Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE SECRETARY Manila
MAR 0 5 2019' DEPARTMENT ORDER
28
NO.
Series of ~Ol~
)
SUBJECT: Cost Estimation Manual for High Rise Buildings
~
) Cl3.II'.
{i
In line with the Department's Quality Policy to implement projects at the right cost, all Implementing Offices are hereby directed to adopt the herein Cost Estimation Manual For High Rise Buildings in the determination of unit cost of Pay Items of Work involved in the construction and repair/retrofitting of high-rise building projects. This Manual aims to enhance the technical capability of DPWH engineers in the preparation and review of Program of Works (POW) and Approved Budget for the Contract (ABC) and to establish consistency in the format of preparation and serve as a uniform basis/reference in the derivation of unit cost for each item of work. It shall be distributed to all concerned offices of the Department and uploaded in the DPWH Intranet. This Order shall be consistent with the implementation of D.O. No. 163, Series of 2015 "Standard Forms of Program of Works (POW) and Approved Budget for the Contract (ABC)" with modification on its format and description of item number and scope of works (Annex A) to conform with the DPWH Standard Specifications for Public Works Structures, Volume III (Buildings, Ports and Harbors, Flood Control and Drainage Structures and Water Supply Systems) and Standardized Pay Items of Work for Buildings as embodied in D.O. 143/ Series of 2017. This Order shall take effect immediately.
~~
MARK A. VILLAR Secretary 6.1.3 ECG/AMD/WRO Departtrent
of Public Works and Highways Office of the Secretary
1111111111111111111111111111111111111 WIN9W02111
-
2019
Bureau of Construction
Cost Estimation Manual for High Rise Buildings
Department of Public Works and Highways
COST ESTIMATION MANUAL FOR HIGH RISE BUILDINGS
or
TABLE OF CONTENTS
FOREWORD -----------------------------------------------------------------------------------------------------------------------ii i DEFINITION OF TERMS ----------------------------------------------------------------------------------------------------v iii
UNITS, ABBREVIATIONS AND ACRONYMS----------------------------------------------------------------i v PREFACE------------------------------------------------------------------------------------ vivii
INTRODUCTION----------------------------------------------------------------------------------------------viii1
GENERAL NOTES---------------------------------------------------------------------------------------------i 3
A. COST ESTIMATION PROCESS --------------------------------------------------------------------------------------------15 B. STANDARD DETAILED UNIT PRICE ANALYSIS (DUPA) SHEETS ---------------------------------6 13 B.1 Summary Table of Items of Work and Description -----------------------------------------------------7 15 Part A - Earthworks -------------------------------------------------------------------------------------------1626
Part B - Plain and Reinforced Concrete Work ------------------------------------------------------------------------6737 Part C - Finishing---------------------------------------------------------------------------------------7641 Part D - Electrical ---------------------------------------------------------------------------------------------133 187
Part E - Mechanical -------------------------------------------------------------------------------------------------------1 237 B.2 Derivation of DUPA Cost Sheet---------------------------------------------------------------------------------------1 257
C. COSTING OF SUPPORT EQUIPMENT ----------------------------------------------------------------------------------1 259 D. CALCULATION OF CYCLE TIME FOR HAULING EQUIPMENT ----------------------------------------243 263 D.1 Estimated travel speed, loading/unloading time & allowance for delay ---------------------------------244 265 D.2 Formula for the calculation of dump truck travel time --------------------------------------------------------244 265 D.3 Computation of cycle time ---------------------------------------------------------------------------------------244 265 E. COMPUTATION OF LABOR RATES --------------------------------------------------------------------------------245 264 E.1 Basis of Computation -------------------------------------------------------------------------------------------246 265 E.2 Condition for the usage of the labor rates -----------------------------------------------------------------------246 265 E.3 Sample tabulation of labor rates for NCR -------------------------------------------------------------------------247 265 F. EQUIPMENT RENTAL RATES --------------------------------------------------------------------------------------------248 269
FOREWORD
Aligned with the current administration's "Build, Build, Build" program and consistent with its commitment
to excellence, the Department
continuously
formulated
of Public Works and Highways (DPWH) has
and developed guides and techniques
in various fields of the
construction process. This is to ensure the highest standards of its outputs at the right cost.
This Cost Estimation Manual for High Rise Buildings provides Standard Cost Sheets for pay items of work used in high-rise building construction in accordance with the DPWH Standard Specifications for Public Structures (Volume III). This manual was purposely developed to provide uniform reference/basis in unit cost estimation and in the preparation of Program of Works (POW) and Approved Budget of Contract (ABC) for future projects of the Department.
~R~<::"'----Secretary Department
of Public Works and Highways Office of the Secretary
1111111111111111111111111111111111111
WIN9W02111
DEFINITION OF TERMS Program of Works (POW) - is the total estimated cost of the project which covers the Civil Works Cost, Engineering Supervision and Administrative Overhead, Road Right-of-Way Acquisition Cost, Construction Contingency, etc. The POW shall include information about the project location and limits, quantity and unit cost for each item of work, construction duration, funding source, equipment requirements, etc. Approved Budget for the Contract (ABC) - is the total estimated agency estimate (direct cost, indirect cost and tax) for civil works contract of infrastructure projects, wherein it is the ceiling of award of contract for government locally-funded projects and reference for comparison of bid costs of contractors for both locally-funded and foreign-assisted projects. Detailed Unit Price Analysis (DUPA) - is the determination of reasonable unit cost of each item of work which reflects the breakdown showing the quantities of work items, unit prices of materials, equipment rental rates, labor rates and DPWH-prescribed indirect costs including taxes. Standard Labor Rates - are matrices prepared and issued by Department of Public Works and Highways (DPWH) periodically showing the required compensation for manpower workforce of different categories, which comprises the minimum wage as approved by the NWPC, DOLE plus the monetary benefits. ACEL Guidebook 2014 - is a guidebook where rental rates of commonly used equipment for infrastructure projects are based. It is published by Association of Carriers and Equipment Lessors, (ACEL) Inc.. Construction Materials Price Data (CMPD) - is a compilation of unit prices of construction materials updated quarterly per District Engineering Office to be used as reference in the pricing of materials component of the pay items of work in the preparation of DUPA, ABC & POW, including new items of work involved in a VO.
iii
DPWH Standard Specifications for Public Works and Highways - commonly called as “Blue Book”, is a compilation of detailed descriptions of work items in constructing public works and highways projects such as roads, bridges, buildings, etc. In other words, a compilation of specifications of standard works acceptable to the DPWH. - is composed of specifications containing detailed description of the workmanship, material requirements, technical dimensions, materials proportion, datum lines and grades and other established references to follow or adhere to, e.g. AASHTO, ASTM, etc.; basis of measurement, payment and unit of measure/measurement; and basis of acceptance and special details that would give the user a clear view of the work to be done. High Rise Building “16-Storeys or taller in height, i.e. from 48.00 meters above established grade; elevators, fire escapes, sprinkler systems, arrester, beacons and other safety systems, particularly if near airports, are mandatory for all high-rise buildings/structure” Source:
iv
Implementing Rules and Regulations of the National Building Code of the Philippines (PD 1096), 2005 Revised Edition
UNITS AND ABBREVIATIONS
ACRONYMS
Ø " ' % A bd-ft cfm cm cyl ea ft ft³ Ga/# gal h ha hp kg km L ls m m² m³ min mm mt pc PhP psi thk tph yd³
AASHTO American Association of State Highway and Transportation Officials ABC Approved Budget for the Contract Air Cooled Condensing Unit ACCU ACEL Association of Carriers and Equipment Lessors, Inc. ACP Asphalt Concrete Pavement ASTM American Society for Testing and Materials Black Iron BI BOC Bureau of Construction BOD Bureau of Design Compact Fluorescent Lamp CFL Concrete Hollow Block CHB CI Curb Inlet CMPD Construction Materials Price Data CP Contractor's Profit Central Price Monitoring Committee CPMC CWN Common Wire Nail DEO District Engineering Office DO Department Order DOLE Department of Labor and Employment Exhaust Air Grilles EAG ECC Employer's Compensation Contribution ECOLA Emergency Cost Of Living Allowance EDC Estimated Direct Cost EMT Electrical Metal Tubing Fresh Air Grille FAG Fan Coil Unit FCU GI Galvanized Iron High Density Polyethylene HDPE IMC Intermediate Metal Conduit LED Light Emitting Diode NCR National Capital Region NEMA National Electrical Manufacturers Association NWPC National Wages and Productivity Commission OCM Overhead, Contingencies & Miscellaneous OS & Y Outside Screw/Stem and Yoke Valve PACU Package Type Airconditioning Unit PCCP Portland Cement Concrete Pavement PE Polyethylene PN Pressure Nominal POW Program of Works PPR-C Polyprophylene Random Copolymer PVC Polyvinyl Chloride
diameter inch foot percent ampere board-foot cubic foot per minute centimeter cylinder each foot cubic foot Gauge gallon hour hectare horsepower kilogram kilometer liter lump sum meter square meter cubic meter minute millimeter metric ton piece Philippine Peso pound per square inch thick ton per hour cubic yard
v
ACRONYMS RC Reinforced Concrete RCD Return Ceiling Diffuser RCPC Reinforced Concrete Pipe Culvert RLD Return Linear Diffuser Regional Office RO RPM Raised Pavement Markers RSB Reinforcing Steel Bar RSC Rigid Steel Conduit SCD Supply Ceiling Diffuser SLD Supply Linear Diffuser SPT Standard Penetration Test SSS Social Security System THHN Thermoplastic High Heat Nylon-coated TW Thermoplastic Wire TWHN2Thermoplastic Water and Heat resitant Nylon-coated UPMO Unified Project Management Office UPVC Unplasticized Polyvinyl Chloride VO Variation Order VRF Variable Refrigerant Flow XLPE Cross-Linked Polyethylene
vi
PREFACE
The Department of Public Works and Highways, in pursuit of continuous development in performing its mission, formulates standards and guidelines to establish common bases in attaining desired outputs. This manual, Cost Estimation Manual for High Rise Buildings, encloses the scheme of deriving the unit cost of items of work specialized for high rise building construction using actual average productivity rates for labor-intensive or equipment-based works in accordance with the guidelines established by the Department in the preparation of Approved Budget for the Contract (ABC). In anticipation of the Department to the probability of implementing high-rise government buildings and to cope up with the “Build, Build, Build” program of the current administration and thriving construction industry, the Bureau of Construction sees the necessity of establishing guidelines in estimating cost for high-rise buildings aligned with the Department’s mantra of implementing projects at the right cost. Generation of this manual aims to provide a uniform basis in the preparation of reasonable cost estimates specifically for High Rise Buildings which the Department will be involved in the future. Likewise, this manual will aid in facilitating a more efficient review and evaluation of Detailed Unit Price Analysis (DUPA) and Program of Works (POW). Guidelines presented in this manual are structured to be more applicable for high rise building projects to be implemented by the DPWH and other government agencies. Sources in the formulation of this manual were collated data from previously programmed projects of the Bureau, with the help of some private construction companies with expertise in construction of high-rise buildings.
vii
viii
INTRODUCTION Development in construction technology drives the society to invest in building structures designed with new innovations. In keeping up with the continuous progress in the construction industry, the government likewise has been instituting measures in building structures upgraded for resiliency at a reasonable cost. Dealing with the “Build, Build, Build” program, many government agencies started to propose development on their infrastructures to improve their public service and to level competencies amongst private entities. As the construction arm of the government, the DPWH has been involved in providing technical assistance on building construction not only to its own Implementing Offices but also with other government agencies. Hence, as a tool to improve efficiency through facilitating the preparation, review and evaluation of Detailed Unit Price Analysis (DUPA) and Approved Budget for the Contract (ABC) particularly for government building projects, this cost estimation manual is formulated to establish a uniform basis or reference. This manual covers only the common pay items of work in building construction with details on the breakdown for costing of materials, labor, equipment including the overhead cost and contingencies. Usage of this manual in the derivation of unit cost for DPWH projects requires the user’s input for unit rates of materials and labor based on the Department’s Construction Materials Price Data (CMPD) and Standard Labor Rates that are variable for different locations (i.e. Regional and District Engineering Offices). It is limited only to unit cost derivation, thus, methods and techniques in quantity take off are not discussed. It also provides guidelines in the selection of support equipment for construction of high-rise building. This intends not to establish a uniform cost but serves only as a reference on the means of unit cost derivation thus, the estimators may indicate their logical discretion as needed.
1
2
GENERAL NOTES
1.
The capacity of equipment as presented in the standard cost sheet for each item of work may be adjusted to a higher or lower capacity, provided the resulting unit cost is more economical. Rental rates shall still be based on ACEL Guidebook of 2016. Example: In hauling of materials, use of Dump Truck with higher capacity of fifteen (15) m3 instead of ten (10) m3 capacity as presented will result to a lower price, as the capacity gets bigger, the lower the resulting cost of P45.46/m3 of hauling cost from P54.10/m3. Furthermore, the utilization of a Payloader will be optimized.
2.
The capacity of ten (10) m3 for the Dump Truck as presented, may be reduced in cases of extraordinary conditions where the road has a very steep gradient, in a severely deteriorated condition or in cases of bridges with load limitations. It is impractical during the actual hauling to load the full capacity of the Dump Truck. A proper explanation/justifications shall be made, however, in the preparation of estimate.
3.
For items of work that involves hauling and disposal of materials where hauling distance was indicated, in cases when actual hauling distance is shorter or longer than the assumed hauling distance of 3 km in the standard cost sheets, corresponding equipment hours for Dump Truck shall be adjusted based on the cycle time analysis. The actual hauling distance should be the nearest possible disposal site determined by the Implementing Office prior to the preparation of the ABC/POW and shall be indicated in the DUPA.
4.
For equipment utilization of less than one (1) day, the scheduled operating hours shall be paid at operated cost per hour and the remaining hours of the minimum 8 hours a day shall be considered for payment as bare rental rates.
5.
The utilization of equipment other than the equipment model and capacity presented in the standard cost sheets may be allowed, provided there is a corresponding justification in the substitution. Rental rates of equipment should be based from ACEL Guidebook or the Bureau of Equipment Rental Rates guidelines.
6.
The presented DUPA is based on a one (1) gang of labor and equipment with the specified output per unit. To increase the output, additional equipment and labor may be added or an equipment with a higher capacity may be adopted.
7.
The production outputs per item of work were established based on normal condition and study conducted by the Bureau of Construction (BOC) in collaboration with some construction companies expertise in construction of high-rise buildings. Any deviation to suit actual site condition that tends to increase the total unit cost shall be subjected for approval by the BOC.
3
8.
For item of work involving the exposure of workers in the outside environment and height hazards, production output from Cost Estimation Manual for Low Rise Building were adopted but adjusted with additional labor as compensation to the efficiency lost due to such hazards.
9.
For items of work involving interior works, production output from Cost Estimation Manual for Low Rise Building were adopted. It is suggested that hauling of materials on such items be facilitated through support equipment (i.e. Construction Elevator) and delivered on assigned staging area inside the building prior to enclosure of the building perimeter.
10. The application of Mark-Up (OCM and Profit) shall be in accordance with the ranges of the Total Estimated Direct Cost (EDC) of the project as prescribed under D.O. No. 197, Series of 2016 or latest issuance. 11. The cost of materials component in the Standard Cost Sheets shall be based on the latest Construction Materials Price Data submitted quarterly by the District Engineering Offices, which includes payment of local taxes and hauling/delivery cost to site. 12. The cost of labor shall be based on the labor rates established for each District Engineering Office, following the minimum labor wage as approved by the NWPC, DOLE, plus monetary benefits calculated in accordance with D.O. No. 72, Series of 2018 or latest issuance.
4
SECTION A COST ESTIMATION PROCESS
5
6
A. COST ESTIMATION PROCESS DEO
Consultant
Yes Is the project within the limits of authority delegated to the DEO? No
UPMO
RO Yes Is the project within the limits of authority delegated to the RO?
No
BOD & BOC
Assistant Secretary Undersecretary Secretary
District Engineering Office (DEO): 1. The Estimator shall determine the items of work involved based on the Approved Plans. 2. The Estimator shall prepare the DUPA, ABC & POW including its attachments applying the items of work involved based on the latest standard labor rates & CMPD, standard cost sheets and D.O. 22, Series of 2015. 3. The District Engineer shall approve the ABC & POW, if the project is within the limits of authority delegated to him/her. 4. If beyond the authority of the DEO, forward the DUPA, ABC & POW and Approved Construction Plans together with the required attachments to the Regional Office for review/evaluation and approval, if the project is within the limits of the delegated authority of the Regional Director. 5. If Planning and Design Division of the Regional Office will make an adjustment in the quantities and delete/add pay item/s in the submitted construction plans, the ABC & POW shall be adjusted accordingly by the District Engineering Office and resubmit the same for approval. Regional Office (RO): 1. The Estimator shall determine the items of work involved based on the Approved Plans. 2. The Estimator shall prepare the DUPA, ABC & POW including its attachments applying the items of work involved based on the latest standard labor rates & CMPD, standard cost sheets and D.O. 22, Series of 2015. 3. The Regional Director shall approve the ABC & POW, if the project is within the limits of authority delegated to him/her.
7
4. If beyond the authority of the RO, forward the DUPA, ABC & POW and Approved Construction Plans together with the required attachments to the Bureau of Construction (BOC) and Bureau of Design (BOD) respectively, for review/evaluation for approval of the Assistant Secretary for Technical Services, Undersecretary for Technical Services or Secretary depending on the limits of authority. 5. If Bureau of Design shall make an adjustment in the quantities and delete/add pay item/s in the submitted construction plans, the ABC & POW shall be adjusted accordingly by the Regional Office and resubmit the same for approval. Unified Project Management Office (UPMO): 1. The Consultant shall determine the items of work involved based on the Approved Plans. 2. The Consultant shall prepare the DUPA, ABC & POW including its attachments applying the items of work involved. 3. The Project Director shall conduct review/evaluation of the proposed ABC & POW and recommends its approval to the authorized approving official concerned. 4. Forward the ABC & POW and Approved Construction Plans together with the required attachments to the Bureau of Construction (BOC) and Bureau of Design (BOD) respectively, for review/evaluation to be approved by the Assistant Secretary for Technical Services, Undersecretary for Technical Services or Secretary depending on the limits of authority. 5. If the Bureau of Design shall make an adjustment in the quantities and delete/add pay item/s in the submitted construction plans, the ABC & POW shall be adjusted accordingly by the concerned UPMO and resubmit the same for approval. Approval of the ABC & POW shall be based on the following (or its latest issuance): 1. Department Order No. 91, Series of 2012 – Authority of the Assistant Secretary for Technical Services to Approve Plans, Program of Works and Approved Budget for the Contract for DPWH Locally-Funded and Foreign-Assisted Civil Works Projects Costing more than PhP50 Million up to PhP100 Million. 2. Department Order No. 95, Series of 2013 – Reissuance of D.O. No. 9, S. 2011 Re: Conduct of Pre-Procurement, Procurement, and Implementation Activities for DPWH Foreign-Assisted Civil Works Projects. 3. Department Order No. 109, Series of 2014 – Approval of Plans, Program of Works (POW) and Approved Budget for the Contract for DPWH Locally-Funded Projects Costing PhP50 Million and below Implemented by Unified Project Management Offices. 4. Department Order No. 140, Series of 2014 – Increased Limits of Delegated Authority to Regional Directors to Approve Plans, Program of Work (POW) and Approved Budget for the Contract (ABC) of Locally-Funded Projects. 5. Department Order No. 54, Series of 2011 – Revised Limits of Responsibilities and Authorities of Concerned DPWH Offices and Officials in the Conduct of PreProcurement, Procurement, and Implementation Activities for DPWH Locally-Funded Civil Works Project.
8
PREPARATION OF DETAILED UNIT PRICE ANALYSIS 1. General a. Determine the scope of works based on approved plans and specification including other requirements adopting the standard pay items of works per Department Order No. 143, Series of 2017. b. Calculate the quantity and cost of material component of every item of work based on plans and specifications and prevailing prices of construction materials in the Construction Materials Price Data (CMPD) with consideration of allowance for waste and/or losses not to exceed 5% of the material’s requirement. c. Determine the appropriate quantity based on best norms and practices in the construction industry and cost for manpower and equipment requirement to be used based on Standard Labor Rates per Region and latest ACEL rates. d. Determine the unit cost per item of work as presented in Item 5. 2. Determination of category of work supervisor The appropriate number and category of supervisor including unskilled labor to be deployed depends on the specific type and complexity of an item of work to be done. In this manual, the labor force (crew or gang) were established based on actual study and best practices observed during the construction of BOC implemented projects. Example: Item 900-Concrete Works Foreman------------------------------------1 Skilled Worker (Mason, carpenter)----- 2 Unskilled Labor---------------------------- 6 3. Calculation of production output per hour of an item of work The production output per hour of an item of work should be derived based on the number of days and appropriate manpower and equipment utilized to complete the work in accordance with the right construction methodology. In this manual, the production output was derived by the Bureau of Construction (BOC) Engineers based on actual study and best practices during the construction of BOC implemented projects. Example: Item 900-Concrete Works Volume of Concrete = 21.50 cubic meter Number of hours to complete the work which includes setting of equipment and accessories, batching, delivery and pouring of concrete= 6 hours and 21 minutes (6.85 hr) Type and number of manpower utilized during pouring Foreman---------------------------------- 1 Skilled Worker (Mason, Carpenter) --- 2 Unskilled Labor--------------------------- 6
9
Type and number of equipment and tools including lightings utilized during pouring: Transit Mixer ------------------------------4 Pump-Crete --------------------------------1 Concrete Vibrator--------------------------2 Lighting System (if applicable) ----------1 Production output per hour=volume of concrete poured/number of hours consumed to complete the pouring session = 25.5 cu.m/ 6.85 hr = 3.72 cu.m/hr 4. Determination of percentages of Overhead, Contingency and Miscellaneous (OCM) expenses, Profit and Value-Added Tax (VAT) The percentages of OCM, Profit and VAT to be applied to the estimated direct cost (i.e. cost of material, labor and equipment rental) should be based on Department Order (DO) No. 197, Series of 2016 (Guidelines in the Preparation of Approved Budget for the Contract) or latest issuance. 5. Determination of unit cost per item of work Unit Cost=total unit direct cost (i.e. cost of materials, labor, Equipment) plus indirect cost (i.e. OCM, Profit and VAT) Example: Item 900-Concrete Works
10
6. Cost estimation techniques and best practices a. Skills in the interpretation of the plans and specifications b. Wide experience in actual construction and estimating works c. Familiarity with different types of construction materials and equipment d. Consideration on actual site condition in the preparation of DUPA i.e. hauling distance, terrain, etc. e. Familiarity on laws, policies, guidelines and procedures pertaining to the implementation of government infrastructure projects to ensure cost estimates are done at the right cost
11
12
SECTION B STANDARD DETAILED UNIT PRICE ANALYSIS (DUPA) SHEETS
13
14
B.1 SUMMARY TABLE OF ITEMS OF WORK AND DESCRIPTION ITEM NO.
DESCRIPTION
PART A
EARTHWORKS
PAGE NO.
800(1)
Clearing and Grubbing (m2)
26
800(2)
Clearing and Grubbing (l.s.)
27
803(1)a
Structure Excavation (Common Soil)
28
803(1)b
Structure Excavation (Soft Rock)
29
803(1)c
Structure Excavation (Hard Rock)
30
803(2)
Trimming Works
31
803(3)
Soil Stablization - a. Jet Grouting (0.80 m diameter)
32
803(3)
Soil Stablization - b. Structural Steel Sheet Piles, furnished and driven
33
804(1)a
Embankment from Structure Excavation
34
804(1)b
Embankment from Common Borrow by Equipment
35
804(4)
Gravel Bedding
36
PART B
PLAIN AND REINFORCED CONCRETE WORKS Structural Concrete (Ready Mix, Class AA/Class A/Class B/Class C/Class P/Seal Concrete, 7 days/14 days/ 28 days)
37
901(1)
Lean Concrete (Ready Mix, 28 days)
38
902(1)
Reinforcing Steel of Reinforced Concrete Structures for Two upto Five Storey , Grade 40/Grade 60
39
903(2)
Formworks and Falseworks (for two to five-storey building)
40
900
PART C
FINISHING
1000(1)
Soil Poisoning
41
1001(1)a
50 mm Ø -100 mm Ø PVC Pipe and Fittings, Series 600/ Series 1000
42
1001(1)a
150 mm - 300 mm Ø PVC Pipe and Fittings, Series 600/ Series 1000
43
1001(1)b1
150 mm Ø Concrete Pipe
44
1001(1)b2
200 mm Ø Concrete Pipe
45
15
Summary Table of Items of Work and Description
ITEM NO. 1001(1)b3
DESCRIPTION
PAGE NO.
250 mm Ø Concrete Pipe
46
1001(1)b4
300 mm Ø Concrete Pipe
47
1001(1)b5
350 mm Ø Concrete Pipe
48
1001(1)c
50 mm Ø - 100 mm Ø High Density Polyethylene (HDPE) Pipe
49
1001(1)c
150 mm Ø - 300mm ØHigh Density Polyethylene (HDPE) Pipe
50
PVC/HDPE Fittings
51
1001(2)
Concrete Gutter
52
1001(5)
Catch Basin (Concrete/CHB)
53
1001(7)
Junction Box (Concrete/CHB)
54
1001(8)
Sewer Line Works (lump sum)
55
1001(9)
Storm Drainage and Downspout (lump sum)
56
1002(1)
13 mm Ø - 50 mm Ø Galvanized Iron Pipe and Fittings
57
1002(1)
65 mm Ø - 150 mm Ø Galvanized Iron Pipe and Fittngs
58
1002(2)
Galvanized Iron Fittings
59
1002(2)a
13mmØ - 50mm ØPolyprophylene Random Copolymer (PPR-C) Pipe and Fittings, PN 16/ PN 20
60
1002(2)
63mmØ - 100mm Ø Polyprophylene Random Copolymer (PPRC) Pipe and Fittings PN 16/ PN 20
61
1002(3)
Polyprophylene Random Copolymer (PPR-C) Fittings
62
1001
1002(3) 1002(3)
13 mm Ø - 50 mm Ø Polyvinyl Chloride (PVC) Pipe and Fittings, Blue 65 mm Ø - 100 mm Ø Polyvinyl Chloride (PVC) Pipe and Fittings, Blue
63 64
1002(4)
Polyvinyl Chloride (PVC) Fittings, Blue
65
1002(4)
Plumbing Fixtures
66
1002(5)
Water Closet/ Urinal with Complete Accessories
67
1002(11)
Kitchen Sink/Scrub Up Sink/Slop Sink with Complete Accessories
68
1002(14)
Wall Hung/Countertop/Under Counter Lavatory with Complete Accessories
69
16
Summary Table of Items of Work and Description
ITEM NO.
