Cronogramas De Valorizado De Obra 1 2.xls

  • Uploaded by: ELISBER MISAEL VARGAS CRUZ
  • 0
  • 0
  • April 2020
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Cronogramas De Valorizado De Obra 1 2.xls as PDF for free.

More details

  • Words: 12,319
  • Pages: 31
I. GENERALIDADES 1.1

Datos Generales de la Obra 1.1.1 Generalidades

Unidad Gestora

: #REF!

Unidad Ejecutora

: VICEMINISTERIO DE VIVIENDA Y URBANISMO

Función

:

Programa

:

Sub Programa

:

Proy. y/o Actividad

:

Meta

:

Oficina de Supervisión

: PROGRAMA NACIONAL DE VIVIENDA RURAL

1.1.2 Datos de la Obra Nombre de la Obra

: #REF!

Codigo SNIP

:

Ppto Aprobado Perfil Técnico

:

Resol. de aprob. de Exp.Tecnico

:

Resol. de aprobación de Bases

:

Financiamiento

:

Modalidad del Contrato

:

Modalidad del Concurso

:

Fecha de concurso

:

Monto de Presupuesto Base

: S/. 0.00

Fecha de presupuesto base

: Dec-99

Antigüedad valor referencial

#VALUE!

< a 6 meses

1.1.3 Datos del Contrato de Obra Adjudicación de Buena Pro

:

Contrato Nº

:

Contratista

:

Domicilio legal del contratista

:

de fecha

Representante Legal 0.00%

Participación de Empresas Consorciadas -

:

0.00%

-

:

0.00%

-

:

-

:

Monto del presupuesto Contratado

: #REF!

Fecha de suscripción de contrato

:

Plazo de ejecución

:

Fecha de entrega de terreno

:

30-Dec-99

Fecha de Inicio contractual de obra

:

30-Dec-99

Fecha prevista de conclusión

:

30-Dec-99

1ra Paralización de Obra

:

Desde

30-Dec-99

Hasta el

30-Dec-99

2da Paralización de Obra

:

Desde

30-Dec-99

Hasta el

30-Dec-99

3ra Paralización de Obra

:

Desde

30-Dec-99

Hasta el

30-Dec-99

4ta Paralización de Obra

:

Desde

30-Dec-99

Hasta el

30-Dec-99

1ra Ampliación de Plazo

:

0 D.C.

RES

2da Ampliación de Plazo

:

0 D.C.

RES

3ra Ampliación de Plazo

:

0 D.C.

RES

Con IGV. Días calendario

30-Dec-99

4ta Ampliación de Plazo

:

0 D.C.

RES

5ta Ampliación de Plazo

:

0 D.C.

RES

Fecha de termino contractual

:

Monto Adel. directo y fecha INC/IGV.

:

S/. 0.00

#REF!

fecha:

30-Dec-99

Monto Adel. para Mater. Nº 1 INC/IGV.

:

S/. 0.00

#REF!

fecha:

30-Dec-99

Monto Adel. para Mater. Nº 2 INC/IGV.

:

S/. 0.00

#REF!

fecha:

30-Dec-99

Monto Adel. para Mater. Nº 3 INC/IGV.

:

S/. 0.00

#REF!

fecha:

30-Dec-99

30-Dec-99

PRESUPUESTO OFERTADO POR FORMULA :

S/. 0.00

:

S/. 0.00

:

S/. 0.00

:

S/. 0.00

:

S/. 0.00

:

S/. 0.00 S/. 0.00 S/. 0.00

Total costo directo

:

S/. 0.00

Gastos Generales fijos

:

0.00%

S/. 0.00

Gastos Generales Variables

:

0.00%

S/. 0.00

Utilidad

:

0.00%

S/. 0.00

Sub. Total

:

Factor de Relación

:

1.00000

S/. 0.00

I. G. V.

:

18.00%

S/. 0.00

Total

:

S/. 0.00

S/. 0.00

PRESUPUESTOS ADICIONALES Y DEDUCTIVOS Adicional de obra No 01 INC/IGV.

:

Resolución

:

Detalle

:

Adicional de obra No 02 INC/IGV.

:

Resolución

:

Detalle

:

Adicional de obra No 03 INC/IGV.

:

Resolución

:

Detalle

:

Adicional de obra No 04 INC/IGV.

:

Resolución

:

Detalle

:

Adicional de obra No 05 INC/IGV.

:

Resolución

:

Detalle

:

Adicional de obra No 06 INC/IGV.

:

Resolución

:

Detalle

:

Adicional de obra No 07 INC/IGV.

:

Resolución

:

Detalle

:

Adicional de obra No 08 INC/IGV.

:

Resolución

:

Detalle

:

Deductivo de obra No 01 INC/IGV.

:

Resolución

:

Detalle

:

Deductivo de obra No 02 INC/IGV. Resolución

: :

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

S/. 0.00 fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

Detalle Deductivo de obra No 03 INC/IGV.

: :

Resolución

:

Detalle

:

Deductivo de obra No 04 INC/IGV.

:

Resolución

:

Detalle

:

Deductivo de obra No 05 INC/IGV.

:

Resolución

:

Detalle

:

Deductivo de obra No 06 INC/IGV.

:

Resolución

:

Detalle

:

Deductivo de obra No 07 INC/IGV.

:

Resolución

:

Detalle

:

Deductivo de obra No 08 INC/IGV.

:

Resolución

:

Detalle

:

Total modificaciones de obra

:

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

S/. 0.00 fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

MAYORES GASTOS GENERADOS EN EJECUCION DE OBRA Reconocimiento de mora Firma Contrato

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Comp.Gastos incump. entrega terreno

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Reconocimiento Mayores G.G. prorroga 01

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Reconocimiento Mayores G.G. prorroga 02

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Reconocimiento Mayores G.G. prorroga 03

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Reconocimiento Mayores G.G. prorroga 04

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Reconocimiento Mayores G.G. prorroga 05

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 01

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 02

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 03

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 04

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 05

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 06

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 07

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 08

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 09

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 10

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 11

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 12

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

TOTAL MAYORES GASTOS

S/. 0.00

Otras resoluciones: -

: RES

fecha:

30-Dec-99

-

: RES

fecha:

30-Dec-99

-

: RES

fecha:

30-Dec-99

-

: RES

fecha:

30-Dec-99

MONTO DE LA INVERSION CON IGV

:

S/. 0.00

1.1.4 Datos del personal de Empresa Contratista

INGRESO

TERMINO

Residente de Obra

:

30-Dec-99

30-Dec-99

Residente de Obra

:

30-Dec-99

30-Dec-99

Residente de Obra

:

30-Dec-99

30-Dec-99

Asistente de obra

:

30-Dec-99

30-Dec-99

Administrador de obra

:

30-Dec-99

30-Dec-99

Prevencionista seguridad

:

30-Dec-99

30-Dec-99

Especialista en acabados

:

30-Dec-99

30-Dec-99

Instalaciones Sanitarias

:

30-Dec-99

30-Dec-99

Instalaciones Eléctricas

:

30-Dec-99

30-Dec-99

Instalaciones Especiales

:

30-Dec-99

30-Dec-99

:

30-Dec-99

30-Dec-99

:

30-Dec-99

30-Dec-99

Resoluciones de nombramiento -

: RES

fecha:

00/00/0000

-

: RES

fecha:

00/00/0000

-

: RES

fecha:

00/00/0000

-

: RES

fecha:

00/00/0000

-

: RES

fecha:

00/00/0000

-

: RES

fecha:

00/00/0000

-

: RES

fecha:

00/00/0000

:

30-Dec-99

30-Dec-99

:

fecha:

30-Dec-99

:

30-Dec-99

30-Dec-99

:

fecha:

30-Dec-99

:

30-Dec-99

30-Dec-99

:

fecha:

30-Dec-99

de fecha

30-Dec-99

1.1.5 Datos del Inspector de obra de la Entidad Contratante Inspector de Obra Resolución Inspector de Obra Resolución Inspector de Obra Resolución

1.1.6 Datos del Contrato de Supervisión de obra Proceso de Selección

:

Adjudicación de Buena Pro

: 30-Dec-99

Contrato Nº

:

Fuente de Financiamiento

:

Consultor

:

Domicilio legal del consultor de obra

:

Representante Legal

: 0.00%

Participación de Empresas Consorciadas -

:

0.00%

-

:

0.00%

-

:

0.00%

Valor Referencial

:

Monto Contratado:

:

Factor de Relación

:

Sistema de Contratación:

: 0

Plazo de Ejecución

:

S/. 0.00 Con IGV. S/. 0.00 Con IGV. #DIV/0! 0 D.C.

Correspondiente a ejecución de obra

0 D.C.

Correspondiente a liquidación de obra

Fecha de Inicio contractual

:

30-Dec-99

Fecha prevista de conclusión

:

30-Dec-99

1ra Paralización de Obra

:

Desde

30-Dec-99

Hasta el

30-Dec-99

2da Paralización de Obra

:

Desde

30-Dec-99

Hasta el

30-Dec-99

3ra Paralización de Obra

:

Desde

30-Dec-99

Hasta el

30-Dec-99

4ta Paralización de Obra

:

Desde

30-Dec-99

Hasta el

30-Dec-99

1ra Ampliación de Plazo

:

0 D.C.

RES

2da Ampliación de Plazo

:

0 D.C.

RES

3ra Ampliación de Plazo

:

0 D.C.

RES

4ta Ampliación de Plazo

:

0 D.C.

RES

5ta Ampliación de Plazo

:

0 D.C.

RES

Fecha de termino contractual

:

Monto Adel. directo y fecha INC/IGV.

:

30-Dec-99 S/. 0.00

#REF!

fecha:

30-Dec-99

PRESUPUESTOS ADICIONALES Y DEDUCTIVOS Adicional de consultoría No 01 INC/IGV.

:

Resolución

:

Detalle

:

Adicional de consultoría No 02 INC/IGV.

:

Resolución

:

Detalle

:

Adicional de consultoría No 03 INC/IGV.

:

Resolución

:

Detalle

:

Adicional de consultoría No 04 INC/IGV.

:

Resolución

: 0

Detalle

:

Adicional de consultoría No 05 INC/IGV.

:

Resolución

:

Detalle

:

Adicional de consultoría No 06 INC/IGV.

:

Resolución

:

Detalle

:

Adicional de consultoría No 07 INC/IGV.

:

Resolución

:

Detalle

:

Adicional de consultoría No 08 INC/IGV.

:

Resolución

:

Detalle

:

Deductivo de consultoría No 01 INC/IGV.

:

Resolución

:

Detalle

:

Deductivo de consultoría No 02 INC/IGV.

:

Resolución

:

Detalle

:

Deductivo de consultoría No 03 INC/IGV.

:

Resolución

:

Detalle

:

Deductivo de consultoría No 04 INC/IGV.

:

Resolución

:

Detalle

:

Deductivo de consultoría No 05 INC/IGV.

:

Resolución

:

Detalle

:

Deductivo de consultoría No 06 INC/IGV.

:

Resolución

:

Detalle

:

Deductivo de consultoría No 07 INC/IGV.

:

Resolución

:

Detalle

:

Deductivo de consultoría No 08 INC/IGV.

:

Resolución

:

Detalle

:

Total modificaciones del servicio consultoría

:

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

#DIV/0!

S/. 0.00 fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

fecha:

30-Dec-99

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

MAYORES GASTOS GENERADOS EN EJECUCION DE OBRA Reconocimiento de mora Firma Contrato

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Comp.Gastos incump. entrega terreno

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 01

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 02

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 03

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 04

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 05

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 06

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 07

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 08

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 09

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 10

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 11

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

Intereses por Mora, INC/IGV Valorización 12

:

#DIV/0!

S/. 0.00

fecha:

30-Dec-99

TOTAL MAYORES GASTOS

S/. 0.00

Otras resoluciones: -

: RES

fecha:

30-Dec-99

-

: RES

fecha:

30-Dec-99

-

: RES

fecha:

30-Dec-99

-

: RES

fecha:

30-Dec-99

MONTO DEL SERVICIO CONSULTOIRA

:

1.1.7 Datos del personal profesional de la Consultoría de obra

S/. 0.00

con IGV

INGRESO

TERMINO

Jefe de Supervisión

:

30-Dec-99

30-Dec-99

Jefe de Supervisión

:

30-Dec-99

30-Dec-99

Jefe de Supervisión

:

30-Dec-99

30-Dec-99

Asistente de Supervisión

:

30-Dec-99

30-Dec-99

Asistente de Supervisión

:

30-Dec-99

30-Dec-99

Asistente de Supervisión

:

30-Dec-99

30-Dec-99

Arquitecto

:

30-Dec-99

30-Dec-99

Arquitecto

:

30-Dec-99

30-Dec-99

Arquitecto

:

30-Dec-99

30-Dec-99

Especialista en estructuras

:

30-Dec-99

30-Dec-99

Especialista en estructuras

:

30-Dec-99

30-Dec-99

Especialista en estructuras

:

30-Dec-99

30-Dec-99

Ingeniero Electricista

:

30-Dec-99

30-Dec-99

Ingeniero Electricista

:

30-Dec-99

30-Dec-99

Ingeniero Electricista

:

30-Dec-99

30-Dec-99

Especialista en instalaciones sanitarias

:

30-Dec-99

30-Dec-99

Especialista en instalaciones sanitarias

:

30-Dec-99

30-Dec-99

Especialista en instalaciones sanitarias

:

30-Dec-99

30-Dec-99

-

:

30-Dec-99

30-Dec-99

-

:

30-Dec-99

30-Dec-99

-

:

30-Dec-99

30-Dec-99

-

:

30-Dec-99

30-Dec-99

-

:

30-Dec-99

30-Dec-99

-

:

30-Dec-99

30-Dec-99

Resoluciones de nombramiento -

: RES

fecha:

30-Dec-99

-

: RES

fecha:

30-Dec-99

-

: RES

fecha:

30-Dec-99

-

: RES

fecha:

30-Dec-99

-

: RES

fecha:

30-Dec-99

-

: RES

fecha:

30-Dec-99

-

: RES

fecha:

30-Dec-99

1.2 Ubicación de la Obra Proyecto Ubicación

#REF! Región

CUSCO

Departamento

CUSCO

Provincia

CANAS

Distrito

CANAS

Localidad Linderos Frente

Trocha carrozable

Fondo

via proyectada

Izquierda

via proyectada

Derecha

via proyectada

1.3 Descripción del Proyecto.

0

0

0

0

0

0

#REF! VICEMINISTERIO DE VIVIENDA Y URBANISMO PROGRAMA NACIONAL DE VIVIENDA RURAL

#REF!

