Essential Formula Sheet

  • Uploaded by: Janell Parkhurst, PMP
  • 0
  • 0
  • May 2020
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Essential Formula Sheet as PDF for free.

More details

  • Words: 363
  • Pages: 2
Essential PMP® Formulas __________________________________________________________

Project Selection Bigger is Better: BCR – Benefit/Cost Ratio IRR – Internal Rate of Return PV – Present Value NPV – Net Present Value EVA – Economic Value Add ROI – Return On Investment ROIC – Return On Invested Capital

Smaller is Better: Opportunity Cost Payback Period

Return on Invested Capital (Project Selection – bigger is better) ROIC= Net Income After Tax ÷ Total Capital Invested (Project Selection – bigger is better) Economic Value Add EVA = Net Operating Profit After Tax – Cost of Capital = (Revenue - Op. Expenses - Taxes) (Investment Capital x % Cost of Capital)

PERT Estimate a.k.a. “Three-Point Estimate” (P + 4R + O) / 6 P = Pessimistic R = Realistic (or Most Likely)

O = Optimistic

Standard Deviation of PERT Estimate (P – O) / 6 Pessimistic less Optimistic divided by 6 Critical Path – the combination of activities that, if any are delayed, will delay the project’s finish

Copyright © 2007 Velociteach. All rights reserved.

Essential PMP® Formulas (cont’d) __________________________________________________________

Float – amount of time an activity may be delayed before it moves the project’s critical path Free Float – amount of time an activity may be delayed before impacting early start of any subsequent activity Communication Channels N ( N – 1 ) / 2 ; Where N = the number of people in your team Point of Total Assumption (PTA) The cost point beyond which the Seller incurs all incremental costs, assuming 100% of the risk of cost increases. PTA = Target Cost + ((Ceiling Price – Target Price) / Buyer’s Share) Remember: Cost + Profit = Price Earned Value: BAC = Total Budgeted for the project PV= Planned % Complete X BAC EV= Actual % Complete X BAC AC= Sum of the actual costs CV= EV – AC (From ‘C’ to shining ‘C’) CPI= EV / AC (For a given period of time) EVC / ACC (From beginning to a point in time) CPIC= SV= EV – PV SPI= EV / PV EAC= BAC / CPIC (always use cumulative values for forecasting) ETC= EAC – ACC VAC= BAC - EAC

Copyright © 2007 Velociteach. All rights reserved.

Related Documents


More Documents from ""

June 2020 8
Dpmo Sigma
July 2020 7
June 2020 8