEE SHALL MATCH WITH THE THICKNESS OF THE RUN PIPE & BRANCH PIPE AS INDICATED ABOVE.

3 REV. NO.

BY

NAME

DATE

CLIENT : CHKD

DATE

DRWN

APPROVED d:\BNPL\FTData Sheet - Flow Tee -10 x 10-300#

02

APPRD

REVISIONS

DSGN

Nos.

: FLOW TEE SHALL BE SUITABLE FOR UNDER GROUND INSTALLATION

DESCRIPTIONS

SECTION OIL & GAS

Qty.

REFERENCES

DRG. NO.

HINDUSTAN PETROLEUM

MECON LIMITED

CORPORATION LIMITED PROJECT : BAHADURGARH TEKRIKALAN PIPELINE PROJECT

DATA SHEET FOR FLOW TEES

SCALE :

NTS

DATA SHEET NO.: MEC/ 23LK/05/21/M/000/DS-011-1

REV 0

DATA SHEET FOR FLOW TEES

DESIGN DATA 1.

FLOW TEE MFR.

2.

PURCHASER'S SPECIFICATION NO. : MEC/TS/05/21/011

3.

RATING

: 300#

4.

DESIGN PRESSURE

: 49 BAR(G)

5.

DESIGN TEMPERATURE

:0°C to 65°C

6.

SERVICE

: ULHSSD / SKO / ULMS

7.

CORROSION ALLOWANCE

: 1.5 MM

8.

SIZE NB MM(INCHES)

: 200 X 200 X 200 (8" X 8" X 8")

9.

END CONNECTION

: BUTT-WELD AT BOTH ENDS

10.

DESIGN CODE

: ASME B31.8

11.

DESIGN FACTOR

: 0.5

12.

HYDROSTATIC TEST PRESSURE

: 73.5 BAR(G)

13.

CHARPY TEST(TEES, END PIECES)

: REQUIRED AS PER SPEC.

14.

HARDNESS TEST

: REQUIRED AS PER SPEC.

15

SUITABILITY OF FLOW TEE

: FOR PIGS AND SPHERES

16

FLOW DIRECTION

: BI - DIRECTIONAL

17

MATERIALS SPECIFICATION (EQUIVALENT OR SUPERIOR) 1) TEE 2) END PIECES 3) INTERNAL SLEEVE

18

: MSS - SP - 75 Gr. WPHY 42 : ASTM A - 694 F - 42 : API 5L Gr. B

CONNECTING PIPE SPECIFICATION TAG NO. RUN PIPE DETAILS SL. NO. D1 T1 THK.(Min.) MATERIALS

1

NOTE:

:

NB (INCH)

(MM)

8

7.1

-

D2 NB (INCH)

API 5L Gr. B

BRANCH PIPE DETAILS T2 THK.(Min.) MATERIALS

8

(MM)

7.1

API 5L Gr. B

19

SPECIAL REQUIREMENTS

1 2

MANUFACTURE TO INDICATE DIMENSIONS MARKED A & B IN THE SKETCH ABOVE. MANUFACTURER TO FURNISH DETAILS OF THE HOLES IN INTERNAL SLEEVE. THE AREA OF THE HOLES SHALL BE MINIMUM EQUAL TO THE INTERNAL AREA OF THE BRANCH PIPE. RELEVENT CALCULATIONS TO THIS EXTENT SHALL BE FURNISHED. THE WALL THICKNESS OF ALL PARTS OF FLOW TEE SHALL MATCH WITH THE THICKNESS OF THE RUN PIPE & BRANCH PIPE AS INDICATED ABOVE.

3 REV. NO.

BY

NAME

DATE

CLIENT : CHKD

DATE

DRWN

APPROVED d:\BNPL\FTData Sheet - Flow Tee -8 x 8-300#

02

APPRD

REVISIONS

DSGN

Nos.

: FLOW TEE SHALL BE SUITABLE FOR UNDER GROUND INSTALLATION

DESCRIPTIONS

SECTION OIL & GAS

Qty.

REFERENCES

DRG. NO.

HINDUSTAN PETROLEUM

MECON LIMITED

CORPORATION LIMITED PROJECT : BAHADURGARH TEKRIKALAN PIPELINE PROJECT

DATA SHEET FOR FLOW TEES

SCALE :

NTS

DATA SHEET NO.: MEC/ 23LK/05/21/M/000/DS-011-2

REV 0

DATA SHEET FOR SUMP TANK 1

Tag No.

: T-0201, T-0401, T-0701 & T-0702

2

Quantity

: 4 Nos.

3

Fluid

: ULMS/ ULSHSD/ SKO/ SLOP

4

Working Pressure

: Atmospheric

5

Design Pressure

: Full of water + 150 mm WC

6

Working Temperature, °C

: Ambient

7

Design Temperature, °C

: 65°C

8

Corrosion Allowance, mm

: 3.0

9

Radiography

: 100%

10

Sp. Gr. of fluid handled

: 0.72 - 0.87

11

Storage Capacity, m3

: 18

12

Earthquake Specification

: IS:1893

13

Design Code

: ASME SEC-VIII Div. 1

14

Weight (Empty), kg

:

15

Weight (Water filled), kg

:

16

Material of construction i) Shell, Dished End, Sump, Pump Nozzle, Manhole Nozzle with Cover ii) LT, UC, Vent, Feed Inlet Nozzle iii) Companion/ Blind Flanges iv) Bolts & Nuts

: SA 106 Gr. B : A 105 : A 193.B7/ A197.2H

Internal Epoxy coating compatible with ULMS/ ULSHSD/ SKO/ SLOP

17

Painting

18

Code of Practice for Design, Fabrication and Installation

19

Vendor's Name  Vendor to specify

Note: 1) 2) 3) 4) 5) 6) 7)

REV. NO.

: SA 516 Gr. 60

DATE

: API 650/ - IS 10987 : 1992 (Reaffirmed 2003) :

When submitting the offer, bidder to submit assembly drawing with overall dimensions and list of materials to be used. Proper stiffner rings shall be provided. For GAD of Sump Tank, refer drg. No.: MEC/23LK/05/21/M/000/VS-001, Rev-0 For Technical Specification, refer document no.: MEC/TS/05/21/021A, Rev-0 This tank shall be fitted with Vertical Sump Pump. Pump nozzle size sahll be provided by Sum Pump vendor. This tank shall be installed underground. Outer surface of shell shall be protected from corrosion by providing suitable coating/ painting.

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS

SECTION Oil & Gas NAME

REFERENCES

DRG. NO.

CLIENT : HINDUSTAN PETROLEUM CORP. LTD. DATE

CHKD

DATE

DSGN DRWN

APPROVED

d:\fateh\narimanam-kuthalam\tender rfq\condensate tank\DS-Sump Tank

PROJECT :BAHADURGARH TIKARIKALAN PIPELINE PROJECT SUMP TANK TAG NO. : T-0201, T-0401,T-0701 & T-0702

MECON LIMITED SCALE : DATA SHEET NO. : MEC/DS/05/21/23LK/ST/01

REV 0

DATA SHEET FOR VERTICAL SUBMERSIBLE PUMPS FOR SUMP TANK JOB NO. AREA CLASS DESIGN CODE APPLICATION

23LK FLAME PROOF API 610, 6 th Edition TO PUMP OUT ULMS/ SLOP FROM SUMPTANK

OPERATING CONDITIONS: LIQUID HANDLED CAPACITY (NORMAL)KLPH CAPACITY (MAXIMUM)KLPH SUCTION HEAD MLC DISCHARGE HEAD MLC TOTAL DIFF HEAD MLC PUMPING TEMP. (P.T.) (°C)/ MAXIMUM TEMPERATURE NPSH AVAILABLE MLC VAP. PR AT P.T. KG/CM2 a VISCOSITY AT P.T. CST SPECIFIC GRAVITY CORROSIVITY SUSPENDED SOLIDS INLET PR. MIN/MAX MOUNTING ARRANGEMENT DEPTH OF TANK (M) MINIMM SUBMERGENCE

TWO P-0402, P-0702

PERFORMANCE DATA(BY MANF.): NPSH REQUIRED NO. OF STAGES R.P.M. SPECIFIC SPEED EFFICIENCY AT DUTY POINT MAX. BHP ABSORBED BHP ABSORBED AT DUTY PT.

ULMS/ / SLOP 18 30 FLOODED 35 35 20 / 45 FLOODED (NOTE-4) 0.7 0.5 - 0.7 0.72 - 0.775 NIL NIL

SHUT OFF HEAD DIRECTION OF ROTATION FACING DRIVER END WATER COOLING REQD. FOR JACKETING REQD. FOR FLUSHING REQD. FOR NAME OF MANUFACTURER PUMP MODEL NO. TEST CURVE NO. PUMP SECTIONAL DRG. NO MECHANICAL SEAL DRG. NO

N/A

CLOSED/

INSPECTION AND TESTING : SHOP TEST : REQUIRED AND WITNESSED PERFORMANCE TEST HYDROSTATIC TEST PR. MAX. ALLOWABLE CASING PR.

YES YES AS PER STANDARD AS PER STANDARD

FLEXIBLE SPACER

MATERIALS OF CONSTRUCTION

S 5(as per API 610)

CASING : IMPELLER: SHAFT : SHAFT SLEEVE WEAR RINGS : BEARING ENCLOSURE :

ASTM A216 GR WCB ASTM A216 GR WCB ASTM A322 TP4140 ASTM A743 GRCA15H ASTM A743 GRCA15H ASTM A216 GR. WCB

OVER TANK NOZZLE REFER TANK DRG. NO. MEC/23LK/05/21/M /000/VS-001 Rev-0

CONSTRUCTION DETAILS TYPE : HORZ/HORZ SPLIT/ VERT/VERT SPLIT/SINGLE OR DOUBLE VOLUTE IMPELLER : TYPE AND DIA COUPLING : TYPE AND RATING BEARING NO : DRIVER END/ANTIFRICTION DRIVEN END/ ANTIFRICTION BEARING LUBRICANT MECHANICAL SEAL: MODEL AND MAKE DISCHARGE NOZ.SIZE/ RATING SUCTION POSN.

NUMBER REQD TAG NUMBERS PUMP VENDOR

RADIAL SPLIT SINGLE

N/A / 150# SUBMERGED

DRIVE MOTOR DETAILS :

ACCESORIES REQUIRED:

SUPPLIED BY TYPE INSULATION

APPROVED VENDOR SQUIRREL CAGE & FLP CLASS F (TEMP. RISE LIMITED TO CLASS-B)

MOTOR HP DUTY LOCATION

INTERMITTENT INSIDE U/G TANK, T-0401, T-0702

MOUNTING PLATE FOUNDATION BOLTS FLEXIBLE COUPLING

YES N/A YES

COUPLING GUARD V-BELT AND PULLEY BELT GUARD COMPANION FLANGES& GSKT BOLTS AND NUTS FOR GSKTS

N/A NOT REQUIRED NOT REQUIRED YES, SORF 150# YES

Tank Details are given in the enclosed sketch no. MEC/23LK/05/21/M/000/VS-001, R-0

Note: 1) 2) 3) 4)

REV. NO.

When submitting the offer, bidder to submit assembly drawing with overall dimensions and list of materials to be used. Pump/ Motor shall be supplied with interlock, flame proof cables, Push Button, Starter, Canopy suitable for Outdoor Installation. Vendor to furnish remaining unfilled data alongwith motor HP calculation. Pump vendor to indicate sump area.

DATE

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS

SECTION PROCESS & PIPING NAME

DATE

CHKD

DSGN DRWN

APPROVED

d:\fateh\feeder line\tender rfq\condensate tank\DS - VSP_ms

REFERENCES

DRG. NO.

CLIENT : HINDUSTAN PETROLEUM CORP.LTD.

Maeka$Na ilim4eD

DATE

PROJECT : BAHADURGARH -TIKARIKALAN PIPELINE PROJECT VERTICAL SUBMERSIBLE PUMP TAG NO. P-0402, P-0702

MECON LIMITED SCALE : DATA SHEET NO. : MEC/DS/05/21/23LK/VSP/001

REV 0

DATA SHEET FOR VERTICAL SUBMERSIBLE PUMPS FOR SUMP TANK JOB NO. AREA CLASS DESIGN CODE APPLICATION

23LK FLAME PROOF API 610, 6 th Edition TO PUMP OUT ULSHSD/ SKO/ SLOP FROM SUMPTANK

OPERATING CONDITIONS: LIQUID HANDLED CAPACITY (NORMAL)KLPH CAPACITY (MAXIMUM)KLPH SUCTION HEAD MLC DISCHARGE HEAD MLC TOTAL DIFF HEAD MLC PUMPING TEMP. (P.T.) (°C)/ MAXIMUM TEMPERATURE NPSH AVAILABLE MLC VAP. PR AT P.T. KG/CM2 a VISCOSITY AT P.T. CST SPECIFIC GRAVITY CORROSIVITY SUSPENDED SOLIDS INLET PR. MIN/MAX MOUNTING ARRANGEMENT DEPTH OF TANK (M) MINIMM SUBMERGENCE

ULMS/ ULSHSD/SKO/ SLOP 18 30 FLOODED 35 35 20 / 45 FLOODED (NOTE-4) 0.1 - 0.3 8 0.775 - 0.87 NIL NIL

TWO P-0202, P-0701

PERFORMANCE DATA(BY MANF.): NPSH REQUIRED NO. OF STAGES R.P.M. SPECIFIC SPEED EFFICIENCY AT DUTY POINT MAX. BHP ABSORBED BHP ABSORBED AT DUTY PT. SHUT OFF HEAD DIRECTION OF ROTATION FACING DRIVER END WATER COOLING REQD. FOR JACKETING REQD. FOR FLUSHING REQD. FOR NAME OF MANUFACTURER PUMP MODEL NO. TEST CURVE NO. PUMP SECTIONAL DRG. NO MECHANICAL SEAL DRG. NO

N/A

CLOSED/

INSPECTION AND TESTING : SHOP TEST : REQUIRED AND WITNESSED PERFORMANCE TEST HYDROSTATIC TEST PR. MAX. ALLOWABLE CASING PR.

YES YES AS PER STANDARD AS PER STANDARD

FLEXIBLE SPACER

MATERIALS OF CONSTRUCTION

S 5(as per API 610)

CASING : IMPELLER: SHAFT : SHAFT SLEEVE WEAR RINGS : BEARING ENCLOSURE :

ASTM A216 GR WCB ASTM A216 GR WCB ASTM A322 TP4140 ASTM A743 GRCA15H ASTM A743 GRCA15H ASTM A216 GR. WCB

OVER TANK NOZZLE REFER TANK DRG. NO. MEC/23LK/05/21/M /000/VS-001 Rev-0

CONSTRUCTION DETAILS TYPE : HORZ/HORZ SPLIT/ VERT/VERT SPLIT/SINGLE OR DOUBLE VOLUTE IMPELLER : TYPE AND DIA COUPLING : TYPE AND RATING BEARING NO : DRIVER END/ANTIFRICTION DRIVEN END/ ANTIFRICTION BEARING LUBRICANT MECHANICAL SEAL: MODEL AND MAKE DISCHARGE NOZ.SIZE/ RATING SUCTION POSN.

NUMBER REQD TAG NUMBERS PUMP VENDOR

RADIAL SPLIT SINGLE

N/A / 150# SUBMERGED

DRIVE MOTOR DETAILS :

ACCESORIES REQUIRED:

SUPPLIED BY TYPE INSULATION

APPROVED VENDOR SQUIRREL CAGE & FLP CLASS F (TEMP. RISE LIMITED TO CLASS-B)

MOTOR HP DUTY LOCATION

INTERMITTENT INSIDE U/G TANK, T-0201, T-0701

MOUNTING PLATE FOUNDATION BOLTS FLEXIBLE COUPLING

YES N/A YES

COUPLING GUARD V-BELT AND PULLEY BELT GUARD COMPANION FLANGES& GSKT BOLTS AND NUTS FOR GSKTS

N/A NOT REQUIRED NOT REQUIRED YES, SORF 150# YES

Tank Details are given in the enclosed sketch no. MEC/23LK/05/21/M/000/VS-001, R-0

Note: 1) 2) 3) 4)

REV. NO.

When submitting the offer, bidder to submit assembly drawing with overall dimensions and list of materials to be used. Pump/ Motor shall be supplied with interlock, flame proof cables, Push Button, Starter, Canopy suitable for Outdoor Installation. Vendor to furnish remaining unfilled data alongwith motor HP calculation. Pump vendor to indicate sump area.

DATE

ZONE

DESCRIPTIONS

BY

APPRD

REVISIONS

SECTION PROCESS & PIPING NAME

DATE

CHKD

DSGN DRWN

APPROVED

d:\fateh\feeder line\tender rfq\condensate tank\DS - VSP_ulshsd_sko

REFERENCES

DRG. NO.

CLIENT : HINDUSTAN PETROLEUM CORP.LTD.

Maeka$Na ilim4eD

DATE

PROJECT : BAHADURGARH -TIKARIKALAN PIPELINE PROJECT VERTICAL SUBMERSIBLE PUMP TAG NO. P-0202, P-0701

MECON LIMITED SCALE : DATA SHEET NO. : MEC/DS/05/21/23LK/VSP/002

REV 0

BAHADURGARH TIKARIKALAN PIPELINE PROJECT MECON LIMTIED, DELHI

CLIENT : HINDUSTAN PETROLEUM CORPORATION LIMITED Data Sheet No: MEC/23LK/05/E5/DS/IROT/01

INTELLIGENT METAL TUBE ROTAMETER Units : Flow  Liquid-M3/Hr Gas Kg/Hr, Steam Kg/Hr, Pressure  Kg/Cm2 G, Temperature  Deg C Level/ Length  mm TAG NO

FT-0301

FT-0302

2

LINE NO.

1"-C-01-0305-A1K

1"-C-01-0310-A1K

3

SERVICE

ULMS

ULHSD/ SKO

4

TYPE

1

GENERAL

INDICATE & TRANSMIT

5

FUNCTION

6

CONN. SIZE TYPE AND RATING

7

CONN. SIZE : FACING AND FINISH

RF SERR

RF SERR

8

DIRECTION : INLET / OUTLET

BOTTOM / TOP

BOTTOM / TOP

INDICATE & TRANSMIT

Flange connection & DN25

9 10 11

METER

TUBE SIZE TUBE MATL.

*

/

REQUIRED

/

FLOAT GUIDE

*

/

FLOAT MATL.

NOTE-2 / SS 316

NOTE-2 / SS 316

*

*

/

REQUIRED

12

SCALE LENGTH AND TYPE

13

SCALE GRADUATION

LPH

LPH

14

RANGE

NOTE-1

NOTE-1

15

FLOW SPAN

10:1

16

METER FACTOR

*

*

17

EMD FITTING MATL. (FLG)

SS-316

SS-316

18

PACKING OR O-RING MATL.

*

*

19

ACCURACY

+ 1%

+ 1%

20

SUPPLY POWER

12-28V DC (two-wire system) battery power

21

PROTECTION CLASS

IP 67, GR. II A & GR. II B two-wire system

22

OUTPUT

23

FROT SHIELD WITH SAFETY GLASS

REQUIRED

REQUIRED

24

JACKETING MEDIUM / CONN

-

-

25

JACKETING TEMP C / PRESSURE

-

-

26

FLANGE TO FLANGE DISTANCE

*

*

27

NEEDLE VALVE

-

-

28

FILTER REGULATOR WITH GUAGE

-

-

29

FLUID AND STATE

ULMS

ULHSD/ SKO

30

MAXIMUM FLOW

3 LPH

5 LPH

31

MINIMUM FLOW

0.4 LPH

1 LPH

32

NORMAL FLOW

33

PRESSURE OPER / MAX

- / 250 BAR

- / 250 BAR

34

TEMP OPER / MAX

35

OPER SG / MAL WT

36

MAX OPER VISCOSITY MPAS (CSt)

0.5 - 0.7

1.6 - 8

37

MAX ALLOWABLE PR DROP

MINIMUM

MINIMUM

38

MODEL NO.

*

*

OPTIONS

SERVICE CONDITIONS

39

NOTES :

TUBE NO.

/

FLOAT NO.

4 - 50 / -

4 - 50 / 0.72 - 0.775

*

/

/

-

0.7752 - 0.87

*

*

/

/

-

*

40

TAG PLATE

TO BE SCREWED ON BODY

TO BE SCREWED ON BODY

41

SPECIFICATIPON REMARKS

-

-

1

VENDOR TO SELECT RANGE TO COVER MAXIMUM AND MINIMUM FLOW RATE.

2

TOUGHENED BOROSILICATE GLASS

3

* BY VENDOR

4

AS PER INSTALLATION STD

5

VENDOR TO SUBMIT SPECIFICATIONS AND FILLED IN DATA SHEET FOR MECON's REVIEW AND APPROVAL.

0

REV.

DATE

BY

CHKD.

APPD.

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

20.0

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ANNEXURES TO PARTICULAR JOB SPECIFICATION

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 62 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ANNEXURE TO PARTICULAR JOB SPECIFICATION

CONTENTS 

Annexure-I

: Technical Input of Civil & Structural Works



Annexure-II

: Technical Input of Instrumentation Works



Annexure-III

: Technical Input of Telecom Works



Annexure-IV : Technical Input of Cathodic Protection Works



Annexure-V

: Technical Input of Fire Fighting Works

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 63 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Annexure-I to Particular Job Specification (CIVIL & STRUCTURAL WORKS)

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 64 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

1.0

CIVIL & STRUCTURAL WORKS

I)

General

MECON LIMITED

The scope of work to be performed under this contract shall include complete civil and steel structural works as per plans, equipment layout, drawings & technical specifications for the various Structures of Bahadurgarh – Tikrikalan pipeline project of M/s HPCL. The location and type of structures to be constructed at Tikrikalan & Bahadurgarh Terminal are as follows: Facilities for which structures are to be constructed at: A. Dispatch Terminal at Bahadurgarh: -

Control Room Building of Size 12x16 m. Transformer & DG set Yard of size 10x20 m. Transformer yard of size 10 x 10m MCC Room of size 8x26 m. Area for Metering, Basket Filter, DT and Booster Pumps of size 60x13 m. Booster Pump House of size 20x7 m. Mainline Pump House of size 20x7 m. RCC Box Culverts Earth filling in roads as well as construction of Roads Dismantling of Brick, RR Masonary, PCC, RCC Brick Masonary drain Pipe supports sleepers Sump Tank of size 10x7.5 m. Dosing shed of size 3 x 5m. Concrete Pavement

B. Receiving Terminal at Tikrikalan: -

Control Room of size 36x16 m. Electrical DG Room of size 12x10 m. Sump Tank of size 10x7.5 m. Area for SRVS & Control Valves of size 22x12 m. Metering Basket Filter & DT of size 44x15 m. Scrapper Area of size 23x15 m. Car Parking Shed of size 12x6 m. 30 M High Mast Pipe supports sleepers Concrete Pavement

Note: All the buildings are single storey with parapet wall having drain, Plinth protection all around.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 65 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

II)

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Scope of Supply Contractor shall procure & supply to site all the materials including cement, reinforcing steel, steel sections/plates, pipes, barbed wire, Chain link fencing, chequered plate, mesh and other accessories, other masonry materials, bitumen/asphalt, admixtures & bonding agents, sealants, kerb stones, pavior block, sand and boulder etc., and any other construction material/item required to complete the civil & structural works. All costs towards testing/inspection of materials/goods shall be borne by the Contractor. No materials/items shall be supplied by the Owner.

III)

Site Work Complete construction work including supply of labour, construction materials, construction equipment, survey, tools & tackles, dismantling & modification/strengthening, supervision, testing etc. required to complete all the structures, foundations, roads, drains, pavements, finishes, supply, fabrication, erection of steel structures, chain link fencing, painting, including site grading/earthwork in cutting & filling etc. as specified and required to complete the civil works in all respect. (All enabling works e.g. construction water tank, casting/fabrication yard, electricity, site stores & office, safety and security measures, coordination with other contractors working at site etc. shall be Contractor’s responsibility. Special permits to such as ‘Hot Permit”, “Fire Safety Permit” to work at dispatch terminal shall be contractor’s responsibility.) The Contractor’s rate for any item of work in the schedule of item shall, unless stated otherwise be held to include the cost of all materials including wastage, conveyance and delivery, unloading, storing, fabrication, all consumable materials, like electrodes, putty, gases, etc. hoisting, all labour for finishing to required shape and size, tools and plants, power fuel, consumables, all taxes, royalties, other revenue expenses, temporary facilities like roads etc

2.0

EARTHWORK IN EXCAVATION/SITE GRADING Brief description of major items shall be as follows: a) b) c) d) e) f)

Taking pre-work and finished levels. Stripping and grubbing the top soil of 150 mm and preparation of subgrade. Disposal of unserviceable and surplus earth to authorized dumping ground to any lead. Backfilling in layers of 150 mm thickness in controlled way. Watering and compaction of soil with manual/mechanical means. Actual work shall be carried out as per certified construction drawings to be issued to successful tenderer.

Note: For all these items only consolidated final filling quantity in Cum shall be

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 66 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

measured for payment. Payment for earthwork in excavation shall be made based on bottom most dimensions of the structure / foundation and as such contractor shall take in to account for doing additional excavation for working space etc. required for safe construction. 3.0

EARTH WORK IN FILLING Complete earthwork in filling with borrowed earth is included in the scope. Brief description of major items shall be as follows:

a. b. c. d. e. f.

Taking pre-work and finished levels. De-watering of excessive water. Strutting and shoring to retain the earth. Borrowing of approved quality good earth from any lead. Filling in layers of 150 mm. Watering and compaction up to 95% of its MDD with mechanical means.

Note: Payment for item earthwork in filling shall be compacted net volume of filling after deductions of foundations, culverts, etc. 4.0

PCC WORK Providing and laying PCC M 7.5 / M15 in position (at all height and depth for any type of structure), construction and handing over of PCC in foundations, substructure, superstructure and under floor, etc complete in all respects as per scope of work, detailed construction drawings, technical specifications and direction of Engineer-in-charge. The rate shall be inclusive of providing shuttering and strutting of all types (If necessary

5.0

REINFORCED CEMENT CONCRETE Brief description of major items shall be as follows:

6.0

a)

RCC of Grade M25 as per drg. & specification at all height and depth for all type of structures, supply of cement, coarse aggregate, fine aggregate, placement, all inclusive & testing of concrete and other materials.

b)

Fixing of all inserts, conduits, precast covers/chequered plates as well as fixing of free issue items into permanent works etc.

c)

Application of two coats of hot bitumen on surfaces in contact with soil.

BRICK WORK Complete works in brick masonry foundation is included in the scope. Brief description of major civil items shall be as follows: Brick work in foundation/superstructure at all height and depth with not less than M-7.5 grade bricks in 1:6 / 1:4 cement mortar.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 67 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

7.0

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

SOAK PIT AND SEPTIC TANK Complete works for the making and proper functioning of soak pit and septic tank is included in the scope: Brief description of major items shall be as follows:

a) b) c) d) e) f) g) h) i)

Earth work in excavation, back filling, and disposal of surplus earth. PCC 1:4:8. Brick work 1:5. Plaster 12 mm thick 1:3, finished with floating coat of neat cement inside and rough plaster outside. Brick bat filling in soak pit. Honey comb brick work in soak pit. RCC M-20 grade including reinforcement, shuttering etc in slabs. Making all types of connections for sewerage collection and disposal. Providing and fixing Vent pipe Soak pit and septic tank shall be provided inclusive of all related works complete in all respect shown in the drawing. Offer to be prepared by the tenderer based on the enclosed drawings and on lump sum unit rate (per installation).

8.0

PCC Kerb Stone in Specified Areas Brief description of major works to be considered in this item is as follows:

a) b) c) d) e)

Supplying and fixing Kerb Stone made of PCC – M 15 grade with 20 mm down graded stone aggregates. Bedding of 20mm thick cement sand mortar of grade 1:4. Painting with approved quality paint Jointing and pointing in cement sand mortar of grade 1:4. Necessary Excavation and backfilling

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 68 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Annexure-II to Particular Job Specification (INSTRUMENTATION WORKS)

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 69 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

CONTENTS 1.

INTRODUCTION

2.

GENERAL

3.

SCOPE OF WORK

4.

SCOPE OF SUPPLY

5.

FREE ISSUED ITEMS

6.

SPECIFICATION FOR INSTALLATION, TESTING AND COMMISSIONING

7.

LIST OF ATTACHMENTS

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 70 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

1.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

INTRODUCTION: The Scope of Instrumentation work shall be Installation, field testing/ calibration & commissioning of the complete instrumentation and control, system and supply of materials in accordance with the “Schedule of Rates for instrumentation” and other technical documents attached with this Tender Specification.

2.

GENERAL:

2.1.0

The Contractor shall be responsible for complete activities involving all subcontractors under him and also instrument sub-contractor (if applicable) works under him for the complete instrument works, as part of his scope.

2.1.1.

Scope of work shall be read in conjunction with the Schedule of Rates, drawings, specifications and other documents forming a part of the Contract document. Wherever there is a contradiction between the above, Schedule of Rates and this document shall take precedence.

2.1.2.

In the control room, the contractor's scope shall include laying, tagging and identification of all cables connected between the field and the control room, dressing of the same inside the control room. It is the responsibility of the contractor for proper routing, dressing of cables, terminations in UCP’s, inside the control room and also for loop checking.

2.1.3.

Contractor shall quote unit rates for all items covered in the “Schedule of Rates” (SOR).

2.1.4.

Contractor shall be responsible for co-ordination during installation, pre commissioning and commissioning with his Mechanical and other sub contractors for proper installation of line mounted instruments like Pressure/Thermal Relief valves, Electro-Hydraulic Control valves, Turbine flow meters, Rotameters, Surge Relief Valve Skid, Restriction Orifice plates etc.

2.1.5.

Contractor shall be responsible for installation, providing assistance for field testing, calibration, pre-commissioning and commissioning of special items such as Turbine flow meters, Density meters and Sulphur Analyser etc.

2.1.6.

Contractor shall be responsible for coordination with the turnkey instrumentation vendor for all kind of works in side the control room i.e. cable laying, tray erection, if any, and for proper cable terminations and loop checking.

2.1.7.

Drawings and Installation Standards enclosed with the tender are only for reference and indicative of general nature for scope of work. Actual installation shall be carried out based on final installation standards, Bill of material and vendor’s drawings / documents issued to site and as per instructions of Engineer-in-Charge.

2.1.8.

Instrument items such as tubes, tube fitting, valves & manifold, junction boxes, cables, cable glands, plugs, adapters, pipe and pipe fittings etc., as required for installation & hook-ups of instrument listed under SOR shall be supplied from the attached list of Approved Vendor’s only. Contractor shall take prior approval of make and specification of such items before placement of order.

2.1.9.

Sealing of cable entries into the control room after laying and testing of all cables through pipe sleeves by filling with sealing compound.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 71 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

2.1.10. Contractor’s scope shall also include dropping/shifting of the TSV/PSV from the installed position to laboratory for calibration/re-calibration/rechecking, etc., and reinstall back to original location including parts replacement, gasket, stud/bolts etc., re-fixing of the TSV/PSV including lapping if required to be done. The unit rate in the Schedule of Rates shall also include the same. 2.1.11. During trial run/start up/commissioning at all the locations, the contractor shall provide skilled personnel and supervision round the clock at contractor’s cost. Any defect or changes of setting, recalibration, etc., if any during the above activity shall be rectified/done immediately to the satisfaction of engineer-in-charge or his representative. The number and category of the personnel shall be as decided by the engineer-in-charge. The cost of the above is deemed to be included by the contractor in the rate quoted. 2.1.12. Contractor's scope shall include making holes in the RCC for fixing up of supports for instrumentation items, trays etc. 2.1.13. Contractor shall note that elbows (if required) shall be installed on the impulse line wherever required as per instructions of the Engineer-in-Charge even if it is not indicated in the installation standards. 2.1.14 The methodology of cable supports shall be as follows:a)

Perforated/Angle/Ladder Trays (Contractor’s supply) for all the cables from the individual instruments to the respective junction boxes.

b)

Perforated/Angle/Ladder Trays (Contractor’s supply) or Trenches (Prepared by contractor) as per the layout drawings (and any subsequent site adjustments as deemed necessary by the engineer-in-charge) from the junction boxes to the control room(s), the same supports/routes will have to be used for direct run cables from the individual instruments to the control room.

2.1.15 The field work shall be carried out under strict safety regulations and work permits as laid down by the client. The contractor shall take extreme care regarding safety and all safety gear like helmets; hand gloves, safety belts, spectacles etc. shall have to be provided by the contractor. 2.1.16 The ferruling for cables shall be done with tag no. of instruments for individual pair. Cross ferruling shall be done for cable ferruling in field, fire water control panel and UCP panels as per instruction of the Engineer in charge. 2.1.17 The contractor shall have to assess the actual site conditions/requirements before placement of order for cable/trays as per the actual site condition. Contractor has to prepare a cable routing layout as per actual site requirements from field to existing control room and get the approval before placement of procurement. 2.1.18 Allowable minimum bending radius of multipair / multicore cable shall be 6 times the outside diameter for unshielded cables and 8 times the outside diameter for shielded cables unless otherwise recommended by the supplier. 2.1.19 Location and flow direction of on-line instruments shall be checked by the contractor and to be rectified in case of any discrepancy as per the instruction of Engineer-In-Charge 2.1.20 The cable entry to the Control room shall be through pipe sleeves for all the control rooms, which shall be installed by the contractor. The installation of the pipe sleeves shall be as approved by the Engineer-in-charge. Contractor shall run all cables from field to Control Room. The cables shall run through Tray / Trench / IRC (instrument road crossings) from field to the control room as per

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 72 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Instrument Layout Drawings (to be furnished during execution). 2.1.21 Wherever trenches of longer/ smaller dimension than the maximum dimension identified in the SOR, the rate shall be considered as pro-rata basis for increase/ decrease in floor area change. 2.1.22 Welding/NDT, Charpy V-notch, QA/QC requirement etc. shall be as per Piping Material Specification (PMS), MECON standards & specifications and other requirement attached / mentioned elsewhere in the tender document. Contractor to also note that 100% MPI shall be carried out in the entire socket weld joints in the installation of instruments. The SOR price shall include all the above in the installation of respective instrument/item. 2.1.23 Welding shall be as per welding standard attached elsewhere in the tender document.

3.

SCOPE OF WORK: 3.1 The instrumentation works shall include, but not limited to the following to complete the works: a) b) c) d) e) f) g) h) i)

j) k) l)

m) n) o)

Installation of all field instruments. Calibration of field instruments. Installation of junction boxes Fabrication, erection, laying & painting of cable trays. Preparation of cable trenches (Buried). Laying of all interconnection cabling (single pair & multi pair signal, alarm, control and power cables and system cables etc.) between instruments and junction boxes, instrument / junction boxes to fire control room marshalling racks/cabinets/panels Laying of system cable/ serial link cable from PLC based station control system in control room to remote I/O cabinet of PLC system located in sub-station and from control room to sulphur analyzer cabinet in the field Installation of canopies for instruments. Dressing, Tagging, ferruling, glanding, pair/core identification and termination of all field cables (single pair & multi pair signal, alarm, control, power and system cables etc.) in the field instruments/ junction boxes, local control panel and UCP panels, supplied by pump vendor, at control room end. Installation of instrument valves & manifolds, mounting accessories, impulse piping/ tubing, pipe/tube fittings, cable glands, identification tags, conduits, structural material required for instrument and junction box supports, trays and painting etc. Laying of earthing cables / strips for instrument cases & junction boxes to earth grid, GI / copper strips for grounding of racks/ cabinets/ panels in the control room with earth pit. Installation of marshalling cabinets, power distribution cabinets, system cabinets, I/O cabinets, metering cabinet, consoles for PLC based Station Control system etc in the respective control rooms including physical shifting from owner’s store to control rooms, including supply & fabrication of base frame/support, grouting etc and commissioning assistance. Installation of remote I/O cabinet of PLC system in sub-station including physical shifting from owner’s store to control rooms, including supply & fabrication of base frame/support, grouting etc and commissioning assistance. Installation of line mounted instruments like control valves, orifice plates and flanges, variable area flow meters, turbine flow meters, tank level instruments, etc. Installation of skid mounted Density meter analyzer in field including: Physical shifting of density meter skid from Owner’s store to erection site. All civil works like grouting, fixing, etc and patch up work in the flooring for installation of the skid, hook up of all inlet outlet tubing/piping etc. between sample point and skid. Laying of power and signal cables between density meter skid junction boxes to Purchaser’s control room. Glanding &

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 73 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

p)

q) r) s) t) u) v)

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

termination of the cables at field side. Excavation of trenches for burring the cables, filling with sand, laying of bricks, back filling and compacting of the excavated earth. Removal of pre-cast concrete slabs (If required) and sand on the existing concrete trench, and re-filling of RCC cable trenches with sand & re-fixing back the concrete slabs after laying of new cables. Complete loop checking and megger testing of cables. Hydraulic testing of instrument impulse lines (piping/tubing). Calibration of all instruments. Commissioning. Documentation. As built drawings.