Contrato Obra #REF! Ubicación

#REF! #REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

March-19 #REF! VICEMINISTERIO DE VIVIENDA Y URBANISMO PROGRAMA NACIONAL DE VIVIENDA RURAL

#REF!

Contrato Obra #REF! Ubicación

#REF! #REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

March-19 #REF! VICEMINISTERIO DE VIVIENDA Y URBANISMO PROGRAMA NACIONAL DE VIVIENDA RURAL

#REF!

Contrato Obra #REF! Ubicación

#REF! #REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

March-19

#REF! VICEMINISTERIO DE VIVIENDA Y URBANISMO

PROGRAMA NACIONAL DE VIVIENDA RURAL

CONTENIDO ITEM

DESCRIPCION

1

Carta del Jefe de Supervision

2

Carta de Contratista

3

Iforme de Supervision de obra

4

Prestacion ADICIONAL DE OBRA

5

Formula Polinomica Adiconal de Obra

6

Acta de Pactacion de Precios

7

Precios de insumos

8

Fletes

9

Deductivo de Obra No 01

10

Consultas de Obras

11

Respuesta a Consultas

12

Item No 02

Prestación Adicional de Obra No 01

13

Item No 03

Prestación Adicional de Obra No 01

14

Item No 04

Prestación Adicional de Obra No 01

15

Item No 05

Prestación Adicional de Obra No 01

16

Item No 06

Prestación Adicional de Obra No 01

17

Item No 07

Prestación Adicional de Obra No 01

18

Item No 08

Prestación Adicional de Obra No 01

19

Item No 09

Prestación Adicional de Obra No 01

20

Item No 10

Prestación Adicional de Obra No 01

21

Item No 11

Prestación Adicional de Obra No 01

22

Item No 12

Prestación Adicional de Obra No 01

23

Item No 13

Prestación Adicional de Obra No 01

24

Item No 14

Prestación Adicional de Obra No 01

PAGINAS

RELACION PARTIDAS #REF!

#REF! #REF!

#REF!

#REF! #REF! #REF!

#REF! #REF! #REF!

#REF! RESIDENTE: Código

No PARTIDA

Grupo

No Partida

DESCRIPCION

UND #REF!

0 0 1 1 1

PRESUPUESTO DE OBRA

OE.1.3.1 OE.1.3.1.1 OE.2.2.1.2 OE.2.2.1.12

PXXX P04010090 P04010270

OE.1.1.9

P02030000

1

TRAZOS NIVELES Y REPLANTEO

OE.1.1.9.1

P02032000

1

TRAZOS NIVELES Y REPLANTEO PRELIMINAR

OE.1.1.9.1.1 OE.2.5

P02032020 P08000000

2 2

TRAZO, NIVELES Y REPLANTEO PRELIMINAR

OE.2.5.2

P08011000

OE.2.5.2.1

P08011020

OE.2.5.3

P08012000

OE.2.5.3.1

P08012020

OE.2.5.4

P08013000

OE.2.5.4.1 OE.2.6

P08013020 P09000000

OE.2.6.1

P09010000

OE.2.6.1.1

P09010020

O.E.3.3

P11058140

O.E.3.4

P12060000 P02510760

O.E.3.4.2.16

P12069500

O.E.3.4.2.15.1

P12069520

O.E.3.7

P18000000

O.E.3.7.1

P18001000

O.E.3.7.1.1

P18001090

O.E.3.7.2

P18002000

O.E.3.7.2.5

P18002050

O.E.3.9

P20040000

O.E.3.9.1

P20041000

O.E.3.9.1.2 O.E.3.9.1.7

P20041020 P20041070

O.E.3.9.2

P20042000

O.E.3.9.2.4

P20042040

O.E.3.10

P21050000

O.E.3.10.4.2

P21054120

O.E.3.11

P22010000

O.E.3.11.2

P22015000

O.E.3.11.2.4

P22015160

O.E.3.11.3

P22020000

O.E.3.11.3.5 ITEM 15 O.E.8.1.1 O.E.8.1.2

P22020180

O.E.8.1.3 O.E.3.2 O.E.3.2.16

02

08 08 08

09

P11050000

O.E.3.3.6.2.7 OE.2.1.1.2.2

04 04 04

11 02 12

18 18

KIT DE CAPACITACION KIT DE CAPACITACION POR BENEFICIARIO SUBCIMIENTO MEZCLA 1:12 + 30 % P.G. CIMIENTOS CORRIDOS, ENCOF. Y DESENCOF.

2

ESTRUCTURAS DE MADERA VIGAS

3

VIGAS DE MADERA 3"X6"X10`

3

TIJERALES Y RETICULADOS

4

TIJERALES DE EUCALIPTO (ROLLISOS)

4

CORREAS

5 5

CORREAS DE MADERA

5

COBERTURAS COBERTURA DE PLANCHAS CORRUGADAS GALVANIZADAS

6

COBERTURA CALAMINA Nº 30, 11 CANALES

6

CIELORRASOS

7

FALSO CIELO RASO TERMICO CON POLIESTIRENO Y TRIPLAY

7

PISOS Y PAVIMENTOS

8

NIVELACION Y APISONADO MANUAL DE TERRENO

8

MADERA MACHIHEMBRADA

9

MACHIHEMBRADO MAD.3/4"X4" DURMIENTE 2"X3"

9

CARPINTERIA DE MADERA

9

PUERTAS

10

PUERTA CN C/TABLEROS MAD. PINO

10

VENTANAS

11

VENT. CN S/SEG. V4 (1.5X1.4), OCTOGONO

11

CERRAJERIA

UND M3 M2

M2

PZA UND P2

M2 M2 M2 M2

M2 M2

11

BISAGRAS

12 13

BISAGRA ALUMIN. DE 3.5" PESADA EN PUERTAS BISAGRA ALUMIN. DE 2" PESADA EN VENTANAS

13

CERRADURAS

14

CERRADURA PARA PUERTA INTERIOR DOBLE PERILLA

14

VIDRIOS CRISTALES Y SIMILARES

15

VIDRIOS DOBLES IMPORTADO

15

PINTURA

15

PINTURA DE PUERTAS

16

PINTURA BARNIZ EN PUERTAS DE MADERA

16

PINTURA DE VENTANAS PINTURA BARNIZ EN VENTANAS DE MADERA FLETE

M2

P30020000 P30020500

17 17 18 19

FLETE NEC FLETE NE

GLB GLB

P30020600 P10030000 P10039000

20 20 20

FLETE RURAL TAMBO A VIVIENDA

GLB

20

ENLUCIDO DE YESO SOBRE MUROS DE ADOBE

20

ENLUCIDO DE YESO.- MUROS DE ADOBE

20 20 20 21

22 22

P10039500

O.E.3.2.16.1.1

P10039520

O.E.3.5

P13080000

20

ZOCALOS Y CONTRAZOCALOS

O.E.3.5.1

P13081000

20

ZOCALOS

O.E.3.5.1.4.1

P13081910

20

ZOCALO DE CEMENTO SOBRE MURO DE ADOBE H=90CM

OE.2.1.2 OE.2.1.2.2 OE.2.1.2.2.6

P03000000 P03011000 P03011140

13

03

PZA P2

M2

REVOQUES Y REVESTIMIENTOS ENLUCIDO DE YESO

O.E.3.2.16.1

10

PZA PZA

#VALUE! EXCAVACIONES #VALUE! EXCAVACIONES SIMPLES #VALUE! EXCAV.ZANJAS Y ZAPATA Rt < 2 kg/cm2 h = 1.00 m

M2

M3

CHEK

RELACION PARTIDAS #REF!

#REF! #REF!

#REF!

#REF! #REF! #REF!

#REF! #REF! #REF!

#REF! RESIDENTE: Código

No PARTIDA

O.E.3.1 O.E.3.1.12 O.E.3.1.12.1

P09011000 P09022500 P09022520

OE.2.5.2 OE.2.5.2.1 OE.2.2.6.1

P08011000 P08011020 P04020040

Grupo

P29000000 P29012000 P29015100

UND

09

M2 M2

08 04

#VALUE! VIGAS-DINTELES #VALUE! DINTEL DE MADERA #VALUE! SOBRECIMIENTO, CONCRETO 1:8 + 25% P.M.

PZA M3

0

OE.4.5 P28000000 OE.4.5.1.1 P28011000 OE.4.5.1.1.1.1 P28012100

DESCRIPCION

0 MUROS Y TABIQUES DE ALBAÑILERIA #VALUE! MUROS DE ADOBE (SIMPLE O ESTABILIZADO) #VALUE! MURO DE ADOBE e=0.40 cm

O.E.7

OE.5 OE.5.2 OE.5.2.1.2.1

No Partida

OTROS LIMPIEZA DE OBRA FINAL

GLB

28

0 0 0

SISTEMA DE DRENAJE PLUVIAL CANALETAS CANALETA DE FIERRO GALVANIZADO Y TUBERIA PVC 3" P/LLUVIAS

GLB

29

0 0 0

INSTALACIONES ELECTRICAS SALIDAS PARA ALUMBRADO, TOMACORRIENTES INSTALACIONES ELECTRICAS INTERIORES

GLB

CHEK

RELACION PARTIDAS #REF!

#REF! #REF!

#REF!

#REF! #REF! #REF!

#REF! #REF! #REF!

#REF! RESIDENTE: Código

No PARTIDA

Grupo

No Partida

DESCRIPCION

UND

CHEK

PARTIDA MODELO FECHA:

31-May-13

PROYECTO: PROPIETARIO: CONSULTOR:

MEJORAMIENTO Y FORTALECIMIENTO DE LA CARRERA PROFESIONAL DE INGENIERIA AGROPECUARIA EN CHUMB

Código

---

XXX

UNSAAC ING. JOSE LUIS ROZAS LATORRE PARTIDA

Cod

ORIGEN

RNC Partida

PXXX

XX

No

#REF! XXXX XXXX XXXX #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

---

#REF!

DESCRIPCION

UND

M3

MODULOS - AGRUPAMIE

TO

UND

TO

UND

I

II

III

G-I-AI

1

2

3

4

5

6

1.00

0.00

0.00

0.00

0.00

1.00

UBICACIÓN: SUPERVISOR: RESIDENTE:

RIA EN CHUMBIVILCAS PRESUPUESTO BASE

ULOS - AGRUPAMIENTO MODULOS

PRESUPUESTO OFERTADO

TOTAL

TOTAL

TOTAL

MET

P.U. BASE

SUB TOTAL

OC

0

0

0

0

DED

ADC

3 al 11

BASE

S/. S/IGV

S/. S/IGV

7

8

9

10

11

14

15

16

17

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

SANTO TOMAS - CHUM ING. FREDDY PEZO AC Hugo Martinez

-

0.00

METRADO

P.U.

MAT

MO

S/. S/IGV

S/. S/IGV

S/. S/IGV

6 0.00

#REF!

#REF!

#REF!

TOMAS - CHUMBIVILCAS - CUSCO EDDY PEZO ACURIO

OFERTADO

TANTEO

PRESUPUESTO MINIMO

PRESUPUESTO MINIMO OFC

REQUERIMIENTO

EQ

SUB TOTAL

P.U.

SUB TOTAL

P.U.

SUB TOTAL

P.U.

SUB TOTAL

METRADO

S/. S/IGV

S/. S/IGV

S/. S/IGV

S/. S/IGV

S/. S/IGV

S/. S/IGV

S/. S/IGV

S/. S/IGV

REQUERIMIENTO

S/. S/IGV

#REF!

#REF!

#REF!

#REF!

#REF!

-

-

#REF!

0.00

0.00

1.00

REQUERIMIENTO

DIFERENCIA

DIFERENCIA

DIFERENCIA

REQUERIMIENTO PTO OFERTADO - PTO OFERTADO - PTO OFERTADO S/. S/IGV #REF!

#REF!

PTO MINIMO OFC -

PTO MINIMO OFC

PTO BASE.

#REF!

#REF!

#REF!

#REF!