DESCRIPTION
1002(16)
Floor Drain Plates
70
1002(5)
Soap Holder ( Toilet Soap/ Liquid Soap)
71
1002(5)
Toilet Tissue Holder/Dispenser
72
1002(17)
Bidet/ Faucet/ Hose Bibb
73
1002(18)
Stainless Steel Grab bar
74
1002(19)
Shower head/ Shower Valve
75
1002(20)
Facial Mirror
76
1002(24)
Cold Waterline Pipes and Fittings
77
1002(25)
Hot Waterline Pipes and Fittings
78
1003(1)
4.5mm Fiber Cement Board/ 4.5 mm Marine Plywood/ 6 mm Marine Plywood/ 6mm Ordinary Plywood on Metal Frame Ceiling
79
1003(1)a
4.5mm Fiber Cement Board/ 4.5 mm Marine Plywood/ 6 mm Marine Plywood/ 6mm Ordinary Plywood in Wood Framing Ceiling
80
1003(1)e
Gypsum Board on Metal Frame Ceiling
81
1003(2)
4.5mm/ 6.0 mm Fiber Cement Board/ 4.5mm/ 6.0 mm 4' X 8' thk fiber cement board/ 4.5mm Marine Plywood/ 6.0 mm Marine Plywood/ 6.0 mm Ordinary Plywood on Metal Frame Double Wall Partition
82
1004(2)
Finishing Hardware
83
1005
Residential Casement Steel Windows/ Heavy Duty Side-hinged Ventilator/ Projected Ventilator/ Awning Ventilator/ Grille Window
84
1006
Hollow Steel Door/ Steel Flush Door/ Grille Door/ Steel Louver Door
85
Fire Rated Fire Exit Steel Door
86
1007
Aluminum Glass Door (Sliding Type/Swing Type)
87
1008
Aluminum Glass Window (Sliding/ Casement/ Awning/ Fixed Type)
88
1010(1)
Frames (Jambs, Sill, Head, Transoms and Mullions)
89
1010(2)a
Hollow Core Flush Door
90
1010(2)b
Wooden Panel Door
91
1006(5)
PAGE NO.
17
Summary Table of Items of Work and Description
ITEM NO.
DESCRIPTION
PAGE NO.
1011(1)
Steel/ Aluminum Roll Up Door
92
1012(1)
Tempered Glass Door (10 mm/ 12mm)
93
1012(1)
Tempered Glass Windows (8 mm/ 10mm)
94
1013(1)
Corrugated Metal Roofing
95
1013(2)
Fabricated Metal Roofing Accessory (Ridge/Hip Rolls/Flashings/Counter Flashing/Valley Roll)
96
1013(2)c
Fabricated Metal Roofing Accessory (Gutter)
97
1014
Prepainted Metal Sheets (Corrugated, Short Span/ Long Span, below 0.427 thk/ above 0.427 thk)
98
1014
Prepainted Metal Sheets (Rib Type, Short Span/ Long Span, below 0.427 thk/ above 0.427 thk)
99
1016(1)a
Waterproofing Cement Base
100
1016(1)b
Liquid Waterproofing
101
1016(2)
Built-up and Preformed Membrane
102
50mm ø - 100mm ø Roof Drain/Canopy Drain/ Gutter Drain with Strainer
103
Glazed Tiles and Trims
104
Unglazed Tiles/ Granite Tiles/ Synthetic Granite Tiles
105
1019(1)
Wood Tiles (Narra, Tanguile, others)
106
1019(1)d
Laminated Wood Tiles
107
1020(1)
Vinyl Tiles
108
1021(1)a
Plain Cement Floor Fnish
109
1021(3)
Floor Topping
110
1023(1)
Granolithic Marble Work
111
1024(1)
Pea Gravel Finish
112
1026(1)
Pebble Washout Finish
113
1027(1)
Cement Plaster Finish
114
1032(1)a
Painting Works (Masonry Painting)
115
1032(1)b
Painting Works (Wood Painting)
116
1017 1018(1) 1018
18
Summary Table of Items of Work and Description
ITEM NO.
DESCRIPTION
PAGE NO.
1032(1)c
Painting Works (Metal Painting)
117
1032(2)
Varnishing Works
118
1032(4)
Ducco Finish
119
1034(1)
Damproofing ( Polyethylene Sheets)
120
1038(1)
Reflective Insulation
121
1042(1)
Stainless Steel Door and Frames
122
1043(1)
PVC Doors and Frames
123
1045(1)
Perforated Aluminum Ceiling Panels
124
1046
100 mm CHB Non Load Bearing/Load Bearing (including Reinforcing Steel)
125
1046
150mm CHB Non-LoadBearing/ Load Bearing (including Reinforcing Steel)
126
1047(1)
Structural Steel Roof Framing
127
1047(2)a
Structural Steel Roof Framing
128
1047(2)b
Structural Steel Roof Truss
129
1047(2)c
Structural Steel Purlins
130
1047(3)a
Metal Structure Accessories (Anchor Bolts)
131
1047(3)b
Metal Structure Accessories (Sagrods)
132
1047(3)c
Metal Structure Accessories (Turnbuckle)
133
1047(3)d
Metal Structure Accessories (Crossbracing, )
134
1047(4)
Metal Structure Accessories (Crossbracing)
135
1047(5)
Metal Structure Accessories (Steel Plates)
136
1048(1)a
Carbon Fiber (1 layer)
137
1048(2)
Glass Fiber
138
1049(1)
Jet Grouting (0.80 m diameter)
139
1052(4)a.1
Precast Concrete Piles, furnished (400mm x 400mm -type A)
140
1052(4)a.2
Precast Concrete Piles, furnished (400mm x 400mm -type B)
141
19
Summary Table of Items of Work and Description
ITEM NO.
DESCRIPTION
PAGE NO.
1052(4)b.1
Precast Concrete Piles, furnished (450mm x 450mm -type C)
142
1052(4)b.2
Precast Concrete Piles, furnished (450mm x 450mm -type D)
143
1052(5)a
Precast, Prestressed Concrete Piles, furnished (400 mm x 400 mm)
144
1052(5)b
Precast, Prestressed Concrete Piles, furnished (450 mm x 450 mm)
145
1052(6)
Structural Steel Sheet Piles, furnished
146
1052(7)a
Precast Concrete Sheet Piles, furnished (0.50 m x 0.35 m)
147
1052(7)b
Precast Concrete Sheet Piles, furnished (0.50 m x 0.35 m), (Ready Mix Concrete)
148
1052(11)
Steel Pipe Piles, furnished and driven
149
1052(12)
Structural Steel Sheet Piles, driven
150
1052(13)
Precast Concrete Sheet Piles, driven
151
1052(14)a
Precast Concrete Piles, driven (soft strata)
152
1052(14)b
Precast Concrete Piles, driven (hard strata)
153
1052(15)a
Precast, Prestressed Concrete Piles, driven (soft strata)
154
1052(15)b
Precast, Prestressed Concrete Piles, driven (hard strata)
155
1052(16)a
Test Piles, furnished and driven (type A, B, C or D), soft strata
156
1052(16)b
Test Piles, furnished and driven (type A, B, C or D), hard strata
157
1052(17)a
Concrete Piles cast in Drilled Holes, 0.80 m. Ø, fc' = 28 MPa (ordinary soil condition)
158
1052(17)b
Concrete Piles cast in Drilled Holes, 1.00 m. Ø, fc' = 28 MPa (ordinary soil condition)
159
1052(17)c
Concrete Piles cast in Drilled Holes, 1.20 m. Ø, fc' = 28 MPa (ordinary soil condition)
160
1052(17)d
Concrete Piles cast in Drilled Holes, 1.50 m. Ø, fc' = 28 MPa (ordinary soil condition)
161
1052(17)e
Concrete Piles cast in Drilled Holes, 1.80 m. Ø, fc' = 28 MPa (ordinary soil condition)
162
1052(17)f
Concrete Piles cast in Drilled Holes, 2.00 m. Ø, fc' = 28 MPa (ordinary soil condition)
163
20
Summary Table of Items of Work and Description
ITEM NO.
DESCRIPTION
1052(18)a
Concrete Piles cast in Steel Shells, furnished and driven
164
1052(18)b
Concrete Piles cast in Steel Shells, furnished and driven (Ready Mix Concrete)
165
1052(19)a
Concrete Piles cast in Steel Pipes, furnished and driven
166
1052(19)b
Concrete Piles cast in Steel Pipes, furnished and driven (Ready Mix Concrete)
167
1052(20)
Pile Shoes
168
1052(23)a
Bored Piles, 0.80 m. Ø (ordinary soil condition)
169
1052(23)b
Bored Piles, 1.00 m. Ø (ordinary soil condition)
170
1052(23)c
Bored Piles, 1.20 m. Ø (ordinary soil condition)
171
1052(23)d
Bored Piles, 1.50 m. Ø (ordinary soil condition)
172
1052(23)e
Bored Piles, 1.80 m. Ø (ordinary soil condition)
173
1052(23)f
Bored Piles, 2.00 m. Ø (ordinary soil condition)
174
1052(24)a
Permanent Casing (0.80 m Ø)
175
1052(24)b
Permanent Casing (1.00 m Ø)
176
1052(24)c
Permanent Casing (1.20 m Ø)
177
1052(24)d
Permanent Casing (1.50 m Ø)
178
1052(24)e
Permanent Casing (1.80 m Ø)
179
1052(24)f
Permanent Casing (2.00 m Ø)
180
1052(25)
Splicing of RC Piles with Epoxy (400 mm x 400 mm)
181
1052(26)
Splicing of RC Piles with Epoxy (450 mm x 450 mm)
182
1052(27)a
Pile Integrity Testing (Sonic), ordinary soil condition
183
1052(27)b
Pile Integrity Testing (PIT), ordinary soil condition
184
1052(22)b
High Strain Dynamic Testing (PDA), ordinary soil condition
185
1052 (29)
Micro Piles In Drilled Holes, 0.20m Ø (ordinary soil condition)
186
D. 1100(1)
PAGE NO.
ELECTRICAL 15 mm Ø - 25 mm Ø Rigid Steel Conduit (RSC)/Intermediate metal Conduit (IMC)/ Electrical Metal Tubing (EMT)
21
187
Summary Table of Items of Work and Description
ITEM NO.
DESCRIPTION
PAGE NO.
1100(1)
32 mm Ø - 40 mm Ø Rigid Steel Conduit (RSC)/ Intermediate metal Conduit (IMC)/ Electrical Metal Tubing (EMT)
188
1100(1)
50 mm Ø - 65 mm Ø Rigid Steel Conduit/ Intermediate metal Conduit (IMC)/ Electrical Metal Tubing (EMT)
189
1100(1)
80 mm Ø - 100 mm Ø Rigid Steel Conduit (RSC)/ Intermediate metal Conduit (IMC)/ Electrical Metal Tubing (EMT)
190
1100(3)
15 mm Ø - 25 mm Ø Flexible Metal Conduit
191
1100(6)
15 mm Ø - 32 mm Ø Polyvinyl Chloride (PVC) Pipes
192
1100(9)
PVC/RSC/ IMC/ EMT Conduit Fittings
193
1100(11)
Junction/ Utility/ Pull/ Square Box
194
1100(10)
Conduit Works, Boxes and Fittings
195
1101(1)
1.6 mm2 - 5.5 mm2 Electric Wire (TW/THHN/TWHN2)
196
1101(1)
8.00 mm2 - 22 mm2 Electric Wire (TW/THHN/TWHN2)
197
1101(1)
30.00 mm2 - 38 mm2 Electric Wire (TW/THHN/TWHN2)
198
1101(1)
50.00 mm2 - 60 mm2 Electric Wire (TW/THHN/TWHN2)
199
1101(1)
80.00 mm2 - 125 mm2 Electric Wire (TW/THHN/TWHN2)
200
1101(1)
150.00 mm2 - 250 mm2 Electric Wire (TW/THHN/TWHN2)
201
1101(1)
325.00 mm2 - 400 mm2 Electric Wire (TW/THHN/TWHN2)
202
500.00 mm2 Electric Wire (TW/THHN/TWHN2)
203
1101(2)
XLPE Electric Wires
204
1109(4)
2.00 mm2 - 5.5 mm2 Bare Copper Wire
205
1109(4)
8.00 mm2 - 22.00 mm2 Bare Copper Wire
206
1109(4)
30.00 mm2 - 38.00 mm2 Bare Copper Wire
207
1109(4)
50.00 mm2 - 60.00 mm2 Bare Copper Wire
208
1109(4)
80.00 mm2 - 125.00 mm2 Bare Copper Wire
209
1109(1)
200.00 mm2 - 250.00 mm2 Bare Copper Wire
210
1101(33)
Switches
211
1101(1)b19
22
Summary Table of Items of Work and Description
ITEM NO.
DESCRIPTION
PAGE NO.
1101 (15)
Single Convenience Outlet/Receptacle, Grounding Type (GT)/ Heavy Duty Convenience Outlet/Receptacle, Grounding Type (GT)/ Weather Proof Single Convenience Outlet/Receptacle, Grounding Type (GT)/ Pop-up Type/Floor Triplex Convenience Outlet/Receptacle, Grounding Type (GT)
212
1101 (16)
Duplex Convenience Outlet/Receptacle, Grounding Type (GT) / Weather Proof Duplex Convenience Outlet/Receptacle, Grounding Type (GT)/ Special Purpose Convenience Outlet/Receptacle, Grounding Type for ACU, WH, etc/ Explosion Proof Type Duplex Convenience Outlet/Receptacle, Grounding Type (GT)/ Duplex Convenience Outlet/Receptacle with Ground Fault Circuit Interupter
213
1101 (21)
Pop-up Type/Floor Single Convenience Outlet/Receptacle, Grounding Type (GT)/ Pop-up Type/Floor Duplex Convenience Outlet/Receptacle, Grounding Type (GT)/ Explosion Proof Type Single Convenience Outlet/Receptacle, Grounding Type (GT)/ Single Convenience Outlet/Receptacle with Ground Fault Circuit Interrupter
214
1101 (33)
Wires and Wiring Devices
215
1102 (1)
Panel Board with Main Breaker/Branches, 3 wires, 1 neutral, 250 Amp - 400 Amp
216
1102 (1)
Panel Board with Main Breaker/Branches, 3 wires, 1 neutral, 50 Amp - 200 Amp
217
1102 (1)
NEMA I (Enclosed Circuit Breaker) Single Phase or Three Phase Commercial/Industrial Type
218
1102 (1)
NEMA 3R (Enclosed Circuit Breaker) Single Phase or Three Phase Commercial/Industrial Type
219
1102 (2)
Motor Control Center with main, branch breaker and motor starter (NEMA 1, NEMA 3R and 4X) Flush or Surface Mounted
220
1102 (16)
Generator (Stand by and Continuous), Synchonizing Panel for Generator, High Voltage Switch Gear
221
1102 (1)
Main Enclosed Automatic Circuit Breaker 50 AT, 60 AT, 70 AT , 3P, 240V: NEMA I, NEMA 3R, NEMA 4x Flushed/ Surface Mounted
222
1102 (1)
Main Enclosed Automatic Circuit Breaker 50 AT, 60 AT, 70 AT , 2P, 240V NEMA I, NEMA 3R, NEMA 4x Flushed/ Surface Mounted
223
23
Summary Table of Items of Work and Description
ITEM NO.
DESCRIPTION
PAGE NO.
1102 (1)
Main Enclosed Automatic Circuit Breaker 100 AT, 125 AT, 205 AT , 225 AT, 3P, 240V NEMA I, NEMA 3R, NEMA 4x Flushed/ Surface Mounted
224
1102 (1)
Main Enclosed Automatic Circuit Breaker 100 AT, 125 AT, 200 AT , 2P, 225 AT, 2P, 240V NEMA I, NEMA 3R, NEMA 4x Flushed/ Surface Mounted
225
1102 (1)
Low Voltage Switch Board Main 2500-4000 AT, 3P, 240V NEMA I with Breaker
226
1102 (1)
Main Enclosed Automatic Breaker 250-500 Amp
227
1103 (1)
Fluorescent Lighting Fixture with Ballast /Light Emitting Diode (LED) Bulb, 1 Bulb
228
1103 (1)
Fluorescent Lighting Fixture with Ballast /Light Emitting Diode (LED) Bulb, 2 Bulbs
229
1103 (1)
Fluorescent Lighting Fixture with Ballast /Light Emitting Diode (LED) Bulb, 3 Bulbs
230
1103 (1)
Fluorescent Lighting Fixture with Ballast /Light Emitting Diode (LED) Bulb, 4 Bulbs
231
1103 (1)
Downlight/Pinlight Fixture with One- Compact Fluorecent Lamp (CFL) or LED Bulb, 1 Bulb
232
1103 (1)
Downlight/Pinlight Fixture with Two- Compact Fluorecent Lamp (CFL) or LED Bulb, 2 Bulb
233
1103 (1)
High Bay Aluminum Reflector, Dome Luminaire
234
1103 (1)
Die-Cast Aluminum Floodlight with Electrocoat Paint Finish
235
1103 (1)
Lighting Fixtures
236
PART E
MECHANICAL
1200(13)a
Air Conditioning and Refrigiration System
237
1201(1)
Water Pumping System
238
1202(1)
Automatic Water Sprinkler System
239
1202(2)
Fire Pump with complete control and standard accessories
240
1202(3)
Jockey Pump with complete control and standard accessories
241
1202(1)
Sprinkler Head, upright/pendent/wall
242
1202(1)
Alarm Check Valve
243
24
Summary Table of Items of Work and Description
ITEM NO.
DESCRIPTION
PAGE NO.
1202(1)
Flow Meter
244
1202(1)
OS & Y Gate Valve 175 psi
245
1202(1)
Pressure Gauge
246
1202(1)
Pressure Relief Valve
247
1202(1)
Floor Control Valve
248
1202(1)
Inspector Test Valve
249
1202(1)
Inspector Test Connection
250
1202(1)
25 mm Ø - 50 mm Ø Black Iron (B.I.) Pipe and Fittings
251
1202(1)
65 mm Ø -150 mm Ø Black Iron (B.I.) Pipe and Fittings
252
1202(1)
Fittings
253
1202(7)
Fire Hose Valve siames 150 mm Ø x 2 w x 65 mm Ø with cap
254
1202(5)
Fire Hose Cabinet
255
1202(a1)
Fire Extinguisher
256
25
Summary Table of Items of Work and Description
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
800(1)
Clearing and Grubbing 2 m 500.00 m2
Designation
No. of Person/s
No. of Hour/s
1 2
1.00 1.00
No of Unit/s
No. of Hour/s
a. Dumptruck (12 yd )
2
1.00
3
1 1
1.00 1.00
Unit
Quantity
A. Labor a. Construction Foreman b. Unskilled Laborer
Hourly Rate
Amount (PhP)
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment 3
b. Payloader (1.50 m ) c. Bulldozer (155 Hp), D65A-8 Note: Assumed hauling distance is 3 km. If actual hauling distance is shorter or longer than 3 km, the time of dump truck will be adjusted accordingly based on the hauling cycle analysis. Based on assumed 150 mm cut all throughout. A corresponding adjustment in the output shall be computed based on the actual field requirements.
Sub - Total for B Total (A + B) 2 500.00 m D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
26
Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
800(2)
Clearing and Grubbing ls 1.00 ls
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
No. of Hour/s
Hourly Rate
Amount (PhP)
Quantity
Unit Cost
Amount (PhP)
A. Labor See derivations for Item Nos. 800(1), 800(3) and 800(4)
Sub - Total for A Name and Capacity
No of Unit/s
B. Equipment See derivations for Item Nos. 800(1), 800(3) and 800(4)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.00 ls E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials See derivations for Item Nos. 800(1), 800(3) and 800(4)
Sub - Total for F G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/ 8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item No. 800(1), 800(3), and 800(4)
27
Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
803(1)a
Structure Excavation (Common Soil) 3 m 3 20.00 m
Designation
No. of Person/s
No. of Hour/s
1 3
1.00 1.00
No of Unit/s
No. of Hour/s
a. Backhoe (0.80 m )
1
1.00
b. Dump Truck (12 yd3) Minor Tools (10% of labor cost)
2
1.00
Unit
Quantity
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment 3
Sub - Total for B Total (A + B) 20.00 m3 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/ 8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note: 1. Additional labor and/or equipment may be added for dispossal of surplus excavated material.
28
Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
803(1)b
Structure Excavation (Soft Rock) 3 m 3 14.00 m
Designation
No. of Person/s
No. of Hour/s
1 3
1.00 1.00
No of Unit/s
No. of Hour/s
2
1.00
1
0.50
1
0.50
Unit
Quantity
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment 3
a. Dump Truck (12 yd ) 3
b. Backhoe (0.80 m ) 3
c. Backhoe with Breaker (0.80 m ) Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 14.00 m3 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
29
Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
803(1)c
Structure Excavation (Hard Rock) 3 m 3 4.00 m
Designation
No. of Person/s
No. of Hour/s
1 3
1.00 1.00
No of Unit/s
No. of Hour/s
2
1.00
1
0.25
1
0.75
Unit
Quantity
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment 3
a. Dump Truck (12 yd ) 3
b. Backhoe (0.80 m ) 3
c. Backhoe with Breaker (0.80 m ) Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 4.00 m3 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
30
Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
803(2)
Trimming Works 2 m 2 5.00 m
Designation
No. of Person/s
No. of Hour/s
1 4
1.00 1.00
No of Unit/s
No. of Hour/s
1 1
0.50 0.50
Unit
Quantity
kg
30.72
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Bentonite Bin b. Bentonite Mixer c. Minor Tools (10 % of Labor rate)
Sub - Total for B Total (A + B) 5.00 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Bentonite
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
31
Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
803(3)
Soil Stablization - a. Jet Grouting (0.80 m diameter) m 1.18 m
Designation
No. of Person/s
No. of Hour/s
1 6 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 1 1
1.00 1.00 1.00 1.00 1.00 1.00
Name and Specification
Unit
Quantity
a. Portland Cement b. Additives c. Consumables (5% of Material Cost)
bags L
14.00 3.50
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
B. Equipment a. Jetting Machine b. Air Compressor 12 Bars/600 CFM c. Water Tank/Pump d. Agitator e. Generator/Power Supply f. High Pressure Pump
See latest ACEL rental rates.
Sub - Total for B Total (A + B) 1.20 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Unit Cost
Amount (PhP)
F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
32
Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
803(3)
Soil Stablization - b. Structural Steel Sheet Piles, furnished and driven m. 72.00 m.
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor Refer to Item 1052(6) - Structural Steel Pile, furnished and Item 1052(12) - Structural Steel Pile, driven
Sub - Total for A Name and Capacity
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
B. Equipment Refer to Item 1052(6) - Structural Steel Pile, furnished and Item 1052(12) - Structural Steel Pile, driven
Sub - Total for B C. Total (A + B) D. Output per Hour = 72.00 m. E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
F. Materials Refer to Item 1052(6) - Structural Steel Pile, furnished and Item 1052(12) - Structural Steel Pile, driven
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
33
Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
804(1)a
Embankment from Structure Excavation 3 m 3 9.84 m
Designation
No. of Person/s
No. of Hour/s
1 3
1.00 1.00
No of Unit/s
No. of Hour/s
1
0.75
1
0.75
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
B. Equipment a. Plate Compactor (5 hp) 3 b. Backhoe (0.80 m ) Minor Tools (10% of Labor)
Sub - Total for B Total (A + B) 9.84 m3 D. Output per Hour = E. Direct Unit Cost (C ÷ D)
0.00 0.00
C.
Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
F. Materials
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
34
Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
804(1)b
Embankment from Common Borrow by Equipment 3 m 3 9.84 m
Designation
No. of Person/s
No. of Hour/s
1 3
1.00 1.00
No of Unit/s
No. of Hour/s
1
0.75
1
0.75
Unit
Quantity
m3
1.25
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Plate Compactor 3 b. Backhoe (0.80 m ) Minor Tools (10% of Labor)
Sub - Total for B Total (A + B) 9.84 m3 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Embankment Material (w/ 25% Shrinkage Factor)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
12%9%7%6% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
35
Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
804(4)
Gravel Bedding 3 m 3 1.20 m
Designation
No. of Person/s
No. of Hour/s
1 3
1.00 1.00
No of Unit/s
No. of Hour/s
1
0.50
Unit
Quantity
m3
1.05
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Plate Compactor Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 1.20 m3 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Gravel Bedding (G1) (w/ 5% Shrinkage Factor)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
36
Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output per hour
: :
900
Structural Concrete (Ready Mix, Class AA/Class A/Class B/Class C/Class P/Seal Concrete, 7 days/14 days/ 28 days) 3
m 3.72
Designation
No. of Person/s
No. of Hour/s
1 3 6
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
2 1
1.00 0.27
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District Labor Rates are variable Region/District based on minimum wage per as approved by based on minimum as approved DOLE. Refer to the wage Schedule of Labor by Rates. DOLE.Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
B. Equipment a. Concrete Vibrator b. Pumpcrete Minor Tools (10% of labor cost)
* if beyond reach of pumpcrete concrete bucket may be used and costing shall be considered in the support equipment Sub - Total for B Total (A + B) 3 3.35 m D. Output per Hour = E. Direct Unit Cost (C ÷ D)
0.00 0.00
C.
