Heitor Moura 2007 Risk Management For Private Equity Investments

  • Uploaded by: Heitor Moura
  • 0
  • 0
  • December 2019
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Heitor Moura 2007 Risk Management For Private Equity Investments as PDF for free.

More details

  • Words: 2,380
  • Pages: 27
Heitor Moura

A RISK MANAGEMENT PLAN for an investment and trading project

January 2007

UNICONSULT SERVIÇOS TÉCNICOS LTDA. – RIO DE JANEIRO

Risk and its management • Risk is the possibility that an event will occur, which adversely affects the achievement of objectives. • Risk management is: • • • • • •

PROJECT

an on-going process, a means to an end; carried out through plans, policies, surveys, controls, information and fundamentally by people; applied in a strategic setting, that is, directed towards objectives; applied throughout the organization, at all hierarchical levels and regional units; aimed at identifying and managing potential adverse events and situations; designed to offer reasonable assurance to its management and board of the organization's understanding of risks and of its capability of minimizing their effect.

jANUARY 2007

2

Risk Management Process

RISK MANAGEMENT PLANNING

RISK MANAGEMENT MONITORING

RISK OCCURRENCE RESPONSE

PROJECT

jANUARY 2007

3

Risk Management Process - Planning RISK MANAGEMENT PLANNING

RISK IDENTIFICATION

RISK MANAGEMENT MONITORING

RISK OCCURRENCE RESPONSE

RISK OF DELAY IN INVESTMENT DECISION

RISK ASSESSMENT

LIKELIHOOD: IMPROBABLE IMPACT: SMALL TIME-FRAME: SHORT-TERM

MITIGATION OF LIKELIHOOD

MITIGATION OF EVENTUAL IMPACT

PROJECT SCHEDULE

SIMULTANEOUS PROJECTS PARTIAL-DECISION PROCESS

PROJECT

jANUARY 2007

RISK-RESPONSE PLAN

4

Risk Management Process - Monitoring RISK MANAGEMENT PLANNING

MONITORING

RISK MANAGEMENT MONITORING

RISK OCCURRENCE RESPONSE

FOLLOW-UP OF NEGOTIATION PROCESS

CONTINUED RISK ASSESSMENT

CHANGE TO LIKELIHOOD? CHANGE TO IMPACT? CANGE TO TIME-FRAME?

REVIEW MITIGATION OF LIKELIHOOD

REVISION OF SCHEDULE

ACCELERATE NEGOTIATIONS OPEN NEW NEGOTIATIONS ETC.

PROJECT

jANUARY 2007

REVIEW MITIGATION OF EVENTUAL IMPACT

REVIEW RISK-RESPONSE PLAN

5

Risk Management Process - Response RISK MANAGEMENT PLANNING

RISK MANAGEMENT MONITORING

OCCURRENCE OF RISK EVENT

RISK OCCURRENCE RESPONSE

DECISION IS DELAYED

RESPONSE TO SITUATION

ACTION TO SPEEDEN DECISION ACTION TO SUBSTITUTE PROJECT

CONTROL OF RESPONSE

FOLLOW-UP ON ACTIONS

ASSESSMENT OF SITUATION POST-EVENT

REVIEW OF PLAN REVIEW OF RESPONSE

PROJECT

jANUARY 2007

6

Risk components

TIME-FRAME

EXPECTED IMPACT OF OCCURRENCE

LIKELIHOOD OF OCCURRENCE

POSSIBILITY OF REDUCING LIKELIHOOD

DECISION TO TAKE ON RISK

EFFECT OF RISK

POSSIBILITY OF COVERAGE

PLANNED RESPONSE TO EVENTUAL OCCURRENCE

INTENSITY OF EFFECT

EXPECTED RESIDUAL RISK

PROJECT

jANUARY 2007

7

Risk components 2 • Likelihood of occurence Probability • • • • •

0% to 1% : over 1% to 5%: over 5% to 20%: over 20% to 50%: over 50% to 100%:

