Project-wise Activities Completed and Likely Period of Completion No. 1
Project Rice Productivity Enhancement
Activities to be completed Mechanisation: • Settlement of the claims of the machines purchased • Around 10% of the physical target in distributing the machines • Remaining 5 demonstrations of machines (which can be done only during the cropping season June – October 2006). Participatory Technology Development: • Results of field trials are to be mapped and reports are to be compiled.
2
Integrated Farming System
Likely month of Completion According to the Agri. department, Physical activities are to be completed by Oct 20 06.
According to KAU, the component will extend till Oct-2006 in order to facilitate trials in the farmers’ fields to arrive at an authentic report for further recommendation.
Demonstration: • Third year component to be completed August 2006 in all the 160 plots. Model farms: Out of 4175 plots to be identified for implementation in the two blocks, 605 farms to be surrendered and the balance 3570 farms to be completed by October – 06. • Organisation of SHGs and training component (can be done only after the October 06 physical implementation of model farm units). • The documentation of success stories October 06 (to be done after the completion of the project). • The labour saving farm mechanisation component (assessment of requirement, tender procedures, purchase, etc. are yet to pick up momentum).
•
Modelling of nutrient flow: • The recording and analysis of the March 2007 quantification of litter addition and nutrient input to continue for a year so
• 3
Promotion of Bamboo cultivation
•
4
Vegetable & Fruit Promotion
•
Floriculture through Women Groups
• •
Completed
•
Completed
•
The analysis of the soil samples collected including upland soil samples Preparation of soil fertiliser maps and September 2007 development of regional rice recommendation (in progress at present). Adaptive trials. The plant sample analysis.
• • •
•
6
7
8
9 10 11 12
Setting up of Modern • Rice Mill Complex • Grain Storage Centres
August/September 2006
The construction of the remaining four market centres. Monitoring activities and the output analysis of Banana cultivation for the year 2005- 06 (harvest during AugustSeptember 2006). Purchase of riefer van Construction of the flower collection centre which is underway The handing over of the revolving fund to the flower collection centre once it is functional. The implementation of floriculture in NSS College Ottappalam - planting, the work of rainwater harvesting tank is in progress. Construction of the godown component The purchase and installation of the sortex machine • Physical Complete. The sanction and release of the additional requirement of Rs. 1.05 lakhs is awaited. Project has been dropped. Remaining payment of Rs. 1.75 lakhs has to be given to CFTRI. Completed
•
5
that reports can be developed. Disease mapping to be done for the next two seasons for the microbial analysis. Casualty replacement of plants.
•
Setting up of Fruit & Vegetable Processing Units Rural Micro Enterprises & Leased Land Farming Promotion of Modern Breeds of Goats Reservoir Fisheries
• •
Technology Development for Agriculture
•
•
•
September 2006
October 2006
December 2006 August 2006 August 2006
May 2006
• • 13
Establishment of • Agriculture Precision Diagnostic Centre •
Recording of the findings of the adaptive trials. Finalisation of the total soil survey report for 42 Panchayats.
14
Malampuzha Irrigation Project
•
Electrification work (nearing completion). The supply orders placed and to receive the balance equipments. Completed
15
Mangalam Irrigation Project
•
Completed
16
Pothundi Irrigation Project Ground Water Development
• • •
Physical Completed. Final bill settlements. Completed
August 2006
Local Level Water Resources Management Model Watershed
•
The balance work of 4 ponds
August 2006
•
The project has been dropped.
20
River Basin Planning & Consultancies
•
Draft report submitted. Final to be prepared after scrutiny.
21
Re construction of Kunnumpidari Eri
•
Completed
22
Renovation of Muthukaunder weir
•
Completed
23
Watershed based Master plan
•
Completed
24
Participatory Irrigation Management
•
The handing over and the monitoring to be done after the completion of the project.
25
Drinking Water Supply SchemeKunnamkattupathy
•
The ongoing works in the left and right abutment, retaining walls on the left and right sides and fabrication works. 4 piers from the right, pier middle of scour pan in progress and laying of pipeline yet to start. The mechanical works yet to start.
17 18 19
• •
August 2006
August 2006
August 2006 (for completion of the rehabilitation works) November 2006 (Turn over phase can be done only after water release during the second crop)
November 2006
26
Strengthening of School Laboratories
•
Completed
27
Up gradation of Primary Health Centre and Taluk Hospital Rehabilitation Centre for Disabled Children and Destitute Care
•
The electrification works of Alathur August 2006 Taluk Hospital & Kodumbu and Mankara PHCs.
Solid Waste Management and Organic manure Production
•
28
29
ICCONS
•
• • • • •
30 31
.Water supply and sanitary works, floor weather proofing course and painting. • ‘Ashraya’ is complete. The completion of the construction of the treatment plant The road within the plant The construction for the rotary sieve base. Installation of the rotary sieve, rain water harvesting tank, sedimentation tank, purchase of vehicles and bins, Training for workers, awareness camps, etc. District Hospital electrification. Completed and inaugurated.
Girivikas Educational • Complex for Tribal boys and girls Capacity Building Farming System Informatics: • The draft DVDROM nearing completion and to be submitted for scrutiny of the expert team of KAU. • Submission of the final product. Development Plans for Agro ecological zones of Palakkad Dist. • 50% of the project to be complete including the compilation of the data and the report preparation.
August 2006
December 2006
September 2006
December 2006