Name and Specification
Unit
a. Ready Mix, Class AA/Class B/Class C/Class P, 7 days/14 days/ 28 days
m
Quantity
Unit Cost
Amount (PhP)
F. Materials 3
1.05
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/ 8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note: 1. This cost sheet shall be used for concrete pouring by pumpcrete. Item Nos. 900(1)a1, 900(1)b1, 900(1)c1, 900(2)a, 900(2)b, 900(2)c, 900(3)a, 900(3)b, 900(3)c, 900(4)a, 900(4)b, 900(4)c, 900(5), 900(6), and 900(8) shall used this cost sheet.
37
Part B - Plain and Reinforced Concrete Works
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
901(1)
Lean Concrete (Ready Mix, 28 days) 3 m 3 3.72 m
Designation
No. of Person/s
No. of Hour/s
1 2 6
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
2 1
1.00 0.27
Unit
Quantity
m3
1.05
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE.Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
B. Equipment a. Concrete Vibrator b. Pumpcrete Minor Tools (10% of Labor Cost)
See latest ACEL rental rates.
Sub - Total for B C.
Total (A + B)
3.72 m3 D. Output per Hour = E. Direct Unit Cost (C ÷ D) Name and Specification
Unit Cost
Amount (PhP)
F. Materials a. Ready Mix Concrete, Lean Concrete, 28days
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
38
Part B - Plain and Reinforced Concrete Works
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
902(1)
Reinforcing Steel of Reinforced Concrete Structures kg 129.094 kg
Designation
No. of Person/s
No. of Hour/s
1 6 12
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
1 1
0.50 0.50
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
B. Equipment a. Bar Cutter b. Bar Bender Minor Tools (10% of labor cost)
C.
Sub - Total for B
0.00
Total (A + B)
0.00
D. Output per Hour = 129.094 kg E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
Quantity
kg
1.00
kg
0.015
Unit Cost
Amount (PhP)
F. Materials a. Deformed Reinforcing Steel Grade 60/Grade 40 b. #16 Galvanized Iron Wire c. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
39
Part B - Plain and Reinforced Concrete Works
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
903(2)
Formworks and Falseworks 2 m 2 4.5 m
Designation
No. of Person/s
No. of Hour/s
1 4 8
1.00 1.00 1.00
2 6
0.56 0.56
Quantity
No. of Day/s
40
14.00
62 80 80 62 16 32 216 278 558
14.00 14.00 14.00 14.00 14.00 14.00 14.00 14.00 14.00
Unit
Quantity
Hourly Rate
Amount (PhP)
A. Labor Installation a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer Stripping a. Skilled Laborer b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Daily Rental Rate
Amount (PhP)
B. Equipment Area = 205.01 m2 34.50 a. H-Frame 1.7 m x 1.2m, set 2 pcs H-frames 4 pcs diagonal cross braces 4 pcs horizontal braces 8 pcs joint pins b. Shoring Jack , 3.8 m full extension c. Adjustable U-head Jack, 0.6m d. Adjustable Base Jack, 0.6m e. 1-1/2" GI Pipe x 6.0 m f. 1-1/2" GI Pipe x 3.0 m g. 1-1/2" GI Pipe x 4.0 m h. 1-1/2" GI Pipe x 1.0 m i. Tie Rod x 0.60m. j. Round Wing Nut
Rental cost for scaffoldings may vary per Region/District.
Sub - Total for B C. Sub - Total for C (B ÷ Area) D. Output per Hour = E. Direct Unit Cost (A ÷ D) + C Name and Specification F. Materials a. Phenolic Board (0.019 x 1.2 x 2.4) - 3 uses c. Good Lumber - 3 uses b. Consumables (5% of material cost)
pcs bd ft
0.347 4.727
Unit Cost
Amount (PhP)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
Sub - Total for F G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/ 8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. This cost sheet analysis is only applicable for Formworks and Falseworks considering steel scafoldings 2. Area of consideration includes beams, columns, and suspended slabs.
40
Part B - Plain and Reinforced Concrete Works
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1000(1)
Soil Poisoning L 5.4 L
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
L
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 5.4 L E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Soil Poisoning
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitring Committee.
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
41
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1001(1)a
50 mm Ø -100 mm Ø PVC Pipe and Fittings, Series 600/ Series 1000 m 3.00 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 3.00 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 50 mm - 100 mm Ø PVC Pipe and Fittings, Series 600/Series 1000 b. Consumables (5% of material cost)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note: 1. Use this cost sheet for Item Nos. 1001(1)a1, 1001(1)a2,1001(1)a3, 1001(1)a5, 1001(1)a5, and 1001(1)a7.
42
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1001(1)a
150 mm - 300 mm Ø PVC Pipe and Fittings, Series 600/ Series 1000 m 4.00 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 4.00 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 150 mm Ø PVC Pipe and Fittings, Series 600/ Series 1000 m b. Consumables (5% of material cost)
1.00
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note: 1. Use this cost sheet for Item Nos. 1001(1)a4, 1001(1)a8, 1001(1)a9, 1001(1)a10 and 1001(1)a11.
43
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1001(1)b1
150 mm Ø Concrete Pipe m 1.00 m
Designation
No. of Person/s
No. of Hour/s
1 2 4
0.98 0.98 0.98
No of Unit/s
No. of Hour/s
1
0.09
Unit
Quantity
m3 bags m m3
0.19 0.01 1.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Plate Compactor (5 hp) Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1.00 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Portland Cement b. Sand c. Concrete Pipe (150 mm Ø) d. Sand Bedding/Selected sandy soil
0.05
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%8% of G
I. Contractor's Profit (CP)
5% of (G + H + I) (G + H + I + J)
J. Value Added Tax (VAT) K. Total Unit Cost
44
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1001(1)b2
200 mm Ø Concrete Pipe m 1.00 m
Designation
No. of Person/s
No. of Hour/s
1 2 4
1.07 1.07 1.07
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Plate Compactor (5 hp) Minor Tools (10% of labor cost)
0.11
Sub - Total for B C. Total (A + B) D. Output = 1.00 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
Quantity
m3 bags m m3
0.25 0.01 1.00
F. Materials a. Portland Cement b. Sand c. Concrete Pipe (200 mm Ø) d Sand Bedding/Selected sandy soil
G. H. I. J. K.
0.05
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
45
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1001(1)b3
250 mm Ø Concrete Pipe m 1.00 m
Designation
No. of Person/s
No. of Hour/s
1 2 4
1.17 1.17 1.17
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Plate Compactor (5 hp) Minor Tools (10% of labor cost)
0.12
Sub - Total for B C. Total (A + B) D. Output = 1.00 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
Quantity
m3 bags m m3
0.32 0.02 1.00
F. Materials a. Portland Cement b. Sand c. Concrete Pipe (250 mm Ø) d Sand Bedding/Selected sandy soil
G. H. I. J. K.
0.06
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
46
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1001(1)b4
300 mm Ø Concrete Pipe pc 1 pc
Designation
No. of Person/s
No. of Hour/s
1 2 4
1.26 1.26 1.26
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Plate Compactor (5 hp) Minor Tools (10% of labor cost)
0.13
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
Quantity
m3 bags m m3
0.38 0.02 1.00
F. Materials a. Portland Cement b. Sand c. Concrete Pipe (300 mm Ø) d Sand Bedding/Selected sandy soil
G. H. I. J. K.
0.06
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
47
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1001(1)b5
350 mm Ø Concrete Pipe m 1.00 m
Designation
No. of Person/s
No. of Hour/s
1 2 4
1.35 1.35 1.35
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Plate Compactor (5 hp) Minor Tools (10% of labor cost)
0.14
Sub - Total for B C. Total (A + B) D. Output = 1.00 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
Quantity
m3 bags m m3
0.44 0.03 1.00
F. Materials a. Portland Cement b. Sand c. Concrete Pipe (350 mm Ø) d Sand Bedding/Selected sandy soil
0.07
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
15%/ 12%/ 10%/ 8% of G 10%8% of G
I. Contractor's Profit (CP)
5% of (G + H + I) (G + H + I + J)
J. Value Added Tax (VAT) K. Total Unit Cost
48
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1001(1)c
50 mm Ø - 100 mm Ø High Density Polyethylene (HDPE) Pipe m 3.00 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 3.00 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 50 mm Ø High Density Polyethylene (HDPE) Pipe b. Consumables (5% of material cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note: 1. Use this cost sheet for Item Nos. 1001(1)c1, 1001(1)c2, and 1001(1)c3.
49
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
of G of G of (G + H + I) (G + H + I + J)
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1001(1)c
150 mm Ø - 300mm ØHigh Density Polyethylene (HDPE) Pipe m 4.00 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
a. 150 mm Ø High Density Polyethylene (HDPE) Pipe b. Consumables (5% of material cost)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 4.00 m E. Direct Unit Cost (C ÷ D)
F. Materials
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note: 1. Use this cost sheet for Item Nos. 1001(1)c4, 1001(1)c5,1001(1)c6 and 1001(1)c7.
50
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
of G of G of (G + H + I) (G + H + I + J)
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output per hour
: :
1001(2)
PVC/HDPE Fittings ea 1 ea
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
labor cost for these items are considered in the installation of pipes.
Sub - Total for A Name and Capacity
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
a. PVC/HDPE Fittings ( Elbow/ Clean Out/ Coupling/ Wye/ Tee/ Reducer/ P-trap/ Bushing/ Plug)
ea
1.00
B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = 1 ea E. Direct Unit Cost (C ÷ D)
F. Materials Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
G. Direct Unit Cost (E + F) 15%/ 12%/ 10%/ 8% of G H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 10%8% of G I. Contractor's Profit (CP) 5% of (G + H + I) J. Value Added Tax (VAT) (G + H + I + J) K. Total Unit Cost Note : 1. All items under Item No 1001(2) are considered as fittings. Use this cost sheet for Item Nos. 1001(2)a to 1001(2)w.
51
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1001(2)
Concrete Gutter m
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Item 900 - Reinforced Concrete b. Item 902 - Reinforcing Steel a. Item 903 - Formworks and Falseworks
m3 kg m2
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note: 1. This item shall be based on the standard Detailed Unit Price Analysis (DUPA) of each component items such as Item Nos. 900,902, and 903.
52
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1001(5)
Catch Basin (Concrete/CHB) ea 1.00 ea
Designation
Quantity
Unit Cost
Amount (PhP)
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
Unit
A. Labor a. Item 803 - Structure Excavation
m3
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Item 900 - Reinforced Concrete b. Item 902 - Reinforcing Steel c. Item 1046 - CHB Wall
m3 kg m2
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note: 1. These items are variable in dimensions based on actual condition which combines component items, hence standard estimate should be based on the standard Detailed Unit Price Analysis (DUPA) of each component items such as Items 803, 900, 902
53
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1001(7)
Junction Box (Concrete/CHB) ea 1.00 ea
Designation
Quantity
Unit Cost
Amount (PhP)
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
Unit
A. Labor a. Item 803 - Structure Excavation
m3
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Item 900 - Reinforced Concrete b. Item 902 - Reinforcing Steel c. Item 1046 - CHB Wall
m3 kg m2
G. Direct Unit Cost (E + F) 15%/ 12%/ 10%/ 8% of G H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) 10%8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note: 1. These items are variable in dimensions based on actual condition which combines component items, hence standard estimate should be based on the standard Detailed Unit Price Analysis (DUPA) of each component items such as Items 803,900,902 and 1046.
54
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1001(8)
Sewer Line Works l.s. 1.00 l.s.
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor Amount shall be derived from individual DUPA for Item Nos. 1001(1)a, 1001(1)c, and 1001(2).
Sub - Total for A Name and Capacity
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1.00 l.s. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials Enumerate materials and quantities involved for Item Nos. 1001(1)a, 1001(1)c, and 1001(2).
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note: 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item Nos. 1001(1)a, 1001(1)c, and 1001(2)
55
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1001(9)
Storm Drainage and Downspout l.s. 1.00 l.s.
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor Amount shall be derived from individual DUPA for Item Nos. 1001(1)c, 1001(3), 1001(4), 1001(5), 1001(6) and 1001(7).
Sub - Total for A Name and Capacity
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1.00 l.s. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials Enumerate materials and quantities involved for Item Nos. 1001(1)c, 1001(3), 1001(4), 1001(5), 1001(6) and 1001(7).
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item Nos. 1001(1)c, 1001(3), 1001(4), 1001(5), 1001(6) and 1001(7).
56
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1002(1)
13 mm Ø - 50 mm Ø Galvanized Iron Pipe and Fittings pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
2.00 2.00 2.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a.13 mm Ø - 50 mm Ø Galvanized Iron Pipe and Fittings
pc
1.00
b. Consumables (5% of material cost)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note: 1. Use this cost sheet for Item Nos. 1002(1)a, 1002(1)b, 1002(1)c, 1002(1)d, and 1002(1)e.
57
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1002(1)
65 mm Ø - 150 mm Ø Galvanized Iron Pipe and Fittngs pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.50 1.50 1.50
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 65 mm Ø - 150 mm Øx 6 m Galvanized Iron Pipe and Fittings b. Consumables (5% of material cost)
pc
1.00
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1002(1)f, 1002(1)g, 1002(1)h, and 1002(1)i.
58
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
of G of G of (G + H + I) (G + H + I + J)
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1002(2)
Galvanized Iron Fittings pc 1 pc No. of Hour/s
Hourly Rate
Amount (PhP)
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
a. Galvanized Iron Fittings (Elbow/ Tee/ Reducer-Tee/ Socket/ Coupling/ Reducer Coupling)
pc
1.00
Designation
No. of Person/s
A. Labor labor cost for these items are considered in the installation of pipes.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = 1 pc E. Direct Unit Cost (C ÷ D)
F. Materials
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1002(2)b to 1001(2)f.
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
59
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1002(2)a
13mmØ - 50mm ØPolyprophylene Random Copolymer (PPR-C) Pipe and Fittings, PN 16/ PN 20 pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.33 1.33 1.33
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 13 mm Ø - 50 mm Ø x 4.00 mPolyprophylene Random Copolymer (PPR-C) Pipe and Fittings, PN 16/ PN 20 b. Consumables (5% of material cost)
pc
1.00
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1002(2)a2 to 1002(2)e3
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
60
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1002(2)
63mmØ - 100mm Ø Polyprophylene Random Copolymer (PPR-C) Pipe and Fittings PN 16/ PN 20 pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 63 mm Ø - 100 mm Ø x 4.00 m Polyprophylene Random Copolymer (PPR-C) Pipe and Fittings PN 16/ PN 20Copolymer (PPR-C) Pipe
pc
1.00
b. Consumables (5% of material cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1002(2)f1 to 1002(2)h3.
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
61
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1002(3)
Polyprophylene Random Copolymer (PPR-C) Fittings pc 1 pc
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
labor cost for these items are considered in the installation of pipes
Sub - Total for A Name and Capacity
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
a. Polyprophylene Random Copolymer (PPR-C) Fittings (Elbow/ Tee/ Female Threaded Tee/ Female Elbow/ Female Threaded Adaptor/ Male Threaded Adaptor/ End Cap)
pc
1.00
B. Equipment
Sub - Total for B C. Total (A + B) D. Output= 1 pc E. Direct Unit Cost (C ÷ D)
F. Materials
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1002(3)b to 1001(3)l.
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
62
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1002(3)
13 mm Ø - 50 mm Ø Polyvinyl Chloride (PVC) Pipe and Fittings, Blue pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per hour = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 13 mm Ø - 50 mm Ø x 3 m Polyvinyl Chloride (PVC) Pipe and Fittings, blue b. Consumables (5% of material cost)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. Use this cost sheet for Item Nos. 1002(3)a, 1002(3)b, 1002(3)c, 1002(3)d, and 1002(3)e.
63
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1002(3)
65 mm Ø - 100 mm Ø Polyvinyl Chloride (PVC) Pipe and Fittings, Blue pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
0.75 0.75 0.75
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
LaborRates Ratesare are variable Region/District Labor variable perper Region/District basedon onminimum Minimumwage wage approved based as as approved by by DOLE.Refer to the Schedule of Labor Rates. DOLE.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 65 mm Ø 100 mm Ø x 3 m Polyvinyl Chloride (PVC) Pipe and Fittings, blue b. Consumables (5% of material cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1002(3)f, 1002(3)g, and 1002(3)h.
64
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
of G of G of (G + H + I) (G + H + I + J)
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1002(4)
Polyvinyl Chloride (PVC) Fittings, Blue pc 1 pc
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Labor cost for these items are considered in the installation of pipes
Sub - Total for A Name and Capacity
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
a. Polyvinyl Chloride (PVC) Fittings, Blue (Elbow/ Tee/ Tee-Reducer/ Elbow Reducer/ Socket/ Coupling/ Reducer/ Male Threaded Adaptor/ Female Threaded Adaptor/ Cap)
pc
1.00
B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D)
F. Materials
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1002(4)b to 1001(4)l.
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
65
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1002(4)
Plumbing Fixtures l.s. 1.00 l.s.
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor Amount shall be derived from individual DUPA for Item Nos. 1002(5)a to 1002 (5)s.
Sub - Total for A Name and Capacity
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1.00 l.s. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials See derivation for Item Nos. 1002(5)a to 1002 (5)s.
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item Nos. 1002(5)a to 1002(5)s.
66
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1002(5)
Water Closet/ Urinal with Complete Accessories set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
2.00 2.00 2.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Water Closet / Urinal with complete accessories b. Consumables (5% of material cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note: 1. Use this cost sheet for Item Nos. 1002(5)a and 1002(10).
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
67
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1002(11)
Kitchen Sink/Scrub Up Sink/Slop Sink with Complete Accessories set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
2.00 2.00 2.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Kitchen Sink/Scrub Up Sink/Slop Sink with complete accessories b. Consumables (5% of material cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1002(11)a to 1002(13).
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
68
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1002(14)
Wall Hung/Countertop/Under Counter Lavatory with Complete Accessories set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
2.00 2.00 2.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Lavatory (Wall Hung/Countertop/Under Counter) b. Consumables (5% of material cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1002(14)a to 1002(15)b.
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
69
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1002(16)
Floor Drain Plates set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
0.40 0.40 0.40
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Floor Drain Plate b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
70
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1002(5)
Soap Holder ( Toilet Soap/ Liquid Soap) pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
0.75 0.75 0.75
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Soap Holder ( Toilet Soap/ Liquid Soap) b. Consumables (5% of material cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1002(5)i and 1002(5)j.
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
71
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1002(5)
Toilet Tissue Holder/Dispenser pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
0.75 0.75 0.75
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Toilet Tissue Holder/Dispenser b. Consumables (5% of material cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1002(5)k and 1002(5)l.
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
72
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1002(17)
Bidet/ Faucet/ Hose Bibb pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1
0.40 0.40
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Bidet/ Faucet/ Hose Bibb b. Consumables (5% of material cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1002(5)m, 1002(5)q, and 1002(5)r.
73
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
of G of G of (G + H + I) (G + H + I + J)
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1002(18)
Stainless Steel Grab bar m 0.45 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 0.45 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 40 mm Ø Stainless Steel Grab Bar b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
74
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1002(19)
Shower head/ Shower Valve set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Shower head/ Shower Valve b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
75
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1002(20)
Facial Mirror m2 0.4 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m2
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 0.4 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Facial Mirror b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee. Committee
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
76
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1002(24)
Cold Waterline Pipes and Fittings l.s. 1.00 l.s.
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor See derivation for Items 1002(1) to Items 1002(5)
Sub - Total for A Name and Capacity B. Equipment See derivation for Items 1002(1) to Items 1002(5)
Sub - Total for B C. Total (A + B) D. Output per Hour = E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials See derivation for Items 1002(1) to Items 1002(5)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item No. 1002(1)a to Item No. 1001(5)
77
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1002(25)
Hot Waterline Pipes and Fittings l.s. 1.00 l.s.
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor See derivation for Item Nos. 1002(3)a to 1002(3)l.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials See derivation for Item Nos. 1002(3)a to 1002(3)l.
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item No.1002(3)a to 1002(3)l.
78
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output per hour
: :
1003(1)
4.5mm Fiber Cement Board/ 4.5 mm Marine Plywood/ 6 mm Marine Plywood/ 6mm Ordinary Plywood on Metal Frame Ceiling m2 1.243 m2
Designation
No. of Hour/s
1 1 3
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
0.365
pc
1.131
c. Carrying Channels (size variable depends on plans and specifications)
pc
0.357
d. Hanger Bars/Rod (size variable depends on plans and specifications)
pc
1
e. Channel clip f. Wall Angle g. Rivets h. 1" Metal Screw
pc pc pc pcs
6 0.238 14 4
A. Labor for Installation : a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Hourly Rate
Amount (PhP)
No. of Person/s
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 1.243 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. 4.5mm Fiber Cement Board/ 4.5 mm Marine Plywood/ 6 mm Marine Plywood/ 6mm Ordinary Plywood b.Metal Furring (size variable on plan and and specifications ) 3m length
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
Note: Quantities were derived from plans and specificartions of standard school building with carrying channels spaced by 1.20 m and metal furring spaced by 0.40 m on center.
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note: 1. Use this cost sheet for Item Nos. 1003(1)a1, 1003(1)b1, 1003(1)c1, and 1003(1)d1.
79
of G of G of (G + H + I) (G + H + I + J)
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output per hour
: :
1003(1)a
4.5mm Fiber Cement Board/ 4.5 mm Marine Plywood/ 6 mm Marine Plywood/ 6mm Ordinary Plywood in Wood Framing Ceiling m2 1.489 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 3
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
0.365
bd.ft kg
9.257 0.139
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 1.489 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. 4.5mm Fiber Cement Board/ 4.5 mm Marine Plywood/ 6 mm Marine Plywood/ 6mm Ordinary Plywood b. Good Lumber c. Assorted Nails Note : Quantities are derived from a ceiling system with ceiling nailers spaced at 0.40 m on center
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note: 1. Use this cost sheet for Item Nos. 1003(1)a2, 1003(1)b2, 1003(1)c2, and 1003(1)d2.
80
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
of G of G of (G + H + I) (G + H + I + J)
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1003(1)e
Gypsum Board on Metal Frame Ceiling m2 1.340 m2
Designation
No. of Hour/s
1 1 3
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc pc
0.365 1.13
pc
0.36
pc
1.00
pcs pc pcs pcs
6 0.238 14 4
A. Labor for Installation a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Hourly Rate
Amount (PhP)
No. of Person/s
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 1.340 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Gypsum Board b.Metal Furring (size variable on plan and c. Carrying Channels (size variable depends on plans and specifications) d. Hanger Bars/Rod ((size variable depends on plans and specifications) e. Channel clip f. Wall Angle g. Rivets h. 1" metal screw
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee
Note: Quantities were derived from plans and specificartions of standard school building with carrying channels spaced by 1.20 m and metal furring spaced by 0.40 m on center.
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
81
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output per hour
: :
1003(2)
4.5mm/ 6.0 mm Fiber Cement Board/ 4.5mm/ 6.0 mm 4' X 8' thk fiber cement board/ 4.5mm Marine Plywood/ 6.0 mm Marine Plywood/ 6.0 mm Ordinary Plywood on Metal Frame Double Wall Partition m2 0.776 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 3
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pcs
0.730
b. Metal Studs (size variable depends on plan and specs.) 3 m length
pcs
1.181
c. Rivets d. 1" Metal Screw
pcs pcs
117.00 4.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 0.776 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. 4.5mm/ 6.0 mm 4' X 8' thk fiber cement board/ 4.5mm Marine Plywood/ 6.0 mm Marine Plywood/ 6.0 mm Ordinary Plywood
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note: 1. Use this cost sheet for Item Nos. 1003(2)a1, 1003(2)b1, 1003(2)c1, 1003(2)d1 and 1003(2)e1.
82
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1004(2)
Finishing Hardware set 1 set
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor Labor cost for these items are considered in the installation of Doors, Windows, and other Fabricated Materials
Sub - Total for A Name and Capacity
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
B. Equipment
Sub - Total for B C. Total (A + B) D. Output = E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
a. Finishing Hardwares (Lockset/Latches, Bolts, Door Closer, Knobs/Handles/ Hinges/ Ladder/ Grab Bar)
set
1.00
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note: 1. Use this cost sheet for Item Nos. 1004(2)a to 1004(2)i.
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
83
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output per hour
: :
1005
Residential Casement Steel Windows/ Heavy Duty Side-hinged Ventilator/ Projected Ventilator/ Awning Ventilator/ Grille Window m2 0.18 m2
Designation
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
1
0.25
Name and Specification
Unit
Quantity
a. Residential Casement Steel Windows/ Heavy Duty Side-hinged Ventilator/ Projected Ventilator/ Awning Ventilator/ Grille Window b. Consumables (5% of material cost)
m2
1.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Welding Machine Minor Tools (10% of labor cost)
Note: It is assumed that steel windows are already fabricated. Thus, labor and equipment output are based on installation time only.
Sub - Total for B Total (A + B) 0.18 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
F. Materials
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note: 1. Use this cost sheet for Item Nos. 1005(1), 1005(2), 1005(3), 1005(4), and 1005(7).
84
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
of G of G of (G + H + I) (G + H + I + J)
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1006
Hollow Steel Door/ Steel Flush Door/ Grille Door/ Steel Louver Door m2 0.26 m2
Designation
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
1
0.25
Unit
Quantity
m2
1.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Labor Rates Rates are are variable variable per per Region/District Region/District based based on on minimum Minimum wage wage as as approved approved by by DOLE. Refer to the Schedule of Labor Rates. DOLE.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Welding Machine Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 0.26 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Hollow Steel Door/ Steel Flush Door/ Grille Door/ Steel Louver Door b. Consumables (3% of material cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1006(1), 1006(2), 1006(3) and 1006(4).