3.2

Scope of work shall also include Instrumentation works related to Mainline Pumps. Installation and commissioning of all Instruments & Controls for the Main line Pumps including loop checking complete in all respects (under the supervision of Pump Vendor) shall be included as under:

a)

All Unit Control Panels (UCP) including Marshalling/Relay/Power supply distribution cabinets and PCs (for monitoring of temperature & Vibration monitoring system) for all main line pumps shall be physically shifted from owners stores to control room and shall be positioned & grouted inside the control room.

b)

Laying of cables from instruments to junction boxes / Local panels on pump skids and from Junction boxes/Local control panels to Unit Control Panel in control room. Termination of cables, tagging, glanding and ferruling of all cables in skid junction boxes / Local panels and Unit Control Panel in control room. Supply of all installation and erection materials including identification tags, conduits, structural material required for instrument supports and trays and painting etc.

c)

Laying of earthing cables/ strips/wire for instrument junction boxes/local panel.

d)

Erection of cable trays in the skid up to the main cable trench including support for Trays.

e)

Calibration of pump skid instruments.

f)

Preparation of trenches/pipe sleeves from pump skid up to Main Cable Trench leading up to control room and laying of all the cables up to Control Panel in control room.

g)

Pump’s Unit Control Panel and all associated cabinets in the control room shall be connected to the earth pit with GI/copper strips for grounding, by the contractor.

h)

Commissioning of all instruments & controls including local panel and Unit Control Panel for the Main line Pumps in coordination with Pump Vendor and Turnkey Instrumentation Vendor. Installation of all instruments, testing of impulse lines, instrument air lines, pneumatic signal tubes and instrument cables including special instruments / items if any, and calibration of all instruments shall be carried out as per the requirement described in the “Clause 6. Specification for Material Installation, Testing and Commissioning” attached in this document

4.

SCOPE OF SUPPLY a)

The scope of contractor for supply of instrumentation items shall include, but not limited to the following to complete the Instrumentation work: i.

Supply of cable trays, perforated/angle trays including clamping, identifying tags.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 74 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ii.

Supply of junction boxes, cable glands, plugs and adapters.

iii.

Supply of all interconnecting cables (single pair & multi pair signal, alarm, RTD and control cables etc.) between instruments and junction boxes and up to control room mounted cabinets/ panels.

iv.

Supply of ferrules and identifying tags for cables at field, fire water control panel and UCP panels.

v.

Supply of all installation and erection materials (pipe fittings shall be as per the tube/tube fittings shall be of SS 316) including instrument valves &manifolds, accessories, impulse piping/ SS tubing, pipe/tube fittings, cable glands, plugs, identification tags, conduits, structural material required for instrument supports and painting etc.

vi.

Supply of earthing cables / strips for connecting instrument cases to earth grid, GI / copper strips/shielded cables for grounding of panels in control room with earth pit.

vii.

Supply of yoke supports for instruments and junction boxes.

viii.

Supply of canopies fabricated out of 2 mm thick MS sheet for instruments.

ix.

Supply of pipe sleeves for instrumentation cable entry to the control room.

x.

Supply of Rodent repellers.

PMS and mounting adapters, and trays

b)

Supply of junction boxes, cable glands, cables, pipes, pipe fittings, tubes, tube fittings, instrument valves & manifolds etc shall be from MECON approved vendors.

c)

Contractor to note that wherever stainless steel is specified it refers to austenitic and / or ferrite steel.

d)

All cable glands shall be double compression type and shall be provided with PVC hood. Cable glands shall be suitable for the cable dimensions with ±2 mm tolerance.

e)

For all electrical items supplied by the contractor including junction boxes, cable glands and accessories supplied for projects in India, certification from CMRS for explosion proof to IS 2148 suitable for NEC Class -I, Div-1, Group C & D and Weatherproof to IP 55 as per IS 13947 and approval from CCOE (Chief Controller of Explosives, India) shall be furnished irrespective of place of manufacture.

f)

For instrument material supplied by Contractor such as cables, junction boxes, pipe, pipe-fittings, tube, tube-fittings, Instrument valves and Manifolds; drawings, data from vendor shall be furnished as required as per the respective standard specification. Also Contractor shall furnish: i. ii. iii. iv. v. vi.

Specification / Datasheet of Junction Boxes, Cable Glands, Plugs and adaptors. Complete catalogues with part list for all contractor supplied instruments. GA drawing of Junction boxes and canopies Certificates from statutory body for hazardous area for junction boxes, cable glands, plugs, adaptors. Material test certificates. Vendor List for all items

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 75 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd. vii. viii.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

As-built Drawings / Documents Site Calibration report for all instruments.

Note: This list indicates the minimum drawings and document requirements. However, vendor shall submit a complete list of document and drawing schedule listing all the drawings and documents to be submitted by them during the course of execution of the job. The schedule shall list all drawings and documents along with their number and expected date of submission. 5.

FREE ISSUED ITEMS: The following instrument item shall be free issued to contractor: a)

All field instruments like pressure transmitters, differential pressure transmitters (for DP, level & flow), pressure switches, pressure gauges, level gauges, level transmitter, temperature element and thermowell, temperature transmitter.

b)

All line mounted instruments such as pressure/thermal relief valves, turbine flow meters, orifice plates and flanges, skid mounted surge relief valves, control valves etc.

c)

Skid mounted density analyzer and associated accessories / equipments

d)

All Control Room mounted equipments i.e flow computers, density converters, master control units of MOV control system, marshalling cabinets, I/O cabinets, PLC system cabinets, power supply cabinets, metering panels and consoles for control system etc.

e)

All pump skid instruments, interconnecting cables between pump skid and control room for main line pumps, cable glands, junction boxes, unit control panels, power distribution cabinets, relay panels and all other associated instruments & accessories for Main Line Pumps.

6.

SPECIFICATION for INSTALLATION, TESTING AND COMMISSIONING

6.0

ERECTION MATERIAL SUPPLY The Contractor shall ensure supply of all erection hardware required for installation of all instrumentation. This includes items like cables, cable glands, junction boxes, instrument valves, mounting accessories, impulse piping / tubing, pipe / tube fittings, pneumatic signal tubes, air line pipes, filter regulator, steam / electrical tracing, insulation materials, cable trays, conduits, identification tags, structural material required for instrument supports and trays etc. The above broadly covers the items required for any typical plant, however the Contractor shall supply all other items necessary to make the erection and commissioning work complete in all respects. The following are the minimum acceptable salient features of some of the erection materials.

6.1

CABLES 0

6.1.1 All cables shall have PVC insulated primary insulation of 85 C, PVC as per IS-5831 Type C 0 and inner and outer jacket shall be 90 C, PVC to IS-5831 Type ST-2. Oxygen index of PVC 0 shall be over 30% and temperature index shall be over 250 C. 6.1.2 All the cables are required to be fire retardant, they shall be as per standard IEC 332 Part III Cat. A.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 76 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

6.1.3 The insulation grade shall be 600 V/1100 V as a minimum and shall meet insulation resistance voltage and spark test requirements as per BS-5308. 6.1.4 All cables shall be twisted and armoured. Armour over inner jacket shall be of galvanized steel wire / flat as per IS-1554 Part–I. 6.1.5 For signal and control cables, inner jacket colour shall be black. Outer jacket colour shall be light blue for intrinsically safe application and black for others. For thermocouple extension cables the inner and outer jacket colour shall be as per IS-8784. 6.1.6 Maximum DC resistance of the conductor of the completed cable shall not exceed the following: a) b)

0

2

12.3 ohms/km at 20 C for cables with 1.5 mm conductor. 0 2 39.7 ohms/km at 20 C for cables with 0.5 mm conductor.

6.1.7 The mutual capacitance of the pair of adjacent cores shall not exceed 250 pF/m at a frequency of 1kHz. The capacitance between any core and screen shall not exceed 4(X) pF/m at a frequency of 1 kHz. 2

6.1.8 L/R ratio of adjacent cores shall not exceed 40 mH / ohms for cables with 1.5 mm conductor 2 and 25 PH /  for cables with 0.5 mm conductor. 6.1.9 The drain wire resistance including shield shall not exceed 30 ohms/km. 2

6.1.10 A pair of communication wire shall be provided for multipair cables. Each wire shall be 0.5 mm 0 of plain annealed single or multi-strand copper conductor with 0.4 mm thick 85 C, PVC insulation shall be green and red colour coded. 6.2

Signal /Alarm Cables -

Single pair shielded signal / alarm cables shall be used between field instruments switches and junction boxes / local control panels.

-

Multipair individually and overall shielded signal / alarm cable shall be used between junction boxes / local control panel and control room in general.

-

The single pair / triad cable shall be 1.5 mm conductor size made of electrolytic copper conductor of 7 strands with each strand of 0.53 mm diameter, multipair cable with 0.5 2 mm conductor size shall have 16 strands of annealed electrolytic grade copper conductor with each strands of 0.2 mm diameter, multi triad cable or multi pair cable 2 with 1.5 mm conductor shall have 7 strand with each strand of 0.53 mm diameter.

-

Shield shall be aluminum backed mylar / polyester tape bonded together with metallic side down helically applied with either side having 25% overlap and 100% coverage. The minimum shield thickness shall be 0.05 mm in case of single pair / traid and 0.075 mm incase of multipair / triad cable.

-

Drain wire shall be provided for individual pair and overall shield which shall be 0.5 mm multi stranded bare tinned annealed copper conductor. The drain wire shall be in continuous contact with aluminum side of the shield.

-

All multi pair cables shall have 6 pair / 12 pairs only while multitriad cable shall have 6 triads / 8 triads only.

2

2

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 77 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd. 6.3

6.4

6.5

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Control Cables -

Single pair control shall be used between field mounted solenoid valves and junction boxes / local control panels and shall meet the requirements specified in para 6.2 above.

-

Multipair control cables shall be used between junction boxes / local panels and control room mounted devices in general. These cables shall have only overall shielding.

-

The control cables shall have 1.5 sq. mm conductor size with 7 stranded conductors of annealed electrolytic grade copper with each strand of 0.53 diameter.

Thermocouple Extension Cables -

Single pair shielded thermocouple extension cables shall be used between thermocouple head and junction boxes transmitters / local control panel mounted instruments.

-

Multi pair individually and overall shielded thermocouple extension cables shall be used between junction boxes and control room mounted devices.

-

The type of thermocouple extension cables shall be compatible with thermocouple used. In addition the colour coding of the primary insulation shall be as per IS-8784-1987 Table 5.

-

The cable shall have 16 AWG and 20AWG solid conductors for single and multi pairs respectively.

-

All thermocouple extension cable shall be matched and calibrated in accordance with IEC-584-2.

-

Shield shall be aluminum backed by mylar / polyester tape bonded together helically applied with the metallic side down with either side having 25% overlap and 100% surface. Minimum shield thickness shall be 0.05 mm for single pair and 0.075 mm for 2 multi pair cable. Drain wire shall be 0.5 mm multi strand bare tinned annealed copper conductor. The drain wire shall be in continuous contact with aluminum side of shield.

-

Inductance shall not exceed 4mH/Km. However, for J-type thermocouple inductance could be 8 mH/ km.

-

All multi pair cables shall have 6 pairs / 12 pairs only.

Power Supply and Other Cables -

All power supply cable shall be as per IS-1554 Part – I and shall have copper 2 conductors. Minimum conductor size shall be 2.5 mm . All these cable shall be PVC insulated and armoured.

-

Any other special cable required for instruments shall also be supplied as per requirements. Contractor shall ensure that these cables are armoured type and shall meet all other requirements specified in para 6.1.1 through 6.1.10 as applicable.

-

Contractor shall include a minimum of 30% of quantity of each type of cables supplied as spare, and in each multi pair cable 20% spare cores shall be kept.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 78 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd. -

6.6

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Contractor shall clearly state if any of the above cable does not suit vendor’s instruments requirement in the offer stage itself and indicate type of the cable required.

CABLES GLANDS Contractor shall supply all cable glands required to gland the above mentioned cables both at field instrument and at control room (local and main) / control room devices / junction boxes. All cables glands shall be of anodized aluminum alloy or of nickel plated brass and they shall be double compression type suitable for armoured cables. Explosion proof glands wherever required shall be supplied. Contractor / Vendor shall supply a 20% of cable glands of each type / size as spare.

6.7

JUNCTION BOXES Contractor / Vendor shall supply junction boxes wherever required. These shall be of die cast aluminum alloy body and shall be weather proof only when connected to intrinsically safe circuit. However when connected to an explosion proof instrument / circuit the junction boxes shall be weather proof and explosion / flame proof. 2

These boxes shall have terminals suitable for min 4mm cable terminations (klippon) mounted on rails. 20% spare terminals shall be supplied in each junction box. Telephone shoe shall be provided in junction boxes. Each junction box shall have a minimum of 10% or 2 Nos. of each size entry, whichever is more. Each of spare entries shall be duly provided with plugs. 6.8

INSTRUMENT VALVES AND MANIFOLDS Contractor / Vendor shall supply instrument valves (miniature type) and valve manifolds wherever required. Body material and rating shall be as per piping class or SS whichever is better and shall be forged type. Valve trim material shall be 316SS as minimum or superior as required by process conditions. Contractor / Vendor shall supply a minimum of 10% such instrument valves and manifolds as spare.

6.9

IMPULSE PIPING / TUBING In general Contractor / vendor shall supply 1/2" OD x 0.065" thick ASTM A 269 TP 316 SS seamless tubes as minimum for impulses lines. Where the pressure (operating) exceeds 70 kg/cm2 seamless pipes size ½ NB of required thickness shall be supplied with material as per piping class. Seamless tubes shall have a hardness of Rockwell RB – 65-70 at scale 30T. Tubes shall be free from scratches and shall be suitable for bending. Unless otherwise specified the tube wall thickness shall be 0.049’’ for ½  O.D and 1mm for 6 mm O.D tubes Contractor / Vendor shall supply a minimum of 20% of pipes / tubes as spare.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 79 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

6.10

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

PIPES AND TUBE FITTINGS Nomenclature of all tube fitting shall be as per ISA RP42.1 Contractor / Vendor shall supply flareless compression type tube fitting and of three piece construction with design similar to swagelock / Parker Hanifen / Evmeto etc. All parts shall be made of SS 316. The fitting/ferrule hardness shall be in the range of RB 85-90 at scale 30T so as to ensure a minimum hardness difference of 5 to 10 between tube and fitting and of stainless steel in general. Thread ends of fittings shall be NPT according to ASME 16.11. Socket weld type forged pipefittings of suitable material and ratings shall be supplied for pipefittings. The minimum rating shall be 3000 lbs. Weld neck fitting shall be used where socket weld type are not allowed by piping class. All threaded fitting shall have NPT thread as per ANSI/ASME B16.11 only. Contractor / Vendor shall supply a minimum of 20% each type of pipe / tube fittings as spare.

6.11

PNEUMATIC SIGNAL TUBES Contractor / Vendor shall supply 6mm OD x 1mm thick SS – 316 seamless pneumatic signal tubes.

tubes

for

Contractor / Vendor shall avoid use of intermediate connections and shall estimate single length for each instrument location. Contractor / Vendor shall supply a minimum of 20% of these tubes as spares. 6.12

INSTRUMENT AIR LINES FITTINGS AND VALVES. Seamless, inside and outside galvanized Carbon steel pipes used for instrument air distribution, shall be as per IS 1239 class Heavy Duty Type. Galvanized forged screwed Carbon Steel fittings 2000 lbs rating, shall be used. Isolation valve on instrument air service shall be packless gland type full-bore ball / globe valves. Contractor / Vendor shall supply a minimum of 20% of air pipe, fittings and valves as spare.

6.13

AIR FILTER REGULATOR Instrument air filter regulator of suitable sizes shall be supplied for each pneumatic instrument. The body of the filter shall be anodised Aluminum. The filter shall have 25 micron sintered bronze / ceramic filter element and shall be provided with manual drain and 2" dia nominal size pressure gauge.

6.14

CABLE TRAYS All cables / tubes shall run on cable trays. These cable trays shall be made out of perforated galvanized MS with red oxide primer and

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 80 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

shall be made of sheet of 2.5mm thick. The width shall be so selected that 50% of tray space of each is available for future use of the complete installation. Suitable cable clamps shall be supplied for binding the cables, tubes at every 500mm. 6.15

INSTRUMENT SUPPORT / STRUCTURAL STEEL Contractor / Vendor shall supply instrument stands, stanchions and other structural steel material required for supporting the cable trays, impulse lines and instruments.

6.2

INSTALLATION

6.2.1

Contractor shall be completely responsible for installation of all instruments within his battery limit, as per the installation sketches (typical) furnished alongwith this bid document. All direct mounted instruments like thermocouple thermowells, temperature gauges, pressure gauges, pressure switches etc. shall be installed in such a way that they have better readability and accessibility. All capillary type instruments shall have the capillary supported properly and shall have protection of capillary against mechanical damage. All Pressure, Differential Pressure instruments shall be provided with block and bleed, bypass, drain / vent valves etc. as per the installation sketches, and shall have easy accessibility. All primary piping / tubing (impulse lines) shall have a slope of 10% on the horizontal run. All welding shall be carried out as per the relevant code with proper electrodes. Any tests (nondestructive) like DP test on root weld and final weld shall be carried out as applicable. All consumables shall be part of Contractor's scope. All threaded joints shall be joined by teflon tapes only. All impulse line shall be supported at regular intervals as specified elsewhere. Instrument drain / vent connections shall be piped to safe area like OWS or above pipe racks to avoid accumulation of hazardous fluid in the plant atmosphere. Steam tracing wherever required shall be carried out by 10mm OD x 1mm thick copper tubes, and condensate traps shall be provided to collect all the steam condensate and shall be piped to the nearest pipe drain funnels. All tubes / cables shall be properly laid on cable trays which shall be supported at regular intervals. Complete Physical separation shall be maintained between signal cables and shut down / power cables. Wherever intrinsic safe circuit system cabling is employed, a minimum separation of 150mm shall be adhered between IS and non-IS signal cables, over and above separation between signal and Power Cables. The casing of instruments shall be earthed by earthing wire to the nearest earth bus bar

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 81 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

provided by others, for safety reasons. In case the cables are to be buried or laid in the concrete trench, the same shall be carried out by vendor / contractor with prior intimation to ONGC. Painting of cable trays / ducts, MS cable ways, angle trays, instrument supports, all structural supports shall be as under The surface to be painted shall be thoroughly cleaned with wire brush, emery paper to remove all scales to achieve desired surface finish. After cleaning, one coat of red oxide zinc chromate primer shall be given conforming to IS 2074 and allowed to dry. Two coats of paint shall be applied subsequently. Further third / final coats of paint of final colour shall be given before handing over the plant / commissioning. 6.3

TESTING AND CALIBRATION

6.3.1

All impulse lines shall be properly flushed after isolating both the instrument and the vessel / piping. All impulse lines shall be tested hydraulically at 1.5 times the maximum operating pressure. Contractor to ensure that instrument and vessel / piping is isolated during this test. In case of special conditions where hydro testing is not permitted due to service conditions, the impulse lines testing shall be carried out by using air or nitrogen. All external cage type level instruments shall be tested up to 1.5 times operating pressure by using nitrogen only. After pressure testing all these impulse line shall be drained and dried with dry air / Nitrogen to remove any moisture. Instrument air lines will be service tested only for any leak after pressuring and isolating the main root valve, by soap solution. Pneumatic signal tubes shall be flushed and tested with instrument air for any leak at a pressure of 1.5 kg/cm2g. After pre commissioning the line, the source of pressure is cut off and rate of fall in pressure shall be ensured to be less than 1 PSI for each 100 feet for a period of 3 minutes as per ISA. All instrument cables shall be tested for continuity and insulation. While Meggar is used for insulation testing, ensure that all instruments and Zener barrier are isolated at both ends. All instruments supplied by the vendor shall be calibrated using proper test equipment. All test instruments shall have proper certificates and tracabilities of valid calibration to national or international standard without which installation shall not be acceptable. Standard format of calibration shall be offered by the contractor for approval of ONGC after the award of contract. All instruments shall be calibrated minimum for 0%, 25%, 50%, 75% and 100% and vice versa. All temperature gauges shall be calibrated using Temperature Baths. All thermocouple activated instruments shall be calibrated by generating standard millivolts by

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 82 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

a Potentiometer / Calibrator. All transmitters shall be calibrated as per instrument ranges. All displacer type level transmitters shall be calibrated with water or suitable fluids and corrected for specific gravity of the actual process fluid. All alarm and trip switches shall be calibrated over the entire range and finally set and checked for alarm / trip points and reset points as per the alarm / trip set point schedule. After setting these shall be sealed. All Control Valves prior to stroke checking shall be internally & externally cleaned thoroughly. The full stroke of valve shall be checked for opening and closing, in the range of 0%, 25%, 50%, 75% and 100%. Any adjustments required for obtaining full stroke and reducing hysterisis shall be carried out. Bubble tight shut off Control Valves and Shut Down Valves shall be checked for seat leak test and gland leak test Solenoid valve shall be checked functionally for its operation, & seat leakages. Safety valves and relief valves shall be set / tested by using dry air / nitrogen. Leakage if any shall be removed by proper lapping of seat and disc. All electronic / pneumatic receiver instruments shall be calibrated as per the manufacturer's instruction. Controllers shall be aligned properly. All special instruments like analyser shall be checked and calibrated as per manufacturer’s instruction. Prior to testing, all analyser sample lines shall be thoroughly cleaned by Carbon Tetrachloride or any other cleaning liquid. After cleaning, these lines shall be thoroughly purged with dry nitrogen. No oil should be used on oxygen service lines. The overall accuracy shall be with + 1% for Electronic Instrument Loops and + 1.5% for Pneumatic Loops. Where deviation is found to exist more than specified limit, Contractor shall recalibrate the instrument at no extra cost & time. After performing the calibration of all instruments, the entire loop shall be checked for proper operation. The entire shutdown scheme shall be simulated from the process trip switches and the scheme shall be tested for its proper operation, prior to start up of the unit. If no dry instrument air is available, Vendor / Contractor shall provide necessary N2 cylinders to carry out the above activity. 6.4

COMMISSIONING

6.4.1

This activity shall be carried out in a systematic manner so as to avoid any accident to plant and operating personnel. All perquisite checks prior to startup are to be completed in all respect, result recorded and approval of EIC for ensuring readiness of plant and all safety aspects adherence for startup is to be obtained by contractor. During the plant start up all the instruments calibration, controller alignment, trip point settings shall be trimmed / checked & confirmed so as to meet the operation requirement.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 83 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Prior to guarantee run of any package unit the vital instruments as required by vendor have to be recalibrated and the results to be recorded. 7.

LIST OF ATTACHMENTS: Refer the List of Standard Specifications and Standard Drawings enclosed else where in the tender document. STANDARD SPECIFICATIONS

Sl No.

DESCRIPTION

SPEC. No.

1

Specification for Installation of Instruments

MEC/S/05/26/01

2

Specification for Instrument Tubing

MEC/S/05/26/02

3

Specification for Inlet Outlet Sections & FS

MEC/S/05/26/03

4

Specification for Instrument Tube Fittings

MEC/S/05/26/04

5

Specification for Instrument Valves and Manifolds

MEC/S/05/26/05

6

Specification for Junction Boxes and Cable Glands

MEC/S/05/26/06

7

Specification for Signal Cable

MEC/S/05/26/07

8

General Technical Specification for Instrumentation

MEC/S/05/26/08

9

Specification for Cabling

MEC/S/05/26/21

10

Specification for Earthing

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

MEC/S/05/26/23 A

Page 84 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

LIST OF STANDARD DRAWINGS

Sl. No.

Drawing No.

DESCRIPTION

REV.

1

MEC/05/E5/SD/PT/001

INSTALLATION DIAGRAM FOR PRESSURE TRANSMITTER.

0

2

MEC/05/E5/SD/RTD/002

MOUNTING DETAILS FOR RTD ON THERMOWELLS.

0

3

MEC/05/E5/SD/DPG/003

INSTALLATION DIAGRAM FOR DIFERENTIAL PRESSURE GAUGE.

0

4

MEC/05/E5/SD/PG/004

INSTALLATION DIAGRAM FOR PRESSURE GUAGE.

0

5

MEC/05/E5/SD/TG-RTD/005

INSTALLATION DIAGRAM FOR TEMPERATURE GUAGE & RTD.

0

6

MEC/05/E5/SD/RTD-TW/006

MOUNTING DETAILS FOR THERMOWELLS (RTD).

0

7

MEC/05/E5/SD/TG-TW/007

MOUNTING DETAILS FOR THERMOWELLS (T G).

0

8

MEC/05/E5/SD/JB/009

SUPPORT DETAILS FOR JUNCTION BOXES.

0

9

MEC/05/E5/SD/CY/011

FABRICATED CANOPY FOR INSTRUMENTS.

0

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 85 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Annexure-III to Particular Job Specification (TELECOM WORKS)

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 86 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

SCOPE OF WORK FOR TELECOMMUNICATION 1)

INTRODUCTION M/s HPCL proposes to lay 2 parallel cross country petroleum product pipelines of 14.5 KM (apprx.) from the proposed dispatch station inside the existing Bahadurgarh Terminal of Mundra Delhi Pipeline in Haryana. The pipelines will terminate at HPCL’s proposed Tikarikalan terminal in Delhi. The Marketing Terminal at Tikarikalan is being constructed by HPCL. One pipeline will be utilized for dedicated pumping of Motor Spirit (MS) and other pipeline for pumping of High Speed Diesel (HSD) / Superior Kerosene Oil (SKO). To facilitate proper operation and management control of Pipeline, a reliable and dedicated Telecommunication System is proposed to be setup in future connecting the various attended and unattended station along the pipeline. The system will also provide for voice communication from unmanned station to the attended stations. Telecom system shall comprise of STM -1& STM-4 equipment. 12 fibers armored Optical fiber cable (free issued from client) shall be laid in self-lubricated 40mm HDPE conduit along with the pipeline to facilitate proper operational & management control of the pipeline and dedicated Telecommunication system.

2)

SCOPE OF WORK:a) Telecommunication work: The scope of work related to telecommunication work (but not limited to) shall include all the necessary work for supply and laying of one number self – lubricated HDPE duct, Laying of OFC (12 fiber) by Blowing technique in laid HDPE Duct along the new pipeline from Bahadurgarh to Tikarikalan in same trench and in separate trench inside the terminals including supply of HDPE Duct & accessories, supply & laying of Warning mat, Supply of FTC, wire mesh, Termination & Testing of OFC & HDPE duct including any civil work, commissioning , Quality assurance and Control, Documentation and any other job as per direction of Engineer In-charge required for completion and hooking up of OFC based telecom system. The erection, testing and commissioning of SCADA system and Telecom equipment (STM-1 & STM-4) and accessories are in other contractor’s scope. Detail Scope of Telecom Work (but not limited to): 1. Supply & Laying of 40 mm diameter HDPE Telecom pre-lubricated Ducts & accessories, estimation of quantity, including Storage, Transportation, and unloading at site, submission of HDPE alignment sheets (part of OFC alignment sheet documents), planning and HDPE lying schedule preparation. 2. Erection, testing commissioning and making the work complete in all respect as per specification. a)

Permanently solid Pre Lubricated 40mm diameter HDPE Telecom Duct as per specification along entire underground pipeline in the same trench including cased crossing for installation of OFC in future.

b)

HDPE casing /CS pipe casing for Nallah, River/ Canal, Railways, Major Road Crossing as directed by Engineer-in-charge wherever required and as directed by Engineer-in-charge in all type of soils and terrain.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 87 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

3. Supply and Preparation of cable Blowing & Jointing pit, jointing of HDPE Duct /conduit, scaling of conduit, HDPE conduit testing after laying sealing of HDPE conduit, cased crossing, separate trench & conduit near the terminals, joints locations marking, back filling, sealing of conduit, cable markers, joint markers, Warning mat etc. as per the MECON specification. All the accessories, if 2 required, must be suitable of 8 Kg/cm (min.) pressure rating. Testing, commissioning, and handing over of system, drawings & documentation as per contract. 4. Taking over of free issue 12 fibre OFC (after OTDR testing) from designated HPCL Store, transportation to site, loading, unloading storage and make it ready for erection. 5. Laying of Free issued 12 Fibre OFC by Blowing Technique , jointing closures and accessories, Submission test reports and documents for supplied material, storage, Transportation, unloading at site, submission of OFC alignment sheets based on the pipeline alignment sheet, planning and OFC laying schedule preparation, Laying of OFC (12 Fiber) testing before and after laying, all cable sealing, padding backfilling etc. using all material including supply and laying of warning mats etc., termination of cables at FTC with all accessories, cable jointing, commissioning and making the work complete in all respect as per specification Drawings & documentation as per contracts & other relevant work specified by Engineer-in-charge. 6. Supply and installation of 300 mm diameter cable marker mounted on Main pipeline Marker, Separate OFC joint marker, electronic marker & marker locator etc., as per specification. 7. Supply, Installation, testing and commissioning of “JOINTING CLOSURE” as per stander specification. 8. Supply of jointing pit. Jointing of OFC after properly placing it in manholes and providing protection to surplus OFC loop in the jointing chamber. 9. Supply of FTC and wire mesh for both ends. Installation of FTC & wire mesh, other accessories for termination of OFC-12 fiber in the control room, splicing with street fiber, test of the fiber for smooth operation of system on a wavelength. Test of laid OFC, identification of fault, rectification of fault, Cable Jointing, Earthing, all the termination and commissioning work, Reconciliation, complete in all respect. 10. Testing including power testing complete cable section between two stations at 1310 nm & 1550 nm and testing of end sealing. 11. Providing necessary Testing Tools and power supply at site for splicing and testing etc. 12. Preparations and submission of as-built drawings with soft copy as per contract specification. 13. All necessary civil works related to erection and cabling. 14. All electrical works associated with installation and commissioning of OFC. 15. Earthing / Grounding of FTC, Telecom equipment. Any other work required for completion of OFC based Telecommunication work as per the direction of Engineer-in-charge. SCOPE of work for OFC and HDPE Telecom Duct Laying: The scope of work related to above work shall include all the necessary work (but not limited to) for supply and laying of one number self – lubricated HDPE duct, Erection of OFC (12 fibre) directly buried in ground along the new pipeline from Bahadurgarh to Tikarikalan along the pipeline in

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 88 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

same trench and in separate trench inside the terminals including supply of HDPE Duct & accessories, supply & laying of Warning Mat, Supply of FTC, wire mesh, splicing, Termination & Testing of OFC & HDPE duct including any civil work, Commissioning , Quality Assurance and Control, Documentation and any other job as per direction of Engineer In-charge required for completion and hooking up of OFC based telecom system. Detail Scope of Work (But not limited to): HDPE Duct Laying: 1. Supply and Laying of 40 mm diameter self lubricated HDPE Ducts & accessories, making records of test report of material, estimation of quantity, including Storage, Transportation, and unloading at site, submission of HDPE alignment sheets, planning and schedule preparation for HDPE laying. 2. Erection, testing commissioning and making the work complete in all respect as per specification. a)

Permanently solid Lubricated 40mm diameter HDPE Conduit as per specification along entire underground pipeline in the same trench including cased crossing for installation of OFC in future.

b)

HDPE casing /CS pipe casing for Nallah, River/ Canal, Railways, Major Road Crossing as directed by Engineer-in-charge wherever required and as directed by Engineer-in-charge in all type of soils and terrain.

3. Supply and erection of cable Blowing & jointing pit, joint of HDPE conduit, scaling of conduit, HDPE conduit testing after laying as define in specification, sealing of HDPE conduit, cased crossing, separate trench & conduit near the terminals, joints locations marking, back filling, sealing of conduit, cable markers, joint markers, Warning mat etc. as per the MECON 2 specification. All the accessories, if required, must be suitable of 8 Kg/cm (min.) pressure rating. Testing, commissioning and handing over of system, drawings & documentation as per contract. General guideline for OFC based telecommunication system: 1. Vendor must submit the details of specific experience of the party responsible for OFC, HDPE Duct laying, jointing, splicing, Testing. Sufficient documentary evidences also to be submitted at the time of submission of bid. The parties having proven experience and track record in respective field shall be allowed to execute the job. 2. After award of work, Contractor shall supply 2 copies of detailed activity Bar chart, manpower and machinery mobilization plan, QA/ QC plan and inspection formats, execution procedures for different type of activities, for review and approval by the Engineer-in-charge within 15 days from the date of FOI (Fax of Intent). 3. The Vendor shall use the data provided in the tender for reference purpose only. It shall be the Vendor’s responsibility to check accuracy and utility of this data. 4. The contractor shall bring all duct & OFC laying, jointing, splicing equipment, tools as deemed necessary for the timely implementation of the work. 5. The OFC cable & HDPE Duct alignment sheets (to be submitted 15 days before final laying) in the format specified by the Engineer-in-charge shall indicate various rail, road, canal, river & utility crossing, location of high tension lines running in parallel with the route of OFC, location

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 89 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

of each of jointing locations & type of cable etc. After completion of laying vendor shall submit “As Built Drawing” as define in the specification. 6.

Special care should be taken to avoid any twist or damage of duct/ OFC while laying Optical Fiber Cable under road, Nalla, Railway line, culvert as specified elsewhere in the tender document.

7. Contractor shall take all safety measures required to prevent damage to the cable and accessories. The contractor shall be responsible for any damage to the cable, accessories and all other free issue items and existing underground services in route, if any. 8. The back filling and compacting of trench in layers of 20 cms. Restoration of road, Nalla, pavements etc. after the completion of laying work as specified elsewhere in this document. 9. Testing of the complete cable section (between two stations) to the satisfaction of HPCL as per test schedule mentioned elsewhere in the tender document. 10. Jointing, Splicing of OFC, in jointing pit, testing, end sealing etc. has to be done. OFC loop should not be left without proper protection at any place. The OFC loop or surplus cable should be accommodated within the jointing pit / chamber. 11. If during the course of execution of work any discrepancy or inconsistency error or omission in any one of the provision of the contract is discovered which needs to be clarified, the same matter shall be referred to the EIC / Consultants who shall give his decision in the matter and issue instruction then accordingly the work to be carryout. The decision of the EIC / Consultant will be final and binding to contractor. 12. For the payment for laying, the payable length of optical fiber cable will be the length of pipeline as per pipeline chainages. For inside Terminal the actual laid length in separate trench up to control room will be considered for measurement. No separate rate will be payable for separate trench. OFC Laying: 1. OFC (12 fibre – free issued) - Submission of test reports and documents for free issued material, storage, Transportation, unloading at site, submission of OFC alignment sheets based on the pipeline alignment sheet, planning and OFC laying schedule preparation, Laying by blowing technique of OFC (12 Fibre) testing before and after laying, all cable sealing, padding backfilling etc. using all material including supply and laying of warning mats etc., termination of cables at FTC with all accessories, cable jointing, commissioning and making the work complete in all respect as per specification Drawings & documentation as per contracts & other relevant work specified by Engineer-in-charge. 2. Supply and installation of 300 mm diameter cable marker mounted on Main pipeline Marker, Separate OFC joint marker, electronic marker & marker locator etc., as per specification. 3. Supply, Installation, testing and commissioning of “JOINTING CLOSURE” and “FTC” as per standard specification. 4. Supply of jointing pit. Jointing/ splicing of OFC after properly placing it in manholes and providing protection to surplus OFC loop in the jointing chamber. 5. Supply of FTC and wire mesh for both ends. Installation of FTC & wiremesh, other accessories for termination of OFC-12 fibre in the control room, splicing with street fiber, test of the fiber for smooth operation of system on a wavelength end to end. Test of laid OFC, identification of

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 90 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

fault, rectification of fault, Cable Jointing, Continuity test, Earthing, all the termination of OFC at FTC and commissioning work complete in all respect. 6. Testing including power testing complete cable section between two stations at 1310 nm & 1550 nm as applicable and testing of end sealing. 7. Providing necessary Testing Tools and power supply at site for end to end splicing and testing etc. 8. Preparations and submission of as-built drawings with soft copy as per define in the specification. 9. All necessary civil works related to erection and cabling. 10. All electrical, Earthing / Grounding works associated with installation and commissioning of OFC, FTC, RTU, Telecom equipment. The earthing pit for telecom equipments are also in the vendor scope. Separate SOR item is available in the price schedule. This will be operated as per the requirements 11. Any other work required for completion of OFC based Telecommunication work as per the direction of Engineer-in-charge. Enclosures: LIST OF STANDARDS SPECIFICATIONS Sl. No.

