Capacity Planning purpose Critical to the success of a Sprint planning session, a team estimates the total number of “ideal hours” it has available to work on sprint-related tasks.
Step #1
What are ideal hours?
Whose on vacation? Ask each team member if they Are going to miss any time during the sprint. I’m out all week baby!
?
The number of hours in a day that a team member has available to work on a sprintrelated task.
I’m out 2 days
Campbell Lewis Queener Thomason Yang Ince Stetzel
Step #2
How many are on the team? Determine the total number of People you will have available To work on sprintrelated tasks
Let’s see…… 5 people, times 4 ideal hours, times 10 days in a sprint, minus 25 hours for vacation equals 175 hours capacity!!!!
Step #4 So, what’s our capacity? Calculate the total number of productive hours # team members x # productive hours x # days in the sprint
Scripps networks interactive scrum training, 2007
Step #3
How many days in the sprint? Define the total number Of working days in the sprint.
If you have “shared” team mates remember to account for their time as needed