85
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee
of G of G of (G + H + I) (G + H + I + J)
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1006(5)
Fire Rated Fire Exit Steel Door m2 0.26 m2
Designation
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
1
0.25
Unit
Quantity
m2
1.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Welding Machine Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 0.26 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Fire rated Fire Exit Steel Door b. Consumables (3% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
86
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1007
Aluminum Glass Door (Sliding Type/Swing Type) m2 0.26 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m2
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 0.26 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Aluminum Glass Door (Sliding Type/Swing Type) b. Consumables (3% of material cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1007(1)a and 1007(1)b.
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
87
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1008
Aluminum Glass Window (Sliding/ Casement/ Awning/ Fixed Type) m2 0.36 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m2
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 0.36 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Aluminum Glass Window (Sliding/ Casement/ Awning/ Fixed Type) b. Consumables (3% of material cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1008(1)a, 1008(1)b, 1008(1)c and 1008(1)d.
88
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
of G of G of (G + H + I) (G + H + I + J)
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1010(1)
Frames (Jambs, Sill, Head, Transoms and Mullions) set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
2.00 2.00 2.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Jambs, Sill, Head, Transoms and Mullion b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
89
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1010(2)a
Hollow Core Flush Door m2 0.32 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m2
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 0.32 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a.Hollow Core Flush Door
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost 0
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
90
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1010(2)b
Wooden Panel Door m2 0.36 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m2
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 0.32 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Wooden Panel Door
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
91
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1011(1)
Steel/ Aluminum Roll Up Door set 1.00 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 14.71 14.71
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
Set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1.00 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Steel/ Aluminum Roll Up Door b. Consumables (3% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitring Committee Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
92
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1012(1)
Tempered Glass Door (10 mm/ 12mm) m2 0.26 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m2
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 0.26 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Tempered Glass Door (10 mm/ 12mm) b. Consumables (3% of material cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1012(1)d1 and 1012(1)d2.
93
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1012(1)
Tempered Glass Windows (8 mm/ 10mm) m2 0.36 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m2
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 0.36 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Tempered Glass Windows (8 mm/ 10mm) b. Consumables (3% of material cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1012(1)e1 and 1012(1)e2.
94
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1013(1)
Corrugated Metal Roofing 2 m 2 2.076 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 3
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
a. Corrugated Roofing Sheet b. teckscrew/J-bolt with washers c. Consumables ( 3% of material cost)
m2 pcs
1.05 10
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 2.076 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
F. Materials
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
95
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1013(2)
Fabricated Metal Roofing Accessory (Ridge/Hip Rolls/Flashings/Counter Flashing/Valley Roll) m 10.00 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.05
pcs
19.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 10.6 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Ridge/Hip Rolls/Flashings/Valley Roll/ Counter Flashing (Gauge 26) b. Blind Rivets c. Consumables (3% of material cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%/8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this costing sheet for Item Nos. 1013(2)a, 1013(2)b, 1013(2)e, and 1013(2)f.
96
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
of G of G of (G + H + I) (G + H + I + J)
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1013(2)c
Fabricated Metal Roofing Accessory (Gutter) m 11.80 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m pcs pcs
1.00 3.00 16.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 11.80 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Gutter(Gauge 26) b. 12" x 1" Plain GI Strap c. Blind Rivets d. Consumables (3% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
97
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1014
Prepainted Metal Sheets (Corrugated, Short Span/ Long Span, below 0.427 thk/ above 0.427 thk) 2 m 2 2.076 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 2.076 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Prepainted Metal Sheets (Corrugated, Short Span/ Long Span, below 0.427 thk/ above 0.427 thk) b. teckscrew/J-bolt with washers c. Consumables ( 3% of material cost)
m
2
1.05
pcs
10
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1014(1)a and 1014(2)a.
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
98
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1014
Prepainted Metal Sheets (Rib Type, Short Span/ Long Span, below 0.427 thk/ above 0.427 thk) 2 m 2.769 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 2.769 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Prepainted Metal Sheets (Rib Type, Short Span/ Long Span, below 0.427 thk/ above 0.427 thk) b. teckscrew/J-bolt with washers c. Consumables (3% of material cost)
m
2
1.00
pcs
10.00
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1014(1)b and 1014(2)b.
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
99
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1016(1)a
Waterproofing Cement Base 2 m 1.875 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m2
1.05
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Sub - Total for A Name and Capacity
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
B. Equipment
Minor Tools (10% of labor cost)
C.
Sub - Total for B Total (A + B)
1.875 m D. Output per Hour = E. Direct Unit Cost (C ÷ D)
2
Name and Specification F. Materials a. Cement-based waterproofing
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitring Committee Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
100
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1016(1)b
Liquid Waterproofing m2 2 5.772 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
gal gal
0.04 0.03
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 5.772 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Primer Coat b. Liquid Waterproofing c. Consumables (3% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitring Committee Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
101
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1016(2)
Built-up and Preformed Membrane 2 m 4.805 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
gal 2 m
0.10
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District Labor on Rates are variable perapproved Region/District based minimum wage as by based on Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates. DOLE.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 4.805 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Asphalt Primer b. Preformed Membrane c. Consumables (5% of material cost)
G. H. I. J. K.
1.05
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitring Committee
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
102
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1017
50mm ø - 100mm ø Roof Drain/Canopy Drain/ Gutter Drain with Strainer set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1
0.50 0.50
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Skilled Laborer b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 50mm ø - 100mm ø Roof Drain/Canop Drain/ Gutter Drain with Strainer
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. Use this cost sheet for Item Nos. 1017(1)a1, 1017(1)a2, 1017(1)a3, 1017(1)a4, 1017(2)b1, 1017(2)b2, 1017(2)b3, 1017(2)b4, 1017(3)c1, 1017(3)c2 and 1017(3)c3
103
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1018(1)
Glazed Tiles and Trims m2 2 1.365 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 5 5
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m2 bags m3 bags bags
1.050 0.325
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 2 1.365 m D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Glazed Tiles b. Cement c. Sand d. Tile Grout e. Tile Adhesive (25 kg) f. Consumables (3% of Material Cost)
G. H. I. J. K.
0.026 0.125 0.143
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
104
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1018
Unglazed Tiles/ Granite Tiles/ Synthetic Granite Tiles 2 m 1.95 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 5 5
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m2 bags m3 bags
1.050 0.325
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 1.95 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Unglazed Tiles/ Granite Tiles/ Synthetic Granite Tiles b. Cement c. Sand d. Tile Grout
0.026 0.125
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%/8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this costing sheet for Item Nos. 1018(2), 1018(3) and 1018(4).
105
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
of G of G of (G + H + I) (G + H + I + J)
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1019(1)
Wood Tiles (Narra, Tanguile, others) 2 m 1.56 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 5 5
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m2 L bags m3 L L L
1.050 0.500 0.325
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 1.56 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Wood Tiles b. Glue Adhesive c. Cement d. Sand e. Polyurethane Floor Varnish Sealer f. Polyurethane Floor Varnish Topcoat g. Polyurethane Reducer h. Consumables (5% of material cost)
G. H. I. J. K.
0.026 0.400 0.200 0.06
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
106
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1019(1)d
Laminated Wood Tiles m2 1.95 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 5 5
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m2 L bags m3
1.050 0.500 0.325
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 1.95 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Laminated Wood Tiles b. Glue Adhesive c. Cement d. Sand
0.026
e. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
107
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1020(1)
Vinyl Tiles 2 m 2 4.285 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 2 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 4.385 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Vinyl Tiles b. Glue Adhesive c. Cement d. Sand
2
m L bags m3
1.050 0.500 0.726 0.055
e. Consumables (3% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
108
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1021(1)a
Plain Cement Floor Fnish 2 m 5.95 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 3
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
bags m3
0.726
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 5.95 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Cement b. Sand
G. H. I. J. K.
0.055
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
109
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1021(3)
Floor Topping 2 m 6.545 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 3
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
bags m3
0.693
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 6.545 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Cement b. Sand
0.055
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1021(3)a and 1021(3)b.
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
110
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1023(1)
Granolithic Marble Work 2 m 5.95 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 3
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 5.95 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Marble chips b. Portland cement c. Divider strips
G. H. I. J. K.
3
m bags m
0.726 0.055 1.00
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitring Committee
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
111
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1024(1)
Pea Gravel Finish m2 2 1.785 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
bags m3
0.795
m3
0.039
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 5.95 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Cement b. Pea Gravel c. Sand
G. H. I. J. K.
0.013
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitring Committee Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
112
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1026(1)
Pebble Washout Finish 2 m 2 1.785 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
bags m3
0.795
m3
0.039
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on Minimum Region/District based wage on minimum as approved wage byas DOLE. by DOLE. Refer to the Schedule approved of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 5.95 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Cement b. Pea Gravel c. Sand
G. H. I. J. K.
0.013
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
113
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description Unit of Measurement Output per hour
: : :
1027(1)
Cement Plaster Finish 2 m 7.125 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 2 4
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
bags cu.m.
0.330 0.027
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Note : In cases of outside wall plastering utilization of gondolla as support equipment is recommended.
Sub - Total for B Total (A + B) 7.125 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Cement b. Sand
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : For Exterior Plastering support equipment shall be utilized.
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
114
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1032(1)a
Painting Works (Masonry Painting) m2 2 2.10 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 2 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
gal gal gal gal
0.02 0.04 0.05 0.08
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 2.10 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Concrete Neutralizer b. Concrete Sealer/Primer c. Patching Compound d. Semi Gloss Latex (one coat only) e. Consumables (5% of material cost)
G. H. I. J.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
K. Total Unit Cost
115
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1032(1)b
Painting Works (Wood Painting) m2 2 1.89 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 2 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
gal gal gal gal pint
0.05 0.04 0.04 0.01 0.01
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 2 1.89 m D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Glazzing Putty b. Flat Wall Enamel c. Enamel Quick Dry d. Paint Thinner e. Tinting Color (Optional) f. Consumables (5% of material cost)
G. H. I. J.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
K. Total Unit Cost
116
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1032(1)c
Painting Works (Metal Painting) m2 2 2.00 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 2 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
a. Red Oxide Primer b. Enamel Paint c. Paint thinner d. Consumables (5% of material cost)
gal gal lit
0.04 0.10 0.25
e. Tinting Color (Optional)
pint
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 2.00 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
F. Materials
G. H. I. J. K.
0.010
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
117
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1032(2)
Varnishing Works 2 m 2 3.945 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 2 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
a.Varnish b. Consumables (5% of material cost)
gal
0.04
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 3.945 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
F. Materials
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
118
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1032(4)
Ducco Finish 2 m 2 1.512 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 2 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
gal gal gal gal pint
0.05 0.04 0.04 0.01 0.01
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 1.512 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Glazzing Putty b. Flat Wall Enamel c. Enamel Quick Dry d. Paint Thinner e. Tinting Color (Optional) f. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
119
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1034(1)
Damproofing ( Polyethylene Sheets) 2 m 2 37.559 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 37.559 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. 6 mils Polyethylene Sheets
m
2
1.000
b. Consumables (3% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
120
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1038(1)
Reflective Insulation 2 m 5.56 m2
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 3
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m2
1.000
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 5.56 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Reflective Insulation b. Consumbles (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
121
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1042(1)
Stainless Steel Door and Frames 2 m 2 0.32 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m2
1.000
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 0.32 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. Stainless Steel Doors and Frames b. Consumables (3% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
122
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1043(1)
PVC Doors and Frames m2 2 0.315 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m2
1.000
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 0.315 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. PVC Doors and Frames b. Consumables (5% of material cost)
G. H. I. J.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
K. Total Unit Cost
123
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1045(1)
Perforated Aluminum Ceiling Panels 2 m 2 0.763 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 3
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
a. Perforated Aluminum Ceiling Pannel with frames b. Consumables (3% of material cost)
m2
1.000
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 0.763 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
F. Materials
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
124
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1046
100 mm CHB Non Load Bearing/Load Bearing (including Reinforcing Steel) 2 m 2 3.825 m
Designation
No. of Person/s
No. of Hour/s
1 2 4
1.00 1.00 1.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
136.93 100.61 77.86
Sub - Total for A Name and Capacity
136.93 201.22 311.44
649.59 No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
3
1.00
172.00
516.00
B. Equipment a. One-bagger mixer Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 3.825 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D)
516.00 1,165.59
C.
Name and Specification
101.58 Unit
Quantity
pcs bags cu.m. kgs kgs
13.00 0.525 0.04 3.24* 0.05
Unit Cost
Amount (PhP)
F. Materials a. 100 mm thk CHB (Non-Load Bearing/Load b. Cement c. Sand d. Reinforcing Steel e. #16 Tie wire *Quantity derived from 10mm Ø. bars spaced by 0.4 m vertically and every 3 layers of CHB
G. H. I. J.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT)
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J) K. Total Unit Cost Note : 1. This cost sheet shall be used for Item Nos. 1046(1)a and 1046(2)a.
125
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1046
150mm CHB Non-LoadBearing/ Load Bearing (including Reinforcing Steel) 2 m 2 3.180 m
Designation
No. of Person/s
No. of Hour/s
1 2 4
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
3
1.00
Unit
Quantity
pcs bags cu.m. kgs kgs
13.00 1.500 0.04 3.24* 0.05
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. One-bagger mixer Minor Tools (10% of labor cost)
Sub - Total for B Total (A + B) 3.180 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification F. Materials a. 150 mm thk CHB (Load Bearing) b. Cement c. Sand d. Reinforcing Steel e. #16 Tie wire
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
*Quantity derived from 10mm Ø. bars spaced by 0.4 m vertically and every 3 layers of CHB
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%/8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. This cost sheet shall be used for Item Nos. 1046(1)b and 1046(2)b.
126
of G of G of (G + H + I) (G + H + I + J)
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1047(1)
Structural Steel Roof Framing l.s. l.s.
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor See derivations for Item Nos. 1047(2) - 1047(6)
Sub - Total for A Name and Capacity B. Equipment
See derivations for Item Nos. 1047(2) - 1047(6)
Sub - Total for B C. Total (A + B) D. Output per Hour = E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials See derivations for Item Nos. 1047(2) - 1047(6)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
127
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1047(2)a
Structural Steel Roof Framing kg 85.00 kg
Designation
No. of Person/s
No. of Hour/s
Fabrication a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
1 3 3
1.00 1.00 1.00
Erection a. Skilled Laborer b. Unskilled Laborer
4 4
0.49 0.49
No. of Unit/s
No. of Hour/s
1 1
0.75 0.25
Unit
Quantity
kg kg kg kg
1.00 0.011 0.022 0.020
Hourly Rate
Amount (PhP)
A. Labor
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Welding Machine b. Cutting Outfit Minor Tools (10 % of labor cost)
Lifting Equipment considered under support equipment Sub - Total for B C. Total (A + B) D. Output per Hour = 85.00 kg E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Structural Steel Framing including cross b. Acetylene c. Oxygen d. Welding Rod e. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
128
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1047(2)b
Structural Steel Roof Truss kg 85.00 kg
Designation
No. of Person/s
No. of Hour/s
Fabrication a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
1 3 3
1.00 1.00 1.00
Erection a. Skilled Laborer b. Unskilled Laborer
4 4
0.49 0.49
No. of Unit/s
No. of Hour/s
1 1 1
0.75 0.25 0.49
Unit
Quantity
kg kg kg kg
1.00 0.011 0.022 0.020
Hourly Rate
Amount (PhP)
A. Labor
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Welding Machine b. Cutting Outfit Lifting Equipment considered under support equipment Minor Tools (10 % of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 85.00 kg E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Structural Steel Truss b. Acetylene c. Oxygen d. Welding Rod e. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
129
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1047(2)c
Structural Steel Purlins kg 90.45 kg
Designation
No. of Person/s
No. of Hour/s
1 3 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
3
1.00
Unit
Quantity
kg kg
1.05 0.020
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Welding Machine Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 90.45 kg E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Structural Steel Purlins b. Welding Rod c. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
130
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1047(3)a
Metal Structure Accessories (Anchor Bolts) pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
0.10 0.10 0.10
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 90.45 kg E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Anchor Bolt
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
131
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1047(3)b
Metal Structure Accessories (Sagrods) pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
0.10 0.10 0.10
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Sagrod with nuts and bolts
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
132
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1047(3)c
Metal Structure Accessories (Turnbuckle) pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
0.15 0.15 0.15
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Standard Turnbuckle
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
133
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1047(3)d
Metal Structure Accessories (Crossbracing) pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
0.25 0.25 0.25
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cross Bracing b. Consumables (3% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
134
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1047(4)
Metal Structure Accessories (Crossbracing) kg 12.995 kg
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
kg
1.05
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 12.995 kg E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cross Bracing b. Consumables (3% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
135
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1047(5)
Metal Structure Accessories (Steel Plates) kg 12.995 kg
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
kg
1.05
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 12.995 kg E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Steel Plates b. Consumables (3% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
136
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1048(1)a
Carbon Fiber (1 layer) 2 m 2 1.20 m
Designation
No. of Person/s
No. of Hour/s
1
1.00
2 4
0.71 0.71
2 2
1.00 1.00
No. of Unit/s
No. of Hour/s
2 1 1 1 1 1 1 1
0.40 0.20 0.40 0.40 0.20 0.10 0.20 0.10
1 1
0.10 0.10
Unit
Quantity
gal gal sack pc pc
0.27 0.13 0.18 0.30 0.10
m2
1.05
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman Site Preparation b. Skilled Laborer c. Unskilled Laborer Application a. Skilled Laborer b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Surface Preparation a. Portable Grinder b. Jack Hammer c. Air Compressor c. Speed Ventilator d. Electric Drill e. Chipping Gun f. Paddle Mixer g. Generator Set (20KVA) Application a.Saturator Machine b. Generator Set (20 KVA)
Hourly Rate
Amount (PhP)
See latest ACEL rental rates.
Sub - Total for B Total (A + B) 1.20 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification
Unit Cost
Amount (PhP)
F. Materials Surface Preparation a. Clear Epoxy A b. Clear Epoxy B c. Kalcomine d. Cup Wheel e. Diamond Disk Application a. Carbon Fiber
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
137
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1048(2)
Glass Fiber 2 m 2 1.20 m
Designation
No. of Person/s
No. of Hour/s
1
1.00
2 4
0.71 0.71
2 2
1.00 1.00
No. of Unit/s
No. of Hour/s
2 1 1 1 1 1 1 1
0.40 0.20 0.40 0.40 0.20 0.10 0.20 0.10
1 1
0.10 0.10
Unit
Quantity
gal gal sack pc pc
0.27 0.13 0.18 0.30 0.10
m2
1.05
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman Site Preparation b. Skilled Laborer c. Unskilled Laborer Application a. Skilled Laborer b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Surface Preparation a. Portable Grinder b. Jack Hammer c. Air Compressor c. Speed Ventilator d. Electric Drill e. Chipping Gun f. Paddle Mixer g. Generator Set (20KVA) Application a.Saturator Machine b. Generator Set (20 KVA)
Hourly Rate
Amount (PhP)
See latest ACEL rental rates.
Sub - Total for B Total (A + B) 1.20 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Name and Specification
Unit Cost
Amount (PhP)
F. Materials Surface Preparation a. Clear Epoxy A b. Clear Epoxy B c. Kalcomine d. Cup Wheel e. Diamond Disk Application a. Glass Fiber
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
138
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1049(1)
Jet Grouting (0.80 m diameter) m 1.18 m
Designation
No. of Person/s
No. of Hour/s
1 6 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 1 1
1.00 1.00 1.00 1.00 1.00 1.00
Name and Specification
Unit
Quantity
a. Portland Cement b. Additives c. Consumables (5% of Material Cost)
bags L
14.00 3.50
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
B. Equipment a. Jetting Machine b. Air Compressor 12 Bars/600 CFM c. Water Tank/Pump d. Agitator e. Generator/Power Supply f. High Pressure Pump
See latest ACEL rental rates.
Sub - Total for B Total (A + B) 1.20 m2 D. Output per Hour = E. Direct Unit Cost (C ÷ D) C.
Unit Cost
Amount (PhP)
F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
139
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(4)a.1 Precast Concrete Piles, furnished (400mm x 400mm -type A) : m. : 2.50 m. Designation
No. of Person/s
No. of Hour/s
1 4 8
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 1
0.05 0.10 0.28 0.28 0.28
Unit
Quantity
cu.m
0.168
kg. kg. bd.ft pc kg.
40.45 0.809 15.333 0.268 0.163
cu.m bd.ft cu.m
0.03 1.00 0.06
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Payloader (1.50 m3), LX80-2C b. Concrete Vibrator c. Plate Compactor (for Casting Bed) d. Bar Bender e. Bar Cutter Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per Hour = 2.50 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
a. Ready Mix concrete, Class AA-27.60Mpa @ 28D* b. Reinforced Steel Bar, Grade 60 c. Tie Wire #16 (2% of RSB) d. Good Lumber - 4 uses e. Marine Plywood, 1/2" x 4' x 8' - 4 uses f. Assorted CWN (1kg./100bd.ft of Lumber) Casting Bed a. Ready Mix Concrete Class B b. Good Lumber c. Base Course
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
Note: If no available Ready Mix Concrete at Project Site, derive the cost of concrete using the Batching Plant or One Bagger Mixer for small quantity
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
140
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(4)a.2 Precast Concrete Piles, furnished (400mm x 400mm -type B) : m. : 2.50 m. Designation
No. of Person/s
No. of Hour/s
1 4 8
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 1
0.05 0.10 0.28 0.28 0.28
Unit
Quantity
a. Ready Mix concrete, Class AA-27.60Mpa @ 28D* b. Reinforced Steel Bar, Grade 60 c. Tie Wire #16 (2% of RSB) d. Good Lumber - 4 uses e. Marine Plywood, 1/2" x 4' x 8' - 4 uses f. Assorted CWN (1kg./100bd.ft of Lumber)
cu.m kg. kg. bd.ft pc kg.
0.168 48.69 0.974 15.333 0.268 0.163
Casting Bed a. Ready Mix Concrete Class B b. Good Lumber c. Base Course
cu.m bd.ft cu.m
0.03 1.00 0.06
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment 3
a. Payloader (1.50 m ), LX80-2C b. Concrete Vibrator c. Plate Compactor (for Casting Bed) d. Bar Bender e. Bar Cutter Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per Hour = 2.50 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
Note: If no available Ready Mix Concrete at Project Site, derive the cost of concrete using the Batching Plant or One Bagger Mixer for small quantity
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
141
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(4)b.1 Precast Concrete Piles, furnished (450mm x 450mm -type C) : m. : 2.30 m. Designation
No. of Person/s
No. of Hour/s
1 4 8
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 1
0.05 0.10 0.27 0.27 0.27
Unit
Quantity
a. Ready Mix concrete, Class AA-27.60Mpa @ 28D* b. Reinforced Steel Bar, Grade 60 c. Tie Wire #16 (2% of RSB) d. Good Lumber - 4 uses e. Marine Plywood, 1/2" x 4' x 8' - 4 uses f. Assorted CWN (1kg./100bd.ft of Lumber)
cu.m kg. kg. bd.ft pc kg.
0.213 50.040 1.001 17.25 0.30 0.183
Casting Bed a. Ready Mix Concrete Class B b. Good Lumber c. Base Course
cu.m bd.ft cu.m
0.033 1.00 0.07
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment 3
a. Payloader (1.50 m ), LX80-2C b. Concrete Vibrator c. Plate Compactor (for Casting Bed) d. Bar Bender e. Bar Cutter Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per Hour = 2.30 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
Note: If no available Ready Mix Concrete at Project Site, derive the cost of concrete using the Batching Plant or One Bagger Mixer for small quantity
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
142
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(4)b.2 Precast Concrete Piles, furnished (450mm x 450mm -type D) : m. : 2.30 m. Designation
No. of Person/s
No. of Hour/s
1 4 8
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 1
0.05 0.10 0.27 0.27 0.27
Unit
Quantity
a. Ready Mix concrete, Class AA-27.60Mpa @ 28D* b. Reinforced Steel Bar, Grade 60 c. Tie Wire #16 (2% of RSB) d. Good Lumber - 4 uses e. Marine Plywood, 1/2" x 4' x 8' - 4 uses f. Assorted CWN (1kg./100bd.ft of Lumber)
cu.m kg. kg. bd.ft pc kg.
0.213 62.46 1.249 17.25 0.30 0.183
Casting Bed a. Ready Mix Concrete Class B b. Good Lumber c. Base Course
cu.m bd.ft cu.m
0.033 1.00 0.07
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment 3
a. Payloader (1.50 m ), LX80-2C b. Concrete Vibrator c. Plate Compactor (for Casting Bed) d. Bar Bender e. Bar Cutter Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per Hour = 2.30 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
Note: If no available Ready Mix Concrete at Project Site, derive the cost of concrete using the Batching Plant or One Bagger Mixer for small quantity
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
143
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1052(5)a
Precast, Prestressed Concrete Piles, furnished (400 mm x 400 mm) m. 48.00 m.
Designation
No. of Person/s
No. of Hour/s
1 2 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1
1.00
Unit
Quantity
m
1.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41 - 45 mt) Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 48.00 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Precast, Prestressed Concrete Piles (delivered at site) Miscellaneous (2% of material cost)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
144
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1052(5)b
Precast, Prestressed Concrete Piles, furnished (450 mm x 450 mm) m. 48.00 m.
Designation
No. of Person/s
No. of Hour/s
1 2 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1
1.00
Unit
Quantity
m
1.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41 - 45 mt) Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 48.00 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Precast, Prestressed Concrete Piles (delivered at site) Miscellaneous (2% of material cost)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
145
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1052(6)
Structural Steel Sheet Piles, furnished m. 72.00 m.
Designation
No. of Person/s
No. of Hour/s
1 2 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1
1.00
Unit
Quantity
kg.
48.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41 - 45 mt) Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 72.00 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Steel Sheet Pile KSP II (delivered at site) Miscellaneous (2% of material cost)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
146
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1052(7)a
Precast Concrete Sheet Piles, furnished (0.50 m x 0.35 m) m. 1.90 m.