Standard Specification No.

Description

Remarks

1.

MEC/S/05/E5/T/001

Specification for Optical Fibre Cable & HDPE Duct Laying and Associated Work

Enclosed with Vol-II of II

2.

MEC/S/05/E5/T/002

Specification / Procedure for the Testing of Optical Fibre Cable

Enclosed Vol-II of II

LIST OF TECHNICAL SPECIFICATIONS Sl. No. 1.

Standard Specification No. MEC/TS/05/E5/T/096

Description Technical Specification for Optical Fibre Cable & Accessories (To be refer for Jointing Closures only)

Remarks

Enclosed with Vol-II of II

2.

MEC/TS/05/E5/T/037

Technical Specification PLE HDPE Telecom Duct and Accessories

Enclosed Vol-II of II

3.

MEC/TS/05/E5/T/042

Technical specification of Warning Mats for OFC & Telecommunication HDPE Duct

Enclosed with Vol-II of II

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 91 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Annexure-IV to Particular Job Specification (CATHODIC PROTECTION WORKS)

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 92 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

DESIGN BASIS FOR TEMPORARY /PERMANENT CATHODIC PROTECTION SYSTEM

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 93 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

MECON LIMITED

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

CONTENTS

Sl. No.

Description

1.

INTRODUCTION

2.

SCOPE

3.

CODES & STANDARDS

4.

SITE CONDITIONS

5.

AREA CLASSIFICATIONS

6.

POWER SUPPLY DETAILS

7.

MONITORING AND CONTROL SIGNAL FOR SCADA

8.

CABLES

9.

CATHODIC PROTECTION SYSTEM

10.

STATUTORY APPROVAL

11.

DRWINGS AND DESIGN DOCUMENTS

Prepared By

Checked By

Approved By

Aashish Moyal

Saurabh Singh

D K Pande

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 94 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

1.0

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

INTRODUCTION The project envisages laying of 10’” & 8” NB and 15 Km long petroleum product pipeline from dispatch terminal at Bahadurgarh to receiving terminal at Tikrikalan for supplying of MS, SKO/ HSD to the marketing terminal of HPCL at Tikrikalan. 1) 2)

Dispatch terminal at Bahadurgarh Receiving terminal at Tikrikalan

This document presents design criteria for CP (TCP/PCP) system for 3LPE Coated, 10’” & 8” NB and 15 Km long petroleum product pipeline against corrosion for a service life of 35 years. It indicates minimum requirements for detailed design of CP system and equipments. This design data defines the design requirements applicable for this project in addition to the Specification for Temporary cathodic protection system MEC/TS/05/21/016A, specification for permanent current cathodic protection system MEC/TS/05/21/016B. 2.0

SCOPE Survey, Design, detailed engineering, supply, packing, transportation to site, installation, testing and commissioning of the temporary & permanent cathodic protection system to protect the external surface of 3LPE Coated, 10’” & 8” NB and 15 Km long petroleum product pipeline against corrosion for a service life of 35 years, as per Standard Specification No. MEC/TS/05/21/016A for Temporary cathodic protection system and MEC/TS/05/21/016B for permanent cathodic protection system & SOW (scope of work).

3.0

CODES & STANDARDS The system design, performance and materials to be supplied shall, unless otherwise specified, conform to the requirements of the following latest relevant applicable specifications: i)

NACE Standard RP-0169

:

ii)

NACE Publication 10A190

:

Standard Recommended Practice Control of External Corrosion on Underground or Submerged Metallic Piping Systems. Measurement technique related to criteria for CP of Underground or Submerged Steel Piping System (as defined in NACE Standard RPO169-83).

ii)

NACE Standard RP-0177 of

:

Standard Recommended Practice Mitigation

iv)

NACE Standard RP-0286

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

:

Alternating Current and Lightning Effects on Metallic Structures and Corrosion Control System. Standard Recommended Practice the electrical isolation of Cathodically Protected Pipelines.

Page 95 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

v)

NACE Publication No. 54276 :

vi)

NACE Standard RP-0572

:

vii)

IS 8062

:

viii)

BS 7361 Part I

:

ix)

VDE 0150

:

x) xi)

IS: 7098 Part I IS: 1554 Part I

: :

MECON LIMITED

Cathodic Protection Monitoring for Buried Pipelines. Standard Recommended Practice Design, Installation & Operation of Impressed Current Deep Ground beds. Recommended Practice ICCP for Underground Piping. Code of Practice for Cathodic Protection for land and marine application. Protection against Corrosion due to Stray Current from DC Installations. XLPE Insulated Cables. PVC Insulated (heavy duty) cables.

3.2

In case of imported equipments standards of the country of origin shall be applicable if these standards are equivalent or stringent than the applicable Indian standards.

3.3

The equipment shall also confirm to the provisions of Indian Electricity rules and other statutory regulations currently in force in the country.

3.4

In case of any contradiction between various referred standards/ specifications/ data sheet and statutory regulations the following order of priority shall govern.     

4.0

Statutory regulations. Data sheets. Scope of Work/ Job specification. This specification. Codes and standards.

SITE CONDITIONS The equipment offered and the installation shall be suitable for continuous operation under the following site conditions: Ambient temperature Max relative humidity Altitude Atmosphere

Control Room/Electrical 5.0

: : : :

:

50°C (max.)/ 0°C (Min.) 90% Less than 1000m above MSL To withstand site condition (Dry, dust storms during summer, Humid & Heavy Rainfall during Monsoon) Safe Area

ARES CLASSIFICATION Classification of hazardous area will be in accordance with BIS and IS: 5572. Following selection will be considered for proper selection of electrical equipment for use in hazardous area:

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 96 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

MECON LIMITED

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

a) Area Classification

:

Zone-1

b) Group

:

IIA and IIB

c) Temperature Classification :

T3

All electrical equipment installed in hazardous area will be selected as per IS: 5571. 5.1

All the electrical equipment for hazardous areas shall be of Ex-d type suitable for temp classification T3.

6.0

POWER SUPPLY DETAILS

(A)

For despatch/receiving terminal at Bhadurgarh/Tikrikalanl CP Station power supply to PCP system (TR unit) shall be through UPS to TR unit, however cathodic protection power supply module TR/CPPSM unit to be provided by CP CONTRACTOR.

(B)

CP power supply : - Type & Voltage: (*) - Out put voltage: (*) - Location of TR unit: (*) - Number/ configuration: (*) (*) shall be furnished/confirmed by client.

7.0

MONITORING AND CONTROL SIGNAL FOR SCADA Digital and analogue monitoring and control signals as required for CP system shall be provided in various electrical equipment for connection to SCADA system. CPPSM/TR unit shall be properly interfaced with RTU with RS485 serial data link for various analogue, digital signals & control signal, CONTRACTOR shall provide RS485 serial link. Details of SCADA monitoring & control signals are given below-

Sl No.

MONITERING/ CONTROL

ANALOUGE /DIGITAL

CPPSM/CPTR OUT PUT VOLTAGE CPPSM OUT PUT CURRENT

M

AI

M

AI

3

PIPELINE PROTECTED

OVER

M

DI

4

PIPELINE

UNDER

M

DI

1 2

DESCRIPTION

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 97 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

MECON LIMITED

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

PROTECTED 5

PIPE TO SOIL POTENTIAL

M

AI

6

ALL REFERENCE CELLS FAILED

M

DI

7

REFERENCE CELL-1 VOLTAGE

M

AI

8

REFERENCE CELL-2 VOLTAGE

M

AI

9

REFERENCE CELL-3 VOLTAGE

M

AI

10

Unit Working in AUTO REF Mode

M

DI

11

Unit Working in AVCC mode

M

DI

12

DC (solar)/ AC input fail.

M

DI

13

Setting of DC output voltage

C

AO

14

Setting of DC output current

C

AO

15

Setting of pipe to soil potential (PSP) Setting of Auto/AVCC mode

C

AO

C

DO

16 1 2 3 4 8.0

AI: Analogue monitoring signal from Equipment to PLC/Telemetry interface cabinet (TIC) AO: Analogue control signal from PLC/(TIC) to Equipment DI: Digital Monitoring signal from Equipment to PLC/(TIC) DO: Digital control signal from PLC/(TIC) to Equipment

CABLES a. Cables shall be annealed high conductivity tinned stranded copper conductor, XLPE insulated, PVC sheathed, 650/1100 V grade, armoured for Cathode/Anode / measurement cable. Unless otherwise specified in project specifications, the size of the copper conductor shall be minimum 35 sq. mm. for anode and cathode cables, 6 sq. mm. for potential measurement and reference cells, 10 sq. mm. for current measurement, 25 sq. mm. for bonding/ grounding and 10 sq. mm. for anode tail cables. The anode tail cables shall be XLPE insulated & PVC sheathed and shall not be armoured. The length shall be sufficient for termination on anode lead junction box without any joint. PE sleeves shall be provided for unarmoured cables.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 98 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

b. The T/R unit incomer cable shall be minimum 10 sq. mm. aluminium, 650/1100 V PVC insulated, armoured, PVC sheathed. The cable shall be of 3 core type for single phase TR units/CPPSM unit and 4 core type for 3 phase TR units. c. The cables for connecting various transducers from TR unit/ CPPSM to telemetry interface junction box shall be twisted pair with individual pair shielded and overall shielded with aluminium backed by mylar/polyster tape, PVC sheathed, armoured, PVC over all sheathed type. d. CABLING SYSTEM Cable laying philosophy A. Paved area: B. Unpaved area: C. Type of cable trays: 8.0

Cable tray/RCC trench Directly buried Galvanized prefabricated

CATHODIC PROTECTION SYSTEM TCP system- (Temporary Cathodic Protection System) A. Type

:

Sacrificial magnesium anode

B. Design life

:

1 Year or till commissioning of PCP whichever is later

C. Pipeline coating

:

Three Layer Polyethylene

D. Protective current density

:

As per specification

E. Anode material (for sacrificial

:

Zinc/ Magnesium (As per specification) CP System)

F. Electrical resistance probes

:

Shall be provided as per spec.

a. Quantity of E/R probes b. No. of E/R probe reading

: 2 nos. per section, location in consultation with OWNER/MECON by CP Contractor as per specification. : One per Section instrument

G. Polarisation coupons

: Shall be provided as per specification

a. Size of exposed area of coupon

: 100mm x 100mm

b. No. of coupons

: To be decided by CP contractor as per specification & in consultation with OWNER/MECON

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 99 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

c.

No. of magnet devices for : operation of magnetic reed switch

-DO-

H.

Polarisation cell

: Electrolytic type as per specification

I.

Additional tests to evaluate the coating defects

: Shall not be conducted

J. CPL survey

: Shall not be conducted during TCP

K. DC interference & AC induced voltage survey

: Shall be carried out as per specification

PCP system- (Permanent Cathodic Protection System) A. Type B. Design life of protection C. Pipeline coating D. Design protection current density

: : : :

Impressed current type 35 Years Three Layer Polyethylene As per specification

E. Current drainage & coating resistance measurement survey F. Type of Anodes for anode ground bed:

:

Shall be carried out Tubular mixed metal oxide titanium or as per specification.

G Polarisation cell

:

Electrolytic type

H. Computerized test stations

:

Shall be provided (Location & no. of computerized test station shall be decided in detail engineering)

I. Chain link fencing around the ground Bed

:

Shall be provided

J Acquisition of land for Anode bed, Anode junction boxes and anode ground bed cable laying.

:

By Contractor

K. Close interval potential logging survey L. Additional tests to be conducted for identifying pipe coating defects/ holidays

: :

M. Proposed location of CP stations/Anode: Ground bed

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Shall be carried out DCVG/CAT survey

To be decided by CP contractor. (However tentative location of CP station are mentioned in the PJS, Exact location shall be decided in

Page 100 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

detail engineering & approval of design document in consultation with HPCL/MECON) N. Proposed location of Computerised test stations

:

To be decided by CP contractor during detail engineering based on specifications and in consultation with the Client/MECON.

O. CP stations/ anode ground bed for Impressed current system:a) Tentative locations of CP stations are mentioned in Scope of work (SOW), actual numbers of CP stations shall be finalized during the approval of design documents submitted by the Contractor. However PCP system shall be designed in such a manner that CP stations & anode bed shall be located coinciding with despatch/receiving stations, as far as possible. 10.0

STATUTORY APPROVAL The submission of application on behalf of the Owner to Govt. Authority/ Central Electricity Authority, if required along with copies of required certificates complete in all respects, shall be done by the contractor well ahead of time so that the actual commissioning of are not delayed for want of approval from authority. The actual inspection of work by the Govt. inspector shall be arranged by the Contractor and necessary coordination and liaison work in this respect shall be the responsibility of the contractor. However any fee paid to the Govt. Authority in this regard shall be reimbursed by the Owner on submission of bills with documentary evidence. The Inspection and acceptance of the work as above shall not absolve the Contractor from any of responsibilities under this contract.

11.0

DRWINGS AND DESIGN DOCUMENTS

11.1

The following documents shall be submitted along with the offer: a) b) c) d) e) f)

11.2

Filled up data sheet. QAP Design calculations of TCP & PCP system List of two years operation and maintenance spare. Approx. dimensions of the system Catalogues for TR/CPPSM unit, MMO Titanium Anode, reference cell etc.

The following drawings (in three sets) & documents shall be submitted for approval within 3 weeks of award of contract. a) b) c) d)

Soil survey report with information of terrain along the pipeline Detailed design calculations of TCP & PCP system, formulae used Procedure for AC & DC interference detection & mitigation. Procedure for CP system installation, field testing, pre-commissioning & commissioning.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 101 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

e) f) g) h) i) j) k) l) m) 11.3

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Procedure for post commissioning surveys. Detailed design of Anode ground bed, typical lay out drawings for Anode bed connection & installation. Equipment layout, Cable layout & schedule. AJB, TLP, CJB, permanent Cu-CusO4 & junction box installation & erection details drawings Incorporation of Anode bed, Polarisation cell, surge arrester, TLP, AJB, CJB, Junction boxes & other relevant feature in PCP system design in Alignment sheet & Plot plan. G.A. of TR/CPPSM unit. Schematic Bill of Material Wiring diagram for reference.

After the job completion, contractor shall prepare AS-BUILT drawings/data sheets and documents, submit catalogues/manuals (O&M) of major brought out items. Final certified as built drawings, documents and manuals etc shall be submitted by the contractor to owner in bound volume with one set in soft copy (CD) plus five sets of prints. Other drawings and documents shall be submitted by contractor along with AS-BUILT Drawings/Datasheets-

a) Original deed for Anode Bed shall be handed over to M/s HPCL. b) Test documents & drawings for bought out items. c) Detailed commissioning report of pipeline.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 102 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

SCOPE OF WORK FOR TEMPORARY & PERMANENT CATHODIC PROTECTION SYSTEM

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 103 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

CONTENTS

Sl. No.

Description

1.

INTRODUCTION

2.

SCOPE

3.

CODES & STANDARDS

4.

CATHODIC PROTECTION SYSTEM

5.

SCOPE OF WORK

6.

SCOPE OF SUPPLY

7.

STATUTORY APPROVAL OF WORKS

8.

INSPECTION, TESTING & COMMISSIONING

9.

DRAWINGS, STANDARD SPECIFICATION AND INSTALLATION STANDARDS

10.

MAKE OF MATERIALS/BOUGHTOUT ITEMS

11.

DOCUMENTATION

Prepared By

Checked By

Approved By

Aashish Moyal

Saurabh singh

D K Pande

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 104 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

1.0

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

INTRODUCTION The project envisages laying of 10’” & 8” NB and 15 Km long petroleum product pipelines from dispatch terminal at Bahadurgarh to receiving terminal at Tikrikalan for supplying of MS, SKO/ HSD to the marketing terminal of HPCL at Tikrikalan. 1) Dispatch terminal at Bahadurgarh 2) Receiving terminal at Tikrikalan This document presents design criteria for CP (TCP/PCP) system for 3LPE Coated, 10’” & 8” NB and 15 Km long petroleum product pipelines against corrosion for a service life of 35 years. It indicates minimum requirements for detailed design of CP system and equipments. This design data defines the design requirements applicable for this project in addition to the Specification for Temporary cathodic protection system MEC/TS/05/21/016A, specification for permanent current cathodic protection system MEC/TS/05/21/016B.

3.0

SCOPE Survey, Design, detailed engineering, supply, packing, transportation to site, installation, testing and commissioning of the temporary & permanent cathodic protection system to protect the external surface of 3LPE Coated, 10’” & 8” NB and 15 Km long petroleum product pipelines against corrosion for a service life of 35 years, as per Standard Specification No. MEC/TS/05/21/016A for Temporary cathodic protection system and MEC/TS/05/21/016B for permanent cathodic protection system.

3.0

CODES & STANDARDS The system design, performance and materials to be supplied shall, unless otherwise specified, conform to the requirements of the following latest relevant applicable specifications: i)

NACE Standard RP-0169

ii)

NACE Publication 10A190

ii)

NACE Standard RP-0177

iv)

NACE Standard RP-0286

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

:

Standard Recommended Practice Control of External Corrosion on Underground or Submerged Metallic Piping Systems.

: Measurement technique related to criteria for CP of Underground or Submerged Steel Piping System (as defined in NACE Standard RPO169-83). :

Standard Recommended Practice Mitigation of Alternating Current and Lightning Effects on Metallic Structures and Corrosion Control System. :

Standard Recommended Practice the electrical isolation of Cathodically Protected Pipelines.

Page 105 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

v)

NACE Publication No. 54276 :

Cathodic Protection Monitoring for Buried Pipelines.

vi)

NACE Standard RP-0572

vii)

IS 8062 Underground

viii)

BS 7361 Part I

ix)

VDE 0150

x)

IS: 7098 Part I

:

XLPE Insulated Cables.

xi)

IS: 1554 Part I

:

PVC Insulated (heavy duty) cables.

: : :

Standard Recommended Practice Design, Installation & Operation of Impressed Current Deep Ground beds. Recommended Practice ICCP for Piping. Code of Practice for Cathodic Protection for land and marine application.

:

Protection against Corrosion due to Stray Current from DC Installations.

3.5

In case of imported equipments standards of the country of origin shall be applicable if these standards are equivalent or stringent than the applicable Indian standards.

3.6

The equipment shall also confirm to the provisions of Indian Electricity rules and other statutory regulations currently in force in the country.

3.7

In case of any contradiction between various referred standards/ specifications/ data sheet and statutory regulations the following order of priority shall govern.     

Statutory regulations. Data sheets. Scope of Work/ Job specification. This specification. Codes and standards.

3.8

The work shall be performed in conformity with this specification, standard specifications and installation standards enclosed elsewhere in this tender and code of practices of the Bureau of Indian Standards. In case of any conflict, the stipulations under this specification shall govern.

3.9

In addition, the work shall also conform to the requirements of the following: The Indian Electricity Act, and the rules framed thereunder. The Fire Insurance Regulations. The regulations laid down by the Chief Electrical Inspector of the state government/ Central Electricity Authority (CEA). The regulations laid down by the Factory Inspector. The regulations laid down by the Chief Controller of Explosives. Any other regulations laid down by the Central, State or Local Authorities from time to time during the execution of this contract. OISD Standards HPCL’s Safety Standard

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 106 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

3.10

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

The design, selection and installation of equipment and materials shall also conform to the requirements of the relevant latest standards of: BS Specification and codes of practice OISD Standard 138 IS: 8437 (Part-II)/ 8062 (Part-I) NACE Standards DNV Publications IEEE Publications

4.0

CATHODIC PROTECTION SYSTEM Project description M/s HPCL Limited intends to lay a 10”X 15 km & 8”X 15 km. long pipelines from dispatch terminal at Bahadurgarh in Harayana State to Tikrikalan in Delhi State for supply of petroleum product to Tikrikalan storage terminal. These pipelines are externally coated with 3 layer side extruded polyethylene as passive protection from corrosion. However 3 layer PE coating alone cannot protect the pipelines from corrosion due to combined attack of chemicals like acid, sulphates, chlorides from the soil and ground water. Hence it is intended to protect the above pipelines from corrosion by temporary cathodic protection system for design life of minimum 1 years or till the commissioning of PCP system, whichever is later and permanent Cathodic Protection System for a service life of 35 years. Insulating joints shall be provided on the above ground pipelines before leaving/ entering the ground. The pipeline is crossing various roads, rivers, HT & LT overhead lines, railway traction lines (AC traction system) and other pipelines/ services etc. along its route. Project Details Description Mainlines and Terminals

4.1

General The work being tendered is covered as indicated below: Sections Pipelines Dia. Sl. No. TRUNK LINES 1. Tap-off Point cum Despatch Terminal at 10” Bahadurgarh to Tikrikalan 2 Tap-off Point cum Despatch Terminal at 8” Bahadurgarh to Tikrikalan Total Length of 10” & 8” pipeline

Length (Approx.) 15.0 km 15.0 Km 30.00 Km

Description of the facilities covered in the above are described in following clauses.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 107 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

4.2

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Details of pipelines & terminals are given belowa)

b)

Proposed new pipelines The proposed new pipelines shall be originated from D/T at Bahadurgarh terminal and terminated at R/T at Tikrikalan. The new pipelines shall be of 10” & 8” NB 15 Km long and running parallel. Details of Proposed Pipelines Main Lines Main Line- I Bahadurgarh to Tikrikalan – – – – – – – – – – – – – – –

Material of Construction : Carbon Steel Line Size : 10” NB Length, in km : ~ 15.0 (appox.) Pipe Specification : ERW, API 5L Gr.B, PSL-2 Thickness : 6.4 mm, 7.1 mm Design pressure : 49 Kg/cm2 Corrosion Allowance : 0.5 mm External Coating : 3-LPE Internal Coating : Liquid epoxy Design Code : ANSI/ ASME B31.8 (Latest Edition) Major Water Crossings : As per Alignment Sheet Major Road Crossings : As per Alignment Sheet Rail Crossings : As per Alignment Sheet HT line crossing : As per Alignment Sheet Design Temperature -Buried : 0 to 45°C -Aboveground : 0 to 65°C

Main Line- II Bahadurgarh to Tikrikalan – – – – – – – – – – – – – – –

Material of Construction : Carbon Steel Line Size : 8” NB Length, in km : ~ 15.0 (appox.) Pipe Specification : ERW, API 5L Gr.B, PSL-2 Thickness : 6.4 mm, 7.1 mm Design pressure : 49 Kg/cm2 Corrosion Allowance : 0.5 mm External Coating : 3-LPE Internal Coating : Liquid epoxy Design Code : ANSI/ ASME B31.8 (Latest Edition) Major Water Crossings : As per Alignment Sheet Major Road Crossings : As per Alignment Sheet Rail Crossings : As per Alignment Sheet HT line crossing : As per Alignment Sheet Design Temperature -Buried : 0 to 45°C -Aboveground : 0 to 65°C

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 108 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

4.3

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Terminals a)

Despatch Bahadurgarh

i)

At tap-off cum Despatch Terminal at Bahadurgarh

             

A 10” & 8” NB tap-off from existing Bahadurgarh terminal. Local & panel mounted instruments such as PT, TG & Pig Signalers, AV Valves Operation. Control Panel Control Room Building Scrapper Launcher Facility Metering Facility Chemical Dosing Facility LEL Detection System Cartridge Filter with PSV Ultrasonic Meters with Panel Mounted Flow Computers Quick Opening End Closure UPS SCADA & Telecom

ii)

Receiving Terminal at Tikrikalan

 

Scrapper Receiver Local & panel mounted instruments such as PT, TG & Pig Signalers, GOV/AV Valves Operation Control Panel Control Room Building LEL Detection System Pressure Control Valve with Bypass Pressure Regulators PCV Turbine Flow Meter Flow Computers TSV Meter Proving Facility UPS TR Unit for PCP system (A common impressed current type Cathodic Protection System has been considered for both new pipelines) SCADA & TELECOM

            4.5

Guarantee

4.5.1

The contractor shall guarantee the installation against any defects of workmanship and materials (supplied by the contractor) for a period 24 months after supply of CP material at site or 12 months after successful commissioning at site, which ever is earlier. Any damage or defects connected with the erection of materials, equipments of fittings supplied by the

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 109 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

contractor that may be undiscovered at the time of issue of the completion certificate, or may arise or come to light thereafter, shall be rectified or replaced by the contractor at his own expense as deemed necessary and as per the instruction of the Engineer-in-charge within the time limit specified by Engineer-in-charge. 5.5.2

The above guarantee shall be applicable for the quality of work executed as well as for the equipment/ cable/ fittings/ other materials etc supplied by the contractor.

4.6

Site Conditions The equipment offered and the installation shall be suitable for continuous operation under the following site conditions: Ambient temperature Max relative humidity Altitude Atmosphere

4.7

: : :

50°C (max.) 90% Less than 1000m above MSL : To withstand site condition

Power Supply Parameters

2.10.1 AC/ DC Operated Units AC Panel 5.0

SCOPE OF WORK

5.1

Cathodic Protection System

230 V AC ±10%, 1 Phase from UPS

a) Temporary Cathodic Protection System Design, detailed engineering, supply, installation, testing and commissioning of the temporary cathodic protection system using Mg/ Zn galvanic anodes to protect the external surface of 10’” & 8” NB and 15 Km long 3LPE coated petroleum product pipelines from dispatch terminal at Bahadurgarh to receiving terminal at Tikrikalan against corrosion for design life of minimum 1 years or till the commissioning of PCP system, whichever is later as per standard specification No. MEC/TS/05/21/016A for temporary cathodic protection system. Scope shall also include but not limited to the following for completion of jobs:a) Measurement of soil resistivity along the right of way of the main pipelines route as per specification for design & installation of anodes. b) Collection of additional data related to cathodic protection along the right of way of pipelines as per specifications. c)

The test stations for 10” OD pipeline need to be installed matching with the test station of 8” OD pipeline, for bonding purpose.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 110 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

d) New 10” & 8” NB dia pipelines are running parallel direct/resistance bonding connection shall be made between pipelines at the test stations along the pipeline route at an average interval 1Km and at additional locations wherever required. The size of cable for bonding shall be 1Cx25 sqmm. e) Direct/resistance bonding connection between 10”/8” pipeline shall be made in TLP of 10” dia pipeline & Connection to sacrificial anode shall be made in TLP of 8” dia pipeline. However each TLP of 10”/8” dia pipeline have facility of measurement of pipe to soil potential. f)

Supply, installation, testing & commissioning of one set of spark gap arrestor with 2 plate Zinc grounding cell of 20 kg net weight each across each insulating joint provided at dispatch terminal, receiving terminal etc as per P&ID / specification .

g) Supply, installation, testing & commissioning one set of polarisation cell with zinc anode at all high tension electrical power transmission line/equipments /railway tractions(all 66 KV & above) crossing or running parallel to the pipelines for grounding purpose as per specification. The rating shall depend upon anticipated fault current & ground bed resistance at the location of installation. However, the rating of polarisation cell (krick) shall not be less than 5 KA & number of 20 kg net weight zinc anode shall not be less than two. h) Supply & installation of Zinc Ribbon Anodes at 4-8 O’clock position in the interval of 2 metre (max.) on carrier pipes at all cased crossings i.e. railways/ roads etc. i)

Monitoring of the TCP system till commissioning of the permanent cathodic protection system.

j)

All civil/ structural works related to TCP system including supply of bricks, cement & steel etc. required for completion of the system.

b) Permanent Cathodic Protection System Survey, Design, detailed engineering, supply, packing, transportation to site, installation, testing and commissioning of the permanent cathodic protection system by impressed current method using MMO coated Titanium anodes to protect the external surface of 3LPE Coated, 10’” & 8” NB and 15 Km long petroleum product pipelines against corrosion for a service life of 35 years, as per Standard Specification No. MEC/TS/05/21/016B for permanent cathodic protection system. The scope shall include complete permanent Cathodic protection system, including carrying out the soil resistivity measurement for anode ground beds, design of anode ground beds considering size / rating of anode bed not less than the minimum requirements of the anode ground bed specified, Interference detection and mitigation, AC/DC interference on pipelines and CP System due to proximity of foreign AC/DC source, detection and mitigation of high induced voltage at pipelines due to proximity of HT line, close interval potential logging survey for entire length of 10” & 8” dia pipelines and additional surveys i.e. CAT, DCVG etc at selected locations which shall be decided from the abnormal areas of close interval potential logging survey results to identify coating defects/holiday, conducting pipelines line current & coating resistance test at

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 111 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

selected locations where current measurement test stations shall be installed, preparation of commissioning report and as built drawings etc. All work shall be carried out conforming to the Scope of work, Design Basis, Data Sheets, specifications & standards. Scope shall also include disconnection of TCP system which does not form part of PCP system. Equipments coming under new installed TCP system (TLP, Corrosion coupons, E/R probes, Zn/Mg ribbon anodes etc) if useful & required in PCP system, shall be used effectively in designing of PCP system. If any inadequacy present in these equipments, in such case all work associated with supply, installation, testing and commissioning shall be in scope of PCP contractor. The Scope shall also include but not limited to the following for completion of jobs:viii) Selection of plot (60mX5m Min.) for anode ground bed at receiving station Tikrikalan (15.0 km Chainage) at a distance of min. 100m from the pipelines. (If adequate protection is not achieved with one anode ground bed two parallel anode ground beds shall be considered for two lines). ix)

Carrying out the soil resistivity survey for design of anode ground bed at the selected location as mentioned above.

x)

Development of topo sheets which should be suitable for use in land acquisition at Stations.

xi)

Acquisition of land for anode ground bed, Anode Junction box, laying of cable and transferring the title of land in favour of HPCL at the selected locations mentioned above for 10”/8” dia pipelines.

xii)

Design of shallow/deepwell anode beds for construction at selected location as per national/ international standard & specification.

xiii) Common power source (TR unit) shall be considered for both new lines with two parallel anode ground beds if required. Positive header cable from the AJB of new anode ground bed shall be terminated to the Positive terminal of common CPTR unitt. Similarly Negative header cable from the CJB of the 10” line & 8” line shall be connected to the common Negative terminal of CPTR unit. So that separate drainage connections are made to each pipeline from the common CPTR unit at CP Station. [In addition to the separate drainage connections at CP Station stated above, direct/resistance bonding connections shall also be made between the two pipelines at the test stations along the pipeline route at an average interval 1Km and at additional locations where ever required to minimise interference between the two lines (Already mentioned in scope of TCP work)] xiv) Supply, installation, testing & commissioning of minimum ten numbers Mixed Metal Oxide Coated Titanium Hollow Tubular Anodes of 25mm dia. / 1000mm long size along with 1C x 10mm2 Copper XLPE/ PVC tail cable as per specification at the selected locations. Actual numbers of anode shall be finalised during the approval of design calculation submitted by the Contractor. Total ground bed resistance of PCP System shall be as per specifications.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 112 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

xv)

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Incase of deepwell anodebed, supply, installation, testing & commissioning of an anode string consisting of minimum ten numbers of Mixed Metal Oxide Coated Titanium Tubular Anodes with single dead weight of 25mm dia./ 1000mm long size alongwith 1C x 50mm2 Copper EPR/CSPE tail cable as per specification. Actual numbers of anodes shall be finalised after the approval of design calculation submitted by the Contractor. Total ground bed resistance of PCP System shall be as per Specification.

xvi) Disconnection of temporary cathodic protection system which does not form part of permanent cathodic protection system. xvii) Supply, installation, testing & commissioning of Computerized Test Stations (CTSU) for automatically monitoring and recording the pipe to soil potential, pipe current etc of the pipelines. Locations shall be decided during detailed engineering. xviii) Supply, laying, termination, Glanding and ferruling of all the cables of CP system, including all incoming power cable and outgoing CP cables of CPTR units. xix) The above mentioned location is tentative, actual numbers/Locations of CP stations & anode beds shall be finalized during the approval of design documents submitted by the Contractor. However PCP system shall be designed in such a manner that anode beds & TR/CPPSM units comes at receiving terminal. xx)

3 Nos. references cell each at the proposed locations for CP stations for the entire length of 10’” & 8” NB, 3LPE Coated, 15 Km long petroleum product pipelines. Two permanent reference cell connections at CPTR unit from the 10” line, one permanent reference cell connection from 8” line, so that common CPTR unit at CP Station can get feedback from both the 10” line & 8” line for control of CP System current.

xxi) Operating current of each CP Stations shall be shared by each anode ground bed (where 2 anode beds shall operate in parallel) according to their resistance and each 10” / 8” pipe line according to their coating conductance. Due to such current sharing the PSP level of any one of the pipelines may become higher than the other. To minimize this PSP level difference between 10” / 8” pipe line, the max current limit settings and the target PSP settings at each CPTR unit at CP Station need to be adjusted in such a manner so that entire length of both the pipeline is adequately protected without overprotecting any one of the pipelines. xxii) Supply including design, manufacturing, shop testing, inspection, packing, forwarding, delivery erection/ installation, civil/ structural support, earthing, testing & commissioning of 1(one) no. 25V/25A output rating AC/ DC operated automatic CP transformer rectifier unit at receiving terminal (Tikrikalan) confirming to standard specification No. MEC/TS/05/E9/082A, Data Sheet & Drawing. The TR Units at receiving terminal end shall be installed inside the control room. All the TR units shall have SCADA monitoring facility, current interruption facility with timer and commissioning spares as required. xxiii) Bonding in between existing pipelines running parallel or crossing as required.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 113 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

xxiv) Carrying out “ON/ OFF” PSP Survey, Close interval potential logging survey for the entire length of 10’” & 8” NB, 3LPE Coated, 15 Km long petroleum product pipelines. xxv) The contractor shall carry out interference detection and mitigation measures, AC/DC interference on pipelines and CP System due to proximity of foreign AC/DC source, detection and mitigation of high induced voltage at pipelines due to proximity of HT line, close interval potential logging survey for entire length of 10” & 8” dia pipeliness against DC interference due to proximity of foreign DC source & high induced voltage at pipelines due to proximity of HT line. The contractor shall do additional surveys i.e. CAT, DCVG etc at selected locations which shall be decided from the abnormal areas of close interval potential logging survey results to identify coating defects/holiday and implement mitigation measures for the CP system of the entire length of 10” & 8” dia , 3LPE coated, 15.0kM long petroleum product pipelines from Bahadurgarh to Tikrikalan. In case contractor on his own do not possess the adequate experience for the same, the contractor shall include the services of specialist agencies, (like PLE Germany,Vender Velde Holland, Nippon Japan, SSS India, IACS of UK or equivalent) for doing interference/additional surveys and implementing mitigation measures. Necessary measures shall be adopted to mitigate the stray current interference due to crossings of high tension line, electrified railway track, existing pipelines in the close vicinity etc. by providing sacrificial anodes, grounding cells, diodes etc. xxvi) Sacrificial type CP System needs to be installed at all river crossings for 35 years design life in addition to the ICCP system. xxvii) The TR/CPPSM units shall be provided with facilities for sending and receiving digital and analogue input/output signals for remote SCADA monitoring and controlling. xxviii) Supply and installation of the power supply cable from switch fuse unit/ MCC /PDB of OWNER’S Electrical substation to CPPSM/CPTR Units shall be CP CONTRACTOR’s scope of work. xxix) Monitoring & maintenance (as a whole) of PCP System of entire length of 10” & 8” dia , 3LPE coated, 15.0kM long petroleum product pipelines from Bahadurgarh to Tikrikalan for 3 months after final commissioning. Note:- For chainages refer Pipelines MEC/23LK/05/21/M/000/1021) 5.2

Schematic

Route

Diagram

(Drg

No.-

Other Miscellaneous Works i)

The job includes all civil works including supply of bricks, cements steel etc. connected with grouting of equipment to be installed, providing foundation for TR / CPPSM units, test stations, ALJB/ CJB & chain link fencing around each ground bed etc. The job includes repairing of all civil works damaged during installation of electrical and other facilities.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 114 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

ii)

Preparation of buried cable trenches including excavation, back filling, compacting, providing of brick protection by second-class bricks, spreading of fine river sand, including all supplies.

iii)

The job includes the engagement of the service of a specialist agency for doing interference survey & implementing mitigation measures against interference for CP System.

iv)

The scope of work under this contract shall be inclusive of breaking of walls and floors, and chipping of concrete foundations necessary for the installation of equipment, materials, and making good of the same. Minor modifications wherever required to be done in the owner free supplied equipments or devices to enable cable entry, termination, etc.

v)

Checking of all connections, i.e. power, control, earthing and testing and commissioning of all equipment erected and/or connected under this contract as per testing procedures and instructions of Engineer-in-Charge.

vi)

All electrical equipments are to be doubly earthed by connecting two earth wires from the frame of the equipment to be earth grid. The cable armours will be earthed thro’cable glands. The following shall be earthed:

vii)



All non-current carrying metallic parts of electrical equipments such as lighting and power panels, push button stations, cable trays etc.