Likelihood highly improbable improbable eventual probable highly probable

• Time-frame for this occurence • •

PROJECT

within 2 years after investment: short-term, i.e. there is little time to change risk conditions until 8 years after investment: medium term. i.e. there is some time to change risk conditions

jANUARY 2007

8

Risk components 3 • Effect of risk • • • • •

Delay in operations Increase in cost Loss of revenue Loss of assets Increase in liabilities

• Intensity of effect • • •

low medium high

• Result of occurence • • • • PROJECT

small: medium: great: drastic:

affects standard IRR by less than 1% p.a. affects standard IRR by over 1% up to 3% p.a. affects standard IRR by over 3% up to 5% p.a. affects standard IRR by over 5% p.a. jANUARY 2007

9

Risk coverage

INSURANCE

HEDGE MITIGATION OF EVENTUAL IMPACT GUARANTEE

OTHER CONTRACTUAL TRANSFER ABSORTION OF RESIDUAL RISK

PROJECT

jANUARY 2007

10

Risk categories combined with results 100

200

400

800

3200

100

200

400

1600

50

100

200

400

1600

50

100

200

800

20

40

80

160

640

20

40

80

320

10

20

40

80

320

10

20

40

160

5

10

20

40

160

5

10

20

80

2

4

8

16

64

2

4

8

32

1

2

4

8

32

1

2

4

16

2

4

8

32

1

2

4

16

Small

Medium

Great

Drastic

Small

Medium

Great

Drastic

SHORT TERM

MEDIUM TERM

RISK CLASSIFICATION From 1 to 7

Acceptable

From 8 to 19

Acceptable

From 20 to 31

Acceptable

From 21 to 63

Acceptable

From 64 to 99

Only acceptable if covered

From 100 to 299

Only acceptable if covered

From 300 to 499

Only acceptable if covered

500 or over PROJECT

jANUARY 2007

Not acceptable 11

Decision parameters • Acceptable risks • • •

Define risks Analyse possible reduction of likelihood and mitigation of impact Include cost of these counter-measures in investment analysis

• Risks acceptable only if covered • • • •

Define risks Analyse possible reduction of likelihood and mitigation of impact Establish coverage (insurance, hedge, security) Include cost of these counter-measures and coverage in investment analysis

• Non-acceptable risks • • • •

PROJECT

Define risks Analyse if possible counter-measures or coverage can change their classification Reject investment if this is not feasible and efficient (investment phase) or Take drastic counter-measures or divest operation (after investment phase)

jANUARY 2007

12

Main risks in each phase of Project •

Investment decisions • • •



Entry into each local business • •



Market fluctuations Lack of or reduced synergy among operations

Divestment of each business • • •



Technical risks Regulatory and tax context Management efficiency

Joint operation of all businesses • •



Resistance from local groups Delay in establishing management procedures and controls

Operation of each local business • • •



Delayed decision Competition for each investment Unprofitable choice

Market Protracted negotiations Competition for new investors

Post-divestment •

PROJECT

Outstanding liabilities

jANUARY 2007

13

Risks in the investment phase An example • Risk identification • Type • Level • Likelihood • Impact • Time-frame