Designation
No. of Person/s
No. of Hour/s
1 4 8
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 1 1 1
0.03 0.25 0.25 0.03 0.15 0.15 0.03
Unit
Quantity
41.64 1.66
c. Sand
kg. bag m3
d. Gravel e. Plywood, 1/2" x 4' x 8' - 4 uses f. Good Lumber - 4 uses g. #16 GI Tie Wire (2% of RSB) h. Assorted CWN (1 kg/100 bd-ft of Lumber)
m3 pc bd-ft kg kg
0.18 0.24 12.40 0.83 0.12
bag m3
0.296
m3 bd.ft m3
0.037 1.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Payloader (1.50 m3), LX80-2C b. One Bagger Mixer c. Concrete Vibrator d. Water Truck/Pump (16000 L) e. Bar Cutter f. Bar Bender g. Plate Compactor (5 hp), for Casting Bed Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.90 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Reinforcing Steel Bar b. Cement
Casting Bed a. Cement b. Sand c. Gravel d. Good Lumber - 4 uses e. Base Course G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
0.09
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
0.019
0.08
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
147
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1052(7)b
Precast Concrete Sheet Piles, furnished (0.50 m x 0.35 m), (Ready Mix Concrete) m. 2.30 m.
Designation
No. of Person/s
No. of Hour/s
1 4 8
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 1
0.03 0.10 0.03 0.22 0.22
Unit
Quantity
kg. m3 pc bd-ft kg kg
41.64
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment 3
a. Payloader (1.50 m ), LX80-2C b. Concrete Vibrator c. Plate Compactor (5 hp), for Casting Bed d. Bar Cutter e. Bar Bender Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 2.30 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Reinforcing Steel Bar b. Ready Mix Concrete, fc'=27.60 Mpa c. Plywood, 1/2" x 4' x 8' - 4 uses f. Good Lumber - 4 uses g. #16 GI Tie Wire (2% of RSB) h. Assorted CWN (1 kg/100 bd-ft of Lumber)
0.18 0.24 12.40 0.83 0.12
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
Casting Bed a. Ready Mix Concrete, Class B d. Good Lumber - 4 uses e. Base Course
3
m bd-ft m3
0.037 1.00 0.08
Note:
If no available Ready Mix Concrete at Project Site, derive the cost of concrete using the Batching Plant or One Bagger Mixer for small quantity
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
148
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1052(11)
Steel Pipe Piles, furnished and driven m. 3.00 m.
Designation
No. of Person/s
No. of Hour/s
1 6 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 1
0.58 0.25 0.13 0.08 0.08
Unit
Quantity
m
1.00
kg set m bd-ft kg
0.048 0.019 1.00 16.00 0.16
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41 - 45 mt) b. Diesel Hammer (K25 or equivalent) c. Drop Hammer d. Welding Machine (500 A), Gas/Diesel Driven e. Cutting Outfit Minor Tools (5% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 3.00 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Tubular Pile (0.40 m Ø x 9.50 mm thk) (delivered at site) b. Welding Rod (1 kg/2000 kg of Steel) c. Oxygen/Acetylene (1 set/5000 kg of Steel) d. Coco Log - 2 uses e. Good Lumber (Falsework) - 4 uses f. Nail/Spike (1 kg/100 bd-ft of Lumber) Miscellaneous (2% of Materials Cost)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
Note: Assumed weight of Tubular Pipe Pile is 95.93 kg/m
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
149
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1052(12)
Structural Steel Sheet Piles, driven m. 10.00 m.
Designation
No. of Person/s
No. of Hour/s
1 6 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 1
1.00 1.00 1.00 1.00 0.50
Unit
Quantity
kg set m bd-ft kg
0.024 0.0096 0.18 1.55 0.02
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41 - 45 mt) b. Diesel Hammer (K25 or equivalent) c. Drop Hammer d. Welding Machine (500 A), Gas/Diesel Driven e. Cutting Outfit Minor Tools (5% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 10.00 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Welding Rod (1 kg/2000 kg of Steel) b. Oxygen/Acetylene (1 set/5000 kg of Steel) c. Coco Log - 2 uses d. Good Lumber - 4 uses e. Assorted CWN (1 kg/100 bd-ft of Lumber) Miscellaneous (2% of Materials Cost)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
150
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1052(13)
Precast Concrete Sheet Piles, driven m. 2.80 m.
Designation
No. of Person/s
No. of Hour/s
1 6 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 2 1
0.56 0.31 0.31 0.19 0.19
Unit
Quantity
m bd-ft kg kg
0.71 6.19 0.06 0.06
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41 - 45 mt) b. Diesel Hammer (K25 or equivalent) c. Drop Hammer d. Jack Hammer e. Air Compressor (356 - 450 cfm) Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 2.80 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Coco Log - 2 uses b. Good Lumber - 4 uses c. Nail/Spike (1 kg/100 bd-ft of Lumber) d. Assorted CWN (1 kg/100 bd-ft of Lumber) Miscellaneous (2% of Materials Cost)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
151
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(14)a Precast Concrete Piles, driven (soft strata) : m. : 2.40 m. Designation
No. of Person/s
No. of Hour/s
1 6 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 2 1
0.53 0.27 0.13 0.20 0.20 0.20
Unit
Quantity
m bd-ft kg kg
1.00 16.00 0.16 0.01
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41 - 45 mt) b. Diesel Hammer (K25 or equivalent) c. Drop Hammer d. Cutting Outfit e. Jack Hammer f. Air Compressor (356 - 450 cfm) Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 2.40 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Coco Log - 2 uses b. Good Lumber - 4 uses c. Nail/Spike (1 kg/100 bd-ft of Lumber) d. Oxygen/Acetylene Miscellaneous (2% of Materials Cost)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
152
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(14)b Precast Concrete Piles, driven (hard strata) : m. : 1.95 m. Designation
No. of Person/s
No. of Hour/s
1 6 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 2 1
0.62 0.41 0.11 0.16 0.16 0.16
Unit
Quantity
m bd-ft kg set
1.00 16.00 0.16 0.01
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41 - 45 mt) b. Diesel Hammer (K25 or equivalent) c. Drop Hammer d. Cutting Outfit e. Jack Hammer f. Air Compressor (356 - 450 cfm) Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.95 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Coco Log - 2 uses b. Good Lumber - 4 uses c. Nail/Spike (1 kg/100 bd-ft of Lumber) d. Oxygen/Acetylene Miscellaneous (2% of Materials Cost)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
153
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(15)a Precast, Prestressed Concrete Piles, driven (soft strata) : m. : 2.40 m. Designation
No. of Person/s
No. of Hour/s
1 6 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 2 1
0.53 0.27 0.13 0.20 0.20 0.20
Unit
Quantity
m bd-ft kg set
1.00 16.00 0.16 0.01
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41 - 45 mt) b. Diesel Hammer (K25 or equivalent) c. Drop Hammer d. Cutting Outfit e. Jack Hammer f. Air Compressor (356 - 450 cfm) Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 2.40 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Coco Log - 2 uses b. Good Lumber (Falsework) - 4 uses c. Nail/Spike (1 kg/100 bd-ft of Lumber) d. Oxygen/Acetylene Miscellaneous (2% of Materials Cost)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
154
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(15)b Precast, Prestressed Concrete Piles, driven (hard strata) : m. : 1.95 m. Designation
No. of Person/s
No. of Hour/s
1 6 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 2 1
0.62 0.41 0.11 0.16 0.16 0.16
Unit
Quantity
m bd-ft kg set
1.00 16.00 0.16 0.01
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41 - 45 mt) b. Diesel Hammer (K25 or equivalent) c. Drop Hammer d. Cutting Outfit e. Jack Hammer f. Air Compressor (356 - 450 cfm) Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.95 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Coco Log - 2 uses b. Good Lumber (Falsework) - 4 uses c. Nail/Spike (1 kg/100 bd-ft of Lumber) d. Oxygen/Acetylene Miscellaneous (2% of Materials Cost)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
155
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(16)a Test Piles, furnished and driven (type A, B, C or D), soft strata : m. : 2.40 m. Designation
No. of Person/s
No. of Hour/s
1 6 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 2 1
0.53 0.27 0.13 0.20 0.20 0.20
Unit
Quantity
m bd-ft kg set m
2.00 16.00 0.16 0.01 1.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41 - 45 mt) b. Diesel Hammer (K25 or equivalent) c. Drop Hammer d. Cutting Outfit e. Jack Hammer f. Air Compressor (356 - 450 cfm) Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 2.40 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Coco Log - 2 uses b. Good Lumber (Falsework) - 4 uses c. Nail/Spike (1 kg/100 bd-ft of Lumber) d. Oxygen/Acetylene e. Fabricated RC Pile (delivered at site)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
Note: The unit cost of Fabricated RC Pile is dependent on its type. Please refer to the Direct Cost of Item 1052(7)a
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
156
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(16)b Test Piles, furnished and driven (type A, B, C or D), hard strata : m. : 1.95 m. Designation
No. of Person/s
No. of Hour/s
1 6 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 2 1
0.62 0.41 0.11 0.16 0.16 0.16
Unit
Quantity
m bd-ft kg set m
2.00 16.00 0.16 0.01 1.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41 - 45 mt) b. Diesel Hammer (K25 or equivalent) c. Drop Hammer d. Cutting Outfit e. Jack Hammer f. Air Compressor (356 - 450 cfm) Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.95 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Coco Log - 2 uses b. Good Lumber (Falsework) - 4 uses c. Nail/Spike (1 kg/100 bd-ft of Lumber) d. Oxygen/Acetylene e. Fabricated RC Pile (delivered at site)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
Note: The unit cost of Fabricated RC Pile is dependent on its type. Please refer to the Direct Cost of Item 1052(7)a
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
157
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(17)a Concrete Piles cast in Drilled Holes, 0.80 m. Ø, fc' = 28 MPa (ordinary soil condition) : m : 1.58 m. Designation
No. of Person/s
No. of Hour/s
1 5 6
1.00 1.00 1.00
9.00 17.00
0.50 0.50
No. of Unit/s
No. of Hour/s
1 1 1
0.26 0.95 0.95
1
0.95
1 1 1 1 1 1 1 1 1 1 1 1 2 1 1
0.95 0.95 0.50 0.50 0.74 0.74 0.50 0.50 0.71 0.71 0.24 0.24 0.05 0.05 0.95
Unit
Quantity
cu.m. kg. kg. set kg.
0.55 205.00 4.10 0.041 0.10
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer Fabrication of Cage Bar d. Skilled Laborer e. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Drilling Rig (300 hp) b. Crawler Crane (41 - 45 mt) c. Crawler Crane (21 - 25 mt) 3 d. Dump Truck (12 yd ) 3
e. Payloader (1.50 m ), LX80-2C f. Generator Set (300 KW) g. Bentonite Bin h. Bentonite Mixer i . Water Pump, 100 mm suction Ø (7.5 hp) j. Water Truck (16000 L) k. Bar Cutter l. Bar Bender m. Welding Machine (500A), Electric Driven n. Cutting Outfit o. Tremie Pipe Set p. SPT & Desanding Machine q. Portable Breaker, BHF30S r. Air Compressor, Portable (126 - 160 cfm) s. Lighting System/Tower Lights Minor Tools (10% of Labor) Sub - Total for B C. Total (A + B) D. Output per Hour = 1.58 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Ready Mix Concrete, fc' = 28 Mpa @ 28 D b. Reinforcing Steel Bar * c. Tire Wire (2% of RSB) d. Oxygen/Acetylene (1 set/5000 kg. of RSB) e. Welding Rod (1 kg./2000 kg. of RSB) Miscellaneous (3% of Materials, Bentonite and etc.)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
* Its quantity is variable depending on the actual design
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
158
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(17)b Concrete Piles cast in Drilled Holes, 1.00 m. Ø, fc' = 28 MPa (ordinary soil condition) : m : 1.33 m. Designation
No. of Person/s
No. of Hour/s
1 5 6
1.00 1.00 1.00
9 16
0.56 0.56
No. of Unit/s
No. of Hour/s
1 1 1
0.31 0.96 0.96
1
0.96
1 1 1 1 1 1 1 1 1 1 1 1 2 1 1
0.96 0.96 0.53 0.53 0.78 0.78 0.56 0.56 0.73 0.73 0.22 0.24 0.04 0.04 0.96
Unit
Quantity
cu.m. kg. kg. set kg.
0.86 253.59 5.07 0.051 0.13
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer Fabrication of Cage Bar d. Skilled Laborer e. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Drilling Rig (300 hp) b. Crawler Crane (41 - 45 mt) c. Crawler Crane (21 - 25 mt) 3 d. Dump Truck (12 yd ) 3
e. Payloader (1.50 m ), LX80-2C f. Generator Set (300 KW) g. Bentonite Bin h. Bentonite Mixer i . Water Pump, 100 mm suction Ø (7.5 hp) j. Water Truck (16000 L) k. Bar Cutter l. Bar Bender m. Welding Machine (500A), Electric Driven n. Cutting Outfit o. Tremie Pipe Set p. SPT & Desanding Machine q. Portable Breaker, BHF30S r. Air Compressor, Portable (126 - 160 cfm) s. Lighting System/Tower Lights Minor Tools (10% of Labor) Sub - Total for B C. Total (A + B) D. Output per Hour = 1.33 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Ready Mix Concrete, fc' = 28 Mpa @ 28 D b. Reinforcing Steel Bar * c. Tire Wire (2% of RSB) d. Oxygen/Acetylene (1 set/5000 kg. of RSB) e. Welding Rod (1 kg./2000 kg. of RSB) Miscellaneous (3% of Materials, Bentonite and etc.)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
* Its quantity is variable depending on the actual design
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
159
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(17)c Concrete Piles cast in Drilled Holes, 1.20 m. Ø, fc' = 28 MPa (ordinary soil condition) : m : 1.09 m. Designation
No. of Person/s
No. of Hour/s
1 5 6
1.00 1.00 1.00
8 15
0.60 0.60
No. of Unit/s
No. of Hour/s
1 1 1
0.35 0.96 0.96
1
0.96
1 1 1 1 1 1 1 1 1 1 1 1 2 1 1
0.96 0.96 0.56 0.56 0.82 0.82 0.60 0.60 0.75 0.75 0.22 0.25 0.04 0.04 0.96
Unit
Quantity
cu.m. kg. kg. set kg.
1.24 304.30 6.09 0.06 0.15
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer Fabrication of Cage Bar d. Skilled Laborer e. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Drilling Rig (300 hp) b. Crawler Crane (41 - 45 mt) c. Crawler Crane (21 - 25 mt) 3 d. Dump Truck (12 yd ) 3
e. Payloader (1.50 m ), LX80-2C f. Generator Set (300 KW) g. Bentonite Bin h. Bentonite Mixer i . Water Pump, 100 mm suction Ø (7.5 hp) j. Water Truck/Pump (16000 L) k. Bar Cutter l. Bar Bender m. Welding Machine (500 A), Electric Driven n. Cutting Outfit o. Tremie Pipe Set p. SPT & Desanding Machine q. Portable Breaker, BHF30S r. Air Compressor, Portable (126- 160 cfm) s. Lighting System/Tower Lights Minor Tools (10% of Labor) Sub - Total for B C. Total (A + B) D. Output per Hour = 1.09 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Ready Mix Concrete, fc' = 28 Mpa @ 28 D b. Reinforcing Steel Bar * c. Tire Wire (2% of RSB) d. Oxygen/Acetylene (1 set/5000 kg. of RSB) e. Welding Rod (1 kg./2000 kg. of RSB) Miscellaneous (3% of Materials, Bentonite and etc.)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
* Its quantity is variable depending on the actual design
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
160
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(17)d Concrete Piles cast in Drilled Holes, 1.50 m. Ø, fc' = 28 MPa (ordinary soil condition) : m : 0.81 m. Designation
No. of Person/s
No. of Hour/s
1 5 6
1.00 1.00 1.00
7 13
0.65 0.65
No. of Unit/s
No. of Hour/s
1 1 1
0.39 0.97 0.97
1
0.97
1 1 1 1 1 1 1 1 1 1 1 1 2 1 1
0.97 0.97 0.61 0.61 0.86 0.86 0.65 0.65 0.76 0.76 0.22 0.26 0.03 0.03 0.97
Unit
Quantity
cu.m. kg. kg. set kg.
1.94 387.77 7.76 0.08 0.19
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer Fabrication of Cage Bar d. Skilled Laborer e. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Drilling Rig (300 hp) b. Crawler Crane (41 - 45 mt) c. Crawler Crane (21 - 25 mt) 3 d. Dump Truck (12 yd ) 3
e. Payloader (1.50 m ), LX80-2C f. Generator Set (300 KW) g. Bentonite Bin h. Bentonite Mixer i . Water Pump, 100 mm suction Ø (7.5 hp) j. Water Truck/Pump (16000 L) k. Bar Cutter l. Bar Bender m. Welding Machine (500 A), Electric Driven n. Cutting Outfit o. Tremie Pipe Set p. SPT & Desanding Machine q. Portable Breaker, BHF30S r. Air Compressor, Portable (126- 160 cfm) s. Lighting System/Tower Lights Minor Tools (10% of Labor) Sub - Total for B C. Total (A + B) D. Output per Hour = 0.81 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Ready Mix Concrete, fc' = 28 Mpa @ 28 D b. Reinforcing Steel Bar * c. Tire Wire (2% of RSB) d. Oxygen/Acetylene (1 set/5000 kg. of RSB) e. Welding Rod (1 kg./2000 kg. of RSB) Miscellaneous (3% of Materials, Bentonite and etc.)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
* Its quantity is variable depending on the actual design
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
161
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(17)e Concrete Piles cast in Drilled Holes, 1.80 m. Ø, fc' = 28 MPa (ordinary soil condition) : m : 0.62 m. Designation
No. of Person/s
No. of Hour/s
1 5 6
1.00 1.00 1.00
6 11
0.68 0.68
No. of Unit/s
No. of Hour/s
1 1 1
0.42 0.98 0.98
1
0.98
1 1 1 1 1 1 1 1 1 1 1 1 2 1 1
0.98 0.98 0.64 0.64 0.90 0.90 0.68 0.68 0.76 0.76 0.22 0.26 0.02 0.02 0.98
Unit
Quantity
cu.m. kg. kg. set kg.
2.80 451.98 9.04 0.09 0.23
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer Fabrication of Cage Bar d. Skilled Laborer e. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Drilling Rig (300 hp) b. Crawler Crane (41 - 45 mt) c. Crawler Crane (21 - 25 mt) 3 d. Dump Truck (12 yd ) 3
e. Payloader (1.50 m ), LX80-2C f. Generator Set (300 KW) g. Bentonite Bin h. Bentonite Mixer i . Water Pump, 100 mm suction Ø (7.5 hp) j. Water Truck/Pump (16000 L) k. Bar Cutter l. Bar Bender m. Welding Machine (500 A), Electric Driven n. Cutting Outfit o. Tremie Pipe Set p. SPT & Desanding Machine q. Portable Breaker, BHF30S r. Air Compressor, Portable (126- 160 cfm) s. Lighting System/Tower Lights Minor Tools (10% of Labor) Sub - Total for B C. Total (A + B) D. Output per Hour = 0.62 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Ready Mix Concrete, fc' = 28 Mpa @ 28 D b. Reinforcing Steel Bar * c. Tire Wire (2% of RSB) d. Oxygen/Acetylene (1 set/5000 kg. of RSB) e. Welding Rod (1 kg./2000 kg. of RSB) Miscellaneous (3% of Materials, Bentonite and etc.)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
* Its quantity is variable depending on the actual design
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
162
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1052(17)f Concrete Piles cast in Drilled Holes, 2.00 m. Ø, fc' = 28 MPa (ordinary soil condition) m 0.53 m.
Designation
No. of Person/s
No. of Hour/s
1 5 6
1.00 1.00 1.00
5 10
0.70 0.70
No. of Unit/s
No. of Hour/s
1 1 1
0.44 0.98 0.98
1
0.98
1 1 1 1 1 1 1 1 1 1 1 1 2 1 1
0.98 0.98 0.65 0.65 0.91 0.91 0.70 0.70 0.77 0.77 0.21 0.26 0.02 0.02 0.98
Unit
Quantity
cu.m. kg. kg. set kg.
3.46 490.33 9.81 0.098 0.25
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer Fabrication of Cage Bar d. Skilled Laborer e. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Drilling Rig (300 hp) b. Crawler Crane (41 - 45 mt) c. Crawler Crane (21 - 25 mt) 3 d. Dump Truck (12 yd ) 3
e. Payloader (1.50 m ), LX80-2C f. Generator Set (300 KW) g. Bentonite Bin h. Bentonite Mixer i . Water Pump, 100 mm suction Ø (7.5 hp) j. Water Truck/Pump (16000 L) k. Bar Cutter l. Bar Bender m. Welding Machine (500 A), Electric Driven n. Cutting Outfit o. Tremie Pipe Set p. SPT & Desanding Machine q. Portable Breaker, BHF30S r. Air Compressor, Portable (126- 160 cfm) s. Lighting System/Tower Lights Minor Tools (10% of Labor) Sub - Total for B C. Total (A + B) D. Output per Hour = 0.53 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Ready Mix Concrete, fc' = 28 Mpa @ 28 D b. Reinforcing Steel Bar * c. Tire Wire (2% of RSB) d. Oxygen/Acetylene (1 set/5000 kg. of RSB) e. Welding Rod (1 kg./2000 kg. of RSB) Miscellaneous (3% of Materials, Bentonite and etc.)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
* Its quantity is variable depending on the actual design
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
163
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(18)a Concrete Piles cast in Steel Shells, furnished and driven : m : 1.80 m. Designation
No. of Person/s
No. of Hour/s
1 6 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 1 1 1 1 1 1 1
0.39 0.15 0.07 0.12 0.12 0.05 0.05 0.17 0.04 0.04 0.17
Name and Specification
Unit
Quantity
a. Tubular Pile (0.40 m Ø x 9.50 mm thk)* b. Reinforcing Steel Bar c. Cement d. Sand e. Gravel f. #16 Tie Wire (2% of RSB) g. Welding Rod (1 kg/2000 kg of Steel) h. Oxy/Acetylene (1 kg/5000 kg of Steel) i. Coco Log- 2 uses j. Good Lumber (Falsework)- 4 uses k. Nail/Spike (1 kg/100 bd-ft of Lumber) Miscellaneous (2% of Materials Cost)
m. kg. bag m³ m³ kg. kg. set m. bd-ft kg.
1.00 29.547 1.194 0.063 0.126 0.591 0.063 0.025 1.00 16.00 0.16
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41 - 45 mt) b. Diesel Hammer (K25 or equivalent) c. Drop Hammer d. Bar Cutter e. Bar Bender f. Welding Machine (500A), Gas/Diesel Driven g. Cutting Outfit h. One Bagger Mixer i. Water Truck/Pump (16000L) j. Concrete Vibrator k. Tremie Pipe Set Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.80 m. E. Direct Unit Cost (C ÷ D)
F. Materials Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
Note: Assumed weight of Tubular Pipe Pile is 95.93 kg/m.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
164
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(18)b Concrete Piles cast in Steel Shells, furnished and driven (Ready Mix Concrete) : m : 2.00 m. Designation
No. of Person/s
No. of Hour/s
1 6 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 1 1 1 1 1
0.45 0.17 0.08 0.14 0.14 0.06 0.06 0.01 0.05
Name and Specification
Unit
Quantity
a. Tubular Pile (0.40 m Ø x 9.50 mm thk)* b. Reinforcing Steel Bar c. Ready Mix Concrete fc'=20.7 MPa d. #16 Tie Wire (2% of RSB) e. Welding Rod (1 kg/2000 kg of Steel) f. Oxy/Acetylene (1 kg/5000 kg of Steel) g. Coco Log- 2 uses h. Good Lumber (Falsework)- 4 uses i. Nail/Spike (1 kg/100 bd-ft of Lumber) Miscellaneous (2% of Materials Cost)
m. kg. m³ kg. kg. set m bd-ft kg.
1.00 29.547 0.132 0.591 0.063 0.025 1.00 16.00 0.16
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41 - 45 mt) b. Diesel Hammer (K25 or equivalent) c. Drop Hammer d. Bar Cutter e. Bar Bender f. Welding Machine (500A), Gas/Diesel Driven g. Cutting Outfit h. Concrete Vibrator i. Tremie Pipe Set Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per Hour = 2.00 m. E. Direct Unit Cost (C ÷ D)
F. Materials Prices of materials are variable per Region/ District based on the prevailing unit Region/ prices in Prices of materials are variable per the locality which include payment local in District based on the prevailing unitofprices taxes and hauling cost to payment the project the locality which include of site. local Refer to the Construction Material Price taxes and hauling cost to the project site.Data established quarterly by Central Price Monitoring Committee.
Note: Assumed weight of Tubular Pipe Pile is 95.93 kg/m.
If no available Ready Mix Concrete at Project Site, derive the cost of concrete using the Batching Plant or One Bagger Mixer for small quantity.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
165
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(19)a Concrete Piles cast in Steel Pipes, furnished and driven : m : 2.40 m. Designation
No. of Person/s
No. of Hour/s
1 6 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 1 1 1 1 1 1 1
0.39 0.15 0.07 0.12 0.12 0.05 0.05 0.17 0.04 0.04 0.17
Name and Specification
Unit
Quantity
a. Tubular Pile (0.40 m Ø x 9.50 mm thk)* b. Reinforcing Steel Bar c. Cement d. Sand e. Gravel f. #16 Tie Wire (2% of RSB) g. Welding Rod (1 kg/2000 kg of Steel) h. Oxy/Acetylene (1 kg/5000 kg of Steel) i. Coco Log- 2 uses j. Good Lumber (Falsework)- 4 uses k. Nail/Spike (1 kg/100 bd-ft of Lumber) Miscellaneous (2% of Materials Cost)
m. kg. bag m³ m³ kg. kg. set m bd-ft kg.