Rendimiento Rendimiento Rendimiento Rendimiento MINIMO

5.00

MIN OFC

5.00

1.1

RENDIMIENTO

CP

5.50

5.00

OP

OF

EN USO

TANTEO

5.00

0.10

1.00

1.00

ANALISIS DE COSTOS UN PROYECTO: PROPIETARIO: UBICACIÓN: SUPERVISOR:

PROGRAMACION OBRA DURACION DIAS PE

PERSONAL EN OBRA CUAD

5.00

-

OP

5.00

OF

-

-

ACT

-

-

UNSAAC SANTO TOMAS - CHUMBIVILCAS - CUSCO

ING. FREDDY PEZO ACURIO

 

No

PE

MEJORAMIENTO Y FORTALECIMIENTO DE LA CARRERA PROFESIONA

CODIGO

INSUMO

0 XXX

XXXX XXXX XXXX

0

Rendimiento (M3 /día) INSUMO Materiales mat 1 mat 2 mat 3 mat 4 mat 5 Mano de obra CAPATAZ OPERARIO OFICIAL PEON Equipo HERRAMIENTA equ 1 equ 2 equ 3

0 CODIGO 0 0 0 0 0 0 0 M 0 470100000 0 470200000 0 470300000 0 470400000 0 E 0 480900000 0 0 0 0

UND

CUADRILLA

5.00 CUADRILLA

0.10 1.00 1.00 5.00 %MO 1.00 1.00 1.00

STOS UNITARIOS

RA PROFESIONAL DE INGENIER

FECHA:

BLOQUEAR PRECIOS

31-May-13 ADMINISTRACION DIRECTA ====>

ING. JOSE LUIS ROZAS LATORRE

PRECIOS EXPEDIENTE ====>

Hugo Martinez

SELECCIÓN DEL COSTO ====>

S/. S/IGV CANTIDAD

PRECIO

PARCIAL

SUB_TOTAL

REQ_MAT

Metrado CANTIDAD

PRECIO

S/. S/IGV PARCIAL

0.4200 0.8500 0.1840 9.7400 8.6930

#REF! #REF! #REF! #REF! #REF!

#REF! #REF! #REF! #REF! #REF!

0.1600 1.6000 1.6000 8.0000

#REF! #REF! #REF! #REF!

#REF! #REF! #REF! #REF!

3.0000 1.6000 1.6000 1.6000

#REF! 6.35 4.52 12.60

#REF! 10.16 7.23 20.16

#REF! SUB_TOTAL #REF!

REQ_MAT

Metrado

0.00 REQ_MAT

1.00 REQ_MAT

0.00 0.00 0.00 0.00 0.00

0.42 0.85 0.18 9.74 8.69

0.00 0.00 0.00 0.00

0.16 1.60 1.60 8.00

#REF! 0.00 0.00 0.00

#REF! 1.60 1.60 1.60

#REF!

#REF!

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

N S X PRECIO  EXPEDIENTE

TOTAL

EST ARQ SAN ELE

CONSULTOR: RESIDENTE:

PRECIO ACTUAL

FECHA  INSUMO

DEL 

MAT

S/. S/IGV S/. S/IGV S/. S/IGV

S/. S/IGV

--#REF!

#REF!

#REF!

#REF! #REF! #REF! #REF! #REF!

#REF! #REF! #REF! #REF! #REF!

#REF! #REF! #REF! #REF! #REF!

#REF! #REF! #REF! #REF!

#REF! #REF! #REF! #REF!

#REF! #REF! #REF! #REF!

#REF! #REF! #REF!

#REF! #REF! #REF!

#REF! #REF! #REF!

#REF!

MO

#REF!

EQ

#REF!

OBSERVACIONES

TANTEO

0.00 CUADRILLA

INFES

CANTIDAD

CANTIDAD

CUADRILLA

CANTIDAD

5.00 CUADRILLA

CANTIDAD

5.00 CUADRILLA

CANTIDAD

0.4200 0.8500 0.1840 9.7400 8.6930 0.10 1.00 1.00 5.00

#DIV/0! #DIV/0! #DIV/0! #DIV/0! 3.0000 0.8000 0.8000 0.8000

REGION CUSCO

CUADRILLA

0.4200 0.8500 0.1840 9.7400 8.6930 0.10 1.00 1.00 5.00

0.1600 1.6000 1.6000 8.0000 3.0000 0.8000 0.8000 0.8000

0.4200 0.8500 0.1840 9.7400 8.6930 1.00 1.00 5.00 0.00

1.6000 1.6000 8.0000 0.0000 3.0000 0.8000 0.8000 0.8000

ACTUAL ACUMULADO SALDO

XXXXX CUADRILLA

CANTIDAD

YYYY CUADRILLA

CANTIDAD

ZZZZZ CUADRILLA

CANTIDAD

REQUERIMIENTO

1

MONTO REQUERIDO S/. S/IGV

METRADO ACUMULADO

MONTO ACUMULADO S/. S/IGV

SALDO

ACM REQ 1.00

#REF!

1.00

#REF!

-1.00###

REQUERIMIENTO

REQUERIMIENTOREQUERIMIENTOREQUERIMIENTOREQUERIMIENTOREQUERIMIENTOREQUERIMIENTOREQUERIMIENTOREQUERIMIENTOREQUERIMIENTO

S

COSTO

TOTAL

M de Obra

M de Obra

#REF!

#REF!

SUB CONTRATO

COSTO

COSTO

SUB CONTRATO

SUB CONTRATO

MIN

COSTO

TOTAL

%

FORMULAS  PRECIO  EXPEDIENTE

FORMULAS  RENDIMIENTO  USO

EN 

0.00

SUB CONTRATO SUB CONTRATO MAX

MONTO  REQUERIDO  X INSUMO TOTAL

DIF.REDOND

chek

DIF.CU

0.00

#REF!

-

0.00%

#REF!

0.00

0.00

0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00

#REF! #REF! #REF! #REF! #REF!

0.00 0.00 0.00 0.00

#REF! #REF! #REF! #REF!

#REF! #REF! #REF! #REF!

0.00 0.00 0.00 0.00

#REF! 0.00 0.00 0.00

#REF! -10.16 -7.23 -20.16

#REF!

0.00 0.00 0.00 0.00 #REF! #REF! #REF! #REF! #REF! 0.00 #REF! #REF! #REF! #REF! 0.00 #REF! 10.16 7.23 20.16 0.00

Err:520

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Err:520

0.00 0.00 0.00 0.00 0.00 0 10.00 100.00 100.00 500.00 0 #REF! 100.00 100.00 100.00

M 100000 200000 300000 400000 E 900000

PXXX

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO #REF!

Periodo Item

Descripción

Und.

Metrado

P.U.

Parcial

MES 01 AVANCE MENSUAL

Mes Metrado

01 01.01 01.01.01 01.01.02 01.02

BOCATOMA TIPO BARRAJE N°01 (01 UND)

01.02.01

TRABAJOS PRELIMINARES

01.02.01.01 01.02.02

und

1.00

1,283.13

1,283.13

glb

1.00

1,837.18

1,837.18

1.000 1.000

TRAZO Y REPLANTEO PARA BOCATOMA

m2

30.55

10.58

323.22

0.000

01.02.02.01

MOVIMIENTO DE TIERRAS EXCAVACION MANUAL EN TERRENO CONGLOMERADO

m3

30.51

25.75

785.63

01.02.02.02

RELLENO CON MATERIAL PROPIO Y COMPACTADO

m3

2.90

11.06

32.07

01.02.02.03

ELIMINACION DE MATERIAL EXCEDENTE

m3

35.23

8.58

302.27

30.510 2.900 35.230

01.02.03 01.02.03.01

OBRAS DE CONCRETO SIMPLE SOLADO PARA BOCATOMA e=3" OBRAS DE CONCRETO ARMADO

m2

30.18

31.33

945.54

ACERO DE REFUERZO fy=4,200 kg/cm2

kg

340.00

4.43

1,506.20

m3

2.98

237.46

707.63

01.02.04.03

CONCRETO CICLOPEO f'c=175 kg/cm2 + 30% PM ENCOFRADO Y DESENCOFRADO EN MUROS

m2

79.28

33.96

2,692.35

01.02.04.04

CONCRETO f'c=175 kg/cm2 CON MEZCLADORA

m3

11.57

450.09

5,207.54

01.02.04.05 01.02.05

EMBOQUILLADO DE CONCRETO f'c=175 kg/cm2

m3

2.15

308.63

663.55

01.02.05.01

TARRAJEO CON IMPERMEABILIZANTE 1:3 E=1.5CM TARRAJEO CON MORTERO EXTERIOR 1:5 E= 1.50 Cm

m2

56.74

37.60

2,133.42

01.02.05.02

m2

27.92

17.98

01.02.06

INSTALACION DE ACCESORIOS Y OTROS

01.02.06.01 01.02.06.02

REJILLA EN LA VENTANA DE CAPTACION (0.3*0.30 M)DE 3/8"

und und

1.00 1.00

01.03

DESARENADOR Nº01 (01 UND) TRABAJOS PRELIMINARES

01.02.04.02

01.03.01 01.03.01.01

Parcial

MES 02 AVANCE MENSUAL % Avance Metrado

Parcial

MES 03 AVANCE MENSUAL Parcial

MES 04 AVANCE MENSUAL Parcial

MES 05 AVANCE MENSUAL

% Avance

Metrado

% Avance

Metrado

% Avance

Metrado

100% 100%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

0 0

0% 0%

0 0

Parcial

#REF! MES 06 AVANCE MENSUAL

% Avance

Metrado

0% 0%

0 0

Parcial

% Avance

0% 0%

CONSTRUCCIÓN DEL SISTEMA DE RIEGO POR ASPERSIÓN TOTORA OBRAS PROVICIONALES CARTEL DE OBRA DE 3.60 X4.80 MTS CAMPAMENTOS EN GENERAL

01.02.04 01.02.04.01

S/.

CREACION DE ESPACIOS DE RECREACION MULTIUSOS EN EL SECTOR DE LAUPAY DEL CP. CCOCHA Y LA C. HUANCA UMUYTO DEL , DISTRITO DE HAQUIRA - COTABAMBAS - APURIMAC

1,283.13 1,837.18

323.22

0%

0.00

0%

0.00

0%

0

0%

1

100%

0

0%

100% 100% 100%

0.00 0.00 0.00

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0 0 0

0% 0% 0%

0 0 0

0% 0% 0%

0 0 0

0% 0% 0%

0.000

0%

0.00

0%

0.00

0%

0

0%

0

0%

30.180019151

945.54

100%

0.000 0.000 0.000 0.000 0.000

0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0%

0 0 0 0 0

0% 0% 0% 0% 0%

0 0 0 0 0

0% 0% 0% 0% 0%

340 2.979996631 79.280035336 11.569997112 2.1499854194

1,506.20

100% 100% 100% 100% 100%

0.000 0.000

0% 0%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

0 0

0% 0%

0 0

0% 0%

56.739893617 27.919911012

2,133.42

502.00

72.86 364.13

72.86 364.13

0.000 0.000

0% 0%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

0 0

0% 0%

0 0

0% 0%

1 1

72.86 364.13

100% 100%

785.63 32.07 302.27

707.63 2,692.35 5,207.54 663.55

REVOQUES Y ENLUCIDOS

COMPUERTA TIPO IZAJE marc.0.30x1.15 mts, Planch .25x.0.75 mts e=1/4"

502

100% 100%

TRAZO Y REPLANTEO PARA DESARENADOR MOVIMIENTO DE TIERRAS

m2

18.30

4.45

81.44

0.000

0%

0.00

0%

0.00

0%

0

0%

0

0%

18.301123596

81.44

100%

01.03.02 01.03.02.01

EXCAVACION MANUAL EN MATERIAL SUELTO

m3

11.49

14.72

169.13

EXCAVACIÓN MANUAL EN TERRENO CONGLOMERADO

m3

1.96

26.25

51.45

01.03.02.03 01.03.02.04

RELLENO CON MATERIAL PROPIO Y COMPACTADO

m3 m3

5.68 11.14

12.18 8.58

69.18 95.58

0.000 0.000 0.000 0.000

0% 0% 0% 0%

0.00 0.00 0.00 0.00

0% 0% 0% 0%

0.00 0.00 0.00 0.00

0% 0% 0% 0%

0 0 0 0

0% 0% 0% 0%

0 0 0 0

0% 0% 0% 0%

11.489809783 1.96 5.6798029557 11.13986014

169.13

01.03.02.02

95.58

100% 100% 100% 100%

m2

6.44

60.73

391.10

0.000

0%

0.00

0%

0.00

0%

0

0%

0

0%

6.4399802404

391.1

100%

kg m2

168.96 32.59

4.29 33.64

724.84 1,096.33

3.63

413.43

1,500.75

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0 0 0

0% 0% 0%

0 0 0

0% 0% 0%

168.96037296 32.590071344 3.6299978231

724.84

m3

0.000 0.000 0.000

100% 100% 100%

m2

6.59

17.98

118.49

15.92

37.60

598.59

0.000 0.000

0% 0%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

0 0

0% 0%

0 0

0% 0%

6.5901001112 15.919946809

118.49

m2 und und

1.00 2.00

377.56 139.19

377.56 278.38

1.00

771.83

771.83

und

1.00

132.74

132.74

0% 0% 0% 0%

0.00 0.00 0.00 0.00

0% 0% 0% 0%

0.00 0.00 0.00 0.00

0% 0% 0% 0%

0 0 0 0

0% 0% 0% 0%

0 0 0 0

0% 0% 0% 0%

1 2 1 1

377.56

und

0.000 0.000 0.000 0.000

0.000 0.000

0% 0%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

0 0

0% 0%

0 0

0% 0%

1259 1259

503.6

0% 0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0%

0 0 0 0 0 0

0% 0% 0% 0% 0% 0%

0 0 0 0 0 0

0% 0% 0% 0% 0% 0%

604.32023061 1139 1139 152 377.7 38.08974359

11,530.43

326.81

100% 100% 100% 100% 100% 100%

164.96

100%

81,939.66

364.1

100% 100% 100% 100% 100%

01.03.03

ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE

01.03.03.01

SOLADO PARA DESARENADOR E=3"