PROJECT

jANUARY 2007

14

RISK

TYPE

LEVEL

LIKELIHOOD

IMPACT

TIME-FRAME

Organization Human factor

1-Project

2-improbable

1-small

3-short-term

Human factor

1-Project

3-eventual

1-small

3-short-term

3 Delay in making decision

Organization Human factor

1-Project

2-improbable

1-small

3-short-term

4 Delay in concluding negotiations

Economic Human factor

1-Project

3-eventual

2-medium

3-short-term

5 Back-trading by sellers

Economic Human factor

1-Project

4-probable

2-medium

3-short-term

6 Change in country market context

Economic

2-Country

5-highly probable

3-great

2-medium-term

7 Change in world market context

Economic

3-Organization

5-highly probable

3-great

3-short-term

8 Change in country business context

Economic

2-Country

3-eventual

3-great

2-medium-term

9 Change in world business context

Economic

3-Organization

3-eventual

3-great

3-short-term

Delay in establishing and executing documents

Organization Human factor

1-Project

2-improbable

1-small

3-short-term

11 Inclusion of undesirable/incorrect clause

Organization Human factor

1-Project

1-highly improbable

2-medium

3-short-term

12 Non delivery of mandatory licenses

Regulatory Human factor

1-Project

2-improbable

2-medium

3-short-term

13 Delay in delivery of mandatory licenses

Regulatory Human factor

1-Project

3-eventual

1-small

3-short-term

Non discovery of unacceptable risks or liabilities

Organization Human factor

1-Project

2-improbable

4-critical

2-medium-term

Criminal

1-Project

2-improbable

4-critical

2-medium-term

Cultural Human factor

1-Project

4-probable

1-small

3-short-term

1 Delay in identifying prospects 2

10

14

Delay and/or non supply of information by sellers

15 Fraud in delivered information 16

Resistance from local management / labour PROJECT

jANUARY 2007

15

RISK

GUARANTEE INSURANCE HEDGE POSSIBILITIE POSSIBILITIES POSSIBILITIES S

RESIDUAL RISK

REDUCING LIKELIHOOD

MITIGATION OF IMPACT

Pro-active search

Simultaneous projects

None

None

None

Low

Documentation list Local follow-up Expliciting the requirement Expliciting consequences

Partial-decision process

None

None

None

Medium

3 Delay in making decision

Project schedule

Simultaneous projects Partial-decision process

None

None

None

Low

4 Delay in concluding negotiations

Project schedule

Simultaneous projects

None

None

None

Medium

Clear negotiation Reputable partners

Simultaneous projects Competitive negotiation Analysis parameters with expected time-frame average Analysis parameters within expected time-frame average Sensibility analysis within expected parameter range Sensibility analysis within expected parameter range

None

None

None

Medium

Country risk

Price hedge

None

Medium

None

Price hedge

None

Low

Country risk

Price hedge

None

Medium

None

Price hedge

None

High

Simultaneous projects

None

None

None

Medium

None

None

None

None

Low

None

None

None

None

1 Delay in identifying prospects Delay and/or non supply of information 2 by sellers

5 Back-trading by sellers 6 Change in country market context

None

7 Change in world market context

None

8 Change in country business context

None

9 Change in world business context

None

10

Delay in establishing and executing documents

11 Inclusion of undesirable/incorrect clause 12 Non delivery of mandatory licenses 13 Delay in delivery of mandatory licenses 14

Non discovery of unacceptable risks or liabilities

15 Fraud in delivered information 16

Resistance from local management / labour

PROJECT

Competent legal advisors Internal review Competent legal advisors Internal review Competent legal advisors Local representatives Competent legal advisors Local representatives

Contractual obligation to deliver correct information Contractual obligation to deliver correct information

Comprehensive due dilligence

Contractual generic guarantees

None

None

Contractual obligation

Low

Contractual obligation to deliver correct information

None

None

Contractual obligation

Low

Contractual generic guarantees

None

None

None

High

Comprehensive due dilligence Adequate confidentiality procedures Winning local management Communication program with local stakeholders

jANUARY 2007

Contractual obligation Contractual obligation

Low Medium

16

List of potential risks 1 •

Commercial - Sourcing • • • •



Performance: non delivery of raw materials Performance: late delivery of raw materials Performance: raw material off specifications Change in availability of raw materials

Commercial - Sales • • • • •

PROJECT

Credit: Non-receipt of sales Credit: Late receipt of sales Performance: non acceptance of products by buyer Performance: delay in acceptance of products by buyer Performance: raw material off specifications

jANUARY 2007

17

List of potential risks 2 •

Commodity markets •

Cost of raw materials  Materials not yet purchased  Materials purchased but not fixed  Materials in inventory



Sale prices of produced goods  Unsold products  Products sold but not fixed





Price fluctuations in straight commercial open positions (purchases and sales unrelated to production)

Exchange markets •

Exchange rate fluctuation as to investments  investment in USD x earnings in local currencies



Exchange rate fluctuation in current operations  foreign sales x domestic costs

PROJECT

jANUARY 2007

18

List of potential risks 3 •

Agriculture • • • •



Climate – rain Water (availability, investment for sourcing, cost) Labour (quality, possibility of strikes, cost) Agricultural management (quality, availability, cost)