1.00 29.547 1.194 0.063 0.126 0.591 0.063 0.025 1.00 16.00 0.16
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41 - 45 mt) b. Diesel Hammer (K25 or equivalent) c. Drop Hammer d. Bar Cutter e. Bar Bender f. Welding Machine (500A), Gas/Diesel Driven g. Cutting Outfit h. One Bagger Mixer i. Water Truck/Pump (16000L) j. Concrete Vibrator k. Tremie Pipe Set Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per Hour = 2.40 m. E. Direct Unit Cost (C ÷ D)
F. Materials Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
Note: Assumed weight of Tubular Pipe Pile is 95.93 kg/m.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
166
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(19)b Concrete Piles cast in Steel Pipes, furnished and driven (Ready Mix Concrete) : m : 2.00 m. Designation
No. of Person/s
No. of Hour/s
1 6 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1 1 1 1 1 1
0.45 0.17 0.08 0.14 0.14 0.06 0.06 0.01 0.05
Name and Specification
Unit
Quantity
a. Tubular Pile (0.40 m Ø x 9.50 mm thk)* b. Reinforcing Steel Bar c. Ready Mix Concrete fc'=20.7 MPa d. #16 Tie Wire (2% of RSB) e. Welding Rod (1 kg/2000 kg of Steel) f. Oxy/Acetylene (1 kg/5000 kg of Steel) g. Coco Log- 2 uses h. Good Lumber (Falsework)- 4 uses i. Nail/Spike (1 kg/100 bd-ft of Lumber) Miscellaneous (2% of Materials Cost)
m. kg. m³ kg. kg. set m bd-ft kg.
1.00 29.547 0.132 0.591 0.063 0.025 1.00 16.00 0.16
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41 - 45 mt) b. Diesel Hammer (K25 or equivalent) c. Drop Hammer d. Bar Cutter e. Bar Bender f. Welding Machine (500A), Gas/Diesel Driven g. Cutting Outfit h. Concrete Vibrator i. Tremie Pipe Set Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per Hour = 2.00 m. E. Direct Unit Cost (C ÷ D)
F. Materials Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
Note:
Assumed weight of Tubular Pipe Pile is 95.93 kg/m. If no available Ready Mix Concrete at Project Site, derive the cost of concrete using the Batching Plant or One Bagger Mixer for small quantity
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
167
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1052(20)
Pile Shoes ea 4.00 ea
Designation
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1
1.00 0.25 0.25
Unit
Quantity
kg. kg. kg.
23.86 6.00 0.015
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Welding Machine (500A), Electric Driven b. Bar Cutter c. Bar Bender
Sub - Total for B C. Total (A + B) D. Output per Hour = 4.00 ea E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Reinforcing Steel Bar, Grade 40 b. Steel Plate (100+100) x 300 mm, 12 mm thk c. Welding Rod ( 1 kg/2000 kg of Steel)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit Region/ prices in Prices of materials are variable per the locality which include payment local in District based on the prevailing unitofprices taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
168
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(23)a Bored Piles, 0.80 m. Ø (ordinary soil condition) : m : 1.58 m. Designation
No. of Person/s
No. of Hour/s
1 5 6
1.00 1.00 1.00
9.00 17.00
0.50 0.50
No. of Unit/s
No. of Hour/s
1 1 1
0.26 0.95 0.95
1
0.95
1 1 1 1 1 1 1 1 1 1 1 1 2 1 1
0.95 0.95 0.50 0.50 0.74 0.74 0.50 0.50 0.71 0.71 0.24 0.24 0.05 0.05 0.95
Unit
Quantity
cu.m. kg. kg. set kg.
0.55 205.00 4.10 0.041 0.10
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer Fabrication of Cage Bar d. Skilled Laborer e. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Drilling Rig (300 hp) b. Crawler Crane (41 - 45 mt) c. Crawler Crane (21 - 25 mt) 3 d. Dump Truck (12 yd ) 3
e. Payloader (1.50 m ), LX80-2C f. Generator Set (300 KW) g. Bentonite Bin h. Bentonite Mixer i . Water Pump, 100 mm suction Ø (7.5 hp) j. Water Truck (16000 L) k. Bar Cutter l. Bar Bender m. Welding Machine (500A), Electric Driven n. Cutting Outfit o. Tremie Pipe Set p. SPT & Desanding Machine q. Portable Breaker, BHF30S r. Air Compressor, Portable (126 - 160 cfm) s. Lighting System/Tower Lights Minor Tools (10% of Labor) Sub - Total for B C. Total (A + B) D. Output per Hour = 1.58 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Ready Mix Concrete, fc' = 28 Mpa @ 28 D b. Reinforcing Steel Bar * c. Tire Wire (2% of RSB) d. Oxygen/Acetylene (1 set/5000 kg. of RSB) e. Welding Rod (1 kg./2000 kg. of RSB) Miscellaneous (3% of Materials, Bentonite and etc.)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
* Its quantity is variable depending on the actual design
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
169
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(23)b Bored Piles, 1.00 m. Ø (ordinary soil condition) : m : 1.33 m. Designation
No. of Person/s
No. of Hour/s
1 5 6
1.00 1.00 1.00
9 16
0.56 0.56
No. of Unit/s
No. of Hour/s
1 1 1
0.31 0.96 0.96
1 1 1 1 1 1 1 1 1 1 1 1 1 2 1 1
0.96 0.96 0.96 0.53 0.53 0.78 0.78 0.56 0.56 0.73 0.73 0.22 0.24 0.04 0.04 0.96
Unit
Quantity
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer Fabrication of Cage Bar d. Skilled Laborer e. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Drilling Rig (300 hp) b. Crawler Crane (41- 45 mt) c. Crawler Crane (21- 25 mt) 3 d. Dump Truck (12yd ) e. Payloader (1.50 m3), LX80-2C f. Generator Set (300 KW) g. Bentonite Bin h. Bentonite Mixer i . Water Pump, 100 mm suction Ø (7.5 hp) j. Water Truck/Pump (16000L) k. Bar Cutter l. Bar Bender m. Welding Machine (500 A), Electric Driven n. Cutting Outfit o. Tremie Pipe Set p. SPT & Desanding Machine q. Portable Breaker, BHF30S r. Air Compressor, Portable (126- 160 cfm) s. Lighting System/Tower Lights Minor Tools (10% of Labor) Sub - Total for B C. Total (A + B) D. Output per Hour = 1.33 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Ready Mix Concrete, fc' = 28 Mpa b. Reinforcing Steel Bar * c. Tire Wire (2% of RSB) d. Oxygen/Acetylene (1 set/5000 kg. of RSB) e. Welding Rod (1 kg./2000 kg. of RSB) Miscellaneous (3% of Materials, Bentonite and etc.)
3
m kg. kg. set kg.
0.86 253.59 5.07 0.051 0.13
Prices of materials are variable per Region/ Prices materials areprevailing variable per Districtofbased on the unit Region/ prices in District based on the prevailing unitofprices the locality which include payment local in the locality which include payment of local taxes and hauling cost to the project site. taxes hauling cost to the project site.Data Refer and to the Construction Material Price Refer to the quarterly Construction Material Price Data established by Central Price established quarterly by Central Price Monitoring Committee. Monitoring Committee
* Its quantity is variable depending on the actual design
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
170
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(23)c Bored Piles, 1.20 m. Ø (ordinary soil condition) : m : 1.09 m. Designation
No. of Person/s
No. of Hour/s
1 5 6
1.00 1.00 1.00
8 15
0.60 0.60
No. of Unit/s
No. of Hour/s
1 1 1
0.35 0.96 0.96
1 1 1 1 1 1 1 1 1 1 1 1 1 2 1 1
0.96 0.96 0.96 0.56 0.56 0.82 0.82 0.60 0.60 0.75 0.75 0.22 0.25 0.04 0.04 0.96
Unit
Quantity
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer Fabrication of Cage Bar d. Skilled Laborer e. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Drilling Rig (300 hp) b. Crawler Crane (41- 45 mt) c. Crawler Crane (21- 25 mt) 3 d. Dump Truck (12yd ) e. Payloader (1.50 m3), LX80-2C f. Generator Set (300 KW) g. Bentonite Bin h. Bentonite Mixer i . Water Pump, 100 mm suction Ø (7.5 hp) j. Water Truck/Pump (16000L) k. Bar Cutter l. Bar Bender m. Welding Machine (500 A), Electric Driven n. Cutting Outfit o. Tremie Pipe Set p. SPT & Desanding Machine q. Portable Breaker, BHF30S r. Air Compressor, Portable (126- 160 cfm) s. Lighting System/Tower Lights Minor Tools (10% of Labor) Sub - Total for B C. Total (A + B) D. Output per Hour = 1.09 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Ready Mix Concrete, fc' = 28 Mpa b. Reinforcing Steel Bar * c. Tire Wire (2% of RSB) d. Oxygen/Acetylene (1 set/5000 kg. of RSB) e. Welding Rod (1 kg./2000 kg. of RSB) Miscellaneous (3% of Materials, Bentonite and etc.)
3
m kg. kg. set kg.
1.24 304.30 6.09 0.061 0.15
Prices of materials are variable per Region/ Prices materials areprevailing variable per Districtofbased on the unit Region/ prices in District based on the prevailing unitofprices the locality which include payment local in the locality which include of site. local taxes and hauling cost to payment the project taxes hauling cost to the project site.Data Refer and to the Construction Material Price Refer to the quarterly Construction Material Price Data established by Central Price established quarterly by Central Price Monitoring Committee. Monitoring Committee
* Its quantity is variable depending on the actual design
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
171
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(23)d Bored Piles, 1.50 m. Ø (ordinary soil condition) : m : 0.81 m. Designation
No. of Person/s
No. of Hour/s
1 5 6
1.00 1.00 1.00
7 13
0.65 0.65
No. of Unit/s
No. of Hour/s
1 1 1
0.39 0.97 0.97
1 1 1 1 1 1 1 1 1 1 1 1 1 2 1 1
0.97 0.97 0.97 0.61 0.61 0.86 0.86 0.65 0.65 0.76 0.76 0.22 0.26 0.03 0.03 0.97
Unit
Quantity
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer Fabrication of Cage Bar d. Skilled Laborer e. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Drilling Rig (300 hp) b. Crawler Crane (41- 45 mt) c. Crawler Crane (21- 25 mt) 3 d. Dump Truck (12yd ) e. Payloader (1.50 m3), LX80-2C f. Generator Set (300 KW) g. Bentonite Bin h. Bentonite Mixer i . Water Pump, 100 mm suction Ø (7.5 hp) j. Water Truck/Pump (16000L) k. Bar Cutter l. Bar Bender m. Welding Machine (500 A), Electric Driven n. Cutting Outfit o. Tremie Pipe Set p. SPT & Desanding Machine q. Portable Breaker, BHF30S r. Air Compressor, Portable (126- 160 cfm) s. Lighting System/Tower Lights Minor Tools (10% of Labor) Sub - Total for B C. Total (A + B) D. Output per Hour = 0.81 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Ready Mix Concrete, fc' = 28 Mpa b. Reinforcing Steel Bar * c. Tire Wire (2% of RSB) d. Oxygen/Acetylene (1 set/5000 kg. of RSB) e. Welding Rod (1 kg./2000 kg. of RSB) Miscellaneous (3% of Materials, Bentonite and etc.)
3
m kg. kg. set kg.
1.94 387.77 7.76 0.078 0.19
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
* Its quantity is variable depending on the actual design
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
172
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(23)e Bored Piles, 1.80 m. Ø (ordinary soil condition) : m : 0.62 m. Designation
No. of Person/s
No. of Hour/s
1 5 6
1.00 1.00 1.00
7 12
0.68 0.68
No. of Unit/s
No. of Hour/s
1 1 1
0.42 0.98 0.98
1
0.98
1 1 1 1 1 1 1 1 1 1 1 1 2 1 1
0.98 0.98 0.64 0.64 0.90 0.90 0.68 0.68 0.76 0.76 0.22 0.26 0.02 0.02 0.98
Unit
Quantity
m3 kg. kg. set kg.
2.80 451.98 9.04 0.090 0.23
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer Fabrication of Cage Bar d. Skilled Laborer e. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Drilling Rig (300 hp) b. Crawler Crane (41- 45 mt) c. Crawler Crane (21- 25 mt) 3 d. Dump Truck (12 yd ) 3
e. Payloader (1.50 m ), LX80-2C f. Generator Set (300 KW) g. Bentonite Bin h. Bentonite Mixer i . Water Pump, 100 mm suction Ø (7.5 hp) j. Water Truck/Pump (16000L) k. Bar Cutter l. Bar Bender m. Welding Machine (500 A), Electric Driven n. Cutting Outfit o. Tremie Pipe Set p. SPT & Desanding Machine q. Portable Breaker r. Air Compressor, Portable (126- 160 cfm) s. Lighting System/Tower Lights Minor Tools (10% of labor cost) Sub - Total for B C. Total (A + B) D. Output per Hour = 0.62 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Ready Mix Concrete, fc' = 28 Mpa b. Reinforcing Steel Bar * c. Tire Wire (2% of RSB) d. Oxygen/Acetylene (1 set/5000 kg. of RSB) e. Welding Rod (1 kg./2000 kg. of RSB) Miscellaneous (3% of Materials, Bentonite and etc.)
Prices of materials are variable per Region/ District based on the prevailing unit Region/ prices in Prices of materials are variable per the locality which include payment local in District based on the prevailing unitofprices taxes and hauling cost to payment the project the locality which include of site. local Refer to the Construction Material Price taxes and hauling cost to the project site.Data established by Central Price Refer to the quarterly Construction Material Price Data Monitoring establishedCommittee. quarterly by Central Price Monitoring Committee
* Its quantity is variable depending on the actual design
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
173
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1052(23)f Bored Piles, 2.00 m. Ø (ordinary soil condition) m 0.53 m.
Designation
No. of Person/s
No. of Hour/s
1 5 6
1.00 1.00 1.00
5 10
0.70 0.70
No. of Unit/s
No. of Hour/s
1 1 1
0.44 0.98 0.98
1
0.98
1 1 1 1 1 1 1 1 1 1 1 1 2 1 1
0.98 0.98 0.65 0.65 0.91 0.91 0.70 0.70 0.77 0.77 0.21 0.26 0.02 0.02 0.98
Unit
Quantity
m3 kg. kg. set kg.
3.46 490.33 9.81 0.098 0.25
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer Fabrication of Cage Bar d. Skilled Laborer e. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Drilling Rig (300 hp) b. Crawler Crane (41- 45 mt) c. Crawler Crane (21- 25 mt) 3 d. Dump Truck (12 yd ) 3
e. Payloader (1.50 m ), LX80-2C f. Generator Set (300 KW) g. Bentonite Bin h. Bentonite Mixer i . Water Pump, 100 mm suction Ø (7.5 hp) j. Water Truck/Pump (16000L) k. Bar Cutter l. Bar Bender m. Welding Machine (500 A), Electric Driven n. Cutting Outfit o. Tremie Pipe Set p. SPT & Desanding Machine q. Portable Breaker r. Air Compressor, Portable (126- 160 cfm) s. Lighting System/Tower Lights Minor Tools (10% of labor cost) Sub - Total for B C. Total (A + B) D. Output per Hour = 0.53 m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Ready Mix Concrete, fc' = 28 Mpa b. Reinforcing Steel Bar * c. Tire Wire (2% of RSB) d. Oxygen/Acetylene (1 set/5000 kg. of RSB) e. Welding Rod (1 kg./2000 kg. of RSB) Miscellaneous (3% of Materials, Bentonite and etc.)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
* Its quantity is variable depending on the actual design
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
174
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(24)a Permanent Casing (0.80 m Ø) : m : 3.00 m. Designation
No. of Person/s
No. of Hour/s
1 4 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1
1.00 0.50 0.50 0.50
Name and Specification
Unit
Quantity
a. Steel Casing, 10 mm thk b. Oxy/Acetylene (1 set/2500 kg of Steel) c. Welding Rod (1 kg/500 kg of Steel)
m set kg.
1.025 0.082 0.409
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41- 45 mt) b. Vibro Hammer w/ Hydraulic Power Pack c. Welding Machine (500 A), Gas/Diesel Driven d. Cutting Outfit Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 3.00 m. E. Direct Unit Cost (C ÷ D)
F. Materials
Note: Assumed length of Steel Casing without splicing but with full weld = 12.00 meter, 2.50% additional quantity of Steel Casing represents the collar of 0.30 m for 12 m.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
175
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(24)b Permanent Casing (1.00 m Ø) : m : 2.40 m. Designation
No. of Person/s
No. of Hour/s
1 4 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1
1.00 0.50 0.50 0.50
Name and Specification
Unit
Quantity
a. Steel Casing, 10 mm thk b. Oxy/Acetylene (1 set/2500 kg of Steel) c. Welding Rod (1 kg/500 kg of Steel)
m set kg.
1.025 0.102 0.511
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41- 45 mt) b. Vibro Hammer w/ Hydraulic Power Pack c. Welding Machine (500 A), Gas/Diesel Driven d. Cutting Outfit Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 2.40 m. E. Direct Unit Cost (C ÷ D)
F. Materials
Note: Assumed length of Steel Casing without splicing but with full weld = 12.00 meter, 2.50% additional quantity of Steel Casing represents the collar of 0.30 m for 12 m.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
176
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(24)c Permanent Casing (1.20 m Ø) : m : 2.00 m. Designation
No. of Person/s
No. of Hour/s
1 4 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1
1.00 0.50 0.50 0.50
Name and Specification
Unit
Quantity
a. Steel Casing, 10 mm thk b. Oxy/Acetylene (1 set/2500 kg of Steel) c. Welding Rod (1 kg/500 kg of Steel)
m set kg.
1.025 0.122 0.612
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41- 45 mt) b. Vibro Hammer w/ Hydraulic Power Pack c. Welding Machine (500 A), Gas/Diesel Driven d. Cutting Outfit Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 2.00 m. E. Direct Unit Cost (C ÷ D)
F. Materials
Note: Assumed length of Steel Casing without splicing but with full weld = 12.00 meter, 2.50% additional quantity of Steel Casing represents the collar of 0.30 m for 12 m.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitorng Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
177
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(24)d Permanent Casing (1.50 m Ø) : m : 1.60 m. Designation
No. of Person/s
No. of Hour/s
1 4 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1
1.00 0.50 0.50 0.50
Name and Specification
Unit
Quantity
a. Steel Casing, 10 mm thk b. Oxy/Acetylene (1 set/2500 kg of Steel) c. Welding Rod (1 kg/500 kg of Steel)
m set kg.
1.025 0.153 0.763
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41- 45 mt) b. Vibro Hammer w/ Hydraulic Power Pack c. Welding Machine (500 A), Gas/Diesel Driven d. Cutting Outfit Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.60 m. E. Direct Unit Cost (C ÷ D)
F. Materials
Note: Assumed length of Steel Casing without splicing but with full weld = 12.00 meter, 2.50% additional quantity of Steel Casing represents the collar of 0.30 m for 12 m.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
178
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(24)e Permanent Casing (1.80 m Ø) : m : 1.33 m. Designation
No. of Person/s
No. of Hour/s
1 4 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1
1.00 0.50 0.50 0.50
Name and Specification
Unit
Quantity
a. Steel Casing, 10 mm thk b. Oxy/Acetylene (1 set/2500 kg of Steel) c. Welding Rod (1 kg/500 kg of Steel)
m set kg.
1.025 0.163 0.814
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41- 45 mt) b. Vibro Hammer w/ Hydraulic Power Pack c. Welding Machine (500 A), Gas/Diesel Driven d. Cutting Outfit Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.33 m. E. Direct Unit Cost (C ÷ D)
F. Materials
Note: Assumed length of Steel Casing without splicing but with full weld = 12.00 meter, 2.50% additional quantity of Steel Casing represents the collar of 0.30 m for 12 m.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
179
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1052(24)f Permanent Casing (2.00 m Ø) m 1.20 m.
Designation
No. of Person/s
No. of Hour/s
1 4 6
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1 1 1 1
1.00 0.50 0.50 0.50
Name and Specification
Unit
Quantity
a. Steel Casing, 10 mm thk b. Oxy/Acetylene (1 set/2500 kg of Steel) c. Welding Rod (1 kg/500 kg of Steel)
m set kg.
1.03 0.203 1.016
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41- 45 mt) b. Vibro Hammer w/ Hydraulic Power Pack c. Welding Machine (500 A), Gas/Diesel Driven d. Cutting Outfit Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.20 m. E. Direct Unit Cost (C ÷ D)
F. Materials
Note: Assumed length of Steel Casing without splicing but with full weld = 12.00 meter, 2.50% additional quantity of Steel Casing represents the collar of 0.30 m for 12 m.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
180
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1052(25)
Splicing of RC Piles with Epoxy (400 mm x 400 mm) ea 0.50 ea
Designation
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1
1.00
Unit
Quantity
kg. set gal m
51.83 0.70 1.40 3.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41-45 mt) Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 0.50 ea E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Reinforcing Steel Bar (36 mm Ø x 1.50 m)* b. Concrete Epoxy for RC Piles (Part A & B) c. Silica Sand d. Pipe Sleeve, 50 mm Ø GI Miscellaneous (2% of Materials Cost)
Prices of materials are variable per Region/ Prices of materials are variable per District based on the prevailing unit Region/ prices in District the locality based which on the include prevailing payment unitofprices local in taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
* Depth of dowel will be as recommended by the manufacturer of epoxy resin in order to develop required pile joint strength.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
181
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1052(26)
Splicing of RC Piles with Epoxy (450 mm x 450 mm) ea 0.50 ea
Designation
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
1
1.00
Unit
Quantity
kg. set gal m
51.83 0.80 1.60 3.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Truck Mounted Crane (41-45 mt) Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 0.50 ea E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Reinforcing Steel Bar (36 mm Ø x 1.50 m)* b. Concrete Epoxy for RC Piles (Part A & B) c. Silica Sand d. Pipe Sleeve, 50 mm Ø GI Miscellaneous (2% of Materials Cost)
Prices of materials are variable per Region/ Districtofbased on the unit Region/ prices in Prices materials areprevailing variable per the locality which include payment local in District based on the prevailing unitofprices taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
* Depth of dowel will be as recommended by the manufacturer of epoxy resin in order to develop required pile joint strength.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
182
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(27)a Pile Integrity Testing (Sonic), ordinary soil condition : ea : 1.00 ea (assumed pile length = 30 m) Designation
No. of Person/s
No. of Hour/s
1 1 1
4.00 4.00 4.00
2 2
4.00 4.00
No. of Unit/s
No. of Hour/s
1
lot
1
4.00
Unit
Quantity
m kg
120.00 0.10
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer Pipe Installation a. Skilled Laborer b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Pile Integrity Testing (Sonic) and accessories (includes professional fee of Structural Engineer and reports) b. Welding Machine (500A), Electric Driven Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.00 ea E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Black/GI Pipe & acc. 2" Ø x 6 m, Schedule 20 b. Welding Rod Miscellaneous (2% of Materials Cost)
Prices of materials are variable per Region/ District based on the prevailing unit Region/ prices in Prices of materials are variable per the locality which include payment local in District based on the prevailing unitofprices taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
Note: Materials quantity component, equipment and labor output may vary proportionately depending on the pile length.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
183
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(27)b Pile Integrity Testing (PIT), ordinary soil condition : ea : 1.00 ea Designation
No. of Person/s
No. of Hour/s
1 1 1
2.00 2.00 2.00
No. of Unit/s
No. of Hour/s
1
lot
1
2.00
Unit
Quantity
pc
1.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a.Pile Integrity Testing and accessories (includes professional fee of Structural Engineer and reports) b. Grinding Machine and accessories
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.00 ea E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Grinding Disc
Prices of of materials materials are are variable Region/ Prices variable per per Region/ District based prevailing unit District based on on the the prevailing unit prices prices in in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
Note:
Materials quantity component, equipment and labor output may vary proportionately depending on the pile length.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
184
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1052(22)b High Strain Dynamic Testing (PDA), ordinary soil condition : ea : 1.00 ea (assumed pile Ø = 1.50 m) Designation
No. of Person/s
No. of Hour/s
1 2 4
4.00 4.00 8.00
No. of Unit/s
No. of Hour/s
1
lot
1 1 1 1 1 1
4.00 4.00 8.00 0.60 2.00 2.00
Unit
Quantity
m m3 kg set
3.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a.Dynamic Pile Testing (includes professional fee of Structural Engineer) b. Truck Mounted Crane (45 mt) c. Drop Hammer w/ accessories d. 1 Air Compressor w/ 2 Jack Hammer e. Concrete Vibrator f. Cutting Outfit g. Welding Machine (500A), Electric Driven Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.00 ea E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Steel Casing, L = 2 x Pile Ø, thickness = 100 mm* b. Ready Mix Concrete, 3000 psi c. Welding Rod (1 kg/500 kg of Steel) d. Oxy/Acetylene (1 kg/2500 kg of Steel) Miscellaneous (5% of Materials Cost)
5.57 2.234 0.447
Prices of materials are variable per Region/ District based on the prevailing unit Region/ prices in Prices of materials are variable per the locality which include payment local in District based on the prevailing unitofprices taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
Note:
Materials quantity component, equipment and labor output may vary proportionately depending on the pile length.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
185
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1052 (29) Micro Piles In Drilled Holes, 0.20m Ø (ordinary soil condition) m 3.00 m
Designation
No. of Person/s
No. of Hour/s
1 5 6
1.00 1.00 1.00
4 8
0.25 0.25
No. of Unit/s
No. of Hour/s
1 1 1 1 1 1 1 1 1 1 1 1
0.74 0.95 0.04 0.04 0.50 0.50 0.50 0.50 0.50 0.24 0.24 0.50
Unit
Quantity
0.033 12.626* 0.006
cu.m. kg kg
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer Fabrication of Cage Bar d. Skilled Laborer e. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
Unit Cost
Amount (PhP)
B. Equipment a. Drill Rig, Mechanical Rotary b. Truck Mounted Crane (25T) c. Bar Bender d. Bar Cutter e. Bentonite Mixer f. Bentonite Bin g. Water Pump h.Water Truck i. Welding Machine j. Tremie Pipe Set k. SPT & Desanding Machine l. Tower Light m. Minor Tools (10% of labor cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 3.00 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Ready Mix b. Reinforced Steel Bar c. Welding Rod (1kg/2000kg of RSB) d. Miscellaneous (3% of Materials, Bentonite & etc.)
