GRP Pipe Manufacturing by CFW Process Flowchart Mixing
Resin + Cobalt
Catalyst
Fiberglass Reinforcemen ts
Infrared curing
Hydro-testing
Chamfering, Shaving, Calibration, Cutting
Storage
In-line automatic spigot calibration & Chamfering
Dosing of cobalt – automatic
PLC controlled chemical dosing
Pipe Design Recipe
Feed the design parameters into the CFW machine
In-house Tests
Axial Tensile Strength Test
Stiffness Test
Flexure Test
Split Disc Testing Machine – for HOOP strength test
Beam Strength Test
Strain-Corrosion Test
Strain-Corrosion End-point
Strain-Corrosion Test Report
Strain-Corrosion Test Report
Fig. 2. Plot of regression line,
HDB Test
HDB Test Report
HDB Test Report
Fig. 2 – Graph of regression line, 95% Confidence and Prediction Limits.
Cell Classification System Type 1
: Filament-Wound
Type 2
: Centrifugally Cast
Grade 1
: Glass Fiber Reinforced Epoxy (RTRP Epoxy)
Grade 2
: Glass Fiber Reinforced Polyester (RTRP Polyester)
Grade 3
: Glass Fiber Reinforced Epoxy Mortar (RPMP Epoxy)
Grade 4
: Glass Fiber Reinforced Polyester Mortar (RPMP Mortar)
Liner A
: No Liner
Liner B
: Thermoplastic Liner
Liner C
: Reinforced Thermoset Liner
Liner D
: Non-reinforced Thermoset Liner
Example : Type 1, Grade 2, Liner C (Filament-wound, RTRP Polyester, Reinforced Thermoset Liner)
STIS E’b Backfill
E’n
Traffic Loads
Installations Compaction
Pipe Invert
Native Soil Pipe Crown Vertical deflection
Facts about GRP Pipe
AWWA M45 fig. 6-1
Trench Cross-Section Terminology
Native Soil Group Classification Appendix C Nativ e Soil Grou p 1
Blow Counts’
E’n value3,4 (MPa)
Description
Friction Angle (degrees)
Description
Unc. Comp. Str. (kPa)
> 152
34.5
Compact
33
Very stiff
192 - 384
2
8 – 15
20.7
Slightly compact
30
Stiff
96 – 192
3
4–8
10.3
Loose
29
Medium
48 – 96
4
2–4
4.8
Very loose
28
Soft
24 – 48
5
1–2
1.4
Very loose
27
Very soft
12 - 24
6
0-1
0.34
Very, very loose
26
Very, very soft
0 - 12
Blows/foot from standard penetration test, ASTM D1586. For higher blow counts, E'n values increase to 345 MPa for rock. 3 The use of geotextiles in the pipe zone will likely increase the values of E'n above those listed. 4 If permanent sheeting is used in the pipe zone, consider native E’n = E'b, Sc = 1 1 2
Field testing to assist Classification of Native Soils Table E1 Simple Field Test for Determining Soil Group1
Native Soil Group
Measurable Characteristic
1
Can be barely penetrated with thumb
2
Can be 4mm Can be 10mm Can be 25mm Can be 50mm Can be
3 4 5 6
penetrated with thumb to penetrated by thumb to penetrated by thumb to penetrated by thumb to penetrated by fist to 25mm
Based on Peck, Hanson and Thornburn, "Foundation Engineering," 2nd Ed., John Wiley and Sons, Inc., 1974 and ASTM D2488. 1
Ideal backfill material, but costly…
Description of Backfill Soils Appendix D1 Backfill Soil Type Classification Backfill Type
Description
Unified Soil Classification Designation, ASTM D2487
A
Crushed stone and gravel, < 12% fines
GW, GP, GW – GM, GP - GM
B
Gravel with sand, sand, < 12% fines
C
Silty gravel and sand, 12 – 35% fines, LL < 40% Silty, clayey sand, 35 – 50% fines, LL < 40% Sandy clayey silt, 50 – 70% fines, LL < 40% Low plasticity fine-grained soils,LL < 40%
GW – GC, GP – GC, SW, SP SW – SM, SP – SM, SW – SC, SP SC GM, GC, GM – GC, SM, SC, SM - SC
D E F
GM, GC, GM – GC, SM, SC, SM - SC CL, ML, CL - ML CL, ML, CL - ML
Backfill Modulus of Passive Resistance, E’b (MPa) Appendix D2 Backfill Modulus of Passive Resistance (NonSaturated) Backfill Type
E’b values (MPa) at Relative Compaction 80%
85%
90%
95%
A
16
18
20
22
B
7
11
16
19
C
6
9
14
17
D
3
6
9
102
E
3
6
9
102
F
3
6
92
102
100% relative compaction defined as maximum Standard Proctor Density at optimum moisture content. 2 Values typically difficult to achieve, included as reference. 1
Backfill Modulus of Passive Resistance, E’b (MPa) Appendix D3 Backfill Modulus of Passive Resistance (Saturated) Backfill Type
E’b values (MPa) at Relative Compaction 80%
85%
90%
95%
A
13
13
14
15
B
5
7
10
12
C
2
3
14
4
D
1.7
2.4
9
3.12
E
NA3
1.7
9
2.42
F
NA3
1.4
1.72
2.12
1. 100% relative compaction defined as maximum Standard Proctor Density at optimum moisture content. 2. Values typically difficult to achieve, included as reference, 3. Not recommended for use.