01.03.04

OBRAS DE CONCRETO ARMADO

01.03.04.01 01.03.04.02

ACERO DE REFUERZO fy=4,200 kg/cm2

01.03.04.03 01.03.05 01.03.05.01

ENCOFRADO Y DESENCOFRADO EN MUROS CONCRETO f'c=175 kg/cm2 CON MEZCLADORA TARRAJEO CON MORTERO 1:5 E= 2.00 Cm TARRAJEO CON IMPERMEABILIZANTE 1:3 E=1.5CM

01.03.06

INSTALACION DE ACCESORIOS Y OTROS

01.03.06.01 01.03.06.02

COMPUERTA TIPO IZAJE marc.0.25x1.28 mts, Planch .25x.1.0 mts e=1/4"

01.03.06.03 01.03.06.04

VALVULA MARIPOSA TIPO WAFER DE FIERRO DUCTIL DE 110MM CANASTILLA PVC DE 250MM A 250 mm C/ANILLO

01.04

LINEA DE CONDUCCIÓN A PRESIÓN TUB. 220mm (1259.00 m)

01.04.01 01.04.01.01

TRABAJOS PRELIMINARES LIMPIEZA DEL TERRENO MANUAL

m

1,259.00

0.40

503.60

01.04.01.02

TRAZO Y REPLANTEO TOPOGRAFICO DE LA LINEA DE CONDUCCIÓN MOVIMIENTO DE TIERRAS

m

1,259.00

0.35

440.65

m3

604.32

19.08

11,530.43

01.04.02.02

EXCAVACION MANUAL EN ROCA SUELTO REFINE Y NIVELACION ZANJA PARA TUBERIA

m

1,139.00

0.53

603.67

01.04.02.03

CAMA DE APOYO ZARANDEADO PARA TUBERIA E=0.10M

m

1,139.00

0.74

842.86

01.04.02.04

RELLENO CON MATERIAL ZARANDEADO Y COMPACTADO

m3

152.00

11.03

1,676.56

01.04.02.05 01.04.02.06

RELLENO CON MATERIAL PROPIO Y COMPACTADO

m3 m3

377.70 38.09

11.40 8.58

4,305.78 326.81

0.000 0.000 0.000 0.000 0.000 0.000

m3

1.20

137.47

164.96

0.000

0%

0.00

0%

0.00

0%

0

0%

0

0%

1.1999709027

m m

1,139.00 100.00

71.94 17.02

81,939.66 1,702.00

0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0%

0 0 0 0 0

0% 0% 0% 0% 0%

0 0 0 0 0

0% 0% 0% 0% 0%

1139 100 1 11 2

0%

0.00

0%

0.00

0%

0

0%

0

TAPA METALICA 0.80X0.80X1/8"

01.04.03

ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE

01.04.03.01

CONCRETO SIMPLE PARA DADO DE ANCLAJE

01.04.04

SUMINISTRO E INSTALCION DE TUBERIA Y ACCESORIOS PVC SAP

01.04.04.01 01.04.04.02

INSTALACION DE TUBERIA PVC SAP NTO ISO-399.002 (C-7.5) de Ø 200 mm

und

2.00

182.05

364.10

01.04.05

CODO PVC ISO C-7.5 UF DE 200 mm X 45º C/ANILLO PRUEBA HIDRAULICA

0.000 0.000 0.000 0.000 0.000

01.04.05.01

PRUEBA HIDRAULICA

m

1,259.00

0.39

491.01

0.000

01.05 01.05.01

PASE AEREO L=44.00 (01 UND)

01.04.04.03 01.04.04.04 01.04.04.05

INSTALACIÓN DE TUBERIA PVC SAP NTP ISO-1452 (C-7.5) de Ø 90mm TUBERIA HDPE DN 200 ISO 4427 CODO PVC ISO C-7.5 UF DE 200 mm X 22.5º C/ANILLO

glb und

1.00 11.00

10,336.50 182.05

10,336.50 2,002.55

m2

23.23

4.43

102.91

0.000

0%

0.00

0%

0.00

0%

0

0%

0.4999514

01.05.02

TRAZO Y REPLANTEO PARA PASE AEREO MOVIMIENTO DE TIERRAS

01.05.02.01

EXCAVACION MANUAL EN TERRENO CONGLOMERADO

m3

28.52

17.17

489.69

RELLENO CON MATERIAL PROPIO Y COMPACTADO

m3 m3

11.10 24.55

11.06 8.58

122.77 210.64

0.000 0.000 0.000

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0 0 0

0% 0% 0%

0.489575 1 1

239.74

01.05.02.02 01.05.02.03 01.05.03

OBRAS DE CONCRETO SIMPLE SOLADO PARA ZAPATAS e=3"

1,500.75

598.59

278.38 771.83 132.74

440.65

603.67 842.86 1,676.56 4,305.78

1,702.00 10,336.50 2,002.55

100% 100% 100% 100% 100% 100%

100% 100%

0%

1259

491.01

100%

50%

11.616252822

51.46

ELIMINACION DE MATERIAL EXCEDENTE

122.77 210.64

50%

49% 100% 100%

14.557367501 0 0

249.95

51% 0% 0%

100% 100%

0 0

0% 0%

0 0 0

0% 0% 0%

12.65 5.40

32.38 394.64

409.61 2,131.06

0.000 0.000

0% 0%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

0 0

0% 0%

1 1

01.05.04

CONCRETO CICLOPEO f'c=175 kg/cm2 + 30% PM OBRAS DE CONCRETO

m2 m3

409.61

01.05.04.01

CONCRETO f'c=210 kg/cm2 CON MEZCLADORA

m3

4.10

467.78

1,917.90

ENCOFRADO Y DESENCOFRADO EN MUROS

m2

54.20

32.28

1,749.58

01.05.04.03 01.05.05

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0 0 0

0% 0% 0%

1 1 1

1,917.90

01.05.04.02

2,163.48

100% 100% 100%

381.18

100%

0

0%

1

01.05.03.01 01.05.03.02

1,096.33

TRABAJOS PRELIMINARES 51.45

01.05.01.01

69.18

REVOQUES Y ENLUCIDOS

01.03.05.02

01.04.02 01.04.02.01

51.45

ACERO DE REFUERZO fy=4,200 kg/cm2

kg

488.37

4.43

2,163.48

0.000 0.000 0.000

01.05.05.01

REVOQUES Y ENLUCIDOS TARRAJEO CON MORTERO EXTERIOR 1:5 E= 1.50 Cm

m2

21.20

17.98

381.18

0.000

0%

0.00

0%

0.00

0%

0

0%

1

01.05.06

INSTALACION DE ACCESORIOS Y OTROS

01.05.06.01

ACCESORIOS PARA PASE AEREO

glb

1.00

18,011.79

18,011.79

0.000

0%

0.00

0%

0.00

0%

0

0%

0

01.06 01.06.01

PASE AEREO L=25.00 (01 UND) TRABAJOS PRELIMINARES TRAZO Y REPLANTEO PARA PASE AEREO

2,131.06

1,749.58

0% 18,011.79

100%

m2

5.48

4.43

24.28

0.000

0%

0.00

0%

0.00

0%

0

0%

1

24.28

100%

0

0%

EXCAVACION MANUAL EN TERRENO CONGLOMERADO RELLENO CON MATERIAL PROPIO Y COMPACTADO

m3

5.63

17.17

96.67

m3

1.94

11.06

21.46

01.06.02.03

ELIMINACION DE MATERIAL EXCEDENTE

m3

4.81

8.58

41.27

0.000 0.000 0.000

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0 0 0

0% 0% 0%

1 1 1

96.67

01.06.02.02

41.27

100% 100% 100%

0 0 0

0% 0% 0%

01.06.03 01.06.03.01

OBRAS DE CONCRETO SIMPLE SOLADO PARA ZAPATAS e=3"

m2

3.48

32.38

112.68

m3

1.60

394.64

631.42

0% 0%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

0 0

0% 0%

0 1

631.42

0% 100%

3.4799258802 0

100% 0%

01.06.04

CONCRETO CICLOPEO f'c=175 kg/cm2 + 30% PM OBRAS DE CONCRETO

0.000 0.000

112.68

01.06.03.02 01.06.04.01

CONCRETO CICLOPEO f'c=210 kg/cm2 + 30% PM

m3

2.19

394.64

864.26

ENCOFRADO Y DESENCOFRADO EN MUROS

m2 kg

1.80 104.17

32.28 4.43

58.10 461.47

0.00 0.00 0.00

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0 0 0

0% 0% 0%

0 1 1

58.1

ACERO DE REFUERZO fy=4,200 kg/cm2

0% 0% 0%

461.47

0% 100% 100%

2.1899959457 0 0

864.26

01.06.04.02 01.06.04.03

0.000 0.000 0.000

100% 0% 0%

01.06.05

REVOQUES Y ENLUCIDOS TARRAJEO CON MORTERO EXTERIOR 1:5 E= 1.50 Cm

m2

1.55

17.98

27.87

0.000

0%

0.00

0%

0.00

0%

0

0%

1

27.87

100%

0

0%

INSTALACION DE ACCESORIOS Y OTROS ACCESORIOS PARA PASE AEREO

glb

1.00

18,011.79

18,011.79

0.000

0%

0.00

0%

0.00

0%

0

0%

1

18,011.79

100%

0

0%

m2

5.48

4.43

24.28

0.000

0%

0.00

0%

0.00

0%

0

0%

1

24.28

100%

0

0%

m3 m3

5.63 1.94

17.17 11.06

96.67 21.46

0.000 0.000 0.000

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0 0 0

0% 0% 0%

1 1 1

96.67

100% 100% 100%

0 0 0

0% 0% 0%

0.000 0.000

0% 0%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

0 0

0% 0%

1 1

112.68

100% 100%

0 0

0% 0%

01.06.01.01 01.06.02 01.06.02.01

01.06.05.01 01.06.06 01.06.06.01 01.07 01.07.01

MOVIMIENTO DE TIERRAS

PASE AEREO L=20.00 (01 UND)

01.07.01.01

TRABAJOS PRELIMINARES TRAZO Y REPLANTEO PARA PASE AEREO

01.07.02

MOVIMIENTO DE TIERRAS

01.07.02.01 01.07.02.02

EXCAVACION MANUAL EN TERRENO CONGLOMERADO

01.07.02.03

ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE

m3

4.81

8.58

41.27

SOLADO PARA ZAPATAS e=3" CONCRETO CICLOPEO f'c=175 kg/cm2 + 30% PM

m2

3.48

32.38

112.68

m3

1.60

394.64

631.42

01.07.03 01.07.03.01 01.07.03.02 01.07.04

21.46

RELLENO CON MATERIAL PROPIO Y COMPACTADO

OBRAS DE CONCRETO

21.46 41.27

631.42

Periodo Item

Descripción

Und.

Metrado

P.U.