G. H. I. J. K.
* Its quantity is variable depending on the actual design Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
186
Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output per hour
: :
1100(1)
15 mm Ø - 25 mm Ø Rigid Steel Conduit (RSC)/Intermediate metal Conduit (IMC)/ Electrical Metal Tubing (EMT) length 1.333 length
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.333 length E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 15 mm Ø - 25 mm Ø x 3.00 m Rigid Steel Conduit (RSC)/ Intermediate metal Conduit (IMC)/ Electrical Metal Tubing (EMT) b. Consumables (5% of Materials Cost)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. Use this cost sheet for Item Nos. 1100(1)a, 1100(1)b, 1100(1)c, 1100(2)a, 1100(2)b, 1100(2)c, 1100(4)a, 1100(4)b, and 1100(4)c.
187
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output per hour
: :
1100(1)
32 mm Ø - 40 mm Ø Rigid Steel Conduit (RSC)/ Intermediate metal Conduit (IMC)/ Electrical Metal Tubing (EMT) length 1.250 length
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.250 length E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 32 mm Ø - 40 mm Ø x 3.00 m Rigid Steel Conduit (RSC)/ Intermediate metal Conduit (IMC)/ Electrical Metal Tubing (EMT) b. Consumables (5% of Materials Cost)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. Use this cost sheet for Item Nos. 1100(1)d, 1100(1)e, 1100(2)d, 1100(2)e, 1100(4)d and 1100(4)e.
188
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output per hour
: :
1100(1)
50 mm Ø - 65 mm Ø Rigid Steel Conduit/ Intermediate metal Conduit (IMC)/ Electrical Metal Tubing (EMT) length 0.516 length
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 0.516 length E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 50 mm Ø - 65 mm Ø x 3.00 m Rigid Steel Conduit/ Intermediate metal Conduit (IMC)/ Electrical Metal Tubing (EMT) b. Consumables (5% of Materials Cost)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. Use this cost sheet for Item Nos. 1100(1)f, 1100(1)g, 1100(2)f, 1100(2)g, 1100(4)f and 1100(4)g.
189
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output per hour
: :
1100(1)
80 mm Ø - 100 mm Ø Rigid Steel Conduit (RSC)/ Intermediate metal Conduit (IMC)/ Electrical Metal Tubing (EMT) length 0.500 length
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 0.500 length E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 80 mm Ø x 3 m Rigid Steel Conduit (RSC) b. Consumables (5% of Materials Cost)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. Use this cost sheet for Item Nos. 1100(1)h, 1100(1)i, 1100(1)j, 1100(2)h, 1100(2)i, 1100(2)j, 1100(4)h, 1100(4)i, and 1100(4)j.
190
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1100(3)
15 mm Ø - 25 mm Ø Flexible Metal Conduit m 2.00 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 2.00 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 15 mm Ø - 25 mm Ø Flexible Metal Conduit b. Consumables (5% of Materials Cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%/8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1100(3)a, 1100(3)b, and 1100(3)c.
191
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
of G of G of (G + H + I) (G + H + I + J)
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1100(6)
15 mm Ø - 32 mm Ø Polyvinyl Chloride (PVC) Pipes length 3.534 length
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
length
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 3.534 length E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 15 mm Ø - 32 mm Ø x 3.00 mm Polyvinyl Chloride (PVC) Pipes b. Consumables (5% of Materials Cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%/8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1100(6)a, 1100(6)b, and 1100(6)c.
192
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
of G of G of (G + H + I) (G + H + I + J)
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1100(9)
PVC/RSC/ IMC/ EMT Conduit Fittings pc 1.00 pc
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor (Labor cost for these items shall be considered/included in the installation of conduits.)
Sub - Total for A Name and Capacity
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1.00 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Coupling/Elbow/End Bell/Clamp or others
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
193
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1100(11)
Junction/ Utility/ Pull/ Square Box pc 1.00 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1
0.40 0.40
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
A. Labor a. Skilled Laborer b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1.00 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Junction/ Utility/ Pull/ Square Box b. Consumables (3% of Materials Cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
194
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1100(10)
Conduit Works, Boxes and Fittings l.s. 1.00 l.s.
Designation
No. of Hour/s
Hourly Rate
Amount (PhP)
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
No. of Person/s
A. Labor See Derivation for Item No.1100(1) to Item No. 1100(9)
Sub - Total for A Name and Capacity B. Equipment See Derivation for Item No.1100(1) to Item No. 1100(9)
Sub - Total for B C. Total (A + B) D. Output = 1.00 l.s. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials See Derivation for Item No.1100(1) to Item No. 1100(9)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item No. 1100(1) to Item No. 1100(9).
195
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1101(1)
2
2
2
1.6 mm - 5.5 mm Electric Wire (TW/THHN/TWHN ) m 25 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 25 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 1.6 mm2 - 5.5 mm2 Electric Wire (TW/THHN/TWHN2) b. Consumables (3% of Materials Cost)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Price Monitoring Committee. Committee
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. Use this cost sheet for Item Nos. 1101(1)a1, 1101(1)a2, 1101(1)a3, 1101(1)a4, 1101(1)b1, 1101(1)b2, and 1101(1)b3.
196
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1101(1)
2
2
2
8.00 mm - 22 mm Electric Wire (TW/THHN/TWHN ) m 14.286 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 14.286 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
a. 8.00 mm2 Electric Wire (TW/THHN/TWHN2) b. Consumables (3% of Materials Cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%/8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1101(1)b4, 1101(1)b5, and 1101(1)b6.
197
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office OfficePrice Price Monitoring Committee.
of G of G of (G + H + I) (G + H + I + J)
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1101(1)
2
2
2
30.00 mm - 38 mm Electric Wire (TW/THHN/TWHN ) m 5.714 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 2 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 5.714 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 30.00 mm2 - 38 mm2 Electric Wire (TW/THHN/TWHN2) b. Consumables (3% of Materials Cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1101(1)b7 and 1101(1)b8.
198
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1101(1)
2
2
2
50.00 mm - 60 mm Electric Wire (TW/THHN/TWHN ) m 4.615 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 2 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 4.615 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 50.00 mm2 - 60mm2 Electric Wire (TW/THHN/TWHN2) b. Consumables (3% of Materials Cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1101(1)b9 and 1101(1)b10.
199
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1101(1)
2
2
2
80.00 mm - 125 mm Electric Wire (TW/THHN/TWHN ) m 2.857 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 2 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 2.857 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 80.00 mm2 - 125 mm2 Electric Wire (TW/THHN/TWHN2) b. Consumables (3% of Materials Cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%/8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1101(1)b11, 1101(1)b12and 1101(1)b13.
200
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Price Monitoring Committee
of G of G of (G + H + I) (G + H + I + J)
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1101(1)
2
2
2
150.00 mm - 250 mm Electric Wire (TW/THHN/TWHN ) m 1.875 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 4 4
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.875 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a.150.00 mm2 -250 mm2 Electric Wire 2 (TW/THHN/TWHN ) b. Consumables (3% of Materials Cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%/8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1101(1)b14, 1101(1)b15 and 1101(1)b16.
201
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
of G of G of (G + H + I) (G + H + I + J)
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1101(1)
2
2
2
325.00 mm - 400 mm Electric Wire (TW/THHN/TWHN ) m 1.60 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 4 4
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.60 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 325.00 mm2 - 400 mm2 Electric Wire (TW/THHN/TWHN2) b. Consumables (3% of Materials Cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%/8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1101(1)b17, and 1101(1)b18.
202
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
of G of G of (G + H + I) (G + H + I + J)
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) 2
Item No./Description Unit of Measurement Output per hour
2
: 1101(1)b19 500.00 mm Electric Wire (TW/THHN/TWHN ) : m : 1.333 m Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 4 4
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1.333 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 500.00 mm2 Electric Wire (TW/THHN/TWHN2) b. Consumables (3% of Materials Cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
203
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1101(2)
XLPE Electric Wires m
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor (Labor cost shall be included in the Power Contract with MERALCO or Local Power Cooperative.)
Sub - Total for A Name and Capacity
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = 0 E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. XLPE, Creosoted pole, anchor Rod, anchor log, power load studs, pad mounted transformer, pole-type transformer, transformer bracket, Aluminum Conductor Steel-Reinforced (ACSR) powerfuse, concrete pole, power transmission pole, pin insulator, pole top pin, machine bolts and washers
G. H. I. J. K.
(Materials cost included in the Power Contract with MERALCO or Local Power Cooperative.)
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
204
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1109(4)
2
2
2.00 mm - 5.5 mm Bare Copper Wire m 20.00 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 20.00 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 2.00 mm2 - 5.00 mm2 Bare Copper Wire b. Consumables (3% of Materials Cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%/8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1109(4)a, 1109(4)b and 1109(4)c.
205
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
of G of G of (G + H + I) (G + H + I + J)
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1109(4)
2
2
8.00 mm - 22.00 mm Bare Copper Wire m 10.00 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 10.00 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 8.00 mm2 - 22.00 mm2 Bare Copper Wire b. Consumables (3% of Materials Cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%/8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1109(4)d, 1109(4)e and 1109(4)g.
206
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
of G of G of (G + H + I) (G + H + I + J)
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1109(4)
2
2
30.00 mm - 38.00 mm Bare Copper Wire m 12.00 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 2 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 12.00 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 30.00 mm2 - 38.00 mm2 Bare Copper Wire b. Consumables (3% of Materials Cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1109(4)h and 1109(4)i.
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
207
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1109(4)
2
2
50.00 mm - 60.00 mm Bare Copper Wire m 10.00 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 2 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 10.00 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 50.00 mm2 - 60.00 mm2 Bare Copper Wire b. Consumables (3% of Materials Cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1109(4)j and 1109(4)k.
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
208
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1109(4)
2
2
80.00 mm - 125.00 mm Bare Copper Wire m 6.00 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 2 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 6.00 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 80.00 mm2 - 125.00 mm2 Bare Copper Wire b. Consumables (5% of Materials Cost)
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1109(4)l and 1109(4)m.
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
209
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1109(1)
2
2
200.00 mm - 250.00 mm Bare Copper Wire m 6.667 m
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 4 4
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
m
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 6.667 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 200.00 mm2 - 250.00 mm2 Bare Copper Wire b. Consumables (5% of Materials Cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
210
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1101(33)
Switches set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1
1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Skilled Laborer b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Switches
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1101(3) to 1101(14).
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
211
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output
: :
1101 (15) Single Convenience Outlet/Receptacle, Grounding Type (GT)/ Heavy Duty Convenience Outlet/Receptacle, Grounding Type (GT)/ Weather Proof Single Convenience Outlet/Receptacle, Grounding Type (GT)/ Pop-up Type/Floor Triplex Convenience Outlet/Receptacle, Grounding Type (GT) set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1
0.25 0.25
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor a. Skilled Laborer b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
a. Single Convenience Outlet/Receptacle, Grounding Type (GT)/ Heavy Duty Convenience Outlet/Receptacle, Grounding Type (GT)/ Weather Proof Single Convenience Outlet/Receptacle, Grounding Type (GT)/ Pop-up Type/Floor Triplex Convenience Outlet/Receptacle, Grounding Type (GT)
set
1.00
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. Use this cost sheet for Item Nos. 1101(17), 1101(18), 1101(23) , 1101(24)and 1101(26).
212
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output
: :
1101 (16) Duplex Convenience Outlet/Receptacle, Grounding Type (GT) / Weather Proof Duplex Convenience Outlet/Receptacle, Grounding Type (GT)/ Special Purpose Convenience Outlet/Receptacle, Grounding Type for ACU, WH, etc/ Explosion Proof Type Duplex Convenience Outlet/Receptacle, Grounding Type (GT)/ Duplex Convenience Outlet/Receptacle with Ground Fault Circuit Interupter set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1
0.30 0.30
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor a. Skilled Laborer b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Duplex Convenience Outlet/Receptacle, Grounding Type (GT) / Weather Proof Duplex Convenience Outlet/Receptacle, Grounding Type (GT)/ Special Purpose Convenience Outlet/Receptacle, Grounding Type for ACU, WH, etc/ Explosion Proof Type Duplex Convenience Outlet/Receptacle, Grounding Type (GT)/ Duplex Convenience Outlet/Receptacle with Ground Fault Circuit Interupter
set
1.00
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%/8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1101(19), 1101(20) and 1101(25).
213
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
of G of G of (G + H + I) (G + H + I + J)
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output
: :
1101 (21) Pop-up Type/Floor Single Convenience Outlet/Receptacle, Grounding Type (GT)/ Pop-up Type/Floor Duplex Convenience Outlet/Receptacle, Grounding Type (GT)/ Explosion Proof Type Single Convenience Outlet/Receptacle, Grounding Type (GT)/ Single Convenience Outlet/Receptacle with Ground Fault Circuit Interrupter set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1
0.15
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor a. Skilled Laborer b. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum Minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Pop-up Type/Floor Single Convenience Outlet/Receptacle, Grounding Type (GT)/ Pop-up Type/Floor Duplex Convenience Outlet/Receptacle, Grounding Type (GT)/ Explosion Proof Type Single Convenience Outlet/Receptacle, Grounding Type (GT)/ Single Convenience Outlet/Receptacle with Ground Fault Circuit Interupter
set
1.00
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Offiice Price
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. Use this cost sheet for Item Nos. 1101(22), 1101(23), 1101(24), 1101(25) and 1101(26).
214
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1101 (33) Wires and Wiring Devices l.s. 1.00 l.s
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor See derivation for Items 1101(1) to Item 1101(8).
Sub - Total for A Name and Capacity B. Equipment See derivation for Items 1101(1) to Item 1101(8).
Sub - Total for B C. Total (A + B) D. Output = 1.00 l.s E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials See derivation for Items 1101(1)- Item 1101(8).
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item No. 1101(1) to Item No. 1101(32)
215
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1102 (1)
Panel Board with Main Breaker/Branches, 3 wires, 1 neutral, 250 Amp - 400 Amp set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
9.00 9.00 9.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District Labor Rates are variable Region/District based on minimum wage per as approved by based on Minimum as approved DOLE. Refer to the wage Schedule of Labor by DOLE. Rates.
Note: Labor includes disassembling of Panel Board component, fabrication of hole (conduit for main breaker and branches), installation of fitting, alignment of panel board enclosure, re-installation of circuit breaker component and accessories, termination of wire, testing and commissioning.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Panel Board with Main Breaker and 8 Branches 250 amp - 400 amp b. Consumables (3% of Materials Cost)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Price Monitoring Committee. Committee
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note: 1. Additional 1 hr may be added every another 2 circuit branches, 1 hr per every additional main breaker (500-600Amp), 2 hrs per additional main breaker (800-1000Amp) and 4 hrs per additional 1200 Amp main breaker.
216
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1102 (1)
Panel Board with Main Breaker/Branches, 3 wires, 1 neutral, 50 Amp - 200 Amp set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
5.50 5.50 5.50
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
a. Panel Board with Main Breaker and 8 Branches 50 amp - 200 amp
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note: Labor includes disassembling of Panel Board component, fabrication of hole (conduit for main breaker and branches), installation of fitting, alignment of panel board enclosure, re-installation of circuit breaker component and accessories, termination of wire, testing and commissioning.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = 1 set E. Direct Unit Cost (C ÷ D)
F. Materials
b. Consumables (3% of Materials Cost)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note: 1. Additional 0.75 hr may be added every another 2 circuit branches, and deduction of 0.50 for 2 wires, 1 neutral.
217
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1102 (1)
NEMA I (Enclosed Circuit Breaker) Single Phase or Three Phase Commercial/Industrial Type set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note: Labor Includes removal of circuit breaker, Alignment, mounting and removal of hub/hole, installation of pipe/fittings, re-installation of circuit breaker, termination of wires, testing and commisioning.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. NEMA I Enclosed Circuit Breaker, plug-in or bolt type 15AT-70AT Flushed Mounted
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
218
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1102 (1)
NEMA 3R (Enclosed Circuit Breaker) Single Phase or Three Phase Commercial/Industrial Type set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
0.75 0.75 0.75
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note: Labor Includes removal of circuit breaker, Alignment, mounting and removal of hub/hole, installation of pipe/fittings, re-installation of circuit breaker, termination of wires, testing and commisioning.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. NEMA 3R Enclosed Circuit Breaker, plug-in or bolt type 15AT-70AT Flushed Mounted
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
219
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output per hour
: :
1102 (2)
Motor Control Center with main, branch breaker and motor starter (NEMA 1, NEMA 3R and 4X) Flush or Surface Mounted set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 2 2
8.00 8.00 8.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note: Labor Includes removal of circuit breaker, Alignment, mounting and removal of hub/hole, installation of pipe/fittings, re-installation of circuit breaker, termination of wires, testing and commisioning.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Motor Control Center with main, branch breaker and motor starter (NEMA 1, NEMA 3R and 4X) Flush or Surface Mounted
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
220
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output per hour
: :
1102 (16) Generator (Stand by and Continuous), Synchonizing Panel for Generator, High Voltage Switch Gear set 1 set
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor Labor by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)
Sub - Total for A Name and Capacity
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
B. Equipment Equipment Rental by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
F. Materials a. Generator (Stand by and Continuous), Synchonizing Panel for Generator, High Voltage Switch Gear
G. H. I. J. K.
Materials Cost by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
221
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output per hour
: :
1102 (1)
Main Enclosed Automatic Circuit Breaker 50 AT, 60 AT, 70 AT , 3P, 240V: NEMA I, NEMA 3R, NEMA 4x Flushed/ Surface Mounted set 1 set
Designation
Hourly Rate
Amount
No. of Person/s
No. of Hours/s
1 1 1
1.75 1.75 1.75
No of Unit/s
No. of Hour/s
Hourly Rate
Amount
Unit
Quantity
Unit Cost
Amount
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note: Labor Includes removal of circuit breaker, Alignment, mounting and removal of hub/hole, installation of pipe/fittings, re-installation of circuit breaker, termination of wires, testing and commisioning.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials Main Enclosed Automatic Circuit Breaker 50 AT, 60 AT, 70 AT , 3P, 240x: NEMA I, NEMA 3R, NEMA 4x Flushed/ Surface Mounted
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
12%9%7%6% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
222
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output
: :
1102 (1)
Main Enclosed Automatic Circuit Breaker 50 AT, 60 AT, 70 AT , 2P, 240V NEMA I, NEMA 3R, NEMA 4x Flushed/Surface Mounted set 1 set
Designation
Hourly Rate
Amount
No. of Person/s
No. of Hour/s
1 1 1
1.50 1.50 1.50
No of Unit/s
No. of Hour/s
Hourly Rate
Amount
Name and Specification
Unit
Quantity
Unit Cost
Amount
a. Main Enclosed Automatic Circuit Breaker 50 AT, 60 AT, 70 AT , 2P, 240V NEMA I, NEMA 3R, NEMA 4x Flushed/ Surface Mounted
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note: Labor Includes removal of circuit breaker, Alignment, mounting and removal of hub/hole, installation of pipe/fittings, re-installation of circuit breaker, termination of wires, testing and commisioning.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D)
F. Materials
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
12%9%7%6% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
223
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output per hour
: :
1102 (1)
Main Enclosed Automatic Circuit Breaker 100 AT, 125 AT, 205 AT , 225 AT, 3P, 240V NEMA I, NEMA 3R, NEMA 4x Flushed/ Surface Mounted set 1 set
Designation
Hourly Rate
Amount
No. of Person/s
No. of Hour/s
1 1 1
5.50 5.50 5.50
No of Unit/s
No. of Hour/s
Hourly Rate
Amount
Unit
Quantity
Unit Cost
Amount
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note: Labor Includes removal of circuit breaker, Alignment, mounting and removal of hub/hole, installation of pipe/fittings, re-installation of circuit breaker, termination of wires, testing and commisioning.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Main Enclosed Automatic Circuit Breaker 100 AT, 125 AT, 205 AT , 225 AT, 3P, 240V NEMA I, NEMA 3R, NEMA 4x Flushed/ Surface Mounted
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee
12%9%7%6% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
224
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description
:
Unit of Measurement Output per hour
: :
1102 (1)
Main Enclosed Automatic Circuit Breaker 100 AT, 125 AT, 200 AT , 2P, 225 AT, 2P, 240V NEMA I, NEMA 3R, NEMA 4x Flushed/ Surface Mounted set 1 set
Designation
Hourly Rate
Amount
No. of Person/s
No. of Hour/s
1 1 1
5.00 5.00 5.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount
Unit
Quantity
Unit Cost
Amount
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note: Labor Includes removal of circuit breaker, Alignment, mounting and removal of hub/hole, installation of pipe/fittings, re-installation of circuit breaker, termination of wires, testing and commisioning.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Main Enclosed Automatic Circuit Breaker 100 AT, 125 AT, 200 AT , 2P, 225 AT, 2P, 240V NEMA I, NEMA 3R, NEMA 4x Flushed/ Surface Mounted
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee
12%9%7%6% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
225
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1102 (1)
Low Voltage Switch Board Main 2500-4000 AT, 3P, 240V NEMA I with Breaker set 1 set
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount
A. Labor Labor by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)
Sub - Total for A Name and Capacity
No of Unit/s
No. of Hour/s
Hourly Rate
Amount
B. Equipment Equipment Rental by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
Quantity
Unit Cost
Amount
F. Materials a. Low Voltage Switch Board Main 2500-4000 AT, 3P, 240V NEMA I with Breaker
G. H. I. J. K.
Material Cost by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
12%9%7%6% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
226
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1102 (1)
Main Enclosed Automatic Breaker 250-500 Amp set 1 set
Designation
Hourly Rate
Amount
No. of Person/s
No. of Hour/s
1 2 2
12.50 12.50 12.50
No of Unit/s
No. of Hour/s
Hourly Rate
Amount
Unit
Quantity
Unit Cost
Amount
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note: Labor Includes removal of circuit breaker, Alignment, mounting and removal of hub/hole, installation of pipe/fittings, re-installation of circuit breaker, termination of wires, testing and commisioning.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Main Enclosed Automatic Breaker 250-500 Amp
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price
12%9%7%6% of G 10%8% of G 5% of (G + H + I) (G + H + I + J)
227
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1103 (1) : :
Fluorescent Lighting Fixture with Ballast /Light Emitting Diode (LED) Bulb, 1 Bulb set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
a. 1 -20Watts-40Watts flourescent lighting fixture, Box type, Diffuser type, Mirrorized Aluminum Louver, Industrial type (Recessed and Surface Mounted)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note : Labor Includes installation of scaffolding, alignment of fixtures, disassemble of lighting fixture, permanent Installation of insullation material, testing and commisioning.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1 set E. Direct Unit Cost (C ÷ D)
F. Materials
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
228
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: 1103 (1) : :
Fluorescent Lighting Fixture with Ballast /Light Emitting Diode (LED) Bulb, 2 Bulbs set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.15 1.15 1.15
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
a. 2 -20Watts-40Watts flourescent lighting fixture, Box type, Diffuser type, Mirrorized Aluminum Louver, Industrial type (Recessed and Surface Mounted)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note : Labor Includes installation of scaffolding, alignment of fixtures, disassemble of lighting fixture, permanent Installation of insullation material, testing and commisioning.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D)
F. Materials
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
229
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1103 (1)
Fluorescent Lighting Fixture with Ballast /Light Emitting Diode (LED) Bulb, 3 Bulbs set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.25 1.25 1.25
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note : Labor Includes installation of scaffolding, alignment of fixtures, disassemble of lighting fixture, permanent Installation of insullation material, testing and commisioning.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per hour = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 3-20watts-40watts flourescent lighting fixture Box type, Diffuser type, Mirrorized Aluminum Louver, Industrial type (Recessed and Surface Mounted)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
230
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1103 (1)
Fluorescent Lighting Fixture with Ballast /Light Emitting Diode (LED) Bulb, 4 Bulbs set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.50 1.50 1.50
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note : Labor Includes installation of scaffolding, alignment of fixtures, disassemble of lighting fixture, permanent Installation of insullation material, testing and commisioning.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per hour = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 4-20watts-40watts flourescent lighting fixture Box type, Diffuser type, Mirrorized Aluminum Louver, Industrial type (Recessed and Surface Mounted)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
231
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1103 (1)
Downlight/Pinlight Fixture with One- Compact Fluorecent Lamp (CFL) or LED Bulb, 1 Bulb set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note : Labor Includes installation of scaffolding, alignment of fixtures, disassemble of lighting fixture, permanent Installation of insullation material, testing and commisioning.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per Hour = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 1-8watts-21watts Downlight/Pinlight, Recessed/Surface Mounted with or without glass
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
232
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1103 (1)
Downlight/Pinlight Fixture with Two- Compact Fluorecent Lamp (CFL) or LED Bulb, 2 Bulb
set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
0.75 0.75 0.75
No of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note : Labor Includes installation of scaffolding, alignment of fixtures, disassemble of lighting fixture, permanent Installation of insullation material, testing and commisioning.
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10 % of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per hour = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 2- 8Watts-21Watts Downlight/Pinlight, Recessed/Surface Mounted with or without glass
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
233
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1103 (1)
High Bay Aluminum Reflector, Dome Luminaire set 1 set
Designation
No. of Person/s
No. of Hour/s
1 1 2
1.50 1.50 1.50
No of Unit/s
No. of Hour/s
1
1.00
Unit
Quantity
set
1.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note : Labor Includes, installation of scaffolding, alignment of lighting fixture, termination of wire, testing, commissioning and painting.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
B. Equipment a. Truck Mounted, Scissor Lift, Rough Terrain (Gas/Diesel) Minor Tools (10% of Labor Cost)
See latest ACEL rental rates.
