Detailed analysis for huge and voluminous pours Total Total Production Placement Average Capacity, Total Capacity, Total of pour of Production of Placement Description in Sr.No. Concrete, Capacity, Concrete, Capacity, Remarks of location Cubic put to use % age put to use % age meter in Cubic utilization in Cubic utilization per hour meter per meter per hour hour Work carried TG Raft 1 110 30.15 60 55.28 33.17 out by Unit No.5 M/s GDC Work TG Raft carried 2 120 33.93 100 40.72 40.72 Unit No.6 out by M/s SIL Work TG Raft carried 3 120 38.02 100 45.63 45.63 Unit No.8 out by M/s SIL Work Boiler carried 4 Foundation 110 21.11 60 38.70 23.22 out by Unit No.5 M/s GDC Work Boiler carried 5 Foundation 110 29.72 120 27.24 32.69 out by Unit No.7 M/s GDC