Parcial

MES 01 AVANCE MENSUAL

Mes Metrado

01.07.04.01 01.07.04.02 01.07.04.03

CONCRETO f'c=210 kg/cm2 CON MEZCLADORA ENCOFRADO Y DESENCOFRADO EN MUROS

01.07.05

ACERO DE REFUERZO fy=4,200 kg/cm2 REVOQUES Y ENLUCIDOS

01.07.05.01

TARRAJEO CON MORTERO EXTERIOR 1:5 E= 1.50 Cm

01.07.06

INSTALACION DE ACCESORIOS Y OTROS

01.07.06.01 01.08

ACCESORIOS PARA PASE AEREO

Parcial

MES 02 AVANCE MENSUAL % Avance Metrado

Parcial

MES 03 AVANCE MENSUAL Parcial

MES 04 AVANCE MENSUAL Parcial

MES 05 AVANCE MENSUAL Parcial

MES 06 AVANCE MENSUAL

% Avance

Metrado

% Avance

Metrado

% Avance

Metrado

% Avance

Metrado

m3

2.15

467.78

1,005.73

1.65 98.03

32.28 4.43

53.26 434.27

0.000 0.000 0.000

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0 0 0

0% 0% 0%

1 1 1

1,005.73

m2 kg

434.27

100% 100% 100%

0 0 0

0% 0% 0%

m2

1.40

17.98

25.17

0.000

0%

0.00

0%

0.00

0%

0

0%

1

25.17

100%

0

0%

glb

1.00

18,011.79

18,011.79

0.000

0%

0.00

0%

0.00

0%

0

0%

1

18,011.79

100%

0

0%

0.000 0.000 0.000 0.000 0.000 0.000 0.000

0% 0% 0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0% 0%

0 0 0 0 0 0 0

0% 0% 0% 0% 0% 0% 0%

1 1 1 1 1 1 1

11,075.00

100% 100% 100% 100% 100% 100% 100%

0 0 0 0 0 0 0

0% 0% 0% 0% 0% 0% 0%

53.26

Parcial

% Avance

01.08.01

RESERVORIO N°01 CON GEOMENBRANA V=1800.00 M3 CAMARA DE ALMACENAMIENTO TRAPEZOIDAL

01.08.02

MOVIMIENTO DE TIERRAS

01.08.02.01

TRAZO Y REPLANTEO EN OBRAS DE ARTE

m2

2,500.00

4.43

11,075.00

01.08.02.02 01.08.02.03

EXCAVACION EN TERRENO COMPACTO

m3 m3

3,300.00 76.23

9.72 57.90

32,076.00 4,413.72

m2 m3

1,014.46 36.00

5.13 42.74

5,204.18 1,538.64

m3

50.72

9.56

484.88

m3

1,766.41

10.50

18,547.31

m2 m2

1,197.94 1,169.34

16.37 27.93

19,610.28 32,659.67

0.000

0%

0.00

0%

0.00

0%

0

0%

0

0%

1197.9401344

0.000

0%

0.00

0%

0.00

0%

0

0%

0

0%

1169.3401361

m

12.00

134.00

1,608.00

0.000

0%

0.00

0%

0.00

0%

0

0%

0

0%

12

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

0 0 0 0 0 0 0 0 0 0

0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

1 1 1 1 1 1 1 1 1 1

9.26

100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

0 0 0 0 0 0 0 0 0 0

0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

0 0 0 0 0 0 0 0 0 0 0

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

1 1 1 1 1 1 1 1 1 1 1

286.94

100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

0 0 0 0 0 0 0 0 0 0 0

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

0% 0% 0% 0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0% 0% 0%

0 0 0 0 0 0 0 0

0% 0% 0% 0% 0% 0% 0% 0%

1 1 1 1 1 1 1 1

17.81

100% 100% 100% 100% 100% 100% 100% 100%

0 0 0 0 0 0 0 0

0% 0% 0% 0% 0% 0% 0% 0%

01.08.02.04 01.08.02.05 01.08.02.06

VOLADURA Y DESQUINCHE EN ROCA SUELTA PERFILADO COMPACTADO DE TALUDES Y FONDO DE RESERVORIO RELLENO CON MATERIAL PROPIO

01.08.02.07

RELLENO Y COMPACTACION DE ARCILLA E=5CM ELIMINACION MANUAL DE MATERIAL EXEDENTE Dmax=50 m

01.08.03

OBRAS DE IMPERMEABILIZACION

01.08.03.01 01.08.03.02

GEOTEXTIL NO TEJIDO NT 200 200 gr/m2 (100x3m) SUMINISTRO E INSTALACION

01.08.04

GEOMEMBRANA HDPE LISA E=1 MM. POLIETILENO (237X6.8 m) SUMINISTRO E INSTALACION ESCALERAS DE INSPECCION

01.08.04.01

ESCALERA DE TUBO DE F°G°Ø 1" TIPO GATO

01.08.05 01.08.05.01

POZO DISCIPADOR Y PARTIDOR BYPASS TRAZO Y REPLANTEO EN OBRAS DE ARTE

m2

2.09

4.43

9.26

01.08.05.02

EXCAVACION MANUAL EN TERRENO COMPACTO ELIMINACION MANUAL DE MATERIAL EXEDENTE Dmax=50 m

m3

1.33

9.72

12.93

m3 m3

1.73 2.09

10.50 317.01

18.17 662.55

01.08.05.03 01.08.05.04 01.08.05.05

CONCRETO f´c = 100 kg/cm2 (PARA SOLADO MEZCLA MANUAL) CONCRETO f´c = 210 kg/cm2

m3

1.08

524.61

566.58

01.08.05.06

ENCOFRADO Y DESENCOFRADO EN MUROS

m2

1.54

35.20

54.21

01.08.05.07

ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60

kg

36.18

4.21

152.32

01.08.05.08 01.08.05.09

TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:1 e=1 cm

m2 m2

5.84 2.61

23.78 23.78

138.88 62.07

und

2.00

153.00

306.00

01.08.05.10

TARRAJEO INTERIOR MEZCLA 1:1 e=1.5 cm COMPUERTA METALICA TIPO TARGETA DE 0.30 X0.30M. h=0.65 m.

01.08.06

LINIA DE CONDUCCION BYPASS

01.08.06.01

TRAZO Y REPLANTEO EN CANALES

m

57.85

4.96

286.94

01.08.06.02 01.08.06.03

EXCAVACION MANUAL EN MATERIAL SUELTO

m3 m2

36.16 39.96

20.31 2.04

734.41 81.52

m3 m

23.65 57.85

15.42 2.57

364.68 148.67

01.08.06.04 01.08.06.05 01.08.06.06

REFINE Y NIVELACION Y COMPACTACION ZARANDEO DE MATERIAL PROCEDENTE DE EXCAVACION CAMA DE APOYO E=0.10 m PREPARACION Y COLOCACION RELLENO Y COMPACTACION CON MATERIAL SELECCIONADO RELLENO CON MATERIAL PROPIO

m3

22.44

44.51

998.80

01.08.06.07

m3

13.56

42.74

579.55

01.08.06.08

TUBERIA PVC UF DN 250 mm S-25 NORMA 4435 C/ANILLO

m

52.45

43.78

2,296.26

01.08.06.09 01.08.06.10

TUBERIA PVC UF DN 160 mm S-25 NORMA 4435 C/ANILLO

m und

5.45 2.00

28.48 106.20

155.22 212.40

01.08.06.11

und

1.00

58.46

58.46

01.08.07

CACHIMBA PVC UF Ø 250 mm.160 mm x45 CAMARA DE VALVULA

01.08.07.01

TRAZO Y REPLANTEO EN OBRAS DE ARTE

m2

4.02

4.43

17.81

01.08.07.02 01.08.07.03

EXCAVACION MANUAL EN TERRENO COMPACTO

m3 m3

22.38 29.09

9.72 10.50

217.53 305.45

01.08.07.04

CONCRETO f´c = 100 kg/cm2 (PARA SOLADO MEZCLA MANUAL) CONCRETO f´c = 210 kg/cm2

m3

4.02

317.01

1,274.38

01.08.07.05 01.08.07.06

CURVA PVC- UF Ø250 mm

ELIMINACION MANUAL DE MATERIAL EXEDENTE Dmax=50 m

m3 m2

4.53 24.41

524.61 35.20

2,376.48 859.23

kg

242.90

4.21

1,022.61

m2

11.04

23.78

262.53

ACCESORIOS P/CAMARA DE VALVULA Y RESRVORIO.GEOMEMBRANA. SUM. E INST.

glb

1.00

3,537.11

3,537.11

0.000

0%

0.00

0%

0.00

0%

0

0%

1

01.08.07.10

TAPA METALICA 1.00 X 1.00 M.

und

1.00

124.03

124.03

0.000

0%

0.00

0%

0.00

0%

0

0%

1

01.08.08 01.08.08.01

CAMARA DE DISCIPACION Y SALIDA TRAZO Y REPLANTEO EN OBRAS DE ARTE

m2

1.62

4.43

7.18

01.08.08.02

EXCAVACION MANUAL EN TERRENO COMPACTO

m3

36.30

9.72

352.84

01.08.08.03 01.08.08.04

ELIMINACION MANUAL DE MATERIAL EXEDENTE Dmax=50 m CONCRETO f´c = 100 kg/cm2 (PARA SOLADO MEZCLA MANUAL)

m3 m3

47.19 1.62

10.50 317.01

495.50 513.56

01.08.08.05 01.08.08.06

CONCRETO f´c = 210 kg/cm2 ENCOFRADO Y DESENCOFRADO EN MUROS

m3 m2

1.08 10.71

524.61 35.20

566.58 376.99

01.08.08.07

kg

32.70

4.21

137.67

01.08.08.08

ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:1 e=1 cm

m2

4.68

23.78

111.29

01.08.08.09

TARRAJEO INTERIOR MEZCLA 1:1 e=1.5 cm

m2

2.16

23.78

51.36

01.08.08.10 01.08.08.11

TAPA METALICA 0.60 X 0.60 M. ACCESORIOS EN CAMARA DE DICIPACION Y SALIDA

und glb

1.00 1.00

122.90 353.22

122.90 353.22

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

0 0 0 0 0 0 0 0 0 0 0

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

0 0 0 0 1 1 1 1 1 1 1

01.08.09

CERCO DE PROTECCION CERCO PERIMETRICO CON MALLA GANADERA

m

200.00

22.96

4,592.00

0.000

0%

0.00

0%

0.00

0%

0

0%

1

m

0.000 0.000

0% 0%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

0 0

0% 0%

0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0%

0 0 0 0 0

0% 0% 0% 0% 0%

01.08.07.07

ENCOFRADO Y DESENCOFRADO EN MUROS ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60

01.08.07.08

TARRAJEO INTERIOR MEZCLA 1:1 e=1.5 cm

01.08.07.09

01.08.09.01 01.09

LINEA DE ADUCCIÓN A PRESIÓN TUB. 300 mm (1 189.00 m) y TUB. 200mm (1 177.00m)

01.09.01 01.09.01.01

TRABAJOS PRELIMINARES

32,076.00 4,413.72 5,204.18 1,538.64 484.88 18,547.31

12.93 18.17 662.55 566.58 54.21 152.32 138.88 62.07 306

734.41 81.52 364.68 148.67 998.8 579.55 2,296.26 155.22 212.4 58.46

217.53 305.45 1,274.38 2,376.48 859.23 1,022.61 262.53 3,537.11 124.03

100%

19,610.28 32,659.67

1,608.00

0

100% 100% 100%

0%

100%

0

353.22

0% 0% 0% 0% 100% 100% 100% 100% 100% 100% 100%

1.6207674944 36.300411523 47.19047619 1.620011987 0 0 0 0 0 0 0

4,592.00

100%

0

0%

1 1

946.4

100% 100%

0 0

0% 0%

1 1 1 1 1

21,668.77

0 0 0 0 0

0% 0% 0% 0% 0%

566.58 376.99 137.67 111.29 51.36 122.9

0% 7.18 352.84 495.5 513.56

100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0%

2,366.00

0.40

946.40

m

2,366.00

0.35

828.10

m3

1,135.68

19.08

21,668.77

01.09.02.02

EXCAVACION MANUAL EN ROCA SUELTO REFINE Y NIVELACION ZANJA PARA TUBERIA

m

2,366.00

0.53

1,253.98

01.09.02.03

CAMA DE APOYO ZARANDEADO PARA TUBERIA E=0.10M

m

2,366.00

0.74

1,750.84

01.09.02.04 01.09.02.05

RELLENO CON MATERIAL ZARANDEADO Y COMPACTADO RELLENO CON MATERIAL PROPIO Y COMPACTADO

m3 m3

425.88 709.80

11.03 11.40

4,697.46 8,091.72

0.000 0.000 0.000 0.000 0.000

8,091.72

100% 100% 100% 100% 100%

01.09.03 01.09.03.01

OBRAS DE CONCRETO SIMPLE CONCRETO SIMPLE PARA DADO DE ANCLAJE

m3

1.50

137.47

206.21

0.000

0%

0.00

0%

0.00

0%

0

0%

1

206.21

100%

0

0%

01.09.04

SUMINISTRO E INSTALCION DE TUBERIA Y ACCESORIOS PVC SAP

01.09.04.01 01.09.04.02

INSTALACION DE TUBERIA PVC SAP NTO ISO-399.002 (C-7.5) de Ø 300 mm

m m

1,189.00 1,177.00

101.16 71.94

120,279.24 84,673.38

TUBERIA HDPE DN 300 ISO 4427 CODO PVC ISO C-7.5 UF DE 300 mm X 22.5º C/ANILLO

glb

1.00

20,606.50

20,606.50

und und

38.00 5.00

81.79 81.79

3,108.02 408.95

und

14.00

182.05

2,548.70

und

3.00

182.05

546.15

0% 0% 0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0% 0%

0 0 0 0 0 0 0

0% 0% 0% 0% 0% 0% 0%

1 1 1 1 1 1 1

120,279.24

01.09.04.03

0.000 0.000 0.000 0.000 0.000 0.000 0.000

546.15

100% 100% 100% 100% 100% 100% 100%

0 0 0 0 0 0 0

0% 0% 0% 0% 0% 0% 0%

m

2,366.00

0.39

922.74

0.000

0%

0.00

0%

0.00

0%

0

0%

1

922.74

100%

0

0%

m2

25.35

3.43

86.95

0.000

0%

0.00

0%

0.00

0%

0

0%

1

86.95

100%

0

m3 m3

39.42 39.42

17.50 25.75

689.85 1,015.07

0.000 0.000

0% 0%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

0 0

0% 0%

0 0

0% 0%

39.42 39.420194175

01.09.01.02 01.09.02 01.09.02.01

01.09.04.04 01.09.04.05

LIMPIEZA DEL TERRENO MANUAL TRAZO Y REPLANTEO TOPOGRAFICO DE LA LINEA DE CONDUCCIÓN

INSTALACION DE TUBERIA PVC SAP NTO ISO-399.002 (C- 7.5) de Ø 200 mm

01.09.04.06

CODO PVC ISO C-7.5 UF DE 300 mm X 45º C/ANILLO CODO PVC ISO C-10 UF DE 200 mm X 22.5º C/ANILLO

01.09.04.07

CODO PVC ISO C-10 UF DE 200 mm X 45º C/ANILLO

01.09.05

PRUEBA HIDRAULICA

01.09.05.01 01.10

PRUEBA HIDRAULICA

01.10.01

CÁMARAS DE INSPECCION/DISIPADORAS DE ENERGIA (13 UND) TRABAJOS PRELIMINARES

01.10.01.01

TRAZO Y REPLANTEO PARA CAMARA DISIPADORAS DE ENERGIA

01.10.02

MOVIMIENTO DE TIERRAS

01.10.02.01 01.10.02.02

EXCAVACION MANUAL EN MATERIAL SUELTO

01.10.02.03

828.1

MOVIMIENTO DE TIERRAS

EXCAVACION MANUAL EN ROCA SUELTO REFINE, NIVELACION Y COMPACTACION PARA CAMARA DISIPADORA DE ENERGIA

1,253.98 1,750.84 4,697.46

84,673.38 20,606.50 3,108.02 408.95 2,548.70

0% 689.85 1,015.07 117.39

100% 100%

m2

91.00

1.29

117.39

0.000

0%

0.00

0%

0.00

0%

0

0%

0

0%

91

ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE

m3

7.91

8.58

67.87

0.000

0%

0.00

0%

0.00

0%

0

0%

1

67.87

100%

0

0%

01.10.03 01.10.03.01

SOLADO PARA CAMARA DISIPADORA DE ENERGIA E=3"

m2

4.97

66.40

330.01

0.000

0%

0.00

0%

0.00

0%

0

0%

1

330.01

100%

0

0%

01.10.04 01.10.04.01

OBRAS DE CONCRETO ARMADO ACERO DE REFUERZO fy=4,200 kg/cm2

kg

2,223.68

4.73

10,518.01

ENCOFRADO Y DESENCOFRADO EN MUROS CONCRETO f'c=175 kg/cm2 CON MEZCLADORA

m2

204.10

42.46

8,666.09

m3

20.33

436.72

8,878.52

0.000 0.000 0.000

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0 0 0

0% 0% 0%

1 1 1

10,518.01

01.10.04.02

100% 100% 100%

0 0 0

0% 0% 0%

m2 m2

107.12 93.08

37.60 20.59

4,027.71 1,916.52

0.000 0.000

0% 0%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

93.730053 91.625546

3,524.25

und und

13.10 13.00

309.19 139.19

4,050.39 1,809.47

0.000 0.000

0% 0%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

13.100003 13

4,050.39

m2

93.07

6.89

641.25

0.000

0%

0.00

0%

0.00

0%

93.069666

m2

4.64

34.65

160.78

0.000

0%

0.00

0%

0.00

0%

0.000 0.000

0% 0%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

01.10.02.04

01.10.04.03 01.10.05 01.10.05.01 01.10.05.02 01.10.06 01.10.06.01 01.10.06.02 01.10.07 01.10.07.01 01.11