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification
Unit Cost
Amount (PhP)
F. Materials a. High Bay Aluminum Reflector, Dome Luminaire 70Watts - 250 Watts
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
234
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1103 (1)
Die-Cast Aluminum Floodlight with Electrocoat Paint Finish set 1 set
Designation
No. of Person/s
No. of Hour/s
1 1 2
1.50 1.50 1.50
No of Unit/s
No. of Hour/s
1
1.00
Name and Specification
Unit
Quantity
a.Die-Cast Aluminum Floodlight with electrocoat paint finish 70Watts - 250 Watts
set
1.00
Hourly Rate
Amount (PhP)
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note : Labor Includes, installation of scaffolding, alignment of lighting fixture, termination of wire, testing, commissioning and painting.
Sub - Total for A Name and Capacity
Hourly Rate
Amount (PhP)
B. Equipment a. Truck Mounted, Scissor Lift, Rough Terrain (Gas/Diesel)
See latest ACEL rental raets.
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Unit Cost
Amount (PhP)
F. Materials
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/ 8% of G 5% of (G + H + I) (G + H + I + J)
235
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1103 (1)
Lighting Fixtures l.s. 1.00 l.s
Designation
No. of Person/s
No. of Hour/s
Amount (PhP)
Hourly Rate
A. Labor Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
See derivation for Item 1103(1)- Item 1103(12)
Sub - Total for A Name and Capacity
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
B. Equipment See derivation for Item 1103(1)- Item 1103(12)
Sub - Total for B C. Total (A + B) D. Output = 1.00 l.s E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials See derivation for Item 1103(1)- Item 1103(12)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Office Price Price
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item 1103(1) to Item 1103(2).
236
Part D - Electrical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: 1200(13)a Air Conditioning and Refrigiration System : l.s. : 1 l.s. Designation
No. of Person/s
No. of Hour/s
Amount (PhP)
Hourly Rate
A. Labor Labor by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)
Sub - Total for A Name and Capacity
No. of Unit/s
No. of Hour/s
Amount (PhP)
Hourly Rate
B. Equipment Equipment Rental by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)
Sub - Total for B C. Total (A + B) D. Output = 1 l.s. E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
F. Materials
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses I. Contractor's Profit (CP) J. Value Added Tax (VAT) K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1200(13)b and 1200(13)c
237
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1201(1)
Water Pumping System l.s. 1 l.s.
Designation
No. of Person/s
No. of Hour/s
Amount (PhP)
Hourly Rate
A. Labor Labor by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)
Sub - Total for A Name and Capacity
No. of Unit/s
No. of Hour/s
Amount (PhP)
Hourly Rate
B. Equipment Equipment Rental by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)
Sub - Total for B C. Total (A + B) D. Output = 1 l.s. E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
Quantity
Unit Cost
Amount (PhP)
F. Materials See Items 1201(2) - 1012(12)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
238
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1202(1)
Automatic Water Sprinkler System l.s. 1 l.s.
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
A. Labor See Derivations for Items 1202(2) to 1012(12)
Sub - Total for A Name and Capacity B. Equipment See Derivations for Items 1202(2) to 1012(12)
Sub - Total for B C. Total (A + B) D. Output = 1 l.s. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials See Derivations for Items 1202(2) to 1012(12)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
239
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1202(2)
Fire Pump with complete control and standard accessories set 1 set
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor Labor by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)
Sub - Total for A Name and Capacity
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Fire Pump, complete with reinforced concrete pad and following accessories: coupling and guard, mounted steel base plate, pump controller, flow meter autorelease valve, suction and discharge gauge, flow meter and other accessories specified in mechanical plan and specification
set
1.000
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
240
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1202(3)
Jockey Pump with complete control and standard accessories set 1 set
Designation
No. of Person/s
No. of Hour/s
Hourly Rate
Amount (PhP)
A. Labor Labor by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)
Sub - Total for A Name and Capacity
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.000
B. Equipment
Sub - Total for B C. Total (A + B) D. Output = E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Jockey Pump complete with controller and NEMA 3R and other accessories: valve, suction and discharge gauge, flow meter and other accessories specified in mechanical plan and specifications b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
241
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1202(1)
Sprinkler Head, upright/pendent/wall pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1
0.25 0.25
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
A. Labor a. Construction Foreman b. Skilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Sprinkler Head, upright/pendent/wall b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
242
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1202(1)
Alarm Check Valve pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
4.00 4.00 4.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Alarm Check Valve b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
243
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1202(1)
Flow Meter pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
3.00 3.00 3.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Flow meter b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
244
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1202(1)
OS & Y Gate Valve 175 psi pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
3.00 3.00 3.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. OS & Y Gate Valve 175 psi b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
245
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1202(1)
Pressure Gauge pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1
0.50 0.50
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
A. Labor a. Construction Foreman b. Skilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Pressure Gauge b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
246
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1202(1)
Pressure Relief Valve pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
3.00 3.00 3.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Pressure Relief Valve b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
247
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1202(1)
Floor Control Valve pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
3.00 3.00 3.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Pressure Relief Valve b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
248
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1202(1)
Inspector Test Valve pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
0.75 0.75 0.75
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Inspector Test Valve b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
249
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1202(1)
Inspector Test Connection pc 1 pc
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
6.00 6.00 6.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
pc
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1 pc E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Inspector Test Connector b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
250
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1202(1)
25 mm Ø - 50 mm Ø Black Iron (B.I.) Pipe and Fittings length 0.80 length
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
length
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note : Straight line installation, ceiling height of upto 3.5m. Labor output includes setting, scafolding, cutting, fixing of pipe from elbow, tee, flange, valve and painting.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = 0.80 length E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 25 mm Ø - 50 mm Ø x 6.00 m Black Iron (B.I.) Pipe and Fittings b. Consumables (5% of material cost)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. Use this cost sheet for Item Nos. 1202(4)a1, 1202(4)a2, 1202(4)a3 and 1202(4)a4.
251
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1202(1)
65 mm Ø -150 mm Ø Black Iron (B.I.) Pipe and Fittings length 0.75 length
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
length
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Note : Straight line installation, ceiling height of upto 3.5m. Labor output includes setting, scafolding, cutting, fixing of pipe from elbow, tee, flange, valve and painting.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = 0.75 length E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 65 mm Ø -150 mm Ø x 6.00 m Black Iron (B.I.) Pipe and Fittings b. Consumables (5% of material cost)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. Use this cost sheet for Item Nos. 1202(4)a5, 1202(4)a6, 1202(4)a7 and 1202(4)a8.
252
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
1202(1)
Fittings pc
Designation
No. of Hour/s
Hourly Rate
Amount (PhP)
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
No. of Person/s
A. Labor Labor cost for these items are considered in the installation of pipes
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per Hour = 0 E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. B.I. 90 elbow/B.I. Tee/ Bell Reducer/ Blind Flange/ Slip Flange/ Riser Nipple/ Threadolet/ Pipe Sleeve
pc
1.00
b. Consumables (5% of material cost)
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G I. Contractor's Profit (CP) 10%/8% of G J. Value Added Tax (VAT) 5% of (G + H + I) K. Total Unit Cost (G + H + I + J) Note : 1. Use this cost sheet for Item Nos. 1202(4)b, 1202(4)c, 1202(5)a, 1202(5)b, 1202(6)a, 1202(6)b, 1202(7)a, 1202(8)a and 1202(9)a.
253
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1202(7)
Fire Hose Valve siames 150 mm Ø x 2 w x 65 mm Ø with cap set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 2
3.00 3.00 3.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Fire Hose Valve siames 150 mm Ø x 2 w x 65 mm Ø with cap b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
254
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1202(5)
Fire Hose Cabinet set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1 1 1
1.00 1.00 1.00
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Fire Hose Cabinet b. Consumables (5% of material cost)
G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Expenses Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
15%/ 12%/ 10%/ 8% of G 10%/8% of G 5% of (G + H + I) (G + H + I + J)
255
Part E - Mechanical
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
1202(a1)
Fire Extinguisher set 1 set
Designation
Hourly Rate
Amount (PhP)
No. of Person/s
No. of Hour/s
1
0.50
No. of Unit/s
No. of Hour/s
Hourly Rate
Amount (PhP)
Unit
Quantity
Unit Cost
Amount (PhP)
set
1.00
A. Labor a. Unskilled Laborer
Labor Rates are variable per Region/District based on minimum wage as approved by DOLE. Refer to the Schedule of Labor Rates.
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Fire Extinguisher
G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% I. Contractor's Profit (CP) 10%/8% J. Value Added Tax (VAT) 5% K. Total Unit Cost Note : 1. Use this cost sheet for Item Nos. 1202(a2), 1202(a3), 1202(a4), and 1202(a5)
256
Prices of materials are variable per Region/ District based on the prevailing unit prices in the locality which include payment of local taxes and hauling cost to the project site. Refer to the Construction Material Price Data established quarterly by Central Price Monitoring Committee.
of G of G of (G + H + I) (G + H + I + J)
Part E - Mechanical
DERIVATION OF THE DUPA COST SHEET CALCULATION OF PRODUCTIVITY OUTPUT 1. Set the output that you will measure. Works completed are useful aid for the computation of the output productivity if it could be quantified well. 2. Create a gang composed of a combination of Skilled Laborers and Unskilled Laborers and/or Equipment that will be used. 3. Set a monitoring period and monitor activities that are relative to the Item of work e.g., for Item 1003(1) – Ceiling Works relative works are the installation of frames and installation of boards. 4. Divide the total output by the input to get the productivity output.
CALCULATION OF MATERIALS FACTORS 1. Set the total quantity of work to be considered. 2. Estimate all the materials necessary for that certain output. Consider 5% waste factor. 3. Divide each material component by the total quantity of work. Table 1.0 Derivation of DUPA 1. Quantity = 63 sq.m. 2. Materials a. 4.5mm Fiber Cement Board/ 4.5 mm Marine Plywood/ 6 mm Marine Plywood/ 6mm Ordinary Plywood b.Metal Furring (size variable on plan and and specifications ) 3m length c. Carrying Channels d. Hanger Bars/Rod e. Channel clip f. Wall Angle g. Rivets h. 1" Metal Screw
TOTAL QTY
UNIT
FACTOR
23
pcs
0.365
71.25
pcs
1.131
22.5 63 378 15 882 252
pcs pcs pcs pcs pcs pcs
0.357 1.000 6.000 0.238 14.000 4.000
3. Labor a. Construction Foreman b. Skilled Laborer c. Unskilled Laborer
ACTIVITIES 1. Installation of metal frames
1 1 2
DURATION OF ACTIVITIES (in hrs) 28.4 22.28
2. Installation of Boards 50.68 hrs
CEILING WORKS
Production Output: Quantity of Work = 63 square meter = 1.243 sq.m./hr Time 50.68 hrs
257
258
SECTION C COSTING OF SUPPORT EQUIPMENT
259
260
C. 1 Guidelines in Considering Support Equipment (Lifting Equipment) for Construction of High-Rise Buildings In this manual, outputs in the DUPA were adjusted to compensate the difficulty of work (e.g. concrete works) for the construction of High-Rise Building. In cases where items of work shall need support equipment (lifting equipment) to finish the work, this manual provides guidelines in costing of such. Unlike with the construction of low-rise buildings, construction of high-rise buildings requires vertical transportation of resources (i.e. materials, labor, and equipment) in the construction site. Typically, vertical transportation is mainly achieved by the use of temporary lifting hoist, tower cranes and concrete pumping systems. Thus, this support equipment shall be included in the cost of the project as separate pay item of work. For this manual, it is suggested that the following costs shall be considered in the DUPA of Support Equipment: 1. 2. 3. 4.
Rental Rate of the Equipment Installation and Dismantling Cost Operation and Maintenance Cost Mobilization and Demobilization
In considering Support Equipment as separate item of work, choosing the most cost-efficient model/capacity and proper planning in the utilization are the major factors that affect the cost of the project. Different models/capacity have different costs, thus, choosing the right capacity and model will be beneficial for the project. Consideration in choosing the right equipment for costing in all your project may be guided by the following: 1. Resources to be lifted. It should be determined what resources shall be transported by the support equipment, be material, workers and/or equipment. Passenger hoists are preferably used to transport workers to the designated construction floor level. However, if considering that the construction elevator shall be used to deliver both materials and people, the estimator shall check the volume/weight of people versus the materials to be delivered. In cases wherein vast volume of building parts, construction materials (e.g. wide flanges, reinforcing bars, or even concrete) and equipment are required to be delivered vertically on the construction site, tower cranes are recommended to be utilized in the project.
261
2. Range, Height, and Weight Requirement Another factor to be considered is the range, height and weight requirement of the equipment to be utilized. The estimator should consider how to attain optimum resources delivery on the project. Temporary construction elevators/hoists are used to lift resources on a fixed point of the construction site, thus require manual efforts to move resources horizontally. Unlike construction elevators/hoists, tower cranes are more versatile since resources can be transported vertically and horizontally at the project site. Take into considerations that the equipment will be supported by the structure as the building rises, thus, coordination with the structural designer shall be undertaken. To use tower cranes, the following factors should be considered: Maximum free-standing height of the crane Maximum braced height of the crane Weight, dimensions, lift height and radius of the heaviest loads 3. Safety Regulations and other Local Ordinances Utilization of these equipment may cause safety hazards not only within the construction premises but also with the surrounding environment. Such hazards are crush and falling hazard. To mitigate such risk, most of the local government units requires assemble and dismantling plan as well as strict safety certification. For example in utilizing tower cranes, maximum height and possible available headroom which can be developed are need to be considered specially to areas near airports. Another vital factor which affects the cost for the support equipment is the duration of usage of the equipment. It requires proper planning when such equipment will be utilized. For example, during the structural works, tower cranes may be used in lifting structural members, RSB and even delivery of fresh concrete by the used of buckets. However, during lifting of materials involved in the architectural works, construction elevator/hoist are more likely being used. It is also recommended to haul materials for interior works prior to enclosure of the building perimeter. As a requirement in the approval of POW/DUPA and ABC, Project Schedule may be an aid for the estimator in determining the duration of usage of the equipment.
262
SECTION D CALCULATION OF CYCLE TIME FOR HAULING EQUIPMENT
263
264
E. COMPUTATION OF LABOR RATES E.1 BASIS OF COMPUTATION The estimated labor rates for each region/district office were computed in accordance with D.O. 40, Series of 2009, Re: Guidelines for the establishment of Construction Materials Price Data, Standard Labor and Equipment Rental Rates (or latest issuance), and based on the minimum wage rate as published by the National Wages and Productivity Commission, Department of Labor and Employment (DOLE). The computed labor rates including all component costs such as basic wage plus emergency cost of living allowance (ECOLA) and worker's statutory monetary benefits and others are in accordance with the existing laws and government regulations. It shall be updated as the need arises based on the latest issuances for new minimum wages by the NWPC/DOLE and/or any amendments to the benefits of the workers. E.2 CONDITIONS IN THE USAGE OF THE LABOR RATES CASE I - In cases where project/s traverse/s certain barangays, municipalities, towns or cities (with varying labor rates) of a concerned DEO, the average labor cost of the said places shall be utilized by the DEO. CASE II - In cases wherein project/s traverse/s certain provinces within the jurisdiction of only one (1) Regional Office, the average labor cost of the said Regional Office shall be utilized. CASE III - In cases wherein project/s passes numerous provinces within the jurisdiction of two (2) or more Regional Offices, the average labor cost of the said Regional Office with the longest work coverage or with largest major scope of works shall be utilized.
265
266
E.3 SAMPLE TABULATION OF LABOR RATES DPWH - NCR LOCATION : Cities of Caloocan, Las Piñas, Makati, Malabon, Mandaluyong, Manila, Marikina, Muntinlupa, Navotas, Parañaque, Pasay, Pasig, Quezon, San Juan, Taguig and Valenzuela and the Municipality of Pateros DATE OF ESTIMATE : February 2015 RESOURCE 13TH RATE BASIC WAGE SOCIAL BENEFITS LABOR COST DESCRIPTION LEAVES CODE MONTH PER FACTOR NO. DAILY MONTHLY PAY SSS/EC PHILHEALTH PAG-IBIG MONTH 1 2 3 4 5 6 7 8 9
Foreman Leadman Heavy Equipment Operator Highly Skilled Labor Light Equipment Operator Driver Skilled Labor Semi-skilled Labor Unskilled Labor
1.80 1.65 1.50 1.50 1.40 1.30 1.30 1.20 1.00
838.80 768.90 699.00 699.00 652.40 605.80 605.80 559.20 466.00
20,970.00 19,222.50 17,475.00 17,475.00 16,310.00 15,145.00 15,145.00 13,980.00 11,650.00
838.80 768.90 699.00 699.00 652.40 605.80 605.80 559.20 466.00
1,747.50 1,601.88 1,456.25 1,456.25 1,359.17 1,262.08 1,262.08 1,165.00 970.83
1,090.00 1,090.00 1,090.00 1,090.00 1,090.00 1,090.00 1,090.00 999.30 822.70
NOTE: Minimum Wage Rate Basic Daily Compensation
= PhP 466.00 = Minimum Wage multiplied by the Labor Cost Index of each category
Leaves (Service Incentive Leave/ Maternity/Paternal)
= Basic Daily Wage * 25 days per month* 12/300 days
Bonus, 13th Month Pay SSS Contribution Philhealth Pag-Ibig Employer's Compensation Contribution Monthly Rate Daily Rate Hourly Rate
= = = = = = = =
Basic Monthly Wage / 12 Graduated Amount Representing Employee's Contribution Graduated Amount Representing Employee's Contribution 2% of Basic Monthly Compensation below P5,000.00 and P100.00 above P5,000.00 P 10.00 Basic Monthly Wage + Leaves + 13th Month Pay + Social Benefits Monthly Rate / 25 days per month Daily Rate / 8 h per day
250.00 237.50 212.50 212.50 200.00 187.50 187.50 162.50 137.50
100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
24,996.30 23,020.78 21,032.75 21,032.75 19,711.57 18,390.38 18,390.38 16,966.00 14,147.03
RATE PER DAY
RATE PER HOUR
999.85 920.83 841.31 841.31 788.46 735.62 735.62 678.64 565.88
124.98 115.10 105.16 105.16 98.56 91.95 91.95 84.83 70.74
268
SECTION F EQUIPMENT RENTAL RATES
269
270
F. EQUIPMENT RENTAL RATES Rental of equipment presented in the Detailed Unit Price Analysis (DUPA) are based on the prevailing “Association of Carriers and Equipment Lessors, (ACEL) Inc.” rental rates approved for use by the DPWH (Presently it is the 2014 ACEL Rates). Rental rates of equipment not indicated in the ACEL booklet shall be taken from the rental rates prepared by the Bureau of Equipment. For simplicity in computation, the operated rental rates are preferred over the bare rental rates as the former includes operator’s wages, fringe benefits, fuel, oil, lubricants and equipment maintenance. F.1
List of equipment adopted in the standard DUPA with make, model and capacity DESCRIPTION
1. Earthmoving Equipment 1.1 Bulldozer 1.2 Payloader 1.3 Motorized Road Grader 2. Compaction Equipment 2.1 Plate Compactor 3. Lifting Equipment 3.1 Crawler Crane 3.2 Crawler Crane 3.3 Crawler Crane 3.4 Truck Mounted Crane 3.5 Truck Mounted Crane 3.6 Truck Mounted Crane 3.7 Truck Mounted, Scissor Lift, Terrain 4. Excavating Equipment 4.1 Backhoe 4.2 Backhoe w/ Breaker 4.3 Backhoe, Wheel Mounted 4.4 Portable Breaker 5. Foundation Equipment 5.1 Diesel Hammer 5.2 Vibro Hammer Vibro Hammer w/ Hydraulic Power 5.3 Pack 5.4 Vibro Hammer 5.5 Drilling Rig 6 Concreting Equipment 6.1 Concrete Screeder 6.2 Concrete Paver 6.3 One Bagger Mixer 6.4 Transit Mixer 7 Hauling Equipment 7.1 Dump Truck 7.2 Cargo/Service Truck 7.3 Boom Truck 7.4 Cargo/Service Truck 7.5 Water Truck/Pump 8 Air Equipment 8.1 8.2 8.3 8.4 8.5 8.6 8.7
Air Compressor Air Compressor Air Compressor, Portable Air Compressor Diamond Drill Jackhammer Pneumatic Drilling Machine
FLYWHEEL HORSEPOWER
MODEL
CAPACITY
D6H SERIES II PSDS/DD LX80-2C G710A
1.50 m /1.95 yd
3
3
400-500 Gasoline Engine All Models All Models All Models All Models All Models All Models Gas/Diesel Driven
21-25 mt 36-40 mt 41-45 mt 20-25 mT 31-35 mt 41-45 mt
165 110 140
PhP PhP PhP
3,379.00 1,733.00 2,173.00
5
PhP
123.00
145 190 190 200 238 246
PhP PhP PhP PhP PhP PhP PhP
1,522.00 1,902.00 2,151.00 1,631.00 1,861.00 2,606.00 1,386.00
99 99 50 4
PhP PhP PhP PhP
1,537.00 1,998.10 922.00 129.38
40 ft hts x 46 ft range
SE 130 LC-2 0.80 m3/1.04 yd3 3 3 SE 130 LC-2 0.80 m /1.04 yd 3 3 PW60N-1 0.28 m /0.37 yd WACKER PORTABLE PETROL BREAKER, BHF30S
RENTAL RATE
K25 - DSL DPD600T Hydraulic Pile Driver
7500 kg-m 60 ton
201
PhP PhP
1,286.00 2,123.00
MHF12 w/ Hyd Power Pack
120 kN-m
222
PhP
4,118.00
VIBRO FONCEUR, PTC25H1A
45000 kg-m
272.22
PhP
3,069.00
300
PhP
12,637.00
5.50
175
PhP PhP PhP PhP
545.00 6,765.00 172.00 1,318.00
C.M.V. TH18/65, 200 mm Ø 65 m depth & 18000 kg-m Drill Torque Wacker Truss Screed COMMANDER III, FOUR-TRACK All Models
4-6 ft3/min 5-6 yd3
All Models All Models All Models All Models All Makes
12 yd 2-5 mt 2-5 mt 9-10 mt 16000 L
290 160 160 270 360
PhP PhP PhP PhP PhP
1,420.00 783.00 1,017.90 1,212.00 2,450.00
356-450 cfm 161-185 cfm 120-160 cfm 15-35 cfm
130 69 51 20
PhP PhP PhP PhP PhP PhP PhP
965.00 502.00 450.00 205.00 201.25 150.00 170.00
All All All All
Models Models Models Models CP-8
271
3
DESCRIPTION 9 Pumping Equipment 9.1 Water Pump, 100 mm suction Ø 9.2 Water Pump, 100 mm suction Ø 9.3 Pumpcrete DESCRIPTION 10 Power Generating Equipment 10.1 Generator Set 10.2 Generator Set DESCRIPTION 11 Shop Equipment 11.1 Welding Machine 11.2 Welding Machine DESCRIPTION 12 Special Support Equipment 12.1 Chainsaw 13. Miscellaneous Equipment 13.1 Concrete Vibrator 13.2 Bar Cutter 13.3 Bar Bender 14. Others
OUTPUT/DISCHARGE (lpm)
SOLID SIZE FLYWHEEL CAPACITY (mm) HORSEPOWER
2,667 1,800
50
16 7.50 CAPACITY
MODEL
kW
kVA
All Makes All Makes
301-350 kW 700 kW
375 875
MODEL
AMPERES
FLYWHEEL HORSEPOWER
Electric Driven/DC Output Gas/Diesel Driven
500 300
MODEL
CAPACITY
48 FLYWHEEL HORSEPOWER
RENTAL RATE
PhP PhP PhP
266.25 123.38 2,076.00
RENTAL RATE PhP PhP
872.87 2,147.27
RENTAL RATE
PhP PhP
391.00 371.00
RENTAL RATE
HUSQVARNA 2100 CD with CR22, 7 ft Reach, 9 in Standard Blade
PhP
75.36
Flexible Shaft Type 2" Head Ø with 5 Amperes Gasoline Drive Unit 25 mm Maximum Rebar Ø (Grade 40), Single Phase 25 mm Maximum Rebar Ø, Three Phase
PhP PhP PhP
91.25 219.75 351.50
20 mt
PhP PhP PhP
5,000.00 1,265.00 45.45
PhP
65,000.00
Pile Integrity Testing & accessories 14.5 (includes professional fee of Strcutural Engineer and reports)
PhP
37,000.00
Dynamic Pile Testing 14.6 (includes professional fee of Structural Engineer)
PhP
103,000.00
14.1 Drop Hammer w/ accessories 14.2 1 Air Compressor w/ 2 Jack Hammer 14.3 Cutting Outfit Pile Integrity Testing (Sonic) & accessories 14.4 (includes professional fee of Strcutural Engineer and reports)
14.7 Lighting System/Tower Lights 14.8 14.9 15 15.1
Tower Height = 28 ft, No. of Lights = 4 x 1000 watts, hp = 10.50 Generator = 5 kW
PhP PhP PhP PhP
Bentonite Bin Bentonite Mixer SPT & Desanding Machine Tremie Pipe Set DESCRIPTION
16 Tower Crane 16.1 Topless 16.2 Topless 16.3 Topless 16.4 Topless 16.5 Topless 16.6 Topless
Tower Tower Tower Tower Tower Tower
Crane Crane Crane Crane Crane Crane
PhP
MODEL
CAPACITY
MDT 98-1.2M MDT 128 MDT 132 G8 MDT 162 H8 MDT 178 MDT 192 - H12
55M x 6T/1.2T 55M x 6T/1.6T 55M x 8T/1.6T 60M x 8T/ 1.8T 60M x 8T/ 1.5T 60M x 12T/ 2.2T
272
FLYWHEEL HORSEPOWER
543.50 280.00 173.00 559.00 320.00
RENTAL RATE PhP PhP PhP PhP PhP PhP
4,221.00 5,664.00 8,605.00 8,895.00 6,419.00 8,390.00