Lighting fixtures shall be earthed through the extra core provided in the lighting cable/ conduit for this purpose. Supply and installation of all other accessories not specifically mentioned herein but nevertheless necessary for completion of job.

viii) Engineering and preparation of specifications and drawings for procurement & installation of CP System wherever applicable/required by Owner/ MECON and submit to Owner/ MECON for approval/comments. ix)

Correction and submission of all owner’s drawings for as-built status.

x)

Obtaining clearance for energising the complete electrical facilities covered under this tender and approval of installation/drawings from Govt. authority if required.

xi)

Test certificates, catalogues, vendor drawings, installation, operation and maintenance manuals for all equipment/materials in contractor’s scope of supply.

xii)

Co-ordination with other contractors.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 115 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

6.0

SCOPE OF SUPPLY

6.1

Owner’s Supply – NIL

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Supply, testing, Packing, Forwarding, Delivery, Installation and commissioning of all the equipment covered in this package are included in the scope of the contractor. No equipment will be free issued by the owner to the contractor. 6.2

Contractor’s scope of supply shall be as mentioned in Cl. No. 4.0 Scope of Work.

6.3

Bidder shall submit list of two year operational & maintenance spares along with offer and supply the same but not limited to the followingO&M CP Spares/ Tool / Tackles for CP system like Multimeter, Clamp meter, Portable reference cell, UT meter, Tool box Complete for each maintenance base etc.

6.4

O&M CP Spares for TR /CPPSM unit. 1. Contractor to note that the exact cable routing shall be decided at site based on actual site conditions. Exact cable quantities/sizes shall be based on actual measured route lengths at site by Contractor in coordination with Engineer-in-Charge/Client. Contractor shall ensure that there is no surplus or shortage of cables at site and procure cables accordingly. Contractor shall note that payment for supply of cables shall be made as per actual laid cables at site. 2. Contractor to note that all cabling (including supply & laying) & other electrics for the CP System shall be supplied along with the package and no separate payment shall be admissible for the same. Owner shall provide only single point power supply for the same.

7.0

STATUTORY APPROVAL OF WORKS The submission of application on behalf of the Owner to Govt. Authority/ Central Electricity Authority, if required along with copies of required certificates complete in all respects, shall be done by the contractor well ahead of time so that the actual commissioning of are not delayed for want of approval from authority. The actual inspection of work by the Govt. inspector shall be arranged by the Contractor and necessary coordination and liaison work in this respect shall be the responsibility of the contractor. However any fee paid to the Govt. Authority in this regard shall be reimbursed by the Owner on submission of bills with documentary evidence. The Inspection and acceptance of the work as above shall not absolve the Contractor from any of responsibilities under this contract.

8.0

INSPECTION, TESTING & COMMISSIONING All the equipment installed by the contractor shall be tested and commissioned, as required and no separate payments shall be made unless otherwise specified in the schedule of rates. Contractor shall inspect carefully all equipments before receiving them from owner for installation purposes. Any damage or defect noticed shall be brought to the notice of the Engineer-in-charge.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 116 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

The following equipment/items shall be tested and inspected by MECON/ owner at manufacturer’s works before dispatch. Test certificates duly signed by MECON/ Owner shall be issued by the contractor as part of the final document. -

Hazardous area equipment CP TR/ CPPSM units

Any work not conforming to the execution drawings, specifications or codes shall be rejected forthwith and the contractor shall carry out the rectification at his own cost. The contractor shall carry out all the tests as enumerated in the technical specification and technical documents which may be furnished to his during performance of the work. Before the electrical system is made live, the electrical contractor shall carry out suitable tests to establish to the satisfaction of Engineer-in-charge/ Owner that the installation of equipment, wiring and connections have been correctly done and are in good working condition and that it will operate as intended. All tests shall be conducted in the presence of Owner/Engineer-in-charge or his authorized representative unless he waives this requirement in writing. All testing equipment necessary to carry out the test shall be arranged by the contractor. The tests shall be recorded on approved proforma and certified records of the tests shall be submitted to Owner/ Engineer-in-charge. Test proforma for testing and commissioning shall be used for testing and commissioning of various equipment, cables, earthing system and lighting system. These will be issued to the successful contractor after the award or work. 9.0 9.1

DRAWINGS, STANDARD SPECIFICATION AND INSTALLATION STANDARDS (Enclosed with PJS) The drawings accompanying the tender document are indicative of the nature of work and issued for tendering purposes only. Construction shall be as per drawings/specifications issued/ approved by the Owner/ MECON during the course of execution of work. After the job completion, contractor shall prepare ‘AS-BUILT’ drawings, final certified as built drawings vendor drawings for bought out equipments shall be submitted by the contractor to owner in bound volume with one set of reproducible original sepia plus five sets of prints.

9.2

Please refer Vol-II of II enclosed with this tender document for the list of standard specifications, installation drawings etc. The equipments/ materials to be supplied by the contractor shall conform to the requirements of the applicable standard specifications. Also the installation of various material/ equipment shall also conform to the standard specification. The purpose of the pipeline alignment drawings, P&IDs & Plot Plan drawings enclosed

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 117 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

MECON LIMITED

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

with the tender document Vol-II of II is to enable the tenderer to make an offer in line with the requirements of the Owner. These are indicative of the nature of work and issued for tendering purposes only. The bidders, however, shall visit the site before bidding for proper information of site conditions. Construction shall be as per drawings/ specifications issued/ approved by the Owner/ Consultant during the course of execution of work. 9.3

A)

1.0 2.0 3.0 4.0

Specification for Temporary Cathodic Protection System Specification for Permanent Cathodic Protection System Specification for Corrosion Survey Specification for Cathodic Protection TR Units B)

1.0 2.0

SPECIFICATION

DATA SHEETS & QAP

Data- sheet for Cathodic Protection TR Units Quality Assurance Plan

C)

MEC/TS/05/21/016A MEC/TS/05/21/016B MEC/TS/05/21/016C MEC/TS/05/E9/082A

MEC/DS/05/E9/082A MEC/05/E9/23L4/082

STANDARD DRAWINGS 1.0

PREPACKED ZINC ANDOE

MEC/SD/05/21/16/01

2.0

MG RIBBON ANODE FOR GROUNDING

MEC/SD/05/21/16/03

3.0

DETAILS OF TEST STATION FOR TCP

MEC/SD/05/21/16/04

4.0

TEST STATION CONNECTION SCHEMES

MEC/SD/05/21/16/05

5.0

ZINC RIBBON ANODE FOR CASED CROSSINGS WITH COATED CASINGS

MEC/SD/05/21/16/07

6.0

PIPELINE GROUNDING THROUGH POLARISATION CELL AND GALVANIC ANODES

MEC/SD/05/21/16/08

7.0

DETAILS OF ZINC GROUNDING CELL

MEC/SD/05/21/16/09

8.0

PERMANENT COPPER – COPPER SULPHATE REFERENCE CELL & INSTALLATION DETAILS

MEC/SD/05/21/16/10

9.0

SHALLOW ANODE GROUND BED (PCP)

MEC/SD/05/21/16/11

10.0

ANODE LEAD JUNCTION BOX

MEC/SD/05/21/16/12

11.0

CASING PIPE DETAILS

MEC/SD/05/21/16/13

12.0

TEST STATION FOR POLARIZATION CELL

MEC/SD/05/21/16/14

13.0

DETAILS OF THERMIT WELD FOR CABLE TO PIPE JOINT

MEC/SD/05/21/16/18

14.0

EARTH ELECTRODE IN TEST PIT

MEC/SD/05/E9/02/01

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 118 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

10.0

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

MAKE OF MATERIAL/BOUGHT OUT ITEMS An Appendix-I of approved vendors for various major items is enclosed with this tender specification. The bidder shall consider such names only as indicated in the aforesaid list and clearly indicate in the bid the name(s) as selected against these items. For any other item not covered in the list enclosed with this tender document, prior approval shall be obtained by the contractor for its make/ supplier’s name.

11.0

DOCUMENTATION

11.1

The following documents shall be submitted along with the offer: g) h) i) j) k) l)

11.2

The following drawings (in three sets) & documents shall be submitted for approval within 3 weeks of award of contract. n) o) p) q) r) s) t) u) v) w) x) y) z)

11.3

Filled up data sheet. QAP Design calculations of TCP & PCP system List of two years operation and maintenance spare. Approx. dimensions of the system Catalogues for TR/CPPSM unit, MMO Titanium Anode, reference cell etc.

Soil survey report with information of terrain along the pipeline Detailed design calculations of TCP & PCP system, formulae used Procedure for AC & DC interference detection & mitigation. Procedure for CP system installation, field testing, pre-commissioning & commissioning. Procedure for post commissioning surveys. Detailed design of Anode ground bed, typical lay out drawings for Anode bed connection & installation. Equipment layout, Cable layout & schedule. AJB, TLP, CJB, permanent Cu-CusO4 & junction box installation & erection details drawings Incorporation of Anode bed, Polarisation cell, surge arrester, TLP, AJB, CJB, Junction boxes & other relevant feature in PCP system design in Alignment sheet & Plot plan. G.A. of TR/CPPSM unit. Schematic Bill of Material Wiring diagram for reference.

After the job completion, contractor shall prepare AS-BUILT drawings/data sheets and documents, submit catalogues/manuals (O&M) of major brought out items. Final certified as built drawings, documents and manuals etc shall be submitted by the contractor to owner in bound volume with one set in soft copy (CD) plus five sets of prints. Other drawings and documents shall be submitted by contractor along with AS-BUILT Drawings/Datasheets-

d) Original deed for Anode Bed shall be handed over to M/s HPCL.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 119 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

e) Test documents & drawings for bought out items. f) Detailed commissioning report of pipeline.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 120 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

APPENDIX-I Sheet 1 of 2 APPENDIX-I (LIST OF SUPPLIER/S OF MAJOR BOUGHT OUT ITEMS) 1)

CABLES i) ii) iii) iv) v) vi) vii) viii) ix) x) xi) xii) xiii) xiv) xv) xvi) xvii) xviii) xix) xx)

2)

JUNCTION BOX i) ii) iii) iv) v) vi) vii)

3)

Brooks Nicco Biren CMI Delton KEI Reliance Satellite Cables Evershine Torrent Cables Universal Victor Indian Aluminimum Cables Associated Flexible & Wires Asain Fort Gloster Finolex Industrial Rediant NITCO

Exprotecta, Beroad Baliga Flexpro FFLP Control Gears Sterling Sudhir Electrical Equipment Corporation

SACRIICIAL ANODES i) ii) iii) iv) v)

Scientific Metals Engineers Pvt. Ltd., Karaikudi PSL Holding Pvt. Ltd., Mumbai Cathodic Controls, Bangalore BHEL, Bhopal Electro Protection Services, India

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 121 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

APPENDIX-I Sheet 2 of 2 4)

Portable Reference Cell

:

5)

MC Miller (USA) Permanent Reference Cell : Corrtech, Consultech, MC Miller, CCS, CPES, CTS

6)

AC/ DC, DC/DC Operated Automatic Transformer Rectifier Unit

:

M/s Canara Electric, M/s Kriston systems

7)

Thermit Weld

:

M/s Erico, USA, M/s Cad Weld

8)

Digital Multimeter

:

MOTWANE, MODEL DM-375 or Equivalent

9)

CTSU

:

M/s Kriston systems

10)

ER Probes

:

M/s Metricorr, Denmark

11)

Anode (MMO Type)

:

1) Titanor Component Ltd., Goa, India 2) Denora Permelic S.P.A (Italy) Oronzio De Nora S.A. Ingano, Switzerland 3) CER Anode Technologies International USA 4) ACTEL, UK 5) ELTECH System Corporation, Texas – 77478 6) MAGNETO-CHEMIE, Netherlands

12)

Backup Agency for doing CIPL / interference survey

:

1) 2) 3) 4)

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

PLE Germany Vendor Velde Nippon Japan Balslev, Denmark

Page 122 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Annexure-V to Particular Job Specification (FIRE FIGHTING WORKS)

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 123 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

1.0

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

GENERAL PROJECT INFORMATION M/s Hindustan Petroleum Corporation Limited propose to lay 2 parallel pipeline from proposed dispatch station inside existing Bahadurgarh Terminal in Haryana. Three petroleum products namely ULSHSD, ULMS & SKO from existing storage tank (some future tanks also considered) will be transported through these pipelines. The total proposed pipeline is approx. 30Km long, in which 8” x 15Km is proposed for ULMS & 10” x 15Km is proposed for ULSHSD / SKO transportation. The 8” x 15Km will transport 250 m3/hr (6 hrs pumping per day) of ULMS & 10” x 15 Km will transport 350 m3/hr (6hrs pumping per day) of ULSHSD / SKO as per requirement from Bahadurgarh Dispatch (Near Delhi Border) Terminal to proposed Tikrikalan receipt station. The following main facilities are envisaged: a) b) c)

Pumping cum Dispatch station at Bahadurgarh Cross country pipeline between Bahadurgarh dispatch station to Tikrikalan receipt station. Receipt at Tikrikalan

2.0

Intent of Specification

2.1

The intent of the specification is to cover the design, engineering, manufacture / fabrication, procurement, packing, forwarding to site, unloading at site, receipt, storing, erection, testing, shop painting, commissioning and guaranteed performance of the following and as outlined in various chapters of the technical specification: a) b) c) d) e) f)

Fire Hydrant System medium velocity water spray System Automatic Fire detection cum alarm system Automatic clean agent fire suppression system Portable Extinguishers Fire Fighting Accessories

The contractor shall include all supports, inserts etc. required for the above system, instrumentation & electrics of the system, valves and all necessary operating platforms and ladders, if required, for the safety and maintenance of the equipment and the system as a whole. 2. 2

The delivery of the items shall be made at site of M/s HPCL at Bahadurgarh / Tikrikalan.

2.3

Any additional item/ component that are not specifically mentioned in the specification but are required to make the system/ equipment complete in all respects for safe operation and guaranteed performance shall be under the scope of this specification.

2.4

The contractor shall furnish the names of the sub-suppliers, if any, along with the units / quantity intended to be procured from them. List of approved makes of materials is enclosed in the tender document. Only those vendors shall be acceptable for whom the names are

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 124 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

specified against the items. For any other item not mentioned in the list, the successful party will take prior approval before placement of order. 2.5

The fire fighting measures are of paramount importance to safeguard the material, product / information stored manpower and property from the fire hazards. Fire may occur inside the plot premises consisting of general technological unit areas, metering & filtration area, pump area, buildings (control room, MCC room etc.) as per the layout drawing at any location or unmanned rooms due to any mishap or sudden abnormal rise of temperature due to abnormal operating condition. Water has been considered as the general agent for fire extinguishments / cooling at the proposed installations. This water shall be made to reach at all the strategic points of the installations through a closed pressurized piping network.

2.6

The system covers the basic scheme to be implemented to cater fire hazard in the entire area, as per OISD: 117, OISD: 189, OISD: 214 TAC / NFPA, which suggests the following systems / facilities to be installed to provide state of the art fire protection facilities to the area: a) b) c) d) e) f)

2.7

Provision shall be made for tripping off the ventilation and A/C system and power supply to the fire affected zone automatically along with the discharge of the extinguishing media (if any) after getting the confirm fire signal. However, in general the automatic fire extinguishing system shall cover: • • • • •

2.8

Fire Water System consisting of hydrants, monitors, hose boxes containing fire hoses with standard accessories Medium Velocity Water Spray System for pumps, metering & filtration area, scrapper area Automatic Fire detection cum alarm system Automatic clean agent fire suppression system Portable Extinguishers Fire Fighting Accessories

General technological unit areas Filtration and Metering area control room and MCC Room Generators Pumps Technological Part Depending upon the nature of the units to be protected from fire, following types of fire protection systems viz. Fire hydrant and monitor system, Automatic medium velocity water spray system, Fire suppression system clean agent based, automatic fire detection-cumalarm system and portable fire extinguishers shall be provided. However, automatic fire detection-cum-alarm system shall only be provided in all the electrical control rooms, MCC rooms, instrumentation rooms, switchgear rooms/substations/and all such electrical premises. Location wise the proposed fire fighting facilities are listed below:

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 125 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

S.N

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

Facility Fire Alarm & Detection System AC Duct Mounted detector MWS (Medium Velocity Water Spray System) Fire Suppression system (Clean Agent based) Hydrant & Monitor System - Internal - External Manual Call Point - Indoor - Outdoor Siren Portable Extinguisher DCP –

Area - All control rooms (Above & below false ceiling) - All switch gear/MCC rooms, UPS rooms, PLC rooms - Battery- Battery charger rooms - All areas protected by fixed extinguishing system One in each room / partition area of control room. Filtration and Metering Area, Pump House, Scrapper Area Main control room (above and below false ceiling) including annexe rooms.

CO2 Water Foam Mobile type

3.0

MECON LIMITED

All the units & areas as per battery limit. All the units & areas as per battery limit. All the units & areas as per battery limit. All the units & areas as per battery limit. One New Chimney All the units & areas as per battery limit. Process bays / area, MCC rooms,etc. All electrical premises. DG Yard Oil facilities. a) Minimum one number of DCP type for each floor / process bays and as per norms. b) Minimum one number of CO2 type for each floor of the sub-station, main control room etc. as per norms. c) Minimum one number of foam type for oil installation and oil storage tanks as per norms.

Meteorological data of site The fire protection systems shall be designed taking into account the meteorological data prevailing at the project site as mentioned below. Temperature Minimum Maximum

-

5o C 45o C

Relative Humidity Maximum Rainfall

-

50% 25mm

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 126 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Wind Velocity Environment -

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Maximum – 100 Km/Hr Dry & Hot (Desert Condition)

4.0

SCOPE OF WORK AND SERVICES

4.1

General The scope of work of the Tenderer shall include design, engineering, supply, fabrication/manufacture, assembly, inspection, shop testing, piping, transportation, receipt at site storage, installation, painting, testing and commissioning, obtaining statutory approval and demonstration of integrated performance of all equipment required for fire protection system which broadly includes fire detection cum alarm system, clean agent based fire suppression system, piping, valves, cylinders, extinguishers, accessories and other hand appliances at various locations (detail of which mentioned elsewhere in the specification) for the terminal as per the indicative list of items mentioned alongwith tentative quantities. The tenderer shall furnish the list of commissioning and two (2) years maintenance and operational spares in the offer. Complete details of all spare parts, their relation to the equipment and their itemised prices shall be furnished in the tender. Prices shall be mentioned in the price envelope and item wise list of spares without price shall be furnished in the unpriced bid.

4.2

The scope of work and services to be rendered by the Tenderer for installation of fire fighting system shall include but shall not be limited to the following activities.

i/

Design, engineering, manufacture/fabrication, assembly, shop testing and shop painting, sequential packing, delivery FOR site, unloading, unpacking, storage at site, site handling, preparation of erection drawings, erection as per approved drawings, site testing, painting, commissioning and fulfillment of guarantee of fire protection systems, sub-systems and integrated systems as described above and also covered under this tendering specification.

ii/

Miscellaneous materials and services, if not otherwise specifically asked for, shall include the following :

-

Constructing site office, covered store, open storage at designated place including supply of construction material and removal of the same on completion of work.

-

Site cleaning, removal and disposal of debris, maintaining clean condition in and around the working place and as instructed by authorised representative of MECON / Owner.

-

Distribution of electric power supply for erection work through licensed electrical contractor / licensed electrician. Construction power shall be made available by Owner at one place.

-

Supply, installation, testing, commissioning of hydrant sprinklers, water spray system, fire fighting appliances, portable extinguishers and all associated facilities.

-

All piping integral to or between any equipment furnished under this specification, except as otherwise specified.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 127 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

-

All necessary isolation valves fitting at the tapping points and branch pipes.

-

All erection accessories, consumables and miscellaneous materials, though not specifically indicated in this specification, but actually required for completing the job in all respects.

-

All necessary connections for hook-up with Purchaser's pipe network.

-

Erection, testing and commissioning of materials and system as a whole.

-

Initial fill of gas and other fire extinguishing media.

-

All necessary fixtures, supports.

iii/

To obtain No Objection Certificate from the local statutory fire authorities / TAC for the complete system.

5.0

Brief Functional Description The main intentions of provision of first aid and inbuilt fire fighting systems are to extinguish the fire at its inception or to control its spread and to assist the fire department in taking required action and thereby reducing the loss suffered as a result of fire. The Fire Water layout drawing no. MEC/23LK/05/21/M/FF/001, 002, 003 & 004 of the terminal is enclosed for ready reference. The fire protection system envisaged for the plant calls for early detection of fire and quenching the same by various systems envisaged besides giving out an audio visual alarm. The first aid fire fighting arrangements cover the provision of portable fire extinguishers, etc. as per the requirement of OISD: 189 and TAC.

5.1

Hydrant Service A well-designed Hydrant system is the backbone of entire fire fighting system as it fights fire of all classes of risks. The entire dispatch & receiving terminal will be covered with a water based fire hydrant network. For the purpose of hydrant system design, the terminals have been considered as medium Hazard occupancy as per TAC classification. The designed main shall consist of MS coated /DI pipes, 200 mm dia. ring mains. Distribution mains form ring around each unit, which is connected to the ring main running in the vicinity, which mainly consist of double outlet landing valves, monitors, fixed water spray system etc. The work shall be carried out as per OISD: 189. The fire water network lines shall be continuously kept pressurized at 8.0 kg/cm2(g) (at the hydraulically remotest point of application). Activation of hydrants / monitors / water spray system will send a signal in the control room. Distribution mains form ring around each new proposed area, which is connected to the ring main running in the vicinity. The network will be laid generally above ground. Wherever it is laid underground, it should be laid at an average depth of 1m below ground level and 1.2M (Min.) below the ground level at road crossings. All such underground pipes shall be provided with suitable corrosion protection as per IS: 10221. Each area is

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 128 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

being covered with adequate numbers of fire hydrants and water monitors. The fire protection system will also have hose reels, hose boxes, isolation valves, flanges, fittings along with complete electrical and instrumentation work etc. All double headed hydrants, monitors and hose reels shall be provided with a cut-off gate valve on tapping (stand post) from main fire water header with ISI / TAC approval. Hydrants and monitor connections shall be through 4” line. Double outlet hydrant valves shall be laid above ground at a height of 1.2M. At least 10% of all welded joints shall be radiographically tested and half of radiographed joints shall be field joints. Hose boxes with all accessories shall be provided at locations in line with TAC guidelines and construction of hose box shall be made as per specifications given in OISD-115. Hose boxes shall be provided at every alternate hydrant in the network. Each hose box shall consist of two hoses of 63mm dia. 15m long RRL each with end couplings, 2 nos. jet nozzles with branch pipe or two universal branch pipe as per IS: 903. Hoses shall confirm to IS: 636 type-B. Hose reels shall be considered as first aid fire contingency at strategic locations / units like control room and administrative building, non plant rooms etc. Hose reels shall be located 40m apart and shall cover all parts of the buildings in ground floor and upper floors. Hose reels shall be floor-mounted type and they shall have water connection from hydrant network. Above ground fire water pipes shall be painted fire red confirming to shade no. 536 of IS:5. All fire water piping shall be hydro tested to a pressure of 18 Kg/cm2. Adequate nos. of isolation valves in the fire water network shall be provided to ensure easy maintenance at the affected part of the network and at the same time uninterrupted water supply to the rest of the network for fire fighting remains available. Complete fire proofing of equipments in unit shall be carried out as per OISD:164. 5.2

Automatic Water Spray System A deluge type water spray network shall be designed in accordance with NFPA 15 and API 2030.This system shall be located over the equipment areas and designed to provide water at the net rate as specified. Medium Velocity Water Spray system has been envisaged for main & booster pump house (2 x 7m x 20m), metering area (8m x 2.5m), filtration area (8m x 3m) at dispatch terminal, Bahadurgarh and metering & filtration area (15m x 40m), scrapper area (23m x 15m) at receiving terminal, Tikrikalan to provide cooling and / or exposure protection to such type of risks where extinguishment is always not possible. 6” Φ tapping shall be taken from the ring mains exclusively for the spray system. The system comprises of piping, valves, deluge valves, sprinkler based detection system or some other suitable alternative detection system to be suggested by contractor, sprayers and other accessories. The temperature rating of the detector sprinkler shall be at least 30`C above the highest ambient temperature at the site of

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 129 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

installation. In case of increase in temperature in and around the area under coverage, the sprinkler bulbs breaks and the pressure is released from priming chamber of deluge valve faster than it is supplied through the restricted priming line. Therefore clapper moves and allows the inlet water supply to flow through the outlet into the system and associated alarm device and water is sprayed through sprayers to combat fire. The mode of actuation of Deluge Valve shall be hydraulic type. The density of water application by sprayers shall not be less than 10.2 LPM / M2. For the effective protection of the areas, the risk area shall be divided into several zones of width not less than 6M. Each zone shall be controlled by an individual Deluge Valve and flow shall not be more than 13,500 LPM. Each zone shall be so designed that the pressure at the hydraulically most un-favorable sprayer / sprinkler is not less than 1.4 bars and that the most favorable sprayer / sprinkler is not more than 3.5 bars and that the velocity in distribution pipes shall not exceed 5 m/sec. The detection network piping shall be similar to the sprayer network viz. there shall be same number of detectors as there are number of sprayers. Systems shall comprise of network of pipelines with distribution control, units, open spray nozzles- stainless steel material (capable of spraying water with medium velocity), automatic fire detection cum alarm facility, deluge valves, instrumentation (pressure switches, limit switches, pressure gauges) isolation valve & deluge valve housing / room. Water required for the system shall be drawn from existing fire network. Design criteria for medium velocity spray system (MVWS) The medium velocity water spray shall be designed as per the stipulation of TAC rules on the subject as well as NFPA’s guidelines. Following salient parameters shall be followed for the design of the system. Water application rate for conveyors – 10.2 lpm / m2 of the exposed surface area. The system shall be so hydraulically designed that the pressure at the hydraulically remotest sprayer shall satisfy the following conditions: The protected area shall be divided into several zones, each of which shall fed by individual deluge valve. In event of fire water shall be sprayed on the zone concerned (i.e. zone under fire) along with preceding and succeeding zones. Distribution of sprayers: Sprayers shall be providing to spray water on both the top side and bottom side of the process area. Spacing between sprayers shall not be more than 4m. The sprayers shall be installed in rows and spaced at not more than 3 m from each other. Provision for manual operation of the system shall also be made to operate the system in case of failure of the automatic mode.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 130 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

For the protection of deluge valves from mechanical damage and atmospheric conditions civil/structural rooms shall be provided. Standard fence and door shall be provided in addition to illumination facility. 5.3

Automatic Fire Detection-Cum-Alarm System: Manual Push Button Type Fire Alarm System Automatic fire detection-cum-alarm system shall be provided for all the electrical premises like switchgear room, control room & MCC room etc. In addition to detection system, manual push button fire alarm system (manual call points) shall be provided for all the premises / bays within the scope of the Tenderer. Provision shall also be kept by the Tenderer in the control panel to repeat the fire signal in the existing fire control room. For this repeater panel shall be installed in the fire station. Cablings / connection from main fire alarm panel to repeater panels are included in Tenderer’s scope of work. These areas shall be protected from Fire using State-of-the-art Automatic Smoke/ Heat Detection/ Alarm & Fire Control mechanism using Code of Practices approved by agencies such as Bureau of Indian Standards (BIS), British Standards Institute (BSI) or National Fire Protection Association (NFPA). Relevant certificate of approval shall be enclosed. The alarms need to be monitored on a 24 x 7 basis & logged for providing reports. The Fire system shall deploy High Sensitivity Smoke/ Heat Detectors (HSSD) and/ or Very Early Smoke Detection Appliance (VESDA) to allow swift detection of heat and/or smoke. The fire alarm should be designed to cut power to air-conditioning system. Second alarm should cut all the power supply to the data centre and the fire suppression system should be triggered off after a pre-set time interval. The fire detection & alarm system shall comprise of the following items / equipments: 

Fire Alarm Panels consisting of: Central Fire Alarm Panel with Mimic / Central Processing Unit Zonal Fire Alarm Panel Repeat Alarm Panel / Annunciation Panel



Automatic Fire Detectors and Accessories comprising of: -

  

Heat Detectors Ionisation Type Smoke Detectors Photo Electric / Optical Type Smoke Detector UV Flame Detectors IR Detectors Linear Beam Detectors

Heat Sensing Cables Manual Break Glass Boxes / Manual Call Points (MCP) Response Indicators

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 131 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

    

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Exit Signs Hooters Flashing Lights Clean Agent / CO2 Release And Inhibit Switches Any other item(s) required for the completeness of the system

Apart from the various signal and control related to fire detection following signal / facilities and control from each of the deluge valve pertaining to medium velocity water spray and high velocity water spray system shall also be required on the main fire alarm control panel. Following signals are required on the main fire- alarm control panel. 1. 2. 3.

Alarm from DV to know that it is operated ON/OFF command to solenoid operated valve at water line 24V DC power shall be provided for solenoid valves from the FDA system.

Signal and control shall also be provided on main fire alarm control panel from gas based fire extinguishing system. 5.4

Clean Agent Fire Suppression System Fire in strategically important places like computer rooms, control rooms, switch gear rooms etc. is a serious hazard to highly precious and irretrievable items and properties. Occurrence of fire besides leading to personnel injuries and property damage also leads to loss of productivity and precious time. The primary cause of fire may be due to short circuit / overheating of certain components somewhere in the areas. Since most of the areas are unmanned and completely closed, fire inside is not visible and accessible from outside till it becomes too big, dangerous and unmanageable. Fire suppression with conventional water-based systems such as hydrant or sprinkler system can damage the assets permanently. Therefore for these costly & critical areas, the Fire Protection System envisaged calls for early detection of fire and quenching the same by flooding the area with gas based fire suppression system besides giving out an audio visual alarm. The design shall be strictly as per NFPA standard NFPA 2001. The suppression system shall provide for high-speed release of Gas based on the concept of total Flooding protection for enclosed areas. A Uniform extinguishing concentration shall be as applicable and approved by the manufacturer/NFPA 2001/UL/LPCB/ULC of the gases for 70 deg F, or higher as recommended by the system / agent manufacturer. The system discharge time shall be 10 seconds or less, in accordance with NFPA standard 2001. The Fire Suppression System shall include a detection and control system provision for both pre-alarm and automatic agent release. The detection and control system that shall be used to trigger the Fire suppression shall

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 132 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

employ cross zoning of Laser and Multi-criteria smoke detectors. A single detector in one zone activated, shall cause in alarm signal to be generated. Another detector in the second zone activated, shall generate a pre-discharge signal and start the pre-discharge condition. The discharge nozzles shall be located in the protected volume in compliance to the limitation with regard to the spacing, floor and ceiling covering etc. The nozzle locations shall be such that the uniform design concentration will be established in all parts of the protected volumes. The final number of the discharge nozzles shall be according to the OEM’s patented and certified software, which shall also be certifiers such as UL / FM/LPCB/ULC. The Gas shall be stored in seamless storage containers complying with the SMPV Rules set out by Chief Controller of Explosives, Nagpur, India. The Bidder shall be required to produce a NOC for the Chief Controller of Explosives, Nagpur for the storage containers against the cylinder identification numbers punched on them. Welded cylinders for agent storage will not be acceptable The Gas shall be discharged through the operation of an Electric (solenoid) operated device or pneumatically operated device, which releases the agent through the pneumatic operated pressure valve. Systems that employ explosive or pyrotechnic devices for the discharge shall not be permitted. The Gas discharge shall be activated by an output directly from the Gas Release control panel, which will activate the solenoid valve. The Gas agent is stored in the container as a liquid. 5.5

Portable Fire Extinguishers In order to combat any occurrence of fire in any corner of the premises/area, adequate number of first aid portable and heavy-duty trolley mounted fire extinguishers shall be provided. Selection of the fire extinguishers shall be done depending upon the hazard, equipment to be protected, etc. Selection of fire extinguishers shall be done as per latest BIS2190 and as summerised in the table. However, all the computer/automation/PLC/microprocessor rooms shall be provided with CO2 type fire extinguishers (both portable and trolley mounted type). The fire extinguishers selected for each location will be based on the fire hazard class present in that area. Class

Combustible Hazard

Extinguisher Type

A

Ordinary combustibles such as wood, cloth, paper, rubber, plastics etc.

Water, Dry Powder

B

Flammable liquids, oils, greases, oil based paints, lacquers and flammable gases Electrical equipments where it is dangerous to use a conductive medium.

CO2, Dry Powder

C

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Dry Powder,CO2

Page 133 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

All the extinguishers shall conform to relevant IS and also bear ISI marking on their body. All the extinguishers shall be supplied with mountings, accessories and initial fill. The extinguishers supplied shall be of reputed make having approval of the Purchaser. Relevant BIS and TAC approval certificate for all the extinguishers shall be furnished. In addition to the above certificates, a certificate from Chief Inspector of Explosives shall be furnished for carbon dioxide type fire extinguishers. All the portable extinguishers shall be installed along the column/walls near entry/exit/suitable locations and at a. height of approx. 1200 mm from the finished floor level and also in accordance with the requirements laid down in OISD: 189 & 214. The design ,construction and testing of all types of fire extinguishers shall be specified in accordance with recognized standards as mentioned below. Carbon-dioxide type ( 4.5 & 22.5 Kg. Cap.) : Dry chemical powder ( 5.0 & 22.5 Kg Cap.) : Mechanical foam type- AFFF ( 9.0 & 50.0 Ltr. ): Water type (gas cartridge) :

IS2878: 1986,Reaffirmed 1996 IS2171: 1985,Reaffirmed 1995 IS10204: 1989,Reaffirmed 1995 IS940: 1989,Reaffirmed 1995

All types of fire extinguishers shall ,as far as possible, have a standard & simple method of operation. Portable fire extinguisher sizes will be selected as small as practical to be effective and for ease of operator deployment. Co2 extinguisher sizes will be determined to ensure that leakage or accidental discharge will not cause a hazardous CO2 concentration. Dry powder portable and wheeled fir extinguishers shall use potassium based agents and be compatible with AFFF. Portable extinguishers located in exposed and naturally ventilated locations shall be stored in suitable weather proof cabinets as protection from the effects of wind and rain. Trolley mounted dry powder extinguishers shall be provided in addition to portable extinguishers for protection to all areas where primary risk is from a liquid hydrocarbon fire. 6.0

TECHNICAL SPECIFICATION FOR PIPES, VALVES, SLUICE GATES & FITTINGS

6.1

T.S. for Pipes for hydrant system Pipes and pipe fittings in general shall comply with the requirements of BIS codes and TAC norm.The pipes shall be manufactured/supplied as specified below: i)

Upto 150 mm nominal size

-

M.S ERW Black pipes conforming to IS-1239- 1984 Part-I (heavy grade) With Plain ends.

ii)

200 mm to 400 mm size

-

M.S. ERW Pipes conforming to IS-3589 -1973 but thickness as specified below

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 134 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Nominal Dia DN 200 mm DN 250 mm DN 300 mm DN 350 mm DN 400 mm 6.2

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

O.D X Thickness in mm : : : : :

219.1 x 6.35 273.0 x 7.14 323.9 x 7.14 355.6 x 7.14 406.4 x 7.14

T.S. for Pipes and valves for Spray (HVWS & MVWS) system The material of construction and manufacturing standard of pipes, fittings, valves, fasteners, gaskets, etc. shall be as described in table-1 below:-

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 135 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Table-1 Nominal pressure (PN) - 10 Kg/Cm2 Test Pressure (PT) - 15 Kg/Cm2 S. No. 1.

Items Pipe

Nominal dia.(mm) 65 and below 80 100 to 150

IS-1239 (Part-1) - '90 Heavy, IS-1239 (Part-1) - '90 Heavy, IS-1239 (Part-1) - '90 Heavy,

200 to 250

IS-3589 Gr.410 ERW pipe commercial quality or equivalent. Thickness as specified.

250 and above 2.

Pipe fittings

2.1

Screwed fittings

2.2

Fabricated fittings

Specification

A 234 Gr. IS-1239/3589/2062 65 & below

IS-1239 (Part-1) - 90 Galvanised

Bends

150 and above

Mitred bends with radius 1.5 DN from black pipe.