Industry • • • • • •

PROJECT

Equipment (unplanned maintenances, delays, costs) Supply of equipments (availability, delay, cost) Necessity of increasing industrial facilities Necessity of changing industrial process Labour (quality, possibility of strikes, cost) Industrial management (quality, availability, cost)

jANUARY 2007

19

List of potential risks 4 •

Logistics •

Availability of transportation vehicles  Third parties  Own investment  Financing for third parties

• •

Availability of routes Availability of storage capacity  Third parties  Own investment  Financing for third parties

• • • • • •

PROJECT

Availability of maritime terminal time Availability of ships within required regularity Cost of land transportation Cost of storage Cost of maritime terminal Cost of maritime freight

jANUARY 2007

20

List of potential risks 5 •

Financial • • • • •



Interest rates fluctuations Existing and expected bank debts Other existing and expected financial debts Existing and expected tax liabilities Existing and expected labour liabilities

Management •

Implementation and maintenance of required controls  agriculture, industry, logistics, sales, markets  accounting, taxes, labour  IT infrastructure and hardware

• • •

PROJECT

Implementation and maintenance of reporting process Implementation and maintenance of risk management process Motivation of local management and labour

jANUARY 2007

21

List of potential risks 6 •

Environment •

Existing environmental liabilities (in agriculture, industry and logistics)  known, but not evaluated  evaluated but without payment obligation  evaluated with payment obligation

• •



Potential environmental liabilities (in agriculture, industry and logistics) Environment-related licenses (delays, cost)

Regulatory risks • • • • •

PROJECT

Labour regulations Taxes regulations and compliance (on agriculture, industry, logistics, domestics sales, exports, earnings, assets) Accounting regulations and compliance Labour relations compliance Other regulations compliance

jANUARY 2007

22

List of potential risks 7 •

Corporate risks in local operations • • • •



Conflict with previous owners Conflict with remaining partners Conflict with government Conflict with competitors

Country risks • • • •

General political risk Interest rate differential from country rating Social turmoil, acts of God Countries:  with local operations  sources of raw materials and products  sales markets



General corporate risks

PROJECT

jANUARY 2007

23

Agenda for a risk management plan 1 • Review and establish parameters for: • • • • • •

risk identification (list of risks in each phase of Project) organizational levels involved time-frame likelihood of occurrence impact (type of effect, monetary and non-monetary consequences) levels of risk tolerance (acceptance, acceptance with coverage, rejection)

• Define, for each risk listed: • • • • • • • • •

PROJECT

the risk possible impacts how it will be assessed (statistics, market talk, model estimation etc.) who will supply basic input, who will carry out analysis time-frame for this analysis (daily, weekly, monthly,...) process flow of the risk analysis (local level >> country level >> corporate level) possible likelihood-reduction strategies possible impact mitigation strategies initial response plan to eventual occurrence

jANUARY 2007

24

Agenda for a risk management plan 2 • Define documentation on risk management • • •

For each project, during investment phase For each operation, after investment phase For each type of occurrence, during life-time of Project

• • • • • •

To be delivered to local management To be delivered to country management To be delivered to corporate management To be delivered to regulators To be delivered to investors To local authorities

• Define functions/persons responsible for • • • •

PROJECT

Establishment of risk management plan Assessment of risks in each project, during investment phase Assessment of risks in each operation after investment phase Assessment of corporate risks

jANUARY 2007

25

Agenda for a risk management plan 3 • Month 1 • •

Define persons/functions responsible for the establishment of a Preliminary Risk Management Plan (valid until First Closing) Establish and approve this Preliminary Risk Management Plan

• Months 2 and 3 • •

Include extract of Preliminary Plan in presentations to possible Investors Work on Risk Management Plan for investment process

• After First Closing (or on assurance of go-ahead) • • • •

PROJECT

Establish and approve the Risk Management Plan for the investment process Define responsibilities for the execution of the Risk Management Plan during the investment process Organize the means and resources for this execution Beginning discussing and drafting the Operational Risk Management Plan

jANUARY 2007

26

Heitor Moura

A RISK MANAGEMENT PLAN for an investment and trading project

January 2007

Related Documents


More Documents from "Heitor Moura"