MAQUINARIA CAMION VOLTEO

DATOS CAPACIDAD = 4m3 DISTANCIA = 550 m. TIEMPO DE CICLOS = 25 min. EN UNA ORA REALIZA 2.4 CICLOS, ENTONCES EL RENTIMIENTO ES 𝑅=

2.4 𝑋 4 1 hr

= 9.6 m3/hr

MAQUINARIA RETROEXCAVADORA CAT

DATOS FACTOR DE LLENADO = 1.1 CAPACIDAD DE CUCHARON = 1.5 M3 MATERIAL DE ARCILLA SUELTA ANGULO DE GIRO MAX. = 75Β° PROFUNDIDAD DE CORTE = 50% FAVTOR DE EFICIENCIA = 0.75 TIEMPO DE CICLO 22 SEG. (0.22 MIN.) 𝑀𝐼𝑁 𝑋 0.75 𝐻𝑅

(75

0.22 MIN

=255.68 CICLOS/HR.

CANTIDAD DE MATERIAL = CAPACIDAD DE CUCHARON * FACTOR DE LLENADO CANTIDAD DE MATERIAL = 1.5 * 1.1 = 1.65 M2 RENDIMIENTO M2

𝑅 = 1.65 CICLO βˆ— 255.68

CICLOS HR

=421.87 M3/HR

MAQUINARIA COMPACTADORA DE RODILLO LISO HAMM 3520

DATOS CAPA EN METROS DEL MATERIAL SUELTO = 0.45 ANCHO EFECTIVO DEL RODILLO COMPACTODOR = 1.67 NUMERO DE PASADAS NECESARIAS PARA COMPACTAR = 5 COMPACTA = 0.85 KM/HR EFICIENCIA DE PREPARACION = 0.83 CALCULO RENDIMIENTO 𝑅=

0.85 + 0.83 + 0.45 + 1.67 + 100 = 20.76 𝑀3/𝐻𝑅 5

MAQUINARIA EXCAVADORA CAT 320DL

DATOS CAPACIDAD DE CUCHARON = 3.8 PROFUNDIDAD DE EXCAVACION = 0.75 M PROFUNDIDAD DE EXCAVACION DEL CUCHARON = 2.5 M ANGULO DE GIRO 45 Β° CICLO = 18 SEG. CALCULOS LA PROFUNDIDAD Γ“PTIMA PARA LA MAQUINARIA Y EL MATERIAL ES: 0.50 X 2.5 = 1.25 M % DE PROFUNDIDAD MAX. =

0.75 1.25

FACTOR DE EFICIENCIA = 80%

βˆ— 100 = 60%

MAQUINARIA MOTONIVELADORA DATOS LONGITUD POR PERFILAR EN METROS = 250 M. ANCHO DE LA CALZADA MAS BERMAS = 6.50 M NUMERO DE PASADAS = 7 VELOCIDAD DE LA PRIMERA PASADA = 1.5 km/h VELOCIDAD DE LA SEGUNDA PASADA = 2 km/h VELOCIDAD DE LA TERCERA PASADA = 4 km/h VELOCIDAD DE LA CUARTA PASADA = 4 km/h VELOCIDAD DE LA QUINTA PASADA = 4 km/h VELOCIDAD DE LA SEXTO PASADA = 5 km/h VELOCIDAD DE LA SEPTIMA PASADA = 5 km/h EFICIENCIA = 0.75 CALCULO DEL TIEMPO REAL

𝑑=

2 X 0.250 2 X 0.250 2 X 0.250 + + = 0.966 𝐻𝑅. 0.75 0.75 X 4 0.75 X 5

CALCULO DE RENDIMIENTO

𝑅= R = 1811.5942 M2/H

250 𝑋 7 0.966

INSTITUTO TECNOLOGICO SUPERIOR DE LA MONTAΓ‘A

Related Documents

Catalogo
May 2020 8
Catalogo
December 2019 40
Catalogo
May 2020 7
Catalogo
May 2020 7
Catalogo
May 2020 13
Catalogo
May 2020 39

More Documents from ""

December 2019 15
Maquinarias Pesadas.docx
December 2019 25
Cuestionario 2 Sabas.docx
December 2019 17