REVOQUES Y ENLUCIDOS TARRAJEO CON IMPERMEABILIZANTE 1:3 E=1.5CM TARRAJEO CON MORTERO EXTERIOR 1:5 E= 1.50 Cm INSTALACION DE ACCESORIOS Y OTROS COMPUERTA TIPO IZAJE marc.0.30x1.10 mts, Planch .25x.80 mts e=1/4" TAPA METALICA 0.80X0.80X1/8" PINTURA ESMALTE SINTETICO ESTRUCTURA PINTURA ESMALTE SINTETICO ESTRUCTURA

01.11.01

CÁMARAS DE CARGA V=5.50 M3 (1 UND) TRABAJOS PRELIMINARES

01.11.01.01

TRAZO Y REPLANTEO PARA CAMARA DE CARGA

01.11.02 01.11.02.01

MOVIMIENTO DE TIERRAS EXCAVACION MANUAL EN MATERIAL SUELTO

m3

1.16

17.50

20.30

01.11.02.02

EXCAVACION MANUAL EN ROCA SUELTO

m3

0.29

25.75

7.47

8,666.09 8,878.52 503.46

100%

88% 98%

0.1249991 0.0156273

12% 2%

0 0

0% 0%

1,809.47

100% 100%

0 0

0% 0%

0 0

0% 0%

641.25

100%

0

0%

0

0%

4.6401154

160.78

100%

0

0%

0

0%

1.16 0.2900971

20.3

100% 100%

0 0

0% 0%

0 0

0% 0%

1,886.57

7.47

29.95

Periodo Item

Descripción

Und.

Metrado

P.U.

Parcial

MES 01 AVANCE MENSUAL

Mes Metrado

01.11.02.03 01.11.02.04 01.11.02.05

RELLENO CON MATERIAL PROPIO Y COMPACTADO REFINE, NIVELACION Y COMPACTACION PARA CAMARA DE CARGA

01.11.03

ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE

01.11.03.01

SOLADO PARA CAMARA DE CARGA E=3"

01.11.04

OBRAS DE CONCRETO ARMADO

01.11.04.01 01.11.04.02

ACERO DE REFUERZO fy=4,200 kg/cm2

% Avance

Metrado

% Avance

Metrado

% Avance

Metrado

% Avance

Metrado

8.87

5.59 7.74 16.13

0.000 0.000 0.000

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0.6302142 6 1.8799534

5.59

1.29 8.58

16.13

100% 100% 100%

0 0 0

0% 0% 0%

0 0 0

0% 0% 0%

m2

5.94

32.67

194.06

0.000

0%

0.00

0%

0.00

0%

5.9400061

194.06

100%

0

0%

0

0%

kg m2

223.66 46.11

4.36 42.11

975.16 1,941.69

3.27

420.11

1,373.76

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

223.66055 46.10995 3.2700007

975.16

m3

0.000 0.000 0.000

100% 100% 100%

0 0 0

0% 0% 0%

0 0 0

0% 0% 0%

0.000 0.000

0% 0%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

19.570078 8.8800532

351.87

100% 100%

0 0

0% 0%

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0 0 0

0% 0% 0%

1 1 0

01.11.05.01

TARRAJEO CON MORTERO EXTERIOR 1:5 E= 1.50 Cm

m2

19.57

17.98

351.87

01.11.05.02 01.11.06

TARRAJEO CON IMPERMEABILIZANTE 1:3 E=1.5CM

m2

8.88

37.60

333.89

und und

1.00 1.00

778.74 220.25

778.74 220.25

INSTALACION DE ACCESORIOS Y OTROS VALVULA MARIPOSA TIPO WAFER DE FIERRO DUCTIL DE 110MM

Parcial 7.74

1,941.69 1,373.76

333.89

Parcial

MES 06 AVANCE MENSUAL

6.00 1.88

REVOQUES Y ENLUCIDOS

Parcial

MES 05 AVANCE MENSUAL

0.63

01.11.05

Parcial

MES 04 AVANCE MENSUAL

m2 m3

01.11.04.03

% Avance Metrado

MES 03 AVANCE MENSUAL

m

ENCOFRADO Y DESENCOFRADO EN MUROS CONCRETO f'c=175 kg/cm2 CON MEZCLADORA

Parcial

MES 02 AVANCE MENSUAL

778.74

Parcial

% Avance

0% 0%

0 0

100% 100% 0%

0 0 2

333.5

0% 0% 100%

428.08

100%

und

2.00

166.75

333.50

01.11.07

TAPA METALICA 0.80X0.80X1/8" PINTURA ESMALTE SINTETICO ESTRUCTURA

0.000 0.000 0.000

01.11.07.01

PINTURA ESMALTE SINTETICO ESTRUCTURA

m2

62.13

6.89

428.08

0.000

0%

0.00

0%

0.00

0%

0

0%

0

0%

62.130624093

01.12 01.12.01

CÁMARAS DE CARGA V= 11.00 M3 (1 UND)

01.12.01.01

m2

9.28

34.65

321.55

0.000

0%

0.00

0%

0.00

0%

0

0%

1

321.55

100%

0

0%

01.12.02

TRAZO Y REPLANTEO PARA CAMARA DE CARGA MOVIMIENTO DE TIERRAS

01.12.02.01

EXCAVACION MANUAL EN MATERIAL SUELTO

m3

2.33

17.50

40.78

EXCAVACION MANUAL EN ROCA SUELTO

m3 m

0.58 1.25

25.75 8.87

14.94 11.09

01.12.02.04

REFINE, NIVELACION Y COMPACTACION PARA CAMARA DE CARGA ELIMINACION DE MATERIAL EXCEDENTE

m2

12.00

1.29

15.48

m3

3.75

8.58

32.18

0.000 0.000 0.000 0.000 0.000

0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0%

0 0 0 0 0

0% 0% 0% 0% 0%

1 1 1 1 1

40.78

01.12.02.02 01.12.02.03

100% 100% 100% 100% 100%

0 0 0 0 0

0% 0% 0% 0% 0%

m2

11.88

32.67

388.12

0.000

0%

0.00

0%

0.00

0%

11.880012

388.12

100%

0

0%

0

0%

0.000 0.000 0.000

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

130.47 0.00 5.72

29% 0% 88%

316.86009 92.2199 0.8175002

1,381.51

71% 100% 13%

0 0 0

0% 0% 0%

0 0 0

0% 0% 0%

0.000 0.000

0% 0%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

39.140156 17.75

703.74

100% 100%

0 0

0% 0%

0 0

0% 0%

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

2 2 2

333.5

100% 100% 100%

0 0 0

0% 0% 0%

0 0 0

0% 0% 0%

856.15

100%

0

0%

0

0%

0%

0

0%

0

0%

100% 100% 0% 0%

0 0 0 0

0% 0% 0% 0%

0 0 0 0

0% 0% 0% 0%

01.11.06.01 01.11.06.02 01.11.06.03

01.12.02.05 01.12.03

CANASTILLA PVC DE 160MM A 110 mm C/ANILLO

TRABAJOS PRELIMINARES

RELLENO CON MATERIAL PROPIO Y COMPACTADO

01.12.03.01

OBRAS DE CONCRETO SIMPLE SOLADO PARA CAMARA DE CARGA E=3"

01.12.04

OBRAS DE CONCRETO ARMADO

01.12.04.01

ACERO DE REFUERZO fy=4,200 kg/cm2

kg

447.33

4.36

1,950.36

01.12.04.02 01.12.04.03

ENCOFRADO Y DESENCOFRADO EN MUROS

m2 m3

92.22 6.54

42.11 420.11

3,883.38 2,747.52

01.12.05

CONCRETO f'c=175 kg/cm2 CON MEZCLADORA REVOQUES Y ENLUCIDOS

01.12.05.01

TARRAJEO CON MORTERO EXTERIOR 1:5 E= 1.50 Cm

m2

39.14

17.98

703.74

01.12.05.02

TARRAJEO CON IMPERMEABILIZANTE 1:3 E=1.5CM

m2

17.75

37.60

667.40

01.12.06 01.12.06.01

INSTALACION DE ACCESORIOS Y OTROS und

2.00

778.74

1,557.48

TAPA METALICA 0.80X0.80X1/8"

und und

2.00 2.00

220.25 166.75

440.50 333.50

0.000 0.000 0.000

01.12.07.01

PINTURA ESMALTE SINTETICO ESTRUCTURA PINTURA ESMALTE SINTETICO ESTRUCTURA

m2

124.26

6.89

856.15

0.000

0%

0.00

0%

0.00

01.13

TOMAS LATERALES (7.00 UND)

01.13.01 01.13.01.01

TRABAJOS PRELIMINARES TRAZO Y REPLANTEO PARA CAMARA DE CARGA

m2

11.20

3.79

42.45

0.000

0%

0.00

0%

11.20

01.13.02 01.13.02.01

MOVIMIENTO DE TIERRAS EXCAVACION MANUAL EN ROCA SUELTO

m3

7.10

25.75

182.83

01.13.02.02

RELLENO CON MATERIAL PROPIO Y COMPACTADO

m3

7.10

13.30

94.43

01.13.02.03 01.13.02.04

REFINE, NIVELACION Y COMPACTACION PARA CAMARA DE CARGA ELIMINACION MATERIAL EXCEDENTE

m2 m3

9.10 2.31

1.29 8.58

11.74 19.82

0.000 0.000 0.000 0.000

0% 0% 0% 0%

0.00 0.00 0.00 0.00

0% 0% 0% 0%

0.00 0.00 9.10 2.31

01.13.03

01.12.06.02 01.12.06.03 01.12.07

220.25

VALVULA MARIPOSA TIPO WAFER DE FIERRO DUCTIL DE 110MM CANASTILLA PVC DE 160MM A 110 mm C/ANILLO

568.86 2,404.08

3,883.38 343.44

667.4 1,557.48 440.5

0%

124.2598

100%

0 7.1001942 7.1 0 0

182.83

19.82

0% 0% 100% 100%

42.45

11.74

94.43

14.94 11.09 15.48 32.18

OBRAS DE CONCRETO SIMPLE CONCRETO SOLADO MEZCLA 1:12 CEMENTO-HORMIGON e=0.05 m.

m2

9.10

57.81

526.07

0.000

0%

0.00

0%

7.96

460.31

87%

1.1375195

65.76

13%

0

0%

0

0%

01.13.04.01

OBRAS DE CONCRETO ARMADO CONCRETO f'c=175 kg/cm2

m3

3.67

490.93

1,801.71

m2

61.01

35.20

2,147.55

01.13.04.03

ACERO DE REFUERZO fy=4,200 kg/cm2

kg

215.00

4.73

1,016.95

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

3.21 8.90 94.06

88% 15% 44%

0.4587416 52.112784 120.93658

225.21

ENCOFRADO Y DESENCOFRADO EN MUROS

0.000 0.000 0.000

1,576.50

01.13.04.02

12% 85% 56%

0 0 0

0% 0% 0%

0 0 0

0% 0% 0%

01.13.05 01.13.05.01

REVOQUES Y ENLUCIDOS m2

0.000 0.000

0% 0%

0.00 0.00

0% 0%

22.05 23.76

447.18

94% 62%

1.4699211 14.254007

29.81

6% 38%

0 0

0% 0%

0 0

0% 0%

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

4.37 3.06 1.53

6,674.76

62% 44% 22%

2.6250016 3.9375 5.4687837

4,004.86 761.2

38% 56% 78%

0 0 0

0% 0% 0%

0 0 0

0% 0% 0%

01.13.03.01 01.13.04

TARRAJEO CON IMPERMEABILIZANTE 1:3 E=1.5CM TARRAJEO CON MORTERO EXTERIOR 1:5 E= 1.50 Cm

23.52

20.28

476.99

01.13.05.02

m2

38.01

20.59

782.63

01.13.06

INSTALACION DE ACCESORIOS Y OTROS

01.13.06.01

VALVULA MARIPOSA TIPO WAFER DE FIERRO DUCTIL DE 110MM

und

7.00

1,525.66

10,679.62

01.13.06.02 01.13.06.03

CODOS PVC DE 110 mm X 45° C/ANILLO

und und

7.00 7.00

276.00 139.19

1,932.00 974.33

0.000 0.000 0.000

01.13.07 01.13.07.01

TAPA METALICA 0.80X0.80X1/8" PINTURA ESMALTE SINTETICO ESTRUCTURA

845.25 213.13

293.49

1,086.75

38.01016

261.89

100%

0

0%

0

0%

472.16667 7259.5588

141.65

4% 64%

0 0

0% 0%

0 0

0% 0%

0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0%

2720 8215.7045 5547.9595 129.82287 0 0

51,897.60

100% 73% 49% 14% 0% 0%

0 0.2749996 0.5104166 0.7560975 1 1

0% 27% 51% 76% 100% 100%

0 0 0 91.152834008 0 0

0% 0% 0% 0%

0.00 0.00 0.00 0.00

0% 0% 0% 0%

0 0 0 0

0% 0% 0% 0%

1 1 1 1

100% 100% 100% 100%

0 0 0 0

0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

2.00 4.00 2.00 14.00 23.00 9.00 13.00 18.69 16.00 18.69 11.00 4.00 7.48 8.63 8.05 8.00 11.50 3.00 5.00 3.00 3.00 5.00 25.88 15.33 17.25