Tees/Crosses

150 and above

Fabricated from black pipes by smithing.

Reducers

150 and above

Fabricated from black pipes by taper cutting and welding.

3.

Bolting

All sizes

IS – 1367

4.

Gaskets

All sizes

Sheets rubber to IS-635-`79 type-A, 3 mm thick compressed Asbestos to IS-2712-`79

5.

Flanges

All sizes

Slip on flanges to IS-6392 - `71 machined from Carbon Steel plates to IS-2002-`92 Gd. 2 with bore to suit pipe O.D.

Fittings shall be supplied as per IS:1239-1992 Part II for pipes upto 150 mm dia and shall be fabricated from pipes for dia 200 mm and above. 6.3

Technical specification for valves: The valves & sluice gates shall be designed, manufactured and tested as per relevant Indian Standards or as per other International standards acceptable to the Purchaser and will be suitable for the duty conditions specified below. All underground valves will be provided with valve chambers with RCC covers. The size of chambers shall be suitable for easy maintenance of the valve. Complete civil work for this is in the contractor's scope.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 136 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Table-2 S. No. 1.

Items Isolation

Nominal dia.(mm) Below 50

50 to 300

2. 6.4

Throttling

50 and below

Specification Forged Carbon steel gate valve, screwed as per API – 602 standard, class 800 # ASTM A-105, trim 13% Cr, Bolt/Nut – B7/2H, Socket end threading as per ANSI B.16.11 Gasket SPW S.S. 304 with CAF Hand Wheel - Cast steel Cast Carbon Steel flanged gate valve as per standard API-600 class 150 # , Body & bonnet material ASTM A 216 Gr. WCB, Trim 13% Cr S.S, Spindle & Gland bush – A1S1 410. Handwheel C.S, Gasket SW S.S-304 + LAF, flange drilled to ANSI – B.16.5 along with companion slipon welded flange (without hub) drilled as per B.16.5 and gasket, Nut & bolt etc. Hand Wheel - C.S. Gunmetal globe valve, Screwed, as per IS-778-`84 Class-2

Battery Limit The tenderer shall calculate the water requirement for various system viz. medium velocity spray and hydrant system and shall clearly mention in the offer water quality and its pressure. Tenderer is to tap the water from the existing network and shall provide necessary flange connection, isolation valve, valve chamber etc. at the tapping point.

7.0

Design Criteria

7.1

Codes and Standards: STANDARDS

7.1.1

All materials, equipments, piping, valves, fittings etc. dimensional standards, tolerance, prices of manufacture and testing procedure shall be in accordance with the latest revision of relevant Indian, British, American standards wherever applicable.

7.1.2

The material used and equipment supplied shall be new and the best of their kind and shall comply with the latest revisions of all relevant standards. The tenderer shall indicate in his tender the relevant standards to which the equipment, piping, fittings, etc. offered by him shall comply with. The latest revisions of applicable standards indicated in the technical specification shall be used for the design, manufacture, inspecting and testing of the items covered in this specification. The following codes and standards shall be considered for design: -

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 137 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED



OISD-113: Classification of areas for electrical installations at hydrocarbon processing and handling facilities.



OISD-118: Layout for oil and gas installation.



OISD-163: Process control room safety.



OISD-189: Standard on Fire Fighting Equipment for Drilling Rigs, Work Over Rigs and Production Installations



National fire protection association, USA (NFPA) codes



Standard for installation of centrifugal pumps (NFPA-20)



Standard for water spray systems (NFPA- 15)



Standard for sprinkler systems (INFPA-13)



API-25 10 A: Fire protection considerations for design and operation of LPG storage facilities.



Auto start system with bypass arrangement for jockey pumps in case of pressure drop in the fire hydrant line.



Foam and Dry Chemical Power extinguishers of capacity as per SOR shall also be provided and located along with other fire fitting facilities.



Standard for Horizontal Centrifugal Pumps for clear, cold, fresh water IS: 15201980



Technical requirement for roto-dynamic special purpose pumps IS: 5120-1971



Horizontal Centrifugal self priming pumps IS:8418-1977



Code of acceptance tests for centrifugal, mixed flow and axial flow pumps IS: 9137-1978, BS-5316-latest edition, ISO-2548-1973



Technical specification for centrifugal pumps ISO:9908-1993



End suction centrifugal pumps ISO: 2858-1995



Single faced sluice gates IS:3042-1965



Single faced cast iron thimble mounted sluice gates IS:13349-1992



Sluice valves for water works purpose (50-300mm size) IS: 780-1984



Copper alloy gate, globe and check valves for general purpose. IS:778-1984

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 138 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED



Specification for cast iron check valves BS 5153-1991



Foot valves for water works purposes IS:4038-1986



Landing valves IS:5290-1993



Valve inspection & test IS:6157-1981



Specification for inspection and test of steel valves BS:6755-1986



Mild steel tubes, tubular and other wrought iron fittings IS:1239, part-1-1990 & Part-2-1992



Seamless or electrically welded steel pipes for water, gas and sewage IS:35891991



Steel pipe flanges for water, oil, steam etc. IS:6392-1971



Butt welded fittings ANSI B16.9



Circular flanges for pipes, valves and fittings BS1560-latest editions



Code for pressure piping ANSI B31.1



Steel pipe flanges ANSI B 16.5



Code of practice for laying of electrically welded steel pipes for water supply IS:5822-1994



Excavation work-code of safety IS: 3764-1992



Criteria for design of anchor blocks for penstock with expansion joints IS:53301984



Covered electrode for manual metal arc welding of carbon and carbon manganese steel IS:814-1991



Approved tests for welding procedure IS: 7307 (Part-I)-1974



Approved tests for welders working to approved welding procedures IS:7310(PartI)-1974



Specification for arc welding of carbon and carbon manganese steels BS:51351984



Code of practice for coating & wrapping IS:10221



Code of practice for radiographic testing IS:2595-1978

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 139 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

7.6

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED



Recommended practice for radiographic inspection of fusion welded butt joints in steel pipes IS:4853-1982



Recommended practice for radiographic inspection of fusion welded butt joints in steel pipes IS:1182-1983



Safety code for industrial radiographic practice IS:2598-1966



Ready mixed paint, stoving, red-oxide-zinc chrome priming IS:2074-1992



Code of practice for painting of ferrous metals in building IS:1477-1971



Colours for ready mixed paints and enamels IS:5-1994



Steel for general structural purposes IS:2062-1992

First Aid Fire Fighting Equipments: The requirement of these have been estimated and provided at all critical locations by Contractor, as per relevant OISD standards. The quantity shall be as per SOR.

8.0

SPECIAL INSTRUCTIONS TO THE TENDERERS

8.1

General

8.1.1

The instruction to Tenderer shall be read in conjunction with the Invitation to Tender, General Conditions of Contract, Tendering Specifications, Scope of supply and drawing or other supplementary documents detailing the work.

8.1.2

The tenderer shall study the specification and satisfy himself regarding the workability of the proposed system and shall take full responsibility for the proper system design, best quality of material and workmanship, guaranteed operation and smooth performance of all the equipment and accessories. This technical specification is only guidance to the tenderer and hence all the items necessary for safe and satisfactory operation and guaranteed performance of the proposed equipment / facilities shall be included in his offer though these might not have been specifically mentioned in the technical specification/schedule of quantities.

8.1.3

The Tenderer shall submit a statement of similar plants and equipment supplied/installed by him during the last five years, which are under successful operation.

8.1.4

The Tenderer shall satisfy the Purchaser that he possesses the necessary technical experience for design and has at his disposal suitable facilities and crew to ensure that his contract shall be of the best quality and workmanship. Necessary particulars in this regard shall be furnished with the tender.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 140 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

8.1.5

The Tenderer should satisfy himself by a visit to the site to ascertain the actual site conditions before submitting his offer. Failure to do so will not absolve him of his responsibilities of proper execution of the job. No claims for extra payment due to any special site conditions will be considered after the submission of the offer.

8.1.6

Any loss of plant and equipment due to imprudence, negligence and unsuitable treatment and handling shall have to be replaced by the successful tenderer at his cost.

8.1.7

The approval of drawings and/or inspection by Purchaser and/or their authorised representative shall not absolve or relieve the supplier from any of his obligation under this contract and they shall be wholly and solely responsible for the satisfactory operation and guaranteed performance of the systems and equipment forming part of the system. This specification is issued for procurement from indigenous sources. No foreign exchange or import license for importing equipment, components, raw materials or spares will be arranged for or provided by the purchaser. In case the equipment offered involves expenditure in foreign exchange, the same shall be arranged by the tenderer.

8.1.8

Any equipment/material which in any way fails to meet the requirements of the specification will be rejected by the Purchaser and the equipment/material involved shall not be used under the contract. The successful Tenderer will be required to promptly furnish new material at his cost without hampering the overall schedule of commissioning of the project.

8.1.9

Any changes or difficulties which might be encountered during the execution of work or any other problems due to local working conditions which are not anticipated/included in the tender document shall fall under full obligations of the successful Tenderer. No claim on account of any ambiguity in any respect will be entertained after the acceptance of the quotation by the Purchaser.

8.1.10 All equipment supplied shall allow access to facilitate connecting up, inspection, maintenance and repair and shall operate satisfactorily under such variations of load, pressure and climatic conditions as may occur during working. 8.1.11 All material, dimensional standards, tolerances, process of manufacture and testing procedures shall be in accordance with the latest revision of the standard codes specified in this Tendering Specification. In case where such suitable standards are not mentioned, any acceptable Indian/International Standards shall be adopted. 8.1.12 All documents, instructions, name plates etc. shall be written in English language. All weights, dimensions and units shall be in metric system. 8.1.13 The Tenderer shall take note of the climatic conditions of the project site, which is given, in the introductory note of the specification. 8.1.14 The Tenderer shall quote, based on the approved makes of equipment/ supplies, as given in the relevant clauses of this specification. In case of any deviation from the approved list of vendors for bought-out items, prior written approval shall be obtained from the Purchaser/Consultant.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 141 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

8.1.15 The Purchaser reserves the right to reject all or any of the offers fully or partly without assigning any reasons, whatsoever. 8.1.16 The Tenderer shall quote for earliest delivery of the equipment/supplies as well as earliest completion of the entire work. 8.1.17 The Tenderer shall be responsible for completeness of supplies, work and services to make the system complete, operative and properly hooked up to the Purchaser's network. Any equipment and material not specifically mentioned in this tendering specification, but required for safe, smooth and efficient operation and guaranteed performance of the fire protection system will have to be intimated by the tenderer to the purchaser. 8.1.18 The Tenderer shall submit a detailed list of commissioning spares for mechanical, electrical, instrumentation etc that will form a part of main equipment supply. 8.1.19 The Tenderer shall include in his offer the Quality Assurance Plan containing the overall quality management and procedures, which he proposes to follow for performing the work during various phases of execution. 8.1.20 At the time of award of contract, the detailed Quality Assurance Plan to be followed for execution of the contract will be mutually discussed and agreed to. 8.1.21 Wherever applicable, the equipment/supplies offered shall also conform to the provision of statutory regulations of the Government of India and other regulations in force such as Indian Factories Act, Indian Electricity Rules, Chief Controller of Explosives, Nagpur etc. Any permission from statutory bodies, if necessary for execution of work shall be sought and arranged by the Tenderer. 8.1.22 The technical specifications for installation of hydrant system elaborated in different chapters are generally based on NFPA codes USA/TAC codes (India) and OISD 189. However, it will be obligatory on the part of the successful tenderer to obtain approval from Statutory Authority for the system. The tenderers are free to suggest suitable modifications required, if any, to enable them to obtain TAC / local fire services approval / any other statutory bodies approvals for all the systems. No extra claim shall be entertained by the purchaser for obtaining TAC / OISD / any other statutory bodies approval after placement of order. 8.1.23 Materials used and equipment supplied shall be new and the best of their kind. The successful Tenderer for the material used shall furnish manufacturer’s certificates. 8.1.24 If the offer deviates from the standards specified, the Tenderer shall indicate clearly in his offer the standards he proposes to adopt with details there of. Copies of such standards shall be enclosed with the offer. 8.2

Data, Drawings , Documents & Manuals Drawings and Documents to be furnished by the tenderer, not limited to the list indicated below

8.2.1

Drawings/documents to be furnished with offer

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 142 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

The tenderer shall submit the offer along with the following drawing/documents. a/

Scope of work with general description of the system and equipment offered specifying the important features. The tenderer has to give a confirmation with respect to the scope of work as detailed in this specification excepting for the deviations, if any, to be listed in the schedule of deviation. The description to be accompanied by single line diagrams, and equipment layout to enable the Purchaser to have a proper appreciation of the equipment offered and its operation.

b/

Complete bill of material for all the system in the working drawing

c/

Specific exclusions, if any, from scope of work .

d/

Block Scheme diagram for all fire protection system

e/

Equipment layout drawings for all fire protection system

f/

Specification of equipment/material along with their makes/catalogues. Approval certificate from authorising bodies for various components of the systems.

g/

Time Schedule ( Bar Chart L1) for implementation of jobs and number of persons to be deputed at site along with their experience/ qualification and period of posting at site.

h/

Certificate of approval from TAC/UL/FM and similar other authorising body for various component of scope of work. Manufacturer's standard literature, catalogue, instruction for use and copies of certificate from TAC/ Chief Inspector of Explosives for all portable extinguishers.

i/

Write up with control schematic on working of all fire protection systems.

j/

Drawing showing details of fire alarm panel and list of annunciation considered in MFAP.

k/

Line diagram for FDA system with points indicated along with sensor schedule

l/

Line diagram for piping layout for hydrant and spray systems. Line diagram for piping layout for gas based systems.

m/

Detailed water requirement calculation for Hydrant and Monitor system

n/

Any other information tenderer feels to submit to understand the quotation in complete.

o/

Detector type and Catalogues

p/

Fire alarm panel drawing

q/

List of annunciation in MFAP

Note: FAILURE TO COMPLY WITH ABOVE MAY ITSELF BE SUFFICIENT REASON TO REJECT THE OFFER.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 143 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

8.2.2

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Drawing/documents to be furnished after placement of order

For Approval by purchaser/consultant The following design data, drawing & documents shall be submitted by the contractor for approval of the purchaser/ consultant. The contractor shall resubmit the data/drawings/documents incorporating the changes suggested by purchaser/consultant for final approval along with approval by TAC. i/

Overall layout of the plant showing various premises covered under fire detection & alarm system, fire hydrant system, medium velocity water spray system, C02 extinguishing system, Inert gas based system, Passive fire protection system etc.

ii/

G.A Drg. for MVWS system with points numbered serially.

iii/

G.A Drg. for Gas based systems.

iv)

Piping details for Gas based Systems.

v/

G.A. Drg. for fire hydrant & spray system ring mains with points numbered serially.

vi/

Piping detail for Hydrant, MVWS systems.

vii/

Line diagram for individual fire detection system.

viii/

Detailed water requirement calculation for Hydrant system

ix/

Detailed water requirement calculation for MVWS system for individual areas.

x/

System layout drawings showing in Plan and Sections, location of various equipments such as detectors, junction boxes, panels, manual call points, fire indication panels, response indicators, batteries and battery chargers, etc.

xi/

Area wise detector layout with calculation for coverage of area.

xii/

Control and schematic for fire alarm system

xiii/

Fire alarm panel drawings

xiv/

Performance Guarantee Test procedures.

xv/

All drawings required for TAC approval.

xvi/

Proposal for training of purchaser's personnel (equipment wise/ man days basis).

xvii/

Detailed water requirement calculation for MVWS system

8.2.3

Drawings/documents to be furnished for information

Following drawings/documents shall be furnished.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 144 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

a/

Manufacturer's routine test and type test certificates for all equipment and cables.

b/

Detailed technical catalogues for all the equipment.

c/

Ordering specifications to sub-suppliers.

d/

Instruction manuals for erection, maintenance and operation of all the equipments.

e/

All scheme drawings along with list of components for various electronic cards used in the equipments. Necessary guidelines for testing the cards along with test parameters for all such cards.

f/

Spare parts manual containing itemised inventory of equipment supplied.

g/

Details of painting for all equipment.

h/

Details of test results conducted at works for all equipments.

i/

Details of test results conducted at site for all equipments.

j/

Panel wise bill of material indicating type make and brief technical particulars of all items/ accessories mounted on the panels.

k/

Overall GA of all the panels/equipments.

l/

Certificate of approval from TAC/UL/FM and similar other authorising body for various component of scope of work. Manufacturer's standard literature, catalogue, instruction for use and copies of certificate from TAC/ Chief Inspector of Explosives for all portable extinguishers.

8.2.4

As built drawings/documents The Contractor shall submit following As Built drawings/documents in five sets. -

All approved drawings/documents

-

All test charts and inspection certificates in bound volume.

2 set of polyester film reproducible of each of the As built drgs and documents including design calculations incorporating approved changes, if any, during erection, testing, commissioning ( all drawings even if there are no changes). -

CAD version of drawings in floppies.

9.0

INSPECTION

9.1

General Manufacturing progress review, inspection & testing of equipment covered under the technical specification shall be carried out by the Purchaser at the manufacturers'

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 145 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

works/premises prior to dispatch to ensure that their quality & workmanship are in conformity with the contract specifications and approved drawings. These instructions are in addition to provisions laid down in other contract documents of the Purchaser. Inspection & testing stages and finalisation of quality assurance plan (QAP) The quality assurance programme and quality assurance plan will be finalised after mutual discussion after placement of order. 9.2

Responsibility for inspection : Any inspection by the Purchaser does not replace the responsibility of quality assurance and quality control functions, as expected of the Contractor to be performed by him for supply of plant & equipment as part of the contractual obligations. As such, any approval which the Inspecting Engineer of the Purchaser may have given in respect of plant and equipment and other particulars and the work or workmanship involved in the contract (whether with or without test carried out) shall not bind the Purchaser to accept the plant and equipment, should it on further test at site be found not to comply with the requirements of the contract. The inspection shall be carried out as per the approved drawings and codes. The equipments shall be dispatched to site only after getting dispatch instructions from Purchaser. The Contractor is to meet the inspection & testing requirements for the equipment coming under statutory regulations e.g. weights & measures, safety, IE rules, Tariff Advisory Committee/ UL/ FM etc. and submit certificates and documents from appropriate authority to Inspecting Engineer for the same.

9.3

Extent of inspection: The extent of inspection & testing by the Purchaser shall vary from equipment to equipment as per design requirements. Extent of inspection to be carried out shall be finalised with the Contractor after award of the contract on the basis of scope of supply, technical specification and approved GA drawings. However, in case of similar bulk manufactured items, methods of sampling for inspection of different lots shall be governed by relevant Indian or international standards. In case of critical components, the Purchaser inspection. Categories of

reserves

the right to undertake 100%

Equipment Extent of Inspection (as applicable from equipment to equipment)

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 146 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

i) Bought-out items

MECON LIMITED

Following standard bought-out items shall be accepted on the basis of manufacturers' test certificates: - Control/Repeater panel - Smoke detectors & heat detectors - Pressure switches - Pressure gauges - Conduits - Detectors

ii) Final inspection & testing: - Verification of test certificates - Visual & Workmanship - Dimensional -

Witnessing of routine tests as per relevant standards. Manufacturers' test certificates for type test (excepting for AC motors) to be submitted for verification. - Witnessing of proto-type tests, as applicable.

9.4

Tests, test certificates and documents For each of the items being manufactured, following test certificates and documents (as applicable for each of the equipment) in requisite copies shall be prepared and submitted to the Inspecting Engineer for scrutiny & records. i)

Materials identification & physical and chemical test certificates for all materials except IS:2062 -1992 and FG 150 IS:210-1978 materials used in manufacture of the equipment.

ii)

Welding procedures and welder's qualification test certificates, wherever applicable.

iii)

Routine/type/calibration/acceptance/special test certificates for electrical items.

iv)

Surface preparation and painting certificates.

v)

Certificates from competent authority for the items coming under statutory regulations.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 147 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

9.5

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

TESTING OF EQUIPMENT

9.5.01 General Testing of all equipment shall be conducted as per latest IS. Tests shall also confirm to International Standards. All routine tests shall be carried out at manufacturer’s works in presence of purchaser or his representative. The contractor shall submit type test certificates for similar equipment supplied by him elsewhere. In case type test certificates for similar equipment is not available, the same shall be conducted in presence of purchaser or his representative if purchaser so desires, without any financial implications to purchaser. The contractor shall be responsible for satisfactorily working of complete integrated system and guaranteed performance. Following tests shall be carried out in addition to other tests: a) Response characteristics of heat/smoke detectors. b) Temperature rating test of heat detectors. c) Operation test of alarm valves. d) Calibration test on instruments and tests on control panels 9.5.02 Site Tests And Checks General All the equipments shall be tested at site to know their condition and to prove suitability for required performance. The test indicated in following pages shall be conducted after installation. All tools, accessories and required instruments shall have to be arranged by contractor. Any other test which is considered necessary by the manufacturer of the equipment or mentioned in commissioning manual has to be conducted at site. In addition to tests on individual equipment some tests/ checks are to be conducted/ observed from overall system point of view. Such checks are highlighted under miscellaneous tests but these shall not be limited to as indicated and shall be finalised with consultation of client before charging of the system. The contractor shall be responsible for satisfactory working of complete integrated system and guaranteed performance. All checks and tests shall be conducted in the presence of client's representative and test results shall be submitted in six copies to client and one copy to statutory/approving authorities for various equipments. Test results shall be filled in proper proforma.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 148 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Inspection by TAC officials for all site tests where ever required shall be arranged by the contractor at his own cost. The contractor shall be responsible to obtain the necessary approval from time to time during execution of the contract from TAC and final approval from TAC to obtain maximum discount in insurance premium as per rules prevailing with TAC. 10.0

SAFETY PRECAUTIONS Necessary action is to be taken by the contractor during the execution of the works for complying with various safety measures in conformity with relevant laws, if any. Special safety arrangements for working at height are to be made, safety belts, helmets, security surveillance/ watching of various site activities at height, checking and obtaining clearance from the complete authority etc. are to be done by the contractor, and necessary certificates for safe and satisfactory working condition of plants/ equipments are to be submitted periodically by the contractor to the OWNER/ MECON.

11.0

MANPOWER PLANT & EQUIPMENT In view of the rigid time bound completion period of the project, the contractor shall be required to deploy suitable and adequate manpower, plant and equipment resources to progressively achieve the time schedule as assessed by the MECON.

12.0

PERFORMANCE GUARANTEE The supplier shall guarantee the equipment/ system supplied, for satisfactory performance at the specified duty/ site condition for 24 months from the date of FAC.

13.0

SPARE PARTS The contractor shall indicate separately at the time of bidding the list and the price of spare parts (price part in sealed envelop separately) required for two years of normal operation.

14.0

PROTECTIVE PAINTING All equipment shall be properly cleaned and freed from rust and scale and painted with a primary coat of red oxide zinc chromate primer as per IS: 2074 prior to shipment from the manufacturer's premises and final painting at site shall be done as per the painting specification. However, galvanized pipes shall be provided with identification bands at regular intervals instead of epoxy painting. All other equipment shall be painted with epoxy paint. The entire surface which is not accessible after site assembly including the areas to be thermally insulated shall be given one coat of red lead paint conforming to IS: 102 in addition to one coat of primer applied at shop or manufacturer's premises.

15.0

TIME SCHEDULE The delivery and erection of all equipment/plant shall be so scheduled that it shall be possible to commission the complete system package in order to match with the overall

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 149 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

commissioning schedule of the entire Project. The delivery date shall be quoted from the date of issue of letter of intent taking into account the time for approval of design and drawings by the Purchaser. The Successful Tenderer shall guarantee the material delivery and commissioning dates. The Successful Tenderer shall submit bar chart/PERT network showing the start and finish time of all activities connected with completion of the entire fire protection system package keeping in mind the overall commissioning schedule of the project. Progress report shall be submitted by the Successful Tenderer at regular intervals of 2 weeks on a format prescribed by the Purchaser giving the status of design, approval of drawings, ordering position of plant and equipment and other materials ordered, manufactured, fabricated, delivered and erected. 16.0

MATERIALS AND WORKMANSHIP

16.1

Materials used for the manufacture/ fabrication of equipment and individual components shall be new, defect-free and best of its kind. They shall confirm to relevant Indian/ International Standards.

16.2

Only tested materials shall be used for fabrication/ manufacture of the equipment/ components. Necessary test certificates shall be submitted to the purchaser for checking compliance to specified grades of materials.

16. 3

The finish of the equipment and, its components shall be of high quality.

16.4

The equipment shall be fabricated with minimum number of welded joints and the seams of the weld shall be so arranged that no two seams come in one line.

16.5

All the pipe connections to the equipment shall be truly perpendicular or inclined exactly at the angle shown in the fabrication drawing.

16.6

All exposed moving parts shall be adequately guarded to prevent accidents in accordance with the statutory rules in force.

16.7

All the rotating parts shall be statically and dynamically balanced.

17.0

STATUTORY REGULATIONS, LICENCES & PERMITS

17.1

The contractor shall adhere to all applicable statutory requirements including TAC, OISD, Inspectorate of Factories, Indian Electricity Rules and other statutes of Govt. of India and state government. The contractor shall himself ascertain all applicable requisite regulations.

17.2

The contractor shall be solely responsible for obtaining necessary clearances from various statutory bodies including those of Govt. of India / State Govt. and as applicable during the course of manufacture/ fabrication, testing, transportation and delivery of plant and equipment. The rates quoted in this connection shall be deemed to include any fees payable to Govt./ Fire Authorities/ Statutory bodies for obtaining approval.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 150 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

17.3

Contractor shall keep constant liaison with the local Fire Authority, Electrical Authority and all other Statutory Authorities whose approval and permissions/ sanctions before and after execution of the work are required to be obtained.

17.4

It shall be the Contractor's responsibility to obtain the approvals and permissions, sanctions, No Objection certificates from relevant Fire Authorities for work done by him to enable owner to take up the operation of plant. Contractor shall comply with all requirements of the appropriate authorities, submit documents, test reports and conduct such tests as may be required by the concerned authority to its full satisfaction.

18.0

HANDING OVER THE WORK ON COMPLETION The contractor shall be responsible for handing over the work complete in all respects and in proper finished condition, on completion of the work. If there is any damage or disfiguration/ stains on the finished surfaces including on wall, floors, ceiling, columns, beams etc. due to contractors use, damage or any other reason during the period of construction, the same shall be rectified suitable by the contractor without any extra payment.

19.0

SCHEDULE OF RATES / BILL OF MATERIALS The quantities of different material, pipes/ fittings, valves, flanges, erection, accessories etc. mentioned in the specification and SOR are approx. quantities and any change in requirements will be as per the finally approved drawings. Any item, instrument which is not specifically mentioned in the SOR, but required for the completeness of the system, will have to be supplied and erected by the contractor and the financial implication shall be built in the testing and commissioning item.

20.0

General All the pipe / conduit / equipment supports shall be provided as per standard practice. Underground piping network shall be protected against corrosion by providing wrapping and coating material as per TAC / BIS. Wherever pipes and cables are crossing the pipes and cables shall be laid in hume pipe of NP-4 rating at a minimum depth of one meter. Deluge valve housing / room to protect the deluge valve from mechanical damage and other environmental effect viz. Dust, dirt, extreme temperature condition. Civil room for the storage of inert gas cylinders shall be provided. Subsequent to successful commissioning, the systems shall be accepted after 3 months of trial runs and performance guarantee test.

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 151 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

GUIDE LIST OF MAKES OF MATERIAL Fire Hydrant System Sr. No. Product Description 1 ERW MS black pipe 2

MS flanges

3 4 5 6 7 8 9 10 11 12 13 14

Water Monitor Double Headed hydrant Valve Rubberised fabric lined hose Gunmetal branch pipe Gunmetal nozzle Fire men's axe Fire Brigade inlet (2way & 4- way) screwed single acting air valve Cast steel sluice valve Fire Hose cabinet Pressure Gauge Pressure Switch

Make Tisco/ Jindal/ Surya / Ajanta/ Gujarat Steel Aditya forge/ forge & forge/ metal forging/ CD Engg./ Amforge Industries/ JK forge Newage/HD/ Minimax/ Vijay Fire / Zenith Newage/HD/ Minimax/ Vijay Fire / Zenith New age/ Jayshree Newage/HD/ Minimax/ Vijay Fire / Zenith Newage/HD/ Minimax/ Vijay Fire / Zenith Newage/HD/ Minimax/ Vijay Fire / Zenith Newage/HD/ Minimax/ Vijay Fire / Zenith Flowchem/KSB/leader flowchem/KSB/Audco/Kalpana Newage/HD/ Minimax/ Vijay Fire / Zenith AN instrument/ General Inst Indfoss / Switzer or equivalent

Fire water Spray System (HVWS & MVWS) Sr. No.

Product Description

Make

1

GI Pipe

Tisco/ Jindal/ Surya Prakash/ Ajanta/ Gujarat Steel

2 3 4 5

MVWS Nozzle Quartzoid Bulb Detector Deluge Valve Gate valve

6

y' type Strainer

7

Pressure switch

8

Cable

HD/ Kidde or equivalent HD/ wiking/ spray safe or UL listed HD/ Kidde flowchem/venus/KSB/Audco/Kalpana Gujarat Otofilt/ Grandprix / Ravi Techno or as per tender Indfoss/ Switzer or equivalent INCAB/ Universal cable/ Asian cable/ KEI or as per tender make

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 152 of 153

CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE Hindustan Petroleum Corporation Ltd.

Bid Doc. No.: 05/51/23LK/HPCL/001(i)

MECON LIMITED

Fire Detection & Alarm System Sr. No. Product Description 1 Mcd Detector 2 Flame proof Manual call point 3 Hooter 4 Flasher

Make Apollo/ Morley IAS/ GST/ Honeywell PCD/ Agni control PCD/ Agni control PCD/ Agni control

5

Panel

Control Equipment/ Morley IAS/ GST/ Honeywell

6

Response Indicator

7

Cable

8

Abort Switch

Agni/ PCD/ Securico INCAB/ Universal cable/ Asian cable/ KEI or as per tender make system sensor/ Agni/ PCD

D:\old data\Vijyant\HPCL\Tender\Laying\Vol-I of IV\ParticularJobSp-Tikari-final.doc

Page 153 of 153

SECTION – 4 (GENERAL TERMS & CONDITIONS FOR WORKS CONTRACT)

GENERAL TERMS & CONDITIONS OF WORKS CONTRACT (GTC)

1 PRELIMINARY 1.1 This is a Contract for execution of __________________ work at _______________________. (please fill up the blanks) 1.2 The tenderer for the abovementioned item of work is ____________________________. (please give the name and address of the tenderer) 1.3 The terms and conditions mentioned hereunder are the terms and conditions of the Contract for the execution of the work mentioned under item 1.1 above. 1.4 It is the clear understanding between Hindustan Petroleum Corporation Limited and the tenderer ______________________________________ that (name and address of the tenderer) in case the tender of ______________________________________________________________ is (name and address of the tenderer) accepted by Hindustan Petroleum Corporation Limited and an intimation to that effect is so issued and also a Purchase Order is placed with ________________________________________________________ (name and address of the tenderer) this document will be termed as a Contract between the parties and terms and conditions hereunder would govern the parties interest. 1.5 Interpretation of Contract Documents: All documents forming part of the Contract are to be taken mutually explanatory. Should there be any discrepancy, inconsistency, error or omission in the contract, the decision of the Owner/Engineer-in-Charge/Site-in-Charge shall be the final and the contractor shall abide by the decision. The decision shall not be arbitrable. Works shown upon the drawings but not mentioned in the specification or described in the specifications without being shown on the drawings shall nevertheless be deemed to be included in the same manner as if they are shown in the drawings and described in the specifications. 1.6 Special conditions of Contract : The special conditions of contract, if any provided and whenever and wherever referred to shall be read in conjunction with General Terms and Conditions of contract, specifications, drawings, and any other documents forming part of this contract wherever the context so requires. Notwithstanding the subdivision of the documents into separate sections, parts volumes, every section, part or volume shall be deemed to be supplementary or complementary to each other and shall be read in whole. In case of any misunderstanding arising the same shall be referred to decision of the Owner/ Engineer-in-Charge/Site-in-Charge and their decision shall be final and binding and the decision shall not be arbitrable. It is the clear understanding that wherever it is mentioned that the Contractor shall do/perform a work and/or provide facilities for the performance of the work, the doing or the performance or the providing of the facilities is at the cost and expenses of the work not liable to be paid or reimbursed by the Owner. 2. DEFINITIONS In this contract unless otherwise specifically provided or defined and unless a contrary intention appears from the contract the following words and expressions are used in the following meanings; 2.1 The term "Agreement" wherever appearing in this document shall be read as

"Contract". 2.2 The "Authority" for the purpose of this Contract shall be the Chairman and Managing Director or any other person so appointed or authorised. 2.3 The "Chairman and Managing Director" shall mean the Chairman and Managing Director of HINDUSTAN PETROLEUM CORPORATION LIMITED or any person so appointed, nominated or designated and holding the office of Chairman & Managing Director. 2.4 The "Change Order" means an order given in writing by the Engineer-in-Charge or by Owner to effect additions to or deletion from or alterations into the Work. 2.5 The "Construction Equipment" means all appliances and equipment of whatsoever nature for the use in or for the execution, completion, operation or maintenance of the work except those intended to form part of the Permanent Work. 2.6 The "Contract" between the Owner and the Contractor shall mean and include all documents like enquiry, tender submitted by the contractor and the purchase order issued by the owner and other documents connected with the issue of the purchase order and orders, instruction, drawings, change orders, directions issued by the Owner/Engineer-in-Charge/Site-in-Charge for the execution, completion and commissioning of the works and the period of contract mentioned in the Contract including such periods of time extensions as may be granted by the owner at the request of the contractor and such period of time for which the work is continued by the contractor for purposes of completion of the work. 2.7 "The Contractor" means the person or the persons, firm or Company whose tender has been accepted by the Owner and includes the Contractor's legal heirs, representative, successor(s) and permitted assignees. 2.8 The "Drawings" shall include maps, plans and tracings or prints thereof with any modifications approved in writing by the Engineer-in-Charge and such other drawings as may, from time to time, be furnished or approved in writing by the Engineer-in-Charge. 2.9 The "Engineer-in-Charge or Site-in-Charge" shall mean the person appointed or designated as such by the Owner and shall include those who are expressly authorised by the owner to act for and on its behalf. 2.10 "The Owner" means the HINDUSTAN PETROLEUM CORPORATION LIMITED incorporated in India having its Registered office at PETROLEUM HOUSE, 17, JAMSHEDJI TATA ROAD, BOMBAY 400020 and Marketing office at ____________________________________________ or their successors or assignees. 2.11 The "Permanent Work" means and includes works which form a part of the work to be handed over to the Owner by the Contractor on completion of the contract. 2.12 The "Project Manager" shall mean the Project Manager of HINDUSTAN PETROLEUM CORPORATION LIMITED, or any person so appointed, nominated or designated.

2.13 The "Site" means the land on which the work is to be executed or carried out and such other place(s) for purpose of performing the Contract. 2.14 The "Specifications" shall mean the various technical and other specifications attached and referred to in the tender documents. It shall also include the latest editions, including all addenda/corrigenda or relevant Indian Standard Specifications and Bureau Of Indian Standards. 2.15 The "Sub-Contractor" means any person or firm or Company (other than the Contractor) to whom any part of the work has been entrusted by the Contractor with the prior written consent of the Owner/Engineer-in-Charge/Site-in- Charge and their legal heirs, representatives, successors and permitted assignees of such person, firm or Company. 2.16 The "Temporary Work" means and includes all such works which are a part of the contract for execution of the permanent work but does not form part of the permanent work confirming to practices, procedures applicable rules and regulations relevant in that behalf. 2.17 The "Tender" means the document submitted by a person or authority for carrying out the work and the Tenderer means a person or authority who submits the tender offering to carry out the work as per the terms and conditions. 2.18 The "Work" shall mean the works to be executed in accordance with the Contract or part thereof as the case may be and shall include extra, additional, altered or substituted works as maybe required for the purposes of completion of the work contemplated under the Contract. 3. SUBMISSION OF TENDER 3.1 Before submitting the Tender, the Tenderer shall at their own cost and expenses visit the site, examine and satisfy as to the nature of the existing roads, means of communications, the character of the soil, state of land and of the excavations, the correct dimensions of the work facilities for procuring various construction and other material and their availability, and shall obtain information on all matters and conditions as they may feel necessary for the execution of the works as intended by the Owners and shall also satisfy of the availability of suitable water for construction of civil works and for drinking purpose and power required for fabrication work etc. Tenderer, whose tender may be accepted and with whom the Contract is entered into shall not be eligible and be able to make any claim on any of the said counts in what so ever manner for what so ever reasons at any point of time and such a claim shall not be raised as a dispute and shall not be arbitrable. ® A pre-bid meeting may be held as per the schedule mentioned in the tender. 3.2 The Tenderer shall be deemed to have satisfied fully before tendering as to the correctness and sufficiency of his tender for the works and of the rates and prices quoted in the schedule of quantities which rates and prices shall except as otherwise provided cover all his obligations under the contract. 3.3 It must be clearly understood that the whole of the conditions and specifications are intended to be strictly enforced and that no work will be considered as extra work and allowed and paid for unless they are clearly outside the scope, spirit, meaning of the Contract and intent of the Owner and have been so ordered in writing by Owner and/or Engineer-in-Charge/Site-in-Charge, whose decision shall be final and binding.