Standard Trench Installation, Type 1 Without Traffic Burial depth, m corresponding to values of E’b E’b MPa
1 6
20.7
23.0m
13.8
18.0m
10.3
15.0m
6.9
11.0m
4.8
2
Native Soil Group 3 4
5
2500 STIS 11.0 m 10.0 m 9.0m
7.0m
2.8m
NA
6.0m
2.6m
NA
5.5m
2.6m
NA
7.5m
5.0m
2.4m
NA
8.5m
18.0 m 15.0 m 13.0 m 10.0 m 7.5m
6.0m
4.0m
2.0m
NA
3.4
6.0m
5.5
5.0m
3.8m
1.8m
NA
2.1
4.0m
3.5m
3.5m
2.8m
1.6m
NA
1.4
2.6m
2.6m
2.6m
2.2m
1.4m
NA
Standard Trench Installation, Type 1 Without Traffic Burial depth, m E’b MPa
1
2 6
Native Soil Group 3 4
5
5000 STIS
20.7
23.0m
18.0m
12.0m
7.0m
2.8m
1.2m
13.8
18.0m
15.0m
10.0m
6.5m
3.0m
1.2m
10.3
15.0m
13.0m
9.0m
6.0m
2.8m
1.2m
6.9
11.0m
10.0m
8.0m
5.0m
2.6m
1.2m
4.8
9.0m
7.5m
6.5m
4.5m
2.2m
NA
3.4
6.0m
6.0m
5.0m
4.0m
2.0m
NA
2.1
4.0m
4.0m
3.5m
3.0m
1.8m
NA
1.4
3.0m
3.0m
3.0m
2.6m
1.6m
NA
Standard Trench Installation, Type 1 Without Traffic Burial depth, m E’b MPa
1
2 6
Native Soil Group 3 4
5
10000 STIS
20.7
24.0m
19.0m
12.0m
8.0m
3.6m
1.8m
13.8
19.0m
16.0m
11.0m
7.0m
3.6m
1.8m
10.3
15.0m
13.0m
10.0m
6.5m
3.4m
1.6m
6.9
12.0m
10.0m
8.5m
5.5m
3.2m
1.6m
4.8
9.0m
8.5m
7.0m
5.0m
2.8m
1.6m
3.4
7.0m
6.5m
5.5m
4.5m
2.6m
1.6m
2.1
4.5m
4.5m
4.0m
3.5m
2.4m
1.6m
1.4
3.5m
3.5m
3.4m
3.0m
2.2m
1.6m
Standard Trench Installation, Type 1 With Traffic Burial depth, m E’b MPa
1
2 6
20.7
23.0m
13.8
18.0m
10.3
15.0m
6.9
11.0m
4.8
Native Soil Group 3 4
5
2500 STIS 11.0 m 10.0 m 9.0m
7.0m
NA
NA
6.0m
NA
NA
5.5m
NA
NA
7.5m
5.0m
NA
NA
8.5m
18.0 m 15.0 m 13.0 m 10.0 m 7.5m
6.0m
4.0m
NA
NA
3.4
6.0m
5.5m
5.0m
3.8m
NA
NA
2.1
3.5m
3.5m
3.0m
NA
NA
NA
1.4
NA
NA
NA
NA
NA
NA
Standard Trench Installation, Type 1 With Traffic Burial depth, m E’b MPa
1
2 6
20.7
23.0m
13.8
18.0m
10.3
15.0m
6.9
11.0m
4.8
Native Soil Group 3 4
5
5000 STIS 12.0m
7.0m
3.0m
NA
10.0m
6.5m
2.4m
NA
9.0m
6.0m
2.4m
NA
8.0m
5.0m
NA
NA
8.5m
18.0 m 15.0 m 13.0 m 10.0 m 7.5m
6.5m
4.5m
NA
NA
3.4
6.0m
6.0m
5.0m
4.0m
NA
NA
2.1
4.0m
4.0m
3.5m
3.5m
NA
NA
1.4
2.4m
2.4m
2.2m
NA
NA
NA
Standard Trench Installation, Type 1 With Traffic Burial depth, m E’b MPa
1
2 6
Native Soil Group 3
4
5
10000 STIS
20.7
24.0m
19.0m
12.0m
8.0m
3.5m
NA
13.8
19.0m
16.0m
11.0m
7.0m
3.5m
NA
10.3
15.0m
13.0m
10.0m
6.5m
3.0m
NA
6.9
12.0m
10.0m
8.5m
5.5m
3.0m
NA
4.8
9.5m
8.5m
7.0m
5.0m
2.5m
NA
3.4
7.0m
6.5m
5.5m
4.5m
NA
NA
2.1
4.5m
4.5m
4.0m
3.5m
NA
NA
1.4
3.0m
3.0m
3.0m
2.8m
NA
NA
Compaction of Backfill Helpful tips for compacting the various types of backfill: 1. As a means of "calibrating" an installation method with a given backfill type, we recommend that specific attention be given to compaction techniques and relative compaction results during the installation of the initial sections of pipe used at a given installation site. 2. When these initial pipes are installed, testing should be conducted frequently to assure relative compaction and pipe deflection criteria are being achieved. 3. For backfill placement and compaction in the haunch areas, start compacting under the pipe and work away from the pipe. 4. For side fill, compaction usually progresses best when the backfill is compacted at the trench wall first and compaction progresses toward the pipe. 5. Usually the number of "passes" or repeated applications of the compaction equipment (at a constant rate of movement) will increase the relative compaction. 