530.61

100% 100% 100% 100% 72% 100% 100% 72% 100% 29% 100% 100% 58% 58% 58% 100% 96% 100% 100% 100% 100% 100% 96% 96% 26%

0 0 0 0 9 0 0 7.3124706 0 46.312361 0 0 5.5249629 6.3749349 5.9497339 0 0.5 0 0 0 0 0 1.1251025 0.666775 48.75

0% 0% 0% 0% 28% 0% 0% 28% 0% 71% 0% 0% 42% 42% 42% 0% 4% 0% 0% 0% 0% 0% 4% 4% 74%

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

2,833.00

100%

0

6.89

261.89

0.000

0%

0.00

0%

0.00

LIMPIEZA DEL TERRENO MANUAL

m

11,332.00

0.30

3,399.60

01.14.01.02 01.14.02

TRAZO Y REPLANTEO TOPOGRAFICO DE LA LINEA DE DISTRIBUCIÓN

m

11,332.00

0.34

3,852.88

0.000 0.000

0% 0%

0.00 0.00

0% 0%

10859.83 4072.44

01.14.02.01

m3

2,720.00

19.08

51,897.60

01.14.02.02

EXCAVACION MANUAL EN ROCA SUELTO REFINE Y NIVELACION ZANJA PARA TUBERIA

m

11,332.00

0.44

4,986.08

01.14.02.03

CAMA DE APOYO ZARANDEADO PARA TUBERIA E=0.10M

m

11,332.00

0.74

8,385.68

01.14.02.04 01.14.02.05

RELLENO CON MATERIAL ZARANDEADO Y COMPACTADO

m3 m3

906.00 1,813.00

9.88 8.47

8,951.28 15,356.11

01.14.02.06

ELIMINACION MATERIAL EXCEDENTE SUMINISTRO E INSTALCION DE TUBERIA PVC SAP

m3

565.00

10.30

5,819.50

0.000 0.000 0.000 0.000 0.000 0.000

0% 0% 0% 0% 0% 0%

0.00 0.00 0.00 0.00 0.00 0.00

0% 0% 0% 0% 0% 0%

m

383.00

27.81

10,651.23

01.14.03.02

INSTALACIÓN DE TUBERIA PVC SAP NTP ISO-1452 (C-7.5) de Ø 110mm INSTALACIÓN DE TUBERIA PVC SAP NTP ISO-1452 (C-7.5) de Ø 90mm

m

3,892.00

17.02

66,241.84

01.14.03.03

INSTALACIÓN DE TUBERIA PVC SAP NTP ISO-1452 (C-7.5) de Ø 63mm

m

2,543.00

10.00

25,430.00

01.14.03.04

INSTALACIÓN DE TUBERIA PVC SAP NTP ISO-399.002 (C-7.5) de Ø 1 1/2"

m

4,514.00

9.24

41,709.36

0.000 0.000 0.000 0.000

0% 0% 0% 0%

0.00 0.00 0.00 0.00

01.14.04 01.14.04.01

SUMINISTRO E INST.DE ACCESORIOS PARA TUBERIAS PVC SAP

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

01.14.03 01.14.03.01

489.14

572.03

0%

38.01

LINEA DE DISTRIBUCIÓN L= 11 332.00 ML TRABAJOS PRELIMINARES

01.14.01.01

PINTURA ESMALTE SINTETICO ESTRUCTURA

444.92

1,834.37

96% 36%

m2

01.14.01

01.14

313.18

3,257.95 1,384.63

2,468.25

MOVIMIENTO DE TIERRAS

RELLENO CON MATERIAL PROPIO Y COMPACTADO

167.5

3,614.91 4,105.49 1,282.65

1,371.17 4,280.19 6,768.04 15,356.11 5,819.50 10,651.23 66,241.84 25,430.00 41,709.36

900.59

0% 0% 0% 10% 0% 0%

01.14.04.22

REDUCCIÓN PVC ISO C-7.5 UF DE 110 mm a 63mm REDUCCIÓN PVC ISO C-7.5 UF DE 110 mm a 1 1/2"

und

5.00

48.50

242.50

01.14.04.23

REDUCCIÓN PVC ISO C-7.5 UF DE 90 mm a 63mm

und

27.00

48.76

1,316.52

01.14.04.24

REDUCCIÓN PVC ISO C-7.5 UF DE 90 mm a 1 1/2"

und

16.00

30.76

492.16

01.14.04.25 01.14.05

REDUCCIÓN PVC ISO C-7.5 UF DE 63 mm a 1 1/2"

und

66.00

30.76

2,030.16

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

01.14.05.01

PRUEBA HIDRAULICA PRUEBA HIDRAULICA

m

11,332.00

0.25

2,833.00

0.000

0%

0.00

0%

11332.00

0%

0

0%

0

0%

01.15

VALVULAS DE CONTROL(20.00 UND)

01.15.01

TRABAJOS PRELIMINARES TRAZO Y REPLANTEO PARA CAJA DE VALVULAS DE CONTROL

m2

9.80

2.67

26.17

0.000

0%

0.00

0%

9.80

26.17

100%

0

0%

0

0%

0

0%

m3 m3

5.88 7.35

14.72 7.35

86.55 54.02

0.000 0.000

0% 0%

0.00 0.00

0% 0%

5.88 7.35

86.55

100% 100%

0 0

0% 0%

0 0

0% 0%

0 0

0% 0%

m2 m3

39.60 3.86

35.20 247.51

1,393.92 955.39

0.000 0.000

0% 0%

0.00 0.00

0% 0%

39.60 3.86

1,393.92 955.39

100% 100%

0 0

0% 0%

0 0

0% 0%

0 0

0% 0%

m2

33.80

20.59

695.94

0.000

0%

0.00

0%

33.80

695.94

100%

0

0%

0

0%

0

0%

und und

3.00 14.00

203.63 685.63

610.89 9,598.82

0.000 0.000

0% 0%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

3 14

100% 100%

0 0

0% 0%

0 0

0% 0%

CODO PVC-U NTP-ISO - 399.002 DE 110 mm x 45° C-7.5 CODO PVC-U NTP-ISO 399.002 DE 110 mm x 22.5° C-7.5

und

2.00

83.75

167.50

01.14.04.02

und

4.00

83.75

335.00

01.14.04.03

CODO PVC-U NTP-ISO 339.002 DE 110 mm x 90° C-7.5

und

2.00

83.45

166.90

01.14.04.04

CODO PVC-U NTP-ISO 399.002 DE 90 mm x 45° C-7.5

und

14.00

78.75

1,102.50

01.14.04.05 01.14.04.06 01.14.04.07 01.14.04.08 01.14.04.09

CODO PVC-U NTP-ISO 399.002 DE 90 mm x 22.5° C-7.5 CODO PVC-U NTP-ISO 399.002 DE 90 mm x 90° C-7.5 CODO PVC-U NTP-ISO 399.002 DE 63 mm x 45° C-7.5 CODO PVC-U NTP-ISO 399.002 DE 63 mm x 22.5° C-7.5

und und

32.00 9.00

78.75 78.75

2,520.00 708.75

und und

13.00 26.00

63.75 63.75

828.75 1,657.50

16.00

63.75

1,020.00

01.14.04.10

CODO PVC-U NTP-ISO 399.002 DE 63 mm x 90° C-7.5 CODO PVC-U NTP-ISO ISO-399.002 DE 1 1/2" x 45°

und und

65.00

17.96

1,167.40

01.14.04.11

CODO PVC-U NTP-ISO ISO-399.002 DE 1 1/2" x 90°

und

11.00

19.96

219.56

01.14.04.12 01.14.04.13

TEE PVC-U NTP-ISO 399.002 DE 110 mm C-7.5

und und

4.00 13.00

120.50 107.76

482.00 1,400.88

01.14.04.14

TEE PVC-U NTP-ISO 399.002 DE 63 mm C-7.5 TEE PVC-U NTP-ISO ISO-399.002 DE 1 1/2" C-10

und

15.00

76.76

1,151.40

01.14.04.15

und

14.00

16.91

236.74

01.14.04.16

CRUZ PVC-U NTP-ISO 399.002 DE 110 mm C-7.5

und

8.00

175.50

1,404.00

01.14.04.17 01.14.04.18

CRUZ PVC-U NTP-ISO 399.002 DE 90 mm C-7.5

und und

12.00 3.00

113.76 93.76

1,365.12 281.28

01.14.04.19

CRUZ PVC-U NTP-ISO ISO-399.002 DE 1 1/2" C-7.5 REDUCCIÓN PVC ISO C-7.5 UF DE 110 mm a 90mm

und

5.00

23.65

118.25

und und

3.00 3.00

58.50 48.50

175.50 145.50

01.14.04.20 01.14.04.21

01.15.01.01 01.15.02 01.15.02.01 01.15.02.02 01.15.03 01.15.03.01 01.15.03.02

TEE PVC-U NTP-ISO 399.002 DE 90 mm C-7.5

CRUZ PVC-U NTP-ISO 399.002 DE 63 mm C-7.5

MOVIMIENTO DE TIERRAS EXCAVACION MANUAL EN MATERIAL SUELTO ELIMINACION DE MATERIAL EXCEDENTE CONCRETO SIMPLE ENCOFRADO Y DESENCOFRADO EN MUROS

01.15.04

CONCRETO f'c=175 kg/cm2 CON MEZCLADORA REVOQUES Y ENLUCIDOS

01.15.04.01

TARRAJEO CON MORTERO INTERIOR Y EXTERIOR 1:5 E= 1.50 Cm

01.15.05

INSTALACION DE ACCESORIOS Y OTROS

01.15.05.01 01.15.05.02

VALVULA COMPUERTA DN 63 mm VALVULA COMPUERTA DN 90 mm

335 166.9 1,102.50 1,811.25 708.75 828.75 1,191.33 1,020.00 335.63 219.56 482 805.51 662.06 136.13 1,404.00 1,308.24 281.28 118.25 175.5 145.5 242.5 1,261.67 471.65

54.02

708.75

466.17 831.77

595.37 489.34 100.61 56.88

54.86 20.51 1,499.55

610.89 9,598.82

Periodo Item

Descripción

Und.

Metrado

P.U.

Parcial

MES 01 AVANCE MENSUAL

Mes Metrado

01.15.05.03 01.15.05.04 01.16

VALVULA COMPUERTA DN 110 mm TAPA METALICA 0.80X0.80X1/8"

01.16.01

VALVULAS DE PURGA(26.00 UND) TRABAJOS PRELIMINARES

01.16.01.01

TRAZO Y REPLANTEO PARA CAJA DE VALVULA DE PUEGA

01.16.02

MOVIMIENTO DE TIERRAS

01.16.02.01 01.16.02.02

EXCAVACION MANUAL EN TERRENO SUELTO

% Avance

Metrado

3.00

620.87

1,862.61

und

13.00

161.50

2,099.50

0.000 0.000

0% 0%

0.00 0.00

0% 0%

3.00 0.00

m2

12.74

2.67

34.02

0.000

0%

0.00

0%

m3 m3

7.64 9.94

14.72 7.35

112.46 73.06

0.000 0.000

0% 0%

0.00 0.00

0% 0%

0% 0%

0.00 0.00

01.16.03 01.16.03.01

ENCOFRADO Y DESENCOFRADO EN MUROS

m2

51.48

35.20

1,812.10

01.16.03.02

CONCRETO f'c=175 kg/cm2 CON MEZCLADORA

01.16.04 01.16.04.01

REVOQUES Y ENLUCIDOS

% Avance Metrado

Parcial

MES 03 AVANCE MENSUAL

und

ELIMINACION DE MATERIAL EXCEDENTE CONCRETO SIMPLE

Parcial

MES 02 AVANCE MENSUAL

Parcial

MES 04 AVANCE MENSUAL % Avance

Metrado

100% 0%

0 13

0.00

0%

0.00 0.00

0% 0%

0% 0%

0.00 0.00

1,862.61

Parcial

MES 05 AVANCE MENSUAL % Avance

Metrado

% Avance

Metrado

2,099.50

0% 100%

0 0

0% 0%

0 0

0% 0%

12.741573

34.02

100%

0

0%

0

0%

7.6399457 9.9401361

112.46

100% 100%

0 0

0% 0%

0 0

0% 0%

0% 0%

29.601136 5.0199992

1,041.96

58% 100%

0.4249986 0

770.14

42% 0%

0 0

0% 0%

565.45

63%

0

0%

83% 100% 13%

0 0 0

0% 0% 0%

73.06

Parcial

MES 06 AVANCE MENSUAL Parcial

% Avance

m3

5.02

247.51

1,242.50

0.000 0.000

TARRAJEO CON MORTERO INTERIOR Y EXTERIOR 1:5 E= 1.50 Cm INSTALACION DE ACCESORIOS Y OTROS

m2

43.94

20.59

904.72

0.000

0%

0.00

0%

0.00

0%

16.477416

339.27

38%

0.625

VALVULA COMPUERTA DE 1 1/2"

und

26.00

97.28

2,529.28

und

26.00

141.50

3,679.00

01.16.05.03

glb

1.00

1,000.00

1,000.00

0.000 0.000 0.000

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

0.00 0.00 0.00

0% 0% 0%

4.5499589 0 0.875

442.62

TAPA METALICA 0.50X0.50X1/8" ACCESORIOS

17% 0% 88%

0.8250016 1 0.125

01.17

VALVULAS DE AIRE(20.00 UND)