3.4 Before filling the Tender the Contractor will check and satisfy all drawings and materials to be procured and the schedule of quantities by obtaining clarification from the Owner on all the items as may be desired by the Tenderer. No claim for any alleged loss or compensation will be entertained on this account, after submission of Tender by the Tenderer/Contractor and such a claim shall not be arbitrable. ®3.5 Unless specifically provided for in the tender documents or any Special Conditions, no escalation in the Tender rates or prices quoted will be permitted throughout the period of contract or the period of actual completion of the job whichever is later on account of any variation in prices of materials or cost of labour or due to any other reasons. Claims on account of escalation shall not be arbitrable. 3.6 The quantities indicated in the Tender are approximate. The approved schedule of rates of the contract will be applicable for variations upto plus or minus 25% of the contract value. No revision of schedule of rates will be permitted for such variations in the contract value, including variations of individual quantities, addition of new items, alterations, additions/deletions or substitutions of items, as mentioned above. Quantities etc. mentioned and accepted in the joint measurement sheets shall alone be final and binding on the parties. 3.7 Owner reserve their right to award the contract to any tenderer and their decision in this regard shall be final. They also reserve their right to reject any or all tenders received. No disputes could be raised by any tenderer(s) whose tender has been rejected. 3.8 The Rates quoted by the Tenderer shall include Costs and expenses on all counts viz. cost of materials, transportation of machine(s), tools, equipments, labour, power, Administration charges, price escalations, profits, etc. etc. except to the extent of the cost of material(s), if any, agreed to be supplied by Owner and mentioned specifically in that regard in condition of Contract, in which case, the cost of such material if taken for preparation of the Contractor's Bill(s) shall be deducted before making payment of the Bill(s) of the Contractor. The description given in the schedule of quantities shall unless otherwise stated be held to include wastage on materials, carriage and cartage, carrying in and return of empties, hoisting, setting, fitting and fixing in position and all other expenses necessary in and for the full and complete execution and completion of works and in accordance with good practice and recognised principles in that regard. 3.9 Employees of the State and Central Govt. and employees of the Public Sector Undertakings, including retired employees are covered under their respective service conditions/rules in regard to their submitting the tender. All such persons should ensure compliance to the respective/applicable conditions, rules etc. etc. Any person not complying with those rules etc. but submitting the tender in violation of such rules, after being so noticed shall be liable for the forfeiture of the Earnest Money Deposit made with the tender, termination of Contract and sufferance on account of forfeiture of Security Deposit and sufferance of damages arising as a result of termination of Contract. ®3.10 In consideration for having a chance to be considered for entering into a contract with the Owner, the Tenderer agrees that the Tender submitted by him shall remain valid for the period prescribed in the tender conditions, from the date of opening of the tender. The Tenderer shall not be entitled during the said validity period, to revoke or cancel the tender without the consent in writing from the Owner.

In case the tenderer revokes or cancels the tender or varies any of terms of the tender without the Consent of the Owner, in writing, the Tenderer forfeits the right to the refund of the Earnest Money paid along with the tender. ®3.11 The prices quoted by the Tenderer shall be firm during the validity period of the bid and Tenderer agrees to keep the bid alive and valid during the said period. The Tenderers shall particularly take note of this factor before submitting their tender(s). 3.12 The works shall be carried out strictly as per approved specifications. Deviations, if any, shall have to be authorised by the Engineer-in-Charge/Site-in-Charge in writing prior to implementing deviations. The price benefit, if any, arising out of the accepted deviation shall be passed on to the Owner. The decision of Engineer-in-Charge shall be final in this matter. 3.13 The contractor shall make all arrangements at his own cost to transport the required materials outside and inside the working places and leaving the premises in a neat and tidy condition after completion of the job to the satisfaction of Owner. All materials except those agreed to be supplied by the Owner shall be supplied by the contractor at his own cost and the rates quoted by the Contractor should be inclusive of all royalties, rents, taxes, duties, octroi, statutory levies, if any, etc. etc. 3.14 The Contractor shall not carry on any work other than the work under this Contract within the Owner’s premises without prior permission in writing from the Engineer-in-Charge/Site-in-charge. 3.15 The Contractor shall be bound to follow and ensure compliance to all the safety and security regulations and other statutory rules applicable to the area. In the event of any damage or loss or sufference caused due to non-observance of such rules and regulations, the contractor shall be solely responsible for the same and shall keep the Owner indemnified against all such losses and claims arising from the same. 3.16 At any time after acceptance of tender, the Owner reserves the right to add, amend or delete any work item, the bill of quantities at a later date or reduce the scope of work in the overall interest of the work by prior discussion and intimation to the Contractor. The decision of Owner, with reasons recorded therefor, shall be final and binding on both the Owner and the Contractor. The Contractor shall not have right to claim compensation or damage etc. in that regard. The Owner reserves the right to split the work under this contract between two or more contractors without assigning any reasons. 3.17 Contractor shall not be entitled to sublet, sub contract or assign, the work under this Contract without the prior consent of the Owner obtained in writing. 3.18 All signatures in tender document shall be dated as well as all the pages of all sections of the tender documents shall be initialled at the lower position and signed, wherever required in the tender papers by the Tenderer or by a person holding Power of Attorney authorising him to sign on behalf of the tenderer before submission of tender. 3.19 The tender should be quoted in English, both in figures as well as in words. The rates and amounts tendered by the Tenderer in the Schedule of rates for each item and in such a way that insertion is not possible. The total tendered amount should also be indicated both in figures and words with the signature of tenderer.

® If some discrepancies are found between the rates given in words and figures of the amount shown in the tender, the following procedure shall be applied : (a) When there is a difference between the rates in figures and words, the rate which corresponds to the amount worked out by the tenderer shall be taken as correct. (b) When the rate quoted by the tenderer in figures and words tallies but the amount is incorrect, the rate quoted by the tenderer shall be taken as correct. (c) When it is not possible to ascertain the correct rate in the manner prescribed above the rate as quoted in words shall be adopted. 3.20 All corrections and alterations in the entries of tender paper will be signed in full by the tenderer with date. No erasures or over writings are permissible. 3.21 Transfer of tender document by one intending tenderer to the another one is not permissible. The tenderer on whose name the tender has been sent only can quote. 3.22 The Tender submitted by a tenderer if found to be incomplete in any or all manner is liable to be rejected. The decision of the Owner in this regard is final and binding. In case of any error/discrepancy in the amount written in words and figures, the lower amount between the two shall prevail. 4. DEPOSITS a) EARNEST MONEY DEPOSIT (EMD) The tenderer will be required to pay a sum as specified in the covering letter, as earnest money deposit alongwith the tender either thru a crossed demand draft or a non-revokable Bank Guarantee in favour of Hindustan Petroleum Corporation Limited, from any Scheduled Bank (other than a CoOperative Bank) payable at Mumbai in favour of Hindustan Petroleum Corporation Limited, Mumbai in the proforma enclosed. The earnest money deposit will be refunded after finalisation of the contract. Note: Public sector enterprises and small scale units registered with National Small Scale Industries are exempted from payment of Earnest Money Deposit. Small scale units registered with National Small Scale Industries should enclose a photocopy of their registration certificate with their quotation to make their quotation eligible for consideration. The Registration Certificate should remain valid during the period of the contract that may be entered into with such successful bidder. Such tenderers should ensure validity of the Registration Certificate for the purpose. ® b) SECURITY DEPOSIT: The tenderer, with whom the contract is decided to be entered into and intimation is so given will have to make a security deposit of one percent (1%) of the total contract value in the form of account payee crossed demand draft drawn in favour of the Owner, within 15 days from the date of intimation of acceptance of their tender, failing which the Owner reserves the right to cancel the Contract and forfeit the EMD. 1% of PO/Contract value as Security deposit will be acceptable in the form of Demand draft upto Rs. 50,000/- and in the form of Demand draft / Bank guarantee beyond Rs. 50,000/-. Composite Performance Bank Guarantee (CPBG) for 10% of PO value towards Performance Bank Guarantee inclusive of Security Deposit shall be accepted (in lieu of deduction of retention money); such CPBG shall be valid upto a period of 3 months beyond the expiry of defect liability period.

Demand Draft should be drawn on Scheduled Banks, other than co-operative bank. 5. EXECUTION OF WORK All the works shall be executed in strict conformity with the provisions of the contract documents and with such explanatory details, drawings, specifications and instructions as may be furnished from time to time to the Contractor by the Engineer-in-Charge/ Site-in-Charge, whether mentioned in the Contract or not. The Contractor shall be responsible for ensuring that works throughout are executed in the most proper and workman- like manner with the quality of material and workmanship in strict accordance with the specifications and to the entire satisfaction of the Engineer-in- Charge/Site-in-Charge. The completion of work may entail working in monsoon also. The contractor must maintain the necessary work force as may be required during monsoon and plan to execute the job in such a way the entire project is completed within the contracted time schedule. No extra charges shall be payable for such work during monsoon. It shall be the responsibility of the contractor to keep the construction work site free from water during and off the monsoon period at his own cost and expenses. For working on Sundays/Holidays, the contractor shall obtain the necessary permission from Engineer Incharge/Site Incharge in advance. The contractor shall be permitted to work beyond the normal hours with prior approval of Engineer-In-Charge/Site-In-Charge and the contractors quoted rate is inclusive of all such extended hours of working and no extra amount shall be payable by the owner on this account. 5.a. SETTING OUT OF WORKS AND SITE INSTRUCTIONS 5.a.1. The Engineer-in-Charge/Site-in-Charge shall furnish the Contractor with only the four corners of the work site and a level bench mark and the Contractor shall set out the orks and shall provide an efficient staff for the purpose and shall be solely responsible for the accuracy of such setting out. 5.a.2. The Contractor shall provide, fix and be responsible for the maintenance of all necessary stakes, templates, level marks, profiles and other similar things and shall take all necessary precautions to prevent their removal or disturbance and shall be responsible for consequences of such removal or disturbance should the same take place and for their efficient and timely reinstatement. The Contractor shall also be responsible for the maintenance of all existing survey marks, either existing or supplied and fixed by the Contractor. The work shall be set out to the satisfaction of the Engineer-in-Charge/Site-in-Charge. The approval thereof or joining in setting out the work shall not relieve the Contractor of his responsibility. 5.a.3. Before beginning the works, the Contractor shall, at his own cost, provide all necessary reference and level posts, pegs, bamboos, flags ranging rods, strings and other materials for proper layout of the work in accordance with the scheme, for bearing marks acceptable to the Engineer-inCharge/Site-in-Charge. The Centre longitudinal or face lines and cross lines shall be marked by means of small masonary pillars. Each pillar shall have distinct marks at the centre to enable theodolite to be set over it. No work shall be started until all these points are checked and approved by the Engineer-in-Charge/Site-in-Charge in writing. But such approval shall not relieve the contractor of any of his responsibilities. The Contractor shall also provide all labour, materials and other facilities, as necessary, for the proper checking of layout and inspection of the points during construction.

5.a.4. Pillars bearing geodetic marks located at the sites of units of works under construction should be protected and fenced by the Contractor. 5.a.5. On completion of works, the contractor shall submit the geodetic documents according to which the work was carried out. 5.a.6. The Engineer-in-Charge/Site-in-Charge shall communicate or confirm his instructions to the contractor in respect of the executions of work in a "work site order book" maintained in the office having duplicate sheet and the authorised representative of the contractor shall confirm receipt of such instructions by signing the relevant entries in the book. 5.a.7. All instructions issued by the Engineer-in-Charge/Site-in-Charge shall be in writing. The Contractor shall be liable to carry out the instructions without fail. 5.a.8. If the Contractor after receipt of written instruction from the Engineer-in-Charge/ Site-inCharge requiring compliance within seven days fails to comply with such drawings or 'instructions' or both as the Engineer-in-Charge/Site-in-Charge may issue, owner may employ and pay other persons to execute any such work whatsoever that may be necessary to give effect to such drawings or `instructions' and all cost and expenses incurred in connection therewith as certified by the Engineer-in-Charge/ Site-in-Charge shall be borne by the contractor or may be deducted from amounts due or that may become due to the contractor under the contract or may be recovered as a debt. 5.a.9. The Contractor shall be entirely and exclusively responsible for the horizontal and vertical alignment, the levels and correctness of every part of the work and shall rectify effectually any errors or imperfections therein. Such rectifications shall be carried out by the Contractor, at his own cost. 5.a.10. In case any doubts arise in the mind of the Contractor in regard to any expressions, interpretations, statements, calculations of quantities, supply of material rates, etc. etc., the contractor shall refer the same to the Site-in-Charge/ Engineer-in-Charge for his clarification, instructions, guidance or clearing of doubts. The decision of the Engineer-inCharge/Site-in-Charge shall be final and the contractor shall be bound by such a decision. 5.a.11. "The Contractor shall take adequate precautions, to ensure that his operations do not create nuisance or misuse of the work space that shall cause unnecessary disturbance or inconvenience to others at the work site". 5.a.12. "All fossils, coins articles of value of antiquity and structure or other remains of geological or archaeological discovered on the site of works shall be declared to be the property of the Owner and Contractor shall take reasonable precautions to prevent his workmen or any other persons from removing or damaging any such articles or thing and shall immediately inform the Owner/ Engineer-in-Charge/Site-in-Charge." 5.a.13. "Contractor will be entirely and exclusively responsible to provide and maintain at his expenses all lights, guards, fencing, etc. when and where even necessary or/as required by the Engineer-in-Charge/Site-in-Charge for the protection of works or safety and convenience to all the members employed at the site or general public."

5.b. COMMENCEMENT OF WORK The contractor shall after paying the requisite security deposit, commence work within 15 days from the date of receipt of the intimation of intent from the Owner informing that the contract is being awarded. The date of intimation shall be the date/day for counting the starting day/date and the ending day/date will be accordingly calculated. Penalty, if any, for the delay in execution shall be calculated accordingly. Contractor should prepare detailed fortnightly construction programme for approval by the Engineer-in-Charge within one month of receipt of Letter Of Intent. The work shall be executed strictly as per such time schedule. The period of Contract includes the time required for testing, rectifications, if any, re-testing and completion of work in all respects to the entire satisfaction of the Engineer-in-Charge. A Letter of Intent is an acceptance of offer by the Owner and it need not be accepted by the contractor. But the contractor should acknowledge a receipt of the purchase order within 15 days of mailing of Purchase Order and any delay in acknowledging the receipt will be a breach of contract and compensation for the loss caused by such breach will be recovered by the Owner by forfeiting earnest money deposit/bid bond. 5.c. SUBLETTING OF WORK 5.c.1. No part of the contract nor any share or interest thereof shall in any manner or degree be transferred, assigned or sublet, by the Contractor, directly or indirectly to any firm or corporation whatsoever, without the prior consent in writing of the Owner. 5.c.2. At the commencement of every month the Contractor shall furnish to the Engineer-incharge/Site-in-Charge list of all sub-contractors or other persons or firms engaged by the Contractor. 5.c.3 The contract agreement will specify major items of supply or services for which the Contractor proposes to engage sub-Contractor/sub-Vendor. The contractor may from ime to time propose any addition or deletion from any such list and will submit the proposals in this regard to the Engineer-in-charge/Designated officer-in-charge for approval well in advance so as not to impede the progress of work. Such approval of the Engineer-in-charge/Designated officer-in-charge will not relieve the contractor from any of his obligations, duties and responsibilities under the contract. 5.c.4. Notwithstanding any sub-letting with such approval as resaid and notwithstanding that the Engineer-in-Charge shall have received copies of any sub-contract, the Contractor shall be and shall remain solely to be responsible for the quality and proper and expeditious execution of the works and the performance of all the conditions of the contract in all respects as if such subletting or subcontracting had not taken place and as if such work had been done directly by the Contractor. 5.c.5 Prior approval in writing of the Owner shall be obtained before any change is made in the constitution of the contractor/Contracting agency otherwise contract shall be deemed to have been allotted in contravention of clause entitled “sub-letting of works” and the same action may be taken and the same consequence shall ensue as provided in the clause of “sub- letting of works”.

5.d EXTENSION OF TIME ® 1) If the Contractor anticipates that he will not be able to complete the work within the contractual delivery/ completion date (CDD), then the Contractor shall make a request for grant of time extension clearly specifying the reasons for which he seeks extension of time and demonstrating as to how these reasons were beyond the control of the contractor or attributable to the Owner. This request should be made well before the expiry of the Contractual Delivery/ Completion Date (CDD). 2) If such a request for extension is received with a Bank Guarantee for the full Liquidated

Damages amount calculated on the Total Contract Value, the concerned General Manager of the Owner shall grant a Provisional extension of time, pending a decision on the request. 3) The concerned General Manager of the Owner shall expeditiously decide upon the request for time extension and decide the levy of liquidated damages within a maximum period of 6 months fom the CDD or date of receipt of the request, whichever is later. 4) Grant of any extension of time shall be by means of issuance of a Change Order. 5) In order to avoid any cash crunch to the Contractor, a Bank Guarantee could be accepted against LD, as stated above. Once a decision is taken, the LD shall be recovered from any pending bills or by encashment of the BG. Any balance sum of Contractor or the BG (if LD is fully recovered from the bills) shall be promptly refunded/returned to the Contractor. 5.e. SUSPENSION OF WORKS 5.e.1. Subject to the provisions of this contract, the contractor shall if ordered in writing by the Engineer- in-Charge/Site-in-Charge for reasons recorded suspend the works or any part thereof for such period and such time so ordered and shall not, after receiving such, proceed with the work therein ordered to uspended until he shall have received a written order to re-start. The Contractor shall be entitled to claim extension of time for that period of time the work was ordered to be suspended. Neither the Owner nor the Contractor shall be entitled to claim compensation or damages on account of such an extension of time. 5.e.2. In case of suspension of entire work, ordered in writing by Engineer-in-Charge/Site-inCharge, for a period of 30 days, the Owner shall havethe option to terminate the Contract as provided under the clause fortermination. The Contractor shall not be at liberty to remove from the site of the works any plant or materials belonging to him and the Employer shall have lien upon all such plant and materials. 5.e.3. The contract shall, in case of suspension have the right to raise a dispute and have the same arbitrated but however, shall not have the right to have the work stopped from further progress and completion either by the owner or through other contractor appointed by the owner.

5.f. OWNER MAY DO PART OF WORK Not withstanding anything contained elsewhere in this contract, the owner upon failure of the Contractor to comply with any instructions given in accordance with the provisions of this contract, may instead of Contract and undertaking charge of entire work, place additional labour force, tools, equipment and materials on such parts of the work, as the Owner may decide or engage another Contractor to carryout the balance of work. In such cases, the Owner shall have the right to deduct from the amounts payable to the Contractor the difference in cost of such work and materials with ten percent overhead added to cover all departmental charges. Should the total amount thereof exceed the amount due to the contractor, the Contractor shall pay the difference to the Owner within 15 days of making demand for payment failing which the Contractor shall be liable to pay interest at 24% p.a. on such amounts till the date of payment. 5.g. INSPECTION OF WORKS 5.g.1. The Engineer-in-Charge/Site-in-Charge and Officers from Central or State Government will have full power and authority to inspect the works at any time wherever in progress, either on the site or at the Contractor's premises/workshops of any person, firm or corporation where work in connection with the contract may be in hand or where the materials are being or are to be supplied, and the Contractor shall afford or procure for the Engineer-in-Charge/Site-in-Charge every facility and assistance to carryout such inspection. The Contractor shall, at all times during the usual working hours and at all other times at which reasonable notice of the intention of the Engineer-inCharge/Site-in-Charge or his representative to visit the works shall have been given to the Contractor, either himself be present to receive orders and instructions, or have a responsible agent, duly accredited in writing, present for the purpose. Orders given to the Contractor's agent shall be considered to have the same force as if they had been given to the Contractor himself. The Contractor shall give not less than seven days notice in writing to the Engineer-in-Charge/Site-inCharge before covering up or otherwise placing beyond reach of inspection and measurement any work in order that the same may be inspected and measured. In the event of breach of above, the same shall be uncovered at Contractor's expense for carrying out such measurement and/or inspection. 5.g.2. No material shall be removed and despatched by the Contractor from the site without the prior approval in writing of the Engineer-in-charge. The contractor is to provide at all times during the progress of the work and the maintenance period proper means of access with ladders, gangways, etc. and the necessary attendance to move and adapt as directed for inspection or measurements of the works by the Engineer-in-Charge/Site-in-Charge. 5.h. SAMPLES 5.h.1. The contractor shall furnish to the Engineer-in-charge/Site-in-Charge for approval when requested or required adequate samples of all materials and finishes to be used in the work. 5.h.2. Samples shall be furnished by the Contractor sufficiently in advance and before commencenent of the work so as the Owner can carry out tests and examinations thereof and approve or reject the samples for use in the works. All material samples furnished and finally used/applied in actual work shall fully be of the same quality of the approved samples.

5.i. TESTS FOR QUALITY OF WORK 5.i.1. All workmanship shall be of the respective kinds described in the contract documents and in accordance with the instructions of the Engineer-in-Charge / Site-in- Charge and shall be subjected from time to time to such tests at Contractor's cost as the Engineer-in-Charge/Site-in-Charge may direct at the place of manufacture or fabrication or on the site or at all or any such places. The Contractor shall provide assistance, instruments, labour and materials as are normally required for examining, measuring and testing any workmanship as may be selected and required by the Engineer-in-Charge/Site-in-Charge. 5.i.2. All the tests that will be necessary in connection with the execution of the work as decided by the Engineer-in- charge/Site-in-Charge shall be carried out at the contractors cost and expenses. 5.i.3. If any tests are required to be carried out in connection with the work or materials or workmanship to be supplied by the owner, such tests shall be carried out by the Contractor as per instructions of Engineer-in-Charge/Site-in-Charge and expenses for such tests, if any, incurred by the contractor shall be reimbursed by the Owner. The contractor should file his claim with the owner within 15 (fifteen) days of inspection/test and any claim made beyond that period shall lapse and be not payable. 5.j. ALTERATIONS AND ADDITIONS TO SPECIFICATIONS, DESIGNS AND WORKS 5.j.1. The Engineer-in-Charge/Site-in-Charge shall have powers to make any alterations, additions and/or substitutions to the schedule of quantities, the original specifications, drawings, designs and instructions that may become necessary or advisable or during the progress of the work and the Contractor shall be bound to carryout such altered/extra/new items of work in accordance with instructions which may be given to him in writing signed by the Engineer-in-Charge/Site- inCharge. Such alterations, omissions, additions or substitutions shall not invalidate the contract. The altered, additional or substituted work which the Contractor may be directed to carryon in the manner as part of the work shall be carried out by the Contractor on the same conditions in all respects on which he has agreed to do the work. The time for completion of such altered added and/or substituted work may be extended for that part of the particular job. The rates for such additional altered or substituted work under this Clause shall, be worked out in accordance with the following provisions: 5.j.2. If the rates for the additional, altered or substituted work are specified in the contract for similar class of work, the Contractor is bound to carryout the additional, altered or substituted work at the same rates as are specified in the contract. 5.j.3. If the rates for the additional, altered or substituted work are not specifically provided in the contract for the work, the rates will be derived from the rates for similar class of work as are specified in the contract for the work. In the opinion of the Engineer-in- Charge/Site-in-Charge as to whether or not the rates can be reasonably so derived from the items in this contract, will be final and binding on the Contractor.

5.j.4. If the rates for the altered, additional or substituted work cannot be determined in the manner specified above, then the Contractor shall, within seven days of the date of receipt of order to carry out the work, inform the Engineer-in-Charge/ Site-in-Charge of the rate at which he intends to charge for such class of work, supported by analysis of the rate or rates claimed and the EngineerIn-Charge/ Site-in-Charge shall determine the rates on the basis of the prevailing market rates for both material and labour plus 10% to cover overhead and profit of labour rates and pay the Contractor accordingly. The opinion of the Engineer-in- Charge/Site-in-Charge as to current market rates of materials and the quantum of labour involved per unit of measurement will be final and binding on the contractor. 5.j.5 Deletd. 5.j.6. In case of any item of work for which there is no specification supplied by the Owner and is mentioned in the tender documents, such work shall be carried out in accordance with Indian Standard Specifications and if the Indian Standard Specifications do not cover the same, the work should be carried out as per standard Engineering Practice subject to the approval of the Engineerin-Charge/ Site-in-Charge. 5.k. PROVISIONAL ACCEPTANCE Acceptance of sections of the works for purposes of equipment erection, piping, electrical work and similar usages by the Owner and payment for such work or parts of work shall not constitute a waiver of any portion of this contract and shall not be construed so as to prevent the Engineer from requiring replacement of defective work that may become apparent after the said acceptance and also shall not absolve the Contractor of the obligations under this contract. It is made clear that such an acceptance does not indicate or denote or establish to the fact of execution of that work or the Contract until the work is completed in full in accordance with the provisions of this Contract. 5.l. COMPLETION OF WORK AND COMPLETION CERTIFICATE As soon as the work is completed in all respects, the contractor shall give notice of such completion to the site in charge or the Owner and within thirty days of receipt of such notice the site in charge shall inspect the work and shall furnish the contractor with a certificate of completion indicating: a) defects, if any, to be rectified by the contractor b) items, if any, for which payment shall be made in reduced rates c) the date of completion. 5.m. USE OF MATERIALS AND RETURN OF SURPLUS MATERIALS 5.m.1. Notwithstanding anything contained to the contrary in any or all of the clauses of this contract, where any materials for the execution of the contract are procured with the assistance of Government either by issue from Government stocks or purchase made under orders or permits or licences issued by Government, the contractor shall use the said materials economically and solely for the purpose of the contract and shall not dispose them of without the permission of the Owner. 5.m.2. All surplus(serviceable) or unserviceable materials that may be left over after the completion of the contract or at its termination for any reason whatsoever, the Contractor shall deliver the said product to the Owner without any demur. The price to be paid to the Contractor, if not already paid either in full or in part, however, shall not exceed the amount mentioned in the Schedule of Rates for such material and in cases where such rates are not so mentioned, shall not exceed the CPWD scheduled rates. In the event of breach of the aforesaid condition the contractor shall become liable for contravention of the terms of the Contract.

5.m.3. The surplus (serviceable) and unserviceable products shall be determined by joint measurement. In case where joint measurement has failed to take place, the Owner may measure the same and determine the quantity. 5.m.4. It is made clear that the Owner shall not be liable to take stock and keep possession and pay for the surplus and unserviceable stocks and the Owner may direct the Contractor to take back such material brought by the Contractor and becoming surplus and which the Owner may decide to keep and not to pay for the same. 5.n. DEFECT LIABILITY PERIOD The contractor shall guarantee the work executed for a period of 12 months from the date of completion of the job. Any damage or defect that may arise or lie undiscovered at the time of completion of the job shall be rectified or replaced by the contractor at his own cost. The decision of the Engineer In-charge/Site-Incharge/Owner shall be the final in deciding whether the defect has to be rectified or replaced. Equipment or spare parts replaced under warranty/guarantees shall have further warranty for a mutually agreed period from the date of acceptance. The owner shall intimate the defects noticed in writing by a Registered A.D. letter or otherwise and the contractor within 15 days of receipt of the intimation shall start the rectification work and complete within the time specified by the owner failing which the owner will get the defects rectified by themselves or by any other contractor and the expenses incurred in getting the same done shall be paid by the Contractor under the provision of the Contract. Thus, defect liability is applicable only in case of job/works contract (civil, mechanical, electrical, maintenance etc. ) where any damage of defect may arise in future (i.e. within 12 months from the date of completion of job) or lie undiscovered at the time of completion of job. In other words, in case of service contracts (like car hire etc.) where there is no question of damage or defect arising in future, the defect liability clause is not applicable. 5.o. DAMAGE TO PROPERTY 5.o.1. Contractor shall be responsible for making good to the satisfaction of the Owner any loss of and any damage to all structures and properties belonging to the Owner or being executed or procured by the Owner or of other agencies within the premises of the work of the Owner, if such loss or damage is due to fault and/or the negligence or willful acts or omission of the Contractor, his employees, agents, representatives or sub-contractors. 5.o.2. The Contractors shall indemnify and keep the Owner harmless of all claims for damage to Owner's property arising under or by reason of this contract.

6. DUTIES AND RESPONSIBILITIES OF CONTRACTOR 6.a. EMPLOYMENT LIABILITY TOWARDS WORKERS EMPLOYED BY THE CONTRACTOR 6.a.1 The Contractor shall be solely and exclusively responsible for engaging or employing persons for the execution of work. All persons engaged by the contractor shall be on Contractor's payroll and paid by Contractor. All disputes or differences between the Contractor and his/their employees shall be settled by Contractor. 6.a.2. Owner has absolutely no liability whatsoever concerning the employees of the Contractor. The Contractor shall indemnify Owner against any loss or damage or liability arising out of or in the course of his/their employing persons or relation with his/their employees. The Contractor shall make regular and full payment of wages and on any complaint by any employee of the Contractor or his sub contractor regarding non-payment of wages, salaries or other dues, Owner reserves the right to make payments directly to such employees or sub- contractor of the Contractor and recover the amount in full from the bills of the Contractor and the contractor shall not claim any compensation or reimbursement thereof. The Contractor shall comply with the Minimum Wages Act applicable to the area of work site with regard to payment of wages to his employees and also to employees of his sub contractor. 6.a.3. The Contractor shall advise in writing or in such appropriate way to all of his employees and employees of sub-contractors and any other person engaged by him that their appointment/employment is not by the Owner but by the Contractor and that their present appointment is only in connection with the construction contract with Owner and that therefore, such an employment/appointment would not enable or make them eligible for any employment/appointment with the Owner either temporarily or/and permanent basis. 6.b. NOTICE TO LOCAL BODIES The contractor shall comply with and give all notices required under any Government authority, instruction, rule or order made under any act of parliament, state laws or any regulations or by-laws of any local authority relating to the works. 6.c. FIRST AID AND INDUSTRIAL INJURIES 6.c.1 Contractor shall maintain first aid facility for his employees and those of his sub-contractors. 6.c.2. Contractor shall make arrangements for ambulance service and for the treatment of all types of injuries. Names and telephone numbers of those providing such services shall be furnished to Owner prior to start of construction and their name board shall be prominently displayed in Contractor's field office. 6.c.3. All industrial injuries shall be reported promptly to owner and a copy of contractor's report covering each personal injury requiring the attention of a physician shall be furnished to the Owner.

6.d. SAFETY CODE 6.d.1. The Contractor shall at his own expenses arrange for the Safety provisions as may be necessary for the execution of the work or as required by the Engineer-in-Charge in respect of all labours directly or indirectly employed for performance of the works and shall provide all facilities in connections therewith. In case the contractor fails to make arrangements and provide necessary facilities as aforesaid, the Owner shall be entitled to do so and recover the cost thereof from the Contractor. 6.d.2. From the commencement to the completion of the works, the contractor shall take full responsibility for the care thereof and of all the temporary works (defined as meaning all temporary works of every kind required in or for the execution, completion or maintenance of the works). In case damage, loss or injury shall happen to the works or to any part thereof or to temporary works or to any cause whatsoever repair at his (Contractor's) own cost and make good the same so that at the time of completion, the works shall be in good order and condition and in conformity in every respect with the requirement of the contract and Engineer-in-Charge's instructions. 6.d.3. In respect of all labour, directly or indirectly employed in the work for the performance of the Contractor's part of this agreement, the contractor shall at his own expense arrange for all the safety provisions as per relevant Safety Codes of C.P.W.D Bureau of Indian Standards, the Electricity Act/I.E. Rules. The Mines Act and such other Acts as applicable. 6.d.4. The Contractor shall observe and abide by all fire and safety regulations of the Owner. Before starting construction work, the Contractor shall consult with Owner's Safety Engineer or Engineer-in-Charge/Site-in-Charge and must make good to the satisfaction of the Owner any loss or damage due to fire to any portion of the work done or to be done under this agreement or to any of the Owner's existing property. 6.d.5. The Contractor will be fully responsible for complying with all relevant provisions of the Contract Labour Act and shall pay rates of Wages and observe hours of work/conditions of employment according to the rules in force from time to time. 6.d.6. The Contractor will be fully responsible for complying with the provision including documentation and submission of reports on the above to the concerned authorities and shall indemnify the Corporation from any such lapse for which the Government will be taking action against them. 6.d.7. Owner shall on a report having been made by an inspecting Office as defined in the Contract Labour Regulations have the power to deduct from the money due to the Contractor any sum required or estimated to be required for making good the loss suffered by a worker(s) by reasons of non-fulfillment of conditions of contract for the benefit of workers no-payment of wages or of deductions made from his or their wages which are not justified by the terms of contract or non observance of the said contractor's labour Regulation. 6.e. INSURANCE AND LABOUR Contractor shall at his own expense obtain and maintain an insurance policy with a Nationalised Insurance Company to the satisfaction of the Owner as provided hereunder.