6. Pipe zone backfill materials should be placed and compacted in uniform lifts on both sides of the pipe. 7. Compaction over the top of the pipe must assure that there is sufficient material to not impact the pipe. At least 150 mm cover should be sufficient when using a hand operated plate vibrator compactor; however, 300 mm is recommended when using a hand operated impact compactor. A relative compaction of no more than 85% SPD can realistically be achieved when compacting the first 300mm lift over the pipe. A measurement of the increase in the vertical diameter of the pipe is a reasonable measure of compaction effort used during the installation and another good "calibration" measurement.
Spangler Equation developed in 1941, now evolved into IOWA formula thru extensive field studies conducted by Howard.
This condition can be simulated in the lab thru strain-corrosion testing.
FIELD SERVICE ENGINEER
Field Service Representative WATANI can assign a Field Service Representative. He will provide assistance to the installer so as the latter may attain a satisfactory pipe installation. This “on-the-job” field service will be provided early in the installation and may be carried on periodically throughout the execution of the project. The service will range from continuous (full time) to intermittent depending on the job schedule, difficulty, and installation results.
Screen Shot of “Butt-Joint Overlay Calculation Software”
Joint Laminate Calculation Software
Screen Shot of “CEASAR II Software”
UNDERGROUND PIPELINE DESIGN ANSI/AWWA Standard C950-95 and AWWA Manual M45 are the basic references of this guideline to select the appropriate GRP pipe for underground installation. AWWA Manual M45 (First Edition 1996) gives the design requirements and criteria for buried fiberglass pressure pipe. Fiberglass pipes are flexible and can sustain large deformation without any difficulties for the material. Vertical loads (covering soil, traffic and water table) determine a deflection depending on soil compaction around the pipe and on ring stiffness of the pipe cross-section. AWWA Manual M45 recognizes that the pipe design can follow two different procedures based on the stress or on the strain. Watani follows the strain procedure. The design procedure involves the following steps: 1. Check the working pressure, Pw 2. Check the surge pressure, Ps The maximum pressure shall not exceed 1.4 the pressure class of the pipe Pw + Ps ≤ 1.4Pc 3. Check ring bending, Sb and, so on…
Buried Pipe Design Calculation Program based on AWWA M45 guideline
Solutions to some worksite problems….
Taking the exact measurement of Pipe O.D.
Accurately taking the Pipe O.D. using Pi Tape
Specially-made GRP connector for Ductile Pipe
GRP-To-Ductile Iron Connection Fitting
GRP-To-Ductile Connection, pressurized to 10 bar
In-situ building-up of GRP spigot to the measured O.D
Large diameter GRP flanges up to 2600mm
Large diameter “Y” branch
Spools
Following are photo shots of GRP duct system for Ardiya and Sulaibiya Waste Water Treatment Plants…
GRP Ducts & Ducting Components, Sulaibiya & Ardiya Projects
GRP Pipe [Arabi Enertech] DN400
We provided help in in-situ jointing
Jointing by “butt-and-wrap” method
A completed in-situ “butt-and-wrap” joint
Thank you very much for your time….