01.17.01 01.17.01.01

TRABAJOS PRELIMINARES TRAZO Y REPLANTEO PARA CAJA DE VALVULAS DE PURGA

m2

40.00

2.67

106.80

40.000

106.8

100%

0.00

0%

0.00

0%

0

0%

0

0%

0

0%

01.17.02 01.17.02.01

MOVIMIENTO DE TIERRAS EXCAVACION MANUAL EN TERRENO SUELTO

m3

40.00

14.72

588.80

ELIMINACION DE MATERIAL EXCEDENTE

m3

52.00

7.35

382.20

40.000 52.000

588.8

01.17.02.02

100% 100%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

0 0

0% 0%

0 0

0% 0%

0 0

0% 0%

01.17.03 01.17.03.01

CONCRETO SIMPLE ENCOFRADO Y DESENCOFRADO EN MUROS

m2

128.00

35.20

4,505.60

4,425.14

CONCRETO f'c=175 kg/cm2 CON MEZCLADORA REVOQUES Y ENLUCIDOS

m3

8.55

247.51

2,116.21

98% 0%

2.29 8.55

80.46

01.17.03.02

125.714 0.000

2,116.21

2% 100%

0.00 0.00

0% 0%

0 0

0% 0%

0 0

0% 0%

0 0

0% 0%

m2

32.80

20.59

675.35

0.000

0%

32.80

675.35

100%

0.00

0%

0

0%

0

0%

0

0%

01.17.05

TARRAJEO CON MORTERO INTERIOR Y EXTERIOR 1:5 E= 1.50 Cm INSTALACION DE ACCESORIOS Y OTROS

01.17.05.01

VALVULA DE AIRE DE EN TUBERIA 63MM

und

3.00

159.74

479.22

VALVULA DE AIRE DE EN TUBERIA 90MM

und

14.00

172.74

2,418.36

01.17.05.03 01.17.05.04

VALVULA DE AIRE DE EN TUBERIA 110MM

und und

3.00 20.00

174.74 161.50

524.22 3,230.00

0.000 0.000 0.000 0.000

0% 0% 0% 0%

3.00 14.00 3.00 20.00

479.22

01.17.05.02

3,230.00

100% 100% 100% 100%

0.00 0.00 0.00 0.00

0% 0% 0% 0%

0 0 0 0

0% 0% 0% 0%

0 0 0 0

0% 0% 0% 0%

0 0 0 0

0% 0% 0% 0%

m2

20.58

2.67

54.95

0.000

0%

20.58

54.95

100%

0.00

0%

0

0%

0

0%

0

0%

m3

12.35

14.72

181.79

12.35

7.35

90.77

0.000 0.000

0% 0%

12.35 12.35

181.79

m3

100% 100%

0.00 0.00

0% 0%

0 0

0% 0%

0 0

0% 0%

0 0

0% 0%

m2

83.16

35.20

2,927.23

8.11

247.51

2,007.31

0% 0%

83.16 8.11

2,927.23

m3

0.000 0.000

2,007.31

100% 100%

0.00 0.00

0% 0%

0 0

0% 0%

0 0

0% 0%

0 0

0% 0%

m2

70.98

20.59

1,461.48

0.000

0%

61.00

1,255.96

86%

9.98

205.52

14%

0

0%

0

0%

0

0%

0% 0% 0% 0%

0.00 0.00 0.00 0.00

0% 0% 0% 0%

2.00 6.00 3.00 11.00

407.26

1,776.50

100% 100% 100% 100%

0 0 0 0

0% 0% 0% 0%

0 0 0 0

0% 0% 0% 0%

0 0 0 0

0% 0% 0% 0%

01.16.05 01.16.05.01 01.16.05.02

01.17.04 01.17.04.01

01.18

TAPA METALICA 0.80X0.80X1/8" VALVULAS REDUCTORAS DE PRESION(11.00 UND)

01.18.01

TRABAJOS PRELIMINARES

01.18.01.01

TRAZO Y REPLANTEO PARA CAJA DE VALVULAS DE CONTROL

01.18.02 01.18.02.01

MOVIMIENTO DE TIERRAS

01.18.02.02 01.18.03 01.18.03.01

EXCAVACION MANUAL EN MATERIAL SUELTO ELIMINACION DE MATERIAL EXCEDENTE

382.2

2,418.36 524.22

90.77

1,242.50

875

2,086.66 3,679.00 125

CONCRETO SIMPLE

01.18.03.02

ENCOFRADO Y DESENCOFRADO EN MUROS CONCRETO f'c=175 kg/cm2 CON MEZCLADORA

01.18.04

REVOQUES Y ENLUCIDOS

01.18.04.01 01.18.05

TARRAJEO CON MORTERO INTERIOR Y EXTERIOR 1:5 E= 1.50 Cm

01.18.05.01

VALVULA COMPUERTA DN 63 mm VALVULA COMPUERTA DN 90 mm

und

2.00

203.63

407.26

01.18.05.02

und

6.00

685.63

4,113.78

01.18.05.03

VALVULA COMPUERTA DN 110 mm

und

3.00

620.87

1,862.61

01.18.05.04 01.19

TAPA METALICA 0.80X0.80X1/8"

und

11.00

161.50

1,776.50

0.000 0.000 0.000 0.000

01.19.01

INSTALACION DE ACCESORIOS Y OTROS 4,113.78 1,862.61

HIDRANTES (126.00 UND) TRABAJOS PRELIMINARES TRAZO Y REPLANTEO PARA CAJA DE HIDRANTE

m2

80.64

2.71

218.53

0.000

0%

0.00

0%

80.64

218.53

100%

0

0%

0

0%

0

0%

01.19.02.01

MOVIMIENTO DE TIERRAS EXCAVACION MANUAL EN TERRENO SUELTO

m3

76.61

14.72

1,127.70

ELIMINACION DE MATERIAL EXCEDENTE

m3

95.76

7.35

703.84

0.000 0.000

0% 0%

0.00 0.00

0% 0%

76.61 95.76

1,127.70

01.19.02.02

100% 100%

0 0

0% 0%

0 0

0% 0%

0 0

0% 0%

01.19.03

CONCRETO SIMPLE

01.19.03.01 01.19.03.02

ENCOFRADO Y DESENCOFRADO EN MUROS

m2 m3

413.28 51.41

35.20 247.51

14,547.46 12,724.49

0.000 0.000

0% 0%

0.00 0.00

0% 0%

266.91 0.00

9,395.23

65% 0%

146.37017 51.410004

5,152.23 12,724.49

35% 100%

0 0

0% 0%

0 0

0% 0%

m2

181.44

20.59

3,735.85

0.000

0%

0.00

0%

0.00

0%

181.44002

3,735.85

100%

0

0%

0

0%

und und

31.00 95.00

202.00 211.00

6,262.00 20,045.00

0.000 0.000

0% 0%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

31 95

6,262.00

100% 100%

0 0

0% 0%

0 0

0% 0%

MÓDULO DE EQUIPO DE RIEGO MOVIL C/01 LATERAL DE RIEGO CON 01 ASPERSORES DE 3/4" PRUEBAS Y ENSAYOS

und

126.00

376.00

47,376.00

0.000

0%

0.00

0%

0.00

0%

126

100%

0

0%

0

0%

01.21.01

ANALISIS DE DISEÑO DE MEZCLAS Y ROTURA DE TESTIGOS - RESISTENCIA ALA COMPRESIÓN

und

5.00

525.00

2,625.00

0.000

0%

0.00

0%

0.00

0%

5

100%

0

0%

0

0%

01.22

MITIGACION AMBIENTAL

01.22.01

MITIGACION DEL IMPACTO AMBIENTAL CAPACITACION DE OPERACIÓN Y MANTENIMIENTO DEL SISTEMA DE RIEGO POR ASPERSIÓN CAPACITACION DE OPERACIÓN Y MANTENIMIENTO DEL SISTEMA DE RIEGO POR ASPERSIÓN

glb

1.00

7,000.00

7,000.00

0.000

0%

0.00

0%

0.00

0%

1

100%

0

0%

0

0%

glb

1.00

7,000.00

7,000.00

0.000

0%

0.00

0%

0.00

0%

1

100%

0

0%

0

0%

glb

1.00

7,000.00

7,000.00

0.000

0%

0.00

0%

0.00

0%

0.875

88%

0.125

13%

0

0%

glb

1.00

5,000.00

5,000.00

0.000

0%

0.00

0%

0.00

0%

0

0%

1

100%

0

0% 0% 0%

01.19.01.01 01.19.02

01.19.04

CONCRETO f'c=175 kg/cm2 CON MEZCLADORA REVOQUES Y ENLUCIDOS

01.19.04.01

TARRAJEO CON MORTERO INTERIOR Y EXTERIOR 1:5 E= 1.50 Cm

01.19.05

SUMINISTRO E INST.DE ACCESORIOS PARA HIDRANTES

01.19.05.01 01.19.05.02

INSTALACION DE ACCESORIOS P/HIDRANTE EN TUB. DE 63MM ABRAZADERA

01.20 01.20.01 01.21

01.23 01.23.01 01.24 01.24.01 01.25 01.25.01 01.26

INSTALACION DE ACCESORIOS P/HIDRANTE EN TUB. DE 48MM ABRAZADERA MÓDULO DE RIEGO

CAPACITACIÓN EN GESTION DEL AGUA AL COMITE DE REGANTES CAPACITACIÓN EN GESTION DEL AGUA

703.84

20,045.00 47,376.00

2,625.00

7,000.00

7,000.00

6,125.00

875

CAPACITACION EN LA IMPLEMENTACIÓN DE LA CEDULA E CULTIVO CAPACITACION EN LA INPLEMENTACIÓN DE LA CEDULA DE CULTIVO FLETE

5,000.00

01.26.01

FLETE TERRESTRE

glb

1.00

18,715.15

18,715.15

01.26.02 01.27

FLETE RURAL

glb

1.00

30,986.42

30,986.42

1.000 1.000

18,715.15 30,986.40

100% 100%

0.00 0.00

0% 0%

0.00 0.00

0% 0%

0 0

0% 0%

0 0

0% 0%

0 0

01.27.01

PLACA RECORDATORIA

glb

1.00

610.00

610.00

1.000

610

100%

0.00

0%

0.00

0%

0

0%

0

0%

0

PLACA RECORDATORIO

COSTO DIRECTO GASTOS GENERALES (6%) GASTOS UTILIDADES (5%) SUB TOTAL IGV 18% SUPERVISION 2.5% ELABORACION DE EXPEDIENTE TECNICO 1.5% PRESUPUESTO TOTAL

1,236,368.25 74,182.10 61,818.41 1,372,368.76 247,026.38 34,309.22 20,585.53 1,674,289.88

60,054.77 3,603.29 3,002.74 66,660.79 11,998.94 1,666.52 999.91 81,326.17

5% 5% 5% 5% 5% 5% 5% 5%

16,041.83 962.51 802.09 17,806.43 3,205.16 445.16 267.10 21,723.85

1% 1% 1% 1% 1% 1% 1% 1%

62,784.54 3,767.07 3,139.23 69,690.84 12,544.35 1,742.27 1,045.36 85,022.82

5% 5% 5% 5% 5% 5% 5% 5%

240,118.25 14,407.10 12,005.91 266,531.26 47,975.63 6,663.28 3,997.97 325,168.13

19% 19% 19% 19% 19% 19% 19% 19%

640,863.46 38,451.81 32,043.17 711,358.44 128,044.52 17,783.96 10,670.38 867,857.30

52% 52% 52% 52% 52% 52% 52% 52%

0% 216,505.40 12,990.32 10,825.27 240,320.99 43,257.78 6,008.02 3,604.81 293,191.61

18% 18% 18% 18% 18% 18% 18% 18%

DESAGREGADO DE COSTO DIRECTO

COSTO S./

OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES

50485.3

CAMPO DEPORTIVO PAMPA SAN JOSE

443452.28

CONSTRUCCION DE OFICINA, VESTUARIOS Y SERVICIOS HIGENICOS

210326.02

JUEGOS RECREATIVOS INSTALACIONES DE PARARRAYOS

8275.48 60467.18

CERCO PERIMETRICO

73440.5

OBRAS EXTERIORES

17920.7

EVACUACION PLUVIAL DE CAMPO DEPORTIVO

25193.22

EVACUACION PLUVIAL DE OFICINA, VESTUARIO Y SERVICIOS HIGENICOS FLETE TERRESTRE COSTO DIRECTO TOTAL

3337.99 25402.19 918,300.86

S/ COSTO DIRECTO GASTOS GENERALES (6%) GASTOS UTILIDADES (5%) SUB TOTAL IGV 18% SUPERVISION 2.5% ELABORACION DE EXPEDIENTE TECNICO 1.5% PRESUPUESTO TOTAL

918300.8568 55098.051408 45915.04284 ******************* 1019313.951048 183476.51118864 25482.8487762 15289.70926572 ******************* 1243563.020279

Related Documents


More Documents from ""