6.e.1. EMPLOYEES STATE INSURANCE ACT i. The Contractor agrees to and does hereby accept full and exclusive liability for the compliance with all obligations imposed by Employees State Insurance Act, 1948, and the Contractor further agrees to defend indemnify and hold Owner harmless from any liability or penalty which may be imposed by the Central, State or local authority by reason of any asserted violation by Contractor, or sub-contractor of the Employees' State Insurance Act, 1948 and also from all claims, suits or proceedings that may be brought against the Owner arising under, growing out of or by reason of the work provided for by this contract whether brought by employees of the Contractor, by third parties or by Central or State Government authority or any political sub-division thereof. ii. The Contractor agrees to file with the Employees State Insurance Corporation, the Declaration forms and all forms which may be required in respect of the Contractor's or sub-contractor's employee whose aggregate emuneration is within the specified limit and who are employed in the work provided or those covered by ESI Act under any amendment to the Act from time to time. The Contractor shall deduct and secure the agreement of the sub-contractor to deduct the employee's contribution as per the first schedule of the Employee's State Insurance Act from wages and affix the employee's contribution cards at wages payment intervals. The Contractor shall remit and secure the agreement of the sub contractor to remit to the State Bank of India, Employee's State Insurance Corporation Account, the Employee's contribution as required by the Act. iii. The Contractor agrees to maintain all records as required under the Act in respect of employees and payments and the Contractor shall secure the agreement of the sub contractor to maintain such records. Any expenses incurred for the contributions, making contribution or maintaining records shall be to the Contractor's or sub-contractor's account. iv. The Owner shall retain such sum as may be necessary from the total contract value until the Contractor shall furnish satisfactory proof that all contributions as required by the Employees State Insurance Act, 1948, have been paid.

v. WORKMAN'S COMPENSATION AND EMPLOYEE'S LIABILITY INSURANCE Provide Insurance for all the Contractor's employees engaged in the performance of this contract. If any of the work is sublet, the Contractor shall ensure that the sub contractor provides workmen's compensation and Employer's Liability Insurance for the latter's employees who are not covered under the Contractor's insurance. vi. AUTOMOBILE LIABILITY INSURANCE Contractor shall take out an Insurance to cover all risks to Owner for each of his vehicles plying on works of this contract and these insurances shall be valid for the total contract period. No extra payment will be made for this insurance. Owner shall not be liable for any damage or loss not made good by the Insurance Company, should such damage or loss result from unauthorised use of the vehicle. The provisions of the Motor Vehicle Act would apply.

vii. FIRE INSURANCE Contractor shall within two weeks after award of contract insure the Works, Plant and Equipment and keep them insured until the final completion of the Contract against loss or damage by accident, fire or any other cause with an insurance company to be approved by the Employer/Consultant in the joint names of the Employer and the Contractor (name of the former being placed first in the Policy). Such Policy shall cover the property of the Employer only. 6.e.2. ANY OTHER INSURANCE REQUIRED UNDER LAW OR REGULATION OR BY OWNER i. Contractor shall also provide and maintain any and all other insurance which may be required under any law or regulations from time to time. He shall also carry and maintain any other insurance which may be required by the Owner. ii. The aforesaid insurance policy/policies shall provide that they shall not be cancelled till the Engineer-in-Charge has agreed to their cancellation. iii. The Contractor shall satisfy to the Engineer-in-Charge/Site-in-Charge from time to time that he has taken out all insurance policies referred to above and has paid the necessary premium for keeping the policies alive till the expiry of the defects liability period. iv. The contractor shall ensure that similar insurance policies are taken out by his sub-contractor (if any) and shall be responsible for any claims or losses to the Owner resulting from their failure to obtain adequate insurance protections in connection thereof. The contractor shall produce or cause to be proceed by his sub-contractor (if any) as the case may be, the relevant policy or policies and premium receipts as and when required by the Engineer-in-Charge/Site-in-Charge. 6.e.3. LABOUR AND LABOUR LAWS i. The contractor shall at his own cost employ persons during the period of contract and the persons so appointed shall not be construed under any circumstances to be in the employment of the Owner. ii. All payments shall be made by the contractor to the labour employed by him in accordance with the various rules and regulations stated above. The contractor shall keep the Owner indemnified from any claims whatsoever inclusive of damages/costs or otherwise arising from injuries or alleged injuries to or death of a person employed by the contractor or damages or alleged damages to the property. iii. No labour below the age of eighteen years shall be employed on the work. The Contractor shall not pay less than what is provided under the provisions of the contract labour (Regulations and Abolition) Act, 1970 and the rules made thereunder and as may be amended from time to time. He shall pay the required deposit under the Act appropriate to the number of workman to be employed by him or through sub contractor and get himself registered under the Act. He shall produce the required Certificates to the Owner before commencement of the work. The Owner recognises only the Contractor and not his sub contractor under the provisions of the Act. The Contractor will have to submit daily a list of his workforce. He will also keep the wage register at the work site or/and produce the same to the Owner, whenever desired. A deposit may be taken by the Owner from the Contractor to be refunded only after the Owner is satisfied that all workmen employed by the Contractor have been fully paid for the period of work in Owner's premises at rates equal to or better than wages provided for under the Minimum Wages Act. The contractor shall be responsible and liable for any complaints that may arise in this regard and the consequences thereto.

iv. The Contractor will comply with the provisions of the Employee's Provident Fund Act and the Family Pension Act as may be applicable and as amended from time to time. v. The Contractor will comply with the provisions of the payment of Gratuity Act, 1972, as may be applicable and as amended from time to time. vi. IMPLEMENTATION OF APPRENTICES ACT, 1961 The Contractor shall comply with the provisions of the Apprentices Act, 1961 and the Rules and Orders issued thereunder from time to time. If he fails to do so, his failure will be a breach of the contract and the Engineer-in-Charge may, at his discretion, cancel the contract. The Contractor shall also be liable for any pecuniary liability arising on account of any violation by him of the provision of the Act. vii. MODEL RULES FOR LABOUR WELFARE The Contractor shall at his own expenses comply with or cause be complied with Model rules for Labour Welfare as appended to those conditions or rules framed by the Government from time to time for the protection of health and for making sanitary arrangements for worker employed directly or indirectly on the works. In case the contractor fails to make arrangements as aforesaid the Engineer-in-Charge/Site-in-Charge shall be entitled to do so and recover the cost thereof from the contractor. 6.f. DOCUMENTS CONCERNING WORKS 6.f.1. All documents including drawings, blue prints, tracings, reproducible models, plans, specifications and copies, thereof furnished by the Owner as well as all drawings, tracings, reproducibles, plans, specifications design calculations etc. prepared by the contractor for the purpose of execution of works covered in or connected with this contract shall be the property of the Owner and shall not be used by the contractor for any other work but are to be delivered to the Owner at the completion or otherwise of the contract. 6.f.2. The Contractor shall keep and maintain secrecy of the documents, drawings etc. issued to him for the execution of this contract and restrict access to such documents, drawings etc. and further the Contractor shall execute a SECRECY agreement from each or any person employed by the Contractor having access to such documents, drawings etc. The Contractor shall not issue drawings and documents to any other agency or individual without the written approval by the Engineer-inCharge/Site-in- Charge. 6.f.3. Contractor will not give any information or document etc. concerning details of the work to the press or a news disseminating agency without prior written approval from Engineer-incharge/Site-in-Charge. Contractor shall not take any pictures on site without written approval of Engineer-in-Charge/Site-in-Charge. 7. PAYMENT OF CONTRACTOR'S BILLS ®7.1. Payments will be made against Running Accounts bills certified by the Owner's Engineer-inCharge/Site-in-Charge within 15 days from the date of receipt of the bill.. 7.2. Running Account Bills and the final bill shall be submitted by the Contractor together with the duly signed measurements sheet(s) to the Engineer-in-Charge/ Site-in-Charge of the Owner in quadruplicate for certification.

The Bills shall also be accompanied by quantity calculations in support of the quantities contained in the bill along with cement consumption statement, actual/theoretical, wherever applicable duly certified by the Engineer-in-Charge/ Site-in-Charge of the Owner. 7.3. All running account payments shall be regarded as on account payment(s) to be finally adjusted against the final bill payment. Payment of Running Account Bill(s) shall not determine or affect in any way the rights of the Owner under this Contract to make the final adjustments of the quantities of material, measurements of work and adjustments of amounts etc.etc. in the final bill. 7.4. The final bill shall be submitted by the Contractor within one month of the date of completion of the work fully and completely in all respects. If the Contractor fails to submit the final bill accordingly Engineer-in-Charge/Site-in-Charge may make the measurement and determine the total amount payable for the work carried out by the Contractor and such a certification shall be final and binding on the Contractor. The Owner/Engineer- in-Charge/Site-in-Charge may take the assistance of an outside party for taking the measurement, the expenses of which shall be payable by the Contractor. 7.5. Payment of final bill shall be made within 30 days from the date of receipt of the certified bill by the Disbursement Section of the owner. ®7.6 Wherever possible, payment shall be tendered to the contractor in electronic mode (epayment) through any of the designated banks. The contractor will comply by furnishing full particulars of Bank acount (mandate) to which the payments will be routed. Owner reserves the right to make payment in any alternate mode also. 7.a. MEASUREMENT OF WORKS 7.a.1. All measurements shall be in metric system. All the works will be jointly measured by the representative of the Engineer-in-Charge/Site-in-Charge and the Contractor or their authorised agent progressively. Such measurement will be recorded in the Measurement Book/Measurement Sheet by the Contractor or his authorised representative and signed in token of acceptance by the Owner or their authorised representative. 7.a.2. For the purpose of taking joint measurement, the Contractor/representative shall be bound to be present whenever required by the Engineer-in-Charge/Site-in-Charge. If, however, they are absent for any reasons whatsoever, the measurement will be taken by the Engineer-in-Charge/Site-in-Charge or his representative and the same would be deemed to be correct and binding on the Contractor. 7.a.3. In case of any dispute as to the mode of measurement for any item of work, the latest Indian Standard Specifications shall be followed. In case of any further dispute on the same the same shall be as per the certification of an outside qualified Engineer/ Consultant. Such a measurement shall be final and binding on the Owner and the Contractor.

7.b. BILLING OF WORKS EXECUTED The Contractor will submit a bill in approved proforma in quadruplicate to the Engineer-inCharge/Site-in-Charge of the work giving abstract and detailed measurement for the various items executed during a month, before the expiry of the first week of the succeeding month. The Engineer-in-Charge/Site-in-Charge shall take or cause to be taken the requisite measurements for the purpose of having the bill verified and/or checked before forwarding the same to the disbursement office of the Owner for further action in terms of the Contract and payment thereafter. The Engineer-in-Charge/Site-in-Charge shall verify the bills within 7 days of submission of the Bill by the Contractor. 7.c. RETENTION MONEY 10% of the total value of the Running Account and Final Bill will be deducted and retained by the Owner as retention money on account of any damage/defect liability that may arise for the period covered under the defect liability period clause of the Contract free of interest. Any damage or defect that may arise or lie undiscovered at the time of issue of completion certificate connected in any way with the equipment or materials supplied by contractor or in workmanship shall be rectified or replaced by the contractor at his own expense failing which the Owner shall be entitled to rectify the said damage/defect from the retention money. Any excess of expenditure incurred by the Owner on account of damage or defect shall be payable by the Contractor. The decision of the Owner in this behalf shall not be liable to be questioned but shall be final and binding on the Contractor. Thus, deduction towards retention money is applicable only in case of job/works contracts (civil, mechanical, electrical, maintenance etc.) where any damage or defect may arise in future (i.e. within 12 months from the date of completion of job) or lie undiscovered at the time of issue of completion certificate. ®7.d. STATUTORY LEVIES 7.d.1 The Contractor accepts full and exclusive liability for the payment of any and all taxes, duties, octroi, rates, cess, levies and statutory payments payable under all or any of the statutes etc. ® Variations of taxes and duties arising out of the amendments to the Central / State enactments, in respect of sale of goods / services covered under this bid shall be to HPCL’s account, so long as : • They relate to the period after the opening of the price bid, but before the contracted completion period ( excluding permitted extensions due to delay on account of the contractors, if any) or the actual completion period, whichever is earlier; and

• The vendor furnishes documentary evidence of incurrence of such variations, in addition to the invoices/documents for claiming Cenvat /Input Tax credit, wherever applicable. All contributions and taxes for unemployment compensation, insurance and old age pensions or annuities now or hereafter imposed by Central or State Governmental authorities which are imposed with respect to or covered by the wages, salaries or other compensations paid to the persons employed by the Contractor and the Contractor shall be responsible for the compliance with all obligations and restrictions imposed by the Labour Law or any other law affecting employer-employee relationship and the Contractor further agrees to comply and to secure the compliance of all sub-contractors with all applicable Central, State, Municipal and local laws, and regulations and requirements of any Central, State or Local Government agency or authority.

Contractor further agrees to defend, indemnify and hold harmless from any liability or penalty which may be imposed by the Central, State or Local authorities by reason of any violation by Contractor or sub-contractor of such laws, regulations or requirements and also from all claims, suits or proceedings that may be brought against the Owner arising under, growing out of, or by reasons of the work provided for by this contract by third parties, or by Central or State Government authority or any administrative sub-division thereof. The Contractor further agrees that in case any such demand is raised against the Owner, and Owner has no way but to pay and pays/makes payment of the same, the Owner shall have the right to deduct the same from the amounts due and payable to the Contractor. The Contractor shall not raise any demand or dispute in respect of the same but may have recourse to recover/receive from the concerned authorities on the basis of the Certificate of the Owner issued in that behalf. 7.d.2. The rates quoted should be inclusive of all rates, cess, taxes and sales tax on works contracts wherever applicable. However, wherever the sales tax on works contract is applicable and is to be deducted at source, the same will be deducted from the bills of the Contractor and paid to the concerned authorities. The proof of such payments of sales tax on works contract will be furnished to the contractor. 7.d.3. Income tax will be deducted at source as per rules at prevailing rates, unless certificate, if any, for deduction at lesser rate or nil deduction is submitted by the Contractor from appropriate authority. ® 7.d.4 The contractor shall provide accurate particulars of PAN number as required, to enable issuance of TDS (Tax Deduction at Source) certificate. 7.e. MATERIALS TO BE SUPPLIED BY CONTRACTOR 7.e.1. The Contractor shall procure and provide the whole of the materials required for construction including tools, tackles, construction plant and equipment for the completion and maintenance of the works except the materials viz. steel and cement which may be agreed to be supplied as provided elsewhere in the contract. The contractor shall make arrangement for procuring such materials and for the transport thereof at their own cost and expenses. 7.e.2. The Owner may give necessary recommendation to the respective authority if so desired by the Contractor but assumes no responsibility of any nature. The Contractor shall procure materials of ISI stamp/certification and supplied by reputed suppliers borne on DGS&D list. 7.e.3. All materials procured should meet the specifications given in the tender document. The Engineer-in-charge may, at his discretion, ask for samples and test certificates for any batch of any materials procured. Before procuring, the Contractor should get the approval of Engineer-inCharge/Site-in-Charge for any materials to be used for the works. 7.e.4. Manufacturer's certificate shall be submitted for all materials supplied by the Contractor. If, however, in the opinion of the Engineer-in-Charge/Site-in-Charge any tests are required to be conducted on the material supplied by the Contractor, these will be arranged by the Contractor promptly at his own cost.

7.f. MATERIALS TO BE SUPPLIED BY THE OWNER 7.f.1. Steel and Cement maybe supplied by the Owner to the contractor against payment by Contractor from either godown or from the site or within work premises itself and the contractor shall arrange for all transport to actual work site at no extra cost. 7.f.2. The contractor shall bear all the costs including loading and unloading, carting from issue points to work spot storage, unloading, custody and handling and stacking the same and return the surplus steel and cement to the Owner's storage point after completion of job. 7.f.3. The contractor will be fully accountable for the steel and cement received from the Owner and contractor will give acknowledgement/receipt for quantity of steel and cement received by him each time he uplifts cement from Owner's custody. 7.f.4. For all computation purposes, the theoretical cement consumption shall be considered as per CPWD standards. 7.f.5. Steel and Cement as received from the manufacturer/stockists will be issued to the contractor. Theoretical weight of cement in a bag will be considered as 50 Kg. Bags weighing upto 4% less shall be accepted by the contractor and considered as 50 Kg. per bag. Any shortage in the weight of any cement bag by more than 4% will be to the Owner's account only when pointed out by the Contractor and verified by Engineer-in-Charge/Site in Charge at the time of Contract or taking delivery. 7.f.6. The contractor will be required to maintain a stock register for receipt, issuance and consumption of steel and cement at site. Cement will be stored in a warehouse at site. Requirement of cement on any day will be taken out of the warehouse. Cement issued shall be regulated on the basis of FIRST RECEIPT to go as FIRST ISSUE. 7.f.7. Empty cement bag shall be the property of the Contractor. Contractor shall be penalised for any excess/under consumption of cement. The penal rate will be twice the rate of issue of cement for this work. 7.f.8. All the running bills as well as the final bills will be accompanied by cement consumption statements giving the detailed working of the cement used, cement received and stock-on-hand. 7.f.9. The Contractor will be fully responsible for safe custody of cement once it is received by him and during transport. Owner will not entertain any claims of the contractor for theft, loss or damage to cement while in their custody. 7.f.10. The contractor shall not remove from the site any cement bags at any time. 7.f.11. The Contractor shall advise Engineer-in-charge/Site-in-charge in writing atleast 21 days before exhausting the Cement stocks already held by Contractor to ensure that such delays do not lead to interruptions in the progress of work. 7.f.12. Cement shall not be supplied by the Owner for manufacturing of mosaic tiles, precast cement jali and any other bought out items which consume cement and for temporary works.

7.f.13. Cement in bags and in good usable condition left over after the completion of work shall be returned by the contractor to the Owner. The Owner shall make payment to the Contractor at the supply rate for such stocks of cement they accept and receive. Any refused stock of cement shall be removed by the Contractor from the site at his cost and expenses within 15 days of completion of the work. 8. PAYMENT OF CLAIMS AND DAMAGES 8.1. Should the Owner have to pay money in respect of claims or demands as aforesaid the amount so paid and the costs incurred by the Owner shall be charged to and paid by the Contractor and the Contractor shall not be entitled to dispute or question the right of the Owner to make such payments notwithstanding the same may have been without his consent or authority or in law or otherwise to the contrary. 8.2. In every case in which by virtue of the provisions of Workmen's Compensation Act, 1923, or other Acts, the Owner is obliged to pay Compensation to a Workman employed by the Contractor in execution of the works, the Owner will recover from the Contractor the amount of compensation so paid and without prejudice to the rights of Owner under the said Act. Owner shall be at liberty to recover such amount or any part thereof by deducting it from the security deposit or from any sum due to the Contractor whether under this contract or otherwise. The Owner shall not be bound to contest any claim made under Section 12 sub section (1) of the said Act, except on the written request of the Contractor and upon his giving to the Owner full security for all costs for which the owner might become liable in consequence of contesting such claim. 8.a. ACTION AND COMPENSATION IN CASE OF BAD WORK If it shall appear to the Engineer-in-Charge/Site-in-Charge that any work has been executed with bad, imperfect or unskilled workmanship, or with materials, or that any materials or articles provided by the Contractor for execution of the work are not of standards specified/inferior quality to that contracted for, or otherwise not in accordance with the contract, the CONTRACTOR shall on demand in writing from the Engineer-in-Charge/Site-in-Charge or his authorised representative specifying the work, materials or articles complained of, notwithstanding that the same may have been inadvertently passed, certified and paid for, forthwith rectify or remove and reconstruct the work so specified and at his own charge and cost and expenses and in the event of failure to do so within a period of 15 days of such intimation/ information/knowledge, the Contractor shall be liable to pay compensation equivalent to the cost of reconstruction by the Owner. On expiry of 15 days period mentioned above, the Owner may by themselves or otherwise rectify or remove and reexecute the work or remove and replace with others, the materials or articles complained of as the case may be at the risk and expenses in all respects of the Contractor. The decision of the Engineerin- Charge/ Site-in-Charge as to any question arising under this clause shall be final and conclusive and shall not be raised as a dispute or shall be arbitrable. 8.b. INSPECTION AND AUDIT OF CONTRACT AND WORKS This project is subject to inspection by various Government agencies of Government of India. The contractor shall extend full cooperation to all the Government and other agencies in the inspection of the works, audit of the Contract and the documents of Contract Bills, measurements sheets etc. etc. And examination of the records of works and make enquiries interrogation as they may deem fit, proper and necessary. Upon inspection etc. by such agencies if it is pointed out that the contract work has not been carried out according to the prescribed terms and conditions as laid down in the tender documents and if any recoveries are recommended, the same shall be recovered from the contractors running bills/final bill/from ordered/suggested Security Deposit/retention money.

The Contractor shall not rise any dispute on any such account and the same shall not be arbitrable. 9. CONTRACTOR TO INDEMNIFY THE OWNER The Contractor shall indemnify the Owner and every member, officer and employee of the Owner, also the Engineer-in-Charge/Site-in-Charge and his staff against all the actions, proceedings, claims, demands, costs, expenses, whatsoever arising out of or in connection with the works and all actions, proceedings, claims, demands, costs, expenses which may be made against the Owner for or in respect of or arising out of any failure by the Contractor in the performance of his obligations under the contract. The Contractor shall be liable for or in respect of or in consequence of any accident or injury to any workmen or other person in the employment of the Contractor or his sub contractor and Contractor shall indemnify and keep indemnified the Owner against all such damages, proceedings, costs, charges and expenses whatsoever in respect thereof or in relation thereto. 10. LIQUIDATED DAMAGES ® i) In case of any delay in completion of the work beyond the CDD, the Owner shall be entitled to be paid Liquidated Damages by the Contractor. The liquidated damages shall be initially at the rate of 0.5% (half percent) of the total contract value for every week of the delay subject to a maximum of 5% of the total contract value. The liquidated damages shall be recovered by the Owner out of the amounts payable to the Contractor or from any Bank Guarantees or Deposits furnished by the Contractor or the Retention Money retained from the Bills of the Contractor, either under this contract or any other contract. ii) The Contractor shall be entitled to give an acceptable unconditional Bank Guarantee in lieu of such a deduction if Contractor desires any decision on a request for time extension. iii) Once a final decision is taken on the request of the Contractor or otherwise, the LD shall be applicable only on the basic cost of the contract and on each full completed week(s) of delay (and for part of the week, a pro-rata LD amount shall be applicable). iv) This final calculation of LD shall be only on the value of the unexecuted portion/quantity of work as on the CDD. v) Contractor agrees with the Owner, that the above represents a genuine pre-estimate of the damages which the Owner will suffer on account of delay in the performance of the work by Contractor. The Contractor further agrees that the LD amount is over and above any right which owner has to risk purchase under Clause 12.4 and any right to get the defects in the work rectified at the cost of the contractor. 11. DEFECTS AFTER TAKING OVER OR TERMINATION OF WORK CONTRACT BY OWNER The Contractor shall remain responsible and liable to make good all losses or damages that may occur/appear to the work carried out under this Contract within a period of 12 months from date of issue of the Completion Certificate and/or the date of Owner taking over the work, which ever is earlier. The Contractor shall issue a Bank Guarantee to the Owner in the sum of 10% of the work entrusted in the Contract, from any nationalised Bank acceptable to the Owner and if however, the Contractor fails to furnish such a Bank Guarantee the Owner shall have right to retain the Security Deposit and Retention Money to cover the 10% of the Guarantee amount under this clause and to return/refund the same after the expiry of the period of 12 months without any interest thereon.

12. TERMINATION OF CONTRACT 12.1 The owner may terminate the contract at any stage of the construction for reasons to be recorded in the letter of termination. 12.2 The Owner inter alia may terminate the Contract for any or all of the following reasons that the contractor a) has abandoned the work/Contract. b) has failed to commence the works, or has without any lawful excuse under these conditions suspended the work for 15 consecutive days. c) has failed to remove materials from the site or to pull down and replace the work within 15 days after receiving from the Engineer written notice that the said materials or work were condemned and/or rejected by the Engineer under specified conditions. d) has neglected or failed to observe and perform all or any of the terms acts, matters or things under this Contract to be observed and performed by the Contractor. e) has to the detriment of good workmanship or in defiance of the Engineer's instructions to the contrary sub-let any part of the Contract. f) has acted in any manner to the detrimental interest, reputation, dignity, name or prestige of the Owner. g) has stopped attending to work without any prior notice and prior permission for a period of 15 days. h) has become untraceable. i) has without authority acted in violation of the terms and conditions of this contract and has committed breach of terms of the contract in best judgement of the owner. j) has been declared insolvent/bankrupt. k) in the event of sudden death of the Contractor. 12.3 The owner on termination of such contract shall have the right to appropriate the Security Deposit, Retention Money and invoke the Bank Guarantee furnished by the contractor and to appropriate the same towards the amounts due and payable by the contractor as per the conditions of Contract and return to the contractor excess money, if any, left over. ® 12.4 In case of Termination of the contract, Owner shall have the right to carry out the unexecuted portion of the work either by themselves or through any other contractor(s) at the risk and cost of the Contractor. In view of paucity of time, Owner shall have the right to place such unexecuted portion of the work on any nominated contractor(s). However, the overall liability of the Contractor shall be restricted to 100 % of the total contract value. 12.5 The contractor within or at the time fixed by the Owner shall depute his authorised representative for taking joint final measurements of the works executed thus far and submit the final bill for the work as per joint final measurement within 15 days of the date of joint final measurement. If the contractor fails to depute their representative for joint measurement, the owner shall take the measurement with their Engineer-in-Charge/Site-in-Charge or any other outside representatives. Such a measurement shall not be questioned by the Contractor and no dispute can be raised by the Contractor for purpose of Arbitration.

12.6 The Owner may enter upon and take possession of the works and all plant, tools, scaffoldings, sheds, machinery, power operated tools and steel, cement and other materials of the Contract at the site or around the site and use or employ the same for completion of the work or employ any other contractor or other person or persons to complete the works. The Contractor shall not in any way object or interrupt or do any act, matter or thing to prevent or hinder such actions, other Contractor or other persons employed for completing and finishing or using the materials and plant for the works. When the works shall be completed or as soon thereafter the Engineer shall give a notice in writing to the Contractor to remove surplus materials and plant, if any, and belonging to the Contractor except as provided elsewhere in the Contract and should the Contractor fail to do so within a period of 15 days after receipt thereof the Owner may sell the same by public auction and shall give credit to the contractor for the amount realised. The Owner shall thereafter ascertain and certify in writing under his hand what (if anything) shall be due or payable to or by the Owner for the value of the plant and materials so taken possession and the expense or loss which the Owner shall have been put to in procuring the works, to be so completed, and the amount if any, owing to the Contractor and the amount which shall be so certified shall thereupon be paid by the Owner to the Contractor or by the Contractor to the Owner, as the case may, and the Certificate of the Owner shall be final and conclusive between the parties. 12.7 When the contract is terminated by the Owner for all or any of the reasons mentioned above the Contractor shall not have any right to claim compensation on account of such termination. 13. FORCE MAJEURE 13.1. Any delay in or failure of the performance of either part hereto shall not constitute default hereunder or give rise to any claims for damage, if any, to the extent such delays or failure of performance is caused by occurrences such as Acts of God or an enemy, expropriation or confiscation of facilities by Government authorities, acts of war, rebellion, sabotage or fires, floods, explosions, riots, or strikes. The Contractor shall keep records of the circumstances referred to above and bring these to the notice of the Engineer-in-Charge/Site-in-Charge in writing immediately on such occurrences. The amount of time, if any, lost on any of these counts shall not be counted for the Contract period. Once decision of the Owner arrived at after consultation with the Contractor, shall be final and binding. Such a determined period of time be extended by the Owner to enable the Contractor to complete the job within such extended period of time. 13.2. If Contractor is prevented or delayed from the performing any of its obligations under this Agreement by Force Majeure, then Contractor shall notify Owner the circumstances constituting the Force Majeure and the obligations performance of which is thereby delayed or prevented, within seven days of the occurrence of the events. 14. ARBITRATION 14.1 All disputes and differences of whatsoever nature, whether existing or which shall at any time arise between the parties hereto touching or concerning the agreement, meaning, operation or effect thereof or to the rights and liabilities of the parties or arising out of or in relation thereto whether during or after completion of the contract or whether before after determination, foreclosure, termination or breach of the agreement (other than those in respect of which the decision of any person is, by the contract, expressed to be final and binding) shall, after written notice by either party to the agreement to the other of them and to the Appointing Authority hereinafter mentioned, be referred for adjudication to the Sole Arbitrator to be appointed as hereinafter provided.

®14.2 The appointing authority shall either himself act as the Sole Arbitrator or nominate some officer/retired officer of Hindustan Petroleum Corporation Limited (referred to as owner or HPCL) or a retired officer of any other Government Company in the Oil Sector of the rank of Ch. Manager & above or any retired officer of the Central Government not below the rank of a Director, to act as the Sole Arbitrator to adjudicate the disputes and differences between the parties. The contractor/vendor shall not be entitled to raise any objection to the appointment of such person as the Sole Arbitrator on the ground that the said person is/was an officer and/or shareholder of the owner, another Govt. Company or the Central Government or that he/she has to deal or had dealt with the matter to which the contract relates or that in the course of his/her duties, he/she has/had expressed views on all or any of the matters in dispute or difference. 14.3 In the event of the Arbitrator to whom the matter is referred to, does not accept the appointment, or is unable or unwilling to act or resigns or vacates his office for any reasons whatsoever, the Appointing Authority aforesaid, shall nominate another person as aforesaid, to act as the Sole Arbitrator. 14.4 Such another person nominated as the Sole Arbitrator shall be entitled to proceed with the arbitration from the stage at which it was left by his predecessor. It is expressly agreed between the parties that no person other than the Appointing Authority or a person nominated by the Appointing Authority as aforesaid, shall act as an Arbitrator. The failure on the part of the Appointing Authority to make an appointment on time shall only give rise to a right to a Contractor to get such an appointment made and not to have any other person appointed as the Sole Arbitrator. 14.5 The Award of the Sole Arbitrator shall be final and binding on the parties to the Agreement. 14.6 The work under the Contract shall, however, continue during the Arbitration proceedings and no payment due or payable to the concerned party shall be withheld (except to the extent disputed) on account of initiation, commencement or pendency of such proceedings. 14.7 The Arbitrator may give a composite or separate Award(s) in respect of each dispute or difference referred to him and may also make interim award(s) if necessary. ®14.8 The fees of the Arbitrator and expenses of arbitration, if any, shall be borne equally by the parties unless the Sole Arbitrator otherwise directs in his award with reasons. The lumpsum fees of the Arbitrator shall be Rs. 40,000/- per case for transportation contracts and Rs. 60,000/- for engineering contracts and if the sole Arbitrator completes the arbitration including his award within 5 months of accepting his appointment, he shall be paid Rs. 10,000/- additionally as bonus. Reasonable actual expenses for stenographer, etc. will be reimbursed. Fees shall be paid stagewise i.e. 25% on acceptance, 25% on completion of pleadings/documentation, 25% on completion of arguments and balance on receipt of award by the parties 14.9 Subject to the aforesaid, the provisions of the Arbitration and Conciliation Act, 1996 or any statutory modification or re-enactment thereof and the rules made thereunder, shall apply to the Arbitration proceedings under this Clause. 14.10 The Contract shall be governed by and constructed according to the laws in force in India. The parties hereby submit to the exclusive jurisdiction of the Courts situated at say Mumbai for all purposes. The Arbitration shall be held at Mumbai and conducted in English language.

14.11 The Appointing Authority is the Functional Director of Hindustan Petroleum Corporation Limited. 15. GENERAL 15.1. Materials required for the works whether brought by the or supplied by the Owner shall be stored by the contractor only at places approved by Engineer-in-Charge/Site-in-Charge. Storage and safe custody of the material shall be the responsibility of the Contractor. 15.2. Owner and/or Engineer-in-Charge/Site-in-Charge connected with the contract, shall be entitled at any time to inspect and examine any materials intended to be used in or on the works, either on the site or at factory or workshop or at other place(s) manufactured or at any places where these are laying or from which these are being obtained and the contractor shall give facilities as may be required for such inspection and examination. 15.3. In case of any class of work for which there is no such specification supplied by the owner as is mentioned in the tender documents, such work shall be carried out in accordance with Indian Standard Specifications and if the Indian Standard Specifications do not cover the same the work should be carried out as per standard Engineering practice subject to the approval of the Engineerin-Charge/Site-in-Charge. 15.4. Should the work be suspended by reason of rain, strike, lockouts or other cause the contractor shall take all precautions necessary for the protection of the work and at his own expense shall make good any damages arising from any of these causes. 15.5 The contractor shall cover up and protect from injury from any cause all new work also for supplying all temporary doors, protection to windows and any other requisite protection for the whole of the works executed whether by himself or special tradesmen or sub- contractors and any damage caused must be made good by the contractors at his own expense. 15.6 If the contractor has quoted the items under the deemed exports, then it will be the responsibility of the contractor to get all the benefits under deemed exports from the Government. The Owner’s responsibility shall only be limited to the issuance of required certificates. The quotation will be unconditional and phrases like “subject to availability of deemed exports benefit” etc. will not find place in it. ®16. Integrity Pact : Effective 1st September, 2007, all tenders and contracts shall comply with the requirements of the Integrity Pact (IP) if the value of such tenders or contracts exceed Rs.1 crore. Failure to sign the Integrity Pact shall lead to outright rejection of bid. # 17. Grievances of parties participating or intend to participate in the tender shall be addressed in writing to the officer designate of the Grievance Redressal Cell where the tenders have to be submitted within the stipulated period. Detailed mechanism of Grievance Redressal is available on the HPCL website.

SECTION-5

BID FORM To: Date M/s Hindustan Petroleum Corporation Limited Mumbai Gentlemen, Having examined the Conditions of Contract and Specifications including Addenda Nos (Insert Numbers) the receipt of which is hereby duly acknowledged, we the undersigned, offer to supply and deliver (Description of Goods and Services) in conformity with the said Drawings, Conditions of Contract and specifications, for the sum as quoted in e-tender We undertake if our bid is accepted, complete delivery of items as agreed and specified in the RFQ document. If our bid is accepted we will obtain the guarantee of a Bank in a sum not exceeding (10)% of the Contract price for the due performance of the Contract. We agree to abide by this bid for a period of 120 days from the date fixed for bid opening under Instructions to Bidders and it shall remain binding upon us and may be accepted at any time before the expiration of that period. Until a formal contract is prepared and executed, this bid, together with your written acceptance thereof in your notification of award (Fax of Intent ) shall constitute a binding Contract between us. We understand that you are not bound to accept the lowest or any bid, you may receive. Dated this ___________ Day of _______________ Signature ……………………………………… In the capacity of Duly authorised to sign bid for an on behalf of Witness Address Signature

SECTION-6

AGREED TERMS AND CONDITIONS This questionnaire duly filled shall be returned along with each copy of Un-priced bid. Clauses confirmed hereunder should not be repeated in the bid. ALL THE COMMERCIAL TERMS AND CONDITIONS SHOULD BE INDICATED IN THIS FORMAT ONLY. IF REQUIRED DETAILS INCLUDING DEVIATION TO GCC, IF ANY, SHOULD BE INDICATED AS AN ANNEXURE TO THIS FORMAT.

In view of the rejection clause no. 16.0 of Section-2, which will be strictly adhered to, bidders are advised to comply to the terms and conditions of the bid document in the First Instance itself. Sl. NO.

DESCRIPTION

1.

Confirm Your Offer is in complete compliance with the scope of work as specified in the Bid document Confirm you have quoted your prices strictly in the applicable Price schedule format (enclosed with the Bid document) along with Unit and Total Prices INSPECTION : Confirm your quoted prices are inclusive of all testing and inspection requirements as specified in the bid document. Confirm acceptance / compliance with the following conditions /clauses of the Bid document (i) Confirm price basis of your offer is strictly in accordance with Bid document.

2.

3. 4.

(ii)

iii) (iv) (v)

(vi)

Confirm You have furnished Bid security (Bank Guarantee) for the requisite amount in the required format as per terms of bid document. Confirm that You shall furnish Security Deposit as per terms of Bid document. Confirm your Firm completion period shall be strictly as per requirement specified in the Bid Document. Confirm that Your offer will remain Valid for acceptance for a period of 120 days from the Bid due date or extended due date (if the same is Extended). Confirm that the quoted rates shall remain FIRM, FIXED & BINDING till complete Execution of Order irrespective of variation in quantities and payment shall be for the actual quantities installed

BIDDER'S CONFIRMATION

Sl. NO.

DESCRIPTION at site. vii)

5. 6. 7. 8.

9.

Confirm that Defect Liability Period shall be as per Bid document. viii) Confirm that the Force Majeure shall be as per Bid document. (ix) Confirm acceptance of Liquidated Damages clause for delay in completion as per Bid document. (x) Confirm total acceptance to Payment Terms as per Bid document (xi) Arbitration clause shall be as per Bid document. xii) Confirm that extension of time shall be as per the bid document Confirm Terms related to Taxes and Duties shall be as per Provisions of Bid document All correspondence must be in English Language Only Owner reserves the right to make any changes in the terms and conditions of bid document. Confirm The Bidder is required to state whether any of the Director's Bidder is a relative of any Director of Owner or the Bidder is a firm in which any Director of Owner or his relative is a partner. (a) Confirm acceptance in Toto of the Terms and Conditions contained in the Bid document (i) Instructions to Bidders. (ii) Special Conditions of Contract (iii) General Conditions of Contract (iv) All other commercial documents / attachments / sections of the bid document (b)

10.

In case of reservations, confirm that clause wise comments have been specified as annexure to this format.

All the terms and conditions have been indicated in this format (including Annexure, if any) and have been repeated in the Bid elsewhere. It is noted that terms and conditions indicated elsewhere including any printed terms and conditions shall not be considered by the owner Furnish Financial Turnover figures of last 3 years

BIDDER'S CONFIRMATION

Sl. NO.

DESCRIPTION

BIDDER'S CONFIRMATION

TURNOVER 2008 - 2009 2007 - 2008 2006 - 2007 In support of above Bidder shall enclose copies of its published Annual reports of preceding 3 years. Confirm compliance. 11. 12.

Bidder shall furnish details of the Concurrent commitments, with their schedule / expected completion dates. Bidder to confirm that all the schedules in eprocurement website of HPCL have been quoted. Please confirm. Bidder must quote all the items of schedule/SOR Please confirm

BIDDERS NAME, ADDRESS, SIGNATURE AND SEAL

Fax No.

Telephone No.

Email Address

SECTION – 7

PROFORMA/ANNEXURES

ANNEXURE-A DECLARATION (To be submitted along with Un priced bid)

(M/s. __________________________) hereby declare / clarify that we have not been banned or delisted by Government of India or any of the Ministries of Government of India . Stamp and Signature of Bidder

ANNEXURE-B BIDDER’S GENERAL INFORMATION Bid Document No. _________________ To Hindustan Petroleum Corporation Limited Mumbai, India. 1.1

Bidder’s Name:

1.2

Number of Years in Operation:___________________________________

1.3

Registered Address ____________________________________

1.4

Operation Address if different from above: _____________________________________

1.5

Telephone Number (Country code) (Area Code) (Tel. Number)

1.6

E-mail address & Web Site

1.7

Telefax Number __________________________________________ (Country Code) (Area Code) (Tel. Number)

1.8

ISO Certification, if any (if yes, please furnish details)

TO BE FILLED BY BIDDERS REGISTERED WITH NSIC 1 NAME OF BIDDER

2 WHETHER REGISTERED WITH NSIC : YES / NO

3 WHETHER COPY OF NSIC CERTIFICATE ENCLOSED : YES / NO

4 NSIC REGISTRATION CERTIFICATE IS VALID UPTO

5 MONETARY LIMIT OF NSIC REGISTRATION CERTIFICATE 6 WHETHER ITEM QUOTED IS COVERED IN NSIC REGISTRATION CERTIFICATE IF YES, PLEASE MENTION THE ITEM NAME IN NSIC CERTIFICATE UNDER WHICH TENDERED ITEM IS COVERED

7 whether you have suceeded in securing orders for same items(item quoted), in competition (i.e. without price preference) with large scale units during the preceeding 12 months (from the date of this tender. (say : yes or no) Sign & stamp of NSIC registered bidder

Annexure – C QUALIFICATION FORMAT - FORM 1 FOR Annual Financial Turnover Bid Document No………………………………….. Year

Annual Turnover in Rs.

2006-2007 2007-2008 2008-2009

Attach copies of audited balance sheets for the year 2006-2007, 2007-2008, 2008-2009

AUDITORS SEAL AND SIGNATURE BIDDERS SEAL AND SIGNATURE

Annexure – C QUALIFICATION FORMAT - FORM 2 FOR Particular Experience Record Bid Document No…………….. (List only works which are similar to the proposed works for which qualification is sought) Should contain only the works completed during the last 7 years ending last day of month previous to the one in which applications are invited Sl. No.

Work Description

Date of award

Date of completion

Value in Rs

Work Order / Completion certificates Furnished furnished Furnished furnished Furnished furnished Furnished furnished Furnished furnished Furnished furnished Furnished furnished

/ not / not / not / not / not / not / not

Work orders and Completion certificates from clients for the above mentioned works shall be provided. In the absence of the above documents details furnished will be ignored. BIDDERS SEAL AND SIGNATURE.

Annexure – C QUALIFICATION FORMAT - FORM 3 QUALIFICATION ASSESSMENT SUMMARY Bid Document No.9000203-HD-10002 (05/51/23LK/HPCL/001(i))

1

2

Meeting PQ Criteria (Yes /No)

Name of the Company with complete postal address, contact numbers, e-mail id, etc.

Annual Financial turn over shall meet the minimum prescribed bid qualification requirement in each of the three financial years 2006-07 2007-08 2008-09 preceding the financial year in which tenders are invited. (as per clause 3.1 Section 1 ). Bidder should have carried out and completed all of the following, within last seven years reckoned from 30-11-09 i) Laying including testing and Pre-commissioning of buried Cross country hydrocarbon Pipeline (coated) of minimum 6” in diameter and minimum 10km length. AND ii) Installation, testing & commissioning of Station Piping and mechanical equipments in petrochemical or hydrocarbon installations with owner supplied material and or contractor supplied material. AND iii) Construction of RCC building directly or by engaging civil contractor. Contract should be in the name of bidder.

(As per cl. No.3.2.1 of Section-1) Client Order No. & date Description of the work Order value in Rs. Lakhs Year of completion Completion / Taking over certificate

Issued by

a)

(Attach Copy of Auditor's Certificate / Annual Reports for 2006-07, 07-08 & 08-09)

(Attach copy of work orders, completion certificates, taking over certificates from client)

(Attach Copy of work order)

Ref. No. Date

3.

Enclosures

Bidder during the last seven years reckoned from 30-11-09, shall have carried out and completed similar work as under (as per clause 3.3.2 Section 1) One single order of similar nature of value not less than

Attach Copy of completion certificates / taking over certificate issued by clients

Rs.13.12 Crores. (Attach Copy of work order)

Client Order No. & date Description of the work Order value in Rs. Lakhs Year of completion Completion / Taking over certificate

Issued by

Ref. No.

Date Attach Copy of completion certificates / taking over certificate issued by clients

b)

Two order of similar nature of value not less than Rs.8.2 Crores

i)

Client Order No. & date Description of the work Order value in Rs. Lakhs Year of completion Completion / Taking over certificate

(Attach Copy of work order)

Issued by

Ref. No.

Date Attach Copy of completion certificates / taking over certificate issued by clients

ii)

(Attach Copy of work order)

Client Order No. & date Description of the work Order value in Rs. Lakhs Year of completion Completion / Taking over certificate

Issued by

Ref. No.

Date Attach Copy of completion certificates / taking over certificate issued by clients

c)

Three order of similar nature of value not less than Rs.6.56 Crores.

i)

Client Order No. & date Description of the work Order value in Rs. Lakhs Year of completion Completion / Taking over

(Attach Copy of work order)

Issued

Ref. No.

Date

certificate

by Attach Copy of completion certificates / taking over certificate issued by clients

ii)

(Attach Copy of work order)

Client Order No. & date Description of the work Order value in Rs. Lakhs Year of completion Completion / Taking over certificate

Issued by

Ref. No.

Date Attach Copy of completion certificates / taking over certificate issued by clients

iii)

(Attach Copy of work order)

Client Order No. & date Description of the work Order value in Rs. Lakhs Year of completion Completion / Taking over certificate

Issued by

Ref. No.

Date Attach Copy of completion certificates / taking over certificate issued by clients

4.

Whether all Bid Qualification norms are met. NOTE : STRIKE OUT WHICH IS NOT APPLICABLE BIDDERS SEAL AND SIGNATURE

BG FORMATS

BANK GUARANTEE FOR PERFORMANCE OF THE OBLIGATIONS OF SUPPLIER / CONTRACTOR (on non-judicial stamp paper of appropriate value) To, Hindustan Petroleum Corporation Ltd., (Address as applicable) IN CONSIDERATION OF THE HINDUSTAN PETROLEUM CORPORATION LTD. a Government of India Company registered under the Companies Act, 1956, having its registered office at 17, Jamshedji Tata Road, Bombay - 400 020 (hereinafter called "the Corporation" which expression shall include its successors and assigns) having awarded to M/s ___________________________________________________ a partnership firm/sole proprietor business/a company registered under the Companies Act, 1956 having its office at ______________________________ (hereinafter referred to as "the Supplier" which expression shall wherever the subject or context so permits includes its successors and assigns) a supply contract in terms inter alia, of "the Corporation's" Order No. ____________ dated __________________ and the General purchase conditions of "the Corporation" and upon the condition of "supplier's" furnishing security for the performance of "the Supplier's" obligations and/or discharge of "the supplier's" liability under and/or in connection with the said supply contract upto a sum of Rs. _______________ (Rupees_____________________) amounting to 10% (ten percent) of the total contract value. We, ______________________ (hereinafter called "the Bank" which expression shall include its successors and assigns) hereby jointly and severally undertake and guarantee to pay to "the Corporation" in rupees forthwith on demand in writing and without protest or demur of any and all moneys anywise payable by "the Supplier" to "the Corporation" under, in respect of or in connection with the said supply contract inclusive of all the Corporation's losses and damage and costs, (inclusive between attorney and client) charges, and expenses and other moneys anywise payable in respect of the above as specified in any notice of demand made by "the Corporation" to the Bank with reference to this Guarantee upto and aggregate limit of Rs.___________ (Rupees __________________________ ) and "the Bank" hereby agrees with "the Corporation" that: 1. This Guarantee/Undertaking shall be a continuing Guarantee / Undertaking and shall remain valid and irrecoverable for all claims of "the Corporation" and liabilities of "the S u p p l i e r " a r i s i n g u p t o a n d u n t i l m i d n i g h t o f _ _ _ _ _ _ _ _ _ _ _ _ _ _ 2. This Guarantee/Undertaking shall be in addition to any other guarantee or security whatsoever that "the Corporation" may now or any time anywise have in relation to "the Supplier's obligation/liabilities under and/or connection with the said supply contract, and "the Corporation" shall have full authority to take recourse to or enforce this security in preference to the other

security(ies) at its sole discretion and no failure on the part of "the Corporation" to enforcing or requiring enforcement to any other security shall have the effect of releasing "the Bank" from its full liability hereunder. 3. "The Corporation" shall be at liberty without reference to "the Bank" and without affecting the full liability of "the Bank" hereunder to take any other security in respect of "the Supplier's" obligation and/or liabilities under or in connection with the said supply contract and to vary the term vis-a-vis "the supplier" of the said supply contract or to grant time and/or indulgence to "the Supplier" or to reduce or to increase or otherwise vary the prices of the total contract value or to release or to forebear from enforcement of all or any of the obligations of "the supplier" under the said supply contract and/or the remedies of "the Corporation" under any other security(ies) now or hereafter held by "the Corporation" and no such dealing(s), variation(s) or other indulgence(s) or agreement(s) with "the supplier" or release of forbearance whatsoever shall have the effect of releasing "the Bank" from its full liability to "the Corporation" hereunder or of prejudicing rights of "the Corporation" against "the Bank". 4. This Guarantee/Undertaking shall not be determined or affected by the liquidation or winding up, dissolution or change of constitution or insolvency of "the supplier" but shall in all respects and for all purposes be binding and operative until payment of all moneys payable to "the Corporation" in terms hereof. 5. "The Bank" hereby waives all rights at any time inconsistent with the terms of this Guarantee/Undertaking and the obligations of "the Bank" in terms hereof shall not be anywise affected or suspended by reason of any dispute having been raised by "the suppliers" (whether or not pending before any arbitrator, officer, tribunal or court) or any denial of liability by "the supplier" or any other order of communication whatsoever by "the supplier" stopping or preventing or purporting to stop or prevent any payment by "the Bank" to "the Corporation" in terms hereof. 6. The amount stated in any notice of demand addressed by "the Corporation" to "the Bank" as liable to be paid to "the Corporation" by "the supplier" or as suffered or incurred by "the Corporation" on account of any losses or damages or costs, charges/and/or expenses shall be as between "the Bank" and "the Corporation" be conclusive of the amount so liable to be paid to "the Corporation" or suffered or incurred by "the Corporation", as the case may be, and payable by "the Bank" to "the Corporation", in terms hereof. 7. Not withstanding anything contained herein above : i) Our liability under this guarantee shall not exceed Rs.......... ii) This Bank Guarantee shall be valid upto and including .......; and

iii) We are liable to pay the guarantee amount or any part thereof under this Bank Guarantee only and only if you serve upon us a written claim or demand on or # before the expiry of 30 days from the date of expiry of this guarantee. 8. "The Bank" has power to issue this guarantee in favour of "the Corporation" in terms of the documents and/or the agreement/contract or MOU entered into between "the supplier" and "the Bank" in this regard. IN WITNESS Where of __________________ Bank, has executed this document at ________________ on _______________ 199 . ____________________________ Bank (by its constituted attorney) (signature of a person authorized to sign on behalf of "the Bank")

COMPOSITE BANK GUARANTEE FOR MOBILISATION ADVANCE, SECURITY DEPOSIT/RETENTION MONEY/PERFORMANCE GUARANTEE (On Non-Judicial stamp paper of appropriate value) TO : Hindustan Petroleum Corporation Limited (Address as applicable) IN CONSIDERATION OF MESSRS. HINDUSTAN PETROLEUM CORPORATION LIMITED, a Government of India Company registered under the Companies Act, 1956, having its registered office at 17, Jamshedji Tata Road, Bombay-20 (hereinafter called "The Corporation" (which expression shall include its successor in business and assigns) having placed an order on Messers ............................ a partnership firm/sole proprietor business/a company registered under the Companies Act, 1956 having its office at .............. (hereinafter called "the supplier" (which expression shall include executors, administrators and assigns) vide order No....................... dated.............. (hereinafter called "the order" which expression shall include any amendments/alterations to "the order" issued by "the Corporation") for the supply of goods to/execution of services for "the Corporation" and "the Corporation" having agreed : a) not to insist upon immediate payment of Security deposit for the fulfilment and performance of the said order b) to pay "the supplier" as and by way of advance upto a sum of Rupees__________ (Rupees _____________________________ only) being ____% of the value of "the order"; c) that "the supplier" shall furnish a security for the performance of "the supplier's" obligations and/or discharge of "the supplier's" liability in connection with the said "order"; and "the Corporation" having agreed with "the supplier" to accept a composite Bank Guarantee for the mobilisation advance, security deposit, retention money and performance guarantee. We, .................................................... Bank having office at ............................................ (hereinafter referred to as "the Bank" which expression shall includes its successors and assigns) at the request and on behalf of "the supplier" hereby agree to pay to "the Corporation"without any demur on first demand an amount not exceeding Rs........... (Rupees.............................only) against any loss or damage, costs, charges and expenses caused to or suffered by "the Corporation" by reason of non performance and fulfilment or for any breach on the part of "the supplier" of any of the terms and conditions of the said "order". 2. We, ............................. Bank further agree that "the Corporation" shall be sole judge whether the said

"Supplier" has failed to perform or fulfill the said "order" in terms thereof or committed breach of any terms and conditions of "the order" and the extent of loss, damage, cost, charges and expenses suffered or incurred or would be suffered or incurred by "the Corporation" on account thereof and we waive in the favour of "the Corporation" all the rights and defences to which we as guarantors and/or "the Supplier" may be entitled to. 3. We, ................................. Bank further agree that the amount demanded by "the Corporation" as such shall be final and binding on "the Bank" as to "the Bank" 's liability to pay and the amount demanded and "the Bank" undertake to pay "the Corporation" the amount so demanded on first demand and without any demur notwithstanding any dispute raised by "the Supplier" or any suit or other legal proceedings including arbitration pending before any court, tribunal or arbitrator relating thereto, our liability under this guarantee being absolute and unconditional. 4. We, .................................. Bank further agree with "the Corporation" that "the Corporation" shall have the fullest liberty without our consent and without affecting in any manner our obligations hereunder to vary any of the terms and conditions of the said "order"/or to extend time of performance by "the Supplier" from time to time or to postpone for any time to time any of the powers exercisable by "the Corporation" against "the Supplier" and to forbear to enforce any of the terms and conditions relating to "the order" and we shall not be relieved from our liability by reason of any such variation or extension being granted to "the Supplier" or for any forbearance, act or ommission on the part of "the Corporation" or any indulgence by "the Corporation" to "the Supplier" or by any such matter or things whatsoever which under the law relating to sureties would but for this provision have the effect of relieving us. 5. However, it has been agreed between "the Supplier" and "the Corporation" that there shall be only one Composite Bank Guarantee for both the advance and security deposit performance guarantee/Retention Money @ of ____% valid till the end of the defects liability period as per the terms of the P.O. No. _______________ dated ______________ and that in proportion with the recovery of advance @ ______% per bill the same amount/value automatically stands credited to the defects liability account/security deposit or retention money as the case may be and will continue to be credited/treated till the entire advance of Rs._______________________ is fully recovered from the running bills and from the date of full recovery of the advance of Rs.__________________ this guarantee automatically, shall stand valid towards the ____% retention money/defects liability, fully valid in all ® respects unto a further period of 3 (three) months, as per the Purchase Order of "the Corporation". 6. Not withstanding anything contained herein above :

i) Our liability under this guarantee shall not exceed Rs.......... ii) This Bank Guarantee shall be valid upto and including .......; and iii) We are liable to pay the guarantee amount or any part thereof under this Bank Guarantee only and only if you serve upon us a written claim or demand on or before the expiry of 30 days from the date of expiry of this guarantee. 7. We, ........................................ Bank further undertake not to revoke this guarantee during its currency except with the previous consent of "the Corporation" in writing. 8. We, ......................................... Bank lastly agree that "the Bank"'s liability under this guarantee shall not be affected by any change in the constitution of "the Supplier". 9. "The Bank" has power to issue this guarantee in favour of "the Corporation" in terms of the documents and/or the Agreement/Contract or MOU entered into between "the Supplier" and "the Bank" in this regard. IN WITNESS WHEREOF the Bank has executed this document on this ............................. day of ........................... For ........................ Bank (by its constituted attorney) (Signature of a person authorised to sign on behalf of "the Bank")*

(INDEMNITY BOND) (TO BE NOTORISED AND ON STAMP PAPER OF APPROPRIATE VALUE) TO, HINDUSTAN PETROLEUM CORPN. LTD. (Address as applicable) Dear Sirs, WHEREAS Hindustan Petroleum Corporation Limited, a Government of India Company, registered under the Companies Act, 1956, having its Registered Office at 17, Jamshedji Tata Road, Bombay - 400020 (hereinafter called "the Indemnified" which expression shall include its successors and assigns) has awarded to M/s. .......................................... a Partnership Firm/Sole Proprietor Business/a company having its Registered Office at ....................................................... (hereinafter called "the Indemnifier", which expression shall include its successors and assigns) a contract for conditions set out, inter-alia, in "the Indemnified" 's Purchase Order No. ............................. dated .................. (hereinafter referred to as "The Said Contract") to "the Indemnifier". AND WHEREAS "the Indemnified" has agreed to supply to "the Indemnifier" raw material/components to the value of Rs......... (Rupees .............................................. only) for incorporation in fabrication by "the Indemnifier" in terms of "the said contract", the components/raw material to be supplied by "the Indemnified" to "the Indemnifier" for the said fabrication, (hereinafter, for the sake of brevity, referred to as "the said material") and pending fabrication and delivery at job-site of the completed fabricated work(s) incorporating "the said material" and accounting for "the said material" shall be under the sole custody and charge of "the Indemnifier" and shall be kept, stored, altered, worked upon and/or fabricated at the sole risk and expenses of "the Indemnifier" ; As a Pre-condition to the supply of "the said material" by "the Indemnified" to "the Indemnifier", the Indemnified" has required "the Indemnifier" to furnish to "the Indemnified" security in the manner and upon terms and conditions hereinafter indicated : NOW THEREFORE, in consideration of the premises aforesaid "the Indemnifier" Shri ..................................., Shri ............................ all directors/partners/sole proprietor of "the Indemnifier" in consideration of aforesaid "contract" hereby irrevocably and unconditionally and jointly and severally undertake to idemnify and always keep "the Indemnified" from and against all loss, damage and destruction (inclusive but not limited to any or all loss or damage or destruction to or of "the said material" or any item or part thereof) by theft, fire, flood, storm, tempest, lightning, explosion, storage, chemical or physical action or reaction, bending, wrapping, exposure, rusting, faulty workmanship, faulty fabrication or faulty method of technique of fabrication, riot, civil commotion or other act

of omission or commission whatsoever within or beyond the control of "the Indemnifier", misuse and misappropriation by "the Indemnifier's" servants and/or agents whatsoever to, of or in "the said material" or any part or item thereof between the date that the same or relative part or item thereof was supplied to "the Indemnifier" upto and until the return to "the Indemnified" on due dates of "the said material" or relative part or item thereof or completed fabricated work(s) incorporating the said material AND jointly and severally undertake to pay to "the Indemnified" forthwith on first demand in writing without protest or demur the value of "the said material" or item part thereof lost, damaged, destroyed, misused and/or misappropriated, as the case may be, inclusive of "the Indemnified" 's cost and expenses (inclusive but not limited to handling, transportation, cartage, insurance, freight, packing and inspection costs and/or expenses) as specified in the said demand. AND "the Indemnifier" hereby agree with "the Indemnified" that : 1. This Indemnity shall remain valid and irrevocable until the settlement of all claims of "the Indemnified" arising hereunder : 2. This Indemnity shall be in addition to any other Indemnity, Guarantee or Security whatsoever that "the Indemnified" may now or any time anywise have in relation to "the Indemnifier" 's obligations/liabilities under and/or in connection with the said contract inclusive of "the said material" and "the Indemnified" shall have full authority to take recourse to or enforce this security in preference to the other security (ies) at its sole discretion, and no failure on the part of "the Indemnified" in enforcing or requiring enforcement of any other security shall have the effect of releasing "the Indemnifier" from its full liability hereunder : 3. "The Indemnified" shall be at liberty without reference to "the Indemnifier" and without affecting the full liability of "the Indemnifier" hereunder to take any other such security in respect of "the Indemnifier" 's obligations and/or liabilities under or in connection with the "said contract" inclusive of "the said material" and to vary the terms vis-avis "the Indemnifier" of "the said contract" or to grant time and/or indulgence to "the Indemnifier" or to reduce or to increase or otherwise vary the prices or the total contract value or the quantity, quality, description or value of the said material or to release or to forbear from endorsement of all or any of the obligations of "the Indemnifier" under the said contract (inclusive of anything in respect of "the said material") and/or the remedies of "the Indemnified" under any other security(ies) now or hereinafter held by "the Indemnified" and no such dealing(s), variations(s), reduction(s), increase(s) or other indulgence(s) or arrangement(s) with "the Indemnifier" or release or forbearance whatsoever shall have the effect of releasing "the Indemnifier" from their full liability to "the Indemnified" hereunder or of anywise prejudicing rights of "the Indemnified" against "the Indemnifier" and "the Indemnifier" hereby waive all rights, if any,

at any time, inconsistent with the terms of this Indemnity. 4. This Indemnity shall not be determined or affected by the liquidation or winding up, dissolution, or change of constitution or insolvency of "the Indemnifier" and the obligations of "the Indemnifier" in terms hereof shall not be anywise affected or suspended by reason of any dispute or disputes having been raised by "the Indemnifier" (whether now pending before any Arbitrator, Officer, Tribunal or Court) or any denial of liability by "the Indemnifier" or any other order or communication whatsoever by "the Indemnifier" stopping or preventing or purporting to stop or prevent any payment by "the Indemnifier" to "the Indemnified" in terms hereof : 5. The mere statement made by or on behalf of "the Indemnified" in any notice or demand or other writing addressed to "the Indemnifier" as to any of "the said material" or item or part thereof supplied to "the Indemnifier" having been lost, damaged, destroyed, misused or misappropriated while in the custody of "the Indemnifier" before or after completion of the completed fabricated work(s) incorporating "the said material" and delivery at job site thereof shall as between "the Indemnifier" and "the Indemnified" be conclusive of the factum of "the said material" or item or part thereof having been supplied to "the Indemnifier" and/or the loss, damage, destruction, misuse or misappropriation thereof, as the case may be, while in the custody of "the Indemnifier" and/or prior to the completion of the completed fabricated work(s) and delivery to job site thereof without necessity on the part of "the Indemnified" to produce any documentary proof or other evidence whatsoever in support of this; 6. The amount stated in any notice of demand addressed by "the Indemnified" to "the Indemnifier" as the value of any of "the said material", lost, damaged, destroyed or misused or misappropriated, inclusive relative to the cost and expenses incurred by "the Indemnified" in connection therewith shall as between "the Indemnifier" and "the Indemnified" be conclusive of the value of such "said material" and the said costs and expenses as also of the amount liable to be paid by "the Indemnifer" to "the Indemnified" in terms and for the purpose of, without necessity for "the Indemnfied" to produce any voucher, bill or other documentation or evidence whatsoever in support thereof. In witness whereof "the Indemnifier" have hereunto set and subscribed his hand this day and year first hereinabove written in the presence of witnesses. Yours faithfully, 1) 2) 3) WITNESSES 1. 2.

BANK GUARANTEE IN LIEU OF EARNEST MONEY (On Non-Judicial stamp paper of appropriate value) TO : Hindustan Petroleum Corporation Limited (Address as applicable) IN CONSIDERATION OF MESSRS. HINDUSTAN PETROLEUM CORPORATION LIMITED a Government of India Company registered under the Companies Act, 1956, having its registered office at 17, Jamshedji Tata Road, Bombay-20 (hereinafter called "The Corporation" which expression shall include its successor in business and assigns) issued a tender on Messrs. ................................................ a partnership firm/sole proprietor business/a company registered under the Companies Act, 1956 having its office at (hereinafter called "the Tenderer" which expression shall include its executors, administrators and assigns) against Tender no............ dated .................... (hereinafter called "the tender" which expression shall include any amendments/ alterations to "the tender" issued by "the Corporation") for the supply of goods to/execution of services for "the Corporation" and "the Corporation" having agreed not to insist upon immediate payment of Earnest Money for the fulfilment of the said tender in terms thereof on production of an acceptable Bank Guarantee for an amount of Rs....... (Rupees ................................. only). We, ................................... Bank having office at ..................................................... Bombay (hereinafter referred to as "the Bank" which expression shall include its successors and assigns) at the request and on behalf of "the Tenderer" hereby agree to pay to the Corporation without any demur on first demand an amount not exceeding Rs........... (Rupees ...................................... only) against any loss or damage, costs, charges and expenses caused to or suffered by "the Corporation" by reason of non performance and fulfilment or for any breach on the part of "the Tenderer" of any of the terms and conditions of the said "tender". 2. We, ........................................ Bank further agree that "the Corporation" shall be sole Judge whether the said "Tenderer" has failed to perform or fulfill the said "tender" in terms thereof or committed breach of any of the terms and conditions of "the order" and the extent of loss, damage, cost, charges and expenses suffered or incurred or would be suffered or incurred by "the Corporation" on account thereof and we waive in favour of "the Corporation" all the rights and defences to which we as guarantors and/or "the Tenderer" may be entitled to. 3. We, ................................. Bank further agree that the amount demanded by "the Corporation" as such shall be final and binding on "the Bank" as to "the Bank" 's liability to pay and the amount demanded and "the Bank" to undertake to pay "the Corporation" the amount so demanded on first demand

and without any demur notwithstanding any dispute raised by "the Tenderer" or any suit or other legal proceedings including arbitration pending before any court, tribunal or arbitrator relating thereto, our liability under this guarantee being absolute and unconditional. 4. We, ....................................... Bank further agree with "the Corporation" that "the Corporation" shall have the fullest liberty without our consent and without affecting in any manner our obligations hereunder to vary any of the terms and conditions of the said "tender"/or to extend time of performance by "the Tenderer" from time to time or to postpone for any time to time any of the powers exercisable by "the Corporation" against "the Tenderer" and to forbear to enforce any of the terms and conditions relating to "the tender" and we shall not be relieved from our liability by reason of any such variation or extension being granted to "the Tenderer" or for any forbearance, act or ommission on the part of "the Corporation" or any indulgence by "the Corporation" to "the tenderer" or by any such matter or things whatsoever which under the law relating to sureties would but for this provision have the effect of relieving us. 5. NOTWITHSTANDING anything hereinbefore contained, our liability under this Guarantee is restricted to Rs. ......... (Rupees....................................... only). Our liability under this guarantee shall remain in force until expiration of six months from the due date of opening of the said "tender". Unless a demand or claim under this guarantee is made on us in writing within said period, that is, on or before .................................... all rights of "the Corporation" under the said guarantee shall be forfeited and we shall be relieved and discharged from all liabilities thereunder. 6. We, ........................................ Bank further undertake not to revoke this guarantee during its currency except with the previous consent of "the Corporation" in Writing. 7. We, ......................................... Bank lastly agree that "the Bank" 's liability under this guarantee shall not be affected by any change in the constitution of "the Tenderer". 8. "The Bank" has power to issue this guarantee in favour of "the Corporation" in terms of the documents and/or the Agreement/Contract or MOU entered into between "the Tenderer" and "the Bank" in this regard. IN WITNESS WHEREOF the Bank has executed this document on this .......................... day of ........................ For ........................ Bank (by its constituted attorney) (Signature of a person authorised to sign on behalf of "the Bank")

# BANK GUARANTEE IN LIEU OF LIQUIDATED DAMAGES (On Non-Judicial stamp paper of appropriate value) (Clause B.11.1 of Chapter IV) To: Hindustan Petroleum Corporation Limited (Address as applicable) IN CONSIDERATION OF MESSRS. HINDUSTAN PETROLEUM CORPORATION LIMITED a Government of India Company registered under the Companies Act, 1956, having its registered office at 17, Jamshedji Tata Road, Churchgate, Mumbai – 400 020 (hereinafter called "The Corporation" which expression shall include its successor in business and assigns) agreeing to grant a provisional extension of time in respect of the contract entered into with Messrs. ................................................ a sole proprietorship business/ partnership firm/ a company registered under the Companies Act, 1956 having its office at ........................................................... (hereinafter called "the Contractor", which expression shall include its executors, administrators and assigns) against Purchase Order No. .......... dated .................... (hereinafter called "the Contract" which expression shall include any amendments/ alterations to "the contract" issued by "the Corporation") for ………………………………………. (state the purpose of the Contract), and the Contractor having requested for extension of time without deduction of any Liquidated Damages from the bills in terms of the Contract and "the Corporation" having agreed to grant provisional extension of time pending a decision on the request for extension of time and not to insist upon immediate deduction/payment of Liquidated Damages upon receipt of this unconditional irrevocable Bank Guarantee for an amount of Rs....... ………………..(Rupees ....................................................... only). We, ................................... Bank having our office at ..................................................... Bombay (hereinafter referred to as "the Bank" which expression shall include its successors and assigns) at the request and on behalf of "the Contractor" hereby agree to pay to the Corporation without any demur and on first demand an amount not exceeding Rs…………….......... (Rupees ...................................... only) against any loss or damage, costs, charges and expenses caused to or suffered by or likely to be caused to or suffered by "the Corporation" by reason of the delay in performance of work or the Corporation agreeing to grant such provisional extension of time without insisting on deduction of Liquidated Damages. 2. We, ........................................ Bank further agree that "the Corporation" shall be sole Judge whether the said "Contractor" has failed to perform or fulfill the said "Contract" in terms thereof or committed breach of any of the terms and conditions of "the purchase ______________________________________________________________________________ order/Contract" or was not entitled to any extension of time and also the extent of loss, damage, cost, charges and expenses suffered or incurred or would be suffered or incurred by "the Corporation" on account thereof and we waive in favour of "the Corporation" all the rights and defences to which we as guarantors and/or "the Contractor" may be entitled to.

3. We, ................................. Bank further agree that the amount demanded by "the Corporation" as such shall be final and binding on "the Bank" as to "the Bank" 's liability to pay the amount demanded and "the Bank" undertakes to pay to "the Corporation" the amount so demanded on first demand without further proof or conditions and without any demur, reservation, contest, recourse or protest and without any enquiry of you or the Contractor, forthwith and in full without any deductions or set-offs or counterclaim whatsoever, the sum claimed by you in such Demand, notwithstanding any dispute raised by "the Contractor" or the pendency of any suit or other legal proceedings including arbitration pending before any court, tribunal or arbitrator relating thereto, our liability under this guarantee being absolute and unconditional. We further agree that the Corporation shall not be bound to disclose any reasons while demanding any amount under the Bank Guarantee. 4. We,

....................................... Bank further agree with "the Corporation" that "the Corporation" shall have the fullest liberty without our consent and without affecting in any manner our obligations hereunder, to vary any of the terms and conditions of the said "Contract"/or to extend time of performance by "the Contractor" from time to time or to postpone for any time or from time to time any of the powers exercisable by "the Corporation" against "the Contractor" and to forbear to enforce any of the terms and conditions relating to "the Contract" and we shall not be relieved from our liability by reason of any such variation or extension being granted to "the Contractor" or for any forbearance, act or omission on the part of "the Corporation" or any indulgence by "the Corporation" to "the Contractor" or by any such matter or things whatsoever which under the law relating to sureties would, but for this provision, have the effect of relieving us. Any waivers or other forbearance given or variations required under the Contract or any invalidity, unenforceability or illegality of the whole or any part of the Contract or rights of any party thereto, or amendment or other modification of the Contract or any other fact, circumstance, provision of statute or law which might, were our liability to be secondary and not primary, entitle us to be released in whole or in part from our undertaking, shall not in any way release us from our obligations under this Guarantee. Our obligations hereunder in respect of the sum or sums demanded by the Corporation under this Guarantee are primary, independent and absolute and not by way of surety only. The Corporation may make an unlimited number of Demands under this Guarantee provided that the aggregate of all sums paid shall not exceed the entire Guarantee Amount. 5. Notwithstanding anything hereinbefore contained, our liability under this Guarantee is restricted to Rs. ......... ……. (Rupees....................................... only). Our liability under this guarantee shall remain in force until expiration of six months from the expiry of the said "Contract". Unless a demand or claim under this guarantee is made on us in writing within said period, that is, on or before .................................... all rights of "the Corporation" under the said guarantee shall be forfeited and we shall be relieved and discharged from all liabilities thereunder. 6. We, ........................................ Bank further undertake not to revoke this guarantee during its currency except with the previous consent of "the Corporation" in Writing.

7. We, ......................................... Bank lastly agree that "the Bank" 's liability under this guarantee shall not be affected by any change in the constitution of "the Contractor" or its insolvency winding up, reorganisation, amalgamation or liquidation (including any appointment of a receiver, administrator, administrative receiver or supervisor of the Contractor or any of its assets) nor in case of any dispute or disagreement whatsoever under the Agreement. We shall indemnify you immediately on demand against any cost, loss or liability suffered by you as a result of our this obligation being or becoming unenforceable, invalid or contrary to the laws of India (except in the case of a fraud by you). 8. "The Bank" has power to issue this guarantee in favour of "the Corporation" in terms of the documents and/or the Agreement/Contract or MOU entered into between "the Contractor" and "the Bank" in this regard. This Guarantee shall be governed by and construed in accordance with the laws of the Republic of India. 9. Any demand, notice or other communication given in connection with or required by this Guarantee shall be made in writing in English be delivered by hand to, or sent by pre-paid registered post, or facsimile transmission to: ________________________ ________________________ ________________________ IN WITNESS WHEREOF the Bank has executed this document on this .......................... day of ........................ For ........................ Bank (by its constituted attorney) Signature of a person authorised to sign on behalf of the bank") ______________

SECTION- 11

TIME SCHEDULE

Name of Work CONSTRUCTION OF 10" DIA. X 15 KM (APPROX.) & 8” DIA X 15 KM (APPROX.) STEEL PIPELINE, TERMINALS AND ASSOCIATED FACILITIES FOR BAHADURGARH TIKRIKALAN PIPELINE

Time of Completion COMPLETION OF CONSTRUCTION WORKS OF TWO PARALLEL 10’’X15 KM AND 8” X 15 KM U/G PIPELINES TRENCH FROM BAHADURGARH TO TIKARIKALAN, TAPOFF/HOOK UP WITH EXISTING PRODUCT TANKS, INTERCONNECTING ABOVE GROUND COMPLETE PIPING SYSTEM, DISPATCH & RECEIVING TERMINAL WORKS INCLUDING COMPLETE ERECTION OF ALL PUMPS (8 NOS) AND COMMISSIONING ASSISTANCE, CONTROL ROOMS, STRUCTURAL SHEDS AND ALL ASSOCIATED MECHANICAL, CIVIL, STRUCTURAL, ELECTRICAL, INSTRUMENTATION, SCADA & TELECOMMUNICATION WORKS, CP WORKS AT BAHADURGARH & TIKARIKALAN AS PER SCOPE OF WORKS GIVEN IN TENDER WITHIN THE TIME PERIOD AS DETAILED BELOW: 26 WEEKS FROM THE DATE OF FOI. IT SHOULD BE NOTED THAT THE PERIOD OF COMPLETION GIVEN INCLUDES PREPARATION OF DRAWINGS (IF REQUIRED), PROCUREMENT AND SUPPLY OF MATERIAL INCLUDING THEIR INSPECTION AND TESTING, MOBILISATION AT SITE, CONSTRUCTION, LAYING, FABRICATION, ERECTION, INSPECTION, TESTING, RECTIFICATION (IF ANY) AND UPTO PRECOMMISSIONING OF FOLLOWING FACILITIES : A) PIPELINE UPTO HYDRO-TESTING (READY FOR TAKING PRODUCT) B) TERMINALS AFTER TESTING (READY FOR TAKING PRODUCT) C) PUMPS (READY FOR TAKING PRODUCT) D) CP SYSTEM READY FOR COMMISSIONING E) ELECTRICAL & INSTRUMENTATION READY FOR FINAL INTEGRATED TESTING & COMMISSIONING 4 WEEKS FOR OVERALL COMMISSIONING IN ALL RESPECTS TO THE ENTIRE SATISFACTION OF HPCL/MECON FROM THE DATE OF ADVISE TO COMMENCE COMMISSIONING.

Note: 1)

The time of completion shall be reckoned from the date of award of contract, which shall be the date of issue of letter/ Fax of Intent.

2)

The time indicated is for completing all the works in all respects as per specifications, codes, drawings and instructions of Engineer-in-charge.

_______________________________ (STAMP & SIGNATURE OF BIDDER)

Related Documents

Hpcl Steel Line Tender.pdf
December 2019 10
Steel
May 2020 33
Steel
October 2019 42
Hpcl Slide (1)
June 2020 4
Line
June 2020 11

More Documents from ""